Az Electric Power v. Djl 2007 , 246 Ariz. 534 ( 2019 )


Menu:
  •                               IN THE
    ARIZONA COURT OF APPEALS
    DIVISION ONE
    ARIZONA ELECTRIC POWER COOPERATIVE, INC.,
    Plaintiff/Appellee/Cross-Appellant,
    v.
    DJL 2007 LLC, an Arizona limited liability company; DJL ENTERPRISES,
    LLC, an Arizona limited liability company; EAST COAST INVESTOR
    GROUP 535, LLC, a Delaware limited liability company; MARK G.
    KNORR and CAROL A. KNORR, husband and wife; SILVER CREEK
    LAND CO., LLC, an Arizona limited liability company; and MICHAEL
    SUDA, a married man as his sole and separate property; DONALD
    SUDA, a married man as his sole and separate property,
    Defendants/Appellants/Cross-Appellees.
    _________________________________
    MOHAVE ELECTRIC COOPERATIVE, INCORPORATED, an Arizona
    Electric Cooperative Non-Profit Membership Corporation,
    Intervenor/Appellee/Cross-Appellant.
    No. 1 CA-CV 16-0097
    FILED 5-9-2019
    Appeal from the Superior Court in Mohave County
    Nos. B8015CV201404008, B8015CV201404009, B8015CV201404010,
    B8015CV201404011, B8015CV201404012, B8015CV201404013
    (Consolidated)
    The Honorable Charles W. Gurtler, Judge
    AFFIRMED IN PART, REVERSED IN PART, AND REMANDED
    COUNSEL
    Gust Rosenfeld, PLC, Phoenix
    By Charles W. Wirken
    Jennings Strouss & Salmon, PLC, Phoenix
    By Christopher W. Kramer
    Co-Counsel for Plaintiff/Appellee/Cross-Appellant
    Zeitlin & Zeitlin, PC, Phoenix
    By Dale S. Zeitlin
    Counsel for Defendants/Appellants/Cross-Appellees
    The Law Offices of Larry K. Udall, PLLC, Chandler
    By Larry K. Udall
    Counsel for Intervenor/Appellee/Cross-Appellant
    OPINION
    Presiding Judge Kent E. Cattani delivered the opinion of the Court, in
    which Judge Jon W. Thompson and Judge Paul J. McMurdie joined.
    C A T T A N I, Judge:
    ¶1             Both sides in these consolidated condemnation cases appeal
    from the superior court’s rulings (1) fixing a valuation date for purposes of
    calculating just compensation for a right of way for electric transmission
    lines and (2) determining the ownership of existing support structures and
    transmission lines within the right of way. We affirm the court’s ruling as
    to ownership of the existing structures and transmission lines, but we
    reverse the ruling as to valuation date. Under the right-of-way clause of
    Article 2, Section 17 of the Arizona Constitution, a private corporation with
    statutory eminent domain authority cannot effect a taking (which
    establishes the valuation date) by simply occupying property. Instead, the
    taking occurs only after the jury determines damages and the private
    corporation pays full compensation. Because the superior court chose a
    pre-taking valuation date, we reverse and remand for further proceedings
    consistent with this decision.
    2
    AZ ELECTRIC POWER v. DJL 2007, et al.
    Opinion of the Court
    FACTS AND PROCEDURAL BACKGROUND
    ¶2           On May 15, 1981, the United States Department of the Interior,
    Bureau of Land Management (“BLM”), granted a 30-year right of way to
    Arizona Electric Power Cooperative, Inc., across public lands in Mohave
    County for use as an easement for 69kV electric transmission lines. Both
    69kV and 230kV transmission lines were built within the right of way.
    ¶3             By 1990, the BLM had transferred title to the property subject
    to the right of way into private hands. DJL 2007 LLC, DJL Enterprises LLC,
    East Coast Investor Group 535, LLC, Mark and Carol Knorr, Silver Creek
    Land Co., Michael Suda, and Donald Suda (collectively, “Landowners”) are
    the current owners of the relevant parcels. Southwest Transmission
    Cooperative, Inc.,1 as a successor in interest, obtained Arizona Electric
    Power’s interest in the right of way in the early 2000s, and Southwest
    Transmission sold the 69kV line to Mohave Electric Cooperative, Inc., a few
    years later.
    ¶4           The BLM right-of-way grant expired on May 14, 2011. But
    Southwest Transmission and Mohave Electric continued to operate the
    transmission lines thereafter, and in January 2013, Landowners sent
    Southwest Transmission a letter alleging that it was trespassing.
    ¶5            Southwest Transmission is a nonprofit electric generation and
    transmission cooperative corporation under Title 10, Chapter 19, Article 4
    of the Arizona Revised Statutes (“A.R.S.”) and, as such, has statutory
    authority to exercise the power of eminent domain for purposes of
    maintaining or operating electric transmission lines. See A.R.S. § 10-
    2127(A)(11); see also A.R.S. § 12-1111(10). Accordingly, in January 2014,
    Southwest Transmission filed these eminent domain actions to condemn
    rights of way for the transmission lines. Mohave Electric intervened as the
    owner of one of the transmission lines.
    ¶6            The superior court ruled that Southwest Transmission was
    not entitled to an order of immediate possession under A.R.S. § 12-1116.
    Instead, recognizing the practical reality that Southwest Transmission
    1      Southwest Transmission merged into Arizona Electric Power after
    this appeal was filed, and Arizona Electric Power was substituted as
    appellee/cross-appellant. Given Southwest Transmission’s participation
    throughout the superior court proceedings and adopting the convention
    employed by the parties, we refer to Southwest Transmission rather than
    Arizona Electric Power as prospective condemnor throughout this decision.
    3
    AZ ELECTRIC POWER v. DJL 2007, et al.
    Opinion of the Court
    would need to continue to operate, maintain, and repair the lines during
    the pendency of the condemnation proceedings, the court entered a
    preliminary injunction allowing ongoing access to and operation of the
    lines.
    ¶7             Landowners then moved the court to determine the valuation
    date for purposes of calculating just compensation to be paid for the
    property subject to condemnation. Landowners argued that the land
    should be valued as of the date the court eventually enters the final order
    of condemnation. Southwest Transmission countered that the land should
    be valued as of May 15, 2011, the date it remained in possession
    immediately following expiration of the BLM right-of-way grant. After
    briefing and oral argument, the court adopted a middle ground, ruling that
    the valuation date would be January 15, 2014: the date the summons issued
    in the condemnation suit. The court further ruled that Landowners would
    be entitled to rental damages from expiration of the grant to the summons
    date, and that interest would accrue from the valuation date on the amount
    of compensation ultimately awarded. The court denied Landowners’
    subsequent motion for reconsideration.
    ¶8           The parties then filed cross-motions for partial summary
    judgment concerning ownership of the transmission lines and support
    structures, which would determine whether just compensation for the
    taking includes the value of those improvements or just of the underlying
    real property interest. The superior court ruled in favor of Southwest
    Transmission, finding no indication that title to the improvements had
    passed to Landowners.
    ¶9            At the parties’ request, the superior court then entered a
    partial final judgment related to the two issues (valuation date and
    ownership of the improvements). See Ariz. R. Civ. P. 54(b). Landowners
    timely appealed, and Southwest Transmission and Mohave Electric timely
    cross-appealed.
    ¶10            This court initially dismissed the appeal for lack of appellate
    jurisdiction under A.R.S. § 12-2101(A)(1) (appeal from final judgment),
    noting that the judgment was not subject to Rule 54(b) certification because
    it did not resolve any claims of any of the parties. See Ariz. R. Civ. P. 54(b);
    Musa v. Adrian, 
    130 Ariz. 311
    , 313 (1981). The Arizona Supreme Court then
    granted Landowners’ petition for review and remanded to this court to
    consider whether appellate jurisdiction existed under A.R.S. § 12-
    2101(A)(6). See Bilke v. State, 
    206 Ariz. 462
    , 466, ¶ 16 (2003).
    4
    AZ ELECTRIC POWER v. DJL 2007, et al.
    Opinion of the Court
    ¶11            A.R.S. § 12-2101(A)(6) authorizes appeal “[f]rom an
    interlocutory judgment that determines the rights of the parties and directs
    an accounting or other proceeding to determine the amount of the
    recovery.” But a right to appeal from such an interlocutory judgment is not
    automatic; instead, the superior court has discretion to determine whether
    an immediate appeal should be available. See Bilke, 
    206 Ariz. at
    466–67,
    ¶¶ 20–21. To do so, the superior court must make two distinct findings:
    first, whether the ruling as to the rights of the parties is final, and second,
    whether amount of recovery is indeed the only issue remaining. See 
    id.
     at
    467–68, ¶¶ 21, 23, 28; see also Ciena Capital Funding, LLC v. Krieg’s, Inc., 
    242 Ariz. 212
    , 215–16, ¶ 7 (App. 2017). Although the superior court’s Rule 54(b)
    certification satisfied the finality prong, see Bilke, 
    206 Ariz. at 467, ¶ 23
    , the
    parties had not requested and the superior court had not made the requisite
    discretionary finding “expressly direct[ing] that the only issue remaining is
    the amount of recovery.” See 
    id. at 468, ¶ 28
    . Accordingly, we stayed the
    appeal and revested the superior court with jurisdiction to determine
    whether (A)(6) certification was appropriate. The superior court did so, and
    we now have jurisdiction under A.R.S. § 12-2101(A)(6).
    DISCUSSION
    I.     Valuation Date.
    ¶12            The superior court ruled that Southwest Transmission lacked
    authority to condemn property simply by occupying it (a “taking by
    occupation”), so Southwest Transmission and Mohave Electric were
    holdover tenants between expiration of the BLM right-of-way grant and the
    date of the taking, and Landowners would be entitled to rental damages for
    that period. The court further reasoned that Southwest Transmission
    became an agent of the state for condemnation purposes when it filed the
    direct condemnation action, see A.R.S. § 12-1115(C), at which point the
    taking occurred because the government (through Southwest
    Transmission) was in actual physical possession of the property.
    ¶13           Although the parties agree that the valuation date must reflect
    the date of the taking, both sides challenge the court’s determination of the
    valuation date. Southwest Transmission (joined by Mohave Electric)
    asserts that the taking occurred by occupation immediately following
    expiration of the BLM right-of-way grant. Landowners counter that,
    because Southwest Transmission is exercising eminent domain power as a
    non-municipal corporation, the taking cannot occur until a jury determines
    and Southwest Transmission tenders payment of just compensation.
    Neither side challenges the superior court’s ruling as to holdover tenancy
    5
    AZ ELECTRIC POWER v. DJL 2007, et al.
    Opinion of the Court
    pending the date of taking (regardless of when it occurred) or Landowners’
    entitlement to rental damages, although accepting Southwest
    Transmission’s proposed taking date would in effect moot these issues. We
    review the superior court’s ruling de novo as a pure question of law. See
    League of Ariz. Cities & Towns v. Brewer, 
    213 Ariz. 557
    , 559, ¶ 7 (2006).
    ¶14             Both the United States and the Arizona Constitutions
    proscribe the taking of private property without payment of just
    compensation. U.S. Const. amend. V; Ariz. Const. art. 2, § 17 (“No private
    property shall be taken or damaged for public or private use without just
    compensation having first been made . . . .”). To satisfy the constitutional
    requirement of providing “just compensation,” the property condemned
    must be valued as of the date of the constitutional taking. See Kirby Forest
    Indus., Inc. v. United States, 
    467 U.S. 1
    , 9–10 (1984); Calmat of Ariz. v. State ex
    rel. Miller, 
    176 Ariz. 190
    , 193–95 (1993).
    ¶15           By statute, Arizona has designated the date of the summons
    in a condemnation action as the presumptive valuation date. A.R.S. § 12-
    1123(A). When the summons and the taking occur close in time, the
    summons date “establishes a practical and uniform date for valuation
    purposes that is presumptively reasonable.” City of Scottsdale v. CGP-
    Aberdeen, L.L.C., 
    217 Ariz. 626
    , 634, ¶ 36 (App. 2008); see also Calmat, 
    176 Ariz. at
    193–94. But if the summons is remote in time from the taking and
    the value of the property has changed in the interim, the value of the
    property on the date of the taking must control. CGP-Aberdeen, 217 Ariz. at
    629, 634, ¶¶ 10, 36.
    ¶16           Here, Southwest Transmission continued to occupy the
    property after the expiration of its right to do so under the BLM right-of-
    way grant in May 2011. If a governmental entity had so occupied
    Landowners’ property, that occupation would have constituted a taking,
    subject to an owner’s claim for inverse condemnation. See In re Forsstrom,
    
    44 Ariz. 472
    , 481, 488 (1934) (describing a “taking” as “[a]ny substantial
    interference” with an owner’s property rights), overruled in part on other
    grounds by Mohave County v. Chamberlin, 
    78 Ariz. 422
    , 430 (1955), and State ex
    rel. Morrison v. Thelberg, 
    87 Ariz. 318
    , 324 (1960); see also A Tumbling-T
    Ranches v. Flood Control Dist. of Maricopa Cty., 
    222 Ariz. 515
    , 525, ¶ 18 (App.
    2009). But the Arizona Constitution imposes additional limitations on the
    exercise of eminent domain by a private corporation (like Southwest
    Transmission) that preclude a taking by occupation. In particular, as
    explained below, a private corporation may not effect a taking until there
    has been a jury determination of damages and full compensation has been
    paid to the property owner.
    6
    AZ ELECTRIC POWER v. DJL 2007, et al.
    Opinion of the Court
    ¶17           As relevant here, the Arizona Constitution’s eminent domain
    provision includes two operative clauses:
    [(1)] No private property shall be taken or damaged for public
    or private use without just compensation having first been
    made, paid into court for the owner . . . ,
    [(2)] and no right of way shall be appropriated to the use of
    any corporation other than municipal, until full compensation
    therefor be first made in money, or ascertained and paid into
    court for the owner, . . . which compensation shall be
    ascertained by a jury, unless a jury be waived . . . .
    Ariz. Const. art. 2, § 17 (line break added).2 The Arizona Supreme Court
    described the interplay of these two clauses in Hughes Tool Co. v. Superior
    Court: the first—the general clause—requires just compensation in all
    takings, whereas the second—the right-of-way clause—“imposes further
    limitations and conditions on the acquisition of rights of way by private
    corporations through the exercise of powers of eminent domain.” 
    91 Ariz. 154
    , 156 (1962).
    ¶18           In Hughes Tool, a private corporation with eminent domain
    authority filed a direct condemnation action to condemn power line rights
    of way. 
    Id. at 155
    . The superior court issued an order under A.R.S. § 12-
    1116 permitting immediate possession and use before conclusion of the
    2      In full, the general and right-of-way clauses read:
    No private property shall be taken or damaged for public or
    private use without just compensation having first been
    made, paid into court for the owner, secured by bond as may
    be fixed by the court, or paid into the state treasury for the
    owner on such terms and conditions as the legislature may
    provide, and no right of way shall be appropriated to the use
    of any corporation other than municipal, until full
    compensation therefor be first made in money, or ascertained
    and paid into court for the owner, irrespective of any benefit
    from any improvement proposed by such corporation, which
    compensation shall be ascertained by a jury, unless a jury be
    waived as in other civil cases in courts of record, in the
    manner prescribed by law.
    Ariz. Const. art. 2, § 17.
    7
    AZ ELECTRIC POWER v. DJL 2007, et al.
    Opinion of the Court
    condemnation proceedings, and the property owner sought review. Id. at
    155–56. The Arizona Supreme Court directed the superior court to vacate
    the order for immediate possession. Id. at 160. The court highlighted the
    distinction between the requirements of the general clause, which
    authorizes a taking once just compensation is “paid into court for the
    owner,” as compared to the right-of-way clause, which requires
    compensation first be “ascertained and paid into court for the owner.” Ariz.
    Const. art. 2, § 17 (emphasis added); Hughes Tool, 
    91 Ariz. at 158
    . The
    supreme court thus held that the right-of-way clause required “an advance
    jury determination of damages (unless the jury be waived) before a
    corporation other than municipal takes possession of property through
    exercise of the power of eminent domain.” Hughes Tool, 
    91 Ariz. at 160
    .
    ¶19           In Hughes Tool, that meant that a private corporation could not
    receive a § 12-1116 order for immediate possession, because that would
    allow a private corporation to take possession before a jury determined
    damages. Id. Here, the Hughes Tool holding means that a private
    corporation exercising statutory eminent domain authority is not
    constitutionally authorized to effect a taking until after trial and payment;
    it cannot take property in a constitutional sense simply by occupation.
    Thus, Southwest Transmission’s ongoing use of the property was as a hold-
    over tenant and not as a condemnor in possession.
    ¶20           Southwest Transmission argues, however, that Hughes Tool
    only applies to § 12-1116 orders for immediate possession and does not
    apply where, as here, the private condemnor is already occupying the
    property subject to condemnation. Although Hughes Tool arose from an
    order for immediate possession, its reasoning and holding apply generally
    to a private corporation seeking to “take[] possession of property through
    exercise of the power of eminent domain,” not just to a single manner in
    which a private corporation might do so. See id. at 156, 160. More
    importantly, the constitutional right-of-way clause itself draws no such
    distinction. See Ariz. Const. art. 2, § 17.
    ¶21           The authority on which Southwest Transmission relies does
    not support the premise that a private corporation with the power of
    eminent domain can effect a taking by occupation. All of the Arizona case
    law on which Southwest Transmission relies for general principles of taking
    by occupation involve takings by governmental entities, not private
    corporations. See, e.g., Calmat, 
    176 Ariz. 190
    ; Gardiner v. Henderson, 
    103 Ariz. 420
     (1968); State v. Leeson, 
    84 Ariz. 44
     (1958); In re Forsstrom, 
    44 Ariz. 472
    ; A
    Tumbling-T Ranches, 
    222 Ariz. 515
    . And all the out-of-jurisdiction cases
    specific to condemnation by private entities on which Southwest
    8
    AZ ELECTRIC POWER v. DJL 2007, et al.
    Opinion of the Court
    Transmission relies arose in jurisdictions that do not have constitutional
    limitations analogous to Arizona’s Article 2, § 17 right-of-way clause. See,
    e.g., Loretto v. Teleprompter Manhattan CATV Corp., 
    458 U.S. 419
     (1982) (U.S.
    Const. amend. V; N.Y. Const. art. 1, § 7); Windrow v. Middle Tenn. Elec.
    Membership Corp., 
    376 S.W.3d 733
    , 737–38 (Tenn. Ct. App. 2012) (Tenn.
    Const. art. 1, § 21); see also, e.g., Cantu v. Pac. Gas & Elec. Co., 
    234 Cal. Rptr. 365
     (Ct. App. 1987) (Cal. Const. art. 1, § 19).
    ¶22          The closest thing to contrary authority in Arizona case law
    cited by Southwest Transmission appears in a single reference in Gardiner:
    The immediate taking of possession of property by a
    municipality is a taking of property. Possession is certainly
    one of the greatest attributes of ownership of property. The
    possessor exercises dominion over the property, and a
    condemnor, be it municipality or private corporation thereafter
    denies the owner of its usage, its rental value, and its
    enjoyment.
    
    103 Ariz. at 424
     (emphasis added). But Gardiner itself involved a taking by
    a municipality, not a private corporation. 
    Id. at 421
    . And Gardiner
    construed the requirements for taking by means of an order for immediate
    possession under § 12-1116, which Hughes Tool had already ruled was not
    available to a private corporation. See 
    103 Ariz. at 423, 425
    . In short,
    Gardiner did not consider the right-of-way clause’s restrictions on taking by
    a private corporation. Although this language would support Southwest
    Transmission’s position if read broadly, Gardiner’s dicta cannot override the
    express language of the constitutional right-of-way clause or the express
    holding of Hughes Tool.
    ¶23          For the same reasons, the superior court’s ruling that the
    taking occurred on the date of the summons also fails. That conclusion
    made practical sense under the circumstances of this case: it recognized that
    Southwest Transmission could not unilaterally exercise eminent domain by
    occupation, but also that Southwest Transmission was in fact in possession
    when it began to exercise its eminent domain power properly by filing the
    direct condemnation action. But the right-of-way clause as construed in
    Hughes Tool forecloses this result. As a private corporation, Southwest
    Transmission cannot take possession of property as a condemnor until after
    trial and payment of just compensation. See Hughes Tool, 
    91 Ariz. at 160
    . To
    hold otherwise would, in effect, allow the result that Hughes Tool reversed:
    a private corporation could achieve the same result as an order for
    9
    AZ ELECTRIC POWER v. DJL 2007, et al.
    Opinion of the Court
    immediate possession (even though § 12-1116 is unavailable) by simply
    entering the property during the pendency of the condemnation action.
    ¶24            Southwest Transmission’s other arguments are similarly
    unavailing. It suggests that Landowners could have formalized the taking
    by filing an inverse condemnation action immediately after expiration of
    the BLM right-of-way grant (locking in that date as the date of the taking),
    so the date of the taking should not be controlled by Landowners’ decision
    not to do so. But this argument assumes that the taking occurred when
    Southwest Transmission outstayed the BLM right-of-way grant, which the
    right-of-way clause forbids. Moreover, Southwest Transmission itself
    could have eliminated this delay by pursuing a direct condemnation claim
    years earlier.
    ¶25            Southwest Transmission further argues that using the end of
    the condemnation action as the valuation date provides an incentive for
    delay, as one party or the other (depending on whether property values
    were rising or falling) would wish to delay resolution for economic gain.
    But such policy concerns cannot override the constitutional limitations on
    a private corporation’s condemnation authority. And the argument ignores
    that, in straight-condemnation proceedings under federal law, the date of
    the taking is similarly the date the government tenders payment after final
    judgment on just compensation. See, e.g., Kirby Forest, 
    467 U.S. at
    3–4, 11–
    12. In any event, the superior court has other tools to ensure the efficient
    processing of cases before it and, in appropriate circumstances, to sanction
    a party that unreasonably delays the proceeding. See, e.g., A.R.S. § 12-
    349(A)(3); Fenton v. Howard, 
    118 Ariz. 119
    , 121 (1978) (“Every court has
    inherent power to do those things which are necessary for the efficient
    exercise of its jurisdiction.”); State v. Superior Court, 
    39 Ariz. 242
    , 247–48
    (1931) (same); see also Ariz. R. Civ. P. 1 (directing that the civil rules “be
    construed, administered, and employed by the court and the parties to
    secure the just, speedy, and inexpensive determination of every action and
    proceeding”).
    ¶26           Although Southwest Transmission continued to possess and
    use the transmission lines after the BLM right-of-way grant expired, it did
    not—and it constitutionally could not—do so in the capacity of a
    condemnor. Instead, Southwest Transmission simply became a hold-over
    tenant on that date, and under the right-of-way clause of Article 2, § 17,
    could not take Landowners’ property in a constitutional sense until after
    trial and payment. Accordingly, the value of just compensation must reflect
    the value at that time.
    10
    AZ ELECTRIC POWER v. DJL 2007, et al.
    Opinion of the Court
    ¶27           We thus reverse the superior court’s ruling as to valuation
    date as described in this decision. As neither side challenged the court’s
    ruling as to the status of Southwest Transmission and Mohave Electric as
    holdover tenants from expiration of the BLM right-of-way grant through
    the date of the taking and Landowners’ entitlement to rental damages as
    compensation for the period, the balance of the ruling stands.
    II.    Ownership of the Electric Transmission Lines and Structures.
    ¶28            The superior court granted Southwest Transmission’s motion
    for partial summary judgment (joined by Mohave Electric) on ownership of
    the electric transmission lines and structures. The court ruled as a matter
    of law that Southwest Transmission and Mohave Electric originally owned
    the improvements and, under the undisputed factual circumstances
    presented, title had never passed to Landowners. Accordingly, the value
    of the improvements would not be included when calculating just
    compensation for the taking. Landowners challenge this ruling, urging that
    Southwest Transmission and Mohave Electric became trespassers and thus
    forfeited the improvements when they neither paid rent nor removed the
    lines after expiration of the BLM right-of-way grant, or alternatively, that
    disputed facts as to the reasonableness of Southwest Transmission’s
    conduct preclude summary judgment.
    ¶29            Summary judgment is appropriate if there are no genuine
    issues of material fact and, based on those undisputed facts, the moving
    party is entitled to judgment as a matter of law. Ariz. R. Civ. P. 56(a); Orme
    Sch. v. Reeves, 
    166 Ariz. 301
    , 305 (1990). We review the grant of summary
    judgment de novo, viewing the facts in the light most favorable to the party
    against whom judgment was entered. Wells Fargo Bank, N.A. v. Allen, 
    231 Ariz. 209
    , 213, ¶ 14 (App. 2012).
    ¶30           The undisputed facts establish that Southwest Transmission
    and Mohave Electric own the transmission lines and structures. Southwest
    Transmission built the lines and structures while lawfully occupying the
    property pursuant to the BLM right-of-way grant. And the terms of that
    grant contemplated that Southwest Transmission would retain these
    improvements. The grant incorporated regulations including 
    43 C.F.R. § 2807.19
    (a), which required the grantee to remove all facilities (defined as
    improvements or structures) after the grant expired. See also 
    43 C.F.R. § 2801.5
    (b) (defining “Facility”). By requiring removal, the agreement made
    clear the parties’ intent that Southwest Transmission, not the property
    owner, owned the improvements.
    11
    AZ ELECTRIC POWER v. DJL 2007, et al.
    Opinion of the Court
    ¶31            Because Southwest Transmission retained ownership of the
    lines and structures, even the authorities on which Landowners rely
    support the notion that Southwest Transmission need not pay
    compensation for these pre-condemnation improvements. In State v. Teller
    Native Corp., for instance, the Supreme Court of Alaska acknowledged the
    general rule that a condemnor need not pay for its own pre-condemnation
    improvements unless those improvements were made under a contract
    giving the landowner the right to keep them. 
    904 P.2d 847
    , 850 (Alaska
    1995). Because the condemnor in that case had specifically agreed to build
    certain improvements (an airport, taxiway and runway, roadway, and
    parking area) as partial consideration for the lease and to leave them for the
    landowner’s benefit after termination of the lease, the condemnor would
    have to pay the landowner compensation for the improvements. 
    Id.
     at 849–
    50, 850–51; see also United States v. Five Parcels of Land, 
    180 F.2d 75
    , 76–77 (5th
    Cir. 1950) (distinguishing improvements the condemnor/prior-lessee had
    a right to remove (no compensation owed) from those improvements the
    lease contemplated would revert to the landowners after termination
    (compensation required)). Here, in contrast, the fact that the grant allowed
    and required Southwest Transmission to remove the improvements means
    it owned the improvements and need not pay compensation for those
    improvements upon condemnation.
    ¶32            Landowners contend, however, that Southwest Transmission
    and Mohave Electric became trespassers after expiration of the BLM right-
    of-way grant and, by failing to pay rent or promptly remove the
    improvements, forfeited their ownership of the transmission lines and
    structures. See Russell v. Golden Rule Min. Co., 
    63 Ariz. 11
    , 29–30 (1945)
    (noting common law rule regarding abandonment of right to remove
    fixtures by failing to remove such fixtures within a reasonable time). But
    Landowners did not demand that Southwest Transmission remove the
    improvements after the right-of-way grant expired. And the rule
    Landowners propose simply does not apply in the same way to an entity
    with eminent domain authority that constructs improvements to facilitate
    the public use for which it has the authority to condemn the land, and then
    in fact exercises its power to condemn the property. See, e.g., Anderson-Tully
    Co. v. United States, 
    189 F.2d 192
    , 197 (5th Cir. 1951); see also, e.g., Etalook v.
    Exxon Pipeline Co., 
    831 F.2d 1440
    , 1444 (9th Cir. 1987); Ill. Cent. R.R. v. Le
    Blanc, 
    21 So. 760
    , 762 (Miss. 1897) (collecting cases); Seattle & Mont. Ry. v.
    Corbett, 
    60 P. 127
    , 128 (Wash. 1900). Moreover, the superior court’s prior
    ruling that Southwest Transmission and Mohave Electric were holdover
    tenants between expiration of the BLM right-of-way grant and the date of
    the taking and that Landowners are entitled to rental damages for that
    period ensures that Landowners will receive full compensation for the
    12
    AZ ELECTRIC POWER v. DJL 2007, et al.
    Opinion of the Court
    period over which they now fault Southwest Transmission for failing to pay
    rent. See Etalook, 
    831 F.2d at 1444
    .
    ¶33          In short, Southwest Transmission and Mohave Electric
    retained ownership of the improvements after expiration of the grant, and
    we thus affirm the superior court’s ruling as to ownership of the
    transmission lines and structures.
    III.   Attorney’s Fees on Appeal.
    ¶34           Landowners request an award of attorney’s fees on appeal
    under A.R.S. § 12-341.01. Without addressing whether Landowners’
    counterclaim for rental damages renders this condemnation case an “action
    arising out of a contract” for purposes of § 12-341.01, we decline to award
    attorney’s fees at this time, without prejudice to a request for fees in the
    superior court if appropriate on remand.
    CONCLUSION
    ¶35          We reverse the superior court’s ruling as to valuation date,
    affirm as to holdover tenancy from expiration of the BLM right-of-way
    grant through valuation date and Landowners’ right to rental damages for
    that period, affirm as to ownership of improvements, and remand for
    valuation proceedings consistent with this decision.
    AMY M. WOOD • Clerk of the Court
    FILED: AA
    13