Missouri Department of Social Services ( 2019 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                  )
    )
    Missouri Department of Social Services        )       ASBCA No. 61121
    )
    Under Contract No. W911S7-09-D-0029           )
    APPEARANCE FOR THE APPELLANT:                         Keith L. Baker, Esq.
    Baker, Cronogue, Tolle & Werfel, LLP
    McLean, VA
    APPEARANCES FOR THE GOVERNMENT:                       Raymond M. Saunders, Esq.
    Army Chief Trial Attorney
    ChristinaLynn E. McCoy, Esq.
    CPT John M. McAdams III, JA
    Trial Attorneys
    OPINION BY ADMINISTRATIVE JUDGE MCILMAIL
    In November 2016, we found appellant entitled, under Federal Acquisition
    Regulation (FAR) 52.249-2(1), to an equitable adjustment of the prices of the portion
    of its dining services contract that continued after the government terminated the
    contract in part by eliminating from the contract 6 of the 18 dining facilities originally
    covered. Missouri Department of Social Services, ASBCA No. 59191, 16-1 BCA
    ,i 36,563 at 178,093, 178,095-96. Familiarity with that decision is presumed. Because
    the parties have not been able to settle upon quantum, we address that now.
    FINDINGS OF FACT
    We found in the entitlement decision that:
    The record in this appeal contains evidence that the
    reduction in production hours caused by the termination of
    six facilities increased appellant's cost of performing the
    remaining work. Its original pricing proposal estimated
    1,279,423 production hours for all 18 facilities per year,
    but after the elimination of six facilities the revised
    estimate of total production hours per year was 980,682.
    This would indicate that without an upward revision to the
    "retail rate" for Option Years 2 and 3, appellant would not
    recover all of its fixed costs. This is because when
    contract pricing is calculated using the same arithmetic as
    used in the original pricing proposal; the fixed costs have
    not changed but the number of production hours has gone
    down, increasing the price per hour. The record indicates
    that the retail rate would have to increase from 23.8053 to
    25.2242 for Option Year 2 and from 24.6301 to 26.4137
    for Option Year 3 in order for appellant to recover its fixed
    costs to the extent provided for in its original proposal.
    Missouri Department ofSocial Services, 16-1 BCA ,i 36,563 at 178,095 (citations
    omitted). We also found that "[a]ppellant and the government entered into a different
    contract than existed after 6 October 2011-one that included 50% more dining
    facilities and 298,741 more production hours than did the contract after partial
    termination." 
    Id. at 178,096.
    During the entitlement hearing, appellant's expert testified that appellant had
    approximately $717,000 ofunrecovered fixed costs in Option Year 2 and $805,054 of
    unrecovered fixed costs in Option Year 3.* Missouri Department of Social Services,
    16-1 BCA ,i 36,563 at 178,095. To put that in context, appellant's estimated revenue
    for Option Year 2 (that is, total cost and profit) was $30,457,068.71. 
    Id. at 178,093.
    In
    developing its pricing for the original contract, appellant applied a profit rate of 3%. 
    Id. The Defense
    Contract Audit Agency found that "the basis or theory of recovery of the
    costs in [the expert's report] is logical and the calculation is correct, but it is based on
    the estimated data" (R4, tab 153 at 5). Appellant's expert reprised his presentation at
    the quantum hearing, again reporting that based on proposed costs, appellant's
    unrecovered fixed costs (plus 3% profit) were $1,522,617 for Option Years 2 and 3 (R4,
    tab 167 at 8). On an incurred cost basis, he testified that appellant's unrecovered fixed
    costs (plus 3% profit) were $681,795 in Option Year 2 and $553,507 in Option Year 3,
    for a total of $1,235,302 (tr. 1/146; R4, tab 168 at 3).
    Appellant incurred $73,125.75 in "settlement expenses"; that is, legal, clerical,
    and similar costs incurred for the preparation and presentation of its request for equitable
    adjustment and its partial termination settlement proposal (app. br. at 26). On June 24,
    2013, appellant submitted to the contracting officer its certified claim for the increased
    costs of performing the remaining contract work. 16-1 BCA ,i 36,563 at 178,094.
    * This calculation was based on the original cost estimates used to price the contract.
    2
    DECISION
    Equitable adjustments are corrective measures utilized to keep a contractor whole
    when the government modifies a contract; to achieve this we must place the contractor as
    nearly as possible in the position in which it would have been absent the changes. See
    New York Shipbuilding Co., A Div. of Merritt-Chapman & Scott Corp., ASBCA
    No. 16164, 76-2 BCA ,r 11,979 at 57,427. Generally, that includes the contractor's
    entitlement to a fair profit. See 
    id. In our
    entitlement decision, we found that
    "[a]ppellant and the government entered into a different contract than existed after [the
    partial termination] - one that included 50% more dining facilities and 298,741 more
    production hours," and remarked that, "[p]resumably, addressing such a change in the
    parties' expectations is the purpose of FAR 52.249-2(1)." 16-1 BCA ,r 36,563 at 178,096.
    Having already proved the fact of loss, appellant must now prove the amount of
    loss, but only with sufficient certainty so that the determination of the amount of
    damages will be more than mere speculation. See Austin Logistic Services Co.,
    ASBCA Nos. 60916, 61052, 18-1 BCA ,r 36,948 at 180,049. The determination of an
    equitable adjustment is not an exact science; where responsibility for damage is clear.
    it is not essential that the damage amount be ascertainable with absolute or
    mathematical precision. BAE Systems San Francisco Ship Repair, ASBCA
    Nos. 58810, 59642, 16-1 BCA ,r 36,404 at 177 ,503-04.
    Our precedent favors the use of actual incurred costs, if possible, to determine
    the amount of an equitable adjustment. BAE Systems San Francisco, 16-1 BCA
    ,r 36,404 at 177,501 (citing Propel/ex Corp. v. Brownlee, 
    342 F.3d 1335
    (Fed. Cir.
    2003); and Advanced Engineering & Planning Corp., ASBCA Nos. 53366, 54044, 05-1
    BCA ,r 32,806 at 162,336). Based on the calculations proffered by appellant's expert,
    we find that appellant's unrecovered fixed costs due to the partial termination (plus 3%
    profit) amount to $1,235,302. This calculation is based on a review of appellant's
    actual incurred costs, which were adjusted downward by the expert in specific instances
    where they exceeded proposed amounts, thus avoiding recovery of increased costs not
    resulting from the partial termination.
    The government has not proffered its own calculation of the amount of
    equitable adjustment due appellant. Its expert testified to various perceived potential
    deficiencies in appellant's quantum proof which, the government argues, means that
    appellant has not sustained its burden of proof (gov't br. at 22-28). The Board has
    considered the government's arguments, but does not find them persuasive; appellant
    has proved the amount of its loss with sufficient certainty.
    The government also objects to inclusion of 3% profit in the adjustment amount,
    calling it "anticipatory profit" (gov't br. at 23). However, it is well established that an
    equitable adjustment includes a "fair and reasonable" amount for profit. Bruce
    Construction Corp. v. United States, 
    324 F.2d 516
    (Ct. Cl. 1963); Les Killgore 's
    3
    f
    r
    Excavating, ASBCA No. 32261, 86-3 BCA 1 19,117. Otherwise, the contractor is not
    made whole. See also Aero Components Co., ASBCA No. 42620, 92-1 BCA, 24,565 at
    122,565. In developing its pricing for the original contract, appellant applied a profit rate
    of 3 %, which we find to be fair and reasonable.
    Appellant also seeks $73,125.75 in settlement expenses; that is, the legal and
    clerical fees and expenses it incurred for the preparation and presentation of its request for
    equitable adjustment and its partial termination settlement proposal (app. br. at 26). The
    government argues (gov't br. at 28) that appellant's request is not properly before us
    because we held that appellant's entitlement to an adjustment under FAR 52.249-2(1)
    mooted its claim under FAR 52.249-2(g). In C.F.S. Air Cargo, Inc., ASBCA Nos. 36113,
    36126, 91-1BCA123,583 at 118,245-46, we awarded settlement expenses in the context
    of an equitable adjustment following a partial termination for convenience. The
    government does not challenge the reasonableness of, or support for, the $73,125.75 in
    expenses (gov't br. at 28). Following CFS. Air Cargo, we award $73,125.75 in settlement
    expenses, which we find reasonable and supported.
    CONCLUSION
    The appeal is sustained in the amount of$1,308,427.75, with interest under
    41 U.S.C. § 7109, from June 24, 2013, the putative date that the contracting officer
    received appellant's certified claim.
    Dated: January 17, 2019
    WP~Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                          I concur
    RICHARD SHACKLEFORD
    ~(~ (j``
    _L_YN_~.::::D:__;-uT~.
    ,e:::::O+'S_U__._L_L~IV~A~N.v__:__:``=----
    Administrative Judge                               Administrative Judge
    Acting Chairman                                    Acting Vice Chairman
    Armed Services Board                               Armed Services Board
    of Contract Appeals                                of Contract Appeals
    4
    I
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA No. 61121, Appeal of Missouri
    Department of Social Services, rendered in conformance with the Board's Charter.
    Dated:
    JEFFREYD. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    5
    

Document Info

Docket Number: ASBCA No. 61121

Judges: McIlmail

Filed Date: 1/17/2019

Precedential Status: Precedential

Modified Date: 1/28/2019