Town of Lead Hill v. Ozark Mountain Regional Public Water Authority , 2015 Ark. LEXIS 580 ( 2015 )


Menu:
  •                                  Cite as 
    2015 Ark. 360
    SUPREME COURT OF ARKANSAS
    No.   CV-14-848
    TOWN OF LEAD HILL, ARKANSAS,                   Opinion Delivered   October 8, 2015
    ET AL.
    APPELLANTS                 APPEAL FROM THE BOONE
    COUNTY CIRCUIT COURT
    V.                                             [NO. CV-2013-207-1]
    HONORABLE SHAWN A.
    OZARK MOUNTAIN REGIONAL                        WOMACK, JUDGE
    PUBLIC WATER AUTHORITY OF
    THE STATE OF ARKANSAS                          AFFIRMED.
    APPELLEE
    KAREN R. BAKER, Associate Justice
    This appeal stems from a Wholesale Water Purchase Contract (“contract”) between
    appellants, Town of Lead Hill, Arkansas, et al. (“Lead Hill”) and the appellee, Ozark
    Mountain Regional Public Water Authority (“Ozark”). On April 27, 2009, the parties
    entered into a contract with a forty-year term for Ozark to provide potable water to Lead
    Hill. Lead Hill agreed to purchase water with a “minimum monthly charge” based on an
    average daily usage of 56,038 gallons at the rate between $2.75 and $3.25 per thousand
    gallons at a minimum monthly charge between $4,687 and $5,540. Further, the contract
    provided that Lead Hill would pay the minimum monthly charge regardless of whether Lead
    Hill “actually purchased or takes water” from Ozark. Ozark constructed a water-treatment
    facility and connecting water lines and incurred bond indebtedness secured in part by the
    contract. The contract provided that water would be provided commencing in November
    2012.
    Cite as 
    2015 Ark. 360
    On November 12, 2012, Ozark began supplying potable water to Lead Hill, and Lead
    Hill paid for the water. On August 16, and September 16, 2013, Ozark sent Lead Hill
    monthly invoices. The invoices totaled $10,555.02, which included a late fee of $51.99.
    However, Lead Hill did not pay those invoices. On October 15, 2013, Lead Hill notified
    Ozark that the Lead Hill City Council had unanimously voted to terminate its contract with
    Ozark.
    On October 25, 2013, Ozark filed suit against Lead Hill seeking a declaratory
    judgment and a writ of mandamus to enforce the contract. On November 27, 2013, Lead
    Hill filed an answer. On January 15, 2014, Ozark filed a motion for summary judgment and
    brief in support. Lead Hill responded and filed an amended response, and Ozark replied.
    On March 13, 2014, the circuit court held a hearing and, at the request of the parties,
    entered a continuance in the matter and delayed ruling on the motion for summary judgment
    for sixty days while the parties attempted to resolve the matter and Lead Hill was to make
    payments into the registry of the circuit court. On May 22, 2014, the circuit court
    conducted a hearing on the summary-judgment motion. On June 11, 2014, the circuit court
    granted Ozark’s motion for summary judgment and issued a writ of mandamus. On July 9,
    2014, Lead Hill timely filed its notice of appeal and now presents four points on appeal: (1)
    the contract violates article 12, section 4, and amendment 78 of the Arkansas Constitution;
    (2) the contract violates federal law; (3) Ozark lacked the capacity to enter into the contract;
    and (4) the contract is unenforceable under several contract principles. Because this case
    presents an issue involving the interpretation of the Arkansas Constitution, we have
    2
    Cite as 
    2015 Ark. 360
    jurisdiction pursuant to Ark. Sup. Ct. R. 1-2(a)(1) (2014).
    Standard of Review
    This case comes to us from an order granting summary judgment. A trial court may
    grant summary judgment only when it is apparent that no genuine issues of material fact exist
    requiring litigation and that the moving party is entitled to judgment as a matter of law.
    Crockett v. C.A.G. Invs., Inc., 
    2011 Ark. 208
    , 
    381 S.W.3d 793
    . Summary judgment is not
    proper, however, where evidence, although in no material dispute as to actuality, reveals
    aspects from which inconsistent hypothesis might reasonably be drawn and reasonable minds
    might differ. Thomas v. Sessions, 
    307 Ark. 203
    , 
    818 S.W.2d 940
    (1991). In Flentje v. First Nat.
    Bank of Wynne, 
    340 Ark. 563
    , 569-70, 
    11 S.W.3d 531
    , 536 (2000) (internal citations omitted),
    we explained, “we only approve the granting of the motion when the state of the evidence
    as portrayed by the pleadings, affidavits, discovery responses, and admission on file is such that
    the nonmoving party is not entitled to a day in court, i.e., when there is not any genuine
    remaining issue of fact and the moving party is entitled to judgment as a matter of law.
    However, when there is no material dispute as to the facts, the court will determine whether
    reasonable minds could draw reasonable inconsistent hypotheses to render summary judgment
    inappropriate.”
    On appeal, we view the evidence in the light most favorable to the party against whom
    the motion was filed, resolving all doubts and inferences against the moving party. Harrisburg
    Sch. Dist. No. 6 v. Neal, 
    2011 Ark. 233
    , 
    381 S.W.3d 811
    .
    Points on Appeal
    3
    Cite as 
    2015 Ark. 360
    I. Article 12, Section 4, and Amendment 78 of the Arkansas Constitution
    A. Article 12, Section 4
    Turning to Lead Hill’s first point on appeal, Lead Hill asserts that the circuit court
    erred in granting summary judgment regarding two provisions of the Arkansas Constitution,
    article 12, section 4, and amendment 78. Prior to reaching this issue, we note that when
    interpreting the constitution, “our task is to read the laws as they are written, and interpret
    them in accordance with established principles of constitutional construction. . . . Language
    of a constitutional provision that is plain and unambiguous must be given its obvious and
    common meaning.” Smith v. Sidney Moncrief Pontiac, Buick, GMC Co., 
    353 Ark. 701
    , 720,
    
    120 S.W.3d 525
    , 537 (2003) (internal citations omitted).
    First, at issue is article 12, section 4, of the Arkansas Constitution, which provides in
    pertinent part,
    The fiscal affairs of counties, cities and incorporated towns shall be conducted on a
    sound financial basis, and no county court or levying board or agent of any county
    shall make or authorize any contract or make any allowance for any purpose
    whatsoever in excess of the revenue from all sources for the fiscal year in which said
    contract or allowance is made[.]
    In other words, a city cannot enter into a contract for an amount that exceeds its annual
    revenue for a fiscal year. Here, the circuit court held that article 12, section 4 was not a
    valid legal defense to enforcement of the contract.
    Article C, section 19, of the contract provides as follows:
    Funding of Purchaser:
    The parties hereto agree that all Purchaser revenues associated with the
    funding of this Agreement shall be derived solely from revenues generated by
    4
    Cite as 
    2015 Ark. 360
    the sale of the Purchaser’s water to its customers and that except for a pledge
    of said revenues that Purchaser does not otherwise further guarantee the
    obligations hereunder with its full faith and credit.
    On appeal, Lead Hill asserts that the contract violates article 12, section 4, and the contract
    is void and unenforceable because the contract exceeded Lead Hill’s annual revenue. Lead
    Hill further contends that although the provision of the contract may purport to limit the
    payments only from income derived from the sale of water by Lead Hill to its waterworks
    customers, its customer base has been reduced by fifty percent and therefore its financial
    obligation under the contract also exceeds its annual revenue for one year because of its loss
    of customers. Therefore, Lead Hill argues that the terms of the contract are not enforceable
    under article 12, section 4.
    Ozark responds that the contract language is clear – the funding for the contract is
    derived solely from the revenues generated by the sale of the water to its customers. Ozark
    further contends that Lead Hill’s arguments regarding loss of its customers is hearsay and not
    part of the record. Relying on McGehee v. Williams, 
    191 Ark. 643
    , 
    87 S.W.2d 46
    (1935), and
    Hink v. Board of Directors of Beaver Water District, 
    235 Ark. 107
    , 
    357 S.W.2d 271
    (1962), Ozark
    contends that we have affirmed the authority of towns such as Lead Hill to purchase water
    pursuant to multiyear contracts, and the circuit court properly granted summary judgment in
    its favor.
    In McGehee, we held that the town of Alma’s twenty-year-purchase contract did not
    violate article 12, section 4, also known as amendment 10, because the payments due under
    the contract were revenues solely from Alma’s sale of water to its customers and would not
    5
    Cite as 
    2015 Ark. 360
    constitute a guarantee of Alma’s full faith and credit:
    Appellants also contend that this contract is in violation of Amendment No. 10 to the
    Constitution of 1874. This contention is grounded upon the theory that the water
    rentals due under the contract would be a charge against the general revenues of the
    city of Alma during the life of the contract. We do not so construe the contract. The
    rentals therein provided are to be paid from the revenue derived from the distribution
    of the water supply. When the contract is thus construed, it can in no event offend the
    amendment.
    McGehee, 
    191 Ark. 643
    ,649, 
    87 S.W.2d 46
    , 48 (1935).
    Next, in Hink, we also interpreted article 12, section 4, and explained,
    Amendment 10 requires the fiscal affairs of all cities to be conducted on a sound
    financial basis and prohibits any city from entering into any contract or incurring any
    obligation in excess of its revenues for the current fiscal year. By one of the contracts
    now in question, attached as Exhibit C to the complaint, the city would pledge only
    its net waterworks revenues to secure the performance of its contract with the Beaver
    Water District. This contract is valid, for it is well settled that Amendment 10 does not
    prohibit the creation of a debt exceeding current annual revenues if the debt is secured
    by and payable solely out of the income or assets of a special and separable activity such
    as a municipal waterworks. Williams v. Harris, 
    215 Ark. 928
    , 
    224 S.W.2d 9
    .
    
    Hink, 235 Ark. at 110
    , 357 S.W.2d at 273.
    In McGehee and Hink, we held that multiyear purchase contracts for water did not
    violate article 12, section 4 because the contracts did not pledge the full faith and credit of the
    town; but rather they pledged the revenues derived from the sale of the water and pledged
    the revenues of its own waterworks system. Here, the same is true. The contract at issue
    provides,
    The parties hereto agree that all Purchaser revenues associated with the funding of this
    Agreement shall be derived solely from revenues generated by the sale of the
    Purchaser’s water to its customers and that except for a pledge of said revenues that
    Purchaser does not otherwise further guarantee the obligations hereunder with its full
    faith and credit.
    6
    Cite as 
    2015 Ark. 360
    Accordingly, McGehee and Hink are on point, and we do not find merit in Lead Hill’s
    argument. Based on the express terms of the contract and the record before us, Lead Hill has
    pledged payment under the contract “solely from revenues generated by the sale of the [Lead
    Hill’s] water to its customers and that except for a pledge of said revenues that [Lead Hill]
    does not otherwise further guarantee the obligations hereunder with its full faith and credit.”
    Further, as Lead Hill has argued in its brief, the crux of Lead Hill’s argument here is
    the “practical effect” of the enforcement. Our review is of the circuit court’s order
    concerning the terms of the contract, not any future enforcement of the contract. Here, the
    language of the contract does not offend art. 12, section 4. Finally, in support of its position,
    Lead Hill references a contempt order and a sales-and-use tax that Lead Hill alleges was passed
    as a result of the contempt order. However, Lead Hill did not appeal from the contempt
    order.
    We hold that Lead Hill has failed to show that there is a genuine issue as to a material
    fact or that reasonable differing inferences could be drawn from the undisputed facts.
    Accordingly, we affirm on this first point.1
    1
    Justice Danielson’s dissent on this point is fatally flawed for three reasons. First,
    Justice Danielson states that,
    According to Lead Hill, under the terms of its contract with Ozark, it is obligated
    to pay a minimum monthly charge to Ozark that results in a total obligation of $2.25
    million, an amount that far exceeds the town’s annual revenue of approximately
    $360,000.
    This misconstrues Lead Hill’s argument. Lead Hill asserts that its total obligation over the
    40-year term of the contract would be $2.25 million, not an annual obligation of $2.25
    million.
    7
    Cite as 
    2015 Ark. 360
    B. Amendment 78
    Second, Lead Hill asserts that the contract is “wholly void” because the contract term
    Second, Justice Danielson states:
    It is irrelevant that the contract included a provision purporting to prohibit Lead Hill
    from guaranteeing the obligations under the contract with its full faith and credit and
    designating that the purchase price be paid from revenue generated through the sale
    of Ozark’s water, because Lead Hill is obligated to pay a minimum monthly charge
    of between $4,687 and $5,540 regardless of whether it generates sufficient revenue
    from the sale of the water.
    Although Justice Danielson states that the provision is “irrelevant,” our case law indicates
    otherwise. We have approved this “irrelevant” provision and held that multiyear purchase
    contracts for water did not violate article 12, section 4 because the contracts did not pledge
    the full faith and credit of the town; but rather they pledged the revenues derived from the
    sale of the water and pledged the revenues of its own waterworks system. See McGehee v.
    Williams, 
    191 Ark. 643
    , 
    87 S.W.2d 46
    (1935); Hink v. Board of Directors of Beaver Water
    District, 
    235 Ark. 107
    , 
    357 S.W.2d 271
    (1962).
    Third, Justice Danielson’s position is based upon a hypothetical situation that may occur
    upon enforcement. His position is not premised on the record before this court. Simply put,
    Lead Hill asserted below that the contract on its face was void because it was
    unconstitutional. They did not plead, argue, or meet proof with proof showing that
    revenues from the sale of water were insufficient to meet the minimum monthly amount
    agreed to in the contract. Thus, the trial court did not err in granting summary judgment.
    Justice Hart’s dissenting opinion is flawed as well. Justice Hart states:
    The Arkansas Supreme Court has superintending authority over the inferior courts of
    this state. Ark. Const. amend. 80. We should exercise this authority, if for no other
    reason, than to prevent the misuse of an extraordinary writ and the violation of our
    state constitution. . . . Accordingly, in the case before us, we should not act as though
    we are fettered by the arguments raised in the parties’ briefs.
    However, this position is misplaced, our jurisdiction is appellate and we cannot exceed that
    jurisdiction.
    8
    Cite as 
    2015 Ark. 360
    exceeds five years, which is in violation of amendment 78 to the Arkansas Constitution.
    Ozark responds that the contract at issue does not fall within the parameters of amendment
    78.
    The circuit court held:
    The five-year limitation for short term financing obligations under Amendment
    78 to the Arkansas Constitution is not applicable to the Water Purchase Contract.
    Therefore, the Town’s citation of Amendment 78 is not a valid legal defense to the
    enforcement of the Water Purchase Contract.
    Amendment 78 provides in pertinent part:
    For the purpose of acquiring, constructing, installing or renting real property or
    tangible personal property having an expected useful life of more than one (1) year,
    municipalities and counties may incur short-term financing obligations maturing over
    a period of, or having a term, not to exceed five (5) years.
    Ark. Const. Amend. 78, § 2(a).
    Further, the amendment defines “short-term financing obligation” as “a debt, a note,
    an installment purchase agreement, a lease, a lease purchase contract, or any other similar
    agreement, whether secured or unsecured.” Id § 2(b)(1). Lead Hill asserts that the circuit
    court erred because the contract at issue falls within amendment 78 and the terms of the
    contract exceed the five-year limitation prescribed in our constitution. Ozark responds that
    the contract for the delivery of potable water to the master meter does not violate amendment
    78 because it is not a short-term financing obligation.
    Here, the parties entered into a contract to provide potable water to be paid for by
    revenues derived from its customers. The contract is not a short-term financing obligation
    as defined by amendment 78. Based on the record before us, Lead Hill has failed to present
    9
    Cite as 
    2015 Ark. 360
    unresolved material facts on this issue or that reasonable differing inferences could be drawn
    from the undisputed facts. Accordingly, based on our standard of review, we affirm the
    circuit court on this point.
    II. The Contract Violates Federal Law
    Lead Hill next asserts that the circuit court erred in granting summary judgment
    because the contract violates 7 U.S.C. § 1926(b) and is therefore void. Lead Hill contends
    that federal law prohibits a water entity, such as Ozark, from curtailing another entity’s ability
    to repay USDA loans by providing water service in an area where the indebted entity, Lead
    Hill, is already providing water and therefore the contract is unenforceable. Ozark responds
    that the statute is not applicable to the contract.
    Lead Hill’s argument regarding 7 U.S.C. § 1926(b) requires us to interpret the statute.
    “The first rule in considering the meaning and effect of a statute is to construe it just as it
    reads, giving the words their ordinary and usually accepted meaning in common language.”
    Potter v. City of Tontitown, 
    371 Ark. 200
    , 209, 
    264 S.W.3d 473
    , 481 (2007).
    The circuit court held that 7 U.S.C.A. § 1926(b) was not a valid legal defense to
    enforcement of the contract and granted summary judgment on this point.
    7 U.S.C. § 1926(b) provides in pertinent part:
    (b) Curtailment or limitation of service prohibited.
    The service provided or made available through any such association shall not be
    curtailed or limited by inclusion of the area served by such association within the
    boundaries of any municipal corporation or other public body, or by the granting of
    any private franchise for similar service within such area during the term of such loan;
    nor shall the happening of any such event be the basis of requiring such association to
    secure any franchise, license, or permit as a condition to continuing to serve the area
    10
    Cite as 
    2015 Ark. 360
    served by the association at the time of the occurrence of such event.
    Here, Lead Hill contends that it was indebted to the USDA on three separate loans at
    the time it entered into the contract. Further, Lead Hill contends that it had to disconnect
    from its current water supply and use water only from Ozark. In other words, Lead Hill
    asserts that Ozark violated § 1926(b) because the contract required Lead Hill to disconnect
    from its current water system and purchase 100% of its water from Ozark and curtailed its
    ability to repay its USDA loans.
    Ozark responds that Lead Hill has misinterpreted the application of 7 U.S.C. § 1926(b)
    and the noncurtailment statute does not apply to void the contract. Ozark further responds
    that Lead Hill’s waterworks system operated by Lead Hill is financed by the USDA bonds,
    not the water supply, and the waterworks system has not been impaired or affected.
    In Public Water Supply District No. 3 of Laclede County, Missouri. v. City of Lebanon,
    Missouri, the Eighth Circuit Court of Appeals analyzed the applicable statute and explained:
    The key operative provision of § 1926(b) provides that a rural district’s service “shall
    not be curtailed or limited.” In this context, the verbs “curtail” and “limit” connote
    something being taken from the current holder, rather than something being retained
    by the holder to the exclusion of another. See The New Shorter Oxford English Dictionary
    575, 1591 (4th ed.1993) (defining “curtail” as “[s]horten in . . . extent or amount;
    abridge”; defining “limit” as “set bounds to; restrict”); see also CSL Utils., Inc. v.
    Jennings Water, Inc., 
    16 F.3d 130
    , 135 (7th Cir.1993) (“The cases and fragments of
    legislative history available to us all seem to have in mind curtailment resulting from
    substitution of some third party as a water-supplier for [the rural district].” (emphasis
    added)). FN3.
    ...
    FN3. The legislative history is consistent with such a reading. Subsection (b)
    was added to § 1926 in 1961 “to assist in protecting the territory served by such
    an association facility against competitive facilities, which might otherwise be
    developed with the expansion of the boundaries of municipal and other public
    11
    Cite as 
    2015 Ark. 360
    bodies into an area served by the rural system.” S. Rep. 87–566, 1961
    U.S.C.C.A.N. 2243, 2309 (emphasis added).
    
    605 F.3d 511
    , 516 & n.3 (8th Cir. 2010).
    The issue before us is whether the circuit court erred in granting summary judgment
    regarding Lead Hill’s claim that 7 U.S.C. § 1926(b) renders the contract unenforceable. Based
    on the plain language of 7 U.S.C. § 1926(b) and the record before us, 7 U.S.C.A. § 1926(b)
    has no application to the case before us. The parties here are not competing for waterworks
    customers. As Lead Hill acknowledged in its brief to the circuit court, “this is simply [Lead
    Hill] buying water from . . .[Ozark.]” The statute is designed to prevent competition. There
    is no competition or curtailment between Lead Hill and Ozark. Accordingly, we hold that
    the circuit court did not err and affirm on this point.
    III. Ozark Lacked the Capacity to Enter Into the Contract
    Lead Hill next contends that Ozark lacked the capacity to enter into the contract and
    that the circuit court erred by granting summary judgment because a factual question remains
    regarding Ozark’s capacity. Lead Hill asserts that the circuit court erred because Ozark did
    not follow corporate formalities and was not properly formed; therefore, Lead Hill cannot be
    bound to the contract because any act by Ozark is an ultra vires act and it should not be
    bound to the contract.
    In granting Ozark’s motion for summary judgment on this issue, the circuit court held
    that Lead Hill’s “argument that [Ozark] lacked the capacity to enter into the . . . contract is
    not a valid legal defense to the enforcement of the . . . contract under Arkansas law. No facts
    supporting the defense of capacity would change the enforceability of the . . . contract as a
    12
    Cite as 
    2015 Ark. 360
    matter of law.”
    With regard to Ozark’s ability to enter into the contract, Ark. Code Ann. § 4-35-
    210(20) & (22) (Supp. 2013) provides in pertinent part:
    A water authority shall have the following powers, together with all powers incidental
    thereto or necessary to the discharge thereof:
    (20) To do and perform all acts and things and have and exercise any power
    as may be convenient or appropriate to effectuate the purposes for which the
    water authority is formed;
    ...
    (22) To enter into water contracts for the purchase or sale of water on a
    wholesale basis on the terms and conditions the board determines are in the
    best interest of the water authority.
    In Barnhart v. City of Fayetteville, 
    321 Ark. 197
    , 209, 
    900 S.W.2d 539
    , 545 (1995), we
    addressed contracts that may have been formed by ultra vires acts and are unenforceable:
    We have long made a distinction between a contract with a municipality that is ultra
    vires in the general sense and, because it is wholly outside the authority of the
    municipality to make such a contract under any circumstances, is void ab initio, Town
    of Newport v. Batesville & Brinkley Ry. Co., 
    58 Ark. 270
    , 
    24 S.W. 427
    (1893), and a
    contract that is ultra vires in the limited sense because the power to contract was
    merely exercised irregularly and thus can be ratified. Blount v. Baker, 
    177 Ark. 1162
    ,
    
    9 S.W.2d 802
    (1928).
    Further, in Keith v. City of Cave Springs, 
    233 Ark. 363
    , 374–75, 
    344 S.W.2d 591
    , 597
    (1961), we explained that a party cannot be permitted to accept the benefits under the
    contract and at the same time avoid its obligation under such agreement:
    The evidence is undisputed that the City of Cave Springs has for the past ten years
    diligently fulfilled an implied covenant to purchase water for its residential and
    industrial consumers and the express covenant to pay for the water purchased. See
    Mooney v. Gantt, 
    219 Ark. 485
    , 
    243 S.W.2d 9
    . Therefore, appellants cannot be
    permitted to accept the benefits under the contract and at the same time avoid their
    obligation under such agreement. Williams Mfg. Co. v. Strasberg, 
    229 Ark. 321
    , 314
    13
    Cite as 
    2015 Ark. 360
    S.W.2d 500.
    Here, despite whether Ozark adhered to the proper corporate formalities, the record
    demonstrates that Ozark has received articles of incorporation and maintained the statutory
    authority to enter into the contract. Pursuant to Ark. Code Ann. § 4-35-210(20) and (22)
    and Barnhart, Ozark’s acts were not ultra vires. Finally, based on our holding in Barnhart,
    even if Ozark did proceed irregularly, Ozark maintained the authority to enter into the
    contract. Therefore, we do not find error and affirm the circuit court on this point.
    IV. The Contract is Unenforceable Under Several Contract Principles
    For its final point on appeal, Lead Hill contends that its performance under the
    contract is excused and the contract fails based on several contract principles: impossibility
    of performance, impracticability of performance, supervening frustration, unconscionability,
    and lack of mutuality.
    A. Excuse of Performance: Impossibility, Impracticability and Supervening Frustration
    Lead Hill first asserts that its performance under the contract is excused by the
    impossibility of performance, impracticability of performance, and supervening frustration.
    Lead Hill asserts this because “numerous statutes and constitutional provisions . . . will be
    violated” if the contract is enforced. Lead Hill further asserts that the performance of the
    contract has become impractical and frustrated because its customer base was decreased by
    fifty percent.
    Ozark responds that the doctrines are not applicable because Lead Hill’s assertions are
    not based on any factual evidence but on hearsay arguments of counsel concerning the
    14
    Cite as 
    2015 Ark. 360
    number of customers that buy water. Further, Ozark responds that Lead Hill has not alleged
    a change in circumstance that was a basic assumption of the contract and has waived any right
    to argue a change in circumstance because Lead Hill failed to avail itself of the procedural
    mechanisms and remedies in the contract.
    In its June 11, 2014 order granting summary judgment to Ozark, the circuit court held
    that “[n]one of the other defenses raised by the Town in opposing the Motion for Summary
    Judgment constitutes a valid legal defense to the enforcement of the Water Purchase
    Contract. No facts supporting such defenses would change the enforceability of the Water
    Purchase Contract as a matter of law.”
    The Restatement (Second) of Contracts provides in pertinent part:
    § 261 Discharge by Supervening Impracticability
    Where, after a contract is made, a party’s performance is made impracticable without
    his fault by the occurrence of an event the non-occurrence of which was a basic
    assumption on which the contract was made, his duty to render that performance is
    discharged, unless the language or the circumstances indicate the contrary.
    § 265 Discharge by Supervening Frustration
    Where, after a contract is made, a party’s principal purpose is substantially frustrated
    without his fault by the occurrence of an event the non-occurrence of which was a
    basic assumption on which the contract was made, his remaining duties to render
    performance are discharged, unless the language or the circumstances indicate the
    contrary.
    § 266 Existing Impracticability or Frustration
    (1) Where, at the time a contract is made, a parties performance under it is
    impracticable without his fault because of a fact of which he has no reason to know
    and the non-existence of which is a basic assumption on which the contract is made,
    no duty to render that performance arises, unless the language or circumstances
    indicate the contrary.
    15
    Cite as 
    2015 Ark. 360
    (2) Where, at the time a contract is made, a party’s principal purpose is substantially
    frustrated without his fault by a fact of which he has no reason to know and the
    non-existence of which is a basic assumption on which the contract is made, no duty
    of that party to render performance arises, unless the language or circumstances
    indicate the contrary.
    Restatement (Second) of Contracts §§ 261, 265 & 266 (1981).
    Here, the crux of Lead Hill’s argument is that the circuit court erred in granting
    summary judgment on its defenses to performing the contract due to the loss of customers
    and that the contract is now impracticable, impossible, and frustrated. Based on the record
    before us, Lead Hill has failed to demonstrate that the circuit court erred in granting
    summary judgment on this point. We do not find error and affirm.
    B. Unconscionability
    Lead Hill next asserts that there are “numerous” provisions in the contract and that
    the contract as a whole is unconscionable. However, Lead Hill’s primary complaint is that
    Article B, section 2 is unconscionable. That section of the contract provides in pertinent
    part:
    Minimum Charge. Purchaser shall be invoiced each month for its “Minimum
    Charge” which initially shall be based upon the average amount of water
    pumped per day in 2008 (Lead Hill=56,038 gpd). The “Minimum Monthly
    Charge” shall be between $4,687.00 and $5,540.00 dependant on the
    wholesale water rate described in Article B-3 at the commencement of this
    Agreement. The Minimum Charge is calculated by the Seller to be a rate
    whose sum is equal to the Purchaser’s pro-rated share of the debt service, debt
    service reserve deposit requirements, depreciating fund deposit requirements,
    operation and maintenance (O & M) costs and administrative costs associated
    with the construction and operation of the System. Payment of the Minimum
    Charge allows the Purchaser to consume, without further charge, the number
    of gallons of water determined by dividing the Minimum Charge by the
    Wholesale Water Rate, as defined herein.
    16
    Cite as 
    2015 Ark. 360
    Purchaser covenants and agrees to pay the Minimum Charge on a Monthly
    Basis, as invoiced by Seller, regardless of whether Purchaser actually purchases
    or takes water from Seller. To the extent that Purchaser’s consumption of
    water exceeds the amount determined by dividing the Minimum Charge by
    the Wholesale Water Rate, Purchases will be invoiced by Seller monthly for
    the excess based on the prevailing Wholesale Water Rate.
    Lead Hill contends that this provision is unconscionable because this provision and
    the contract terms commit Lead Hill to a perpetual contract and require a minimum monthly
    charge even if Lead Hill never uses the water.
    The circuit court granted Ozark summary judgment on this issue and held, “None
    of the other defenses raised by the Town in opposing the Motion for Summary Judgment
    constitutes a valid legal defense to the enforcement of the Water Purchase Contract. No
    facts supporting such defenses would change the enforceability of the Water Purchase
    Contract as a matter of law.”
    In Gulfco of Louisiana, Inc. v. Brantley, 
    2013 Ark. 367
    , at 9, 
    430 S.W.3d 7
    , 13, we
    explained unconscionability:
    Our standards regarding unconscionability are as follows. An act is
    unconscionable if it affronts the sense of justice, decency, and reasonableness. Baptist
    Health v. Murphy, 
    2010 Ark. 358
    , 
    373 S.W.3d 269
    . We have stated that in assessing
    whether a particular contractual provision is unconscionable, the courts review the
    totality of the circumstances surrounding the negotiation and execution of the
    contract. Jordan v. Diamond Equip. & Supply Co., 
    362 Ark. 142
    , 
    207 S.W.3d 525
          (2005). Two important considerations are whether there is a gross inequality of
    bargaining power between the parties and whether the aggrieved party was made
    aware of and comprehended the provision in question. 
    Id. We also
    observe that
    another factor which may contribute to a finding of unconscionability is a belief by
    the stronger party that there is no reasonable probability that the weaker party will
    fully perform the contract. Restatement (Second) of Contracts § 208.
    We also addressed unconscionability in LegalZoom.com, Inc. v. McIllwain, 
    2013 Ark. 17
                                       Cite as 
    2015 Ark. 360
    370, at 6–7, 
    429 S.W.3d 261
    , 264, and explained,
    While “unconscionability” is not precisely defined in the law, one of the earliest
    applications of the doctrine described an unconscionable contract as one that “no man
    in his senses and not under delusion would make on the one hand, and . . . no honest
    and fair man would accept on the other.” James J. White & Robert S. Summers,
    Handbook of the Law Under the Uniform Commercial Code § 4–1 (3d ed.1988) (quoting
    Earl of Chesterfield v. Janssen (1750) 728 Eng. Rep. 82, 100 (K.B.). In essence, to be
    unconscionable, a contract must oppress one party and actuate the sharp practices of
    the other.
    Here, based on the record before us, the record does not support Lead Hill’s argument
    for reversal. Accordingly, we agree with the circuit court and affirm on this point.
    C. Lack of Mutuality and Illusory Provisions
    Lead Hill also contends that the contract fails for lack of mutuality based on illusory
    provisions in the contract. Lead Hill cites to Article B, section 4(A) and asserts that a
    reallocation must be reviewed and approved by Ozark, which constitutes an illusory promise
    and lacks mutuality because any request must be approved by Ozark. Further, Lead Hill
    again relies on its allegations of a decrease in its customers from South Lead Hill. Ozark
    responds that Lead Hill has waived any argument that the contract contains illusory
    provisions resulting in lack of mutuality because consideration has been conferred. Ozark
    also responds that Lead Hill’s argument regarding lack of mutuality is based on hearsay
    argument by counsel that is not supported by the record before the court.
    Article B, section 4(A) of the contract provides:
    Adjustment to Minimum Charge or Wholesale Water Rate.
    During the term of this Agreement, Seller may adjust the Minimum Charge or the
    Wholesale Water Rate, without the consent or the approval of the Purchaser, in the
    following ways or under the following circumstances:
    18
    Cite as 
    2015 Ark. 360
    A.   In the event that during the courts of this Agreement the number of
    retail customers of any purchaser obtaining water from Seller should
    substantially decrease or increase, then either on request of any
    purchaser or on its own initiative, the Seller shall perform a reallocation
    of the Minimum Charge to all purchasers receiving water from Seller
    so as to relieve undue participant burden associated with the decreasing
    or increasing customer base. A reallocation shall be considered based
    upon the request of any purchaser made in writing to the Seller which
    cites the reasons and rationale for the requested reallocation. Any
    reallocation must be reviewed and approved by the Board of Directors
    of Seller before becoming effective. Seller may perform and implement
    such reallocations from time to time without the necessity of obtaining
    written consent or approval from the Purchaser, but under no
    circumstances will reallocations be performed more often than two
    times in any calendar year.
    In Jordan v. Diamond Equipment & Supply Co., 
    362 Ark. 142
    , 153, 
    207 S.W.3d 525
    ,
    533 (2005), we explained the mutuality of obligations:
    We have recognized that mutuality of contract means that an obligation must
    rest on each party to do or permit to be done something in consideration of the act
    or promise of the other; thus, neither party is bound unless both are bound. The
    Money Place v. Barnes, 
    349 Ark. 411
    , 
    78 S.W.3d 714
    (2002); Showmethemoney Check
    Cashers, Inc. v. Williams, 
    342 Ark. 112
    , 
    27 S.W.3d 361
    (2000). . . . Mutuality of
    obligation involves the exchange of promises, and mutuality of obligations becomes
    “a nonissue” when performance is given.
    Here, the record demonstrates that Lead Hill agreed to pay Ozark to provide potable
    water to Lead Hill’s master meter in exchange for payment and the parties adhered to the
    contract for ten months. Additionally, based on the record before us, Lead Hill has not
    demonstrated the existence of a material fact at issue regarding its loss of customers or that
    reasonable differing inferences could be drawn from the undisputed facts. Therefore, we
    cannot say the circuit court erred in granting summary judgment on this point, and we affirm
    its decision.
    19
    Cite as 
    2015 Ark. 360
    Affirmed.
    DANIELSON and HART, JJ., dissent.
    PAUL E. DANIELSON, Justice, dissenting. Because I believe there is a question of
    material fact at issue, I respectfully dissent from the majority’s decision affirming the circuit
    court’s grant of summary judgment.
    Appellants, the Town of Lead Hill and its various town officials (Lead Hill), argue on
    appeal that the circuit court erred in finding that the Wholesale Water Purchase Contract
    entered into with Appellee Ozark Mountain Regional Public Water Authority of the State
    of Arkansas (Ozark) was a valid and enforceable contract, thereby granting Ozark’s motion
    for summary judgment and issuing a writ of mandamus compelling the mayor and aldermen
    of Lead Hill to satisfy the obligations under the contract. Lead Hill argues, in part, that the
    circuit court erred because there is a question of fact as to whether the contract violates article
    12, section 4, of the Arkansas Constitution. I find this argument persuasive.
    The circuit court, in granting Ozark’s motion for summary judgment, concluded that
    none of the defenses to the enforcement of the contract raised by Lead Hill constituted valid
    legal defenses to the enforcement of the water-purchase contract. According to the circuit
    court, there were no genuine issues of material fact, and Ozark was thus entitled to judgment
    as a matter of law. Although the circuit court did not specifically address Lead Hill’s article
    12, section 4 argument, it clearly rejected each of the contract defenses advanced by Lead Hill.
    In arguing that the court erred in granting summary judgment, Lead Hill asserts that
    its contract with Ozark is void and unenforceable because article 12, section 4, of the Arkansas
    20
    Cite as 
    2015 Ark. 360
    Constitution prohibits a city from entering into a contract that is in excess of the city’s annual
    revenue. According to Lead Hill, under the terms of its contract with Ozark, it is obligated
    to pay a minimum monthly charge to Ozark that results in a total obligation of $2.25 million,
    an amount that far exceeds the town’s annual revenue of approximately $360,000. Thus,
    Lead Hill argues that under article 12, section 4, and this court’s case law interpreting that
    provision, it is clear that its contract with Ozark is void and unenforceable.
    Article 12, section 4 provides in relevant part as follows:
    The fiscal affairs of counties, cities and incorporated towns shall be conducted
    on a sound financial basis, and no county court or levying board or agent of any
    county shall make or authorize any contract or make any allowance for any purpose
    whatsoever in excess of the revenue from all sources for the fiscal year in which said
    contract or allowance is made.
    This provision was added to article 12, section 4 by amendment 10, which was approved by
    the people of Arkansas in the 1924 general election and declared adopted by a special supreme
    court in Brickhouse v. Hill, 
    167 Ark. 513
    , 
    268 S.W. 865
    (1925). The thrust of amendment 10
    was to limit the fiscal affairs of counties, cities, and towns. Purvis v. City of Little Rock, 
    282 Ark. 102
    , 129-A, 
    669 S.W.2d 900
    (1984) (supplemental opinion on denial of rehearing).
    It is quite clear from the plain language of article 12, section 4, that a town such as
    Lead Hill may not authorize a contract that exceeds the town’s annual revenue. It is
    irrelevant that the contract included a provision purporting to prohibit Lead Hill from
    guaranteeing the obligations under the contract with its full faith and credit and designating
    that the purchase price be paid from revenue generated through the sale of Ozark’s water,
    because Lead Hill is obligated to pay a minimum monthly charge of between $4,687 and
    21
    Cite as 
    2015 Ark. 360
    $5,540 regardless of whether it generates sufficient revenue from the sale of the water.
    Moreover, there is no provision allowing Lead Hill to terminate the contract if, for instance,
    the revenue it generates from the sale of Ozark’s water is insufficient to cover the minimum
    monthly amount owed to Ozark.
    On appellate review, this court must determine whether summary judgment was
    proper based on whether the evidence presented by the moving party left a material question
    of fact unanswered. Ryder v. State Farm Mut. Auto. Ins. Co., 
    371 Ark. 508
    , 
    268 S.W.3d 298
    (2007). Here, it is obvious that a material question of fact remains because the contract terms
    are in conflict as to whether Lead Hill must pay the minimum monthly charge to Ozark solely
    out of revenue generated from the sale of the water or whether the contract implicates article
    12, section 4, by requiring the town to extend its full faith and credit to satisfy its contractual
    obligation to Ozark. For this reason, I believe it was improper for the circuit court to grant
    summary judgment in favor of Ozark, and I respectfully dissent.
    JOSEPHINE LINKER HART, Justice, dissenting. I am troubled by the circuit court’s
    order:
    The Court hereby declares that the plain and unambiguous terms of the Water
    Purchase Contract are enforceable against the Town of Lead Hill, and hereby issue a
    writ of mandamus compelling the Mayor and Aldermen of the Town of Lead Hill to
    satisfy their obligations under the Water Purchase Contract.
    I believe it must be reversed. The Arkansas Supreme Court has superintending authority over
    the inferior courts of this state. Ark. Const. amend. 80. We should exercise this authority,
    if for no other reason, than to prevent the misuse of an extraordinary writ and the violation
    of our state constitution.
    22
    Cite as 
    2015 Ark. 360
    We have used this superintending authority to remove judges from the bench, Arkansas
    Judicial Discipline Committee v. Proctor, 
    2010 Ark. 38
    , 
    360 S.W.3d 61
    ; appoint special judges
    to take control over a circuit court’s docket, In re Phillips County, 
    2013 Ark. 55
    ; draft all of
    the rules of civil and criminal procedure; and sit as the final approving authority over how a
    judicial district will operate. Accordingly, in the case before us, we should not act as though
    we are fettered by the arguments raised in the parties’ briefs.
    Lost somewhere in the circuit court’s order, the parties’ briefs, and the majority’s
    decision is the fact that the controversy between the parties is simply the breach of a
    commercial contract. Contract cases always have contract remedies. So, there is an adequate
    remedy at law. By seeking the combination of declaratory judgment and mandamus, Ozark
    has sidestepped the issue of which side committed the first material breach—be it Ozark for
    refusing to adjust the minimum monthly charge in accordance with Article B. paragraph 4A
    of the contract or the repudiation of the contract by Lead Hill. As with any contract, even
    contracts that are unquestionably valid when they are executed, issues can arise that can
    excuse performance. This point is pivotal.
    For a writ of mandamus to compel a public corporation to perform its duties towards
    its creditors, there must first be a judgment to establish the validity and amount of the debt.
    School District No. 3 v. Bodenhamer, 
    43 Ark. 140
    (1884). Our declaratory judgment statute
    does not provide for the rendering of a monetary judgment. See Ark. Code Ann. §§16-111-
    101-111 (Repl. 2006). In fact, the general assembly has declared that the purpose of an action
    under this statute is only to “settle and to afford relief from uncertainty and insecurity with
    23
    Cite as 
    2015 Ark. 360
    respect to rights, status, and other legal relations.” Ark. Code Ann. §16-111-102(b). When
    it is apparent that the stated purpose will not be accomplished, the declaratory judgment
    statute expressly empowers a circuit court to refuse to enter a judgment or decree when it
    “would not terminate the uncertainty or controversy giving rise to the proceeding.” Ark.
    Code Ann. §16-111-108. As noted previously, whether the wholesale water purchase
    contract is valid as written is but one aspect of the controversy.2 The issue of whether there
    were valid defenses to enforcement of the contract had to be litigated before a valid monetary
    judgment could issue.3 It is therefore untenable that the circuit court would grant an
    extraordinary writ to enforce payment of money pursuant to a commercial sales contract.
    Hitherto, our law on the propriety of granting a writ of mandamus has been well
    settled. As this court recently stated in Lonoke County. v. City of Lonoke:
    A “writ of mandamus” is “an order of the circuit court granted upon the petition of
    an aggrieved party or the state when the public interest is affected, commanding an
    2
    In determining if there was a valid contract, the circuit court was only being asked to
    determine if the essential elements of a contract were present: (1) competent parties, (2)
    subject matter, (3) legal consideration, (4) mutual agreement, and (5) mutual obligations.
    Tyson Foods, Inc. v. Archer, 
    356 Ark. 136
    , 
    147 S.W.3d 681
    (2004).
    3
    The circuit court’s order is clearly wrong when it states:
    None of the other defenses raised by [Lead Hill] in opposing the Motion for
    Summary Judgment constitutes a valid defense to the enforcement of the Water
    Purchase Contract. No facts supporting such defenses would change the
    enforceability of the Water Purchase Contract as a matter of law.
    Lead Hill clearly asserted that Ozark had committed the first material breach of the contract,
    which would be an absolute defense to enforcement. At the very least, this is a factual
    dispute that should have defeated summary judgment.
    24
    Cite as 
    2015 Ark. 360
    executive, judicial, or ministerial officer to perform an act or omit to do an act, the
    performance or omission of which is enjoined by law.” . . . The writ is issued where
    (1) the duty to be compelled is ministerial and not discretionary, (2) the petitioner has
    shown a clear and certain right to the relief sought, and (3) the petitioner lacks any
    other adequate remedy.
    
    2013 Ark. 465
    , at 2, 
    430 S.W.3d 669
    , 670 (citations omitted). The existence of another
    “adequate remedy” has been treated as subject matter jurisdiction. See, e.g., Hanley v. Ark.
    State Claims Comm’n, 
    333 Ark. 159
    , 
    970 S.W.2d 198
    (1998). Moreover, it is the burden
    of the party applying for the writ—Ozark—to show the absence of any specific legal remedy.
    Goings v. Mills, 
    1 Ark. 11
    (1837). I have found nothing in the record that shows that Ozark
    has carried this burden. This court should therefore adhere to our long-established practice
    of raising issues of subject-matter jurisdiction on our own motion; it is settled law that
    subject-matter jurisdiction, if lacking, cannot be induced simply because there is no
    objection. Love v. Smackover School Dist., 
    322 Ark. 1907
    S.W.2d 136 (1995) (Brown, J.,
    dissenting) (citing J.W. Reynolds Lumber Co. v. Smackover State Bank, 
    310 Ark. 342
    , 
    836 S.W.2d 853
    (1992)).
    The writ of mandamus issued by the circuit court compels the elected officials in Lead
    Hill, including the mayor and five aldermen, who were sued individually, as well as in their
    representative capacities, to pay contract damages. This is a clear abuse of mandamus. This
    court is now saying that a dispute involving any of the thousands of purchase contracts
    entered into by the state and local governments in Arkansas can subject our elected officials
    to personal liability if the government officials decide that there is a reason not to pay.
    More troubling still is the fact that the circuit court order imposes no limitation on
    25
    Cite as 
    2015 Ark. 360
    the source of the funds to pay the minimum monthly charge for the water. Even thought
    the contract by its express terms in article C, paragraph 19 limits the source of the funds
    “solely [to] revenues generated by the sale of Purchaser’s water to its customers.” A long-
    term water-sales contract, such as the one before us, can pass state constitutional muster only
    if it contains a clause that limits the source of the funds to pay the minimum monthly charge
    to revenues generated by the waterworks. McGehee v. Williams, 
    191 Ark. 643
    , 
    87 S.W.2d 46
    (1935). However, as noted, the circuit court’s order contains no such restriction. The
    result is that the circuit court’s order gives Ozark much more than it contracted for and backs
    it up with the contempt powers wielded by the circuit court.
    Looming in the background, though I admit not squarely before this court, is the
    threat that failure to pay these contract damages will result in these public officials being jailed
    for contempt. This is tantamount to imprisoning these officials for a debt, something clearly
    proscribed by our state constitution. Article 2, § 16 succinctly states, “No person shall be
    imprisoned for debt in any civil action, on mesne or final process, unless in cases of fraud.”
    This court has previously rejected the idea that contract cases could be enforced with jail
    time. In State v. Riggs, 
    305 Ark. 217
    , 
    807 S.W.2d 32
    (1991), this court struck down as
    unconstitutional Arkansas Code Annotated section 5-37-525 (Supp. 1989), a statute that
    sought to criminalize a contractor’s or subcontractor’s knowing refusal to pay for materials.
    Invoking appellate practice and procedure is not a justification for retreating from this
    holding.
    I respectfully dissent.
    Taylor & Taylor Law Firm, P.A., by: Andrew M. Taylor and Tasha C. Taylor, for
    appellants.
    Martin Law Firm, P.A., by: Thomas A. Martin; and
    Friday, Eldredge & Clark, LLP, by: R. Christopher Lawson, for appellee.
    26
    

Document Info

Docket Number: CV-14-848

Citation Numbers: 2015 Ark. 360, 472 S.W.3d 118, 2015 Ark. LEXIS 580

Judges: Karen R. Baker

Filed Date: 10/8/2015

Precedential Status: Precedential

Modified Date: 11/14/2024

Authorities (21)

Thomas v. Sessions , 307 Ark. 203 ( 1991 )

Potter v. City of Tontitown , 371 Ark. 200 ( 2007 )

Ryder v. State Farm Mutual Automobile Insurance , 371 Ark. 508 ( 2007 )

Smith v. Sidney Moncrief Pontiac, Buick, GMC Co. , 353 Ark. 701 ( 2003 )

J.W. Reynolds Lumber Co. v. Smackover State Bank , 310 Ark. 342 ( 1992 )

Purvis v. City of Little Rock , 282 Ark. 102 ( 1984 )

Showmethemoney Check Cashers, Inc. v. Williams , 342 Ark. 112 ( 2000 )

Hanley v. Arkansas State Claims Commission , 333 Ark. 159 ( 1998 )

The Money Place, LLC v. Barnes , 349 Ark. 411 ( 2002 )

Barnhart v. City of Fayetteville, Ark. , 321 Ark. 197 ( 1995 )

Mooney v. Gantt , 1951 Ark. LEXIS 549 ( 1951 )

Flentje v. First Nat. Bank of Wynne , 340 Ark. 563 ( 2000 )

Jordan v. Diamond Equipment & Supply Co. , 362 Ark. 142 ( 2005 )

Csl Utilities, Incorporated and Csl Community Association, ... , 16 F.3d 130 ( 1994 )

Gulfco of Louisiana, Inc. v. Brantley , 2013 Ark. LEXIS 438 ( 2013 )

Public Water Supply Dist. No. 3 of Laclede Cnty. v. City of ... , 605 F.3d 511 ( 2010 )

Keith v. City of Cave Springs , 1961 Ark. LEXIS 406 ( 1961 )

Williams v. Harris, Mayor , 215 Ark. 928 ( 1949 )

McGehee v. Williams , 191 Ark. 643 ( 1935 )

Blount v. Baker , 177 Ark. 1162 ( 1928 )

View All Authorities »