State, Dept. of Natural Resources v. Alaskan Crude Corporation , 441 P.3d 393 ( 2018 )


Menu:
  •      Notice: This opinion is subject to correction before publication in the PACIFIC REPORTER.
    Readers are requested to bring errors to the attention of the Clerk of the Appellate Courts,
    303 K Street, Anchorage, Alaska 99501, phone (907) 264-0608, fax (907) 264-0878, email
    corrections@akcourts.us.
    THE SUPREME COURT OF THE STATE OF ALASKA
    STATE OF ALASKA,                 )
    DEPARTMENT OF NATURAL            )                     Supreme Court Nos. S-16308/16417
    RESOURCES,                       )                     (Consolidated)
    )
    Appellant and     )                     Superior Court No. 3AN-10-04671 CI
    Cross-Appellee, )
    )                     OPINION
    v.                     )
    )                     No. 7283 – August 31, 2018
    ALASKAN CRUDE CORPORATION )
    and JAMES W. WHITE,              )
    )
    Appellees and     )
    Cross-Appellants. )
    )
    Appeal from the Superior Court of the State of Alaska, Third
    Judicial District, Anchorage, Charles W. Ray, Jr., Judge.
    Appearances: John C. Hutchins, Assistant Attorney General,
    and Jahna Lindemuth, Attorney General, Juneau, for
    Appellant and Cross-Appellee. James W. White, pro se,
    Houston, Texas, Appellee and Cross-Appellant. James B.
    Gottstein, Law Offices of James B. Gottstein, Anchorage, for
    Appellee and Cross-Appellant James W. White (limited
    appearance for oral argument). No appearance by Appellee
    and Cross-Appellant Alaskan Crude Corporation.
    Before: Stowers, Chief Justice, Winfree, Maassen, Bolger,
    and Carney, Justices.
    MAASSEN, Justice.
    I.     INTRODUCTION
    An oil and gas lessee conducted drilling activity on the last day of the lease
    term; the lease provided that such activity would extend the term. Two days later,
    however, the Department of Natural Resources (DNR) sent the lessee a notice that his
    lease had expired. The lessee suspended drilling activities and asked DNR to reconsider
    its decision and reinstate the lease.
    DNR reinstated the lease several weeks later. The lessee, however,
    contended that the reinstatement letter added new and unacceptable conditions to the
    lease, and he pursued administrative appeals. Six months later DNR terminated the lease
    on grounds that the lessee had failed to diligently pursue drilling following the lease’s
    reinstatement.
    The superior court reversed DNR’s termination decision, ruling that DNR
    had materially breached the lease by reinstating it with new conditions. Both DNR and
    the lessee appealed to this court. DNR asks us to affirm the termination of the lease, and
    the lessee asks us to remand to the agency for a determination of his damages.
    We conclude that although DNR breached the lease in its notice of
    expiration, it cured the breach through reinstatement. And DNR’s subsequent decision
    to terminate the lease is supported by substantial evidence that the lessee failed to
    diligently pursue drilling activities following reinstatement. Finally, we conclude that
    neither DNR nor the superior court erred in failing to address the lessee’s damages claim.
    We reverse the superior court’s decision reinstating the lease and affirm DNR’s
    termination decision.
    -2-                                       7283
    II.   FACTS AND PROCEEDINGS
    A.     Facts
    On January 1, 2002, DNR and an individual lessee entered into a
    competitive oil and gas lease identified as ADL 389922, covering a 4,800-acre parcel
    near Cook Inlet. The lessee later assigned the lease to James W. White.1 The lease had
    a primary term of seven years, but it also identified circumstances in which the term
    could be extended.
    On the leased land was a plugged and abandoned well. It was White’s
    intent to reenter and test this well, but reentry was prohibited by spacing regulations of
    the Alaska Oil and Gas Conservation Commission (AOGCC) because of the well’s
    proximity to a property line. The AOGCC granted White an exception from the
    regulations, and in March 2005 it granted White a permit to reenter and test the well.
    White began drilling in June 2007, but he soon suspended operations
    following the announcement that a fertilizer plant, his only prospective buyer, was about
    to close. On December 31, 2008, the last day of the seven-year lease term, a DNR
    inspector observed signs of activity at the drill site: the presence of a drill rig, the
    assembly of a blowout preventer, and completion of the initial reentry of the well plug.
    B.     Agency Actions And Proceedings
    On January 2, 2009, DNR mailed White a notice of expiration, informing
    him “that in accordance with the lease agreement, ADL 389922 expired on December 31,
    2008,” and “[t]he case file has been closed in this office.” White suspended operations
    and moved his equipment from the drill site. But on January 15 he wrote the Director
    1
    White is the President of Alaskan Crude Corporation, the operator of the
    lease. Alaskan Crude participated in the administrative and superior court appeals but
    does not participate in this appeal.
    -3-                                      7283
    of the Division of Oil and Gas, asking him to clarify whether the expiration notice had
    been sent in error. White called the Director’s attention to paragraph 4(c)(1) of the lease,
    which allowed extension of the lease if drilling had “commenced as of the date on which
    the lease otherwise would expire”;2 White asserted that he was drilling on the last day
    of the lease term, as witnessed by the DNR representative at the site. He claimed that the
    expiration notice was “a direct breach of [the] lease contract” and damaged his interests
    as lessee. He asked DNR to “please correct [the notice] and advise me by email before
    2:00PM Friday, January 16th that the lease is still in effect.” DNR did not immediately
    respond to White’s letter.
    On January 20 White appealed the expiration notice to the DNR
    Commissioner, seeking “reinstatement of the lease term” or an acknowledgment that the
    lease had not expired. White sent another letter to the Commissioner on January 26.
    Urging the Commissioner to make a decision, he asserted that DNR had “received ample
    documentation of prior well boring activities, along with video, eye witness testimony
    and photos of . . . setting the blowout preventer on December 31, 2008.”
    On January 27 the Commissioner retracted the expiration notice and
    reinstated the lease. The Commissioner found that White’s documented activity on the
    last day of the lease term was “drilling” as defined in paragraph 34(4) of the lease and
    extended the lease under paragraph 4(c)(1). But the Commissioner advised White that
    2
    Paragraph 4(c)(1) provides in full:
    If the drilling of a well whose bottom hole location is in the
    leased area has commenced as of the date on which the lease
    otherwise would expire and is continued with reasonable
    diligence, this lease will continue in effect until 90 days after
    cessation of that drilling and for so long as oil or gas is
    produced in paying quantities from the leased area.
    -4-                                       7283
    the well had to be completed “within 90 days of this decision” or the lease would be
    automatically terminated. The Commissioner added: “After 90 days from the date of
    this letter, April 27, 2009, we will review your progress to determine whether continued
    lease extension is warranted.” The Commissioner summarized:
    [T]he continued extension of the lease is contingent upon
    (1) continued drilling of the well; (2) completion of the well
    by April 27, 2009; (3) valid permits for all operations; and
    (4) sustained production within 90 days following the
    cessation of drilling. The failure to comply with any of these
    conditions will result in the automatic termination of this
    lease.
    On February 11 White sought reconsideration of the reinstatement letter.
    He asserted that the letter’s conditions on reinstatement were in fact attempts to
    unilaterally modify the original lease, and he asked the Commissioner to “remove any
    and all extra conditions included in [his] decision.” Taking particular issue with the
    requirement that he complete the well by April 27, White warned that he could not drill
    once winter was over and would not “risk further capital and resources if the lease will
    expire if [he does] not finish the drilling operations before the arbitrary deadline.”
    On February 18 the Commissioner granted reconsideration and gave White
    the opportunity “to submit additional written material or request a hearing.” The
    Commissioner advised White that during reconsideration the reinstated lease “remain[ed]
    in effect for [White] to pursue continued drilling operations.” White declined a hearing
    but submitted another letter explaining his position in detail. On June 10 the
    Commissioner reaffirmed the January 27 reinstatement letter, explaining that the
    language White deemed a modification was simply a departmental interpretation of lease
    paragraph 4(c)(1) and governing law — AS 38.05.180(m) and 11 Alaska Administrative
    Code (AAC) 83.125. The Commissioner wrote that the April 27 deadline was his
    -5-                                       7283
    interpretation of the lease requirement that drilling be completed with reasonable
    diligence and that it had been calculated by trebling the 30-day estimate White gave in
    his own original plan of operations. Responding to White’s argument that DNR “could
    not require that he bring the completed well into production within 90 days after drilling
    ends,” the Commissioner stated that “the 90 day requirement is clearly set forth in
    AS 38.05.180(m) and [the] lease.”3
    Six weeks later, by letter from the Director of the Division of Oil and Gas
    dated July 23, 2009, DNR terminated White’s lease for “two independent reasons”: first,
    because “according to the AOGCC, Mr. White [did] not have a valid drill permit”; and
    second, because “White did not continue to diligently drill after the lease was re-instated
    on January 27, 2009.” The Director explained that DNR had attempted to confirm
    White’s drilling activities and permit status following the reinstatement. DNR had sent
    White letters, and White had responded but without answering DNR’s specific questions.
    DNR eventually learned that the AOGCC had terminated White’s drilling permit, an
    action White was appealing.
    White appealed the termination of his lease to the Commissioner, asking
    that it again be reinstated. After some procedural delay not relevant here, White was
    granted an administrative hearing presided over by the Deputy Commissioner. White
    asked for “reinstatement of ADL 389922 lease terms, or alternatively an
    acknowledgment from DNR that the lease term did not expire as stated in a letter dated
    3
    See AS 38.05.180(m) (“If drilling, including operations such as redrilling,
    sidetracking, or using other means necessary to reach the originally proposed bottom
    hole location, has commenced on the expiration date of the primary term of the lease and
    is continued with reasonable diligence, the lease continues in effect until 90 days after
    drilling has ceased and for so long thereafter as oil or gas is produced in paying
    quantities.”); lease ¶4(c)(1), quoted supra note 2.
    -6-                                       7283
    January 2nd, 2009, and also an order dated July 23rd, 2009.”                  The Deputy
    Commissioner’s decision affirmed termination of the lease.
    White appealed to the superior court. The court ordered a remand for a new
    administrative hearing on the ground that DNR violated White’s due process rights when
    one of its attorneys, having initially advised DNR on White’s administrative appeal, then
    advised the Deputy Commissioner in her role as hearing officer. To provide guidance
    on remand the superior court also addressed the terms of the January 2009 reinstatement
    letter and the AOGCC permit. The superior court directed DNR that it could not
    terminate White’s lease based on the permit’s validity before the AOGCC had finally
    decided that issue. As for the reinstatement letter, the court interpreted its four
    conditions as not imposing “new conditions or unilateral amendments . . . . Instead,
    DNR appears to be reminding White of his obligations under the lease.” The court
    directed the agency on remand to review White’s efforts after reinstatement “to
    determine if he continued drilling with reasonable diligence” based on the totality of the
    circumstances, stressing that failure to meet the April 27 deadline alone was insufficient
    to show a lack of reasonable diligence.
    On remand, following a second administrative hearing before a different
    hearing officer, the Commissioner again upheld DNR’s termination of the lease. The
    Commissioner explained that White “did not demonstrate that [he] continued to drill with
    reasonable diligence or . . . failed to drill for reasons demonstrating reasonable diligence
    within the totality of the circumstances.”
    White again appealed to the superior court, where the case was heard by a
    different superior court judge.4 After briefing and argument, the court ruled that DNR’s
    4
    The appeal before remand was heard by Superior Court Judge Mark
    (continued...)
    -7-                                      7283
    January 2009 notice of expiration was a material breach: “An unjustified, outright
    cancellation of a contract cannot be other than a ‘material breach.’ ” The court further
    determined, contrary to the court’s analysis in the first appeal, that the breach was not
    cured by DNR’s reinstatement of the lease 25 days later; the court reasoned that the
    reinstatement letter’s requirement for “sustained production within 90 days following
    cessation of drilling” fundamentally conflicted with paragraph 4(d) of the lease, which
    allows a lessee at least six months after notice to bring “a well capable of producing oil
    or gas in paying quantities” into production.5 The court interpreted the lease as requiring
    “reasonableness and diligence, not deadlines,” especially deadlines resulting in automatic
    termination if not met. The court held that DNR’s material breach relieved White of his
    own lease obligations, and it therefore ordered that the lease be reinstated for a
    reasonable time for White “to resume, and then diligently continue, drilling in
    accordance with the Lease.” The court declined to address White’s damage claims,
    noting that “[w]hether other remedies are in order was not addressed by the parties.”
    Both parties appealed to this court.6
    4
    (...continued)
    Rindner. The appeal following the second administrative hearing was heard by Superior
    Court Judge Charles W. Ray, Jr.
    5
    Paragraph 4(d) provides: “If there is a well capable of producing oil or gas
    in paying quantities on the leased area, this lease will not expire because the lessee fails
    to produce that oil or gas unless the state gives notice to the lessee, allowing a reasonable
    time, which will not be less than six months after notice, to place the well into
    production, and the lessee fails to do so. If production is established within the time
    allowed, this lease is extended only for so long as oil or gas is produced in paying
    quantities from the leased area.”
    6
    White filed a motion for reconsideration of the superior court’s order,
    arguing that the issue of damages should have been remanded to the agency. The
    (continued...)
    -8-                                        7283
    III.   STANDARDS OF REVIEW
    We “independently review the merits of an administrative determination.”7
    We have “recognized four principal standards of review for
    administrative decisions: (1) the substantial evidence standard
    applies to questions of fact; (2) the reasonable basis standard
    applies to questions of law involving agency expertise;
    (3) the substitution of judgment standard applies to questions
    of law where no expertise is involved; and (4) the reasonable
    and not arbitrary standard applies to review of administrative
    regulations.”[8]
    “Questions of contract interpretation generally raise questions of law that
    we review de novo.”9 “Under this standard, we exercise our independent judgment,
    substituting it ‘for that of the agency even if the agency’s [interpretation] ha[s] a
    reasonable basis in law.’ ”10 We will “adopt the rule of law that is most persuasive in
    6
    (...continued)
    superior court denied reconsideration after White filed a motion asking that it refrain
    from ruling until we decided DNR’s appeal.
    7
    Handley v. State, Dep’t of Revenue, 
    838 P.2d 1231
    , 1233 (Alaska 1992).
    8
    Alaskan Crude Corp. v. State, Dep’t of Nat. Res., Div. of Oil & Gas, 
    261 P.3d 412
    , 419 (Alaska 2011) (quoting Pasternak v. State, Commercial Fisheries Entry
    Comm’n, 
    166 P.3d 904
    , 907 (Alaska 2007)).
    9
    
    Id. (quoting Beal
    v. McGuire, 
    216 P.3d 1154
    , 1162 (Alaska 2009)); Exxon
    Corp. v. State, 
    40 P.3d 786
    , 792 (Alaska 2001) (“Interpretation of a contract is a question
    of law that is not within the department’s special expertise or skill.”).
    10
    City of Valdez v. State, 
    372 P.3d 240
    , 246 (Alaska 2016) (alterations in
    original) (quoting Tesoro Alaska Petroleum Co. v. Kenai Pipe Line Co., 
    746 P.2d 896
    ,
    903 (Alaska 1987)).
    -9-                                      7283
    light of precedent, reason and policy.”11
    However, notwithstanding the usual substitution of judgment standard for
    questions of contract interpretation, we have applied the reasonable basis standard of
    review to agency interpretations of specialized contract terms derived from statutes or
    regulations.12
    IV.	   DISCUSSION
    DNR appeals the superior court’s decision that it must reinstate White’s
    lease, arguing that neither the January 2009 notice of expiration nor the subsequent
    reinstatement letter was a material breach of the lease. White’s appeal argues that the
    superior court erred by failing to remand the issue of his damages to the agency for a
    determination of what he is owed.
    A.	       The Commissioner Did Not Err In His 2013 Decision Affirming
    Termination of the Lease.
    We agree with the superior court that DNR’s January expiration notice
    materially breached the lease, but we conclude that the breach was cured by the
    11
    Thoeni v. Consumer Elec. Servs., 
    151 P.3d 1249
    , 1253 (Alaska 2007).
    12
    See Alaskan Crude 
    Corp., 261 P.3d at 419
    (applying reasonable basis
    standard when interpreting force majeure clause because force majeure was defined in
    DNR regulations); ConocoPhillips Alaska, Inc. v. State, Dep’t of Nat. Res., 
    109 P.3d 914
    ,
    920-21 (Alaska 2005) (applying reasonable basis standard when interpreting royalty
    rights clause subject to administrative process defined in regulations); N. Alaska Envtl.
    Ctr. v. State, Dep’t of Nat. Res., 
    2 P.3d 629
    , 633 n.12 (Alaska 2000) (“[W]here the
    agency interprets technical or esoteric terminology, we have applied reasonable basis
    review.” (citing Pan Am. Petroleum Corp. v. Shell Oil Co., 
    455 P.2d 12
    , 20-22 (Alaska
    1969))). “Examples of such terms we have deemed to be non-technical include ‘adjacent
    to,’ ‘local authorized planning agencies,’ ‘disposal,’ ‘interest in land,’ and ‘revocable.’
    ” City of 
    Valdez, 372 P.3d at 247
    (first quoting State v. Aleut Corp., 
    541 P.2d 730
    , 736­
    38 (Alaska 1975); and then quoting N. Alaska Envtl. 
    Ctr., 2 P.3d at 633
    ).
    -10-	                                    7283
    reinstatement letter. Thereafter, White continued to have the contractual duty to engage
    in drilling operations with reasonable diligence; the Commissioner’s decision that he
    failed in that duty is supported by substantial evidence.
    1.     The expiration notice breached the lease.
    Paragraph 4(c)(1) of the lease obligated DNR to extend the lease if White
    was engaged in drilling operations on December 31, 2008. DNR does not dispute that
    White satisfied this condition and that it was therefore obligated to extend the lease. But
    DNR sent White a letter on January 2, 2009, announcing without further explanation that
    the lease had expired. DNR argues both that the expiration notice was not a breach and
    that, if it was, the breach was not material.
    DNR contends that the expiration notice could not be a breach because it
    “had no language suggesting that the [S]tate would not perform.” We conclude,
    however, that any other reading of the notice is unreasonable. “When performance is
    due, . . . anything short of full performance is a breach, even if the party who does not
    fully perform was not at fault and even if the defect in his performance was not
    substantial.”13 The expiration notice stated perfunctorily that the lease had “expired” and
    DNR had closed its “case file.” The notice clearly contemplated no further action by
    DNR. The hearing officer at the second administrative hearing found that White’s
    actions in response to the notice — removing his equipment “from the drilling site to a
    different, presumably off-lease site location” — were “not unreasonable . . . in the sense
    of vacating a lease which had apparently been terminated.”14 And DNR’s later actions
    13
    RESTATEMENT (SECOND) OF CONTRACTS § 235 cmt. b (AM. LAW INST.
    1981).
    14
    See 58 C.J.S. Mines and Minerals § 337, Westlaw (database updated
    (continued...)
    -11-                                      7283
    in “retract[ing]” the expiration notice and “reinstat[ing]” the lease would not have been
    necessary had DNR actually viewed the lease as continuing in effect.
    DNR asserts that the expiration notice was only an “anticipatory breach,”
    not “sufficiently positive” to show that DNR had no intent to perform its obligations as
    they came due.15 The law of anticipatory breach applies when a party repudiates a
    contract, evidencing the intent to breach the contract before the party needs to perform.16
    As factors weighing against a finding of repudiation, DNR points to the notice’s
    language, the fact it was signed by a junior employee (a “Natural Resource Specialist”),
    and the lessee’s contractual right to appeal.
    As noted above, we conclude that the notice’s language — advising that the
    lease had “expired” and that “[t]he case file has been closed” — “[is] sufficiently positive
    to be reasonably interpreted to mean” that DNR was not extending the lease.17 This was
    14
    (...continued)
    Mar. 2018) (“[R]epudiation of an oil and gas lease by a lessor relieves the lessee of any
    obligation to conduct any operation on the land in order to maintain the lease in force
    pending a judicial resolution of the controversy between the lessee and the lessor over
    the validity of the lease.” (citing Teon Mgmt., LLC v. Turquoise Bay Corp., 
    357 S.W.3d 719
    , 730 (Tex. App. 2011))).
    15
    See K & K Recycling, Inc. v. Alaska Gold Co., 
    80 P.3d 702
    , 715 (Alaska
    2003) (“To be a repudiation, ‘a party’s language must be sufficiently positive to be
    reasonably interpreted to mean that the party will not or cannot perform.’ ” (quoting
    RESTATEMENT (SECOND) OF CONTRACTS § 250 cmt. b (AM. LAW. INST. 1981))).
    16
    Repudiation, BLACK’S LAW DICTIONARY (10th ed. 2014) (defining
    “repudiation” as “[a] contracting party’s words or actions that indicate an intention not
    to perform the contract in the future; a threatened breach of contract”); see Drake v.
    Wickwire, 
    795 P.2d 195
    , 198 (Alaska 1990) (quoting RESTATEMENT (SECOND) OF
    CONTRACTS § 253(1) (AM. LAW. INST. 1981)).
    17
    See K & K Recycling, 
    Inc., 80 P.3d at 715
    (quoting RESTATEMENT
    (continued...)
    -12-                                       7283
    “a clear, unequivocal challenge to [White’s] title to an interest in the lease” and thus a
    repudiation.18
    The fact that the notice was signed by a junior employee does not change
    this conclusion. Indeed, DNR does not argue that the signing employee lacked the
    necessary authority. Arguing that White should nonetheless have viewed the notice as
    something less than final, DNR points to lease paragraph 24, which identifies the
    Director of the Division of Oil and Gas as the authorized agent “for purposes of
    administering this lease.” But “[a] notification given by an agent is effective as
    notification given by the principal if the agent has actual or apparent authority to give the
    notification.”19 “Apparent authority to do an act is created as to a third person when a
    principal’s conduct, reasonably interpreted, ‘causes the third person to believe that the
    principal consents to have the act done on his behalf by the person purporting to act for
    him.’ ”20
    17
    (...continued)
    (SECOND) OF CONTRACTS § 250 cmt. b (AM. LAW. INST. 1981)); Expire, BLACK’S LAW
    DICTIONARY (10th ed. 2014) (“Expire” means “to be no longer legally effective; to
    become null at a time fixed beforehand”).
    18
    See 58 C.J.S. Mines and Minerals, Westlaw (database updated Mar. 2018)
    (citing Atkinson Gas Co. v. Albrecht, 
    878 S.W.2d 236
    , 239 (Tex. App. 1994)).
    19
    RESTATEMENT (THIRD) OF AGENCY § 5.02(2) (AM. LAW. INST. 2006).
    20
    Airline Support, Inc. v. ASM Capital II, L.P., 
    279 P.3d 599
    , 604-05 (Alaska
    2012) (quoting Askinuk Corp. v. Lower Yukon Sch. Dist., 
    214 P.3d 259
    , 264 (Alaska
    2009)). “We consider three factors when evaluating apparent authority: ‘(1) the
    manifestations of the principal to the third party; (2) the third party’s reliance on the
    principal’s manifestations; and (3) the reasonableness of the third party’s interpretation
    of the principal’s manifestations and the reasonableness of the third party’s reliance.’ ”
    
    Id. at 605
    (quoting Askinuk 
    Corp., 214 P.3d at 264
    ).
    -13-                                       7283
    The expiration notice was sent on DNR’s official stationery; it was sent
    following DNR’s on-site inspection of White’s drilling activity on December 31, 2008;
    and most importantly, as the second hearing officer found, it was “not unreasonable” for
    White to rely on the notice when he ceased drilling and removed his equipment from the
    well site. The hearing officer’s unchallenged finding leads us to the conclusion that the
    DNR employee who signed the expiration notice had at least the apparent authority to
    do so.
    Finally, DNR argues that the expiration notice could not be an anticipatory
    breach because the lease provided that such a notice could be appealed.21 But the right
    to appeal does not change the nature of the act from which the appeal is taken. A breach
    can be cured, but that does not mean it was never a breach.
    2.       DNR’s breach was material.
    Whether DNR’s breach was material is another question. Although the
    agency hearings were the only forums for fact-finding in these administrative
    proceedings, they resulted in no specific findings on materiality. On the first superior
    court appeal, however, the court assumed that DNR had materially breached the lease
    before going on to consider whether DNR cured the breach through reinstatement. On
    the second superior court appeal, the court expressly decided that “DNR’s breach was
    material. . . . An unjustified, outright cancellation of a contract cannot be other than a
    ‘material breach.’ ”
    21
    Paragraph 25(c) of the lease allows White, as the first step in the
    administrative appeal process, to appeal a notice within 30 days of its receipt. See 11
    AAC 02.010(e) (incorporating appeal period “set by 11 AAC 02.040”); 11 AAC
    02.040(a) (setting appeal deadline of 20 days “unless another period is set by . . . [an]
    existing contract”).
    -14-                                      7283
    We agree with the superior courts’ view that DNR’s breach was necessarily
    material. DNR correctly points out that whether a breach is material is a question “of
    degree, centering on the reasonable expectations of the parties, and a material breach is
    one that will or may result in the other party not receiving substantially what that party
    bargained for.”22 And ordinarily the question of materiality must be left to the fact­
    finder.23 But in some cases the breached provision is so obviously central to the purpose
    of the contract that materiality can be determined as a matter of law.24 We conclude that
    22
    See RESTATEMENT (SECOND) OF CONTRACTS § 241 (AM. LAW INST. 1981)
    (listing circumstances that are “significant” to “determining whether a failure to render
    or to offer performance is material,” including “the extent to which the injured party will
    be deprived of the benefit which he reasonably expected”; “the extent to which the
    injured party can be adequately compensated” for the lost benefit; the extent to which the
    non-breaching party “will suffer forfeiture”; the likelihood that the non-breaching party
    “will cure his failure, taking account of all the circumstances including any reasonable
    assurances”; and “the extent to which the behavior of the party failing to perform or to
    offer to perform comports with standards of good faith and fair dealing”).
    23
    See Wirum & Cash, Architects v. Cash, 
    837 P.2d 692
    , 708 (Alaska 1992)
    (remanding for superior court to “enter additional findings and conclusions as to whether
    [partner’s] various breaches [of fiduciary duties] were material breaches of the parties’
    contract” excusing other partner’s performance); 14 RICHARD A. LORD, WILLISTON ON
    CONTRACTS § 43.6, at 627 (4th ed. 2012) (“[W]hether a nonperformance is sufficiently
    material [to suspend or discharge the other party’s duty to perform] is ordinarily an issue
    of fact.”).
    24
    See 23 LORD, supra note 23, § 63.3, at 485 (“Nevertheless, the materiality
    of a breach of contract is not always a question of fact, even if the issue is disputed; thus,
    if there is only one reasonable conclusion, a court must address what is ordinarily a
    factual question as a question of law.”); cf. Gilbert v. Dep’t of Justice, 
    334 F.3d 1065
    ,
    1071-72 (1st Cir. 2003) (explaining that whether breach is material is mixed question of
    law (what contract requires) and fact (what breaching party did); so that “[w]here, as
    here, the facts are undisputed, the determination of whether there has been material non­
    compliance with the terms of a contract, and hence breach, necessarily reduces to a
    (continued...)
    -15-                                        7283
    the breach at issue here, resulting in termination of the lease and prompting White to
    reasonably suspend his own performance while awaiting reinstatement, affected rights
    so central to the parties’ reasonable expectations that it could only be viewed as material.
    3.     Reinstatement of the lease cured the breach.
    The Commissioner retracted the expiration notice and reinstated the lease
    in his January 27, 2009 letter. White asserts that the reinstatement letter added new
    conditions to the lease, amounting to another breach. It is true that “language that clearly
    manifests an ‘intention not to perform except on conditions which go beyond the
    contract’ ” may be a repudiation.25 A demand that new conditions be met, even if based
    on “an alleged ‘contract interpretation,’ ” may be an anticipatory breach.26
    In support of this argument, White refers to the letter’s paragraph that
    begins “in summary” and lists four conditions for “the continued extension of the lease”:
    “(1) continued drilling of the well; (2) completion of the well by April 27, 2009; (3) valid
    24
    (...continued)
    question of law”); Alaska Interstate Constr., LLC v. Pacific Diversified Invs., Inc., 
    279 P.3d 1156
    , 1173 (Alaska 2012) (recognizing rule “that fraud and other forms of
    intentional wrongdoing constitute material breaches of contract as a matter of law”).
    25
    K & K Recycling, Inc. v. Alaska Gold Co., 
    80 P.3d 702
    , 715 (Alaska 2003)
    (quoting RESTATEMENT (SECOND) OF CONTRACTS § 250 cmt. b (AM. LAW INST. 1981));
    see also 10 JOHN E. MURRAY, JR., CORBIN ON CONTRACTS § 54.15, at 200 (Joseph M.
    Perillo ed., rev. ed. 2014) (“If one party to a contract, either willfully or by mistake,
    demands of the other a performance to which he has no right under the contract and
    states definitely that, unless his demand is complied with, he will not render his promised
    performance, an anticipatory breach has been committed. Such a repudiation is
    conditional in character, it is true; but the condition is a performance to which the
    repudiator has no right.”).
    26
    Snow v. W. Sav. & Loan Ass’n, 
    730 P.2d 204
    , 210 (Ariz. 1986) (en banc)
    (quoting United Cal. Bank v. Prudential Ins. Co. of Am., 
    681 P.2d 390
    , 430 (Ariz. App.
    1983)).
    -16-                                       7283
    permits for all operations; and (4) sustained production within 90 days following the
    cessation of drilling.” White contends that the first condition — “continued drilling of
    the well” — conflicts with lease paragraph 4(e), which gives the lessee a reasonable time
    to recommence “operations or production” if the State “directs or approves in writing a
    suspension of all operations on or production from the leased area” and then lifts the
    suspension. But White sought and was granted the extension under paragraph 4(c)(1),
    not paragraph 4(e). And we read paragraph 4, subsections (a) through (f), as addressing
    usually distinct circumstances:
    * Subsection (a) provides automatic lease extensions while oil or gas is
    being produced in paying quantities.
    * Subsection (b) provides automatic lease extensions for leases committed
    to State-approved unit agreements.
    * Subsection (c) provides automatic lease extensions under two scenarios:
    (1) if drilling has commenced “as of the date on which the lease otherwise would expire
    and is continued with reasonable diligence”; and (2) if the lease was producing “oil or
    gas in paying quantities,” production ceases, but “drilling or reworking operations are
    commenced . . . within six months after cessation of production and are prosecuted with
    reasonable diligence.”
    * Subsection (d) addresses leases with wells “capable of producing oil or
    gas in paying quantities”; leases encompassing such wells will not expire despite the lack
    of production unless the State gives the lessee notice “allowing a reasonable time, which
    will not be less than six months after notice, to place the well into production.”
    * Subsection (e) addresses leases subject to State orders to suspend
    operations or production; lessees have “a reasonable time, which will not be less than six
    -17-                                       7283
    months after notice that the suspension has been removed, to resume operations or
    production.”
    * Subsection (f) addresses leases on which operations or production have
    been “prevented by force majeure.”
    The circumstances of White’s lease extension fall squarely within
    paragraph 4(c), which is why he adamantly — and successfully — argued to DNR for
    that provision’s application. White was conducting drilling activities on December 31,
    2008, the date the lease would otherwise have expired, and his lease term therefore
    extended automatically as long as his drilling activities were “continued with reasonable
    diligence.” He did not suspend operations because of a written DNR order that he do so,
    as contemplated by paragraph 4(e). Another lease provision gives DNR an apparently
    broad authority to “from time to time direct or approve in writing suspension of
    production or other operations under this lease.” But a suspension implies a mere
    interruption in performance, not an end to it,27 and fitting this case within the framework
    of paragraph 4(e) thus cuts against White’s central argument that the January expiration
    notice terminated his lease. Indeed, White argues inconsistently on this appeal that
    “DNR did not suspend operations on [the lease], they terminated it.”
    Moreover, subsections 4(c) and (e) cannot reasonably be read as governing
    the same situation simultaneously. Paragraph 4(c) requires that the lessee “continue[]
    with reasonable diligence” the drilling activities engaged in on the last day of the lease
    term (emphasis added); paragraph 4(e) allows the lessee “not . . . less than six months
    27
    “Suspend” means “[t]o interrupt; postpone; defer,” or “[t]o temporarily
    keep (a person) from performing a function . . . or exercising a right or privilege.”
    BLACK’S LAW DICTIONARY (10th ed. 2014).
    -18-                                      7283
    after notice” to resume such activities, having discontinued them because of the
    suspension order.
    Addressing the second condition in DNR’s reinstatement letter —
    “completion of the well by April 27, 2009” — White contends that it conflicts with the
    language of paragraph 4(c)(1) that automatically extends the lease for as long as the
    lessee continues drilling activities “with reasonable diligence.” The State counters that
    the reinstatement letter “simply voiced a reasonable interpretation of when drilling with
    ‘reasonable diligence’ would be complete as provided in the lease”; in other words,
    diligent effort that fails to complete the well by April 27 could not, in the
    Commissioner’s view, be “reasonable.” We agree with White that a fixed deadline
    seems inconsistent with a flexible, fact-based completion standard like the contractual
    term “with reasonable diligence”; a lessee acting “with reasonable diligence” could fall
    short of a fixed deadline for a variety of reasons.28
    On the other hand, we must give some deference to the Commissioner’s
    decision as to what constitutes “reasonable diligence” in this highly specialized context.
    Although the interpretation of a contract presents a question of law, we review questions
    that necessarily involve agency expertise under the “reasonable basis” test, “giving
    deference to the agency’s specialized knowledge and expertise.”29
    28
    See Diligence, BLACK’S LAW DICTIONARY (10th ed. 2014) (defining
    “reasonable diligence” as “[a] fair degree of diligence expected from someone of
    ordinary prudence under circumstances like those at issue”).
    29
    Alaska Fish & Wildlife Conservation Fund v. State, Dep’t of Fish & Game,
    Bd. of Fisheries, 
    289 P.3d 903
    , 912 n.31 (Alaska 2012) (quoting Alaska Exch. Carriers
    Ass’n v. Regulatory Comm’n, 
    262 P.3d 204
    , 208-09 (Alaska 2011)).
    -19-                                     7283
    Here, the Commissioner explained his interpretation of the “reasonable
    diligence” standard in his June 10, 2009 decision on White’s request that DNR
    reconsider the reinstatement letter. The Commissioner recited White’s description of the
    activities he had already done to prepare the well for drilling, including completion of
    a “120 foot water well with a pump to provide water” and the staging of “the workover
    rig, blow out preventer, mud tanks, drill pipe and other major equipment necessary and
    incidental to reach the proposed bottom hole location.” The Commissioner noted his
    reliance on paragraph 4(c)(1) of the lease and the legal sources from which it was
    derived, AS 38.05.180(m) and 11 AAC 83.125, as well as the lease’s expansive
    definition of “drilling.” He explained that the April 27 deadline — 90 days from the date
    of the reinstatement letter — had been extrapolated from “White’s Plan of Operations,
    which stated that it would take 30 days to complete this well.”30 The Commissioner
    trebled White’s own estimate. This interpretation, the Commissioner summarized, was
    based on “the lease language consistent with the terms set forth in state law, in paragraph
    4 of the lease and Mr. White’s own representations about his plans.”
    The Commissioner correctly observed that the contractual “reasonable
    diligence” standard is drawn directly from statute and regulation: AS 38.05.180(m)31 and
    30
    The lease required that the plan of operations set out “the sequence and
    schedule of operations to be conducted[,] including the date operations are proposed to
    begin and their proposed duration,” and that the plan be submitted and approved “before
    any operations may be undertaken.”
    31
    “If drilling, including operations such as redrilling, sidetracking, or using
    other means necessary to reach the originally proposed bottom hole location, has
    commenced on the expiration date of the primary term of the lease and is continued with
    reasonable diligence, the lease continues in effect until 90 days after drilling has ceased
    and for so long thereafter as oil or gas is produced in paying quantities.”
    (continued...)
    -20-                                       7283
    11 AAC 83.125.32 In Alaskan Crude Corp. v. State, Department of Natural Resources,
    Division of Oil & Gas, we considered what standard of review applied to the
    interpretation of a force majeure clause.33 The parties disputed whether the agency
    applied the force majeure clause from the oil and gas lease or the unit agreement: if it
    was from the lease it was subject to de novo review as a matter of contract interpretation,
    but if it was from the unit agreement it was subject to deference as the agency’s
    interpretation of its own regulation.34 We concluded that the agency applied the force
    majeure clause from the unit agreement and its decision was subject to deference because
    “[t]he definition of force majeure [in] the unit agreement is contained in DNR
    regulations.”35 In this case, similarly, we conclude that the Commissioner strived in his
    reconsideration decision to interpret the contractual term “reasonable diligence”
    consistently with its sources in statute and regulation. We conclude that, as in Alaskan
    Crude, the Commissioner’s interpretation of the “reasonable diligence” standard was “an
    31
    (...continued)
    AS 38.05.180(m) (emphasis added).
    32
    “If drilling, including redrilling, sidetracking, or other means necessary to
    reach the originally proposed bottom hole location, has commenced on or before the
    expiration date of the primary term of the lease and is continued through that date with
    reasonable diligence, the lease will continue in full force until 90 days after the drilling
    has ceased and for so long after that date as oil or gas is produced in paying quantities.”
    11 AAC 83.125(a) (emphasis added).
    33
    
    261 P.3d 412
    , 419 (Alaska 2011).
    34
    
    Id. 35 Id.
    (citing 11 AAC 83.395(3)).
    -21-                                       7283
    interpretation of the agency’s own regulations and the deferential reasonable basis
    standard applies.”36
    Relatedly, we have also applied the reasonable basis standard to terms that
    are flexible and evolving rather than immutable and subject to one fixed definition, and
    thus more susceptible to determination as a matter of law. In ConocoPhillips Alaska,
    Inc. v. State, Department of Natural Resources, we held that “the crucial question” for
    us in interpreting a regulatory standard incorporated into an oil and gas lease was
    “whether this standard describe[d] a fixed and immutable test” — which “might well
    present a pure question of law to be decided de novo” — or whether it described instead
    “a more flexible process . . . grounded in the department’s exercise of discretion and
    expertise and having the capacity to evolve as contemporary scientific knowledge
    advances,” in which case our review “would need to be appropriately deferential.”37
    Finding that the standard was flexible and evolving, we deferred to the Commissioner’s
    interpretation of it.38 The concept of “reasonable diligence” in the context of well-
    drilling activities strikes us as flexible enough to require similarly deferential review.
    In support of the Commissioner’s interpretation we note that the
    reinstatement letter advised White not only that he had an additional 90 days to complete
    the well or face “automatic termination of this lease” but also that after 90 days DNR
    would “review [White’s] progress to determine whether continued lease extension [was]
    36
    Id.
    37
    
    109 P.3d 914
    , 920 (Alaska 2005).
    38
    
    Id. at 921-23.
                                               -22-                                       7283
    warranted.”39 We note also that White continued to have the protection of the force
    majeure clause in paragraph 4(f) of the lease, by which he could seek further extensions
    if his failure to meet the April 27 deadline was due to causes “beyond [his] reasonable
    ability to foresee or control.”40 Under our deferential standard of review, we conclude
    that the Commissioner’s decision that White could complete drilling within 90 days —
    by April 27, 2009 — if he exercised “reasonable diligence” has a reasonable basis in the
    facts, the terms of the lease, and the law; we therefore do not disturb it.
    White also challenges the reinstatement letter’s third condition — “valid
    permits for all operations” — as allowing DNR to terminate the lease “on the erroneous
    basis that the Lessee [does] not have a valid drilling permit.” But he does not argue that
    a requirement of “valid permits” is inconsistent with the lease; indeed, any permit
    required by statute or regulation is also required by the lease, which is expressly made
    “subject to all applicable state and federal statutes and regulations in effect on the
    effective date of this lease” and, “as is constitutionally permissible,” laws enacted later
    as well.
    Finally, White challenges the last condition — “sustained production within
    90 days following the cessation of drilling” — as contrary to lease paragraph 4(d), which
    allows a lessee “a reasonable time, which will not be less than six months after notice,”
    39
    See K & K Recycling, Inc. v. Alaska Gold Co., 
    80 P.3d 702
    , 715 (Alaska
    2003) (“[T]o be an anticipatory breach based on a request for additional conditions, ‘the
    request must be coupled with an absolute refusal to perform unless the request is
    granted.’ ” (quoting 17A AM. JUR. 2d Contracts § 738, at 752 (1991))).
    40
    See 11 AAC 83.395(3) (“ ‘[F]orce majeure’ means war, riots, acts of God,
    unusually severe weather, or any other cause beyond the unit operator’s reasonable
    ability to foresee or control and includes operational failure to existing transportation
    facilities and delays caused by judicial decisions or lack of them.”).
    -23-                                      7283
    to place into production “a well capable of producing oil or gas in paying quantities.”
    But as explained above, the subsections of paragraph 4 address different circumstances,
    and White’s circumstances, as he argued consistently himself, fit paragraph 4(c)(1): that
    is, as long as his drilling activities were “continued with reasonable diligence, [the] lease
    [would] continue in effect until 90 days after cessation of that drilling and for so long as
    oil or gas [was] produced in paying quantities.” Paragraph 4(d) addresses wells that are
    already “capable of producing oil or gas in paying quantities.” A lessee with such a
    well, but who is not producing, has at least six months to commence production once
    DNR gives notice that production is required. But White has no such well under the
    lease here at issue. A lessee like White — who extends the lease term by drilling
    activities on the last day of the term — must continue drilling “with reasonable
    diligence,” must commence production within “90 days after cessation of that drilling,”
    and will maintain the lease only “for so long as oil or gas is produced in paying
    quantities.” The reinstatement letter’s fourth condition merely restates the requirements
    of lease paragraph 4(c)(1), the provision governing White’s extension.
    We conclude that the Commissioner did not err when he decided that the
    reinstatement letter did not impose new conditions on DNR’s continued performance
    under the lease but rather interpreted or applied the lease’s terms.
    3.	    DNR’s termination of the lease was supported by substantial
    evidence.
    Because we conclude that DNR’s January 2009 breach was cured by
    reinstatement, we next consider whether DNR was justified in terminating the lease in
    July. White argues that DNR’s justifications for termination — lack of both a valid
    drilling permit and drilling activity — were flawed. In White’s first superior court
    appeal, the court agreed with White about the valid drilling permit, concluding that it did
    -24-	                                      7283
    not justify termination as long as the validity was the subject of a pending administrative
    appeal with AOGCC. But on remand the Commissioner relied solely on White’s failure
    “to drill with reasonable diligence.” On appellate review, our task is to determine
    whether the Commissioner had substantial evidence to support the finding that White did
    not drill with reasonable diligence.41
    We conclude that the Commissioner’s decision is adequately supported.
    His decision related the following facts. On December 31, 2008, DNR’s representative
    at the drill site observed some activities short of “actual boring” that nonetheless
    qualified as “drilling activities” sufficient to extend the lease term. On January 2, 2009,
    upon receipt of the notice of expiration, White demobilized his equipment and removed
    it from the well site to “hard ground.”42 A few weeks later, in the midst of White’s
    attempts to have the expiration notice retracted, DNR personnel observed other “activity
    [at the site] that could be associated with drilling, but did not observe the drill bit actually
    boring in the well or actual operation of the drill rig and systems in the act of drilling.”
    The Commissioner noted that by April, White’s “drill rig had been located to Kenai.”
    41
    “We review the agency’s factual findings using the substantial evidence
    standard. ‘Substantial evidence is defined as such relevant evidence as a reasonable
    mind might accept as adequate to support [the agency’s] conclusion.’ ‘We determine
    only whether such evidence exists and do not choose between competing inferences or
    evaluate the strength of the evidence.’ ” Alaskan Crude Corp. v. State, Alaska Oil & Gas
    Conservation Comm’n, 
    309 P.3d 1249
    , 1254 (Alaska 2013) (quoting Lopez v. Adm’r,
    Pub. Emps.’ Ret. Sys., 
    20 P.3d 568
    , 570 (Alaska 2001) (alteration in original))).
    42
    We note that paragraph 21 of the lease gave White “a period of one year
    after the termination, or any extension of that period as may be granted by the state, to
    remove from the leased area or portion of the leased area all machinery, equipment,
    tools, and materials.”
    -25-                                         7283
    The Commissioner found that “the 25 days lost [between the expiration
    notice and the lease reinstatement] were not critical to the overall capacity to drill on the
    site.” The Commissioner did note, however, that White had a fairly small window of
    opportunity between reinstatement and thaw in order to remobilize, but he found that
    White made no productive use of this window, choosing to focus his efforts “on
    litigation rather than a resumption of activities.” White testified that “following
    reinstatement he did take steps to assess the rental costs of trucking and other costs to
    move drilling equipment back to the site,” as well as the availability of truck drivers for
    that purpose. But the Commissioner noted that White’s decision to focus on litigation
    was a “strategic choice” that banked — ultimately unsuccessfully — on the courts
    accepting White’s contract-interpretation arguments over DNR’s. The Commissioner
    noted further that litigation activity is not a “drilling activity” as defined in the lease.
    White does not dispute that he chose litigation over a resumption of drilling
    activities; he testified that after reinstatement of his lease he “did not perform any further
    work other than the preliminary mobilization process to re-mobilize and transport that
    equipment back out . . . .” We conclude that substantial evidence supports the
    Commissioner’s decision that White did not continue drilling “with reasonable
    diligence” when he had the opportunity to do so, and that he therefore failed to satisfy
    the requirements for a continued lease extension under paragraph 4(c)(1).
    B.     There Is No Agency Decision on Damages For Us To Review.
    White urges us to hold that the superior court should have remanded the
    case to the agency for a determination of his damages; he urges us to order such a
    remand. DNR asks us not to consider White’s claim because his cross-appeal was
    -26-                                        7283
    untimely43 and he waived the issue of damages. Our holding that the initial breach was
    cured by the reinstatement letter moots any claim for damages following reinstatement.
    But the issue remains whether White is entitled to damages incurred between the
    January 2, 2009 expiration notice and the reinstatement 25 days later.44
    However, there is no agency decision on damages for us to review. Oil and
    gas lessees are required, at least initially, “to pursue” “all grievances through
    administrative remedies.”45 When filing an appeal or request for reconsideration, the
    appellant must “specify the remedy requested.”46 In this case, at every step of the
    administrative appeal process White asked only that DNR reinstate the lease. He had
    repeated opportunities in the successive administrative proceedings to present evidence
    of his damages, or at least to assert a right to a separate hearing on the issue.47 But
    43
    We conclude that the timing of White’s pro se cross-appeal indicated a
    good-faith effort to comply with the appellate rules based on reasonable confusion about
    their requirements, and we therefore consider it. See Conitz v. Alaska State Comm’n for
    Human Rights, 
    325 P.3d 501
    , 506 (Alaska 2014).
    44
    See RESTATEMENT (SECOND) OF CONTRACTS § 236 cmt. b (AM. LAW INST.
    1981) (“[E]very breach gives rise to a claim for damages.”).
    45
    White v. State, Dep’t of Nat. Res., 
    14 P.3d 956
    , 960 (Alaska 2000) (citing
    11 AAC 88.155); Danco Expl., Inc. v. State, Dep’t of Nat. Res., 
    924 P.2d 432
    , 434
    (Alaska 1996) (“Oil and gas lessees and lease bidders which have grievances with the
    State must pursue the administrative procedures provided by 11 AAC 02.010, et seq.”).
    46
    11 AAC 02.030(a)(10).
    47
    For example, in February 2009 the Commissioner, responding to White’s
    request for reconsideration of the reinstatement letter, invited him to “submit additional
    written material or request a hearing,” but White declined, stating “I do not believe that
    an additional briefing or hearing is necessary in order for you [to] decide this issue.” At
    the first administrative hearing on the termination, White’s counsel stated: “We do not
    (continued...)
    -27-                                      7283
    although White made references to “being damaged,” experiencing “undue financial
    harm” and “escalating” costs, and losing opportunities to sell gas, he never specifically
    demanded money damages for these alleged harms.
    It is up to DNR in the first instance to determine whether White has waived
    any right to recover damages. On the appellate record, however, we see no basis on
    which to conclude that he was deprived of a right to seek damages in the administrative
    proceeding or that the superior court erred when it failed to remand for further
    proceedings on that issue.
    V.    CONCLUSION
    We REVERSE the superior court’s decision reinstating the lease and
    AFFIRM the Commissioner’s decision terminating the lease.
    47
    (...continued)
    plan on putting any additional evidence on . . . .” At the second administrative hearing
    following the superior court’s remand, White testified that he could prove the costs
    incurred in demobilizing the well site and the damages from lost opportunities to export
    gas, but he provided no evidence in support of the claim and waived the opportunity to
    file a post-hearing brief.
    -28-                                     7283
    

Document Info

Docket Number: 7283 S-16308-S-16417

Citation Numbers: 441 P.3d 393

Judges: Stowers, Winfree, Maassen, Bolger, Carney

Filed Date: 8/31/2018

Precedential Status: Precedential

Modified Date: 10/19/2024

Authorities (19)

ALASKAN CRUDE CORP. v. State , 261 P.3d 412 ( 2011 )

K & K RECYCLING, INC. v. Alaska Gold Co. , 2003 Alas. LEXIS 131 ( 2003 )

Beal v. McGuire , 216 P.3d 1154 ( 2009 )

Askinuk Corp. v. Lower Yukon School District , 2009 Alas. LEXIS 107 ( 2009 )

ConocoPhillips v. DEPT. OF NAT. RESOURCES , 109 P.3d 914 ( 2005 )

Atkinson Gas Co. v. Albrecht , 878 S.W.2d 236 ( 1994 )

Thoeni v. Consumer Electronic Services , 2007 Alas. LEXIS 2 ( 2007 )

Tesoro Alaska Petroleum Co. v. Kenai Pipe Line Co. , 1987 Alas. LEXIS 329 ( 1987 )

Pasternak v. State, Commercial Fisheries Entry Commission , 2007 Alas. LEXIS 107 ( 2007 )

Exxon Corp. v. State , 2001 Alas. LEXIS 139 ( 2001 )

State v. Aleut Corporation , 1975 Alas. LEXIS 313 ( 1975 )

United California Bank v. Prudential Insurance Co. of ... , 140 Ariz. 238 ( 1983 )

Handley v. State, Department of Revenue , 1992 Alas. LEXIS 109 ( 1992 )

Wirum & Cash, Architects v. Cash , 1992 Alas. LEXIS 52 ( 1992 )

Northern Alaska Environmental Center v. State, Department ... , 2000 Alas. LEXIS 52 ( 2000 )

Danco Exploration, Inc. v. State, Department of Natural ... , 1996 Alas. LEXIS 117 ( 1996 )

Pan American Petroleum Corp. v. Shell Oil Co. , 1969 Alas. LEXIS 230 ( 1969 )

Lopez v. Administrator, Public Employees' Retirement System , 2001 Alas. LEXIS 34 ( 2001 )

White v. State, Department of Natural Resources , 2000 Alas. LEXIS 119 ( 2000 )

View All Authorities »