Magness v. Arizona Registrar of Contractors , 234 Ariz. 428 ( 2014 )


Menu:
  •                                 IN THE
    ARIZONA COURT OF APPEALS
    DIVISION ONE
    SHELLEY MAGNESS and COLORADO
    STATE BANK & TRUST COMPANY, N.A.,
    Co-Trustees of The Shelley Magness Trust
    UDA 6/25/2000, Plaintiff/Appellee,
    v.
    ARIZONA REGISTRAR OF CONTRACTORS, Defendant/Appellant.
    No. 1 CA-CV 13-0184
    FILED 4-8-2014
    Appeal from the Superior Court in Maricopa County
    No. CV2011-056468
    The Honorable John R. Doody, Commissioner
    VACATED AND REMANDED
    COUNSEL
    Davidson, Lester & Kaffer, PLLC, Scottsdale
    By Frederick E. Davidson, Brian G. Lester, Chad R. Kaffer
    Counsel for Plaintiff/Appellee
    Arizona Attorney General’s Office, Phoenix
    By Michael Raine
    Counsel for Defendant/Appellant
    MAGNESS v. ARIZ. REGISTRAR OF CONTRACTORS
    Opinion of the Court
    OPINION
    Judge Michael J. Brown delivered the Opinion of the Court, in which
    Acting Presiding Judge Margaret H. Downie and Chief Judge Diane M.
    Johnsen joined.
    B R O W N, Judge:
    ¶1           The Arizona Registrar of Contractors (“ROC”) appeals the
    superior court’s order directing the ROC to issue payment from the
    Residential Contractors’ Recovery Fund (“the Fund”) to Shelley Magness
    and Colorado State Bank & Trust Company, as co-trustees of the Shelley
    Magness Trust (“Magness”). For reasons that follow, we vacate the
    superior court’s order and remand for further proceedings.
    BACKGROUND
    ¶2           In September 2008, Magness and Lendo Management LLC
    (“Lendo”) entered a contract for Lendo to construct a “bath addition” to a
    house owned by Magness for the sum of $49,375. 1 The contract stated
    “that additional work could be undertaken in accordance with Change
    Orders.” Two months later, the parties entered a second contract that
    provided for additional remodeling work to be performed for the sum of
    $38,899 and included the same change order clause as the first contract.
    ¶3           Work on the project began in October 2008, and continued
    through December 2009.        During construction, Magness approved
    numerous change orders. By late December 2009, Magness had paid
    Lendo $366,123.27. At that point, Lendo stopped working even though all
    the contracted work was not yet completed. Magness unsuccessfully
    attempted to contact Lendo to seek redress for the uncompleted work and
    eventually paid other contractors to finish the project.
    ¶4            In April 2010, Magness filed a complaint against Lendo with
    the ROC, which issued a citation naming Lendo. When Lendo failed to
    file a response, an Administrative Law Judge (“ALJ”) entered a decision
    1      It is undisputed that Lendo did not become a licensed contractor
    until March 4, 2009.
    2
    MAGNESS v. ARIZ. REGISTRAR OF CONTRACTORS
    Opinion of the Court
    and order adopting the allegations of the complaint and revoking Lendo’s
    license.
    ¶5           In November 2011, Magness filed a complaint against Lendo
    in superior court alleging numerous claims, including breach of contract,
    unjust enrichment, and conversion. Magness also named the ROC as a
    defendant, alleging it was entitled to recover from the Fund based on
    claimed damages of $17,461.45 ($8,619.40 for unperformed work, $1,030.00
    for reimbursement of charges paid to Lendo for completion of the
    unperformed work, and $7,812.05 for reimbursement of funds paid to
    Lendo that should have been paid to subcontractors and suppliers).
    ¶6            In its answer, the ROC responded it was “without sufficient
    knowledge to form a belief as to whether [Magness] is entitled to recovery
    from the Fund[.]” The ROC also maintained that any award from the
    Fund is statutorily limited to “the actual damages suffered by the claimant
    as a direct result of the contractor’s violations” and “[o]nly those persons
    injured as defined by [Arizona Revised Statute (“A.R.S.”) section] 32-1131
    are eligible for recovery from the Fund.” The ROC requested that the
    court deny Magness any recovery from the Fund unless Magness could
    demonstrate eligibility under A.R.S. §§ 32-1131 and -1132(A) and
    compliance with A.R.S. § 32-1136.
    ¶7            Lendo did not answer as required by Arizona Rule of Civil
    Procedure (Rule) 12(a)(1)(A) and Magness filed an application for entry of
    default and motion for entry of judgment by default without a hearing.
    The superior court entered a default judgment against Lendo. As relevant
    to the Fund claim, the court awarded Magness damages against Lendo in
    the amount of $17,461.45. In response, the ROC filed a notice stating it did
    not object to the entry of default judgment against Lendo, but that it did
    “not waive any objections it has to a payout from the [F]und” and
    “reserve[d] the right to object to an order directing payment from the
    Fund for any other applicable reasons,” citing A.R.S. §§ 32-1131 -1140.
    ¶8             Magness then filed an application for an order directing
    payment from the Fund. The ROC objected, asserting Magness’s
    application did not satisfy statutory requirements because Magness failed
    to (1) establish “eligibility for payment” as a “person injured” because the
    house was owned by a trust; (2) demonstrate that Lendo held a
    contractor’s license at the relevant time period; or (3) limit the claim to
    “actual damages.” The ROC requested that, at a “minimum,” the court
    “order a hearing requiring [Magness] to prove these matters.” The
    superior court entered an unsigned minute entry granting Magness
    3
    MAGNESS v. ARIZ. REGISTRAR OF CONTRACTORS
    Opinion of the Court
    recovery from the Fund in the amount of $14,067.39 ($17,461.45 less
    $3,394.06 that Magness had recovered from Lendo’s contractor’s bond).
    The ROC moved for reconsideration, requesting an evidentiary hearing to
    resolve factual issues relevant to Magness’s eligibility to recover from the
    Fund. The superior court summarily denied the ROC’s motion and
    entered a signed order directing payment from the Fund. The ROC timely
    appealed.
    DISCUSSION
    ¶9           The ROC argues the superior court erred by entering an
    order of payment because Magness failed to demonstrate eligibility, under
    the relevant statutes, to recover the awarded damages from the Fund.
    Additionally, the ROC contends it was entitled to a hearing before such an
    order of payment could be entered.
    ¶10           As a preliminary matter, we reject Magness’s argument that
    because it obtained a default judgment against Lendo awarding damages
    in the amount of $17,461.45 on its Fund claim, the ROC’s challenges to
    Magness’s eligibility to recover from the Fund are precluded. As
    expressly stated in Rule 55(a), default may be entered only against a party
    who has failed to plead or otherwise defend. Here, the ROC filed an
    answer challenging Magness’s eligibility to recover from the Fund before
    an application for default was filed. Therefore, no entry of default against
    the ROC could have occurred and the default judgment against Lendo did
    not eliminate the ROC’s right to object to the subsequent application for
    payment from the Fund. 2
    ¶11        Under the governing statutes (A.R.S. §§ 32-1132, -1136),
    however, a party need not secure a judgment against the ROC as a
    2      To the extent Magness argues that the ALJ’s decision in the license
    revocation proceeding bars the ROC’s challenges on appeal, we likewise
    reject that claim. The ALJ’s order adopted Magness’s allegations that
    Lendo violated the parties’ contracts by failing to perform all of the work
    specified. But the ALJ’s order did not establish that Magness was entitled
    to recover from the Fund; instead, the order expressly noted that Magness
    would not be eligible to recover from the Fund if it denied the contractor
    the opportunity to complete the work. Furthermore, Magness did not
    seek payment from the Fund based on the ALJ’s order as provided for in
    A.R.S. § 32-1154 (setting forth the administrative remedy for collecting
    from the Fund).
    4
    MAGNESS v. ARIZ. REGISTRAR OF CONTRACTORS
    Opinion of the Court
    prerequisite to recovering from the Fund. Section 32-1132(A) sets forth
    the overall eligibility requirements:
    The residential contractors’ recovery fund is established, to
    be administered by the registrar, from which any person
    injured by an act, representation, transaction or conduct of a
    residential contractor licensed pursuant to this chapter that
    is in violation of this chapter . . . may be awarded . . . an
    amount of not more than thirty thousand dollars for
    damages sustained by the act, representation, transaction or
    conduct. An award from the fund is limited to the actual
    damages suffered by the claimant as a direct result of the
    contractor’s violation but shall not exceed an amount
    necessary to complete or repair a residential structure. . . .
    An award from the fund shall not be available to persons
    injured by an act, representation, transaction or conduct of a
    residential contractor who was not licensed pursuant to this
    chapter or whose license was in an inactive status, expired,
    cancelled, revoked, suspended or not issued at the time of
    the contract.
    After obtaining a judgment against a residential contractor, the “injured
    person” may apply to the superior court for an order directing payment
    from the Fund. A.R.S. § 32-1136(B). If the injured person has given
    twenty days’ notice to the ROC, “the court may direct payment out of the
    fund either on receipt of a consent to payment signed on behalf of the
    registrar or, in the absence of any written consent, after the notice
    period[.]” Id. If the ROC files a timely written objection with the court,
    however, “the court shall not direct payment from the fund without
    affording the registrar a reasonable opportunity to present and support its
    objections.” Id. (emphasis added). Thus, § 32-1136(B) establishes the
    ROC’s procedural rights—notice and an opportunity to be heard in a
    meaningful manner.
    ¶12           In this case, it is undisputed that Magness timely notified the
    ROC that it was applying for court-ordered payment from the Fund. In
    response, the ROC filed a timely written objection to Magness’s
    application for payment, arguing Magness had failed to demonstrate its
    eligibility. Citing § 32-1131, which defines “person injured,” in relevant
    part, as “any owner of residential real property . . . which is actually
    occupied or intended to be occupied by the owner as a residence,” the
    ROC argued that Magness, as a trustee, did not qualify as both the
    requisite owner and occupier of the property. Moreover, because it is
    5
    MAGNESS v. ARIZ. REGISTRAR OF CONTRACTORS
    Opinion of the Court
    undisputed that Lendo was not a licensed contractor at the time Magness
    and Lendo entered the first and second contracts, the ROC argued Lendo
    was not a licensed contractor “at the time the parties enter[ed] into the
    contract” under § 32-1132(A). In addition, accepting the allegations of
    Magness’s complaint as true, the ROC asserted that Magness’s requested
    damages ($14,067.39) exceeded those permitted by statute because
    Magness paid other contractors only $8,619.40 to complete the contracted
    work. Finally, the ROC argued that § 32-1136(B) required the superior
    court to hold a hearing to address the ROC’s written objections before
    ordering payment from the Fund.
    ¶13           Magness countered that Shelley Magness, as the sole
    beneficiary of the Trust, qualified as a “person injured” under the statute.
    Magness did not dispute that Lendo was unlicensed at the time the first
    and second contracts were formed, but maintained that each of the
    numerous subsequent change orders was a contract for purposes of § 32-
    1132 and noted that many of them were entered after Lendo obtained a
    contractor’s license. Magness also claimed that the ROC could not
    challenge the amount to be recovered from the Fund because the award of
    damages was established by the superior court’s default judgment.
    Finally, Magness argued that a hearing was not statutorily required and
    the ROC’s request for a hearing should be denied.
    ¶14           The superior court implicitly denied the ROC’s request for a
    hearing and “grant[ed] recovery to Magness in the amount of $14,067.39”
    without expressly addressing any of the ROC’s objections. Thus, as a
    threshold matter, we consider whether the superior court “afford[ed] the
    registrar a reasonable opportunity to present and support its objections.”
    A.R.S. § 32-1136(B).
    ¶15           “The interpretation of a statute is a question of law that we
    review de novo.” Bonito Partners, L.L.C. v. City of Flagstaff, 
    229 Ariz. 75
    , 83,
    ¶ 30, 
    270 P.3d 902
    , 910 (App. 2012). “We interpret statutes to give effect to
    the legislature’s intent, looking first to the statutory language itself.” Baker
    v. Univ. Physicians Healthcare, 
    231 Ariz. 379
    , 383, ¶ 8, 
    296 P.3d 42
    , 46 (2013).
    We strive to give effect to each word or phrase of the statute. Guzman v.
    Guzman, 
    175 Ariz. 183
    , 187, 
    854 P.2d 1169
    , 1173 (App. 1993). When
    construing a statute, “we examine its individual provisions in the context
    of the entire statute to achieve a consistent interpretation.” State v.
    Gaynor-Fonte, 
    211 Ariz. 516
    , 518, ¶ 13, 
    123 P.3d 1153
    , 1155 (App. 2005)
    (citation omitted). “Indeed, if statutes relate to the same subject and are
    thus in pari materia, they should be construed together . . . as though they
    constituted one law.” Bonito, 229 Ariz. at 83, ¶ 30, 
    270 P.3d at 910
    .
    6
    MAGNESS v. ARIZ. REGISTRAR OF CONTRACTORS
    Opinion of the Court
    ¶16           Section 32-1136, which sets forth the process for obtaining
    payment from the Fund, expressly states that recovery is “subject to the
    limitations stated in this article.” Considered in context with the other
    statutes governing Fund eligibility, § 32-1136 necessarily includes the
    threshold eligibility requirements set forth in § 32-1132(A), which, if not
    met, bar recovery from the Fund. In addition, § 32-1136 (D) provides:
    The court shall proceed on an application in a summary
    manner and, on the hearing, the injured person is required to
    show that he:
    (1) Has given notice as required [twenty day notice to the
    registrar].
    (2) Has obtained a judgment which has become final . . .
    stating the amount and the amount owing at the date of
    the application.
    (3) Has proceeded against any existing bond covering the
    residential contractor and has not collected upon such
    bond an amount of thirty thousand or more [except when
    the award is made pursuant to an administrative
    proceeding].
    (4) Is not aware of any personal or real property or other
    assets of the debtor which can be applied in satisfaction
    of the judgment.
    (Emphasis added.) By its plain language, subsection D contemplates a
    hearing when the ROC has objected to an application for payment.
    Nonetheless, Magness argues that because none of the requirements
    outlined in subsection D is contested in this case, no hearing was
    necessary. We do not construe the scope of the hearing referenced in
    § 32-1136(D) so narrowly. The statute establishes a list of minimum
    requirements the injured person must prove. When, as here, the ROC
    challenges an applicant’s lack of compliance with requirements set forth
    elsewhere in the governing statutes, the applicant must also demonstrate
    that those statutory prerequisites have been satisfied.
    ¶17          This construction of § 32-1136(D) gives effect to each of the
    relevant provisions of the statutory scheme governing eligibility for
    payment from the Fund. See Guzman, 
    175 Ariz. at 187
    , 
    854 P.2d at 1173
     (“It
    is a cardinal rule of construction that statutory provisions must be
    considered in the context of the entire statute and consideration must be
    7
    MAGNESS v. ARIZ. REGISTRAR OF CONTRACTORS
    Opinion of the Court
    given to all of the statute’s provisions to determine the legislative intent
    manifested by the entire act.”). Notwithstanding the four conditions listed
    in subsection D, subsection E provides that the “court shall make an order
    directed to the registrar requiring payment from the fund of whatever sum
    it finds to be payable on the claim, in accordance with this section, if the court
    is satisfied on the hearing of the truth of all matters required to be shown
    by the injured person by subsection D of this section.” (Emphasis added.)
    The phrase “whatever sum it finds to be payable on the claim” denotes the
    court’s discretion to evaluate and determine the amount due under the
    statutes. In addition to establishing “actual damages,” a person seeking
    payment from the Fund must satisfy other eligibility requirements that are
    not included in subsection D, such as (1) proving “person injured” status
    under § 32-1131(3) and (2) establishing that the contractor was properly
    licensed at the time of the contract under § 32-1132(A).
    ¶18           In sum, an applicant seeking recovery from the Fund
    through a civil remedy must obtain a judgment against the contractor and
    meet all of the remaining statutory eligibility requirements. Thus, we are
    not persuaded by Magness’s argument that the scope of the hearing
    referenced in § 32-1136(D) is strictly limited to the four requirements of
    that section because doing so would nullify the eligibility requirements of
    § 32-1132 and undermine a key purpose of the Fund, namely, to
    compensate homeowners who have been harmed by licensed contractors.
    See Koss Corp. v. Am. Exp. Co., 
    233 Ariz. 74
    , 79, ¶ 12, 
    309 P.3d 898
    , 903
    (App. 2013) (noting that statutes should not be construed in a manner that
    would lead to an absurd result, conflict with legislative intent or “be
    contrary to the rest of the statutory scheme”). Similarly, Magness’s
    reading of the statute would deprive the ROC of its statutory right to
    present and support its objections and would improperly relieve an
    “injured person” of the burden of demonstrating eligibility for payment
    from the Fund. We therefore conclude the superior court erred in
    summarily granting Magness’s application for payment. 3
    3      Based on our resolution of the hearing issue, we express no opinion
    regarding the merits of the ROC’s challenges to Magness’s eligibility to
    recover from the Fund and remand those matters for consideration by the
    superior court in the first instance. On remand, the superior court is in the
    best position to determine the scope of the hearing needed to determine
    whether Magness has met its burden of establishing eligibility for
    payment from the Fund, recognizing the need to consider Magness’s
    application in a “summary manner.” See A.R.S. § 32-1136 (D).
    8
    MAGNESS v. ARIZ. REGISTRAR OF CONTRACTORS
    Opinion of the Court
    ¶19            Magness has requested an award of attorneys’ fees pursuant
    to A.R.S. § 12-348, which provides that “a court shall award fees and other
    expenses to any party . . . which prevails by an adjudication on the merits”
    in a “court proceeding to review a state agency decision[.]” Magness has
    not prevailed on appeal and, in any event, “the provisions of A.R.S. § 12-
    348 do not apply to attorneys’ fees awarded from the Fund.” Shelby v.
    Ariz. Registrar of Contractors, 
    172 Ariz. 95
    , 100, 
    834 P.2d 818
    , 823 (1992); see
    also A.R.S. § 32-1132(A) (stating that “monies in the residential contractors’
    recovery fund shall not be directly awarded for attorney fees or costs
    except in contested cases appealed to the superior court” via an
    administrative remedy.). Therefore, we deny the request.
    CONCLUSION
    ¶20           Because the ROC was not afforded its statutory right to
    present and support its objections, we vacate the superior court’s order
    directing payment from the Fund and remand for further proceedings
    consistent with this opinion.
    :MJT
    9
    

Document Info

Docket Number: 1 CA-CV 13-0184

Citation Numbers: 234 Ariz. 428, 323 P.3d 711, 2014 WL 1377499, 2014 Ariz. App. LEXIS 60

Judges: Brown

Filed Date: 4/8/2014

Precedential Status: Precedential

Modified Date: 11/2/2024