BRDC, a Joint Venture ( 2019 )


Menu:
  •                 ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeals of --                                  )
    )
    BRDC, a Joint Venture                          )      ASBCA Nos. 60130, 60668, 61611
    )
    Under Contract No. N69450-10-C-1262            )
    APPEARANCE FOR THE APPELLANT:                         Michael T. Ambroso, Esq.
    DCK Worldwide, LLC
    Pittsburgh, PA
    APPEARANCES FOR THE GOVERNMENT:                       Craig D. Jensen, Esq.
    Navy Chief Trial Attorney
    Matthew D. Bordelon, Esq.
    Russell A. Shultis, Esq.
    Trial Attorneys
    OPINION BY ADMINISTRATIVE JUDGE MCILMAIL
    In this construction matter, appellant seeks additional compensation for
    concrete, aggregates, and concrete testing, and for sand for masonry and stucco. The
    parties decided to submit this case on the record pursuant to Board Rule 11. Only
    entitlement is before us.
    FINDINGS OF FACT
    Appellant is a joint venture consisting ofDCK Worldwide, LLC, and Burns and
    Roe Services Corporation (BRSC) (R4, tab 73.2 at 7061-62). On June 3, 2010, the
    government contracted with appellant for the construction of family housing units, and
    the renovation of a fitness center, at Naval Base Guantanamo Bay (GTMO), and to
    begin work within 10 calendar days after receiving the award (rev. R4, tab 6 at 109-91,
    1096).
    In June 2009, prior to contract award, the solicitation provided, by way of
    Amendment 0013:
    The following clarification is provided regarding the
    pricing of concrete for this project:
    The Government cannot guarantee the pricing of concrete,
    aggregate or concrete testing at Guantanamo Bay after
    30 November 2010 when the contract pricing under
    BRSC' s existing contract expires. Offeror 's [sic] should
    do their best to realistically estimate what this cost may be
    after 1 December 2010 [emphasis added].
    The successful offeror will be required to purchase
    concrete, aggregate and concrete testing services from the
    follow on supplier after 1 December 2010. The
    Government does guarantee that the price provided to the
    successful offeror will be no more than the best price
    available to the Government under the successor contract
    which will replace this contract in December of 2010.
    The successful Contractor will be allowed to request an
    equitable adjustment to the contract after award to adjust
    their price if the price for concrete, aggregate and concrete
    testing varies more than 10% as of 1 December 2010 from
    the estimated price. This adjustment may be an increase if
    the price for these commodities in the Government's
    contract goes up, or a reduction in price if the
    Government's price is less. An adjustment will only be
    made if the Government's price varies more than 10% in
    either direction (up or down) from the Contractor's
    estimated price. The Contractor will be required to
    substantiate (provide supporting documentation) their
    request for adjustment.
    (Rev. R4, tab 3 at 2270-71) (secondary emphasis omitted)
    Section 1.3.23 of the contract, Concrete Batch Plant, provides:
    A concrete batch plant is located on Naval Base
    Guantanamo Bay [GTMO]. Up to 5,000
    cubic yards of concrete can be purchased for specific
    projects at GTMO ....
    The government cannot guarantee the pricing of the
    concrete, aggregate or concrete testing at Guantanamo Bay
    after 30 November 2010 when the contract pricing under
    BRSC's existing contract expires. Offeror's [sic] will be
    required to purchase concrete, aggregate and concrete
    testing services from the follow on supplier after
    1 December 2010. The Government does guarantee that
    the price provided to the successful offeror will be no more
    2
    I
    than the best price available to the Government under the
    successor contract which will replace this contract in
    December of 2010.
    The successful Contractor will be allowed to request an
    equitable adjustment to the contract after award to adjust
    their price if the price for concrete, aggregate and concrete
    testing varies more than 10% as of 1 December 2010 from
    the estimated price. This adjustment may be an increase if
    the price for these commodities in the Government's
    Contract goes up or a reduction in price if the
    Government's price is less. An adjustment will only be
    made if the Government's price varies more than 10% in
    either direction (up or down) from Contractor's estimate
    price. The Contractor will be required to substantiate
    (provide supporting documentation) their request for
    adjustment.
    (R4, tab 56 at 4475) (emphasis added)
    The contract also provided, at section 1.3 .4.1, Availability and Cost of
    Government Materials and Services:
    ... The cost of Government materials, equipment, and
    services reflected in this specification are subject to
    fluctuation, revision, and adjustment.... [S]hould the actual
    rate required to be paid by the Contractor vary by more
    than 15 percent from that specified, the contract price will
    be adjusted to reflect the amount by which the rate actually
    paid varies by more than 15 percent from that specified.
    (Id. at 4467) (emphasis added) Finally, in January 2010, prior to awarding the
    contract, the government answered this way to a bidder's question:
    Question RFI 0017-14: Previously, Amendment 0008 had
    a price listing titled Attachment J-1, Exhibit Line Item
    Numbers. Does this still apply? Does it need to be
    reissued? Please advise.
    Answer RFI 0017-14: The proposer shall use the J-1
    provided in amendment 001 7.
    3
    (Rev. R4, tab 3 at 2121, 2125) Attachment J-1 to Amendment 0017 lists prices for
    concrete, aggregate, and concrete testing (R4, tab 3 at 2121, 2152-53). Appellant
    relied upon and incorporated the Attachment J-1 unit prices to calculate its anticipated
    costs for concrete, aggregates, and testing (app. R4, supp. A-1 at 3110 & attachs. 5, 7;
    A-2 at 3 1 11 & attachs. 5, 7; gov't br. at 9). BRSC held the contract to operate the
    concrete batch plant at GTMO from December 1, 2005 through November 30, 2010
    (R4, tab 76 at 2966-75). On December 1, 2010, Bums and Roe Enterprises, Inc., was
    awarded the follow-on contract to operate the plant from December 1, 2010 through
    November 30, 2015 (app. R4, supp. A-3, attach. 2).
    In March 2013, appellant requested a $2,364,246 increase in the contract price,
    citing section 1.3.23 (R4, tab 36 at 1283-84). The government, also citing
    section 1.3.23, responded by unilaterally modifying the contract to add $909,920.13 to
    the contract price (R4, tab 31 at 1187, 1190), as the government now explains (by way
    of a proposed finding of fact), '"to compensate [appellant] for concrete price costs
    increases exceeding 10 percent of the J-1 concrete prices that [appellant] cited" (gov't
    br. at 7121).
    DECISION
    ASBCA Nos. 60130 & 61611
    The government says that appellant cannot rely on the J-1 price list as its
    "estimated price" for purposes of section 1.3.23 (see gov't br. at 9).* Section 1.3.23
    provides that '"[t]he successful Contractor will be allowed to request an equitable
    adjustment to the contract after award to adjust their price if the price for concrete,
    aggregate and concrete testing varies more than 10% as of 1 December 2010 from the
    estimated price." (R4, tab 56 at 44 75) A concurrent interpretation by the parties of
    contract terms prior to a dispute is entitled to great, if not controlling, weight. Ver-Val
    Enterprises, Inc., ASBCA No. 43766, 95-1BCA127,334 at 136,232. Prior to this
    dispute, the government at least implicitly agreed with appellant that J-1 prices could
    be used as the estimated price benchmark for purposes of section 1.3 .23: appellant
    requested a contract price adjustment to take into account an increase above J-1 prices,
    and the government increased the contract price. The government now explains (by
    way of a proposed finding of fact) that the increase in the contract price was '"to
    compensate [appellant] for concrete price costs increases exceeding 10 percent of the
    J-1 concrete prices that [appellant] cited" (gov't br. at 7121 (emphasis added)).
    * Appellant asserts as entitlement issues whether it may recover overhead and profit
    (app. br.at81 l(b)). We regard those as quantum issues. See Missouri
    Department ofSocial Services, ASBCA No. 61121, 19-1 BCA 137,240
    at 181,278-79.
    4
    Although appellant's argument relies upon that government action, the
    government's argument fails to address its import (app. br. at 5-6118, 15-16; gov't
    br. at 8-21). Rather, the government relies heavily on the provision in Amendment
    0013 to the solicitation that "Offeror's should do their best to realistically estimate
    what this cost may be after 1 December 2010" (gov't br. at 13-15), but, as appellant
    points out and the government appears only to acknowledge (reply at 3-4; gov't br.
    at 14 n.8), that provision is not in section 1.3.23 of the contract itself. Moreover, as
    appellant also points out but the government ignores (app. br. at 3; gov't br. at 8-21),
    when a bidder asked whether "a price listing titled Attachment J-1" still applied, the
    government said bidders "should use the J-1." Appellant did so, to estimate its prices.
    For all these reasons, appellant may base a request for a section 1.3.23 price increase
    upon an increase above the Attachment J-1 prices.
    The only issue remaining in ASBCA Nos. 60130 and 61611 is whether, with
    prices having increased more than 10% above its estimated prices, appellant is entitled
    to the first 10% of that increase. The answer is yes. We interpret the contract as a
    whole, to give reasonable meaning to all its parts and avoid conflict or surplusage of
    its provisions. Granite Construction Co. v. United States, 962 F .2d 998, 1003
    (Fed. Cir. 1992). Unlike section 1.3.4.1 of the contract, which expressly limits an
    adjustment to the contract price "to reflect the amount by which the rate actually
    paid varies by more than 15 percent from that specified," (R4, tab 56 at 4467)
    section 1.3.23 provides no such limitation. Consequently, appellant's recovery
    includes the first 10% of the increase above its estimated price. See KiSKA
    Construction Corp.-USA & Kajima Engineering & Construction, Inc., JV, ASBCA
    Nos. 54163, 54614, 09-1BCA134,089 at 168,564 (awarding entire amount of
    quantity increase pursuant to clause providing that equitable adjustment be based upon
    "any increase .. .in costs due solely to the variation above 115 percent...ofthe estimated
    quantity") (alteration in original) ajf'd, 
    736 F. Supp. 2d 171
    , 192 (D.D.C. 2010), aff'd,
    
    443 F. App'x 561
    (D.C. Cir. 2011). Accordingly, appellant is entitled to additional
    compensation in ASBCA Nos. 60130 and 61611.
    ASBCA No. 60688
    Appellant says that the term "aggregate" in section 1.3 .23 includes "masonry
    and stucco sand," and therefore that the contact required it to obtain masonry and
    stucco sand from the GTMO concrete batch plant, despite an unavailability of sand
    suitable for masonry and stucco at the plant that resulted in an increase in its costs
    (app. br. at 18-21; reply at 9). We need not decide whether the term "aggregate" in
    section 1.3.23 includes such "masonry and stucco sand." A contractor is not entitled
    to recover for a defect in a government contract where the contractor was or should
    have been aware of the defect before entering the contract. See E.L. Hamm &
    Associates, Inc. v. England, 
    379 F.3d 1334
    , 1339, 1341-42 (Fed. Cir. 2004). BRSC
    was both the GTMO concrete batch contractor and part of appellant's joint venture
    l
    I
    l                                               5
    when appellant entered the contract on June 3, 2010 (to begin work by June 13, 2010)
    (R4, tab 76 at 2966-75), and therefore was or should have been aware whether sand
    suitable for masonry and stucco was available at the GTMO concrete batch plant at
    that time, regardless of whether such sand would also be available after BRSC stopped
    operating that plant on November 30, 2010. Appellant does not say that between
    June 3 and November 30, 2010 (that is, between when appellant entered the contract
    and BRSC stopped operating the plant), sand suitable for masonry and stucco was
    available at the plant, such that the unavailability of suitable sand arose only after
    BRSC stopped operating the plant, introducing a contract defect that did not exist
    when appellant entered the contract. Consequently, if the contract requires the
    contractor to obtain masonry and stucco sand from the GTMO concrete batch plant,
    and if sand suitable for masonry and stucco was not available at that plant, that was a
    contract defect of which appellant was or should have been aware before entering the
    contract, and for which it may not recover. Accordingly, appellant is not entitled to
    additional compensation in ASBCA No. 60668.
    CONCLUSION
    ASBCA Nos. 6013 0 & 61611 are sustained and returned to the parties for the
    negotiation of quantum. ASBCA No. 60668 is denied.
    Dated: July 8, 2019
    fIMOTHY P:MG         IL
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                          I concur
    JOID-{J. THiASHER                                OWEN C. WILSON
    Administrative Judge                             Administrative Judge
    Chairman                                         Vice Chairman
    Armed Services Board                             Armed Services Board
    of Contract Appeals                              of Contract Appeals
    6
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA Nos. 60130, 60668, 61611,
    Appeals ofBRDC, a Joint Venture, rendered in conformance with the Board's Charter.
    Dated:
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    7
    

Document Info

Docket Number: ASBCA No. 60130, 60668, 61611

Judges: McIlmail

Filed Date: 7/8/2019

Precedential Status: Precedential

Modified Date: 7/22/2019