Southwest v. Sbbi, Inc. ( 2018 )


Menu:
  •                       NOTICE: NOT FOR OFFICIAL PUBLICATION.
    UNDER ARIZONA RULE OF THE SUPREME COURT 111(c), THIS DECISION IS NOT PRECEDENTIAL
    AND MAY BE CITED ONLY AS AUTHORIZED BY RULE.
    IN THE
    ARIZONA COURT OF APPEALS
    DIVISION ONE
    SOUTHWEST CONCRETE PAVING CO.,
    Plaintiff/Appellee/Cross-Appellant,
    v.
    SBBI, INC., et al.,
    Defendants/Appellants/Cross-Appellees.
    No. 1 CA-CV 17-0294
    FILED 5-22-2018
    Appeal from the Superior Court in Maricopa County
    No. CV2014-005443
    The Honorable Kerstin G. LeMaire, Judge
    AFFIRMED IN PART; REVERSED AND REMANDED IN PART
    COUNSEL
    Cheifetz Iannitelli Marcolini, PC, Phoenix
    By Claudio Eduardo Iannitelli, Cynthia R. Estrella, Jason Kelly Thomas
    Counsel for Plaintiff/Appellee/Cross-Appellant
    Thompson Krone PLC, Tucson
    By Evan L. Thompson, Russell E. Krone
    Counsel for Defendants/Appellants/Cross-Appellees
    SOUTHWEST v. SBBI, INC., et al.
    Decision of the Court
    MEMORANDUM DECISION
    Presiding Judge Maria Elena Cruz delivered the decision of the Court, in
    which Judge Jennifer B. Campbell and Judge James P. Beene joined.
    C R U Z, Presiding Judge:
    ¶1            We are asked to review several disputes between a general
    contractor, SBBI, Inc. (“SBBI”), and concrete paving subcontractor
    Southwest Concrete Paving Co. (“Southwest”). We affirm the trial court’s
    delay damages, extra work, and attorneys’ fee award to Southwest. We
    reverse and remand for further proceedings to address whether SBBI
    properly deducted the cost of dowel basket installation from Southwest’s
    contract price.
    FACTUAL AND PROCEDURAL HISTORY
    ¶2           Southwest performed concrete paving work at the UAS
    Maintenance Hangar at Holloman Air Force Base in New Mexico (the
    “Project”). Hensel Phelps Construction Co. (“Hensel Phelps”) was the
    general contractor for the Project. SBBI contracted with Hensel Phelps to
    perform certain site work and paving work on or about February 22, 2012
    (the “SBBI Contract”). SBBI then contracted with Southwest on March 12,
    2012, to complete paving work (the “Southwest Contract”).
    ¶3            The SBBI Contract obligated SBBI to “[f]urnish and install
    reinforcing, dowels, and dowel baskets for the apron paving.”1 Both the
    Southwest Contract and Southwest’s “Final Proposal” included “drilling
    and installing of dowel bars” but neither mentioned dowel baskets. That
    same language appeared in SBBI’s Bid Proposal to Hensel Phelps.
    ¶4           SBBI asked Southwest to price the removal of dowel baskets
    from the Project plans and specifications. Southwest told SBBI that it did
    not include dowel baskets in its Final Proposal because it did not believe
    the owner would approve their use. Nonetheless, Southwest prepared a
    1      Dowel baskets are a method of installing dowel bars used in certain
    concrete applications. Dowel baskets are placed on grade and new concrete
    is poured over the basket assembly. Dowel bars are installed by drilling
    into the vertical edge of existing concrete. The parties do not dispute that
    dowel baskets and dowel bars are not the same.
    2
    SOUTHWEST v. SBBI, INC., et al.
    Decision of the Court
    report showing dowel basket installation would cost $106,278.00. Hensel
    Phelps later removed dowel baskets from the final plans and specifications
    and issued a change order reducing SBBI’s contract price by $106,278.00.
    SBBI then issued a deductive unilateral change order reducing Southwest’s
    contract price by the same amount.
    ¶5            The paving portion of the Project suffered numerous delays.
    The parties disputed who caused the delays; Southwest contended that
    SBBI failed to properly coordinate other subcontractors’ work and that one
    subcontractor, Bray Construction, caused significant delays through
    surveying and aggregate base layer errors. SBBI, on the other hand,
    contended Southwest was responsible for some of the delays alongside
    Bray. Southwest sued SBBI and its surety seeking $172,852.40 in damages
    based on twenty-five days of delay. Southwest also sought $21,575.64 for
    power washing, $11,706.56 for repairs to freshly poured concrete, and
    $6,875.40 to remove and replace a concrete panel, all of which it contended
    constituted extra work beyond the scope of the Southwest Contract.
    ¶6            SBBI moved for partial summary judgment, contending the
    unilateral deductive change order was appropriate because both the SBBI
    Contract and the plans and specifications included dowel baskets when the
    parties entered into the Southwest Contract. SBBI also contended that the
    Southwest Contract precluded Southwest’s delay damages claim:
    Should the Subcontractor, without fault or neglect on its own
    part, be delayed in the commencement or completion of the
    Work by the fault or neglect of the Contractor or another
    subcontractor on the project, Subcontractor shall be entitled
    to a reasonable extension of time only. . . . In no event shall
    the Subcontractor be entitled to receive compensation or
    damages for any aforementioned delays except to the extent
    that the Contractor shall receive such compensation or
    damages from the Agency/Owner or another third party.
    The trial court granted partial summary judgment as to the unilateral
    change order, finding Southwest’s Final Proposal “included dowel baskets
    in its bid price[.]” The court denied summary judgment on Southwest’s
    delay damages claim, however, finding genuine issues of material fact
    remained as to who had caused the delays.
    ¶7           Following a bench trial, the court denied Southwest’s concrete
    repair claim but awarded its full power washing and concrete panel
    replacement claims, finding both constituted extra work under the
    3
    SOUTHWEST v. SBBI, INC., et al.
    Decision of the Court
    Southwest Contract. The court also awarded $40,094.20 in delay damages,
    finding the clause quoted above did not apply because “SBBI willfully and
    knowingly delayed Southwest’s ability to timely perform” by “fail[ing] to
    appropriately supervise Bray.”
    ¶8            The court also invited Southwest to submit an attorneys’ fee
    application and statement of costs. Southwest did so, seeking $78,124.50 in
    attorneys’ fees. SBBI opposed the application and filed its own attorneys’
    fee application requesting a similar amount of fees. The court determined
    that Southwest was the successful party and awarded it $20,000 in
    attorneys’ fees.
    ¶9            SBBI timely appealed the final judgment as well as the ruling
    denying summary judgment on Southwest’s delay damages claim.
    Southwest timely cross-appealed the court’s ruling granting summary
    judgment to SBBI on the unilateral deductive change order. We have
    jurisdiction over both the appeal and cross-appeal pursuant to Arizona
    Revised Statutes (“A.R.S.”) section 12-2101(A)(1).
    DISCUSSION
    I.     The Court’s Denial of Summary Judgment on Southwest’s Delay
    Damages Claim Is Not Appealable.
    ¶10            SBBI first challenges the trial court’s order denying summary
    judgment on Southwest’s delay damages claim. An order denying
    summary judgment typically is not appealable even after entry of a final
    judgment. Cal X-Tra v. W.V.S.V. Holdings, L.L.C., 
    229 Ariz. 377
    , 408 n.50,
    ¶ 105 (App. 2012). This is because such orders do not necessarily affect the
    final judgment; they only indicate the trial court’s belief that the issues
    raised should proceed to trial. Navajo Freight Lines, Inc. v. Liberty Mut. Ins.
    Co., 
    12 Ariz. App. 424
    , 428 (1970). We may review the order, however, if
    the denial is based on a purely legal issue or if the proponent reasserts the
    issue in a motion for judgment as a matter of law pursuant to Arizona Rule
    of Civil Procedure 50 or other post-trial motion. Desert Palm Surgical Grp.,
    P.L.C. v. Petta, 
    236 Ariz. 568
    , 577, ¶ 22 (App. 2015). We review de novo
    whether a pure question of law precluded the denial of summary judgment.
    
    Id. ¶11 SBBI
    contends, as it did below, that the Southwest Contract
    limited Southwest’s remedy for delays “in the commencement or
    completion of the Work by the fault or neglect of the Contractor or another
    subcontractor on the project” to “a reasonable extension of time only.” The
    parties agree on appeal that “no delay damages” clauses generally are
    4
    SOUTHWEST v. SBBI, INC., et al.
    Decision of the Court
    enforceable. See United Dairymen of Ariz. v. Schugg, 
    212 Ariz. 133
    , 138, ¶ 16
    (App. 2006) (“Express contract provisions governing remedies or damages
    are generally binding on the parties.”). Southwest argues, however, that
    we should adopt an “active interference” exception to enforcement that has
    been recognized by other courts. See, e.g., C & H Elec., Inc. v. Town of Bethel,
    
    96 A.3d 477
    , 486 (Conn. 2014) (“Many, if not most, other states recognize a
    separate, judicially created active interference exception to ‘no damages for
    delay’ clauses.”); Triple R Paving, Inc. v. Broward Cty., 
    774 So. 2d 50
    , 54 (Fla.
    Dist. Ct. App. 2000) (“Clauses providing for ‘no damages for delay,’ except
    in the case of fraud, bad faith, or active interference by the owner, are legal
    and enforceable.”). SBBI, meanwhile, relies on other out-of-state cases
    holding that the active interference exception requires “an affirmative,
    willful act.” C & 
    H, 96 A.3d at 486
    (citing cases); see also Pellerin Constr., Inc.
    v. Witco Corp., 
    169 F. Supp. 2d 568
    , 583 (E.D. La. 2001); Phx. Contractors, Inc.
    v. Gen. Motors Corp., 
    355 N.W.2d 673
    , 677 (Mich. Ct. App. 1984).
    ¶12           While the parties argue these legal issues on appeal, the trial
    court did not directly address them in its summary judgment ruling. It
    instead denied SBBI’s motion based on its conclusion that material issues of
    fact remained as to who caused the project delays. SBBI did not seek
    judgment as a matter of law during or after trial, nor did it file any post-
    trial motions. SBBI thus waived its right to appeal this ruling. John C.
    Lincoln Hosp. & Health Corp. v. Maricopa County, 
    208 Ariz. 532
    , 537, ¶ 19
    (App. 2008) (concluding, because the trial court denied the motion for
    partial summary judgment due to the existence of material factual disputes,
    party had waived its right to appeal the sufficiency of the claims at issue by
    not reasserting the issue during or after trial).
    II.    The Trial Court Did Not Abuse Its Discretion in Awarding
    Southwest Extra Work Compensation.
    ¶13           SBBI also challenges the court’s damages awards relating to
    power washing and concrete panel replacement. Because these issues were
    resolved in the bench trial, we review the court’s legal conclusions de novo
    but defer to its findings of fact unless they are clearly erroneous. Town of
    Marana v. Pima County, 
    230 Ariz. 142
    , 152, ¶ 46 (App. 2012). We review any
    factual issues in the light most favorable to upholding the court’s ruling.
    Bennett v. Baxter Grp., Inc., 
    223 Ariz. 414
    , 417, ¶ 2 (App. 2010).
    ¶14         SBBI first contends these tasks fell within paragraph 24 of the
    Southwest Contract, which provides:
    5
    SOUTHWEST v. SBBI, INC., et al.
    Decision of the Court
    Except to the extent of any proceeds received by the
    Contractor for the benefit of Subcontractor under a policy of
    builders’ risk or fire insurance, Contractor shall not be liable
    or responsible for any loss or damage to the Work;
    Subcontractor shall be responsible for any loss or damage to
    the work; Subcontractor shall be responsible for the correction
    or restoration of any such loss or damage to the Work, or to
    the work of the Contractor or any other subcontractor,
    resulting from the operations of the Subcontractor . . .
    Subcontractor shall take reasonable precautions to protect the
    Work from loss or damage prior to acceptance by the
    Agency/Owner.
    ¶15           SBBI cites no evidence to show the concrete panel repair at
    issue fell under this provision. As for concrete cleaning, Southwest
    presented evidence that it consistently excluded traffic control and concrete
    cleaning from its bids because it did not have the necessary equipment for
    those tasks. SBBI contends on appeal that “[t]raffic control . . . did not entail
    the protection of the concrete surface which Southwest was required to
    protect” but again cites no supporting evidence. The court did not clearly
    err in finding that these items were beyond the scope of the Southwest
    Contract.
    ¶16          SBBI also contends Southwest never obtained written
    authorization to proceed with the power washing or concrete panel
    replacement pursuant to paragraph 8 of the Southwest Contract:
    In addition to Change Orders issued under paragraph 7 . . .
    Contractor may from time to time . . . require by written order
    that Subcontractor perform extra Work reasonably related to
    the original Work hereunder. . . . Such extra Work shall be
    invoiced weekly, in reasonable detail and amply supported
    on the basis of the performing party’s actual direct costs and
    without overhead or profit or allowance therefore. Payment
    of such invoices shall be made at the time of the next ensuing
    progress payment or final payment hereunder.
    In no event shall Subcontractor proceed with a Change Order
    without a written Change Order under paragraph[] 7 above
    or a written order from the Contractor for extra Work under
    paragraph 8; and contractor shall not be liable for any
    additional costs incurred or delays encountered in the
    performance of such Work without such a written notice
    6
    SOUTHWEST v. SBBI, INC., et al.
    Decision of the Court
    approved by the Contractor’s home office or a duly
    designated representative from the Contractor’s home office.
    SBBI did not issue written extra work orders for the power washing or
    concrete panel repairs. But Southwest presented evidence showing SBBI
    did not always enforce this requirement.
    ¶17           Southwest also presented evidence that SBBI verbally
    directed it to proceed with the concrete panel repairs and directed it to
    proceed with concrete cleaning in a punch list. Southwest also presented
    evidence showing it was only responsible for approximately forty-five
    percent of the tire marks that necessitated cleaning. Moreover, SBBI’s
    project manager testified that formal orders were not always prepared and
    that he knew Southwest would dispute responsibility for the power
    cleaning costs. Given this evidence, the court’s awards did not constitute
    clear error. See Kocher v. Dep’t of Revenue of State of Ariz., 
    206 Ariz. 480
    , 482,
    ¶ 9 (App. 2003) (“A finding of fact is not clearly erroneous if substantial
    evidence supports it, even if substantial conflicting evidence exists.”).
    III.   The Trial Court Did Not Abuse Its Discretion in Awarding
    Attorneys’ Fees to Southwest.
    ¶18           Section 12-341.01(A) affords the trial court discretion to award
    attorneys’ fees to the successful party in an action arising out of contract.
    McAlister v. Citibank (Ariz.), a Subsidiary of Citicorp, 
    171 Ariz. 207
    , 216 (App.
    1992). We will affirm a successful party determination absent an abuse of
    discretion. Am. Power Products, Inc. v. CSK Auto, Inc., 
    242 Ariz. 364
    , 367,
    ¶ 12 (2017).
    ¶19           SBBI contends Southwest was not the successful party
    because it only recovered approximately $68,000 of its original $442,602.63
    demand. The fact that a party does not recover all of its requested relief
    does not preclude it from being deemed the successful party.2 Sanborn v.
    Brooker & Wake Prop. Mgmt., Inc., 
    178 Ariz. 425
    , 430 (App. 1994); see also Lee
    v. ING Inv. Mgmt., LLC, 
    240 Ariz. 158
    , 161, ¶ 10 (App. 2016) (providing a
    party may be successful for purposes of A.R.S. § 12-341.01(A) “even when
    the recovery it obtains is ‘significantly reduced’”) (quoting Berry v. 352 E.
    2      We also decline SBBI’s invitation to “remand . . . to the trial court
    directing [it] to articulate” its methodology in awarding fees to Southwest.
    The trial court need not explain its fee award so long as the record contains
    a reasonable basis for it. Fulton Homes Corp. v. BBP Concrete, 
    214 Ariz. 566
    ,
    569, ¶ 9 (App. 2007).
    7
    SOUTHWEST v. SBBI, INC., et al.
    Decision of the Court
    Virginia, L.L.C., 
    228 Ariz. 9
    , 14, ¶¶ 23-24 (App. 2011)). Moreover, the fact
    that Southwest obtained a money judgment, while not dispositive, is an
    important consideration in determining who is the successful party. 
    Lee, 240 Ariz. at 161
    , ¶ 10. The trial court did not abuse its discretion in
    awarding attorneys’ fees to Southwest.
    IV.    Issues of Material Fact Remain as to Whether the Southwest Contract
    Excluded Dowel Baskets.
    ¶20            In its cross-appeal, Southwest challenges the court’s ruling
    granting partial summary judgment to SBBI affirming its unilateral
    deductive change order regarding dowel basket installation. We review a
    grant of partial summary judgment de novo. Dobson Bay Club II DD, LLC v.
    La Sonrisa de Siena, LLC, 
    242 Ariz. 108
    , 112, ¶ 18 (2017).
    ¶21           We first consider the relevant terms of the Southwest
    Contract. If the terms are clear and unambiguous, we give effect to them as
    written. Town of 
    Marana, 230 Ariz. at 147
    , ¶ 21. If the terms are ambiguous,
    “parol evidence may be used to explain [the ambiguity], but in the absence
    of fraud or mistake, it may not be used to change, alter or vary the express
    terms in a written agreement.” 
    Id. (quoting Brand
    v. Elledge, 
    101 Ariz. 352
    ,
    358 (1966)).
    ¶22             Paragraph 1 obligated Southwest to “perform and furnish all
    labor, supervision, materials, [and] equipment, to complete the work
    identified and described in [S]chedule A: Work.” It also provided that the
    work was to be performed “strictly in accordance with the contract
    documents including but not limited to the contract between the owner and
    contractor, . . . plans, specifications, . . . and other documents identified in
    Schedule B attached hereto,” which defined “Contract Documents” to
    include the SBBI Contract as well as the project plans and specifications.
    Schedule A similarly provided that the work “shall be in compliance with
    project plans, specifications, . . . [and] contract documents[.]” But while
    Schedule A defined the “Scope of Work” to include “drilling and install of
    dowel bars,” it did not include dowel baskets.
    ¶23           Southwest contends Schedule A demonstrates an agreement
    to exclude dowel baskets, but SBBI contends the Southwest Contract
    obligated Southwest to follow the plans and specifications available at that
    time, which included dowel baskets. When parties submit competing
    interpretations of a contract’s meaning, the court should consider “the
    offered evidence and, if [the court] finds that the contract language is
    reasonably susceptible to the interpretation asserted by its proponent, the
    8
    SOUTHWEST v. SBBI, INC., et al.
    Decision of the Court
    evidence is admissible to determine the meaning intended by the parties.”
    Town of 
    Marana, 230 Ariz. at 147
    , ¶ 21 (quoting Taylor v. State Farm Mut.
    Auto. Ins. Co., 
    175 Ariz. 148
    , 154 (1993)).
    ¶24           Southwest presented evidence showing that Schedule A’s
    reference to “dowel bars,” which it contends are installed “by drilling into
    the vertical edge of existing concrete,” necessarily excluded the use of
    dowel baskets. It also presented evidence showing that it chose not to
    include dowel baskets in its Final Proposal because it believed the owner
    would not approve them in the final plans. Southwest also presented
    evidence that it would have provided dowel baskets at no additional cost
    had the owner approved them. Finally, Southwest presented evidence that
    SBBI copied the language of Southwest’s “Final Proposal” verbatim in its
    own bid proposal to Hensel Phillips and in Schedule A of the Southwest
    Contract.
    ¶25            Based on this evidence, we conclude that the Southwest
    Contract is reasonably susceptible to Southwest’s interpretation that it did
    not include dowel baskets. This evidence thus is admissible. Johnson v.
    Earnhardt’s Gilbert Dodge, Inc., 
    212 Ariz. 381
    , 385, ¶ 19 (2006). Construing
    the evidence in Southwest’s favor, as we must in reviewing a grant of
    summary judgment, we conclude that genuine issues of material fact
    remain as to whether the Southwest Contract included dowel baskets and,
    therefore, whether the unilateral change order reducing Southwest’s
    contract price by the amount estimated for their installation was proper. See
    Nat’l Bank of Ariz. v. Thruston, 
    218 Ariz. 112
    , 116, ¶ 17 (App. 2008) (“[A] court
    must view the [summary judgment] evidence in a light most favorable to
    the non-moving party and draw all justifiable inferences in its favor.”). We
    thus reverse the grant of partial summary judgment on this issue and
    remand for further proceedings.
    V.     Southwest May Recover Reasonable Attorneys’ Fees and Taxable
    Costs Incurred on Appeal.
    ¶26           Southwest requests its attorneys’ fees incurred on appeal
    pursuant to A.R.S. § 12-341.01(A). Southwest is the successful party on
    appeal, and its claims clearly arise out of contract. We therefore will award
    it reasonable attorneys’ fees and taxable costs upon compliance with
    Arizona Rule of Civil Appellate Procedure 21.
    9
    SOUTHWEST v. SBBI, INC., et al.
    Decision of the Court
    CONCLUSION
    ¶27          We reverse the trial court’s grant of partial summary
    judgment to SBBI on the dowel baskets issue and remand for further
    proceedings. We affirm as to all other issues raised.
    AMY M. WOOD • Clerk of the Court
    FILED: AA
    10