Great Western Bank v. LJC Development, LLC ( 2015 )


Menu:
  •                                   IN THE
    ARIZONA COURT OF APPEALS
    DIVISION ONE
    GREAT WESTERN BANK, a bank chartered under the laws of the State of
    South Dakota, successor-in-interest to the loans of TierOne Bank, a
    federally chartered savings bank, by acquisition of assets from the FDIC,
    as Receiver of TierOne Bank, which was closed by the Office of Thrift
    Supervisor on June 4, 2010, Plaintiff/Appellant,
    v.
    LJC DEVELOPMENT, LLC, an Arizona limited liability company; JAMES
    LEO CROWLEY and JANE DOE CROWLEY, husband and wife; JOHN
    CROWLEY and JENNI CROWLEY, husband and wife,
    Defendants/Appellees.
    No. 1 CA-CV 14-0252
    FILED 11-10-2015
    Appeal from the Superior Court in Maricopa County
    No. CV2009-032530
    The Honorable Katherine M. Cooper, Judge
    AFFIRMED
    COUNSEL
    Quarles & Brady LLP, Phoenix
    By William Scott Jenkins, Jr., Alissa A. Brice
    Counsel for Plaintiff/Appellant
    Aspey Watkins & Diesel, PLLC, Flagstaff
    By Whitney Cunningham, Jennifer M. Mott
    Counsel for Defendants/Appellees
    GREAT WESTERN v. LJC, et al.
    Opinion of the Court
    OPINION
    Presiding Judge Kenton D. Jones delivered the opinion of the Court, in
    which Judge Randall M. Howe and Judge Peter B. Swann joined.
    J O N E S, Judge:
    ¶1            Great Western Bank (Great Western) appeals a judgment
    entered in favor of Appellees on its claim and counterclaim following a
    bench trial. For the following reasons, we affirm.
    FACTS1 AND PROCEDURAL HISTORY
    ¶2           This appeal arises from two construction loan agreements
    between Great Western’s predecessor2 and Cedar Ridge Investments,
    L.L.C. (Borrower). Appellees are the guarantors of Borrower.
    ¶3           In early 2007, Borrower sought funding to develop a fifty-
    home subdivision in Flagstaff to be known as Cedar Ridge. Borrower first
    obtained a loan from Great Western to acquire and develop infrastructure
    (the A&D Loan) in May 2007. Appellees agreed to guarantee the A&D Loan
    in an amount up to but not exceeding Borrower’s total principal
    indebtedness to Great Western. In January 2008, Borrower entered into a
    second agreement with Great Western to fund the actual construction of
    homes (the Agreement). The Agreement required Appellees to execute a
    guaranty separate from that securing the A&D Loan and was signed by
    eight bank officials. By its terms, the Agreement expired on December 1,
    2008.
    1      We view the facts in the light most favorable to upholding the trial
    court’s judgment. Bennett v. Baxter Grp., Inc., 
    223 Ariz. 414
    , 417, ¶ 2 (App.
    2010) (citing Sabino Town & Country Estates Ass’n v. Carr, 
    186 Ariz. 146
    , 148
    (App. 1996)).
    2      Great Western’s predecessor in interest, TierOne Bank, was closed
    by the Office of Thrift Supervision and its interest in the loan and litigation
    was purchased from the FDIC by Great Western in June 2010. For ease of
    reference, we refer to both Great Western and its predecessor in interest as
    Great Western.
    2
    GREAT WESTERN v. LJC, et al.
    Opinion of the Court
    ¶4            In July 2008, as acquisition and development of the
    infrastructure was nearing completion and Borrower was preparing to
    obtain permits for the construction of model homes, Great Western made
    an internal decision to cease construction financing in Arizona and advised
    Borrower it was withdrawing from the Agreement. When notified of this
    decision, Borrower immediately expressed to Great Western its concern
    regarding the continued viability of the project without the financing
    agreement in place, slowed construction in an effort to save money, and
    attempted to secure alternate financing. Borrower’s efforts were ultimately
    unsuccessful, and without financing to build model homes, Borrower could
    not sell homes in Cedar Ridge and was therefore unable to generate revenue
    through which to service the A&D Loan.
    ¶5           Great Western then foreclosed on the A&D Loan, sold the
    property to another developer, and sued Appellees for the balance of
    approximately $2.6 million.3 Appellees conceded they, as guarantors, failed
    to repay the A&D Loan but sought offset and affirmative relief for profits
    Borrower lost as a result of Great Western’s termination of the Agreement,
    which they contend constituted anticipatory repudiation and breach of the
    implied covenant of good faith and fair dealing. The case proceeded to trial
    for determination of the merit and value, if any, of Appellees’ claims and
    counterclaims which might offset the deficiency owed to Great Western.
    Great Western submitted a timely request for findings of fact and
    conclusions of law.
    ¶6            At trial, Great Western argued it was not required under the
    Agreement to actually finance construction within Cedar Ridge, asserting
    the Agreement was merely a “guidance line” or an outline of proposed
    future loans, and Great Western retained complete discretion to decline
    funding. The trial court disagreed, noting the Agreement was titled “Loan
    Agreement,” contained express language obligating Great Western to
    “make the Loans to Borrower,” and required Borrower to “accept such
    Loans,” subject to various terms and conditions. And, according to the
    Agreement’s terms, the only basis upon which Great Western was entitled
    to withdraw its participation was Borrower’s default — an event never
    alleged by Great Western.
    3      Although they are named in the caption, John and Jenni Crowley
    sought bankruptcy protection during the litigation and are not parties to
    this appeal.
    3
    GREAT WESTERN v. LJC, et al.
    Opinion of the Court
    ¶7            The trial court concluded Great Western breached the
    Agreement by unilaterally terminating its obligation to extend financing
    without conducting case-by-case review of individual loan requests. The
    court determined Great Western’s breach had prevented Borrower from
    receiving the benefit of the contract — namely, financing it required to build
    and market homes within Cedar Ridge, which would have, in turn,
    provided Borrower revenues through which it would be able to repay the
    A&D Loan. The court found Great Western had no valid excuse for doing
    so because Borrower had the ability to begin construction and was not in
    default of the Agreement. Finally, the court determined Borrower had
    proven with reasonable certainty it would have profited between $2,808,000
    and $3,500,000 had Great Western not terminated the Agreement. Because
    the lost profits exceeded the outstanding balance on the A&D Loan, the
    court found Appellees’ liability under the guaranty was reduced to zero.
    The trial court determined Appellees were the prevailing parties, having
    “effectively recovered $3.1 million, absolving them of their liability” to
    Great Western, and awarded Appellees their attorneys’ fees and double
    their taxable costs pursuant to Arizona Revised Statutes (A.R.S.) sections
    12-3414 and -341.01 and Arizona Rules of Civil Procedure 54(f) and 68.
    ¶8            The trial court denied Great Western’s motions to amend the
    findings of fact and conclusions of law and for reconsideration. Great
    Western timely appealed. We have jurisdiction pursuant to A.R.S. §§ 12-
    120.21(A)(1) and -2101(A)(1).
    DISCUSSION
    I.     Interpretation of the Agreement
    ¶9             In its opening brief, Great Western characterizes the
    Agreement as “an agreement between Borrower and [Great Western] under
    which Borrower could request loans after satisfying certain terms and
    conditions, and subject to an individual case-by-case review by [Great
    Western].” Upon this premise, Great Western argues the trial court erred
    in concluding that “[b]y entering into the [Agreement], [Great Western]
    agreed to make loans, on a case-by-case basis, provided Borrower complied
    with the terms and conditions set forth [there]in,” re-advancing its theory
    that the documents were simply an “outline” for future financing. The
    interpretation of a contract is a question of law which we review de novo.
    Colo. Cas. Ins. v. Safety Control, 
    230 Ariz. 560
    , 565, ¶ 7 (App. 2012) (citing
    4     Absent material revisions from the relevant date, we cite a statute’s
    current version.
    4
    GREAT WESTERN v. LJC, et al.
    Opinion of the Court
    Grubb & Ellis Mgmt. Servs., Inc. v. 407417 B.C., L.L.C., 
    213 Ariz. 83
    , 86, ¶ 12
    (App. 2006)). In doing so, our primary purpose is to discover and enforce
    the parties’ intent at the time the contract was made, Taylor v. State Farm
    Mut. Auto. Ins., 
    175 Ariz. 148
    , 152 (1993), looking first to “‘the plain meaning
    of the words as viewed in the context of the contract as a whole,’” ELM
    Retirement Ctr., L.P. v. Callaway, 
    226 Ariz. 287
    , 290-91, ¶ 15 (App. 2010)
    (quoting United Cal. Bank v. Prudential Ins., 
    140 Ariz. 238
    , 259 (App. 1983)).
    ¶10             Setting aside that Great Western’s own description of the
    purpose of the Agreement is nearly identical to the trial court’s finding, we
    find no error. Although Great Western refers to the Agreement as a
    “guidance line,” these words have no legal significance and appear
    nowhere within the provisions of the Agreement. The contract itself is
    specifically titled “Loan Agreement.”
    ¶11            Great Western’s internal communications and writings to
    Borrower refer to the Agreement inconsistently as a “commitment,” a “line
    of credit,” a “guidance line of credit,” and a “loan agreement.” However,
    in correspondence to Borrower dated the day prior to the execution of the
    Agreement, Great Western explained the term “guidance line,” stating:
    The line of credit that has been approved is a “guidance line,”
    which is an indication of the maximum allowable amount of
    loans outstanding that you may have with [Great Western]
    during the term of the guidance line. Even though this is a
    commitment, each individual housing start and lot purchase
    is subject to [Great Western]’s individual case-by-case
    approval. . . . The guidance line amount is $3,600,000.00.
    Marlin Hupka, a vice president of both Great Western and its predecessor,
    provided the same explanation at trial.
    ¶12          Great Western’s explanation is inconsistent with the actual
    terms of the Agreement, which identifies Great Western as “Lender” and
    begins with an “Agreement to Make and Take Loan,” stating:
    Subject to the terms and conditions set forth in this
    Agreement, Lender agrees to make the Loans to Borrower, each
    such Loan to be used by Borrower for the acquisition of a Lot
    and for subsequent construction by Borrower of
    Improvements thereon, and Borrower agrees to accept such
    Loans from Lender as hereinafter described.
    5
    GREAT WESTERN v. LJC, et al.
    Opinion of the Court
    (Emphasis added). The Agreement continues: “Lender will, from time to
    time, make Lot Specific Advances to Borrower under the Loan for the
    purchase of the Related Lot and construction of Improvements thereon.”
    (Emphasis added). It was only after Great Western withdrew from the
    Agreement that it informed Borrower it considered the Agreement an
    “uncommitted credit facility” or described the Agreement as “not a
    commitment” but “a set of terms” by which to make future loans. To accept
    this explanation would render the language within the “Agreement to
    Make and Take Loan” meaningless. We decline to adopt such a
    construction. See ELM Retirement, 226 Ariz. at 291 (“In interpreting a
    contract, we do not construe one term in a way that renders another
    meaningless.”).
    ¶13            Great Western relies upon language within the Agreement
    that “[t]he Loans are not a line of credit” and each lot-specific loan “is
    subject to Lender’s individual, case-by-case approval and Borrower’s
    satisfaction of all terms and conditions contained in this Agreement with
    respect thereto.” These statements are not, however, dispositive of the issue
    before us because, within the Agreement, “Loans” is defined as “one or
    more of the Loans which Lender agrees to make to Borrower pursuant to this
    Agreement.” (Emphasis added). The Agreement thus states only that the
    lot-specific loans were not a line of credit; it is silent as to whether the
    financing structure contemplated by the Agreement as a whole operated as
    a line of credit. The existence of a defined maximum amount which the
    Borrower could request certainly suggests otherwise.5
    ¶14             By requiring Borrower to follow a specified procedure and
    furnish additional information to obtain each lot-specific loan, the lending
    arrangement is distinguished from a traditional line of credit where a
    certain sum is available to the borrower as he deems appropriate without
    any further explanation to the lender or qualification by the borrower. But
    the fact that individual loans were “subject to the terms and conditions” set
    forth within the Agreement does not change Great Western’s express
    agreement to “make loans” to Borrower upon its compliance with those
    terms, particularly in light of the agreed upon purpose of the arrangement
    “to insure that a lender will be available for construction financing.”
    Additionally, that approval of individual lot-specific loans could be given
    without further input from the full lending committee, who had already
    signed off on the Agreement, suggests the process to obtain a lot-specific
    5     A “line of credit” is “[t]he maximum amount of borrowing power
    extended to a borrower by a given lender, to be drawn on by the borrower
    as needed.” Black’s Law Dictionary (10th ed. 2014).
    6
    GREAT WESTERN v. LJC, et al.
    Opinion of the Court
    loan was more ministerial than substantive. Effectively, the Agreement was
    as much a loan agreement, i.e., a contract binding its signatories to the
    lending and borrowing of money, as any loan agreement ever written,
    notwithstanding Borrower’s obligation to provide certain information to
    Great Western before it could make a draw.
    ¶15            Great Western argues that, as a matter of public policy,
    affirming the trial court’s ruling “would discourage lenders from offering
    uncommitted loan facilities such as the Guidance Line, for fear that
    exercising their discretion to withdraw the same will result in a judgment
    against them.” We are not persuaded that a sophisticated financial
    institution capable of lending monies on a scale allowing for the
    construction of residential subdivisions would be incapable of drafting a
    document evidencing an uncommitted loan facility in a manner that clearly
    and accurately describes the rights and obligations of the parties involved
    if it so intended. And if, as here, the financial institution introduces the
    term “guidance line” into the transaction, defines the term as a “line of
    credit” and “a commitment,” and subsequently executes a “loan
    agreement” to memorialize the parties’ rights and obligations, we find no
    offense in holding the financial institution to the terms of those instruments.
    ¶16           Further, to accept Great Western’s position would place the
    court’s imprimatur upon what has commonly been deemed an illusory
    contract. “[T]o agree to do something and to reserve the right to terminate
    the agreement at will is no agreement at all” — executory or otherwise.
    Shattuck v. Precision-Toyota, Inc., 
    115 Ariz. 586
    , 588 (1977) (“[A]n illusory
    contract is unenforceable for lack of mutuality. . . . [A] contract must have
    mutuality of obligation, and an agreement which permits one party to
    withdraw at his pleasure is void.”) (internal quotations omitted).
    ¶17            Here, both the language of the Agreement and its context
    reflect the parties’ intent that it would operate, effectively, as a line of credit,
    subject to certain limitations and preconditions. We agree with Great
    Western that it was not committed to grant any particular request for a lot-
    specific loan; however, Great Western agreed to be available and was
    required under the terms of the Agreement to at least consider Borrower’s
    requests on a case-by-case basis. As discussed below, the trial court acted
    well within its discretion in finding Great Western breached the Agreement
    by refusing to honor these terms.
    7
    GREAT WESTERN v. LJC, et al.
    Opinion of the Court
    II.    Viability of Claim for Breach of the Implied Covenant of Good
    Faith and Fair Dealing
    ¶18           Great Western next argues Appellees’ claim for breach of the
    implied covenant of good faith and fair dealing is barred as a matter of law
    because it “relies on a promise to lend money not evidenced in writing,” and
    therefore violates Arizona’s statute of frauds and federal law. The
    application of statutes presents a question of law which we review de novo.
    See Gomez v. Maricopa Cnty., 
    175 Ariz. 469
    , 471 (App. 1993) (citing Gary
    Outdoor Advert. Co. v. Sun Lodge, Inc., 
    133 Ariz. 240
    , 242 (1982)).
    ¶19            Arizona’s statute of frauds provides:
    No action shall be brought in any court in the following cases
    unless the promise or agreement upon which the action is
    brought, or some memorandum thereof, is in writing and
    signed by the party to be charged . . . Upon a contract,
    promise, undertaking or commitment to loan money or to
    grant or extend credit . . . involving both an amount greater
    than two hundred fifty thousand dollars and not made or
    extended primarily for personal, family or household
    purposes.
    A.R.S. § 44-101(9). Great Western also asserts the D’Oench doctrine likewise
    prohibits a borrower from asserting defenses or claims against a failed bank
    based upon unwritten agreements.6 See 
    12 U.S.C. § 1823
    (e)(1); Adams, 187
    Ariz. at 589-90 (citing D’Oench, 315 U.S. at 457, and Resolution Trust Corp. v.
    Foust, 
    177 Ariz. 507
    , 517 (App. 1993)).
    ¶20           Great Western’s reliance upon this authority is misplaced and
    appears to arise from its mischaracterization of the Agreement and the
    nature of the underlying claim. Here, the claim for breach of the implied
    covenant of good faith and fair dealing is premised upon Great Western’s
    6      The D’Oench doctrine is a form of estoppel designed to protect the
    FDIC from fraudulent practices by “enabl[ing it] to enforce agreements
    between failed banks and their borrowers in strict accordance with the
    terms of the loan documents,” and not an unwritten “secret agreement”
    between the borrower and a representative of a defunct financial
    institution. FDIC v. Adams, 
    187 Ariz. 585
    , 590 (App. 1996) (citing D’Oench,
    Duhme & Co. v. FDIC, 
    315 U.S. 447
    , 459-62 (1942)).
    8
    GREAT WESTERN v. LJC, et al.
    Opinion of the Court
    withdrawal from the Agreement, which is clearly evidenced in writing. As
    alleged here, it is not a tort claim7 and is not based upon any oral or “secret”
    arrangement to extend the contract past its natural expiration of December
    2008. Therefore, neither the statute of frauds, nor the D’Oench doctrine, has
    any application.
    ¶21            The covenant of good faith and fair dealing is implied in every
    contract, including the Agreement at issue here, and can be breached even
    where the express terms are not violated. Wells Fargo, 201 Ariz. at 490, ¶ 59;
    Bike Fashion Corp. v. Kramer, 
    202 Ariz. 420
    , 424, ¶ 17 (App. 2002). Here,
    Appellees properly alleged Great Western acted in a manner that denied
    Borrower the reasonably anticipated benefit of the Agreement, see Bike
    Fashion, 
    202 Ariz. at 424-25, ¶¶ 17-18
    , when it unilaterally withdrew from
    that agreement, and Appellees were properly permitted to proceed upon
    that theory.8
    III.   Evaluation of the Evidence
    ¶22           The remainder of Great Western’s arguments concern the
    sufficiency of evidence to support the findings of fact upon which the trial
    court’s conclusions are based. We review the trial court’s findings of fact
    for an abuse of discretion. Myers v. W. Realty & Constr., Inc., 
    130 Ariz. 274
    ,
    277 (App. 1981) (citing Lawrence v. Valley Nat’l Bank, 
    12 Ariz. App. 51
    , 57
    7       Arizona recognizes a tort claim for breach of the implied covenant of
    good faith and fair dealing “but only where there is a ‘special relationship
    between the parties arising from elements of public interest, adhesion, and
    fiduciary responsibility.’” Wells Fargo Bank v. Ariz. Laborers Local No. 395
    Pension Trust Fund, 
    201 Ariz. 474
    , 491, ¶ 60 (2002) (quoting Burkons v. Ticor
    Title Ins. Co. of Cal., 
    168 Ariz. 345
    , 355 (1991)). Our courts have generally
    declined to recognize any special relationship between a debtor and
    creditor, see McAlister v. Citibank, 
    171 Ariz. 207
    , 212 (App. 1992) (holding
    bank owed no fiduciary duty to borrower); cf. Stewart v. Phx. Nat’l Bank, 
    49 Ariz. 34
    , 44 (1937) (finding special relationship between debtor and creditor
    existed only because bank officers and directors had been debtor’s financial
    advisors for twenty-three years), and Appellees here do not allege
    otherwise.
    8      The trial court ruled before trial that Appellees, as guarantors, were
    entitled to pursue an offset for the amount of any of Borrower’s claims
    against Great Western. See Restatement (First) of Security § 133 (1941) (cited
    favorably by Great Am. Ins. v. Fred J. Gallagher Constr. Co., 
    16 Ariz. App. 479
    ,
    480-81 (1972)). Neither party challenges this ruling on appeal.
    9
    GREAT WESTERN v. LJC, et al.
    Opinion of the Court
    (1970)). Where there is conflicting evidence, we do not substitute our
    judgment for the trial court’s and will reverse only where the findings are
    clearly erroneous. Id.; Ariz. R. Civ. P. 52(a) (“Findings of fact, whether
    based on oral or documentary evidence, shall not be set aside unless clearly
    erroneous, and due regard shall be given to the opportunity of the trial
    court to judge the credibility of witnesses.”). We therefore review each
    contention to determine whether it is supported by substantial evidence in
    the record. Visco v. Universal Refuse Removal Co., 
    11 Ariz. App. 73
    , 75 (1969)
    (citing Bohmfalk v. Vaughan, 
    89 Ariz. 33
    , 38 (1960), and Reliable Elec. Co. v.
    Clinton Campbell Contractor, Inc., 
    10 Ariz. App. 371
    , 374 (1969)).
    A.     Termination of the Agreement
    ¶23           Great Western argues the trial court abused its discretion in
    finding Great Western breached the Agreement by unilaterally terminating
    its obligation to extend financing. Great Western does not dispute it
    withdrew from the Agreement, but argues instead it was within its
    discretion to do so. Whether a party has breached a contract is a question
    of fact. Maleki v. Desert Palms Prof’l Props., L.L.C., 
    222 Ariz. 327
    , 333, ¶ 28
    (App. 2009) (citing Wells Fargo, 
    201 Ariz. at 493, ¶¶ 69-70
    ).
    ¶24           The language of the Agreement authorizes termination only
    upon Borrower’s default. It does not grant Great Western authority to
    unilaterally withdraw from the Agreement. Great Western did not assert
    Borrower had defaulted, and its termination of the Agreement was a direct
    violation of its written terms. By definition, Great Western’s actions
    constitute a breach of contract, and we find no error.
    B.     Borrower’s Ability to Perform
    ¶25           Great Western next argues the trial court erred in finding
    Borrower was capable of performing under the Agreement, a necessary
    precursor to its conclusion that Great Western committed anticipatory
    breach. See Thomas v. Montelucia Villas, L.L.C., 
    232 Ariz. 92
    , 95, ¶ 9 (2013)
    (requiring the non-breaching party show “‘that he would have been ready
    and willing to have performed the contract, if the repudiation had not
    occurred’” in order to recover damages for anticipatory repudiation)
    (quoting United Cal. Bank, 
    140 Ariz. at 288-89
    ). Specifically, Great Western
    contends that because Borrower had yet to obtain permits for any vertical
    construction or to construct an access road required by the City of Flagstaff,
    it “was never in a position to build” and was therefore unable to perform.
    ¶26          The trial court’s finding that Borrower had the ability to
    perform its obligations when Great Western breached the Agreement is
    10
    GREAT WESTERN v. LJC, et al.
    Opinion of the Court
    supported by the record. Great Western withdrew from the Agreement in
    early July 2008. It is uncontested that Borrower was current on its payments
    for the A&D Loan at least through October 2008. The court was advised
    that Great Western’s own construction inspection, undertaken in August
    2008, rated Borrower’s progress as “acceptable.” In fact, prior to being
    notified of Great Western’s repudiation of the contract, Borrower had
    planned to start obtaining building permits toward vertical construction
    that same month.
    ¶27            Great Western points to evidence that the preconditions to
    financing were not actually completed until after the Agreement would
    have expired. That the project was ultimately delayed when Borrower
    purposefully slowed construction in an effort to conserve funds while it
    searched for alternate financing does not conclusively establish Borrower
    was unable to perform at the time of Great Western’s breach; “the law does
    not require the nonbreaching party to do a futile or useless act.” United Cal.
    Bank, 
    140 Ariz. at
    283 (citing Kammert Bros. Enters., Inc. v. Tanque Verde Plaza
    Co., 
    102 Ariz. 301
    , 306 (1967), and Lee v. Nichols, 
    81 Ariz. 106
    , 111-12 (1956)).
    And, Borrower still had six months before the Agreement expired to
    complete any infrastructure required prior to requesting lot-specific loans.
    See Kammert Bros., 
    102 Ariz. at 306
     (noting a party generally has the right to
    perform at any time during the contract period). Additionally, any
    purported concern over Borrower’s ability to perform is belied by the
    testimony of Great Western’s vice president, Hupka, who, within the
    purview of his task “to manage the risk” for Great Western in its Arizona
    market, recommended reinstating the Agreement and extending additional
    loans to Borrower immediately post-repudiation and through mid-2009,
    believing “[l]ong term, . . . [Borrower] has a good product and location for
    the project and should be able to sell enough homes to settle the debt.”
    ¶28            In light of the conflicting evidence, the trial court acted within
    its discretion in concluding Borrower was able to perform at the time of
    Great Western’s breach.
    C.     Extension of the Agreement
    ¶29           Great Western argues the trial court erred in finding it would
    “[m]ore probably than not” have extended the Agreement beyond its stated
    term. Great Western contends this finding is merely speculative and
    untenable in light of Arizona’s statute of frauds, which prohibits an oral
    contract for the extension, renewal, or modification of a loan. See A.R.S.
    § 44-101(9). However, the finding does not “suggest[] there was an oral
    agreement or understanding that such an extension would have been
    11
    GREAT WESTERN v. LJC, et al.
    Opinion of the Court
    granted” as Great Western contends; rather, it reflects the court’s resolution
    of the factual issue of what, more probably than not, would have occurred
    in the absence of a breach. This fact is relevant to calculating the extent of
    Borrower’s damages and properly within the scope of the findings required
    of the trial court. See Miller v. Bd. of Supervisors of Pinal Cnty., 
    175 Ariz. 296
    ,
    299 (1993) (noting findings of fact required under Rule 52(a) must be
    sufficiently specific and address all pertinent issues).
    ¶30           The finding is also supported by the evidence. Great Western
    acknowledged the opportunity existed to extend the Agreement if it made
    business sense to do so. Market reports indicated the Cedar Ridge
    development would be successful and profitable and would allow
    Borrower to repay its obligations to Great Western. Hupka testified that, if
    the development was building and selling homes, “[i]t would make
    business sense” to extend the Agreement, and he actively encouraged Great
    Western to reinstate the Agreement or offer alternate financing to construct
    model homes at Cedar Ridge, even after the Agreement would have
    otherwise expired by its own terms in December 2008. From this evidence,
    the trial court could reasonably conclude Great Western would have
    continued its arrangement with Borrower.
    D.      Breach of Implied Covenant of Good Faith and Fair Dealing
    ¶31            Great Western argues the trial court abused its discretion in
    finding it breached the implied covenant of good faith and fair dealing by
    withdrawing from the Agreement because Borrower could not have had a
    reasonable expectation it would receive funding from Great Western in the
    absence of a binding obligation to make loans.9 See Bike Fashion, 
    202 Ariz. at 423, ¶ 13
     (noting the “basic purpose” of contract law and the implied
    covenant of good faith and fair dealing is to protect the parties’ reasonable
    expectations) (citing 3A Corbin on Contracts § 654 (Lawrence A.
    Cunningham & Arthur J. Jacobson eds., Supp. 1999)). “Issues of
    reasonableness are generally questions of fact.” In re Estate of Jung, 
    210 Ariz. 202
    , 207, ¶ 28 (App. 2005) (citing Trustmark Ins. v. Bank One, Ariz., N.A., 
    202 Ariz. 535
    , 541, ¶ 25 (App. 2002)).
    9      Although not expressly contained in the record, we presume the trial
    court made all findings necessary to sustain the judgment if they are
    “reasonably supported by the evidence, and not in conflict with the
    [court’s] express findings.” Coronado Co. v. Jacome’s Dep’t Store, Inc., 
    129 Ariz. 137
    , 139 (App. 1981).
    12
    GREAT WESTERN v. LJC, et al.
    Opinion of the Court
    ¶32            To accept this argument requires us to accept Great Western’s
    overarching premise that when it wrote the Agreement, it did not do so for
    the purpose of memorializing an agreement to loan money — a position
    belied by the specific language of the Agreement and one which we have
    rejected. See Part I supra. Contrary to Great Western’s assertions otherwise,
    that Borrower was unable to obtain alternate financing does not illustrate
    Great Western’s decision to terminate the agreement to provide financing
    was made in good faith. Indeed, by unilaterally terminating the Agreement
    six months before it was to expire and depriving Borrower of the ability to
    construct homes within the development, Great Western stripped Borrower
    of the precise benefit for which it contracted and violated the covenant of
    good faith and fair dealing.
    ¶33           We likewise reject Great Western’s suggestions that: (1) it
    acted in a commercially reasonable manner and with Borrower’s best
    interest in mind when it terminated the Agreement given the declining
    economic conditions and its general concerns regarding the success of then-
    existing real estate development projects, and (2) it was authorized to
    terminate the Agreement at its pleasure so long as it had a good faith
    intention, at the time of execution, to make loans to Borrower. Beyond
    being both an incorrect statement of the law, see Wells Fargo, 
    201 Ariz. at 490, ¶ 59
     (stating the “implied covenant of good faith and fair dealing
    prohibits a party from doing anything to prevent other parties to the
    contract from receiving the benefits and entitlements of the agreement,”
    without limiting the obligation to execution of the contract) (emphasis
    added), and contrary to the specific language of the agreement, these claims
    were raised in this Court for the first time at oral argument and were thus
    waived, see Santa Fe Ridge Homeowners’ Ass’n v. Bartschi, 
    219 Ariz. 391
    , 398
    n.3, ¶ 22 (App. 2008) (citing Mitchell v. Gamble, 
    207 Ariz. 364
    , 369-70, ¶ 16
    (App. 2004)).
    ¶34            Alternatively, Great Western argued at oral argument that
    since it had decided not to loan Borrower the contracted-for monies, it was
    more efficient to repudiate the entire contract at once rather than process,
    and reject, applications for funding as they were received. In doing so,
    Great Western conflates the issue of whether it would have approved a lot-
    specific loan request with that actually presented here — its obligation to
    consider requests for funding on a case-by-case basis. The Agreement
    specified it was effective until December 2008, and the only basis for
    termination was an event of default by Borrower. Hupka agreed it would
    be reasonable for Borrower to expect the Agreement to continue until at
    least the stated expiration date. That Borrower had not yet requested a loan
    under the Agreement is irrelevant; it had an additional six months,
    13
    GREAT WESTERN v. LJC, et al.
    Opinion of the Court
    according to the express terms of the contract, to do so. Great Western’s
    arguments that Borrower would not have satisfied the preconditions to
    approval are rejected for the same reasons set forth in Part III(B), supra.
    And, it can reasonably be inferred, based upon Hupka’s personal and
    repeated requests to Great Western to either reinstate the Agreement or
    issue new loans to Borrower, that, had Borrower submitted one or more
    loan requests, they would have been approved by Great Western had it
    dealt with Borrower in good faith.
    ¶35           In sum, substantial evidence supports the trial court’s implicit
    finding that Borrower reasonably expected Great Western to provide
    construction financing and its conclusion that Great Western’s failure to do
    so violated the implied covenant of good faith and fair dealing.
    E.      Lost Profits
    ¶36            Finally, Great Western contends Appellees failed to establish
    with reasonable certainty that Borrower lost profits of $2.8 to $3.5 million
    as a result of Great Western’s breach of the Agreement. Generally, the non-
    breaching party to a loan agreement is entitled to recover an amount that
    will reasonably and fairly compensate him for losses resulting from the
    breach — the amount that would place him in the same position in which
    he would have been had the contract been performed. See Higgins v. Ariz.
    Sav. & Loan Ass’n, 
    90 Ariz. 55
    , 63-64 (1961) (noting where one party has
    broken a contract, damages may amount to what “‘may reasonably be
    supposed to have been in the contemplation of both parties at the time they
    made the contract’”) (quoting Shurtleff v. Occidental Bldg. & Loan Ass’n, 
    181 N.W. 374
    , 376 (Neb. 1921)); Rev. Ariz. Jury Instr. (Civil) Contract 17 (5th ed.
    2013). Both the existence and amount of lost profits present questions of
    fact which must be proven with reasonable certainty. See Harris Cattle Co.
    v. Paradise Motors, Inc., 
    104 Ariz. 66
    , 67 (1968); Earle M. Jorgensen Co. v. Tesmer
    Mfg. Co., 
    10 Ariz. App. 445
    , 450 (1969).
    ¶37            Regarding lost profits, the trial court concluded:
    Had [Great Western] not breached, after payment of the A&D
    loan, Borrower would have realized an estimated net profit in
    the range of $2,808,000 to $3,500,000. The Court concludes
    that the 50 homes would have sold eventually. At a
    minimum, Borrower would have been able to sell
    approximately half of the homes based on the original
    projection of $70,000 net profit per home and the remainder
    for at least the revised projection of $42,320 net profit per
    14
    GREAT WESTERN v. LJC, et al.
    Opinion of the Court
    home. More likely, with Borrower’s ability to reduce
    construction costs to lower price, profits would have been on
    the higher end of that range.
    ¶38           Great Western first argues the award of lost profits was
    inappropriate because, it contends, the loss was more likely caused by a
    declining economy rather than breach of the Agreement. Although this is
    a possible explanation, it is one which the trial court rejected in favor of
    evidence from Great Western’s own appraiser that home sales in Flagstaff
    remained largely consistent through 2009. The record also reflects that
    demand for housing in Flagstaff was significant given the limited
    availability of land in the area and the lower-cost housing proposed for
    Cedar Ridge would fill an underserved niche in the community even in the
    down economy. Great Western’s appraiser also concluded Borrower
    would have been able to sell at least one home per month in 2009 which
    would have been sufficient to service the loans with Great Western. And,
    even if Great Western had decided not to extend the Agreement beyond its
    expiration in December 2008, Borrower would have been able to build
    several model homes in the meantime and enhance its chances of obtaining
    alternate financing, thereby mitigating its damages.
    ¶39            We will not second-guess the trial court’s resolution of
    disputed questions of fact where its findings are supported by the record.
    See Gen. Elec. Capital Corp. v. Osterkamp, 
    172 Ariz. 185
    , 188 (App. 1992) (citing
    City of Phx. v. Geyler, 
    144 Ariz. 323
    , 329 (1985)). We will certainly not do so
    where the findings of the court were based upon the testimony of the
    objecting party’s own witnesses.
    ¶40           Great Western also disputes the trial court’s calculation of lost
    profits, arguing: (1) Appellees did not prove Great Western would have
    extended the Agreement past its expiration, and therefore, damages should
    have been calculated based only upon the number of homes Borrower
    could have built between July and December 2008, and (2) Appellees did
    not present sufficient evidence for the court to determine how many homes
    Borrower would have constructed between July and December 2008. It
    contends the court’s conclusion is “wildly speculative,” and that using the
    words “eventually” and “more likely” “emphasize[s] the uncertainty of the
    situation.”10
    10   Great Western also takes issue with the trial court’s use of the words
    “would have.” We are unable to discern any meaning from the phrase
    15
    GREAT WESTERN v. LJC, et al.
    Opinion of the Court
    ¶41            This position is untenable in light of the trial court’s factual
    findings, as supported by the record and affirmed in ¶¶ 29-30, 38-39, supra,
    that Borrower would have been able to sell the homes at a profit in the
    favorable Flagstaff market, and Great Western would have acted in its own
    best interest by continuing the financing arrangement through to
    completion of the project. Moreover, we have long-recognized that
    absolute certainty in the amount of damages is not necessary where the fact
    of damage is proven, with doubts to be resolved in favor of the non-
    breaching party. See Gilmore v. Cohen, 
    95 Ariz. 34
    , 36 (1963) (citing Story
    Parchment Co. v. Patterson Parchment Paper Co., 
    272 U.S. 555
    , 563-64 (1931);
    Grummel v. Hollenstein, 
    90 Ariz. 356
    , 360 (1962); and Brear v. Klinker Sand &
    Gravel Co., 
    374 P.2d 370
    , 374 (Wash. 1962)); Restatement (Second) of
    Contracts § 352 (1981) (“Doubts are generally resolved against the party in
    breach. A party who has, by his breach, forced the injured party to seek
    compensation in damages should not be allowed to profit from his breach
    where it is established that a significant loss has occurred.”). Reasonable
    certainty is therefore provided where there is “some reasonable method of
    computing [the] net loss.” Lininger v. Dine Out Corp., 
    131 Ariz. 160
    , 163
    (App. 1981) (citing Irish v. Mountain States Tel. & Tel. Co., 
    500 P.2d 151
    , 154
    (Colo. App. 1972)); see also Gilmore, 
    95 Ariz. at 36
     (“[T]he evidence must
    make an ‘approximately accurate estimate’ possible.”) (quoting Martin v.
    LaFon, 
    55 Ariz. 196
    , 199-200 (1940)).
    ¶42            Again, although there was conflicting evidence presented at
    trial as to these issues, we defer to the trial court’s superior position to
    weigh the evidence, make credibility determinations, and resolve conflicts
    in facts and expert opinions. In re Estate of Pouser, 
    193 Ariz. 574
    , 579, ¶ 13
    (1999). After making relevant findings of fact, the court articulated a
    formula, the use of which Great Western does not dispute, that makes an
    “approximately accurate estimate” of the lost profits.11 Nothing more is
    required.
    other than an affirmative declaration that the events described would, in
    fact, have occurred absent Great Western’s breach.
    11     To reach the lower end of the range, the trial court added twenty-
    five homes multiplied by an anticipated profit of $70,000, to twenty-five
    homes multiplied by an anticipated profit of $42,320, for a total of
    $2,807,900. To reach the higher end of the range, the court multiplied fifty
    homes by an anticipated profit of $70,000, for a total of $3,500,000.
    16
    GREAT WESTERN v. LJC, et al.
    Opinion of the Court
    CONCLUSION
    ¶43          The judgment of the trial court is affirmed.
    ¶44           Both parties request an award of attorneys’ fees on appeal
    pursuant to the terms of the A&D Loan and A.R.S. § 12-341.01. As the
    prevailing party, Appellees are awarded their reasonable attorneys’ fees
    and costs incurred on appeal upon compliance with ARCAP 21(b).
    :ama
    17