Hallym Furniture Industrial Co., Ltd. ( 2021 )


Menu:
  •                   ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of -                                )
    )
    Hallym Furniture Industrial Co., Ltd.      ) 
    ASBCA No. 62782
    )
    Under Contract No. W91QVN-20-A-0012        )
    OPINION BY ADMINISTRATIVE JUDGE SMITH
    ON RESPONDENT’S MOTION TO DISMISS
    Appellant, Hallym Furniture Industrial Co., Ltd. (Hallym), appeals a
    contracting officer’s final decision (COFD) that denied Hallym’s certified claim
    seeking reinstatement of its Blanket Purchase Agreement (BPA) with Respondent,
    Department of the Army 411th Contracting Support Brigade, Korea (the government).
    Alternatively, Hallym’s claim sought an equitable adjustment for three different types
    of costs arising from the cancellation of the BPA in the total amount of 169,500,000
    Korean won (approximately $151,287.95).1 The government has moved to dismiss the
    appeal, arguing that the BPA is not a valid contract as required by the Contract
    Disputes Act (CDA), therefore the Board lacks subject matter jurisdiction over
    Hallym’s appeal. Hallym argues that the BPA is a contract because Hallym could not
    refuse a call order once it was issued. On balance, we find that this BPA is similar in
    nature to other BPAs that the Court of Appeals for the Federal Circuit has held to be
    non-contractual, thus we dismiss the appeal for lack of jurisdiction.
    STATEMENT OF FACTS FOR PURPOSES OF THE MOTION
    On April 6, 2020, the parties executed BPA No. W91QVN-20-A-0012 for
    repair of Government-owned wooden furniture. (R4, tab 1) The BPA indicates that
    the BPA “is not a contract” (id. at 5 2), but the BPA contains contrary descriptive
    verbiage as well. 3 The BPA provided that individual repairs or groups of repairs
    1 The symbol for Korean won is “₩” so Hallym’s total claim amount is shown as
    “₩169.5M.”
    2 Paragraph 2 of the Performance Work Statement reads: “TERM OF BPA: This BPA
    is not a contract. If the contractor fails to perform in a manner satisfactory or
    no longer required by the government, this BPA may be cancelled with 30 days
    written notice to the contractor by the Contracting Officer (KO).” (R4, tab 1
    at 5)
    3 For example, and most notably, “Type of Contract. The government contemplates
    award of a Fixed Unit Price, Multiple BPA’s contract resulting from this
    solicitation.” (R4, tab 1 at 21) (emphasis omitted). Also, “[t]he Contractor
    would be separately issued as “purchases” or “calls” or “call orders.” 4 (Id. at 8) The
    BPA provided that call orders would be issued on a rotating basis between Hallym and
    other awardee contractor(s). (Id. at 8) The BPA did not commit the government to
    issue any call orders. Instead, paragraph 13 of the Performance Work Statement
    provides that the government’s obligation arises only from call orders actually made
    under the BPA: “EXTENT OF OBLIGATION: The Government is obligated under
    this BPA only to the extent of authorized purchases [i.e. call orders] actually made
    under the BPA.” (Id. at 8) The BPA indicates that “[t]he Government may require
    continued performance of any services within the limits and at the rates specified in
    the contract” (id. at 21).
    After award of the BPA, the Government issued ten call orders that were
    performed by Hallym. (R4, tab 10 at 5, 7; gov’t reply at 4 (“appellant . . . performed
    all of the ordered repair work.”)) Disagreements arose, however, with regard to the
    prices used by Hallym in its invoices, which were higher than in Hallym’s BPA price
    proposal. (R4, tabs 13, 17-18, 23-27) To correct what it perceived to be defects in
    Hallym’s invoices, the government itself generated the final invoice for Hallym’s work
    (R4, tab 21; app. supp. R4, tab 4), but there is no evidence that the final invoice has
    been paid. ((gov’t. reply br. at 5) (Appellant has not signed or acknowledged the final
    invoice)).
    Based upon the government’s opinion regarding Hallym’s “unsatisfactory
    performance” relating to the invoices, the contracting officer notified Hallym on
    September 21, 2020, that the BPA would be cancelled in 30 days because “[Hallym]
    failed to perform this BPA services (sic) in a manner satisfactory to the Government.”
    (R4, tab 20) 5 A written dialogue ensued where Hallym attempted to persuade the
    contracting officer to retract the cancellation notice. (R4, tabs 22-27) The dialogue
    shall maintain own facility (minimum of 198m2 [60 Pyeong]) to perform this
    contract requirements (sic) for the entire contract period.” (Id. at 8) Also,
    “[t]he Government may require continued performance of any services within
    the limits and at the rates specified in the contract.” (Id. at 21) A word search
    of the BPA finds 45 uses of the word “contract,” many of which are incidental
    like “Section I -- Contract Clauses” (id. at 14), but approximately 10 of which
    are not i.e. the clauses cited above. A document that the government intends
    not to be a contract should minimize use of the word “contract.” Instead,
    “BPA” should be used to describe the agreement.
    4 The BPA uses all three terms to refer to the repair orders issued under the BPA. For
    purposes of this decision, we use the term “call orders.”
    5 The BPA provides that “[i]f the contractor fails to perform in a manner satisfactory
    or no longer required by the Government, this BPA may be cancelled with
    30 days written notice to the contractor by the Contracting Officer.” (R4, tab 1
    at 5)
    2
    devolved into allegations by both parties of “lack of business integrity and ethical
    business practices” (the government’s allegation against Hallym, (R4, tab 24 at 2; see
    also gov’t. reply br. at 2)) and a “gross administrative error” and improper or illegal
    changes to government documents (Hallym’s allegations against the government).
    (Complaint at 6; see R4, tab 25)
    When the government refused to withdraw the cancellation notice, instead
    finalizing the cancellation on November 11, 2020, (R4, tab 27), Hallym submitted a
    certified claim on November 25, 2020, seeking reinstatement of the BPA or, in the
    alternative, ₩169.5M for bid preparation costs, facility lease costs, and lost future
    profits – but not for payment of the government-generated invoice. (R4, tab 28) The
    government denied Hallym’s claim in full with a COFD issued on December 7, 2020.
    (R4, tab 29) The COFD addressed each of Hallym’s claim allegations regarding the
    BPA bid, award, price, invoice process, and claimed financial injuries as well as the
    government’s basis for canceling the BPA. 
    Id.
     This appeal timely followed the COFD.
    DECISION
    I.     Standard of Review
    We review the government’s motion to dismiss for lack of jurisdiction pursuant
    to the standards of FED. R. CIV. P..12(b)(1). L-3 Commc’ns Integrated Sys., L.P.,
    ASBCA Nos. 60713, 60716, 
    17-1 BCA ¶ 36,865
     at 179,624 (applying Rule 12(b)(1)
    because Board may look to Federal Rules of Civil Procedure for guidance where
    Board’s rules are silent). When a motion to dismiss pursuant to FED. R. CIV. P.
    12(b)(1) denies or controverts allegations of jurisdiction, only uncontroverted factual
    allegations are accepted as true for purposes of the motion, and other facts underlying
    the jurisdictional allegations are subject to fact-finding based on the Board’s review of
    the record. Cedars-Sinai Med. Ctr. v. Watkins, 
    11 F.3d 1573
    , 1583-84 (Fed. Cir.
    1993); CCIE & Co., ASBCA Nos. 58355, 59008, 
    14-1 BCA ¶ 35,700
     at 174,816.
    The government’s motion distinguishes between a facial attack on the Board’s
    jurisdiction and a factual attack, and the different standards that apply to our review of
    factual allegations (gov’t. reply br. at 2-3). Though this digression is not incorrect, it
    is unnecessary because the government’s motion to dismiss essentially relies upon no
    facts at all save for the BPA itself and, perhaps, the written content of Hallym’s
    certified claim. Hallym, as the proponent of the Board’s jurisdiction, bears the burden
    of proving the Board’s subject matter jurisdiction by a preponderance of the evidence,
    which includes showing the existence of a valid contract. See 
    41 U.S.C. § 7105
    (e)(2);
    General Mills, Inc. v. United States, 
    957 F.3d 1275
    , 1284 (Fed. Cir. 2020); Reynolds v.
    Army & Air Force Exch. Serv., 
    846 F.2d 746
    , 748 (Fed. Cir. 1988); United Healthcare
    Partners, Inc., 
    ASBCA No. 58123
    , 
    13 BCA ¶35,277
     at 173,156. See also Crewzers
    Fire Crew Transp., Inc. v. United States, 
    741 F.3d 1380
    , 1382 (Fed. Cir. 2014).
    3
    II.    BPAs are Generally not Contracts, and the BPA Here is no Exception
    Fundamental contract law dictates that there can be no contract without mutual
    obligations between the parties. See Kam-Almaz v. United States, 
    682 F.3d 1364
    , 1368
    (Fed. Cir. 2012); Night Vision Corp. v. United States, 
    469 F.3d 1369
    , 1375 (Fed. Cir.
    2006). Specifically, the Court of Appeals for the Federal Circuit has held that BPAs
    that do not impose binding obligations upon the parties are not contracts. Crewzers,
    741 F.3d at 1384; Modern Sys. Tech. Corp. v. United States, 
    979 F.2d 200
    , 206 (Fed.
    Cir. 1992) (“absence of mutuality of obligation leads to the conclusion that the parties
    lacked the requisite contractual intent”); see also See Ridge Runner Forestry v.
    Veneman, 
    287 F.3d 1058
     (Fed. Cir. 2002).6 In particular, where the government is not
    obligated to place call orders, as here, the BPA “reflect[s] illusory promises that do not
    impose obligations on either party.” Crewzers, 741 F.3d at 1382–83.
    The government’s reliance upon Crewzers and Modern Sys. Tech. is apt, albeit
    with a caveat. Despite the clause stating that “[t]his BPA is not a contract” here, the
    parties do not address the fact that the BPA also contains numerous clauses, discussed
    above, that refer to the document as a “contract.” (See, e.g. R4, tab 1 at 21 (Type of
    Contract)) While the internal contradictions in the BPA here, and the government’s
    failure to address them, present a slightly different factual predicate than that found in
    Crewzers and Modern Sys. Tech., 7 the government’s motion goes beyond the
    conclusory self-characterization in the BPA and demonstrates that the nature of the
    BPA itself is, in fact, non-contractual. For example, as in Crewzers and Modern Sys.
    Tech, Hallym’s BPA did not require either party to take action until a call order was
    placed and accepted, supplying the consideration and mutual obligations missing from
    the BPA to create a contractual relationship between the parties. Thus, Hallym’s BPA
    is “a set of ground rules as it were, and no obligations are assumed by either party until
    orders are given by the Government and accepted by the contractor.” Modern Sys
    Tech., 
    979 F.2d 200
     at 204. On that key question, Crewzers and Modern Sys. Tech.
    are on point and we hold that the BPA here lacks mutual obligations and therefore is
    not a binding contract.
    6 The government also cites to McLeod Grp. v. United States, 840 F. App’x 525 (Fed.
    Cir. 2020), an unpublished Federal Circuit decision, and Zhengxing v. United
    States, 204 F. App’x 885 (Fed. Cir. 2006), which is “not citable as precedent.”
    Rather than rely upon unpublished and non-precedential decisions, we instead
    refer primarily to Crewzers and Modern Sys. Tech., which are valid and binding
    precedent and, except as noted below, on point with this appeal.
    7 Our review of Crewzers, Modern Sys. Tech., McLeod and Zhengxing found no
    indication of similar internal contradictions in those BPAs.
    4
    The government’s hypotheticals at pages 12-13 of its reply brief, that the Board
    would not possess jurisdiction if the Government had simply stopped issuing call
    orders to Hallym instead of canceling the BPA, or if the Government had cancelled the
    BPA for a reason unrelated to Hallym’s contract performance, or without stating a
    reason at all, is persuasive and further illustrates the non-obligatory, therefore non-
    contractual nature of the BPA. By plain reading of the provision that permits the
    cancelation of the BPA upon 30 days notice, the government had the prerogative to do
    exactly what it did here – cancel the BPA for any reason or none at all, and certainly
    when the government became dissatisfied with Hallym’s performance related to its
    invoices.
    Hallym attempts to distinguish its BPA from those found not to be contracts by
    arguing that Hallym could not refuse call orders once they were issued by the
    government, a so-called obligation not found in Crewzers that, Hallym argues, makes
    the BPA a valid contract (app. br. at 7-14). Even if true, that still does not provide
    sufficient contract consideration or a mutual obligation that makes the BPA a contract
    where the government is under no obligation to issue any call orders. See Modern
    Sys., 
    979 F.2d at
    204 (citing Gavin, Gov’t Requirements Contracts, 5 PUB. CONT. L. J.
    243, 246 (1972)) (“Usually the parties merely arrange to do business when the
    government places an order at the unit price named in the [BPA]. In such an
    agreement, there is nothing in writing which requires the government to take any
    ascertainable quantity or amount”). And we do not agree with Hallym’s contract
    interpretation anyway. The BPA here provided that the government’s obligations were
    created upon issuance of call orders (R4, tab 1 at 8), which must apply equally to
    Hallym – the parties’ mutual obligations do not arise until the government initiates a
    call order that is accepted by Hallym. Modern Sys. Tech., 
    979 F.2d at 204
    . The BPA
    here did not contain an express provision where Hallym would only perform call
    orders that it was “willing and able” to perform, as existed in Crewzers, 741 F.3d
    at 1381. It also did not explicitly provide that “[e]ach order that the [government]
    places and the contractor accepts becomes an individual contract,” as in Modern Sys.
    Tech., 
    979 F.2d at 204
     (emphasis added). But these clauses are little more than helpful
    statements of the obvious – each call order cannot become a contract until there is an
    offer and acceptance. As a result, the lack of a similar clause does not transform
    Hallym’s BPA into a contract.
    III.   The Board’s Jurisdiction is Limited to Call Order Claims, but None are
    Presented Here
    As discussed above, although Hallym and the government were parties to ten
    call orders, each of which was undisputedly a contract within the purview of the
    5
    CDA, 8 the BPA itself is not a contract and, contrary to Hallym’s argument at page 14
    of its opposition, Hallym’s claim does not allege injury or costs related to the
    performance of Hallym’s ten call orders. (R4, tab 28) As the government noted in its
    Answer at 57, Hallym may have some right to submit a call order claim if it suffered
    recoverable damages during call order performance (including, it appears, to seek
    payment upon the final invoice), but such claims were not made in Hallym’s certified
    claim, were not addressed in the COFD, and we have no authority to adjudicate them
    in this appeal.
    CONCLUSION
    The government’s motion is GRANTED and the appeal is DISMISSED for
    lack of jurisdiction.
    Dated: September 2, 2021
    BRIAN S. SMITH
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    (Signatures continued)
    8   The government’s motion acknowledges that the call orders issued to Hallym were
    CDA contracts. (See, e.g., gov’t. reply br. at 9 (Upon the placement of a call
    order under a BPA, the call would become the contract, which then adopts the
    terms of the BPA; as a matter of law, for purposes of Contract Disputes Act
    jurisdiction; thus making ‘any interpretation required of the terms of the BPA . .
    . an interpretation of the terms of [the call orders placed under the BPA] since
    those orders were the vehicles that formed the contracts.)) (quoting Hewlett-
    Packard Co., ASBCA Nos. 57940, 57941, 
    13 BCA ¶ 35,366
     at 173,548).
    6
    I concur                                          I concur
    RICHARD SHACKLEFORD                               J. REID PROUTY
    Administrative Judge                              Administrative Judge
    Acting Chairman                                   Vice Chairman
    Armed Services Board                              Armed Services Board
    of Contract Appeals                               of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 62782
    , Appeal of Hallym
    Furniture Industrial Co., Ltd., rendered in conformance with the Board’s Charter.
    Dated: September 2, 2021
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    7