Western Sur. Co. v. Bradford Elec. Co., Inc. ( 2007 )


Menu:
  • 483 F. Supp. 2d 1114 (2007)

    WESTERN SURETY COMPANY, Plaintiff,
    v.
    BRADFORD ELECTRIC CO., INC., et al., Defendants.

    No. CV-06-J-183-NE.

    United States District Court, N.D. Alabama, Northeastern Division.

    April 23, 2007.

    *1115 *1116 *1117 Brian A. Dodd, L. Graves Stiff, III, Thomas L. Selden, Starnes & Atchison LLP, Birmingham, AL, for Plaintiff.

    Stacy Linn Moon, Allen L. Anderson, Michael L. Fees, Fees & Burgess PC, Ashley E. Swink, G. Bartley Loftin, III, Balch & Bingham, Huntsville, AL, David Wanhatalo, L. Griffin Tyndall, Burr & Forman LLP, Michael J. Douglas, Friedman Leak & Bloom PC, Christopher J. Zulanas, Friedman Leak Dazzio Zulanas & Bowling PC, John M. Laney, Jr., Laney & Foster PC, Birmingham, AL, Jefferson C. *1118 Orr, Vic L. McConnell, Smith Cashion & Orr PLC, Nashville, TN, for Defendants.

    MEMORANDUM OPINION

    JOHNSON, District Judge.

    In accordance with the settlement agreement of the parties, plaintiff Western Surety Company ("Western") and defendants Bradford Electric Co., Inc., and Richard T. Bradford (collectively "Bradford")[1] submitted briefs to the court on the issue of indemnification and attorney fees. The court held a hearing on that issue on December 12, 2006, at which the aforementioned parties were present by and through their respective counsel of record. Based on the briefs, the arguments of the parties, the pleadings in the record, and the applicable law, the court finds as follows:

    Western issued performance and payment bonds on behalf of Bradford for electrical work Consolidated Construction Company ("Consolidated") subcontracted to Bradford at the Columbia High School project in Huntsville, Alabama. The performance bond was issued in favor of Consolidated for $1,607,756.00, the full amount of the subcontract. Complaint, ¶ 4; Cross-Claim and Counterclaim, ¶¶ 8-9; Bradford Cross-Claim, ¶ 3; exhibit A to the Complaint. Bradford issued a General Agreement of Indemnity (GM) in favor of Western, by which Bradford agreed to indemnify plaintiff from any and all loss or anticipated loss which might result from issuance of the performance bond. Affidavit of Joan Clements, ¶¶ 3-4. Due to disputes over the timeliness of the work being performed by Bradford, Consolidated terminated its contract with Bradford in August 2005 and notified Western it sought payment under the performance bond.

    As of January 4, 2006, Western had paid $24,262.30 under the subcontractor payment bond based on claims from laborers and material suppliers. Affidavit of Clements, ¶ 11. No other sums have been paid under the payment bond. No amounts have been paid under the performance bond.[2] On January 27, 2006, Western filed this action against Bradford, Consolidated, the architect who designed the school, and the electrical engineering company who designed the electrical plans for the school. All claims, cross-claims and counterclaims have been settled. The sole issue before the court is Western's claim for indemnification on attorney fees and related expenses it incurred in this suit. Western seeks a judgment in its favor for the amount paid under the payment bond as well as all attorney fees and costs incurred in this litigation. Bradford responds that the amount claimed by Western is simply not reasonable.[3]

    The General Agreement of Indemnity ("GAI") states in relevant part as follows:

    2. The Indemnitors will indemnify and save the Company harmless from and against every claim, demand, liability, cost, charge, suit, judgment and expense which the Company may pay or incur in consequence of having executed, or procured the execution of such bonds, or *1119 any renewals or continuations thereof or substitutes therefore, including, but not limited, to fees of attorneys, whether on salary, retainer or otherwise, and the expense of procuring, or attempting to procure, release from liability, or in bringing suit to enforce the obligation of any of the Indemnitors under this Agreement. In the event the Company deems it necessary to make an independent investigation of a claim, demand, or suit, the Indemnitors acknowledge and agree that all expense attendant to such investigation is included as an indemnified expense. In the event of payments by the Company, the Indemnitors agree to accept the voucher or other evidence of such payments as prima facie evidence of the propriety thereof, and of the Indemnitors' liability therefore to the Company.

    Plaintiff's exhibit C to the Complaint, ¶ 2. Defendant Bradford, through its president, Richard T. Bradford, signed this agreement on January 31, 2003. Defendant Richard T. Bradford also signed this agreement as an individual indemnitor on this same date.

    Western seeks indemnification for its attorney fees and the sole payment made under the payment bond pursuant to this agreement. The parties do not dispute that the only sum Western paid prior to filing this action was the Automatic Control Devices, Inc., claim of $24,262.30.[4] Western seeks reimbursement for fees and expenses in the total amount of $324,861.11.[5] Despite Western's repeated demands that Bradford provide collateralization based on potential claims under the two bonds, Western has not paid any sums other than the $24,262.30.[6] Thus, the court is troubled by the open season on billing which thereafter apparently occurred.

    Western cites Frontier Insurance Company v. International, Inc., 124 F. Supp. 2d 1211 (N.D.Ala.2000), for the proposition that Western is entitled to "reimbursement from defendants, separately and severally, of all losses, costs, attorney's fees and expenses incurred as a result of the Consolidated claim." Brief of Western Surety (doc. 146) at 8. Frontier Insurance states "a surety is entitled to reimbursement pursuant to an indemnity contract for any payments made by it in a good faith belief that it was required to pay, regardless of whether any liability actually existed." Id., at 1213 (citations omitted).

    However, pursuant to a contract of indemnity for attorney fees, the concept of good faith must be applied. In every contract "there exists an implied covenant of good faith and fair dealing." See Hunter v. Wilshire Credit Corporation, 927 So. 2d 810, 813 (Ala.2005) (quoting Sellers v. Head, 261 Ala. 212, 73 So. 2d 747, 751 (1954)); Lloyd Noland Foundation, Inc. v. City of Fairfield Healthcare Authority, 837 So. 2d 253, 267 (Ala.2002). An indemnitor can defeat a surety's right to recover under indemnity provisions by demonstrating *1120 lack of good faith on the part of the surety in discharging its obligations under the bond. Frontier Insurance Co., 124 F.Supp.2d at 1214; citing Fidelity and Deposit Co. of Maryland v. Bristol Steel and Iron Works, Inc., 722 F.2d 1160, 1163 (4th Cir.1983).

    Thus, although not explicitly stated by the GAI, the court finds that the concept of "reasonableness" must be applied to any claim for indemnification of attorney fees. See e.g., Ideal Electronic Security Co., Inc. v. International Fidelity Insurance Company, 129 F.3d 143, 148-149 (D.C.Cir.1997)(courts in other jurisdictions have indicated that, as a general matter, a surety must show something akin to reasonable necessity when seeking attorney fees under an indemnity agreement (emphasis in original)); Neustrom v. Union Pacific Railroad Company, 156 F.3d 1057, 1068 (10th Cir.1998) ("a duty to act reasonably must be read into every contract, including the terms of indemnification clauses"). Olan Mills, Inc. v. Linn Photo Co., 23 F.3d 1345, 1348 (8th Cir.1994) citing Quinto v. Legal Times of Washington, Inc., 506 F. Supp. 554, 562 (D.D.C. 1981)(good faith entails both honesty in fact and reasonableness).

    The Alabama Supreme Court dealt with this issue directly, many years ago, stating:

    In construing indemnity covenants like that before us, it is everywhere recognized that the indemnitee must act in good faith. He cannot needlessly, in utter disregard of the burdens he is imposing on his indemnitor, incur attorney's fees, and in no case such as are excessive and unreasonable in amount. The rule is otherwise stated as requiring good faith and the exercise of a reasonable discretion. . . .
    Good faith in such cases is that which obtains between persons standing in confidential or fiduciary relations; a good faith which carries a duty to have regard for the interests of his associate, an application of the principles of the golden rule.
    Good faith implies the exercise of a reasonable discretion in the circumstances.

    Kilgore v. Union Indemnity Co., 222 Ala. 375, 132 So. 901 (1931). See also Perkins v. Thompson, 551 So. 2d 204, 209 (Miss. 1989).[7] Following these principles, the Fifth Circuit Court of Appeals held:

    In sum, an indemnity agreement is not a blank check; it does not entitle the surety company to reimbursement for legal expenses which are unreasonable or unnecessary. To hold otherwise would allow bonding companies to retain counsel and to charge attorneys' fees against the indemnitor even when the surety company does not require a separate legal defense to protect its interests. The indemnity contract cannot reasonably be construed as requiring the indemnitee to bear the cost of such redundant representation. Thus, the weight of authority *1121 allows reimbursement for legal costs under the terms of an indemnity contract only if it is necessary for the surety to retain separate counsel, if the amount of the fees claimed is reasonable, and if the surety has acted in good faith toward the bond principal.

    Jackson v. Hollowell, 685 F.2d 961, 966 (5th Cir.1982). Western has repeatedly represented to this court that retention of separate counsel by Western was both necessary and reasonable. See e.g., Brief of Western Surety Company (doc. 146) at 2. In fact, Western asserts that "Western, BECI and Richard T. Bradford have always been adverse in this case." Id.

    With these legal tenets in mind, the court considers the reasonableness of the attorney fees and expenses claimed by Western. The court has also considered that, with the exception of a bad faith claim against Western by Consolidated, all other claims against Western were contingent on liability being found against Bradford. Without that, Western could have no liability. However, unlike many surety situations, Western was not content to rely on Bradford's defense counsel to protect its interests as well.

    The court also considers the basic caveats set forth by the Eleventh Circuit for reasonableness of attorneys fees, such as that time billed must not be "excessive, redundant, or otherwise unnecessary . . ." ACLU v. Barnes, 168 F.3d 423, 428 (11th Cir.1999). Similarly, hours spent on purely clerical work or secretarial tasks are unrecoverable overhead expenses. Allen v. U.S. Steel Corp., 665 F.2d 689, 697 (5th Cir.1982). Paralegal expenses are recoverable only to the extent that the paralegal performs work traditionally done by an attorney. Otherwise, paralegal expenses are unrecoverable overhead expenses. Id.

    During the hearing held on this claim, counsel admitted the following sums were erroneously included in this claim, and are therefore withdrawn:

    7/25/2006    LGS    Preparation for                          2.80    560.00
    hearing on Temporary
    Restraining
    Order request and
    response to inquiry
    from Judge Bowen.
    11/28/2006   BAD    ... preparation of                       4.40    814.00
    motion for summary
    judgment[8]
    11/29/2006   BAD    Preparation and revision                 4.20    777.00
    of Memorandum
    supporting
    Motion for Summary
    Judgment
    11/29/2006   LGS    Review of correspondence                 3.40    680.00
    from
    mediator ... review
    and revision of summary
    judgment
    motion (indemnity
    issue)
    11/30/2006   EMF    Strategic development                    3.60    522.00
    with LGS and
    BAD
    11/30/2006   BAD    Research regarding                       4.10    758.50
    reasonableness
    argument in opposition
    to surety's
    rights ...
    11/30/2006   LGS    Review and revision                      3.70    740.00
    of Memorandum in
    Support of Motion
    for Summary Judgment
    ...
    11/30/2006   JTW    Researched previous                       .60    45.00
    memorandum Opinions
    in favor of surety
    regarding indemnity
    claims.
    

    Thus, the court deducts $4,896.50 from the amount sought by Western.

    The court finds the following claims for reimbursement unreasonable as overhead or clerical expenses:

    11/22/2005   JKH    Retrieval of documents,                   .50    37.50
    and assembling
    same for
    review by LGS
    11/22/2005    JKH   Review and organization                  2.80    210.00
    of documents
    from client.
    12/2/2005     JKH   Continued creation                       2.30    172.50
    of files for materials
    received from client.
    *1122
    12/5/2005    JKH    Creation of index for                     .70     52.50
    files produced by
    client.
    12/28/2005   JKH    Confirming location                       .70     52.50
    of principal's office;
    report to file regarding
    the same; reviewing
    contents of
    Bradford Electric
    Web page ...
    1/3/2006     JKH    Retrieval of documents                   2.10    157.70
    (sic) from file
    for attorney review
    1/4/2006     JKH    Retrieval of documents                   1.80    135.00
    from file for
    review by attorney
    1/6/2006     JKH    Creation of file for                      .30     22.50
    Summary of Report
    by Draper &
    Associates
    1/12/2006    JKH    Correspondence to                         .30     22.50
    opposing counsel enclosing
    revised copy
    of Bradford Electric
    report.
    3/7/2006     JKH    Conference with                           .30     22.50
    Federal Court re:
    filings and non-service
    to counsel for O
    & S Enterprises ...
    3/10/2006    JKH    Conference with                           .40     30.00
    copy service re: status
    of documents
    3/23/2006    JKH    Review of scheduling                      .50     37.50
    order and report
    to file ...
    4/14/2006    JKH    Review and organization                   .50     37.50
    of file....
    4/27/2006    JKH    Correspondence to                         .30     22.50
    copy service enclosing
    invoice and
    payment ...
    6/13/2006    JKH    Correspondence                            .30     22.50
    with client re:
    invoice for copy of
    Architect project file
    7/6/2006     JKH    Conference with                           .30     22.50
    mediator's office re:
    invoices and prior
    payment ...
    8/2/2006     JKH    Review of scheduling                      .30     22.50
    order re:
    Expert disclosures
    deadline; report to
    file.
    8/3/2006     JKH    Correspondence                            .30     22.50
    with counsel for
    general contractors
    Enclosing payment
    for Western Surety's
    share of room
    rental for mediation
    8/9/2006     JKH    Conference with                           .30     22.50
    court re: Response
    to Motion to Intervene;
    report to file
    8/16/2006    JKH    Correspondence                            .30     22.50
    with client enclosing
    invoice for mediation
    services.
    8/23/2006    JKH    Correspondence                            .20     22.50
    with court reporters
    enclosing payment
    for invoice
    9/5/2006     JKH    Review of scheduling                      .90     67.50
    order and report
    to file re: compliance
    with same
    9/18/2006    JKH    Drafting of bill letters                  .40     30.00
    to opposing
    counsel for cost
    of producing
    documents.
    9/19/2006    JKH    Converting deposition                     .50     37.50
    transcripts to
    portable document
    format; correspondence
    with electrical
    engineer for review.
    9/19/2006    JKH    Correspondence                            .40     30.00
    with client enclosing
    deposition transcript
    and errata sheet for
    review.
    9/19/2006    JKH    Conference with                           .30     22.50
    electrical engineering
    expert re:
    deposition transcripts
    for review.
    10/9/2006    JKH    Correspondence                            .30     22.50
    with court reporter
    enclosing executed
    Errata sheet for distribution
    to counsel.
    10/13/2006   JKH    Preparation of documents                  .50     37.50
    for transmittal
    to counsel for
    defendants.
    10/16/2006   JKH    Correspondence                            .30     22.50
    with Preferred Title
    enclosing payment
    for title search.
    10/17/2006   JKH    Correspondence                            .60     45.00
    with William Sealy
    enclosing documents
    for review.
    10/17/2006   JKH    Correspondence                            .50     37.50
    with Ken McLaughlin
    re: documents
    for review.
    10/30/2006   JKH    Correspondence                            .40     30.00
    with client enclosing
    invoice from court
    reporter for
    payment.
    11/9/2006    JKH    Correspondence                            .30        50
    with Ken McLaughlin                        22
    enclosing code of
    professional conduct
    from Board of
    Registration of
    Architects.
    11/9/2006    JKH    Review of mail.                          1.00     75.00
    11/22/2006   JKH    Correspondence                            .30     22.50
    with court reporter
    enclosing payment
    for deposition
    transcript.
    

    Thus the court shall remove the amount of $1,665.20 from Western's claim.

    The court finds the following claims for reimbursement duplicative:

    1/4/2006     BAD    Preparation of Complaint                 5.80     928.00
    for Exoneration
    of Surety
    *1123
    1/4/2006     LGS    Continued preparation                    6.50  1,300.00
    of declaratory
    judgment ...
    1/4/2006     TLS    Continued evaluation                     1.80    360.00
    of grounds for
    termination .... initial
    preparation of
    Declaratory Judgment/Exoneration
    action.
    1/5/2006     BAD    Revision of Complaint;                   1.10    176.00
    Application
    for Injunctive Relief
    1/5/2006     LGS    Further review and                       1.80    360.00
    revision of proposed
    declaratory exoneration.
    1/6/2006     LGS    Further review and                       3.70    740.00
    revision of proposed
    declaratory action
    ...
    1/13/06      LGS    Conference with                          3.30    660.00
    Joan Clements and
    Ken McLaughlin;
    review and revision
    of suit papers ...
    1/14/2006    TLS    Confirmation of                          1.60    320.00
    plans for site visit
    further preparation
    of complaint
    1/16/06      LGS    Further review and                       2.60    520.00
    revision of exoneration/declaratory
    judgment action....
    1/17/06      LGS    Confirmation of                          1.80    360.00
    plans for inspection/observation
    further review and
    revision of revised
    declaratory judgment
    complaint ...
    1/24/2006    LGS    Conference with                          5.50  1,100.00
    Joan Clements and
    Ken McLaughlin;
    final review and
    revision of Complaint
    for Declaratory
    Relief ...
    1/24/06      TLS    Conference with Mr.                      3.80    760.00
    McLauglin
    revised complaint
    for Declaratory Relief
    ...
    1/26/2006    BAD    Final preparation of                     1.90    351.50
    Complaint ...
    

    Because each of the attorneys involved in drafting the complaint "grouped" his hours, listing numerous activities in blocks, the court cannot ascertain with specificity how much of the above claimed time was actually spent drafting the complaint.[9] Giving the attorneys the benefit of the doubt, the court deems one-third the claimed time to have been spent on other activities besides the drafting of the complaint. As the above hours total 41.20, the court deems 13.73 hours spent on other activities, leaving 27.47 hours drafting a complaint. The court finds 20.00 hours more than reasonable, and hence reduces the attorney fees recoverable under the GAI by 7.47 hours, which equals $1,456.65.[10]

    The court also finds that review of the contracts in question by multiple attorneys was duplicative and unnecessary. The following work by the fourth attorney to review those contracts is found unreasonably redundant:

    1/9/2006     EMF    Strategic Development                     .20    32.00
    with LGS re:
    status and research
    issues and review
    contracts re: same.
    1/10/2006    EMF    Continue review of                       3.0     480.00
    contracts.
    1/12/2006    EMF    Continue review of                       3.0     480.00
    contracts and
    research re: issues
    concerning wrongful
    termination
    1/16/2006    EMF    Research and prepare                     5.0     800.00
    memorandum
    re: termination
    issues and strategic
    development with
    LGS ...
    1/19/2006    EM     Continue research                        3.30    528.00
    ... review contracts
    re: latent defects
    1/23/2006    EMF    Strategic development                    4.20    672.00
    with LGS re:
    research memo ...
    1/24/2006    EMF    Strategic development                     .70    112.00
    with LGS re:
    termination memo
    and revise memo
    ...
    

    *1124 The court therefore deducts the amount of $3,104.00.

    1/27/2006    BAD    Final preparation                        3.90    721.50
    for hearing on
    Application of Temporary
    Restraining
    Order; attendance
    in Court for hearing
    1/31/2006    BAD    Preparation for                          1.10    203.50
    hearing on preliminary
    injunction, conference
    with counsel
    for Bradford Electric
    Company
    regarding same.
    

    The court finds these two claims, taken together, are redundant. The court did not have a hearing in this case on January 27, 2006, thus the attorney could not have spent time attending one. However, having prepared for the hearing on January 27, 2006, the court would hope he was still prepared on January 31, 2006, when the hearing was rescheduled for February 7, 2006. As other activities are claimed, the court finds reasonable one-half the time claimed, or 2.50 of the 5.0 hours claimed, a reduction in the amount recoverable of $426.50.

    2/6/2006     TLS    Review of complaint;                     2.30    460.00
    initial preparation
    of Preliminary
    Injunction Order
    2/7/2006     TLS    Review of complaint;                     2.30    460.00
    initial preparation
    of Preliminary
    Injunction Order
    

    The court finds that the second identical entry Thomas L. Seldon, dated 2/7/2006, is surely in error, as the exact same entry was made the previous day, although the same appeared on the previous month's bill to Western. The court shall reduce the amount sought by $460.00.

    1/20/2006    LGS    Travel to and lodging               334.20
    expense in
    Mobile, AL for
    meeting with new
    client
    lawyer
    

    The court is unable to decipher this expense claim. No lawyer in this case is in Mobile, nor does this case involve a lawyer-party. On this same date, Western's expert, Kenneth McLaughlin, submitted a charge, infra, for his expenses in traveling to Huntsville to meet with Attorney Stiff. In fact, on this same date, Attorney Stiff has billed $240.00 for meeting with Ken McLaughlin and Joan Clements. As Mr. McLaughlin claimed to be in Huntsville, and Attorney Stiff claimed to meet with him, the court concludes that the travel and lodging expenses for "meeting with new client lawyer" were erroneous, and deducts $334.20 from the amount sought.

    2/16/2006   JKH     ... preparation of                       1.60    120.00
    Alias Summons to
    SKT Architects
    2/17/2006   BAD     ... preparation of                       1.10    203.50
    alias summons to
    SKT Architects ...
    

    Preparation of an alias summons simply does not take two people two days to prepare. This is especially true given that the court docket the summons received back from the post office and marked "NOT DELIVERABLE AS ADRESSED" until February 21, 2006, four days after Mr. Harred's claim of time spent preparing an alias summons. Thus, the claims of February 16 and 17, 2006, in the total amount of $323.50, shall be deducted from fees recoverable under the GAI.

    3/9/2006     JKH    Initial review of                         .50     37.50
    documents received
    from City of Huntsville
    ...
    3/9/2006     BAD    Review of documents                       .80    148.00
    produced by
    City of Huntsville
    ...
    

    These two claims are clearly redundant. The court finds reasonable one half of each claim, resulting in a total reduction of $92.75 in the amount sought by Western.

    4/5/2006     JKH    Review of order                           .20     15.00
    from court setting
    hearing on Motion
    to Reconsider ...
    4/5/2006     BAD    Review of order                           .20     37.00
    setting Motion to
    Reconsider for
    hearing ...
    

    These two claims are redundant. The court finds reasonable the time claimed by Mr. Harred only, resulting in a reduction of $37.00. *1125

    4/12/2006    LGS    Final Preparation                        4.50    900.00
    for and attendance
    in court on all pending motions ...
    4/12/2006    LGS    Preparation for and                      4.80    960.00
    attendance at argument
    in Judge Johnson's
    court ...
    

    As the court held only one hearing on this date, only one of these entries is correct. As the second claim for the identical activity surely must have been charged by accident, the court will not allow Western to recover from Bradford the amount of $960.00.

    4/4/2006     JKH    Review of financial                       .50     37.50
    information submitted
    by defendant
    Richard Bradford
    ...
    6/27/2006    JKH    Initial review of                         .40     30.00
    Financial Information
    from Bradford
    ...
    

    As financial information documents from Bradford were first reviewed by Mr. Harred in April, his entry in June of an initial review of these documents must have been in error. The court reduced the amount recoverable under the GAT by $30.00.

    5/11/2006    BAD    Review and analysis                      6.60  1,221.00
    of SKT Architect's
    project file ...
    5/12/2006    JKH    Initial review of documents              1.40    105.00
    from project
    file...
    5/12/2006    LGS    Review of key documents                  2.30    460.00
    obtained from
    SKT files ...
    5/15/2006    JKH    Initial review and                       1.90    142.50
    analysis of documents
    produced by
    SKT Architects;
    report to file.
    5/15/2006    JKH    Correspondence                            .20     15.00
    with counsel for
    SKT Architects re:
    cd-rom version of
    documents produced
    ...
    5/17/2006    LGS    Further review of                        1.50    300.00
    documents produced
    by SKT
    5/26/2006    JKH    Review and analysis                      1.40    105.00
    of pay applications
    from architects (Sic)
    project file ...
    

    Counsel and staff for Western spent 15.30 hours reviewing the same documents. The court finds that Mr. Harred could not have an initial review of the same documents two times. The court allows only Attorney Dodd's 6.60 hours reviewing this project file. The remainder of these charges, $1,127.50, are excessive.

    6/7/2006     LGS    Prepare for and                         11.50  2,300.00
    attend depositions
    of CCC reps., Halbrooks
    and Bradford
    rep.
    

    The court notes that the deposition of the "Bradford rep." would be Rick Bradford, whose deposition was attended by Attorney Dodd, but not Attorney Stiff, and which took place on June 8, 2006, and not June 7, 2006. The court therefore deducts one-half of the amount claimed, a reduction of $1,150.00.

    7/11/2006    JKH    Review and analysis                       .90     67.50
    of Motions to Compel
    filed by defendant
    Consolidated
    ...
    7/11/2006    BAD    Review of Motions                         .70    129.50
    to Compel filed by
    Consolidated ...
    7/12/2006    BAD    Continued evaluation                      .70    129.50
    of Consolidated
    ... Motions to
    Compel
    7/12/2006    JKH    Review and revision                      1.10     82.50
    of Response to Motions
    to Compel and
    electronic filing of
    same with court....
    7/12/2006    LGS    Review of Motions                        3.30    660.00
    to Compel filed by
    CCC; preparation
    of response ...
    7/13/2006    LGS    Review of Motions                        3.50    700.00
    to Compel ...
    

    These entries are highly redundant. The court finds the time spent by attorney Stiff on July 12, 2006, reviewing and responding to the motions to compel, and the time spent by Mr. Harred on the same date reviewing and revising the response to be reasonable. The remainder of time spent on this activity is excessive. The court believes the entry by attorney Stiff on July 13, 2006, the day after Western's response to these motions was filed with the court, must have been made in error. The court therefore is of the opinion the sum of $1,026.50 is excessive and not reasonably incurred. *1126

    8/10/2006   JKH     Correspondence                            .50     37.50
    with all counsel confirming
    upcoming
    deposition schedule.
    8/11/2006   JKH     Correspondence                            .40     30.00
    with counsel for defendants
    confirming
    (sic) deposition
    schedule.
    

    The court finds the second charge for this activity redundant and subtracts $30.00.

    8/25/2006    BAD    Conference with architect                 .70    129.50
    for Alabama
    Department of Education
    regarding inspection
    obligations
    ...
    8/25/2006    LGS    ... conference with                      4.40    880.00
    state architect re
    procedures and policies
    for electrical inspections
    and confirmation
    of status of
    inspections by State
    Building Commission ...
    8/28/2006    BAD    Conference with                           .20     37.00
    Alabama Building
    Commission re inspection
    of projection
    file for Columbia
    High School
    project
    

    These two entries seem to include some of the same activities. The court reduces the reasonable fee by .70 hours at 200.00/ hour, and an additional .20 at $185.00/hour, for a sum of $177.00.

    9/25/2006    JKH    Drafting non-party                        .70     52.50
    subpoena and deposition
    notice for representative
    of Building
    Commission
    9/25/2006    LGS    Preparation of                           1.80    360.00
    notice of deposition
    to John Vandiver
    ....
    9/25/2006    BAD    ... conference with                      1.10    203.50
    John Vandiver confirming
    availability
    for deposition;
    review of deposition
    notice and subpoena;
    correspondence to
    Mr. Vandiver
    enclosing same
    9/26/2006    JKH    Review and revision                       .80     60.00
    of deposition subpoena
    to Building
    Commission
    official....
    

    Both Mr. Harred and attorney Stiff claim to have prepared the subpoena to John Vandiver, who was deposed as the representative from the Building Commission. The court allows the time claimed by Mr. Harred only. The court also allows the time claimed by attorney Dodd to confirm and mail the subpoena to John Vandiver on September 25, 2006, but finds Mr. Harred's claim of reviewing and revising the same subpoena the following day to be unreasonable. The court deducts the total amount of $420.00.

    1/13/2006    LGS    Preparation for and                      9.80   1960.00
    attendance at deposition
    of Robert
    Walker; meeting
    with all defense
    counsel re proposed
    rescheduling of mediation
    and meeting
    of defense counsel
    prior thereto; review
    and revision of
    mediators statement
    and report to Joan
    Clements
    11/13/2006   LGS    Preparation for and                      9.80   1960.00
    attendance at deposition
    of Robert
    Walker; meeting
    with all defense
    counsel re proposed
    rescheduling of mediation
    and meeting
    of defense counsel
    prior thereto; review
    and revision of
    mediators statement
    and report to Joan
    Clements.
    

    When questioned about the first of these charges during the hearing, attorney Stiff related that "1/13/2006" was obviously a wrong date and that it was either November or October 13, 2006. The court notes that the proper date must have been November 13, 2006, as this attorney performed these exact activities again on that date. Therefore, finding that this entry was erroneously made two times due to the date being entered improperly the first time, the court deducts the sum of $1,960.00.

    The court finds the following claims for reimbursement excessive for the reasons set forth thereafter:

    12/1/2005    JKH    Continued creation                       1.30     97.50
    of.
    3/31/2006    TLS    Further evaluation                       2.10    420.00
    fo (sic) arguments
    advanced by plaintiff
    in support of "bad
    faith" claim ....
    10/26/2006   JKH    Review and analysis                       .40     30.00
    of deposition notices
    for.
    

    *1127 The court cannot determine what may have been created for 1.30 hours. This sum shall be deducted as unreasonable. Unless Western argued in support of the claim against it, the entry of March 31, 2006, is nonsensical, as Western is the plaintiff. The entry of October 26, 2006, is unintelligible. The court shall deduct the additional sum $547.50.

    11/21/05     LGS    Lunch meeting with                               746.78
    expert
    

    The court is of the opinion that lunch should never cost this much. If this disbursement was for something other than the cost of food, this information is not reflected in Western's claim of indemnity for attorney fees and expenses. The sum of $746.78 shall be deducted as unreasonable.

    1/30/06      LGS    General preparation                      5.40  1,080.00
    for hearing ...
    1/31/2006    LGS    Conference with                          3.80    760.00
    Joan Clements and
    continued preparation
    for preliminary
    injunction hearing
    ...
    

    The court finds these two claims to be excessive, given that the preliminary injunction hearing never occurred. Rather, the surety obtained a consent order against its principal restraining Bradford from disposal of its assets (doc. 11). The court therefore finds 4.20 hours of these claims to be excessive, reducing the amount recoverable under the GAI by $840.00.

    2/14/2006    TLS    Review and analysis                      2.40    480.00
    of counterclaim filed
    by Consolidated
    against surety; evaluation
    of recent case
    law ... and confirmation
    of plans of
    seeking early dismissal
    of "bad faith"
    claim.
    2/15/2006    LGS    Review and analysis                      5.50  1,100.00
    of CCC Counterclaim
    ...
    2/16/2006    LGS    ... review of Answer                     1.80    360.00
    and Counterclaim
    and confirmation
    of client
    instructions re:
    Motion to Dismiss
    bad faith claim,
    etc.
    2/17/2006    LGS    Further evaluation                       2.50    500.00
    of Counterclaim and
    defense strategy
    2/21/2006    LGS    Further review of                        3.30    660.00
    CCC counterclaim
    and proposed response
    thereto....
    3/2/2006     TLS    Further review of                         .80    160.00
    Counterclaim filed
    by Consolidated ...
    

    A total of 16.3 hours were spent by these attorneys in solely the review of the counterclaim against Western. This was not a complex or novel counterclaim, but rather basic contract claims under Alabama law, including a bad faith failure to pay claim against Western. At most, "review," "analysis," "evaluation" and crafting a proposed response should have taken no more than 4 hours. The court deducts 12.30 hours, for a monetary reduction of $2,460.00.

    4/3/2006     BAD    ... review and evaluation                1.60    296.00
    of Order
    (denying motion to
    strike bad faith
    claim).
    4/3/2006     TLS    Receipt of Order                          .60    120.00
    denying Motion to
    Dismiss ...
    4/4/2006     BAD    Continued analysis                       2.70    499.50
    of Order denying
    Motion to Strike ...
    

    The Order in question was one and a half pages and concluded that the law on the issue was unsettled. The court allows one hour for Attorney Dodd to review and evaluate this Order, a reduction of $730.50.

    3/8/2006     BAD    Review of Order setting                   .90    166.50
    briefing schedule
    on Motion to
    Dismiss bad faith
    count of counterclaim
    ...
    3/8/2006     TLS    Receipt of Order                          .80    160.00
    directing Consolidated
    to response (sic)
    to Motion to Dismiss
    "bad faith" claim
    

    This "briefing schedule" was a one page order allowing defendant Consolidated twenty-one days to respond to Western's motion to dismiss one of Consolidated's counter-claims against it. It should not have taken two attorneys 1.70 hours total time to review a one page order which did not require them to do anything. *1128 The court finds a total of .2 hours for reviewing this Order reasonable, reducing the attorneys' time .80 for attorney Dodd and .70 for attorney Seldon. This amounts to a reduction of $288.00.

    3/10/2006    LGS    Conference with                          2.30    460.00
    client ... preparation
    for planning
    conference.
    3/13/2006    BAD    Conference with all                      1.90    351.50
    counsel of record
    ... preparation of
    Report of Parties
    Planning Meeting
    ...
    3/13/2006    LGS    Preparation for and                      2.80    560.00
    participation in planning
    meeting;
    report to client ...
    3/13/2006    TLS    General preparation                      1.10    220.00
    for mandatory
    parties' planning
    meeting ...
    3/14/2006    BAD    Review of revised                         .20     37.00
    Report of Parties
    Planning Meeting;
    conference with
    counsel for Consolidated
    Construction
    Company regarding
    same.
    3/14/2006    LGS    Review of final planning                 1.60    320.00
    meeting report
    and confirmation of
    status of document
    delivery.
    3/16/2006    JKH    Conferences with                          .30     22.50
    opposing counsel re:
    Report Parties Planning
    Meeting and
    filing of same.
    

    The court is of the opinion that 9.90 hours for preparation of a Report of Parties' Planning Meeting is excessive, especially given that it was filed by counsel for Consolidated Construction Company, and not Western. The court notes that attorneys use a "fill in the blank form" for such reports. Even given that these attorneys did not file the report with the court, the court finds a reasonable amount of time to be 3 hours for preparation of the report and 2 hours for the planning meeting itself, a reduction of 4.9 hours, which the court finds to be $955.50.[11] The court finds the claim for filing of the same completely unreasonable, and disallows its entirety, a reduction of $22.50.

    3/20/2006    LGS    ... confirmation of                      2.50    500.00
    status of document
    production from
    parties and non-parties
    and further
    evaluation of discovery
    plan.
    4/13/2006    LGS    Review of status of                      2.80    560.00
    document production
    from parties
    and non-parties;
    evaluation of discovery
    plan.
    4/19/2006    LGS    Further review and                       1.20    240.00
    evaluation of discovery
    plan in light of
    mediation schedule.
    5/1/2006     LGS    Review of correspondence                 1.40    280.00
    further review and
    evaluation of discovery
    plan required
    before mediation
    5/10/2006    LGS    Report to client ...                     1.50    300.00
    confirmation of status
    of documents
    received from all
    parties; outline of
    discovery plan.
    

    The court finds that Attorney Stiff spent 9.4 hours confirming documents produced and evaluating a discovery plan. The court cannot ascertain what exactly these activities might entail. Presumably, before the parties submitted a Report of Parties Planning Meeting to this court, the need for discovery and a plan therefore was evaluated, analyzed and reviewed. The court allows one hour for confirming the status of document production, resulting in a deduction of $1,680.00.

    3/17/2006    JKH    Review and downloading                    .30     22.50
    of documents
    served electronically
    by federal
    court.
    

    The court "served" no documents on this date.

    4/5/2006     JKH    Confirming status                         .40     30.00
    of pending motions
    in assistance to
    attorney.
    

    *1129 On April 5, 2006, the sole motion pending in this case was Western's motion for reconsideration. Looking at CM/ECF for a ruling on this one motion should not take anyone 24 minutes. The court allows .10 for this activity, a reduction of $22.50.

    6/1/2006     TLS    ... evaluation of                         .80    160.00
    filing Partial Summary
    Judgment
    Motion re: claims
    for exoneration
    6/26/2006    JKH    Review and analysis                       .90     67.50
    of Motion for Partial
    Summary Judgment
    6/26/2006    BAD    ... preparation of                       4.10    758.50
    Motion for Partial
    Summary Judgment
    and Supporting
    Memorandum Brief
    6/27/2006    JKH    Assisting attorney                        .60     45.00
    with drafting Motion
    for Summary
    Judgment
    6/27/2006    BAD    Continued preparation                    2.30    425.00
    of revision of
    Motion for Partial
    Summary Judgment
    ... preparation of
    First Amended
    Complaint
    6/27/2006    LGS    Review and revision                      1.80    360.00
    of Motion For Partial
    Summary Judgment
    ... preparation
    of Amended
    Complaint
    6/28/2006    BAD    Continued preparation                    1.30    240.50
    and revision of
    First Amended
    Complaint ...
    6/28/2006    LGS    ... further review                       3.40    680.00
    and revision of Proposed
    Amendment
    to Complaint and
    Motion for Partial
    Summary Judgment
    6/29/2006    JKH    Assisting attorney                        .30     22.50
    with drafting of
    Amended Complaint
    6/29/2006    BAD    Continuing preparation                    .90    166.50
    and revision of
    First Amended
    Complaint.
    6/29/2006    LGS    ... review and continued                 4.70    940.00
    preparation
    of First Amended
    Complaint ...
    6/30/2006    LGS    Final review and                         3.30    660.00
    revision of First
    Amended Complaint
    ...
    7/3/2006     LGS    ... evaluation of                        3.50    700.00
    collateralization
    needs; continued
    preparation of
    Amended Complaint
    7/5/2006     JKH    Assisting attorney                       1.20     90.00
    with revisions to
    amended complaint
    ....
    7/5/2006     BAD    Review of revised                         .30     55.50
    First Amended
    Complaint.
    7/5/2006     LGS    ... final review and                     3.20    640.00
    revision of proposed
    Amended Complaint
    ...
    7/7/2006     JKH    Review of Amended                         .90     67.50
    Complaint ...
    7/7/2006     BAD    Final review and                         1.10    203.50
    revision of Motion
    for Leave to file
    First Amended
    Complaint ...
    7/10/2006    BAD    Review of Order                           .40     74.00
    granting Motion for
    leave to file ... final
    preparation of
    Amended Complaint
    for filing
    7/10/2006    LGS    Confirmation of                          1.70    340.00
    entry of Order
    granting Motion for
    Leave to File ...
    conference with all
    counsel regarding
    service of Amended
    Complaint and compliance
    with Court
    Order ...
    8/14/2006    JKH    Review and revision                       .60     45.00
    of motion and memorandum
    brief in assistance
    to attorney.
    8/14/2006    BAD    ... revision of                          2.60    481.00
    Motion for Partial
    Summary Judgment
    and supporting
    Memorandum brief
    ...
    8/15/2006    JKH    Continued review                          .90     67.50
    and revision of Motion
    for Summaru
    (sic) Judgment in
    assistance to
    attorney
    8/15/2006    BAD    ... continuing preparation               4.10    758.50
    and revision
    of Motion for Partial
    Summary Judgment
    and supporting
    Memorandum Brief
    ...
    8/15/2006    TLS    Conference with Ms.                      1.50    280.00
    Clements re deposition
    testimony, etc;
    review of terms of
    General Agreement
    of Indemnity and
    finalized Memorandum
    Brief in Support
    of Motion for
    Partial Summary
    Judgment[12]*1130
    8/18/2006    BAD    Conference with                          3.10    573.50
    client ... execution
    of affidavit supporting
    Motion for Partial
    Summary Judgment
    ... review of
    response from Bradford
    Electric Company
    to collateralization
    demand.[13]
    10/16/2006   BAD    ... Revision of                          5.10    943.50
    motion for partial
    summary judgment
    and supporting
    memorandum ...
    Review of property
    report prepared by
    Preferred Title.
    Revision of demand
    note, mortgage and
    seculity (sic) agreement.
    Report to
    file.
    10/18/2006   JKH    Assisting attorney                        .40    30.00
    with preparation of
    motion for sumary
    (sic) judgment.
    10/18/2006    LGS   Continuing revision                      3.10    620.00
    of Motion for Partial
    Summary Judgment
    and supporting
    Memorandum Brief;
    conference with
    counsel for Bradford
    Electric Company
    regarding execution
    of demand note,
    mortgage and security
    agreement ....
    confirmation of
    license status of
    expert retained by
    Bradford Electric
    Company; report to
    file
    10/18/2006   LGS    Review of recent                         2.30    460.00
    cases of holding
    surety's rights of
    exoneration; revised
    Memorandum Brief
    and Evidentiary
    Submission in support
    of Partial Summary
    Judgment
    10/23/2006   JKH    Drafting Notice of                        .80     60.00
    Evidentiary Submission
    for filing with
    court.
    10/23/2006   JKH    Preparation of                           1.40    105.00
    Motion and Brief for
    filing with court and
    electronic filing of
    same.
    10/23/2006   JKH    Assisting attorney                        .50     37.50
    with selection of
    documents for use
    as exhibits to
    Motion.
    

    The only motion for partial summary judgment filed by Western was filed on October 23, 2006. The Amended Complaint was filed July 10, 2006. However, Western's counsel managed to lump together billing for both of these activities. The time spent collectively on these two activities is 63.1 hours, which is excessive.[14] The court allows forty hours as reasonable for preparing a motion for summary judgment, and ten hours for preparation of the amended complaint. The court therefore shall deduct 13.1 hours for the sum of $2,323.30[15]

    7/15/2006    WDB    Researching caselaw                      1.10    176.00
    regarding joint
    attorney-client privilege
    between principal
    and surety.
    7/17/2006    WDB    Drafting report to                        .60     96.00
    file regarding
    research for joint
    defense privilege
    between principal
    and surety.
    7/17/2006    BAD    Preparation off (sic)                    1.40    259.00
    responses to Consolidated
    Construction
    Company's second
    document request;
    research regarding
    privilege between
    principal and surety
    in defense of claim.
    7/18/2006    WDB    Continuing to                            2.28    448.00
    research law regarding
    joint attorney-client
    privilege ...
    7/18/2006    BAD    Continuing research                      1.30    240.50
    regarding claim of
    privilege between
    principal and surety
    ...
    *1131
    7/16/2006    Westlaw search                                          374.58
    

    Western has repeatedly informed this court that it had to bring this litigation and incur the attorney fees in issue because its position was always adverse to that of Bradford. As such, the court finds the above research concerning a joint defense privilege to have been unreasonably undertaken. Western's claim is reduced by $1,594.08.

    4/5/2006     JKH    Research of Tennessee                     .50     37.50
    Code re: Homestead
    Exemption
    ...
    4/6/2006     JKH    Research of court                        1.10     82.50
    records re: divorce
    case of Richard T.
    Bradford ...
    4/6/2006     JKH    Purchased of money                                 5.79
    order to obtain copy
    of Mr. Bedford's
    divorce decree
    4/11/2006    JKH    Review of request                         .40     30.00
    for information from
    accounting consultant;
    report to file
    re: divorce decree
    and settlement
    agreement.
    4/11/2006    JKH    Research Secretary                        .50     37.50
    of State website re:
    real estate partnerships
    owned by
    principal ...
    4/13/2006    JKH    Review of Settlement                     1.80    135.00
    Agreement
    from divorce of
    Richard and Pamela
    Bradford ...
    4/18/2006    LGS    Review of mediator's                     2.60    520.00
    statement for
    service ... conference
    ... regarding
    collateralization
    issues raised by
    divorce decree and
    property settlement
    4/26/2006    JKH    Review of memorandum                      .30     22.50
    from accounting
    consultant ...
    documentation of
    divorce settlement
    5/10/2006    JKH    Review of memorandum                      .80     60.00
    from accounting
    consultant ...
    8/21/2006    LGS    Review of collateralization               .70    140.00
    proposal and
    report to Joan
    Clements.
    9/27/2006    LGS    Further review and                       2.30    460.00
    analysis of expert licensure
    requirement
    for engineering testimony
    and exceptions
    thereto ...
    preparation and
    transmittal of collateral
    demand to
    plaintiff's counsel[16]
    10/6/2006    BAD    Preparatoin (sic) of                     2.10    388.50
    demand note, mortgage
    and security
    agreement; correspondence
    to counsel
    for Bradford
    Electric Company
    enclosing same
    10/9/2006    BAD    ... continuing revision                   1.70   314.50
    of demand note,
    mortgage and security
    agreement;
    conference with title
    company confirming
    agreement to perform
    title search on
    principal's property.
    10/9/2006    LGS    ... review and revision                   3.50   700.00
    of Note and
    Mortgage Security
    Agreement;
    response to Tyndal/
    Zulanas re collateral
    security issues
    10/10/2006   JKH    Review of documents                       .60     45.00
    from counsel
    for Bradford; conference
    with Preffered
    (sic) Title re:
    title search of
    Winchester Road
    property
    10/10/2006   JKH    Review and revision                       .70     52.50
    of Promissory Note
    and Mortgage
    Agreement.
    10/10/2006   JKH    Correspondence                            .40     30.00
    with counsel for
    principal re: Promissory
    Note and
    Mortgage
    Agreement.
    10/10/2006   BAD    Final revision of demand                  .90    166.50
    note mortgage
    and security agreement;
    confirmation
    of status of title
    search on commercial
    property;
    report to file
    10/13/2006   JKH    Correspondence                            .40     30.00
    with title company
    re: Title search of
    property owned by
    principal.
    10/13/2006   JKH    Correspondence                            .30     22.50
    with title company
    enclosing legal Description
    of property
    for completion of
    title search.
    10/13/2006   BAD    Continuing conference                    1.70    314.50
    with Preferred
    Title regarding
    Status of title
    search....
    10/16/2006   JKH    Assisting attorney                        .70     52.50
    with selection of
    *1132
    exhibits for enclosure
    with letter to
    counsel for principal.
    10/16/2006   JKH    Review and revision                       .30     22.50
    of mortgage and
    security agreement
    10/17/2006   JKH    Review and analysis                       .30     22.50
    of title search;
    report to file.
    10/17/2006   BAD    Continuing conference                     .30     55.50
    with counsel
    for Bradford Electric
    Company
    regarding status of
    execution of note
    ...
    10/17/2006   LGS    Conference with                          5.50   1100.00
    clients .... review
    and revision of motion
    for deposit for
    collateral.
    10/20/2006   BAD    Revision of note,                        2.30    425.50
    security, agreement
    and mortgage;
    correspondence to
    client enclosing
    same; conference
    with counsel for
    Bradford Electric
    Company regarding
    10/20/2006   LGS    Review and revision                      4.70    940.00
    of letter to attorneys
    Zulanas and Tyndall
    re collateral demand
    and unilateral settlement
    options; conference
    with Joan
    Clements; review of
    order from Judge
    Johnson on all pending
    motions and
    repot (sic) to client
    ... execution of
    note...
    10/20/2006   LGS    Conference with                          4.50    900.00
    Ken McLaughlin
    ... confirmation of
    status of Note and
    Mortgage Security
    Agreement ...
    10/23/2006   BAD    Continuing preparation                   5.80   1073.00
    and revision of
    note, security agreement
    and mortgage
    ... final preparation
    of Motion for Partial
    Summary Judgment
    and supporting
    Memorandum Brief
    ...
    10/23/2006   TLS    Evaluation of bankruptcy                  .50    100.00
    and related
    issues; report re
    same.
    10/23/2006   LGS    Conference with                          5.80   1160.00
    Joan Clements;
    review and revision
    of Note and Security
    Agreements ....
    review and revision
    of Note and Security
    Agreement as
    directed by Joan
    Clements and transmittal
    to opposing
    counsel
    10/24/2006   BAD    ... conference                           2.90    536.00
    with counsel for
    Bradford Electric
    Company regarding
    status of note and
    security agreement
    ...
    10/24/2006   LGS    Review of expert                         6.50    1300.00
    reports ... report
    to Joan Clements
    re revised Note and
    Security Agreement
    and continued negotiation
    with opposing
    counsel re
    execution thereof.
    10/25/2006   JKH    Assisting attorney                        .40     30.00
    with review of documents
    re: promissory
    note and agreement;
    report to file.
    10/25/2006   LGS    Continued review                         4.30    860.00
    and revision of Note
    and Security Agreement;
    conference
    with attorney Tyndall
    regarding same;
    review and revision
    of Motion to Compel
    Collateral Deposit
    ...
    10/26/2006   BAD    Review of file in                        5.20    962.00
    preparation for
    meeting of Scott
    Cole ... conference
    with counsel for
    Bradford Electric
    Company regarding
    status of none (sic)
    security agreement
    and mortgage
    11/6/2006    BAD    Conference with                          4.70    869.50
    counsel for Bradford
    Electric Company
    regarding collateralization
    demand ...
    11/17/2006   LGS    Continued review                         4.50    900.00
    and analysis of
    effect of mediation
    and conference ...
    re unilateral settlement
    options ...
    and analysis of
    collateralization
    requirements.
    11/20/2006   LGS    Review and revision                      4.70    940.00
    of letter to attorneys
    Zulanas and Tyndall
    re collateral demand
    and unilateral settlement
    options ...
    review of order from
    Judge Johnson on
    all pending motions
    and report to client;
    preparation of physician's
    summary for
    pretrial order and
    confirmation of discovery
    schedule.[17]

    *1133 The court finds these activities unnecessary as Western already had a Consent Restraining Order in place protecting its interest in its principal's assets. Therefore, delving into Richard Bradford's divorce could not assist Western in this litigation. Similarly, in spite of the vast amounts of time spent obtaining title searches of Bradford's property, preparing a mortgage and note and talking about "unilateral settlements," Western never paid any amount of money out under the performance bond. It paid one claim of approximately $24,000.00 under the payment bond. In exchange, its counsel billed Western the sum of $15,843.79 solely on investigating and attempting to tie up Bradford's assets. This too was in spite of the fact that Bradford had already entered into a consent order preventing either the business or the individual from disposing of their respective assets. The court finds the entire sum of $15,843.79 unnecessarily incurred.

    7/30/2006    LGS    Review of order on                       2.70    540.00
    Motion to Compel
    and Motion to
    Reconsider by CCC
    counsel; report to
    client and preparation
    for status conference
    with Judge
    Johnson — confirmation
    of discovery
    status.
    

    The court issued an Order granting a motion to compel filed by Consolidated (CCC) on July 12, 2006. On July 21, 2006, Bradford filed a motion to reconsider. The court did not enter any Order on this motion to reconsider until July 31, 2006. Consolidated did not file any motion to reconsider the court's granting of Consolidated's motion. As the court cannot ascertain what Attorney Stiff actually did for 2.70 hours, and Attorney Stiff spend at least another 6.80 hours preparing for the status conference with this court (entries dated 7/25/2006 and 7/31/2006), the court finds this $540.00 charge unreasonable.

    11/28/2006   JKH    review and analysis                       .40    $30.00
    of court order setting
    briefing schedule
    for indemnity
    claim; report to file
    

    The court notes this Order was a grand total of five lines, which should have taken less than thirty seconds to read. It contained one deadline. It was also issued November 29, 2006, the day after this review and analysis took place. The court finds a reasonable amount of time to be .10 hours, reducing the sum allowable by $22.50.

    8/18/2006    JKH    Confirming state                          .30     22.50
    licensure status of
    electrical expert;
    report to file.
    8/23/2006    BAD    Analysis of recent                       1.40    259.00
    Alabama case law
    regarding disqualification
    of nonlicensed
    engineers
    from providing
    expert testimony;
    conference with architect
    license board
    confirming status of
    potential expert;
    report to file.
    8/24/2006    LGS    Conference with                          2.50    500.00
    possible architectural
    experts and confirmation
    of Ken
    McLaughlin position
    re engineering
    negligence.
    9/14/2006    LGS    Review of expert                         3.30    660.00
    issue; conference
    wiht (sic) Ken
    McLaughlin re qualifications/licensure
    issue ...
    9/18/2006    BAD    Conference with                          2.10    388.50
    expert regarding
    availability for deposition;
    continuing
    evaluation of effect
    of recent Alabama
    Supreme Court
    opinion regarding
    license requirements
    for proposed engineering
    experts.
    9/19/2006    BAD    Conference with                          1.70    314.50
    counsel regarding
    status of proposed
    mediation ... continuing
    evaluation of
    *1134
    recent case law
    regarding qualifications
    of non-licensed
    experts.
    9/28/2006    JKH    Preparation of documents                  .40    30.00
    re; Qualification
    of Expert Witnesses
    in Alabama
    ...
    9/28/2006    JKH    Correspondence                            .40    30.00
    with engineering
    consultant re:
    Supreme Court
    decision and advisory
    opinion
    9/28/2006    LGS    Conference with                          3.80    760.00
    Ken McLaughlin re
    licensure issue; conference
    with Joan
    Clements; further
    evaluation of exceptions/applicability
    to
    licensure requirement
    as condition
    precedent to expert
    testimony ...
    10/27/2006   JKH    Review and analysis                       .50     37.50
    of Motion to Strike
    Expert Witness
    by counsel for
    architect.
    10/27/2006   BAD    Review and analysis                      2.20    407.00
    of Motion to Strike
    (sic) ...
    10/30/2006   TLS    Review of Motion to                       .80    160.00
    Strike Expert Designation
    and Brief
    filed in support
    thereof; review of
    case law and confirmation
    of deadline
    for responding to
    same.
    11/6/2006    WDB    Researching law                          5.40    864.00
    regarding admissibility
    of expert testimony
    in federal
    court and whether
    state law applies to
    such admissibility;
    researching the Alabama
    disciplinary
    rules for architects
    ...
    11/6/2006    LGS    Preparation and                          5.60    1120.00
    repsonse (sic) to
    SKT Motion to
    Strike McLaughlin
    ... comprehensive
    discussion with
    attorneys Zulanas
    and Tyndall re
    indemnity issues
    and collateral issues
    ...
    

    As this was the expert of Western's choosing, Bradford should not be liable for Western's decision to select an expert from outside the state of Alabama, who was not licensed in the state of Alabama. The sum of $5,553.00 is excessive.

    9/6/2006     BAD    Conference with                          1.60    296.00
    counsel for all parties
    regarding ...
    proposed extension
    of discovery deadline
    .... preparation
    of draft unopposed
    Motion to Extend
    Discovery.
    9/7/2006     JKH    Assisting attorney                        .80     60.00
    with drafting of
    Motion for Extension
    of time.
    9/7/2006     BAD    Final revision of                        2.10    388.50
    unopposed Motion
    to Extend Discovery;
    correspondence
    to counsel enclosing
    same for review ...
    9/8/2006     JKH    Preparation of document                   .50     37.50
    and electronic
    filing of same with
    Federal Court.
    

    The motion to extend discovery was one page plus one line long. Any attorney should have been able to prepare the motion, proofread the motion, discuss the motion and file the motion in under one and a half hours. The court deducts 3.50 hours from the 5.0 hours claimed. Hence, the court finds a reasonable sum for this activity to be $185.00 (1 hour) for attorney Dodd, and $37.50 (½ hour) for Mr. Harred, a reduction of $559.50.

    9/26/2006    LGS    Preparation for                          2.40    480.00
    meeting with expert
    Bill Sealy; general
    preparation for
    deposition of John
    Vandiver....
    9/29/2006    LGS    Outline of areas for                     1.60    320.00
    coverage for Vandiver
    deposition.
    

    The deposition of John Vandiver reflects that it was attended by attorney Dodd. The court can find no reasonable basis for an attorney to charge for 4 hours work to prepare for a deposition he was not going to attend. The sum of $800.00 is subtracted.

    10/30/2006   JKH    Review and analysis                       .40     30.00
    of court order on
    briefing schedule for
    Motion; report to
    file
    

    This court order was four lines long. It could not have required more than thirty seconds to read. The court finds charging 24 minutes to read a four line order is excessive. Billing .10 hour for this activity *1135 would have been reasonable. The court eliminates .30 hours, for a reduction of $22.50.

    11/20/06     JKH    Review and analysis                      .40     30.00
    of order denying
    motion for partial
    summary judgment
    

    This Order was one and a half pages long. It may have taken two minutes to read. Billing .10 for this activity would have been reasonable. The court eliminates .30 hours, for a reduction of $22.50.

    Counsel for Western also billed thousands of dollars in expenses. Considering the reasonableness of these charges, the court finds as follows:

    Ikon Invoice of 3/9/2006:     $791.83 for office supplies.
    Ikon Invoice of 5/14/2006:     658.68 for office supplies.
    

    Office supplies are out of pocket expenses that are simply law firm overhead. The items purchased include folders, labels and binders. The court will deduct the sum of $1,450.51.

    Dominick, Fletcher Invoice of 6/29/2006:          $584.00
    

    This amount was incurred by Western because all of the parties agreed to attempt mediation in an effort to resolve this case. Each party to the mediation was to pay an equal share of the cost of the mediation. The court is of the opinion that Western is not entitled to recoup this expense from Bradford, as Bradford has already paid its fair share for the cost of this mediation, necessitated by Western's filing of this lawsuit. The court shall deduct this amount.

    Cypress Consulting Invoice of 3/31/2006     $2,263.12
    Bradford Electric Invoice of 3/27/2006         224.06
    Allied Photocopy Invoice of 3/10/2006          217.30
    Cypress Consulting Invoice of 5/31/2006        812.50[18]

    These amounts were incurred by Western in its review of Bradford's financial condition. Bradford's financial condition was never an issue in this lawsuit. No evidence, argument, letter, statement or thought that Bradford might enter bankruptcy over the issues in this lawsuit has ever been brought up by any party to this litigation, other than by Western in trying to justify why it spent tens of thousands of dollars researching Bradford's financial condition. The court finds the amount of $3,516.98 unreasonably incurred.

    McLaughlin invoices from 9/25/2005 through 9/8/2006 include the following:

    9/25/2005     Travel to Huntsville                  $1,040.00
    9/25/2006     Milage                                   465.60
    9/25/2006     Hotel                                    388.50
    9/28/2005     Travel from Huntsville                 1,040.00
    9/28/2005     Travel Expense Reimbursement             465.60
    10/24/2005    Travel to Huntsville                   1,040.00
    10/24/2005    Travel Expense Reimbursement             933.09
    10/26/2005    Travel from Huntsville                 1,040.00
    1/20/2006     Trip to Huntsville                     1,560.00
    1/20/2006     Airfare                                  521.20
    6/25/2006     Arbitration Meeting — Huntsville      1,040.00
    (Travel & Meet)
    6/25/2006     Hotel                                    191.21
    6/26/2006     Mileage                                  358.90
    6/27/2006     Arbitration Meeting — Huntsville        780.00
    (Travel Day)
    

    Western hired an engineering consultant from Louisiana. This individual was not qualified to give expert testimony under Alabama law. While Western was entitled to hire the expert of its choosing, Bradford should not have to pay for that expert to travel to Alabama. Western could have retained experts within the State of Alabama, as there has been no showing that a qualified engineering expert already licensed in this state was unobtainable, or that all engineering consultants in Alabama were unqualified. The court subtracts the amount of $10,864.10. Similarly, the court deducts the amount of $1,546.63, which attorney Stiff claimed for travel expenses on October 17, 2006, to New Orleans, Louisiana, for the deposition of Mr. McLaughlin.

    In sum, the court finds the amount of $73,236.47 not reasonably incurred. Because it was not reasonably incurred, it is not recoverable under the surety agreement. Therefore, the amount of fees and expenses reasonably recoverable by Western from Bradford under the GAI is *1136 $178,384.18. The amount paid under the payment bond, $24,262.30 is also due to Western from Bradford. The court shall so rule by separate Order.

    NOTES

    [1] Richard Bradford is the sole owner of Bradford Electric Co., Inc. Depo. of Richard Bradford (submitted as Consolidated's exhibit 4) at 12.

    [2] The court notes that in settlement of this litigation, Western did pay a sum under the performance bond. However, as part of that settlement agreement, Western does not seek indemnification of this amount.

    [3] At the hearing, Bradford asserted that any liability Western had was contingent solely on Bradford's liability. Bradford both hired construction counsel and had additional counsel from its insurance company to defend against Western's suit. Thus, Bradford argues that Western's attorney fees were vastly excessive, given the posture of this case.

    [4] Bradford actually agreed to pay the amount of $23,403.40 on this claim, because it disputed $889.00 of it. See exhibits A and B to Exhibit 1 to Bradford's opposition to Western Surety's motion for summary judgment (doc. 107).

    [5] The attorney fee and expense records provided to the court show a "Billed to Date" amount of $251, 620.65. Adding the $24,262.30 paid under the payment bond, the court finds the total sum to be $275,882.95. This is $48,978.16 less than the amount sought by Western.

    [6] These requests for collateralization were in spite of the Consent Order restraining Bradford from disposing of any assets worth more than $2,500.00 (doc. 11). Had Bradford deposited with Western $1,500,000.00, the restraints of the Consent Order would have terminated. Id.

    [7] In Perkins, the Court adopted the principles set forth by the Alabama Supreme Court in Kilgore. The Mississippi Supreme Court then concluded, "here the surety is entitled to reimbursement for legal costs only if it is necessary for the surety to retain separate legal counsel, if the amount of the fees claimed is reasonable, and if the surety has acted in good faith toward the principal." Id., at 210. After remand, the Court stated that "in Perkins I, we affirmed that the indemnity agreement was enforceable but held that it did not represent a blank check which enabled [Western] Surety to incur any expense and send the bill to [the indemnitor]." Perkins v. Thompson, 609 So. 2d 390, 399 (Miss.1992). The Court concluded that "[Western] Surety is entitled to recover only fees and expenses incurred ``by reason of having been surety on this bond.' Such fees and expenses and the reasonableness and necessity of same are thus function's of Western Surety's interest in the case and the risks to which it was exposed." Id., at 400.

    [8] This time claim actually includes other activities, all of which were billed by other counsel as well. Therefore, the court deducts the entire amount.

    [9] This habit of "grouping" activities pervades the entire billing record, creating difficulties in determining the reasonableness of all charges. The court has considered each of the activities claimed in each "group" and, where possible, allowed time for clearly compensable activities.

    [10] The court has arrived at this amount by averaging the rates charged by counsel. As two attorneys bill at $200.00 per hour, and a third at $185.00 per hour, the court has added these rates ($200.00 + $200.00 + $185.00), divided by 3 and arrived at the sum of $195.00 per hour for each hour reduced.

    [11] Again, because of the "grouping" of blocks of time, the court has added the total time disallowed and averaged the rate charged for the three attorneys who claimed time for this activity. Hence $200/hr. + $200/hr. + $185.00/hr. ÷ 3 = 195.00 × 4.90 hours disallowed = $955.50.

    [12] Joan Clements' deposition was attended by attorney Stiff, not attorney Seldon. The court notes attorney Stiff spent no less than 20 billed hours preparing for that deposition, which resulted in a 129 page transcript.

    [13] See infra regarding Western's fees incurred on the collateralization issue.

    [14] The court notes this calculation is actually low, as there are further hours spent by Western's counsel on these motions, but grouped with other activities on the collateralization attempts, and discussed there.

    [15] The court determined each individual's share of the total time worked based on percentages and multiplied that for each of his proportional share of the 13.1 hour reduction, as follows:

    Mr. Harred    1.64 hours @ $75/hr =  $  123.00
    Attorney      0.44 hours @ 200/hr =      88.00
    Selden
    Attorney      5.78 hours @ 185/hr =    1068.30
    Dodd
    Attorney      5.22 hours @ 200/hr =    1044.00
    Stiff
    _________
    $2,323.30
    

    [16] For reasons stated infra, the court finds none of these activities reasonable. Additionally, this is a charge by plaintiff's counsel for sending something to plaintiff's counsel.

    [17] Although Western's counsel reference activities relating to "unilateral settlement options" in numerous entries, the term "unilateral settlement" appears to be an oxymoron. The court cannot discern what "physician's summary for pretrial order" attorney Stiff may have worked on, as no medical claims or issues are in this case.

    [18] This invoice includes a $250.00 charge for Western's accounting expert from Connecticut to review Mr. Bradford's divorce documents.