Chayce v. Path Construction ( 2024 )


Menu:
  •                                     IN THE
    ARIZONA COURT OF APPEALS
    DIVISION ONE
    CHAYCE CONCRETE, LLC, Plaintiff/Appellee,
    v.
    PATH CONSTRUCTION SOUTHWEST, LLC, et al., Defendants/Appellants.
    No. 1 CA-CV 24-0030
    FILED 10-22-2024
    Appeal from the Superior Court in Maricopa County
    No. CV2022-008136
    The Honorable Bradley H. Astrowsky, Judge
    VACATED AND REMANDED
    COUNSEL
    Husch Blackwell LLP, Phoenix
    By Brendan A. Melander
    Counsel for Defendants/Appellants
    Thrasher Law PLLC, Phoenix
    By Bobby O. Thrasher, Jr.
    Co-Counsel for Plaintiff/Appellee
    Hill, Hall & Deciancio, PLC, Phoenix
    By Christopher Robbins
    Co-Counsel for Plaintiff/Appellee
    CHAYCE v. PATH CONSTRUCTION, et al.
    Opinion of the Court
    OPINION
    Presiding Judge Jennifer B. Campbell delivered the opinion of the Court, in
    which Judge Kent E. Cattani and Judge Paul J. McMurdie joined.
    C A M P B E L L, Judge:
    ¶1             This is an appeal from the superior court’s order vacating an
    arbitration award under A.R.S. § 12-3023(A)(1) and (A)(3). We vacate the
    court’s order because it hinges on unsupported findings. We remand for
    the trial court to confirm the arbitration award.
    BACKGROUND
    ¶2           Path Construction Southwest, LLC, was the general
    contractor on a City of Scottsdale trailhead improvement project. Chayce
    Concrete, LLC, was a subcontractor hired to work on the project. Path
    sought damages related to Chayce’s alleged failure to complete its work,
    including damages arising from the project’s delayed completion. Chayce
    sought damages related to Path’s alleged failure to make payments. Both
    agreed to submit to binding arbitration to resolve the performance and
    payment disputes.
    ¶3            The parties agreed that the arbitration would be governed by
    the American Arbitration Association’s Construction Industry Arbitration
    Rules and Mediation Procedures (the AAA Rules), and that a private
    attorney would serve as the arbitrator. Consistent with AAA Rule R-24, the
    parties agreed to exchange all documents they intended to rely on, and that
    each could request production of additional relevant information.
    ¶4            Chayce served requests for production, and Path responded
    with more than 7,000 documents. Path also objected in writing to producing
    certain categories of requested documents. Path made general objections
    claiming the documents requested were irrelevant, information not in its
    possession, or were information to which both parties had access. Path also
    made specific objections indicating that it would not be producing
    documents related to third-parties’ work on the project. Path repeatedly
    confirmed that it would “be producing responsive documents related only
    to work completed by Chayce and/or to be completed by Chayce for [the
    project].”
    2
    CHAYCE v. PATH CONSTRUCTION, et al.
    Opinion of the Court
    ¶5            Three months after Path’s production and objections and only
    a few days before the arbitration hearing, Chayce raised issues with Path’s
    objections for the first time. In a pre-hearing brief, Chayce argued that
    Path’s objections constituted a deliberate refusal to provide exculpatory
    information about the possibility that third parties contributed to the
    project’s delayed completion and Path’s alleged damages. Chayce also
    argued that Path should have produced documents related to its contract
    with the City and the retention of a subcontractor to replace Chayce on the
    project. Chayce argued that it could be assumed that the undisclosed
    documents undercut Path’s narrative—but Chayce did not request that the
    arbitration be continued to allow resolution of the discovery issue. The
    arbitration hearing went forward as scheduled.
    ¶6           There is no transcript from the arbitration hearing. At the oral
    argument in the superior court on the motion to vacate the arbitration
    award, Chayce asserted that its counsel repeatedly requested a
    postponement at the arbitration hearing. But Chayce provided no evidence
    confirming that assertion. To the contrary, it was Path’s counsel who
    provided a sworn declaration stating that he did not recall any request for
    postponement being made.
    ¶7            In a post-hearing brief to the arbitrator, Chayce did not once
    refer to any previous request for postponement. Nor did it request a
    post-hearing continuance or any other proceedings at the arbitration level
    to address discovery issues. Chayce argued instead that Path’s
    nondisclosure of third-party information precluded an assessment of delay
    damages against Chayce. Chayce stated that witness Sean Lynch testified
    at the arbitration hearing that Path sought and recovered delay damages
    from other subcontractors. Chayce also argued—for the first time—that
    Path’s nondisclosure of information about its pay-application
    communications with the City entitled Chayce to an adverse inference.
    Chayce stated that Path presented no evidence that it submitted Chayce’s
    pay applications to the City.
    ¶8           The arbitrator issued a partial final award that addressed
    Chayce’s nondisclosure arguments without mentioning any postponement
    request. The arbitrator penalized Path for failing to disclose information
    about third parties’ possible contributions to the completion delay by
    precluding all delay damages. The arbitrator explained he ”refus[ed] to
    reward Path for preventing Chayce’s counsel from discovering potential,
    relevant information related to these delay issues.” In sum, Chayce
    prevailed on delay damages as a direct result of Path’s failure to produce
    relevant documents.
    3
    CHAYCE v. PATH CONSTRUCTION, et al.
    Opinion of the Court
    ¶9            The arbitrator concluded, however, that Chayce could not
    recover damages based on Path’s nondisclosure of information related to
    the status of the City’s progress payments on Chayce’s pay applications
    (which, the arbitrator noted, Chayce could have monitored by filing a
    request with the City under A.R.S. § 34-221(H)1). The arbitrator found that
    documentary evidence showed that one pay application was rejected by
    Path, and that Chayce then chose to abandon its work rather than submit a
    corrected application.
    ¶10            The arbitrator concluded that “Path did not materially breach
    the Subcontract by lawfully withholding submittal to the City or
    certification of Chayce’s Pay Applications pursuant to A.R.S. § 34-221(I),”
    which “allow[ed] Path . . . to withhold from the City a subcontractor’s pay
    application or the certification of a subcontractor’s pay application for a
    number of reasons including unsatisfactory job progress and defective
    construction work.” The arbitrator awarded Path nearly $95,000 in damages
    based on Chayce’s abandonment of its work under the subcontract, plus
    attorney’s fees and costs totaling about $77,000.
    ¶11            Path, along with its insurer, moved the superior court to
    confirm the arbitration award and enter judgment. Chayce objected and
    moved to vacate the award, arguing that the arbitrator “awarded damages
    to Path notwithstanding its withholding of critical evidence from Chayce”
    and “refused Chayce’s request to continue the matter in violation of A.R.S.
    § 12-3023(A)(3).” In briefing before the superior court, Chayce emphasized
    that Path refused to provide information regarding third-parties’ work
    despite Lynch’s testimony that Path had also blamed other subcontractors
    for the completion delay—information relevant to determining the delay
    damages that Path sought (but was not awarded). Chayce also emphasized
    that Path failed to provide information regarding pay-application
    submissions and communications to the City for Chayce’s work—
    information relevant to Chayce’s payment claims. But, contrary to Chayce’s
    representations at oral argument on appeal, Chayce never alleged—in any
    of the arbitration or superior court proceedings—that Lynch testified these
    documents existed (unlike the arbitrator’s finding that Path lawfully
    withheld the pay applications from the City).
    1      Under A.R.S. § 34-221(H), “[a] subcontractor . . . may notify the
    purchasing agency in writing requesting that the subcontractor . . . be
    notified by the purchasing agency in writing within five days after payment
    of each progress payment that is made to the contractor,” with the request
    remaining effective “for the duration of the subcontractor’s . . . work on the
    project.”
    4
    CHAYCE v. PATH CONSTRUCTION, et al.
    Opinion of the Court
    ¶12           After briefing and oral argument, the superior court vacated
    the arbitration award, finding that the award violated A.R.S.
    § 12-3023(A)(1) because “Path committed misconduct by intentionally
    withholding critical information necessary for Chayce to prove claims and
    defenses.” The court also found that the award violated A.R.S.
    § 12-3023(A)(3) because “[t]he Arbitrator refused Chayce’s request to
    continue the matter,” thereby “den[ying] Chayce the ability to obtain and
    present critical evidence” and “substantially prejudic[ing] Chayce.” Path
    and the insurance company appealed.
    DISCUSSION
    ¶13             Arizona public policy favors arbitration as a means for
    resolving disputes. Clarke v. ASARCO Inc., 
    123 Ariz. 587
    , 589 (1979).
    Accordingly, Arizona’s revised uniform arbitration act “strictly limits the
    superior court’s options after the arbitration process is complete.” Hamblen
    v. Hatch, 
    242 Ariz. 483
    , 490, ¶ 31 (2017). “An arbitrator’s decision generally
    is final and conclusive; the act provides very limited grounds for the trial
    court to deny confirmation of an arbitration award . . . .” Fisher v. Nat’l Gen.
    Ins. Co., 
    192 Ariz. 366
    , 369, ¶ 11 (App. 1998) (construing an earlier version
    of the act). The superior court’s review is not for factual or legal error, see
    Atreus Cmtys. Grp. of Ariz. v. Stardust Dev., Inc., 
    229 Ariz. 503
    , 506, ¶ 13 (App.
    2012), and the court may not substitute its view of the evidence for the
    arbitrator’s, see Pawlicki v. Farmers Ins. Co., 
    127 Ariz. 170
    , 173–74 (App. 1980).
    “The superior court may reject an arbitration award only on [the] narrow
    statutorily enumerated grounds” of A.R.S. § 12-3023, Russell Piccoli P.L.C. v.
    O’Donnell, 
    237 Ariz. 43
    , 49, ¶ 23 (App. 2015) (emphasis added) (citation
    omitted), as proved by the party challenging the award, Fisher v. USAA Cas.
    Ins. Co., 
    245 Ariz. 270
    , 272, ¶ 9 (App. 2018).
    ¶14           We review orders granting arbitration awards for abuse of
    discretion. Atreus Cmtys., 229 Ariz. at 506, ¶ 13. Path urges us to adopt a less
    deferential de novo standard to review orders vacating arbitration awards,
    pointing to the absence of Arizona case law on the issue and several Ninth
    Circuit cases. We need not resolve this issue because the superior court
    erred under either standard.
    I.      Vacatur Under A.R.S. § 12-3023(A)(1)
    ¶15          We start with the superior court’s ruling that vacatur was
    required under A.R.S. § 12-3023(A)(1), which provides that the court shall
    vacate an arbitration award if it “was procured by corruption, fraud or
    other undue means.” “[U]ndue means” requires proof of intentional
    misconduct—i.e., “some type of bad faith” action, not merely “sloppy or
    5
    CHAYCE v. PATH CONSTRUCTION, et al.
    Opinion of the Court
    overzealous lawyering.” FIA Card Servs., N.A. v. Levy, 
    219 Ariz. 523
    , 525, ¶ 7
    (App. 2008) (citations omitted).
    ¶16           The court found that Path “committed misconduct by
    intentionally withholding critical information.” The record here does not
    support the court’s finding. To be sure, Path withheld certain information
    when responding to Chayce’s requests for production. But Path did not
    obfuscate its nondisclosure—to the contrary, it clearly and repeatedly
    stated which categories of information it would not produce and provided
    the basis of the objection to production for each category of requested
    documents. And Chayce gave Path little opportunity to cure the alleged
    deficiencies—Chayce asked for the information once, received responses
    and objections, and then waited four months, until mere days before the
    arbitration hearing, to express its dissatisfaction with the production
    provided. And even then, Chayce did not ask the arbitrator to exercise his
    authority under the governing AAA Rules to order the production of
    evidence deemed “necessary to an understanding and determination of the
    dispute.” AAA Rule R-35(a). As the civil rules demonstrate, a party must
    raise discovery issues timely for noncompliance to constitute misconduct.
    See Ariz. R. Civ. P. 37(a) (providing that in civil cases, a party may move to
    compel production only after good faith consultation to resolve the issue).
    ¶17           Even assuming that Path’s production was incomplete,
    nothing suggests that Path engaged in corruption, fraud, or undue means.
    Further, consistent with the arbitrator’s authority to weigh the evidence, see
    AAA Rule R-35, Path was penalized for its failure to disclose the third-party
    information. The court’s vacatur of the arbitration award was not justified
    under A.R.S. § 13-3023(A)(1).
    II.    Vacatur Under A.R.S. § 12-3023(A)(3)
    ¶18          We next address the superior court’s ruling that vacatur was
    required under A.R.S. § 12-3023(A)(3), which provides that the court shall
    vacate an arbitration award if the “arbitrator refused to postpone the
    hearing on showing of sufficient cause for postponement . . . so as to
    prejudice substantially the rights of a party to the arbitration proceeding.”
    ¶19          The court premised its ruling on findings that the arbitrator
    “refused Chayce’s request to continue the matter” based on Path’s
    withholding of “critical evidence” to Chayce’s “substantial prejudice[].”
    The record does not support these findings or the court’s ruling.
    ¶20           First, there is no evidence that Chayce requested to postpone
    the arbitration to allow resolution of the discovery issues. Though Chayce’s
    6
    CHAYCE v. PATH CONSTRUCTION, et al.
    Opinion of the Court
    counsel stated at oral argument in the superior court that he had asked for
    a postponement at the arbitration hearing, this assertion is not evidence. See
    Quine v. Godwin, 
    132 Ariz. 409
    , 412 (App. 1982) (recognizing that counsel’s
    arguments are not evidence). In fact, the only evidence about postponement
    in the record is a sworn declaration from Path’s counsel avowing he did not
    remember Chayce ever requesting a postponement. And, consistent with
    that declaration, neither Chayce nor the arbitrator ever documented any
    postponement request. The record simply does not support the court’s
    finding that Chayce requested a postponement before the close of the
    arbitration hearing. Accordingly, vacatur was unwarranted under A.R.S.
    § 13-3023(A)(3).
    ¶21          But even were we to assume that Chayce requested a
    postponement in the arbitration proceedings, vacatur was still
    inappropriate under A.R.S. § 13-3023(A)(3) because, under the AAA Rules,
    Chayce waived its objection to the denial of the alleged request. The AAA
    Rules provide that “[t]he arbitrator for good cause shown may postpone
    any hearing,” but “[a]ny party who proceeds with the arbitration after
    knowledge that any provision or requirement of these Rules has not been
    complied with and who fails to state an objection in writing shall be deemed
    to have waived the right to object.” AAA RulesR-31, R-42 (emphasis
    added). Chayce did not preserve its objection to the denial of the alleged
    postponement request in writing, either at the hearing or in its post-hearing
    brief.
    ¶22           Finally, even were we to assume that Chayce properly
    requested a postponement and preserved an objection to the request’s
    denial, the arbitrator had discretion to manage the parties’ exchange of
    information, weigh the evidence, and determine whether a postponement
    was warranted under the circumstances. See AAA Rules R-24, R-31, R-35;
    Canon Sch. Dist. No. 50 v. W.E.S. Constr. Co., Inc., 
    180 Ariz. 148
    , 150 (1994)
    (holding that arbitration panel “did not abuse its discretion in denying . . .
    motions” for withdrawal of counsel and continuance given lack of
    prejudice); see also Moore v. Olson, 
    351 P.3d 1066
    , 1075–76 (Alaska 2015)
    (noting, when construing Alaska’s substantially similar statute, that courts
    typically reject claims for vacatur based on the denial of a postponement
    request, and holding that denial was justified in the case at bar because the
    claims were untimely raised and failed to describe adequate cause). On this
    record, where Chayce waited until just before the hearing to raise with the
    arbitrator complaints about identified nondisclosures and the arbitrator
    expressly accounted for the nondisclosures in his decision, the arbitrator
    acted well within his discretion by proceeding with the hearing. The
    correctness of the arbitrator’s factual and legal decisions was beyond the
    7
    CHAYCE v. PATH CONSTRUCTION, et al.
    Opinion of the Court
    scope of the superior court’s review. See Atreus Cmtys., 229 Ariz. at 506, ¶ 13.
    Accordingly, the court erred by vacating the arbitrator’s award under
    A.R.S. § 12-3023(A)(3).
    CONCLUSION
    ¶23           We reverse the vacatur of the arbitration award, including all
    findings that Path committed misconduct. We remand for the superior
    court to confirm the award consistent with A.R.S. § 12-3023(D). In the
    exercise of our discretion, we deny Path’s request for attorney’s fees and
    expenses on appeal under A.R.S. §§ 12-341.01 and -3025. We also deny
    Chayce’s request for attorneys’ fees under A.R.S. § 12-341.01. Path may
    recover its costs under A.R.S. § 12-341 upon compliance with ARCAP 21.
    AMY M. WOOD • Clerk of the Court
    FILED: AGFV
    8
    

Document Info

Docket Number: 1 CA-CV 24-0030

Filed Date: 10/22/2024

Precedential Status: Precedential

Modified Date: 10/22/2024