Power v. Gilbert ( 2015 )


Menu:
  •                       NOTICE: NOT FOR OFFICIAL PUBLICATION.
    UNDER ARIZONA RULE OF THE SUPREME COURT 111(c), THIS DECISION IS NOT PRECEDENTIAL
    AND MAY BE CITED ONLY AS AUTHORIZED BY RULE.
    IN THE
    ARIZONA COURT OF APPEALS
    DIVISION ONE
    POWER ROAD-WILLIAMS FIELD, LLC, an Arizona limited liability
    company; GEORGE M. SIEGELE; and KEITH PULVER,
    Plaintiffs/Appellants,
    v.
    TOWN OF GILBERT, an Arizona municipality, and its members of its
    counsel acting in their official capacity, JOHN W. LEWIS, JENN
    DANIELS, EDDIE COOK, VICTOR PETERSEN, JOHN SENTZ, JORDAN
    RAY, and BEN COOPER; CITY OF MESA, an Arizona municipality;
    COUNTY OF MARICOPA, a political subdivision of the State of Arizona,
    Defendants/Appellees.
    No. 1 CA-CV 13-0609
    FILED 1-13-2015
    Appeal from the Superior Court in Maricopa County
    No. CV2011-005700
    The Honorable George H. Foster, Jr., Judge
    APPEAL DISMISSED AS MOOT
    COUNSEL
    Francis J. Slavin, P.C., Phoenix
    By Francis J. Slavin, Ellen B. Davis
    Counsel for Plaintiffs/Appellants
    Grasso Law Firm, P.C., Chandler
    By Robert Grasso, Jr., Jenny J. Winkler
    Counsel for Defendants/Appellees Town of Gilbert and all named Gilbert Officials
    Dickinson Wright, PLLC, Phoenix
    By Gary L. Birnbaum, David J. Ouimette
    Counsel for Defendant/Appellee City of Mesa
    Maricopa County Attorney’s Office, Phoenix
    By J. Kenneth Mangum, James Fritz
    Counsel for Defendant/Appellee Maricopa County
    MEMORANDUM DECISION
    Judge Maurice Portley delivered the decision of the Court, in which
    Presiding Judge Patricia A. Orozco and Judge Randall M. Howe joined.
    P O R T L E Y, Judge:
    ¶1             Power Road-Williams Field, LLC, an Arizona limited liability
    company, George M. Siegele, and Keith Pulver (collectively “Appellants”)
    appeal the dismissal of Counts One (failure to conform to the Gilbert
    General Plan), Three (failure to enter into an intergovernmental agreement)
    and Four (arbitrary and irrational exercise of police powers) of their First
    Amended Complaint pursuant to Arizona Rule of Civil Procedure (“Rule”)
    12(b)(6) for failure to state a claim, and the summary judgment granted in
    favor of the Town of Gilbert, the City of Mesa and Maricopa County
    (collectively “Appellees”) as to Count Two (failure to follow statutory
    procedures). For the following reasons, we dismiss the appeal.
    PROCEDURAL BACKGROUND
    ¶2            Appellees were engaged in a multi-phased, multi-year project
    to widen and improve a ten-mile stretch of Power Road from Baseline Road
    to Chandler Heights Road. Appellants disagreed with the Phase III (“the
    Project”) design of the multi-phased project, which encompassed the
    intersection of Power Road and Williams Field Road. After lobbying
    unsuccessfully to persuade Appellees to choose a different design,
    Appellants sued seeking to stop the Project. Appellants, however, did not
    seek a preliminary injunction or other stay of construction pending the
    outcome of the litigation.
    ¶3          After Appellants were allowed to amend their complaint,
    Appellees successfully moved to dismiss three of four counts of the
    amended complaint for failing to state a claim for which relief could be
    2
    POWER et al. v. GILBERT et al.
    Decision of the Court
    granted under Rule 12(b)(6). The parties then filed cross-motions for
    summary judgment on the remaining count, and the court subsequently
    entered judgment in favor of Appellees. The Project continued during the
    course of the litigation and is now complete. Appellants appealed and we
    have jurisdiction under Arizona Revised Statutes (“A.R.S.”) section
    12-2101(A)(1).1
    DISCUSSION
    ¶4            Appellants, who sought declaratory judgment and injunctive
    relief, argue that the trial court erred in granting Appellees’ motion to
    dismiss and motion for summary judgment because (1) the Project failed to
    conform to the Gilbert General Plan; (2) Appellees failed to comply with the
    reviews and reports requirements under A.R.S. § 9-461.01; (3) Appellees
    failed to adopt an intergovernmental agreement; and (4) Appellants were
    entitled to a trial on their claim for abuse of power. Appellees contend,
    however, that this appeal is moot because the Project has been completed.2
    We agree.
    ¶5           Unlike federal courts, our state courts do not have a
    “constitutional provision constraining it to consider only cases or
    controversies.” Fraternal Order of Police Lodge 2 v. Phoenix Emp. Relations Bd.,
    
    133 Ariz. 126
    , 127, 
    650 P.2d 428
    , 429 (1982) (internal quotation marks
    omitted). Our supreme court, however, has consistently held that state
    courts will “refrain from considering moot or abstract questions.” 
    Id. Therefore, we
    will not decide a question that is unrelated to an actual
    controversy or that is rendered moot by a change in circumstances. See id;
    Contempo–Tempe Mobile Home Owners Ass’n v. Steinert, 
    144 Ariz. 227
    , 229,
    
    696 P.2d 1376
    , 1378 (App. 1985).
    ¶6             Here, although Appellants objected to the split alignment
    design of the Project, they did not seek a preliminary injunction or any other
    stay to stop construction of the Project. As a result, the construction project
    with the split alignment continued and is now complete. The Project’s
    completion renders this appeal moot because the principal relief sought by
    1We cite to the current version of the statute unless otherwise noted.
    2 The Project construction began in June 2012 and was completed as of
    June 2014. See http://mesaaz.gov/engineering/Projects/PowerRdImpr/
    PowerRdImpr.aspx (“Project is complete.”).
    3
    POWER et al. v. GILBERT et al.
    Decision of the Court
    Appellants in their amended complaint — to “stop the Project”3 — is no
    longer an available remedy. See ASH, Inc. v. Mesa Unified Sch. Dist. No. 4,
    
    138 Ariz. 190
    , 191-92, 
    673 P.2d 934
    , 935-36 (App. 1983) (holding that
    plaintiff’s appeal was moot where challenged contract had been fully
    performed and plaintiff, in failing to seek any of the available procedural
    remedies to stay performance of the contract pending litigation, had not
    effectively preserved the issue on appeal); accord W. Sun Contractors Co. v.
    Superior Court, 
    159 Ariz. 223
    , 227, 
    766 P.2d 96
    , 100 (App. 1988) (noting, while
    issuing an interlocutory stay and granting expedited consideration of the
    merits, that “[b]ecause of the peculiar nature of public contracts the courts
    are loath to grant relief where such contracts have been fully performed
    [and] . . . if no stay were issued, the completion of the work would moot
    any relief”) (internal citations omitted).
    ¶7             Courts will only grant a declaratory judgment when there is
    a justiciable issue between the parties. Thomas v. City of Phoenix, 
    171 Ariz. 69
    , 74, 
    828 P.2d 1210
    , 1215 (App. 1991). Moreover, Appellants’ failure to
    seek to enjoin the construction before it was completed not only moots their
    request for injunctive relief, but also their claim for declaratory relief. See
    
    id. (“Courts will
    not hear cases that seek declaratory judgments that are
    advisory or answer moot or abstract questions. Declaratory relief should
    be based on an existing state of facts, not facts that may or may not arise in
    the future.”) (internal citations omitted).
    ¶8             We can, however, decide an issue of law despite its mootness
    if the matter is of considerable public importance or the principle involved
    is a continuing one. State v. Superior Court, 
    104 Ariz. 440
    , 441, 
    454 P.2d 982
    ,
    983 (1969). However, we do not find that the circumstances of this case fall
    within either exception. Although the issue involved in this case, the split
    alignment design, is capable of repetition, we cannot say as a matter of law
    that it will evade review. Further, given the completion of the project, the
    question involved does not rise to a sufficient level of “public importance”
    to be an exception to the mootness doctrine. See Camerena v. Dep’t of Pub.
    Welfare, 
    106 Ariz. 30
    , 
    470 P.2d 111
    (1970).
    3The amended complaint sought the following relief: (1) a declaration that
    the split alignment design was arbitrary and capricious, irrational and an
    abuse of discretion; (2) an order enjoining the construction and other work
    associated with the split alignment design; and (3) attorney’s fees and costs.
    4
    POWER et al. v. GILBERT et al.
    Decision of the Court
    CONCLUSION
    ¶9          Because the Project has been completed, Appellants’ appeal is
    moot. Accordingly, we dismiss the appeal.
    :ama
    5