Young v. Allen Homes ( 2022 )


Menu:
  •                      NOTICE: NOT FOR OFFICIAL PUBLICATION.
    UNDER ARIZONA RULE OF THE SUPREME COURT 111(c), THIS DECISION IS NOT PRECEDENTIAL
    AND MAY BE CITED ONLY AS AUTHORIZED BY RULE.
    IN THE
    ARIZONA COURT OF APPEALS
    DIVISION ONE
    MICHAEL E. YOUNG, et al., Plaintiffs/Appellants,
    v.
    ALLEN HOMES, LLC, Defendant/Appellee.
    No. 1 CA-CV 21-0740
    FILED 9-29-2022
    Appeal from the Superior Court in Maricopa County
    No. CV2019-056337
    The Honorable Sally Schneider Duncan, Retired Judge
    REVERSED AND REMANDED
    COUNSEL
    The Kozub Law Group, PLC, Phoenix
    By Richard W. Hundley
    Counsel for Plaintiff/Appellant
    FENNEMORE CRAIG, P.C., Phoenix
    By J. Christopher Gooch, Emily Ward
    Counsel for Defendant/Appellee
    MEMORANDUM DECISION
    Judge D. Steven Williams delivered the decision of the court, in which
    Presiding Judge David D. Weinzweig and Judge Randall M. Howe joined.
    YOUNG, et al. v. ALLEN HOMES
    Decision of the Court
    W I L L I A M S, Judge:
    ¶1           Michael Young and Debra Lux-Young (“the Youngs”) sued
    Allen Homes, LLC (“Allen Homes”). Allen Homes counter-sued the
    Youngs. The superior court granted summary judgment for Allen Homes
    on its breach of contract counterclaim. The Youngs appeal. For the
    following reasons, we reverse and remand.
    FACTUAL AND PROCEDURAL HISTORY
    ¶2             The Youngs hired Allen Homes, a small custom home
    builder, to construct their new single-family residence for the agreed sum
    of nearly $2 million. The Youngs paid Allen Homes a “non-refundable
    deposit of $80,000.00” as the parties’ written contract required. The contract
    further required that the Youngs “be responsible for making application for
    the [city] building permits,” as well as “all additional permits necessary”
    for Allen Homes to complete the project.
    ¶3             The Youngs submitted their building plans to the
    homeowner’s association (“HOA”) for approval, but were informed
    approval was “unlikely” because of, in part, the direction the garage doors
    were facing. The Youngs had their architect redesign the project by moving
    the garage and its doors. And over the next few months, the Youngs had a
    series of back-and-forth communications with the HOA about the building
    and landscaping plans. Ultimately, the Youngs decided against submitting
    the plans for the HOA’s final approval or continuing with the project.
    ¶4             The Youngs then requested Allen Homes refund the
    $80,000.00. When Allen Homes refused, the Youngs sought declaratory
    relief and claimed Allen Homes was unjustly enriched. More specifically,
    the Youngs argued that the $80,000.00 deposit was an unenforceable
    penalty because it did not reasonably compensate Allen Homes for its
    actual or anticipated losses. In the alternative, the Youngs claimed that no
    contract was formed because it was based on the mutually mistaken
    assumption that the HOA would approve the building plans.
    ¶5           Both parties moved for summary judgment. The superior
    court granted summary judgment for Allen Homes on the Youngs’ unjust
    enrichment claim but denied the remainder of both parties’ motions. Allen
    Homes then counter-sued the Youngs for breach of contract and
    successfully moved for summary judgment on its counterclaim, rendering
    the Youngs’ remaining claim for declaratory relief moot. The court awarded
    2
    YOUNG, et al. v. ALLEN HOMES
    Decision of the Court
    Allen Homes its costs of $1,380.66 and attorney’s fees of $54,080.93. After
    unsuccessfully moving the court to reconsider, the Youngs timely appealed.
    ¶6           We have jurisdiction under Article 6, Section 9, of the Arizona
    Constitution and A.R.S. § 12-2101(A)(1).
    DISCUSSION
    ¶7            Summary judgment is appropriate when “there is no genuine
    dispute as to any material fact and the moving party is entitled to judgment
    as a matter of law.” Ariz. R. Civ. P. 56(a). To obtain summary judgment on
    its own breach of contract claim, Allen Homes had to prove every element
    of its claim with “undisputed admissible evidence that would compel any
    reasonable juror to find in its favor.” Wells Fargo Bank, N.A. v. Allen, 
    231 Ariz. 209
    , 213, ¶ 18 (App. 2012) (citation omitted). A motion for summary
    judgment “must stand on its own and demonstrate by admissible evidence
    that the [moving party] has met its burden of proof and that it is entitled to
    judgment as a matter of law.” Wells Fargo Bank, 
    231 Ariz. at 211, ¶ 1
    . The
    party asserting a claim always bears the ultimate burden of persuasion,
    Ariz. R. Evid. 301, and “the mere absence of a genuine dispute of material
    fact does not automatically entitle” that party to judgment. Wells Fargo Bank
    at 211-13, ¶¶ 1, 16.
    ¶8            We review a grant of summary judgment de novo, Dreamland
    Villa Cmty. Club, Inc. v. Rainey, 
    224 Ariz. 42
    , 46, ¶ 16 (App. 2010), “view[ing]
    the facts and reasonable inferences in the light most favorable to the
    non-prevailing party,” Rasor v. Nw. Hosp., LLC, 
    243 Ariz. 160
    , 163, ¶ 11
    (2017).
    I.     Liquidated Damages
    ¶9            The Youngs contend that the “non-refundable deposit of
    $80,000.00” was an unenforceable penalty. Because contract remedies are
    compensatory in nature and not punitive, a contract term providing a
    punitive remedy for breach of contract is unenforceable as a matter of
    public policy. Dobson Bay Club II DD, LLC v. La Sonrisa de Siena, LLC, 
    242 Ariz. 108
    , 110, ¶ 9 (2017).
    ¶10             However, parties to a contract can agree in advance to an
    amount of liquated damages should either party breach. 
    Id. at 110, ¶8
    . And
    liquidated damages provisions are enforceable if they are intended “to
    compensate the non-breaching party rather than penalize the breaching
    party.” 
    Id.
     at 109 ¶ 1. The party seeking to avoid enforcement of a liquidated
    damages clause—here, the Youngs— “has the burden of persuading [the
    3
    YOUNG, et al. v. ALLEN HOMES
    Decision of the Court
    court] that the provision imposes an unenforceable penalty.” 
    Id. at 112, ¶ 17
    . Whether a contract provides for proper liquidated damages, or an
    improper penalty is an issue of law we review de novo. Id. at ¶ 18.
    ¶11            The Arizona Supreme Court in Dobson Bay adopted the
    Restatement (Second) of Contracts § 356(1) to test the enforceability of a
    liquidated damages provision. Id. at 111, ¶ 15. Section 356(1) provides that
    a liquidated damages provision will be enforced “but only at an amount
    that is reasonable in the light of the anticipated or actual loss caused by the
    breach and the difficulties of proof of loss.” Id. at ¶ 12. Thus, courts must
    consider “(1) the anticipated or actual loss caused by the breach, and (2) the
    difficulty of proof of loss.” Id.
    A.     Anticipated Loss
    ¶12           On its face, the nonrefundable deposit is an inflexible forecast
    of losses that does not “var[y] with the nature and extent of the breach.”
    Pima Sav. & Loan Ass’n v. Rampello, 
    168 Ariz. 297
    , 300 (App. 1991). Whether
    the Youngs breached on the first day of the contract or the hundredth day,
    they would lose the entire $80,000.00. This fixed amount weighs against
    concluding that the deposit was a reasonable estimate of anticipated losses
    at the time the contract was entered into. See Dobson Bay, at 112, ¶ 21
    (holding that a late fee was unenforceable in part because it was “static”
    and “payable on demand whether the payment [was] one day late or one
    year late.”) And the contract is silent about what anticipated costs or
    damages went into arriving at the $80,000.00 figure. On this record, we
    cannot say that $80,000.00 was a reasonable estimate of anticipated losses
    at the time the contract was entered.
    B.     Actual Loss
    ¶13          But a liquidated damages clause may also be based on actual
    losses under the Second Restatement. And Allen Homes presented some
    evidence of its actual damages, including superintendent costs,
    opportunity costs, and pre-construction work.
    ¶14           First, the contract was entered into April 20, 2018, and the
    Youngs cancelled September 15, 2018. During those five months, Allen
    Homes retained a superintendent for the project at the cost of $900.00 per
    week. Thus, the record shows that Allen Homes suffered roughly
    $18,900.00 in damages (21 weeks x $900.00 per week) by way of payment to
    its superintendent.
    4
    YOUNG, et al. v. ALLEN HOMES
    Decision of the Court
    ¶15          Second, Allen Homes claims “the non-refundable deposit was
    in place because [it] was required to forego other opportunities to build
    homes for clients due to its commitments and obligations” to the Youngs.
    And the record contains evidence that Allen Homes passed up as many as
    two potential home-building projects because of its contract with the
    Youngs.
    ¶16           Third, Allen homes contends the non-refundable deposit
    “provided payment for . . . pre-construction work for [the Youngs’] home,
    such as (1) applying for septic tank permits; (2) clarifying scopes of work
    for Trades; (3) selections of finishes and materials for the home; (4)
    obtaining additional bids from Trades; and (5) creating a construction
    schedule.”
    ¶17             Even so, summary judgment for Allen Homes was not
    warranted because the record did not establish actual damages with
    “undisputed admissible evidence that would compel any reasonable juror
    to find in its favor.” Wells Fargo Bank, 231 Ariz. at ¶ 18. Allen Homes did not
    assign any dollar amount to the lost contracts, and Allen Homes offered no
    monetary value of its alleged pre-construction work. And while the Youngs
    did not present any evidence to contradict the losses Allen Homes’ claims,
    that is not enough. See Wells Fargo Bank, 
    231 Ariz. at 211, ¶¶ 1, 16
     (“[T]he
    mere absence of a genuine dispute of material fact does not automatically
    entitle a plaintiff to judgment.”).
    ¶18           Consequently, we reverse the grant of summary judgment for
    Allen Homes, including its award of attorney’s fees and costs, and remand
    for further proceedings. To be clear, we do not conclude that the $80,000.00
    provision is necessarily unenforceable, only that on this record $80,000.00
    does not reasonably reflect Allen Homes’ actual losses. On a fuller factual
    record, the superior court may or may not conclude otherwise. See Orme
    School v. Reeves, 
    166 Ariz. 301
    , 311 fn. 10 (1990) (“Discovery is complete
    when the parties have completed all the discovery they intend, when they
    have completed the discovery allowed by the court, [or] when the time for
    discovery allowed by rule of the court has expired . . . .“).
    II.    Mutual Mistake of Fact
    ¶19          The Youngs also claim that their contract was unenforceable
    because they and Allen Homes made a mutual mistake of fact about the
    HOA building plan approval. We disagree.
    ¶20          A party seeking to void a contract based on a mutual mistake
    of fact must prove that “(1) the parties made a mistake about a basic
    5
    YOUNG, et al. v. ALLEN HOMES
    Decision of the Court
    assumption on which they made the contract, (2) the mistake had a material
    effect on the exchange of performances, and (3) the party seeking avoidance
    does not bear the risk of mistake.” Hall v. Elected Officials’ Ret. Plan, 
    241 Ariz. 33
    , 42, ¶ 25, (2016) (citing the Restatement (Second) of Contracts § 152(1)
    (1981)).
    ¶21           According to the Youngs, “the mutual mistake was the
    assumption the building plans specifically identified in the Contract
    Agreement would be approved” by the HOA “and the residence built to
    these specifications.” Because the HOA did not approve the building plans,
    the Youngs argue a mutual mistake of material fact arose that voided the
    contract.
    ¶22          The Youngs agree that the contract placed the onus on them
    to obtain not just city permits, but also HOA approval. The contract
    acknowledged that the building plans had not yet been approved and “may
    change,” even providing a process for change orders to the building plans.
    ¶23           Though the Youngs submitted their initial building plans to
    the HOA, they acknowledge they opted not to re-submit the amended plans
    for final HOA approval because they were dissatisfied with the changes to
    the plans the HOA required and “cancelled the Construction Agreement.”
    Whether the HOA’s required changes to the building plan specifications
    were minor in nature, or material in nature (a distinction the Youngs press),
    their contractual obligation to obtain “all additional permits necessary” to
    complete the project remained unchanged. On this record, no mutual
    mistake of material fact existed.
    CONCLUSION
    ¶24            For the foregoing reasons we reverse and remand.
    AMY M. WOOD • Clerk of the Court
    FILED:    JT
    6
    

Document Info

Docket Number: 1 CA-CV 21-0740

Filed Date: 9/29/2022

Precedential Status: Non-Precedential

Modified Date: 9/29/2022