Mission1st Group, Inc. ( 2021 )


Menu:
  •                 ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeals of --                                 )
    )
    Mission1st Group, Inc.                        )      ASBCA Nos. 62461, 62646
    )
    Under Contract No. W52P1J-13-F-0031           )
    APPEARANCES FOR THE APPELLANT:                          Joshuah R. Turner, Esq.
    Elizabeth J. Cappiello, Esq.
    Jason N. Workmaster, Esq.
    Miller & Chevalier Chartered
    Washington, DC
    APPEARANCES FOR THE GOVERNMENT:                         Scott N. Flesch, Esq.
    Army Chief Trial Attorney
    Zachary F. Jacobson, Esq.
    Trial Attorney
    OPINION BY ADMINISTRATIVE JUDGE D’ALESSANDRIS
    In September 2013, the Army Contracting Command – Rock Island Arsenal
    (Army or government) awarded appellant, Mission1st Group, Inc. (M1), a task order
    against M1’s General Services Administration (GSA) Information Technology (IT)
    Schedule 70 Contract. The task order provided for a base period and, pursuant to
    Federal Acquisition Regulation (FAR) 52.217-9, OPTION TO EXTEND THE TERM
    OF THE CONTRACT (MAR 2000), two option periods. In addition, pursuant to FAR
    52.217-8, OPTION TO EXTEND SERVICES (NOV 1999), the task order contained an
    option to extend the contract for a period of up to six months. M1 encountered
    problems retaining staff at the labor rates it proposed in the task order, and discussed
    with the Army terminating the contract. After the Army indicated that it planned to
    exercise the first option period, M1 indicated that it would challenge the exercise of the
    option unless the government agreed to reprice certain contract line items. M1 also
    opposed the Army’s suggestion that the parties agree to a reduced duration three-month
    option period. The Army then exercised its right to extend services for a three-month
    period, pursuant to FAR 52.217-8. The task order was subsequently bilaterally
    modified twice to extend the period of performance.
    M1 contends that the Army improperly exercised the option to extend services
    out-of-sequence, entitling it to a contractual price adjustment. According to M1, the
    option to extend services is really an option period 3 that can only be exercised
    following option periods 1-2. Additionally, M1 argues that the Army’s exercise of the
    option four days before expiration of the base period of performance was not “within
    90 days before the expiration of the contract.” We hold that the language of the task
    order permitted the Army to exercise the option to extend services after the base
    period, and that the option was timely exercised. Additionally, we note that, even if
    the Army’s exercise of the option was defective, M1 waived its right to a contractual
    adjustment through a subsequent bilateral modification.
    FINDINGS OF FACT
    The Army Contracting Command – Rock Island Arsenal awarded Task Order
    No. W52P1J-13-F-0031 to Mission1st Group, Inc. on September 24, 2013, for
    Network and Communications, Engineering and Installation Support pursuant to M1’s
    GSA IT Schedule 70 Contract No. GS35F0199Y, Special Item No. 132 51, IT
    Professional Services contract (R4, tab 1 at 1, 4).1 Under the task order, M1 provided
    theater communications and networking infrastructure and subject matter experts to
    perform project management and information assurance in support of the Army
    primarily in Afghanistan and Kuwait (R4, tab 1 at 4).
    The Army awarded the task order as a firm-fixed price contract, with some
    contract line items (CLINs) such as overtime and travel paid at cost (id.). The task
    order provided:
    This is a Firm-Fixed Price (FFP) task order with a base
    period and three evaluated option periods.
    Base Period: 24 September 2013 to 23 June 2014
    Option Period One: 24 June 2014 to 23 March 2015
    Option Period Two: 24 March 2015 to 23 December 2015
    Option to Extend Services: Six Month Maximum to be
    completed no later than 23 June 2016
    (Id.). The performance work statement “Period of Performance” provides that there is a
    nine-month base period and “two (2) nine (9) month options” (R4, tab 2 at 51). The
    prices proposed by M1 and accepted by the Army included $5,355,900.79 for the
    nine-month base period (R4, tab 1 at 4). The Army also accepted M1’s proposed prices
    for two nine-month option periods, priced at $5,382,254.68 and $5,417,880.85,
    1   We have dropped all leading zeros from the Bates numbers used by the government.
    For documents that were not Bates numbered, we used the document’s internal
    page numbers. Appellant’s opposition and reply brief was not paginated so we
    used the PDF page numbers.
    2
    respectively (id.). In addition to the option years, M1 proposed a price not to exceed
    $3,743,169.77 for up to a total of six months of extended services, to be completed no
    later than June 23, 2016 (id.).
    Noting that M1’s price quote offered a significant discount from the approved
    GSA Schedule rates, the contracting officer noted that M1 had expressly indicated in
    its quote that the discount was intentional, and determined that M1’s quote was still
    responsible (gov’t supp. R4, tab 7 at 1-3). The task order’s clause addendum included
    the following standard clauses from the FAR:
    52.217-8, OPTION TO EXTEND SERVICES (NOV 1999)
    The Government may require continued performance of
    any services within the limits and at the rates specified in
    the contract. These rates may be adjusted only as a result
    of revisions to prevailing labor rates provided by the
    Secretary of Labor. The option provision may be
    exercised more than once, but the total extension of
    performance hereunder shall not exceed 6 months. The
    Contracting Officer may exercise the option by written
    notice to the Contractor within 90 days before the
    expiration of the contract.[2]
    (End of Clause)
    52.217-9, OPTION TO EXTEND THE TERM OF THE
    CONTRACT (MAR 2000)
    (a) The Government may extend the term of this contract
    by written notice to the Contractor within the term of the
    contract prior to contract expiration; provided that the
    Government gives the Contractor a preliminary written
    notice of its intent to extend at least 90 days before the
    contract expires. The preliminary notice does not commit
    the Government to an extension.
    2   Relevant to the jurisdiction of the Board, but not relevant to our interpretation of the
    contract, the last sentence of this clause in the FAR provides: “The Contracting
    Officer may exercise the option by written notice to the Contractor within _____
    [insert the period of time within which the Contracting Officer may exercise the
    option].” FAR 52.217-8. M1’s GSA schedule provides: “The Contracting
    Officer may exercise the option by written notice to the Contractor within
    30 days” (gov’t supp. R4, tab 10b at 46).
    3
    (b) If the Government exercises this option, the extended
    contract shall be considered to include this option clause.
    (c) The total duration of this contract, including the
    exercise of any options under this clause, shall not exceed
    33 months.[3]
    (End of Clause)
    (R4, tab 3 at 123)
    On March 25, 2014,4 91 days prior to the end of the base period of
    performance, the Army provided M1 with its notice of intent to exercise the first
    option period in accordance with the terms and conditions of the contract and FAR
    52.217-9, OPTION TO EXTEND THE TERM OF THE CONTRACT (gov’t supp.
    R4, tab 3). On April 25, 2014 and April 28, 2014, M1 alerted the government that it
    would have difficulty continuing performance on some of its contract line items unless
    the government obligated an additional 25 percent of the estimated not-to-exceed price
    (R4, tab 15 at 489-90).
    The government offered M1 a draft partial option period for the task order on
    June 10, 2014, which, if executed, would have only required M1 to perform for
    three-months, rather than the full nine-months contained in the contractual option period
    (gov’t supp. R4, tab 4 at 1). Having received no comments from M1, the government
    followed-up with M1 on June 17, 2020 (R4, tab 19 at 760). In response, M1 asserted that
    3 Similarly, subsection (c) of the FAR does not specify a total contract duration:
    “(c) The total duration of this contract, including the exercise of any options
    under this clause, shall not exceed ___________ (months) (years).” FAR
    52.217-9(c). M1’s GSA schedule provides “(c) The total duration of this
    contract, including the exercise of any options under this clause, shall not
    exceed . (months) (years)” (gov’t supp. R4, tab 10b at 46).
    4 The government proposed several facts regarding a purported March 21, 2014, meeting
    at which the president of M1, met with the contracting officer to discuss M1’s
    difficulties staffing the contract at the proposed rates, M1’s efforts to retain
    personnel by paying higher wages, and the possibility of terminating the contract
    (gov’t br. at 4). However, the government cites to a document it identifies as
    “SR 4, tab G-1” which was not contained in any of the government’s Rule 4
    submissions. By order dated April 6, 2021, the Board notified the government
    that it appeared some of its cites to its Rule 4 submissions were incorrect and
    requested that the government file a corrected brief. The government’s corrected
    brief continues to cite to the non-existent tab G-1 (gov’t corr. br. at 4). The
    Board was unable to locate support for the proposed facts in the record.
    4
    a partial option period would require a bilateral modification, that it was suffering losses,
    and that it would incur additional losses if the contract were extended (R4, tab 19 at 763).
    M1 indicated that it would only agree to the partial option period if the government agreed
    to reprice the contract for “any period beyond the initial three-month extension” (id.). M1
    stated that an upward price adjustment would “free the government of any liability for
    additional cost and profit incurred by Mission1st over the entire period of performance
    beginning with contract inception” (R4, tab 19 at 763-64).
    M1 described the additional “consequences” for the government of implementing
    a modification without repricing or agreed termination at the end of the three-months,
    such as a reduction in the level of service and performance due to salary cuts of its
    personnel (id. at 764). On June 19, 2014, two days after receiving appellant’s letter, the
    government notified M1 that it was exercising its Option to Extend Services for the
    task order (R4, tab 20).
    On June 23, 2014, the government executed Modification No. P00009 in writing
    to exercise a three-month option period pursuant to contract clause FAR 52.217-8,
    OPTION TO EXTEND SERVICES (NOV 1999) (R4, tab 22 at 768, 770). The
    modification priced the option at $2,149,591 (R4, tab 22 at 768). On July 3, 2014, M1
    responded to the government’s notice of execution with a letter asserting that the notice
    to exercise the Option to Extend Services provided by the government was untimely,
    and therefore ineffective and entitled M1 to an equitable price adjustment (R4, tab 24
    at 790-91). M1 also stated that it was able to perform during the extended period, but
    that it would seek compensation (id. at 791).
    Effective July 16, 2014, the government and M1 bilaterally signed Modification
    No. P00010, which stated that all other terms and conditions remained unchanged (R4,
    tab 25 at 1). Effective August 22, 2014, the government and M1 bilaterally signed
    Modification No. P00011, under which the government exercised its Option to Extend
    Services for the remaining three-months, that stated:
    9. The total contract value and the total funded value for
    the Option to Extend Services period are hereby changed
    from $2,149,591.00 to $4,087,141.03, a total increase of
    $1,937,550.03.
    10. The total contract value and the total funded value for
    this task order are hereby changed from $7,915,976.49 to
    $9,853,526.52, a total increase of $1,937,550.03.
    11. All other terms and conditions remain unchanged.
    (R4, tab 27 at 846, 848-49)
    5
    On September 12, 2014, the government and M1, without exception, bilaterally
    signed Modification No. P00012, which added a logistician position and provided:
    7. The total contract value and the total funded value for
    the Option to Extend Services period are hereby changed
    from $4,087,141.03 to $4,133,723.10, a total increase of
    $46,582.07.
    8. The total contract value and the total funded value for
    this task order are hereby changed from $9,853,526.52 to
    $9,900,108.59, a total increase of $46,582.07.
    9. All other terms and conditions remain unchanged.
    (R4, tab 30 at 961, 1011)
    On June 24, 2019, M1 filed a certified claim in the amount of $3,694,336.73,
    asserting that the government improperly exercised its option to extend services, and
    as a result, it is entitled to excess incurred costs and a reasonable profit (R4, tab 31
    at 1018). On March 5, 2020, the contracting officer denied M1’s claim (R4, tab 32).
    On June 3, 2020, M1 filed a certified claim with the GSA requesting a final decision
    on the same matter currently before the Board (gov’t supp. R4, tab 8). On June 3,
    2020, M1 also filed a second certified claim with the contracting officer, stating that it
    had already appealed the March 5, 2020 final decision to the Board, and that it
    believed that the Board possessed jurisdiction to entertain both counts of its complaint,
    but was submitting a new claim out of an abundance of caution (gov’t supp. R4, tab 9).
    M1 appealed to the Board from the purported deemed denial of its June 3, 2020 claim. 5
    DECISION
    By request of the parties, this appeal is being decided pursuant to Board Rule 11,
    “Submission Without a Hearing.” Unlike a motion for summary judgment, which must
    be adjudicated on the basis of a set of undisputed facts, pursuant to Board Rule 11, the
    Board “may make findings of fact on disputed facts.” Grumman Aerospace Corp.,
    
    ASBCA No. 35185
    , 
    92-3 BCA ¶ 25,059
     at 124,886 n.13 (Kienlen, J. dissenting).
    M1 asserts that the government improperly exercised the option to extend
    performance out of order, thus entitling it to a contractual adjustment (app. br. at 8).
    Alternatively, M1 asserts that the government did not provide it with the contractually
    required notice, thus, entitling it to a contractual adjustment (app. br. at 9).
    5   The record does not contain a final decision issued by a GSA contracting officer.
    6
    I.     The Contract Allowed The Army To Exercise The Option For Extension
    of Services At The End Of The Base Period Of Performance
    The task order clause describing the relevant options provides:
    This is a Firm-Fixed Price (FFP) task order with a base
    period and three evaluated option periods.
    Base Period: 24 September 2013 to 23 June 2014
    Option Period One: 24 June 2014 to 23 March 2015
    Option Period Two: 24 March 2015 to 23 December 2015
    Option to Extend Services: Six Month Maximum to be
    completed no later than 23 June 2016
    (R4, tab 1 at 4). Based upon the location of the option to extend services, below option
    periods one and two, and the reference to three option periods, M1 contends that the
    option to extend services should be interpreted as being, in reality, option period three.
    M1 additionally cites to the end of the performance period for option period three of
    June 23, 2016, as evidence that the option to extend services was to be exercised
    following option period two, which had a performance period ending on December 23,
    2015. (app. br. at 8).
    In Glasgow Investigative Solutions, Inc., 
    ASBCA No. 58111
    , 
    13-1 BCA ¶ 35,286
     at 173,175-76, we held that the option to extend services pursuant to
    FAR 52.217-8 was not limited to use after exercise of the option periods. See also
    Griffin Services, Inc., ASBCA Nos. 52280, 52281, 
    02-2 BCA ¶ 31,943
     at 157,803-04.
    Our prior holding in Glasgow is binding on this panel and compels us to deny M1’s
    appeal. SWR, Inc., 
    ASBCA No. 56708
    , 
    15-1 BCA ¶ 35,832
     at 175,220. However,
    even if we were not bound by Glasgow, we interpret the terms of the task order as
    permitting the government to exercise the option to extend services independent of
    exercising the options to extend the term of the contract.
    M1 relies upon the holding of the United States Court of Appeals for the Federal
    Circuit in Lockheed Martin Corp. v. Walker, 
    149 F.3d 1377
     (Fed. Cir. 1998). In
    Lockheed, the contract provided for a series of options that were to be exercised
    according to a schedule providing set periods of time for each option. The government
    exercised the option at CLIN 0006 to be exercised within 8-18 months after award,
    without first exercising the option at CLIN 0005, which was to be exercised within
    8 months of award. 
    Id. at 1378-79
    . The Federal Circuit held that the government had
    improperly exercised the options out of sequence based upon its reading of the contract
    7
    and the fact that the option periods contained declining unit prices, indicating the use of
    a learning curve. 
    Id. at 1380
    . However, the task order at issue here differs from the
    schedule in Lockheed because the task order contains only an end date, and not a
    beginning date for exercise of the option to extend services under FAR 52.217-8, while
    the options to extend the term of the contract under FAR 52.217-9 contain both start
    and end dates (R4, tab 1 at 3). In Lockheed the option periods had beginning and end
    dates for the exercise of each option. Lockheed, 
    149 F.3d at 1378
    . Additionally, to the
    extent that the reference to “three evaluated option periods” (R4, tab 1 at 4) could be
    ambiguous, it must be read in conjunction with the performance work statement which
    clearly provides in the “Period of Performance” that there is a 9 month base period and
    two 9 month option periods (R4, tab 2 at 52).
    II.    The Army Properly Exercised The Option For Extension Of Services
    Within 90 Days Of The End Of The Contract
    M1 contends that, even if the Army were permitted to exercise the option to extend
    services without first exercising the contract options, the Army did not provide notice in
    accordance with the contract (app. br. at 9). As noted above, the contract provides that
    “[t]he Contracting Officer may exercise the option by written notice to the Contractor
    within 90 days before the expiration of the contract” 6 (R4, tab 3 at123) (emphasis added).
    The base period of the contract expired on June 23, 2014 (R4, tab 1 at 4). The government
    notified M1 that it was exercising its Option to Extend Services for the task order on
    June 19, 2014 – four days before expiration of the contract (R4, tab 20). On June 23, 2014
    – the last day of the base period of the contract -- the government executed Modification
    No. P00009 to exercise three-months of the Option to Extend Services (R4, tab 22). M1
    contends that the Army’s exercise of the option was untimely because “within 90 days
    before the expiration of the contract” means that the Army was required to exercise the
    option “prior to or on the 90th day before the contract expired” (app. br. at 9). M1
    additionally contends that “within” should be read as “at least” (app. resp. at 6).
    We interpret the contract based on the plain meaning of the words in their
    ordinary use. See, e.g., Access Personnel Ser., Inc., 
    ASBCA No. 59900
    , 
    17-1 BCA ¶ 36,845
     at 179,534. Here, the word “within” means “inside the range of (an area or
    boundary) . . . occurring inside (a particular period of time)”. NEW OXFORD
    AMERICAN DICTIONARY 1985 (3d ed. 2010). Clearly, the government exercised the
    option “inside” the 90 day period of time before the end of the contract. Accordingly,
    we hold that the government properly exercised the option to extend services.
    6   As noted above, the language “within 90 days before the expiration of the contract”
    was inserted in the standard FAR clause by the Army contracting officer. Thus,
    this dispute does not involve interpretation of the terms of the GSA schedule
    contract, and does not need to be resolved by a GSA contracting officer. See
    Sharp Elec. Corp. v. McHugh, 
    707 F.3d 1367
    , 1373-74 (Fed. Cir. 2013).
    8
    M1 asserts that the Board’s holdings in APAC-Southeast, Inc. N/K/A Oldcastle S.
    Grp., 
    ASBCA No. 58057
    , 
    12-2 BCA ¶ 35,155
     and Petchem, Inc., 
    ASBCA No. 53792
    ,
    
    05-1 BCA ¶ 32,870
     support its interpretation of “within 90 days” as requiring the
    government to exercise the option at least 90 days before the end of the contract (app.
    br. at 9). However, at best, these Board decisions involved the early exercise of options
    that were not challenged before the Board. Neither appeal involved a determination of
    whether the government timely exercised the option. APAC-Southeast involved the
    exercise of an option, pursuant to FAR 52.217-8 that exceeded the stated contract
    duration. APAC-Southeast, 
    12-2 BCA ¶ 35,155
     at 172,532. In Petchem the
    government exercised an option to extend services, pursuant to FAR 52.217-8, because
    it could not meet the notice requirement for exercise of options pursuant to
    FAR 52.217-9, but then sought to exercise the option to extend services beyond the
    period of time permitted in the contract. Petchem, 
    05-1 BCA ¶ 32,870
     at 162,900-01.
    Neither opinion addresses the timeliness of the exercise of the options.
    III.   Even If The Army Had Not Properly Exercised The Extension Of
    Services, M1 Waived Any Potential Claim Through The Subsequent
    Bilateral 7 Modifications
    As an alternative basis, the government argues that, even if its exercise of the
    option to extend services was deficient, that M1 waived its claim by agreeing to
    bilateral Modification Nos. P00010, P00011, and P00012 8 (gov’t br. at 16-17). The
    government argues that by agreeing to continue performance, with all terms and
    conditions remaining unchanged, M1 waived its rights to object (id.). The government
    analogizes M1’s actions to that of a contractor agreeing to a new delivery schedule and
    waiving the right to raise pre-existing causes of delay (id.at 17). M1 contends that it
    did not waive any rights and that it waived, at most, its right to stop performing the
    contract (app. resp. at 7).
    The government argues that M1 waived its claim by agreeing to the bilateral
    modifications. However, waiver occurs when the parties to a contract accept modified
    performance without changing the terms of the written contract. Here, the parties
    7 FAR 2.101 defines the term “option” as a “unilateral right in a contract by which . . .
    the Government may elect to purchase additional supplies or services . . . or may
    elect to extend the term of the contract.” The exercise of an option must be
    unconditional and set forth terms that are in accord with the option as stated in
    the contract. Any changes to the options, as awarded, would necessitate a
    bilateral agreement. (See Alutiiq Commercial Enterprises, LLC, 
    ASBCA No. 61503
    , 
    20-1 BCA ¶ 37,506
     at 182,198, citations omitted).
    8 The government additionally alleges waiver through continued performance because
    M1 did not object to the exercise of the option until 10 days after it began
    performance (gov’t br. at 17). We need not reach this issue.
    9
    modified performance through formal written modifications. Because there was an
    existing dispute regarding the exercise of the option period at the time of the bilateral
    modifications, the change could be evaluated as an accord and satisfaction. An accord
    and satisfaction occurs “when some performance different from that which was
    claimed as due is rendered and such substituted performance is accepted by the
    claimant as full satisfaction of his claim.” Bell BCI Co. v. United States, 
    570 F.3d 1337
    , 1340-41 (Fed. Cir. 2009) (quoting Cmty. Heating & Plumbing Co. v. Kelso,
    
    987 F.2d 1575
    , 1581 (Fed. Cir. 1993)). However, here the parties twice bilaterally
    modified the terms of the contract to redefine the very performance that M1 challenges
    in its claim. The plain language of the contract, as modified, precludes M1’s claim.
    See, e.g., Supply & Service Team GmbH, 
    ASBCA No. 59630
    , 
    17-1 BCA ¶ 36,678
    at 178,601.
    M1 signed a bilateral modification (Modification No. 11), that extended the
    option period and modified the value of the option period, while providing that all
    other terms and conditions remained the same. “The total contract value and the total
    funded value for the Option to Extend Services period are hereby changed from
    $2,149,591 to $4,087,141.03, a total increase of $1,937,550.03” (R4, tab 27 at 849).
    The original amount of $2,149,591 cited in Modification No. 11 was the amount of the
    option to extend services in Modification No. 9 – the modification being challenged by
    M1 (R4, tab 22 at 768). Thus, in Modification No. 11, M1 agreed to perform the
    option to extend services for a price of $4,087,141.03 and that amount included
    performance of the option to extend services during the period covered by
    Modification No. 9. Therefore, giving effect to the clear and unambiguous language
    of the modification, M1 agreed to perform the entire option to extend services from
    June 24, 2014 to December 23, 2014, including the period of June 24, 2014 to
    September 23, 2014 covered by Modification No. 9, for $4,087,141.03. This
    constitutes an agreement resolving M1’s dispute regarding the exercise of the option to
    extend services, and its attempt to reprice its performance of the option. Similarly, in
    Modification No. 12, M1 agreed to add a logistician position and agreed to a price for
    performance of the option to extend services from June 24, 2014 to December 23,
    2014 (R4, tab 30 at 1011).
    M1 cites to the Board’s holding in Alutiiq Commercial Enterprises, LLC,
    
    20-1 BCA ¶ 37,506
    , for the proposition that, at most, M1 waived its right to object to
    the exercise of the option, but that it did not waive the right to seek additional
    compensation (app. resp. at 7). According to M1, “the modifications at issue should
    not be ‘purport[ed] to resolve’ anything outside the scope of their plain language,
    particularly not the waiver of a right to file a claim” (id.) (quoting Alutiiq, 
    20-1 BCA ¶ 37,506
     at 182,199). While we agree with M1 that a modification only resolves the
    issues within the scope of the plain language of the modification, here, Modification
    10
    No. 11 9 “resolved” the payment for the performance of the option to extend
    performance (R4, tab 27 at 849).
    CONCLUSION
    For the reasons stated above M1’s appeals are denied.
    Dated: August 16, 2021
    DAVID D’ALESSANDRIS
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                            I concur
    RICHARD SHACKLEFORD                                 OWEN C. WILSON
    Administrative Judge                                Administrative Judge
    Acting Chairman                                     Vice Chairman
    Armed Services Board                                Armed Services Board
    of Contract Appeals                                 of Contract Appeals
    9   We do not address the government’s arguments regarding Modification No. 10, and
    make no findings as to whether those modifications also constitute a waiver or
    accord and satisfaction.
    11
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA Nos. 62461, 62646, Appeals of
    Mission1st Group, Inc., rendered in conformance with the Board’s Charter.
    Dated: August 17, 2021
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    12
    

Document Info

Docket Number: ASBCA No. 62461, 62646

Judges: D'Alessandris

Filed Date: 8/16/2021

Precedential Status: Precedential

Modified Date: 9/1/2021