Anaconda Construction Company ( 2017 )


Menu:
  •                 ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                   )
    )
    Anaconda Construction Company                  )      ASBCA No. 60905
    )
    Under Contract No. W91B4N-12-P-5086            )
    APPEARANCE FOR THE APPELLANT:                         Mr. Shoib Khan
    CEO
    APPEARANCES FOR THE GOVERNMENT:                       Raymond M. Saunders, Esq.
    Army Chief Trial Attorney
    MAJ Christopher M. Coy, JA
    Trial Attorney
    OPINION BY ADMINISTRATIVE JUDGE SWEET
    ON THE GOVERNMENT'S MOTION TO DISMISS
    Appellant Anaconda Construction Company (ACC) brings this action
    challenging the government's decision that it was not entitled to the costs of two
    loaders allegedly destroyed in the course of performing the above-captioned contract,
    and the government's decision to deny ACC's settlement proposal. The government
    has moved to dismiss this action for failure to timely appeal the relevant contracting
    officer's final decisions. ACC submitted a short response to the motion. The motion
    is granted.
    STATEMENT OF FACTS CSOF) FOR PURPOSES OF THE MOTION
    1. The Bagram Regional Contracting Center (government) awarded Contract
    No. W91B4N-12-P-5086 to ACC to operate and maintain a burn pit for solid waste at
    Bagram Airfield in Afghanistan (R4, tab 1 at 4, 45 1).
    2. The government terminated the contract for convenience, effective
    15 October 2013 (R4, tab 35 at 164). The termination notice directed ACC to submit
    any settlement proposal by 15 November 2013 (id. at 165).
    3. On 24 October 2013, ACC submitted a claim (October claim) for the cost to
    replace two loaders that were destroyed by fire during incineration operations (R4,
    tab 40 at 185). The October claim was for $160,000 (id.). The October claim also
    1
    All Rule 4 cites are to the consecutively-numbered pages.
    contained a certification in accordance with the requirements of the Contract Disputes
    Act (41 U.S.C. §§ 7101-7109) (id. at 184).
    4. On 28 October 2013, the contracting officer (CO) emailed ACC a final
    decision on the October claim (October decision) (R4, tab 42). The CO determined
    that the government did not owe any funds to ACC (id. at 189). He also informed
    ACC that "[t]his is the final decision of the Contracting Officer. You may appeal this
    decision to the agency board of contract appeals. If you decide to appeal, you must,
    within 90 days from the date you receive this decision, mail or otherwise furnish
    written notice to the agency." (Id.)
    5. On 7 November 2013, ACC apparently submitted a settlement proposal
    (settlement proposal) to the CO for $451,600, which represented labor and leased
    equipment expenses (R4, tab 49 at 210). 2
    6. On 18 November 2013, the CO sent ACC a "Notice of Intent to Settle by
    Contracting Officer Determination." The notice stated that the government intended to
    reject the settlement proposal due to a lack of supporting documentation. (R4, tab 49 at
    210) The notice also requested that ACC submit supporting documentation within
    15 days (id.).
    7. Within 15 days, ACC submitted a revised settlement proposal (R4, tab 48). The
    revised settlement proposal sought to recover ( 1) $160,000 for the two loaders that were
    the subject of the October claim; and (2) $112,900 in other costs (id.). The revised
    settlement proposal did not contain a certification3 (id.).
    8. On 26 November 2013, the CO sent ACC a final decision (November decision)
    on the revised settlement proposal (R4, tab 53). The November decision stated that,
    "[s]ince the matter of the loaders was addressed by previous Contracting Officer Final
    Decision (dated 28 Oct 2013) outside the termination process, ... the cost could not be
    included in the settlement" (id. at 223). The November decision also found that ACC
    was not entitled to any of the claimed $112,900 in costs (id.). As with the October
    decision, the November decision stated that "[t]his is the final decision of the Contracting
    Officer. You may appeal this decision to the agency board of contract appeals. If you
    decide to appeal, you must, within 90 days from the date you receive this decision, mail
    or otherwise furnish written notice to the agency." (Id. at 224)
    2
    The settlement proposal is not part of the record, but is referenced in the
    18 November 2013 notice of intent to settle (R4, tab 49 at 210; SOF ii 6).
    3
    Nor was one required as a settlement proposal is typically submitted for negotiation
    and it becomes a claim after the parties reach an impasse.
    2
    9. On 7 November 2016--more than 90 days after the October decision and the
    November decision-ACC filed a notice of appeal with the Board. 4
    DECISION
    We do not possess jurisdiction over this appeal from either final decision. The
    Contract Disputes Act (CDA) states that "[t]he contracting officer's decision on a
    claim is final and conclusive and is not subject to review by any forum, tribunal, or
    Federal Government agency, unless an appeal or action is timely commenced as
    authorized by this chapter." 41 U.S.C. § 7103(g). The CDA requires that a contractor
    certify a claim for more than $100,000. 41 U.S.C. § 7103(b)(l). Indeed, "a written
    demand or written assertion by the contractor seeking the payment of money
    exceeding $100,000 is not a claim ... until certified as required by the statute."
    FAR 2.101. Therefore, we do not possess jurisdiction to hear an appeal when a
    contractor did not certify a claim for more than $100,000. Sygnetics, Inc., ASBCA
    No. 56806, 10-2 BCA ~ 34,576 at 170,464-65.
    The CDA also requires a contractor to appeal a final decision on a claim within
    90 days of receipt of that decision. 41 U.S.C. § 7104(a). Therefore, we do not possess
    jurisdiction to hear an appeal when a contractor failed to file a notice of appeal within
    90 days of its receipt of the final decision. Cosmic Constr. Co. v. United States, 
    697 F.2d 1389
    , 1390-91 (1982).
    Here, ACC did not certify the November revised settlement proposal, despite
    the fact that it was for more than $100,000 (SOF ~ 7). Therefore, the revised
    settlement proposal was not a claim, and we do not possess jurisdiction over any
    appeal based upon that proposal. FAR 2.101; Sygnetics, 10-2 BCA ~ 34,576 at
    170,464-65. 5 While ACC certified the October claim, it did not file a notice of appeal
    within 90 days of the October decision on that claim (SOF `` 3, 9). Thus, we do not
    possess jurisdiction over an appeal of that decision either. Cosmic Constr., 697 F .2d at
    1390-91.
    ACC does not dispute that it failed to file a notice of appeal within 90 days of its
    receipt of the October decision or the November decision. Rather, in its brief response to
    the government's motion to dismiss, ACC argues that the CO did not inform it that it had
    4
    ACC is not clear whether it is appealing the October decision, the November
    decision, or both (compl.). For purposes of this motion, we assume ACC is
    appealing both decisions.
    5 Even if ACC had certified the revised settlement proposal, it did not file a notice of
    appeal within 90 days of the November decision on that proposal, which would
    preclude our jurisdiction over any appeal based upon the revised settlement
    proposal.
    3
    to file an appeal within "30 days." The period for commencing an appeal does not
    commence if the CO inaccurately advises a contractor about its appeal rights, and the
    contractor detrimentally relies upon that inaccuracy. Decker & Co. v. West, 
    76 F.3d 1573
    ,
    1579 (Fed. Cir. 1996). Here, the CO accurately informed ACC in both the October
    decision and the November decision that "[i]f you decide to appeal, you must, within
    90 days from the date you receive this decision, mail or otherwise furnish written notice to
    the agency" (SOF ilil 4, 8). Because the CO accurately notified ACC that it had
    90 days 6-not 30 days-to file an appeal, the 90-day period for filing a notice of appeal
    commenced respectively when ACC received the October decision and the November
    decision.
    CONCLUSION
    The government's motion to dismiss is granted. This appeal is dismissed for
    lack of jurisdiction.
    Dated: 26 June 2017
    JAMES R. SWEET
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur
    RICHARD SHACKLEFORD
    Administrative Judge
    Acting Chairman
    Armed Services Board
    of Contract Appeals
    6
    We do not know why ACC referenced 30 days in its response to the government's
    motion.
    4
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA No. 60905, Appeal of
    Anaconda Construction Company, rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    5
    

Document Info

Docket Number: ASBCA No. 60905

Judges: Sweet

Filed Date: 6/26/2017

Precedential Status: Precedential

Modified Date: 7/10/2017