Shafi Nasimi Construction and Logistics Company ( 2016 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                   )
    )
    Shafi Nasimi Construction and Logistics Company)       
    ASBCA No. 59916
    )
    Under Contract No. W91B4N-09-C-8 l 50          )
    APPEARANCE FOR THE APPELLANT:                          Mr. Mohammad Shafi Nasimi
    CEO
    APPEARANCES FOR THE GOVERNMENT:                        Raymond M. Saunders, Esq.
    Army Chief Trial Attorney
    Erica S. Beardsley, Esq.
    Trial Attorney
    OPINION BY ADMINISTRATIVE JUDGE DELMAN ON THE GOVERNMENT'S
    MOTION TO DISMISS FOR LACK OF JURISDICTION
    The Board, sua sponte, questioned whether the Board had jurisdiction over this
    appeal. Board Rule 7(b). In response, the government moved to dismiss the appeal
    for lack of jurisdiction. For reasons stated below, we grant the government's motion.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
    1. The Department of Army, Bagram Regional Contracting Center (government)
    awarded this contract to Shafi Nasimi Construction and Logistics Company (appellant)
    on 19 July 2009 for the construction of the Warrior Office Facility at Bagram Airfield,
    Afghanistan (R4, tab 3).
    2. The government issued a Notice to Proceed (NTP) to appellant on
    9 September 2009. Appellant was to begin performance within seven calendar days of
    issuance of the NTP, and to complete performance within 120 days of this notice. (R4,
    tab 23)
    3. The government issued a Stop Work Notice on 14 September 2009 as a
    result of design issues (R4, tabs 24, 26). The government issued a second NTP on
    7 June 2010 (R4, tab 3 7).
    4. By memorandum to appellant dated 2 December 2011, the contracting officer
    (CO) terminated the contract for default as a result of appellant's failure to make
    progress on the project, the completion date of which had been extended to 12 October
    2011. The termination notice provided: "This notice also constitutes a decision that you
    are in default of the contract as specified. You have the right to dispute that decision
    under the Disputes clause of the contract." (R4, tab 62) The termination notice did not
    advise appellant of its appeal rights, nor did the Disputes clause provide this
    information. Appellant acknowledged receipt of the termination notice on 4 December
    2011 (gov't mot., ex. 2).
    5. Over the next 90 days, the parties exchanged emails related to the project,
    but in none of these did the CO entertain or offer to entertain a reconsideration of the
    default termination. During this period, there was some email discussion about the
    extent of the work that appellant had performed and extent to which it could be paid
    for the same. For example, by email to appellant dated 21December2011, the CO
    advised in part as follows:
    I have been in discussion with our base engineers, and
    have learned that they might be able to use some of the
    RLB units that you delivered, after termination of the
    contract. If that is the case, then we would pay you for
    some, but certainly not all, of the cost you incurred on the
    contract.
    (Notice of appeal (NOA), attach.) Also, by email to appellant dated 16 February 2012,
    the CO advised in part as follows:
    I would like to propose that we pay you some amount for
    the work that you have completed. I can tell that there was
    still a lot of work remaining to be done. Please provide me
    a detailed proposal.... I also would like to keep the
    contract open, if you would be interested in coming back
    in the future to dismantle the containers and move them to
    a new location for us. Please let me know ifthat would be
    of interest to you. That would then allow you to eventually
    get paid up to the full contract amount, if your costs to
    move the containers is [sic] reasonable. [Emphasis added]
    (NOA, attach.) There is nothing in the record showing that the government made any
    such payments to appellant after the termination of the contract for any work
    performed.
    6. The 90-day appeal period to the Board, 
    41 U.S.C. § 7104
    (a), expired on
    3 March 2012. Appellant did not file an appeal from the termination notice by this
    date.
    2
    7. Thereafter, it appears that the CO for this project was replaced, and a
    MAJ Michael W. Washington, Construction Flight Chief, was charged with the
    responsibility for this contract. By email from appellant to MAJ Washington dated
    30 July 2012, more than seven months after issuance of the termination notice, appellant
    requested an opportunity "to prove that it was not my fault" (NOA, attach.). Presumably,
    appellant referred to the default termination. Washington replied by email the same day,
    stating:
    Send me your documents. After I have my specialist
    review we will set up a meeting for final determination.
    Right now we have issues getting people on base
    regardless.         ·
    (NOA, attach.)
    8. Appellant replied to MAJ Washington by email dated 3 August 2012, stating
    that approximately 85% of the project work was done, and that the termination was
    attributable in part to the government. Appellant forwarded various documents.
    (NOA, attach.)
    9. By email to appellant dated 3 August 2012, MAJ Washington stated in part
    as follows (NOA, attach.):
    I have all of this documentation. Thank you. I can make
    you no promises.... Despite Mr. Rounds opening the door
    for a possible settlement[,] this contract was set up for a
    Termination for Default. We do not pay on T4D contracts.
    I promise you a full review and decision. This may take
    some time but I will see this through.
    10. By email to appellant dated 5 August 2012, MAJ Washington stated in part
    as follows (NOA, attach.):
    I am now leaning toward some settlement with your
    company as my investigation has revealed several miscues
    by the U.S. Government.
    Our current steps are to replace the money that was
    de-obligated from the contract back onto the contract. We
    then need an estimate from the government (Mr. Dold's
    3
    team) as to the value of the buildings as they were when
    you were told to stop working on the project.. ..
    After I get those issues resolved we will sit down with you
    and negotiate a settlement.
    (NOA, attach.) The record does not indicate that the parties ever met or reached such
    a settlement.
    11. Over two years later, by email dated 25 November 2014, the government
    forwarded a release on this contract to appellant and requested that appellant sign it. It
    appears that appellant did not sign the release. (R4, tab 65)
    12. Appellant filed an undated notice of appeal disputing the default
    termination, received by the Board on 7 April 2015, more than three years after the
    default termination notice was issued.
    DECISION
    The government contends that we have no jurisdiction over this appeal because
    the appeal was not timely filed from the CO's termination notice/decision. As a
    threshold matter, we must address whether this termination notice was in fact a final
    decision that set into motion the 90-day appeal period to this Board.
    The CO's termination notice of2 December 2011 stated that the contractor may
    appeal under the Disputes clause of the contract, but it did not advise the contractor of
    its appeal rights. In Mansoor International Development Services, 
    ASBCA No. 58423
    ,
    14-1BCA~35,742 at 174,926 we recently explored what a contractor must prove to
    avoid the 90-day filing requirement under such circumstances:
    [W]hen confronted with contracting officer decisions that
    only advise the contractor that it may appeal under the
    Disputes clause, omitting additional details of its rights, the
    Board has required the contractor to prove it was actually
    prejudiced by the omission, or that the contractor
    detrimentally relied upon it, to avoid the 90-day limitation
    period. [Citations omitted]
    See also Decker & Co. v. West, 
    76 F.3d 1573
     (Fed. Cir. 1996).
    Appellant has not asserted any actual prejudice, or detrimental reliance upon the
    omission of its appeal rights in the CO decision. We will not presume such prejudice or
    reliance by virtue of the late filing alone. See Medina Contracting Company, ASBCA
    4
    No. 53783, 02-2 BCA ~ 31,979. Accordingly, we believe that the CO's termination
    notice of 2 December 2011 was a CO decision that set into motion the 90-day appeal
    period to this Board.
    Next, we must explore whether this CO decision was reconsidered by the
    government, such that it was no longer a "final decision" for purposes of appeal.
    In Sach Sinha and Associates, Inc., 
    ASBCA No. 46916
    , 95-1~27,499 at 137,041
    (SSA), we stated as follows:
    It is well-established that, if a CO's decision is not
    truly "final," but being reconsidered, a "failure to appeal
    from the decision within the prescribed period will not
    defeat. .. [a] contractor's opportunity to be heard on the
    merits." E.g., Johnson Controls, Inc., 
    ASBCA No. 28340
    ,
    83-2BCA~16,915 at 84,170 .... Accordingly, to ascertain
    if this appeal is timely, we must determine whether the
    "finality" of the CO's decision was vitiated.
    We further explained in SSA that the test for vitiation of finality "is whether the
    contractor presented evidence showing it reasonably or objectively could have
    concluded the CO's decision was being reconsidered." 
    Id. at 137,042
    . The focus is
    upon the action of the government during the appeal period, i.e., whether any
    government action could have reasonably led a contractor to believe that the subject
    matter was not yet final, thereby making an appeal to the board unnecessary. Thus, in
    SSA we found a lack of finality where the CO met with the contractor after the
    issuance of the termination notice; discussed the default termination at the meeting;
    and requested the contractor to submit settlement alternatives in writing that were
    proposed at the meeting.
    Appellant has provided no evidence of any such government conduct during
    the 90-day appeal period to this Board. After the CO issued the termination notice on
    2 December 2011, the CO did not meet with or otherwise engage appellant on the
    merits of the default termination during the appeal period, nor did he promise to do so.
    In an email to appellant on 16 February 2012, the CO did propose to keep the contract
    "open" (SOF ~ 5), but from the context of this email it is clear that the purpose of this
    proposal was to use the contract as a vehicle to pay appellant to move certain
    containers from the site and not to reconsider the default termination.
    Months later, MAJ Washington issued a number of emails to appellant that
    reflected his willingness to consider a "settlement" with appellant, but it is unclear
    whether he referred to a monetary settlement for work performed, consistent with the
    default termination, or to a settlement in which the default would be rescinded and
    converted to a convenience termination (SOF `` 7-10). In any event, these emails
    5
    were issued over four months after expiration of the appeal period to the Board, and
    perforce could not have had any effect on appellant's understanding of the finality of
    the government's 2 December 2011 termination decision during the appeal period.
    Based upon the foregoing, we conclude that the government did not reconsider
    the CO's notice of default termination of2 December 2011 during the appeal period,
    and hence it was a final CO decision for purposes of appeal to this Board. Appellant
    failed to file an appeal to this Board within 90 days of its receipt of this decision (SOF
    ~ 6), as required by the Contract Disputes Act, 
    41 U.S.C. § 7104
    (a). Accordingly, we
    are without jurisdiction over this appeal.
    CONCLUSION
    For reasons stated above, we conclude that appellant's April, 2015 appeal to
    this Board from the government's December, 2011 termination decision was untimely.
    The government's motion to dismiss is granted. The appeal is dismissed for lack of
    jurisdiction.
    Dated: 6 January 2016
    JA~:;r``
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                              I concur
    ``
    , //
    / ;;:7    / /
    //:; /f/ / 7     L/
    7-(L_ __-4(
    l ,., / ,; - -
    /;t/u;:i'.f<
    PA~
    /' /      /   ~// r
    MARK N. STEMPLER                                      REBA
    Administrative Judge                                  Administrative Judge
    Acting Chairman                                       Acting Vice Chairman
    Armed Services Board                                  Armed Services Board
    of Contract Appeals                                   of Contract Appeals
    6
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 59916
    , Appeal of Shafi
    Nasimi Construction and Logistics Company, rendered in conformance with the
    Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    7
    

Document Info

Docket Number: ASBCA No. 59916

Judges: Delman

Filed Date: 1/6/2016

Precedential Status: Precedential

Modified Date: 1/21/2016