Kaman Aerospace Corp. v. Arizona Board of Regents ( 2007 )


Menu:
  •                                                                 FILED BY CLERK
    IN THE COURT OF APPEALS                  AUG 23 2007
    STATE OF ARIZONA                      COURT OF APPEALS
    DIVISION TWO                          DIVISION TWO
    KAMAN AEROSPACE                            )
    CORPORATION, a Delaware                    )         2 CA-CV 2006-0177
    corporation,                               )         DEPARTMENT A
    )
    Plaintiff/Counterdefendant/   )         OPINION
    Appellee/Cross-Appellant,    )
    )
    v.                     )
    )
    THE ARIZONA BOARD OF REGENTS,              )
    UNIVERSITY OF ARIZONA,                     )
    a political subdivision of the State of    )
    Arizona,                                   )
    )
    Defendant/Counterclaimant/     )
    Appellant/Cross-Appellee.     )
    )
    APPEAL FROM THE SUPERIOR COURT OF PIMA COUNTY
    Cause No. C20045114
    Honorable Carmine Cornelio, Judge
    REVERSED IN PART, AFFIRMED IN PART
    Fennemore Craig, P.C.
    By George O. Krauja and Erwin D. Kratz                                             Tucson
    Attorneys for
    Plaintiff/Counterdefendant/
    Appellee/Cross-Appellant
    Lewis and Roca LLP
    By Brian J. Pollock, Lawrence A. Kasten,                                         Phoenix
    and Dale A. Danneman                                                        Attorneys for
    Defendant/Counterclaimant/
    Appellant/Cross-Appellee
    B R A M M E R, Judge.
    ¶1            The Arizona Board of Regents (ABOR)1 appeals from a judgment entered after
    a jury rendered its verdict in favor of Kaman Aerospace Corporation (Kaman) on ABOR’s
    counterclaim for breach of contract and Kaman’s breach of contract claim, awarding Kaman
    $0. ABOR asserts the trial court erred when it denied ABOR’s motions for judgment as a
    matter of law on Kaman’s claim because there was no written agreement obligating it to
    compensate Kaman for additional work and because Kaman had failed to prove an authorized
    signatory had executed contract modifications on ABOR’s behalf. ABOR contends that
    Kaman failed to prove the damages element of its claim and failed to establish that ABOR’s
    breach was material. ABOR also argues Kaman’s breach of contract claim was untimely and
    that the trial court erred in denying ABOR’s motions for a new trial on that claim and on the
    1
    At trial and on appeal, the parties and the trial court use the term “the University”
    interchangeably with “ABOR.”
    2
    jury’s verdict in Kaman’s favor on ABOR’s counterclaim for damages. Kaman cross-
    appeals, asserting the court erred by not awarding it attorney fees as the prevailing party at
    trial.
    Factual and Procedural Background
    ¶2            We view “the evidence in a light most favorable to upholding the jury
    verdict[s].” Hutcherson v. City of Phoenix, 
    192 Ariz. 51
    , ¶ 13, 
    961 P.2d 449
    , 451 (1998).
    ABOR is the governing body of the University of Arizona; the astronomy department of the
    University “has a research wing called Steward Observatory.” The observatory has a mirror
    laboratory, “a unique facility in the world,” that makes large mirrors with “unique properties”
    to exacting specifications. In March 2003, ABOR entered into a fixed price contract with
    Lockheed Martin, effective September 2001, for ABOR to “[d]esign, develop, fabricate,
    assemble, test, deliver, and support integration of a 6.5 [meter] class Collimator” for
    approximately $32 million. A collimator was described at trial as “a telescope operating in
    reverse”; it would be used to test the accuracy of space telescopes while they were still on
    earth.
    ¶3            The mirror laboratory’s manager testified “the scope of the project was larger
    than the observatory could handle alone during the time that Lockheed . . . wanted delivery.”
    Accordingly, ABOR decided to partner with Kaman. ABOR was to provide the mirrors, and
    Kaman would be responsible for providing support and control components of the collimator.
    3
    ¶4             Kaman and ABOR entered into a written contract on December 20, 2001. It
    listed a “Firm Fixed Price” of $9,083,269 for the components Kaman was to provide. The
    contract contained a statement of work (SOW)2 , which described various tasks Kaman was
    expected to perform, and identified certain “billing milestones” when Kaman was to be
    compensated for completing various tasks from March 2002 to May 2006. The SOW listed
    three documents that provided its basis.
    ¶5             Paragraph four of the contract stated the “proposal reflects a fixed price for the
    effort proposed. In the event that there is a modification to the work scope, a modified level
    of effort will be indicated in a revised scope of work to be agreed upon by the parties at the
    time of modification.” Part of paragraph two of the “terms and conditions of sale” attached
    to the contract stated, “[a]fter acceptance by [Kaman] any change of specification/drawings
    manufacturing process delivery schedule and/or quantity may be made only with [Kaman’s]
    written consent and at a charge which [Kaman] shall determine reasonably sufficient to cover
    its additional costs.”
    ¶6              Eleven modifications were entered into by the parties. Relevant here are
    modifications two and four. Modification two, dated May 31, 2002, provided a new SOW,
    now based on six documents, including the original three and “design guidelines” from the
    University.
    2
    ABOR asserts, and Kaman does not dispute, that the “Statement of Work” describes
    the “work scope,” a term that is used in other parts of the contract.
    4
    ¶7            Modification number four, dated August 16, 2002, increased the total value of
    the contract to $12,800,000. This modification included a new “terms and conditions of
    sale,” with a revised paragraph two, that stated in part, “After acceptance by [Kaman] any
    change of specification/drawings manufacturing process delivery schedule and/or quantity
    may be made only with both parties’ written agreement and at a charge which [Kaman] and
    [ABOR] shall determine reasonably sufficient to cover any additional costs.”
    ¶8            Mark Yokley, the program manager for Kaman, testified that when the parties
    agreed to the May 2002 SOW, there were ten design guidelines in existence that formed the
    basis of 222 requirements. Nearly two years later, when Kaman presented its claim to
    ABOR, Yokley stated there had been forty-six revisions or additions to the design guidelines
    leading to a total of seventeen design guidelines and 472 requirements, although only sixty-
    three of the requirements were “really new.”        Yokley testified twenty-three of the
    requirements were more difficult to perform.
    ¶9            On December 18, 2003, Kaman gave ABOR a “very preliminary, rough”
    estimate of what it claimed were additional costs in its “new scope and new/changed
    requirements list.” This proposal listed twenty-eight “new requirement description[s]” and
    an explanation for each charge, with a “total estimated price impact” of $3,821,400. In
    January 2004, ABOR wrote a letter to Kaman, rejecting most of Kaman’s claims and stating
    that “most derive from a failure by Kaman to perform to the statement of work and teaming
    agreement.” Twenty-five of the twenty-eight claims were rejected with supporting rationale,
    5
    two were accepted “pending a full cost proposal,” and one was accepted and a new contract
    was formed with respect to this item, a “dual-use collimator support structure study.”
    ¶10            Kaman then assembled a claim, presenting it to ABOR on April 5, 2004. This
    claim listed twenty-nine separate items at a cost totalling approximately $6.25 million. Three
    of the claims were accepted by ABOR “pending cost evaluation” with a fourth, the support
    structure study, having already been accepted. The rest of the claims were rejected by
    ABOR. In July 2004, Kaman filed a notice of claim through counsel pursuant to A.R.S.
    § 12-821.01 as to ABOR, stating its “claim can be settled for $6,250,110.”
    ¶11            Kaman stopped work on September 17, 2004, and sued ABOR, alleging that
    “[a]fter the parties agreed to the SOW, [ABOR] changed, increased and added new work
    scope and work effort requirements,” and failed to compensate Kaman for the increased
    work.       Kaman’s complaint included counts of breach of contract, negligent
    misrepresentation, unjust enrichment, and quantum meruit.3 ABOR filed a counterclaim in
    which it alleged Kaman had breached the subcontract by failing to fulfill its obligations and
    by abandoning performance.        At the time Kaman sued, ABOR had paid Kaman
    approximately $9.3 million of the $12.8 million contract.
    3
    In December 2004, the trial court granted ABOR’s motions to dismiss Kaman’s
    quantum meruit and unjust enrichment claims, and it granted ABOR’s motion for summary
    judgment on Kaman’s negligent misrepresentation claim in February 2006. Kaman does not
    challenge these rulings.
    6
    ¶12           ABOR also filed a request for a provisional remedy of partial specific
    performance or for replevin simultaneously with filing its counterclaim. The court granted
    the request for replevin upon ABOR’s posting of a $4 million bond. ABOR also gave
    Kaman an additional $1.1 million for parts and materials not covered by the replevin order.
    ¶13           ABOR filed a motion for summary judgment in October 2005, arguing the
    contract between the parties required a written modification and none had been made; any
    purported oral modification of the contract was impermissible under its terms; and, the
    ABOR employees that Kaman argued had modified the contract lacked the authority to enter
    into contracts on behalf of ABOR. Kaman responded that the changes to the design
    guidelines changed the work it was required to perform, and that the contract between the
    parties required ABOR to compensate Kaman for this additional work. The court denied
    ABOR’s motion, stating, “a jury could find that since the SOW is based partly on the design
    guidelines, a significant change to the design guidelines changes Kaman’s level of effort,
    thus triggering either Paragraph 2 of the revised Terms and Conditions or Paragraph 4 of the
    contract, which calls for modification of Scope of Work.” It also found that whether the
    design guidelines were specifications was a factual issue for the jury.
    ¶14           ABOR filed a second motion for summary judgment in December 2005,
    arguing that, during the negotiations as to modification two, “Kaman agreed to drop its
    demand that it could be paid extra for changes to Applicable Documents. . . . [and therefore]
    Kaman cannot now claim that a modification to [the design guidelines that are a part of the]
    7
    Applicable Documents could entitle it to extra payments.” The court rejected this argument
    as well, stating that even with this new information, a jury could conclude that “although the
    University chose to enact changes by characterizing them as revisions to the Design
    Guidelines, it did not mean that . . . they did not cause significant changes to Kaman’s work
    as specifications.”
    ¶15           At the close of Kaman’s case, ABOR again moved for judgment, which the
    trial court denied. After the verdict, ABOR renewed its motion and moved for a new trial,
    both of which the court denied. This appeal followed.
    Discussion
    Denial of Judgment as a Matter of Law - Kaman’s Breach of Contract Claim
    ¶16           ABOR contends the trial court erred in denying its motions for judgment as a
    matter of law and by allowing the jury to interpret the contract. We review de novo a trial
    court’s ruling on a motion for judgment as a matter of law. Monaco v. HealthPartners of S.
    Ariz., 
    196 Ariz. 299
    , ¶ 6, 
    995 P.2d 735
    , 738 (App. 1999). Such a “motion should be granted
    if the facts produced in support of the claim or defense have so little probative value, given
    the quantum of evidence required, that reasonable people could not agree with the conclusion
    advanced by the proponent of the claim or defense.” Orme Sch. v. Reeves, 
    166 Ariz. 301
    ,
    309, 
    802 P.2d 1000
    , 1008 (1990).
    ¶17           ABOR asserts Kaman’s breach of contract claim must fail because “only a
    designated contracting officer of the State can bind the University.” It states, “Kaman has
    8
    never alleged (and cannot allege) that any officially designated contracting officer ever
    assented to any agreement, written or otherwise, to pay Kaman more than the fixed price.”
    ABOR contends that, even if changes to the design guidelines could constitute a written
    agreement, ABOR need not pay for those changes, reasoning that “[n]o University
    contracting officer was ever involved in (let alone signed) the Design Guidelines [as they]
    were promulgated by the Steward engineers on the job site.”
    ¶18            As stated above, the trial court denied several motions ABOR made for
    judgment as a matter of law on this issue. At trial during closing arguments, Kaman’s
    counsel stated:
    Kaman is not saying that when these program people agreed on
    technical requirements, technical changes, that a price increase
    was automatically agreed to, automatically created. But we are
    saying that when technical changes were made [it] beg[a]n a
    process that should have resulted in a contracts person
    ultimately agreeing on a contract modification.
    The trial court instructed the jury that, “[o]nly personnel with authority to enter into contracts
    on behalf of the University of Arizona can bind the University to contractual promises. That
    is, the University of Arizona cannot be held liable for breaching any contractual promise
    agreed to by unauthorized personnel.”
    ¶19            ABOR Policy Number 3-103(A) states that “University officers designated by
    the president of the university, as certified to the Executive Director, are authorized to
    execute contracts and other written instruments on behalf of the Board.” Pursuant to this
    policy, a July 2001 designation by the University’s president certified nine officers “as
    9
    authorized signatories to execute contracts and other written instruments on behalf of The
    University of Arizona and [ABOR].” Two officers so designated were the Director and
    Sponsored Contract Officer of the Office of Research and Contract Analysis, positions that
    were held by Richard Haney and Lee Anne Peters, respectively. The contract between
    Kaman and ABOR was signed by Peters on behalf of ABOR, and all eleven modifications
    were signed by either her or Haney. The changes to the design guidelines were not signed
    by any University official with contracting authority.4
    ¶20           ABOR contends that the state “can never be bound by unauthorized acts of its
    employees,” a statement that Kaman does not dispute. ABOR is a state agency. City of
    Tempe v. Ariz. Bd. of Regents, 
    11 Ariz. App. 24
    , 25, 
    461 P.2d 503
    , 504 (1969). Arizona law
    is clear that “persons dealing with public officers are bound, at their peril, to know the extent
    and limits of their power and that no right can be acquired except that predicated upon
    authorized acts of such officers.” Pinal County v. Pomeroy, 
    60 Ariz. 448
    , 455, 
    139 P.2d 451
    ,
    454-55 (1943); Bigler v. Graham County, 
    128 Ariz. 474
    , 477, 
    626 P.2d 1106
    , 1109 (App.
    1981) (same). Other jurisdictions have reached similar conclusions. See, e.g., Kondos v. W.
    Va. Bd. of Regents, 
    318 F. Supp. 394
    , 397 (S.D. W. Va. 1970) (“[I]t has long been firmly
    established in West Virginia that the state may not be held liable for illegal or unauthorized
    acts of its officers.”); People ex rel. Dunbar v. Dist. Court In and For Chaffee County, 255
    4
    Most were not signed at all, although some included Steward engineers’ typewritten
    names and some were dated.
    
    10 P.2d 743
    , 748 (Colo. 1953) (“‘The state can act only by its agents, duly authorized by law;
    and since public officers cannot bind the government they represent by acts outside their
    express authority, even though within their apparent powers, it is only where officers of the
    state perform their acts agreeably to the authority delegated them that the state is bound.’”),
    quoting State ex rel. Caton v. Indus. Comm’n, 
    61 N.E.2d 806
    , 807 (Ohio Ct. App. 1945).
    And the United States Supreme Court has stated, “Whatever the form in which the
    Government functions, anyone entering into an arrangement with the Government takes the
    risk of having accurately ascertained that he who purports to act for the Government stays
    within the bounds of his authority.” Fed. Crop Ins. Corp. v. Merrill, 
    332 U.S. 380
    , 384, 
    68 S. Ct. 1
    , 3 (1947).5
    ¶21           Kaman responds that
    [t]he parties’ conduct throughout the course of performing the
    contract shows neither side contemplated changes to the written
    Design Guidelines would require a written contract
    modification, or would need to be signed by someone in the
    University contract administration office—such Design
    Guidelines changes were left to . . . the technical program
    personnel.
    However, Kaman sought an additional six million dollars for work it thought it had
    performed or would need to perform outside of the SOW. If it wanted to be compensated for
    the work, it needed to have had someone with authority to bind ABOR sign a new contract
    5
    Kaman does not argue that these principles were altered because ABOR may have
    been acting in a proprietary, rather than governmental, capacity. Consequently, we do not
    consider this issue.
    11
    or modification. For example, when the parties entered into modification number four,
    which increased the value of the contract by nearly $4 million dollars, Peters signed the
    agreement, binding ABOR.
    ¶22           Kaman relies on a single case in its response to ABOR’s argument, Godbey v.
    Roosevelt School Dist. No. 66 of Maricopa County, 
    131 Ariz. 13
    , 21, 
    638 P.2d 235
    , 243
    (App. 1981), for the proposition that “the acts of the parties under the contract, before
    disputes arise, are the best evidence of the meaning of doubtful contractual terms.” It also
    argues “[t]he University’s conduct proves the parties[’] intent when they made the contract.”6
    ¶23           But conduct of the parties is not relevant if no authorized official bound ABOR
    to pay for the work. In a similar factual circumstance in the context of sovereign immunity,
    the Maryland Court of Special Appeals rejected an argument that a governmental entity’s
    course of conduct had modified a written contract and had bound the state, even if that course
    of conduct was identical to the parties’ intent at the time of entering into the contract. Dep’t
    of Pub. Safety & Corr. Servs. v. ARA Health Servs., Inc. (ARA I), 
    668 A.2d 960
    (Md. Ct.
    Spec. App. 1995). The Maryland Court of Appeals affirmed. ARA Health Servs., Inc. v.
    Dep’t of Pub. Safety & Corr. Servs. (ARA II), 
    685 A.2d 435
    (Md. 1996).7 There, ARA, a
    6
    Because Kaman does not argue that ABOR, by later accepting claim twenty-seven
    and entering into a new contract, somehow ratified the conduct of the ABOR engineers, we
    do not address the issue.
    7
    In that case, the Maryland Court of Appeals affirmed the Maryland Court of Special
    Appeals on the same basis and for the same reasons the lower court used to reach its
    conclusion. We have primarily relied on the intermediate appellate court’s opinion because
    of the slightly more detailed factual summary it provides.
    12
    provider of health care services to prison inmates, sought reimbursement from the
    Department for the cost of Acquired Immune Deficiency Syndrome (AIDS) medication.
    ARA 
    I, 668 A.2d at 962
    . ARA had entered into a contract with the Department, which had
    been approved as required by the Board of Public Works, to provide health care services to
    Maryland inmates. 
    Id. at 963-64;
    see also ARA II, 
    685 A.2d 436-37
    . The contract also
    provided ARA was to receive additional compensation for AIDS medication delivered to all
    inmates who were hospitalized, but was not to get this excess compensation for medication
    dispensed in correctional facilities.    ARA 
    I, 668 A.2d at 963-64
    .        A subsequent and
    retroactive modification approved by the Board, however, provided that the Department
    would reimburse ARA for all costs of AIDS medication no matter where the prisoners were
    located, but failed to account for an eighteen-month period starting from the beginning of the
    initial contract and ending on the effective date of the modification. 
    Id. at 964;
    see also ARA
    II, 
    685 A.2d 437
    . Regardless, ARA had already been paid roughly $135,000 by the
    Department in compensation for the eighteen-month period. ARA 
    I, 668 A.2d at 964
    .
    ¶24           State auditors objected to the payment and later withheld money in that amount,
    and an administrative agency rejected ARA’s claim for reimbursement. 
    Id. The trial
    court
    reversed, finding that although the contract was unambiguous on its face and would not
    entitle ARA to reimbursement for the eighteen-month period, by their course of conduct the
    parties had modified the contract. 
    Id. at 964-65.
    The court relied on the Department’s
    payments to ARA for the eighteen-month period and its attempt to defend its policy to the
    13
    auditors, even going so far as to state that it “had contemplated from the beginning that [it]
    would reimburse [ARA] for its expenses in providing AIDS medication . . . [and] that the
    $135,446.00 in disputed payments were in accord with the intent of the parties.” 
    Id. ¶25 On
    appeal, ARA contended that the parties had modified the contract by their
    conduct. 
    Id. at 965.
    The Department argued, however, that ARA’s claim was “barred by
    sovereign immunity because its officials who engaged in the conduct that allegedly modified
    its Contract . . . had no authority to do so.” 8 
    Id. at 967.
    The appellate court looked at a
    number of Maryland statutes and regulations and found the Department lacked the authority
    to create the modification because the contract had not been subjected to the required
    approval procedures. 
    Id. at 968.
    The court held that, “[i]n the absence of actual authority,
    the State may avoid the contract, regardless of the reasonableness of the beliefs of the other
    party.” 
    Id. at 969.
    As noted above, the Maryland Court of Appeals affirmed, stating, “The
    purported modification was not approved by the Board of Public Works, and thus exceeded
    the scope of the [Department’s] authority. Furthermore, as between [ARA] and the public
    generally, [ARA] bears the risk of injury posed by the unauthorized conduct of a public
    agent.” ARA 
    II, 685 A.2d at 440
    .
    8
    As the court in ARA I noted, Maryland law “provides that, in order to avoid the bar
    of sovereign immunity, a contract claim against the State must be based on a written contract
    executed by a State employee ‘within the scope of [his or her] authority.’” ARA 
    I, 668 A.2d at 967
    , quoting Md. Code Ann., State Gov’t § 12-201.
    14
    ¶26           ARA I is relevant for several reasons. Initially, it demonstrates that a course
    of conduct by unauthorized state officials cannot bind the state. This result obtains despite
    the evidence of the Department’s unambiguous intent to compensate ARA for medication
    it provided during the eighteen-month period; indeed, the Department argued this intent to
    the state auditors. This case also shows that, absent approval by an authorized official, the
    state simply could not be required to compensate ARA, regardless of what the parties had
    intended. Similarly here, the Steward engineers could not bind ABOR in contract, even if,
    when they changed the design guidelines, they had intended ABOR would be bound to pay
    additional costs to Kaman.
    ¶27           Nothing in paragraph two of the terms and conditions changes this result. This
    paragraph provides: “After acceptance by [Kaman] any change of specification/drawings
    manufacturing process delivery schedule and/or quantity may be made only with both parties’
    written agreement and at a charge which [Kaman] and [ABOR] shall determine reasonably
    sufficient to cover any additional costs.” Kaman argues this language bound ABOR to a
    process by which a Steward engineer would agree to a change to design guidelines, and at
    some later time an ABOR officer with contracting authority would evaluate and accept
    Kaman’s claim for the work. Thus, under Kaman’s interpretation, a design guideline change
    agreed to by engineers for the respective parties would bind ABOR to negotiate and agree
    on a reasonable price for the change.
    15
    ¶28           However, Kaman’s interpretation cannot overcome the fact that, until an
    ABOR officer with contracting authority executed a document embodying both the change
    and its cost, ABOR was not bound.           Furthermore, although an ABOR official with
    contracting authority agreed to the language in paragraph two, we cannot conclude such a
    contractual provision could further delegate contracting authority to the engineers at the
    observatory. Any such delegation would be contrary to ABOR Policy Number 3-103(A),
    which only provides for the president to “delegate his/her authority to execute contracts . . .
    without certification to the Executive Director,” and even the president can only delegate this
    authority for obligations under $10,000 and when it “does not unduly expose the Board or
    the university to financial loss.” See Clay v. Ariz. Interscholastic Ass’n, Inc., 
    161 Ariz. 474
    ,
    476, 
    779 P.2d 349
    , 351 (1989) (“[A]n [administrative] agency must follow its own rules and
    regulations; to do otherwise is unlawful.”); Porta House, Inc. v. Scottsdale Auto Lease, Inc.,
    
    120 Ariz. 115
    , 119, 
    584 P.2d 579
    , 583 (App. 1978) (persons dealing with public entity
    “charged with notice” of extent and limits of its power); Sch. Dist. No. One of Pima County
    v. Lohr, 
    17 Ariz. App. 438
    , 439, 
    498 P.2d 512
    , 513 (App. 1972) (same); see also Schaefer
    v. Anne Arundel County, Md., 
    17 F.3d 711
    , 713 (4th Cir. 1994) (governmental entity’s
    authorized purchasing agent had no power to delegate authority to others to sign contracts);
    Peck v. Board of Ed. of Yuma Union High Sch. Dist., 
    126 Ariz. 113
    , 115, 
    612 P.2d 1076
    ,
    1078 (App. 1980) (school board cannot delegate functions to superintendent when it “would
    circumvent the language of the statute”).
    16
    ¶29           “The same principles of construction that apply to statutes also apply to
    administrative rules and regulations,” Kimble v. City of Page, 
    199 Ariz. 562
    , ¶ 19, 
    20 P.3d 605
    , 608 (App. 2001), and a public entity’s regulations, if consistent with its statutory
    scheme, “are entitled to be given the force and effect of law,” Civil Service Commission of
    City of Tucson v. Foley, 
    75 Ariz. 364
    , 368-69, 
    257 P.2d 384
    , 387 (1953). Therefore, ABOR
    officials with contracting authority could not delegate contract-modification authority to the
    Steward engineers, regardless of the language of paragraph two. Moreover, even if a
    contracting officer could delegate his or her authority, nothing in the contract clearly does
    so here. See 
    Dunbar, 255 P.2d at 748
    (“‘Public officers cannot bind the government they
    represent by acts outside their express authority.’”), quotinq 
    Caton, 61 N.E.2d at 807
    ;
    Lutzken v. City of Rochester, 
    184 N.Y.S.2d 483
    , 501 (N.Y. App. Div. 1959) (“[W]here there
    is a lack of authority on the part of agents of a [governmental entity] to create a liability,
    except by compliance with well-established regulations, no liability can result unless the
    prescribed procedure is complied with and followed.”).
    ¶30           Because the Steward engineers were not authorized by ABOR to bind it in
    contract, Kaman’s breach of contract claim must fail as a matter of law. See 
    Pomeroy, 60 Ariz. at 455
    , 139 P.2d at 454-55; 
    Bigler, 128 Ariz. at 477
    , 626 P.2d at 1109. The trial court
    therefore erred in denying ABOR’s motions for judgment as a matter of law on this issue.
    In light of this conclusion, we need not address ABOR’s argument that the court erred in
    allowing Kaman’s breach of contract claim to be decided by a jury in the absence of a written
    17
    agreement. Nor need we consider ABOR’s contention that the jury’s award of $0 to Kaman
    “negated an essential element of Kaman’s breach of contract claim and compelled entry of
    judgment” for ABOR, or that this finding mandated a new trial because it was inconsistent
    with its determination that ABOR had breached the contract. Neither do we address ABOR’s
    assertion that the trial court “erroneously admitted evidence regarding a supposed oral
    agreement between [ABOR] and Kaman” because this claim solely concerns Kaman’s breach
    of contract claim. Finally, we need not consider ABOR’s arguments that Kaman’s breach
    of contract claim was untimely under the notice of claim statute and the statute of limitations,
    or that Kaman’s evidence was insufficient to establish breach of contract damages, or that
    any breach by ABOR was not material.
    Judgment as a Matter of Law - ABOR’s Counterclaim
    ¶31           ABOR contends that, if this court “finds that judgment was improperly entered
    for Kaman on Kaman’s breach of contract claim, [we] should direct the trial court to enter
    judgment for the University on its breach of contract counterclaim.” In its underdeveloped
    argument, ABOR asserts “Kaman’s sole defense to [ABOR’s breach of contract] claim has
    always been that its performance under the Subcontract was excused because of the
    University’s alleged material breach,” and, if ABOR did not breach the contract, ABOR must
    18
    be successful as a matter of law on its counterclaim.9 We note ABOR has not asked us to
    remand its counterclaim for a new trial.
    ¶32           Before the jury announced its verdict, ABOR asked the trial court to give
    special interrogatories to the jury, a request the court declined. After the jury found in
    Kaman’s favor on ABOR’s breach of contract counterclaim, but failed to provide a verdict
    on Kaman’s claim against ABOR, ABOR again sought special interrogatories. The court
    simply sent the jury back to deliberate all claims after having provided it with additional
    instructions. The jury then returned two general verdicts, both in favor of Kaman, on its own
    breach of contract claim and on ABOR’s counterclaim. “A general verdict implies a finding
    by the jury on every essential fact in favor of the prevailing party.” Lohmeier v. Hammer,
    
    214 Ariz. 57
    , ¶ 14, 
    148 P.3d 101
    , 106 (App. 2006).
    ¶33           Because it was a general verdict, we cannot know the basis of the verdict in
    favor of Kaman on ABOR’s counterclaim. Our legal conclusion that a duly authorized
    contracting officer did not bind the state does not necessarily preclude the jury’s factual
    9
    Kaman did not respond directly to this argument, but rather confined itself to
    explaining how the jury could have both found for Kaman but awarded it no damages.
    Although we may regard this failure to specifically respond as a confession of error as to any
    debatable issue, we are not required to do so. See Ariz. Minority Coal. for Fair Redistricting
    v. Ariz. Indep. Redistricting Comm’n, 
    211 Ariz. 337
    , n.28, 
    121 P.3d 843
    , 869 n.28 (App.
    2005).
    19
    finding on a separate cause of action that Kaman did not breach the contract.10 ABOR fails
    to cite any authority supporting its position, and we decline to agree with it.11
    ¶34           Moreover, the jury was instructed that “[t]o succeed on a breach of contract
    claim, the party bringing the claim has the burden of proving the existence of a contract, the
    other side’s breach of the contract, and that it has incurred damages as a result of the other
    side’s breach.” And, it was told that “[i]n order to recover damages for breach of contract,
    a party must prove the amount of those damages with reasonable certainty.” Throughout the
    trial, Kaman extensively cross-examined the witnesses ABOR had used to prove its damages,
    including questioning the need for various expenditures, the hours ABOR had billed in its
    efforts to complete Kaman’s work, the accuracy of ABOR’s estimates of projected damages,
    10
    Indeed, the jury could possibly have concluded that ABOR was not entitled to
    prevail on its breach of contract claim because it had anticipatorily breached the contract by
    requesting additional work for which it had no intention of paying, even if the jury was
    unable to find as a matter of law on Kaman’s theory of the case that ABOR had breached the
    original contract by agreeing to changes in the design guidelines, thus binding ABOR to pay
    Kaman additional compensation.
    11
    In its citation of supplemental authority, ABOR lists several cases in which an
    appellate court overturned a general verdict and remanded the case for a new trial because
    of trial error and because it was impossible for the court to tell whether the jury erroneously
    found for the party. See Wiggs v. City of Phoenix, 
    198 Ariz. 367
    , ¶ 17, 
    10 P.3d 625
    , 629-30
    (2000); S. Cas. Co. v. Hughes, 
    33 Ariz. 206
    , 218-19, 
    263 P. 584
    , 588-89 (1928); Bruce
    Church, Inc. v. United Farm Workers of Am., 
    169 Ariz. 22
    , 34-35, 
    816 P.2d 919
    , 931-32
    (App. 1991); Lewin v. Miller Wagner & Co., 
    151 Ariz. 29
    , 34-35, 
    725 P.2d 736
    , 741-42
    (App. 1986). These cases are inapposite, however, for in none did the appellate court enter
    judgment on a counterclaim because of the reversal of the verdict on the principal claim.
    Only Lewin involved a counterclaim, which went unchallenged on appeal, although the
    defendants were successful in their attempt to reverse and remand for new trial a general
    verdict against them in the plaintiffs’ malpractice 
    claim. 151 Ariz. at 37
    , 725 P.2d at 744.
    20
    and whether some of the supplies ABOR had ordered could otherwise be reused by it. And,
    during closing arguments, Kaman disputed the damages claimed by ABOR, calling ABOR’s
    estimates “inherently unreliable,” and generally disputed ABOR’s damage calculations.
    Whether ABOR had proven its damages with reasonable certainty was a materially disputed
    fact. For us to enter judgment as a matter of law in favor of ABOR on its counterclaim, we
    would be required to resolve these disputed facts. See Silva v. De Mund, 
    81 Ariz. 47
    , 53, 
    299 P.2d 638
    , 642 (1956) (“If the facts are undisputed, [appellate court] will direct the rendition
    of the correct judgment.”); Henderson v. Las Cruces Prod. Credit Ass’n, 
    6 Ariz. App. 549
    ,
    553, 
    435 P.2d 56
    , 60 (1967) (“When a record is presented to an appellate court which leaves
    no question of fact to be determined and only a question of law to be determined, this Court
    may direct the entry of the judgment which should have been entered in the trial court.”).
    Because the jury could have concluded ABOR had not proved Kaman had breached the
    contract, had itself breached the contract, or had not been persuaded by ABOR’s damages
    evidence, either alternatively or collectively, we therefore affirm the trial court’s denial of
    ABOR’s motion for a new trial solely as to damages on its counterclaim.
    Cross-Appeal
    ¶35            On cross-appeal, Kaman contends the trial court erred in not awarding it, as the
    prevailing party, attorney fees pursuant to A.R.S § 12-341.01. Section 12-341.01 provides,
    in relevant part as follows: “In any contested action arising out of a contract, express or
    implied, the court may award the successful party reasonable attorney fees.” “The decision
    21
    as to who is the successful party for purposes of awarding attorneys’ fees is within the sole
    discretion of the trial court, and will not be disturbed on appeal if any reasonable basis exists
    for it.” Sanborn v. Brooker & Wake Prop. Mgmt., Inc., 
    178 Ariz. 425
    , 430, 
    874 P.2d 982
    ,
    987 (App. 1994).
    ¶36              Kaman argues that it was the prevailing party because it prevailed on its claim
    and on ABOR’s counterclaim. The trial court rejected Kaman’s request for attorney fees and
    costs, “declin[ing] to find [it] the successful party after it sought in excess of Six Million
    Dollars and it obtained zero. While it is true that [it] successfully defended the University’s
    claim, the evidence [and] work was intertwined. Accordingly, [t]he Court believes this
    matter essentially ended in a draw.” 12 In light of our reversal of the award in favor of
    Kaman on its breach of contract claim, it is no longer the prevailing party on its claim, so this
    issue is moot.
    ¶37              Because we reverse the jury’s verdict in favor of Kaman on its claim, neither
    party has prevailed on their respective claims. In similar factual situations where neither
    party prevailed on its claim at trial, appellate courts have found a trial court’s refusal to
    award attorney fees proper. Gen. Cable Corp. v. Citizens Utilities Co., 
    27 Ariz. App. 381
    ,
    385, 
    555 P.2d 350
    , 354 (1976) (“Under the facts of this case, where a complaint seeks greater
    12
    Kaman’s complaint alleged specific damages of approximately $5.9 million as well
    as damages to be determined at trial. Kaman asked the jury for approximately $2.9 million
    in “[t]otal damages” during closing arguments. ABOR asserts it asked the jury for
    approximately $10.8 million during closing arguments.
    22
    damages than the counterclaim and the trial court has denied relief to both parties, we find
    that neither party is the ‘successful party’ under the provisions of § 12-341.”); see also
    Coldwell Banker Commercial Group, Inc. v. Camelback Office Park, 
    156 Ariz. 214
    , 223-24,
    
    751 P.2d 530
    , 539-40 (App. 1987) (finding it possible to have no successful party when one
    party prevails on complaint and other party prevails on counterclaim), vacated in part on
    other grounds, 
    156 Ariz. 226
    , 
    751 P.2d 542
    (1988). The trial court did not abuse its
    discretion in declining to award attorney fees to Kaman. See 
    Sanborn, 178 Ariz. at 430
    , 874
    P.2d at 987.
    Disposition
    ¶38            We reverse the judgment in favor of Kaman on its breach of contract claim but
    affirm the judgment in its favor on ABOR’s breach of contract counterclaim. We affirm the
    trial court’s decision to deny Kaman’s request for attorney fees. Both sides have sought
    attorney fees on appeal pursuant to § 12-341.01 and Rule 21(c), Ariz. R. Civ. App. P., 17B
    A.R.S. In our discretion, we deny the parties’ requests for an award of attorney fees.
    J. WILLIAM BRAMMER, JR., Judge
    CONCURRING:
    JOSEPH W. HOWARD, Presiding Judge
    JOHN PELANDER, Chief Judge
    23
    

Document Info

Docket Number: 2 CA-CV 2006-0177

Filed Date: 8/23/2007

Precedential Status: Precedential

Modified Date: 10/30/2014

Authorities (30)

Federal Crop Ins. Corp. v. Merrill , 68 S. Ct. 1 ( 1947 )

State Ex Rel. Caton v. Industrial Commission , 76 Ohio App. 249 ( 1945 )

ARA Health Services, Inc. v. Department of Public Safety & ... , 344 Md. 85 ( 1996 )

Bigler v. Graham County , 128 Ariz. 474 ( 1981 )

General Cable Corp. v. Citizens Utilities Co. , 27 Ariz. App. 381 ( 1976 )

Southern Casualty Co. v. Hughes , 33 Ariz. 206 ( 1928 )

Arizona Minority Coalition for Fair Redistricting v. ... , 211 Ariz. 337 ( 2005 )

Orme School v. Reeves , 166 Ariz. 301 ( 1990 )

Monaco v. HealthPartners of Southern Arizona , 196 Ariz. 299 ( 1999 )

Lewin v. Miller Wagner & Co., Ltd. , 151 Ariz. 29 ( 1986 )

Bruce Church, Inc. v. United Farm Workers of America , 169 Ariz. 22 ( 1991 )

Godbey v. ROOSEVELT SCH. DIST. NO. 66, ETC. , 131 Ariz. 13 ( 1981 )

Coldwell Banker Commercial Group, Inc. v. Camelback Office ... , 156 Ariz. 214 ( 1987 )

Wiggs v. City of Phoenix , 198 Ariz. 367 ( 2000 )

Lohmeier v. Hammer , 214 Ariz. 57 ( 2006 )

Coldwell Banker Commercial Group, Inc. v. Camelback Office ... , 156 Ariz. 226 ( 1988 )

Henderson v. Las Cruces Production Credit Ass'n , 6 Ariz. App. 549 ( 1967 )

William P. Schaefer, D/B/A Schaefer Radio Company v. Anne ... , 17 F.3d 711 ( 1994 )

School District No. One of Pima County v. Lohr , 17 Ariz. App. 438 ( 1972 )

City of Tempe v. Arizona Board of Regents , 11 Ariz. App. 24 ( 1969 )

View All Authorities »