Steel Industry Compliance Extension Act of 1981 ( 1981 )


Menu:
  •            Steel Industry Compliance Extension Act of 1981
    The Steel Industry Compliance Extension A ct o f 1981 (A ct) permits the Administrator of
    the Environm ental Protection Agency to accede to a steel company’s request for an
    extension o f otherwise applicable deadlines for compliance with the Clean A ir Act only
    if the A dm inistrator finds that the company has met its ongoing obligations under its
    existing consent decrees, or th at any violations are de minimis in nature.
    While the term “de minimis” is not defined in the Act, the legislative history confirms
    that it was meant to have its ordinary meaning—that is, “negligible” or “insubstantial
    o r inconsequential.”
    November 9, 1981
    MEMORANDUM FOR THE ASSISTANT ATTORNEY
    G EN ERA L, LAND A ND NATURAL RESOURCES DIVISION
    This responds to your request for our views concerning the proper
    construction of the term “de minimis” as used in the Steel Industry
    Compliance Extension Act of 1981, Pub. L. No. 97-23, 
    95 Stat. 139
     (to
    be codified at 
    42 U.S.C. § 7413
    (e)) (Act), familiarly known as the Steel
    Tripartite Amendment, Tripartite, and Steel Stretch-out. We have
    found nothing in the statute or its legislative history to suggest that de
    minimis was meant to have anything other than its usual meaning—that
    is, negligible, insubstantial, or inconsequential. Anderson v. Mt. Clemens
    Pottery Co., 
    328 U.S. 680
    , 692, 693 (1946). We therefore conclude that
    the Act does not permit the Administrator of the Environmental Pro­
    tection Agency (EPA) to enter into or modify a consent decree for the
    purpose of extending compliance deadlines under the Clean Air Act, 
    42 U.S.C. § 7401
     et seq. (Supp. IV 1980), unless the Administrator finds
    that a company is in compliance with its existing consent decrees, or
    any violations are of a de minimis nature, as defined; at the time the
    company applies for an extension.
    In reaching this conclusion, we have carefully reviewed the legisla­
    tive history of the Act, including the House and Senate reports,1 the
    1 H.R. Rep. No. 161, 97th Cong., 1st Sess. (1981), H.R. Rep. No. 121, 97th Cong., 1st Sess. (1981);
    S. Rep. No. 133, 97th Cong., 1st Sess. (1981).
    326
    hearings,2 and the floor debates.3 This material makes it clear that both
    Congress and the members of the Steel Tripartite Committee (Commit­
    tee) who drafted the Act intended that the EPA Administrator have
    discretion to grant extensions only to those companies who had met
    their ongoing obligations under a consent decree.
    I. Background
    The Clean Air Act Amendments of 1970, 
    42 U.S.C. § 1857
     et seq.
    (1976) (amending the Air Quality Act of 1967, Pub. L. No. 90-148, 
    81 Stat. 485
     (codified at 
    42 U.S.C. § 1857-1871
    /) (1970)) (amended 1977),
    developed lists of air pollutants, promulgated national ambient air qual­
    ity standards, 42 U.S.C. § 1857c-4 (1970 ed.), and required each state to
    develop a plan to implement the air quality standards. Id. at § 1857c-5.
    The state, or, if it failed to act, the EPA, was authorized to prevent the
    construction or modification of any new sources of pollution—such as
    factories—from being built if the construction would prevent attain­
    ment or maintenance of the national air quality standards. Id. at
    § 1875c-5(a) (2)(D), (4). The Clean Air Act Amendments of 1977, 
    42 U.S.C. § 7401
     (Supp. IV 1980), extended the deadlines for meeting most
    of the standards for pollutants to December 31, 1982. The EPA Admin­
    istrator was charged with seeking injunctions and recovering civil pen­
    alties against those who violate the Clean Air Act’s provisions. 
    42 U.S.C. §§7413
    , 7420 (Supp. IV 1980). Through this enforcement mech­
    anism, the Administrator has brought actions and, in most instances,
    obtained consent decrees. Mandatory investment schedules contained in
    those decrees insure, through the mechanism of the threat of stipulated
    damages, that the companies meet the 1982 final compliance deadline.4
    By 1979, when the EPA had reached consent decrees with most of
    the major steel companies, H.R. Rep. No. 121, supra, at 4-8 (Table 1),
    expenditures for pollution control had become a major drain on the
    resources available to the steel industry for capital investment. In 1980,
    for example, 19% of the steel industry’s annual capital expenditure was
    for pollution control. This was far greater than that spent by compara­
    ble heavy industries such as the electric utilities (9.2%) or the automo­
    2 Steel Tripartite Committee Proposal: Hearings on H.R. 1817. H.R. 2024. H.R. 2219. et al. Before the
    Subcomm. on Health and the Environment o f the House Comm, on Energy and Commerce. 97th Cong.,
    1st Sess. (1981) [hereafter cjted as Hearings on H.R. 1817\\ Steel Industry Compliance Extension Act o f
    1981: Hearing on S. 63 Before the Senate Comm, on Environment and Public Works. 97th Cong., 1st
    Sess. (1981) [hereafter cited as Hearing on S. 63]\ Report o f the Steel Tripartite Comm. Hearings Before
    the Senate Comm, on Environment and Public Works. 96th C ong, 2d Sess (1980) [hereafter cited as
    Tripartite Hearings).
    3 127 Cong Rec. H3747-52 (daily ed. June 26, 1981); id. at S6985-87 (daily ed. June 25, 1981); id. at
    S6605 (daily ed. June 19, 1981); id. at S6090-93 (daily ed. June 11, 1981); id. at H2463-64 (daily ed.
    May 28, 1981); id. at H2444-56 (daily ed. May 28, 1981).
    *See C. Stewart, Air Pollution, Human Health and Public Policy 35-48 (1979). See generally.
    Environmental Law Institute, Air and W ater Pollution Control Law- 1980 (G. Wetstone, ed. 1980);
    Hearing on S. 63. supra, at 62 (Report of the Steel Tripartite Advisory Committee Working Group on
    Environmental Protection).
    327
    tive industry (5.4%). Id. at 9 (Table 2). Not only was the percentage of
    capital invested higher, it was also more difficult for the steel industry
    to raise. Id. (Table 3). This, the steel companies argued, was due to
    pressure on the industry by the federal government not to raise prices,
    making it increasingly difficult to recapture costs, and because of the
    willingness of the federal government to sacrifice the domestic steel
    industry to foreign policy considerations by allowing “dumping” of
    foreign steel. Hearings on H.R. 1817, supra, at 48-9; Tripartite Hearings,
    supra, at 101-02 (report prepared by the Congressional Research Serv­
    ice).
    The Steel Tripartite Committee was formed to advise the President
    on the steel industry’s problems and to suggest ways to revitalize the
    industry. It was made up of representatives of the senior management
    of the steel companies, the United Steelworkers of America Union, and
    the federal government. The Committee’s working group on environ­
    mental issues later added a fourth member, the Natural Resources
    Defense Council (NRDC).5 These disparate groups brought to the
    negotiating table concerns about the flagging health of the steel indus­
    try, the protection of local economies threatened by plant closings, the
    promotion of worker health and safety, and the public’s interest in
    continued progress toward the goals of the Clean Air Act. Out of their
    dynamic balancing of interests and resultant compromises came the
    1981 amendments embodied in the Act. In order “to provide the steel
    industry with vitally needed capital for modernization, while maintain­
    ing public health and environmental protection,” the Committee pro­
    posed that steel companies be given 3 more years in which to meet the
    requirements of the Clean Air Act. H.R. Rep. No. 121, supra, at 8-9.
    The “trade-off’ for the extension of the deadline for compliance with
    the Clean Air Act was that the companies obtaining the benefit of the
    extension would invest in modernization efforts the capital resources
    which would otherwise have gone into more immediate compliance
    efforts.6 The compromise reflected by the Act was, therefore, to im­
    prove the efficiency and productivity of the American steel industry at
    the cost of some temporary setbacks in the achievement of the goals for
    cleaner air contained in the Clean Air Act. However, to ensure that the
    companies would not abandon progress toward pollution control, each
    company applying for an extension would have to meet six carefully
    crafted conditions. In order to consent to an extension of the schedule
    for compliance, the EPA Administrator would have to find:
    5T he N R D C is a national environmental group which frequently plays an active role in the
    legislative process. It was invited to jo in the working group by the Executive Office of the President
    and the United Steelworkers of America Union.
    6 Since the new er equipment would contain the most modern technology, it was argued that it
    would usually be cleaner than what it was replacing.
    328
    (A) That the extension is necessary to allow the com­
    pany to make capital investments designed to improve
    efficiency and productivity;
    (B) That funds equal to what would otherwise have
    been spent by December, 1982 on pollution control will
    be spent within two years on capital investments;
    (C) That the company will enter into a consent decree
    establishing a schedule for bringing all its stationary
    sources of pollution into compliance;
    (D) That the company will have enough money to
    comply with its consent decrees;
    (E) That the company is in compliance with existing
    federal consent decrees or that any violations are de ,
    minimis in nature; and
    (F) That any extensioin will not result in degradation of
    air quality during the extension.
    See Act, § 113(e)(1) (A)-(F). Each of these requirements was included
    in response to objections that the Act was special-interest legislation.
    On each of the six, the company “bears the burden of proof.” H.R.
    Rep. No. 121, supra, at 10.
    Section 113(e)(1)(E) is Congress’ response to critics who claimed the
    Act would “give relief to those companies which have been avoiding
    the law and penaliz[e] those who have complied.” Tripartite Hearings,
    supra, at 27 (Follow-up Questions for EPA). As finally enacted,
    § 113(e)(1)(E) requires that
    the Administrator find[ ], on the basis of information sub­
    mitted by the applicant and other information available to
    [the Administrator] that the applicant is in compliance
    with existing Federal judicial decrees (if any) entered
    under section [113] of this Act applicable to its iron- and
    steel-producing operations or that any violations of such
    decrees are de minimus [sic] in nature.
    Act, § 113(e)(1)(E). You have asked us to consider what kind of viola­
    tions can be considered de minimis.
    II. The Meaning of De Minimis Under the Act
    De minimis is not defined in the Act. It was suggested as the
    standard by Ms. Frances Dubrowski, NRDC representative, during the
    late stages of the Committee’s drafting of the Act.7 The suggestion was
    made in response to the steel industry’s suggestion that the test be
    “substantial compliance” with one’s consent decree.8 That the parties
    7 Telephone conversation with Mr. Stephen D. Ramsey, Chief, Environmental Enforcement Sec­
    tion, Land and Natural Resources Division, United States Department of Justice, October 16, 1981.
    8 Id.
    329
    intended a narrow definition is supported by the Senate report which
    states:
    A de minimis violation of an emission limitation is a
    violation resulting from circumstances beyond the control
    of the source owner or employee which causes no meas­
    urable increase in emissions from a source.
    S. Rep. No. 133, supra, at 4. “The intent of this provision is twofold: to
    ensure that pollution control expenditures required to be made before
    the grant of an extension under this act are not deferred and to ensure
    that only those companies making a good faith effort to comply with
    existing environmental obligations obtain the benefit of further deadline
    extensions.” H.R. Rep. No. 121, supra, at 10.
    De minimis matters have traditionally been defined as “negligible,”
    “trifles,” “insubstantial and insignificant.” Anderson v. Mt. Clemens Pot­
    tery Co., 
    328 U.S. 680
    , 692, 693 (1946).9 The legislative history is scanty
    on the issue, but what there is reflects this understanding. The Senate
    report, for instance, defines de minimis violations of a consent decree as
    those resulting in “no measurable increase in emissions from a source.”
    S. Rep. No. 133, supra, at 4. A violation that “result[s] from circum­
    stances beyond the control of the source owner” would bar even a
    minor violation, if caused by the owner’s fault or neglect. Id. And a
    violation that really causes “no measurable increase in emissions” must
    be one so minor as to be truly insignificant. Id.
    Whether a particular violation is de minimis is a decision that must
    initially be made by EPA, since the discretion belongs to the Adminis­
    trator and it is his expertise which will inform your review and will
    guide your judgment as to whether you (on behalf of the Attorney
    General) will approve the modification of the decree. The EPA Imple­
    mentation Manual describes the test to be used.
    In determining what are insignificant deviations, the
    agency should consider the extent of the delay, the nature
    of the violation, the good faith of the company, and the
    extent to which the delay impacts other provisions of the
    decree.
    Manual, Ex. G., at 2. We assume this involves determinations of issues
    such as whether a violation is temporary or, if easily curable, likely to
    be cured because of the company’s good faith willingness or effort to
    cure. However, “[w]here emissions limits are in issue, these cannot be
    viewed as ‘de minimis’ unless they cause no significant increase in
    emissions from a source.” Id. at 1.
    9 See also Industrial Union Depl v. American Petroleum Institute, 
    448 U.S. 607
    , 664 (1980) (Burger,
    J , concurring) (“ insignificant,” "scant o r minimal risks” ); Hunter v. Madison Aye. Corp., 
    174 F.2d 164
    ,
    167 (6th Cir. 1949) ("inconsequential” ).
    330
    III. The Role of § 113(e)(1)(E) and De Minimis Under the Act
    The Administrator should make every effort to give effect to Con­
    gress’ desire to afford economic relief to the steel industry so that it can
    devote capital resources to modernization. The Act, however, expressly
    and unequivocally conditions the companies’ eligibility for an extension
    of the time deadlines under the Clean Air Act on the Administrator’s
    making of two crucial findings: no “degradation of air quality,”
    (§ 113(e)(1)(F)), and no extensions unless a company is “in compliance
    with existing Federal judicial decrees (if any) . . . [or] any violations of
    such decrees are de minim[i]s in nature.” (§ 113(e)(1)(E)). If the Admin­
    istrator cannot reasonably make such findings, the Act simply does not
    allow an exercise of discretion that ignores the Act’s language in an
    attempt to maximize the number of steel companies eligible for relief.
    Compliance with the pollution control schedules contained in the con­
    sent decrees is just as integral a part of the Act as the desire to allow
    diversion of capital from air pollution equipment to improvements in
    plant efficiency.
    Congress clearly contemplated, based in substantial part on the testi­
    mony of representatives of the steel industry, that compliance with
    existing decrees was a condition which was acceptable to the industry
    and attainable by it. While the provision was being fully debated by the
    committee that drafted the statute and the Congress that passed it, there
    was no indication that the steel companies could not or would not
    comply. In fact, on March 3, 1981, the EPA testified that most of the
    steel companies would be in compliance with their respective consent
    decrees by the end of the year.
    The steel industry used to have a fairly well-deserved
    reputation as a major polluter of air and water. However,
    that situation has now changed very much for the better.
    Where in July 1978 only 32 percent of air pollution
    sources in the steel industry were in compliance or on
    court-ordered compliance schedules, by the end of this
    year that number will be up to approximately 90 percent.
    Hearings on S. 63, supra, at 6 (statement of Walter C. Barber, Jr.,
    Acting Administrator, EPA); Hearings on H.R. 1817, supra, at 88 (85%)
    (statement of Walter C. Barber, Jr.); Tripartite Hearings, supra, at 13
    (84%) (statement of Michele B. Corash, General Counsel, EPA). Since
    the steel companies’ representatives were present and made no objec­
    tion to these figures,10 Congress must have assumed that this condition
    could be met by most steel companies.
    10   The steel companies complained that because they were complying with their respective consent
    decrees, they would have no money left for modernization under the Act. See n 13 infra.
    331
    The necessity of complying with outstanding consent decrees was
    discussed during the floor debates 11 and the hearings.12 The steel
    companies themselves expressly recognized that the failure to be in
    compliance with their respective consent decrees would bar them from
    relief under the Act and, therefore, that each day’s delay in enacting
    the law reduced the value of the Act to them.
    If I might depart from the Chairman’s questions briefly,
    the point we most want to make here today is that this
    issue requires immediate legislative action. Those compa­
    nies who have existing consent decrees with the EPA are
    on a schedule of compliance which requires weekly and
    sometimes daily commitment of funds to meet the Decem­
    ber 31, 1982 deadline. Failure to meet these increments of
    progress places us in technical violation of the consent
    agreements. S. 63 states that an extension applicant must be
    in compliance with existing consent agreements. [Emphasis
    added.] If we are to have any funds to defer for modern­
    ization, we must have this amendment now.
    Hearings on S. 63, supra, at 47 (statement of George A. Stinson, Chair­
    man of National Steel Corp.) (March 3, 1981). A few weeks later, the
    same speaker made the point again.
    The terms of the agreement, coupled with long leadtimes
    for construction, require us to commit the funds early in
    the agreement if we are to meet the 1982 completion
    dates. Some funds for engineering, for site clearance, and
    the like have already been, expended, and within a very
    few weeks we will have to make major capital commit­
    ments which in many cases will be impossible to defer
    further.
    These commitments are spelled out in the judicial
    decree with specific dates for action, and failure to meet
    those dates puts us in technical violation of the agreement.
    A ny violation o f the agreement would in turn make us ineli­
    gible under the provisions o f H.R. 1817 i f it becomes law.
    For these reasons, we and others need this amendment
    very soon if it is to have any benefit toward a rapid
    modernization of the industry. Passage of the amendment
    later this year under the reauthorization of the Clean Air
    Act would be of very little, if any, benefit to the industry.
    11 127 Cong. Rec ' H3750 (daily ed. June 26, 1981); id. at H2447 (daily ed. May 28, 1981).
    12 Tripartite Hearings, supra, at 18 (EPA ), 27 (EPA); Hearings on S. 63, supra, at 91 (NRDC);
    Hearings on H .R. 1817, supra, at 132 (statement by Pres. Carter submitted by the White House for the
    record).
    332
    Hearings on H.R. 1817, supra, at 65 (emphasis added) (March 25,
    1981).13 David M. Roderick, Chairman of the United States Steel
    Corp., made the same point at the same hearings.
    The existence or prospects of the consent decrees, as I
    mentioned earlier, is what creates the urgent need for this
    legislation.............Our willingness to enter into these
    agreements has created binding obligations to make cap­
    ital commitments that I mentioned earlier. In order to
    comply with our consent decrees and make the milestone
    schedules which they contain, we must commit millions
    of dollars virtually every month. Once these funds are
    committed, they are no longer available to be considered
    for stretchout, and we lose the opportunities to use these
    funds in the interim for modernization.
    Id. at 70.
    The Administrator’s flexibility in interpreting the Act is limited by
    the fact that any modification to any consent decree issued pursuant to
    the terms of the Act must be approved by the judge in whose court the
    prior consent decree was approved. Act, § 113(e)(7)(B)(ii). Information
    (unless confidential) used to make the decision and the decision itself
    will be matters of public record. Id. § 113(e) (3), (7). The right of
    private parties or states to intervene under § 304 of the Clean Air Act,
    
    42 U.S.C. § 7604
     (Supp. IV 1980) for violation of emission standards
    remains available, § 113(e)(8); H.R. Rep. No. 121, supra, at 13, and
    would no doubt be exercised if such litigants felt that there had been an
    abuse of discretion by the Administrator in consenting to an extension
    where the de minimis finding was not defensible. United States v.
    Republic Steel Corp., 15 Env’t Rep. (BNA) 1463 (N.D. 111. 1980); Fed.
    R. Civ. P. 24. Evaluation of whether a violation is de minimis, there­
    13 The steel companies were obliged to meet schedules in their consent decrees premised on a
    complete cleanup by December 1982. The race to get the Act passed before all the money was
    committed to compliance as mandated by consent decrees is illustrated in the following exchange
    between Rep. Waxman and Mr Stinson, Chairman of National Steel Corp., and Mr. Roderick,
    Chairman o f United States Steel Corp.
    Mr. Waxman. Mr. Roderick and Mr. Stinson, when is the latest possible date for
    passage of this legislation to be valuable to the industry?
    Mr. Stinson. Well, every additional day, Mr Chairman, poses a problem for us. It is
    quite difficult for me to say whether it is March 31 or April 30, but I could definitely
    say to you that if it were delayed into the late summer, it would be o f virtually no
    benefit to us.
    Mr. Roderick. . . [E]ach month of delay would mean basically about $15 million to
    $20 million that otherwise would be available for modernization would have to go to
    environmental commitments, and if by July we didn’t have even the EPA approval by
    that time, we would pretty well have run the gamut, we would have pretty well have
    had to commit on almost all the facilities in order to make the 1982 deadline. So I
    would say legislatively, Mr. Chairman, we would hope that it would be possible to
    have this legislation sometime no later than the end of April, allowing us time to make
    our presentations to the EPA and satisfy their requirements so that we would not have
    to commit, let’s say, after July.
    Hearings on H.R. 1817. supra, at 90. The Act did not become law until July 17, 1981
    333
    fore, is not a matter analogous to the exercise of prosecutorial discre­
    tion—it is an administrative decision that will be reviewed by the
    courts and critiqued by highly interested advocates. Unless supported
    by a cogent rationale, a finding that a violation is de minimis is likely to
    be rejected.
    IV. Arguments in Favor of a Broader Meaning of De Minimis
    We have evaluated several potential arguments that might be ad­
    vanced to support a broader meaning of de minimis, but they appear to
    be unsupported by the traditional meaning of the term or the Act’s
    legislative history.
    A.      We have considered whether de minimis might be measured
    against a particular company’s entire pollution control program or its
    compliance rate with all of its consent decrees, rather than measured
    against its operations at a particular plant. We do not believe that it
    may. The Act was an attempt to balance the steel industry’s need for
    extensions so that it could devote capital resources to modernization
    against the continuing interest of the public in cleaner air. Exceptions
    under the Act were to be carefully scrutinized to ensure that all the
    conditions were met. “T he bill does not authorize the granting of
    extensions on a blanket basis. Each request for an extension with re­
    spect to a specific emission control requirement and facility is to be
    considered individually.” S. Rep. No. 133, supra, at 1. The emphasis
    appears to have been placed quite intentionally on individual stationary
    sources. In fact, rather than a violation at one plant being viewed as de
    minimis because of compliance at 99% of the company’s other plants,
    the drafters apparently contemplated that a violation at one plant
    would preclude the granting of an exception even for the 99% of that
    company’s plants that are in compliance.
    The owner of a source which is in violation of an
    emission limitation after a compliance deadline in an exist­
    ing decree is not eligible for a compliance extension
    beyond 1982 for any source which would otherwise be
    eligible until the violating source is brought into compli­
    ance with the applicable emission limitation.
    Id. at 4 (emphasis added).14 We therefore do not believe that determi­
    nation of whether a violation is de minimis should be made in the
    context of a company’s entire compliance program.
    14   This understanding is reflected in a recent letter from the United States Steel Corp. to the EPA.
    “ [T]he A ct appears to contemplate th at the Administrator may make a finding related to only one of
    the applicant's sources which leads to a decision that the applicant is ineligible under the Act, and that
    the ineligibility then applies to all o f applicant's sources.” Letter from Ms. Dorothy H. Servis, Senior
    Genera] A ttorney, Environmental and Real Estate, United States Steel Corp., to Mr. Michael Alushin,
    D irector, Steel T ripartite Task Force, E PA at 2 (Oct. 23, 1981).
    334
    Moreover, this interpretation of de minimis would lead to an incon­
    sistent and unequal application of the de minimis standard. The same
    violation would be a de minimis violation for a large company with
    many plants but a substantial violation for a small company with only a
    few plants. The larger the company, the more violations it could absorb
    and still obtain an exception. This construction would be particularly
    anomalous since the larger companies are also presumably generally
    better able to generate the capital necessary to eliminate violations. We
    therefore do not find support for the argument that whether a violation
    is de minimis should be measured against the total company compliance
    with the Clean Air Act or all of a particular company’s outstanding
    decrees.16
    B. We have also considered whether the Administrator could avoid
    the issue of whether or not a violation is de minimis by agreeing to
    modifications of the existing consent decrees to remove the require­
    ments that give rise to the violations. We believe that the Act does not
    authorize such a procedure. Not only would this create a major loop­
    hole that would permit the Administrator effectively to eliminate
    § 113(e)(1)(E) from the Act, but it would also contradict the Act’s
    language and the repeated statements by all parties assuring Congress
    that the steel companies knew they had to be in compliance and would
    be in compliance with their consent decrees. Most importantly, it
    would contradict the clearly expressed desire of Congress that only
    companies that had made the effort and expended the funds necessary
    to comply with their outstanding consent decrees were entitled to this
    exception. “[EJxisting decrees may not be amended so as to make
    companies eligible for extensions under this proposal.” H.R. Rep. No.
    121, supra, at 10. Congress foresaw and precluded this argument.
    C. The same response must be made to the suggestion that the
    Administrator commence contempt actions against the violators and
    then settle the actions, collect outstanding stipulated penalties, and
    substitute new compliance schedules. Substitution of new compliance
    schedules would effectively amend existing consent decrees, contrary to
    the letter and spirit of the House report. It would permit companies
    that had failed to abide by their consent decrees access to the benefits
    of the Act. Since we believe that Congress clearly intended that such
    16 A similar argument was rejected in an early case discussing de minimis, N L R B v. Cowell Portland
    Cement Co., 
    108 F.2d 198
     (9th Cir. 1939), in which the issue was whether a company was doing
    enough interstate business to fall within the NLRB’s jurisdiction.
    The quantity of cement shipped out of state is not de minimis merely because it is but a
    small percentage of respondent's total sales Otherwise, we would have the anomaly of
    one plant under federal regulation because exporting its entire product of 14,000
    barrels while alongside it another competing plant was under state regulation because,
    though' shipping the same amount of 14,000 barrels, they constituted, say, but 4 percent
    of its product. Congress could not have intended that it would subject laboring men or
    employers to such a confusing and, in business competition, such a destructive anom­
    aly.
    
    Id.
     at 201
    335
    companies be barred from an extension under the Act, we do not
    believe the Administrator may interpret the Act to permit such substi­
    tution of new compliance schedules.
    We believe that de minimis means what it has traditionally meant—an
    insignificant or insubstantial matter. Where the violation of a consent
    decree cannot reasonably be described as insignificant, we do not be­
    lieve that the Administrator can properly authorize an extension under
    the Act.
    V. Conclusion
    We have not attempted to determine whether any particular com­
    pany is or is not in violation of its consent decrees or, if the facts
    support a finding that there is a violation, whether that violation is de
    minimis. That would require a factual determination which we are not
    qualified to make and must be made, subject to your approval, by the
    Administrator. Each applicant, as noted earlier, has the burden of
    establishing that it is in compliance with the consent decrees or that its
    violations are de minimis.
    The normal meaning o f the term de minimis is entirely consistent
    with the Act’s legislative history. Indeed, all of the legislative history
    on the subject supports that conclusion and none of it supports a more
    expansive definition. Since the EPA and the steel industry and Con­
    gress all seemed to believe that nearly all of the steel companies would
    be in compliance with their consent decrees, the Act did not contem­
    plate any substantial deviations from the consent decrees. We have no
    way of determining whether Congress would have voted for the Act at
    all if the information had established that the companies were not then
    substantially in compliance or capable of placing themselves into such a
    status. We certainly cannot attribute to Congress an intent to allow the
    EPA Administrator to ignore or deviate in any material way from one
    of the integral components of the Act.
    T h e o d o r e B. O l s o n
    Assistant Attorney General
    Office o f Legal Counsel
    336