Aegis Defense Services, LLC, f/k/a Aegis Defence Services Ltd. ( 2017 )


Menu:
  •                 ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeals of --                                 )
    )
    Aegis Defense Services, LLC,                  )      ASBCA Nos. 59082, 60111, 60259
    f/k/a Aegis Defence Services Ltd.            )
    )
    Under Contract No. W52P1J-l 1-D-0082          )
    APPEARANCES FOR THE APPELLANT:                       Armani Vadiee, Esq.
    Ashley N. Amen, Esq.
    Smith Pachter McWhorter, PLC
    Tysons Comer, VA
    APPEARANCES FOR THE GOVERNMENT:                      Raymond M. Saunders, Esq.
    Army Chief Trial Attorney
    MAJ David H. Stem, JA
    Trial Attorney
    OPINION BY ADMINISTRATIVE JUDGE PROUTY
    Although the facts of these appeals are intriguing, involving, as they do, the
    Milo Minderbinderesque (see JOSEPH HELLER, CATCH-22 (Simon & Schuster 1961))
    machinations sometimes necessary to do business in Iraq, in the end the issues
    presented are quite straightforward: what are the government's obligations to a
    contractor to which it gave a right of first refusal to purchase armored sport utility
    vehicles (SUVs), known as LAVs (short for "light armored vehicles") at the
    completion of contract performance, so long as it had no further need for them? And
    did the government meet those obligations when it refused to sell the LAVs to its
    contractor and, instead, gave them to the Government of Iraq, unbidden? As explained
    below, although the United States had its reasons for declining to make the sale to its
    contractor, those reasons do not excuse it from complying with its contractual
    obligations.
    FINDINGS OF FACT
    I.     The Contract and Efforts of the Government to Furnish Aegis with LAVs
    On 1June2011, the Rock Island Contracting Center (the Army) awarded
    the above-captioned contract (the contract) to appellant's predecessor in interest,
    Aegis Defence Services Ltd. (Aegis), a company doing business in the United
    Kingdom (R4, tab 1 at 1). As explained at the hearing, Aegis is primarily in the
    business of providing private security services to governments and commercial
    organizations (tr. 1/14). The contract, which was a multiple-award
    indefinite-delivery/indefinite-quantity (ID/IQ) contract 1, was for the provision of
    security support services to the United States Department of Defense and Department
    of State in Iraq (R4, tab 1 at 4, 24; tr. 1117-18).
    Aegis was awarded Task Order No. 0002 (TO 2) on the contract on 2 September
    2011, and both parties executed it on 13 September 2011 (R4, tab 3 at 203). TO 2 was
    intended to provide mobile and staffing security to various sites within Iraq (tr. 1/23).
    This task order required Aegis to reach "full operational capability" by the end of the
    month, and included a period of performance for the base year to conclude at the end of
    2011 (R4, tab 3 at 206). TO 2 was priced at more than $28 million for this first period
    of performance (id. at 230), and it included the prospect of up to four additional option
    years (id. at 206).
    With respect to the LAVs that are at the heart of this dispute, TO 2, which
    contemplated the government's providing such vehicles, took a very different approach
    than the original contract, which required the contractor to provide them and to keep
    ownership of them through the conclusion of contract performance. The original contract
    directed, in section 13 .1.5 .1, that Aegis would "provide all weapons, ammunition, LAV s
    [and other equipment]" (R4, tab 1 at 73). Section 13.1.5.2 of the contract further stated
    that "Vehicles [including LAVs] provided by the Contractor in support of providing
    transportation services for this contract shall remain the Contractor's property. The
    Government will not own or accept ownership of any vehicles furnished to it by the
    Contractor." (Id.) The Performance Work Statement (PWS) of TO 2, by contrast, stated,
    in paragraph 11.0, that, "[t]he Government will provide 155 LAVs for use to perform the
    required services under this task order" (R4, tab 3 at 235). The TO 2 PWS further
    elaborated, in paragraph 12.0, that, except for the LAVs, the remainder of the equipment
    utilized by Aegis would be "Contractor furnished" (id.), consistent with the dictates of
    the original contract (see also tr. 1/23-27).
    When Aegis bid on TO 2, it took into account the fact that it would not be
    required to provide its own LAVs, and priced its offer accordingly (tr. 1/25-26).
    Almost immediately after Aegis began performance of TO 2, though, it became clear
    that the notion of government-provided LAVs was problematic.
    1
    A multiple-award ID/IQ contract is a contractual vehicle by which the government
    awl:j.rds similar contracts to several different contractors and then (subject to any
    requirement to make minimum awards to each contractor) awards separate task
    orders on that contract to whichever contractor it chooses for the particular task
    order. Typically, contractors submit competing bids to the contracting officer to
    vie for the award of the task orders. See, e.g., Relyant, LLC, ASBCA No. 58172,
    16-1BCA~36,228 at 176,748-49.
    2
    Iraq in 2011 was a country in the midst of a significant transition, with the
    expectation that American military forces would soon leave the country as a result of
    the United States keeping its commitment to remove its military presence from that
    sovereign nation (tr. 1124-25). One of the consequences of this transition was the Iraqi
    government's greater involvement in the regulation of private security contractors
    (PSCs) operating within its territory- even those PSCs working on behalf of the
    United States. With respect to LAVs operating on the open road in Iraq, the Private
    Security Department of the Iraqi Ministry of the Interior required a "vehicle sticker"
    on such vehicles (tr. 1126). Before providing such a sticker, the Iraqi Ministry of the
    Interior required proof of ownership, which had to be obtained through the Iraqi
    Ministry of Transport (tr. 1/26-27). And without such a sticker, Aegis had a real
    concern that, as soon as one of its LAVs encountered a checkpoint manned by Iraqi
    troops, the LAV would be impounded and its occupants arrested (tr. 1/18-19, 28).
    The United States Government Office of Security Cooperation - Iraq (OSC-1)
    worked with Aegis to get stickers from the Iraqi government for the LAVs that the
    Army intended to provide (tr. 1128-30). These efforts were extensive, involved
    embassy and other personnel, and lasted through November 2011, culminating in
    OSC-I's obtaining a letter from a senior Iraqi official that, unfortunately, proved
    insufficient for registration purposes (id.). At some point, it was suggested that the
    matter could be resolved if Aegis purchased LAVs in its own name and then
    approached the appropriate Iraqi ministries as the actual owner ofthe LAVs (tr. 1129).
    Ms. Melissa Burant, the contracting officer (CO), ultimately requested Aegis to submit
    a formal proposal to do just that (tr. 1131-32).
    IL    Aegis and the Government Agree that Aegis will Purchase the LAVs; They
    also Agree upon Terms Regarding the Possible Procurement of the LAVs by
    Aegis after Completion of Contract Performance
    In response to Ms. Burant' s request, Aegis investigated the commercial
    marketplace for such vehicles and found an Iraqi commercial supplier. Aegis then
    prepared a proposal that it submitted to the Army, based upon obtaining the LAVs from
    the Iraqi supplier2 (tr. 1/32). The first informal proposal, for between 50 and 80 LAVs,
    was sent from Aegis to the Army on 11November2011 (supp. R4, tab 72). After
    some back and forth, a more formal amended proposal was sent by Aegis to the Army
    on 11 December 2011 (tr. 1133-34; app. supp. R4, tab 1).
    2
    The LAVs were "up-armored" commercial SUVs. Though Aegis proposed using the
    Toyota Land Cruiser for its lower "profile," American personnel strongly
    preferred the relatively roomier Chevrolet Suburban, which was what they got
    (tr. 1/34-35).
    3
    The 11 December proposal (drafted by Aegis's in-house counsel, Ms. Sylvia White
    (see tr. 1137)), was for the purchase of 54 LAVs at $138,375 per unit (app. supp. R4,
    tab 1 at 8319 3) and included three provisions relevant to the dispute here. First, the
    revised proposal included a statement regarding the costs of transferring ownership from
    Aegis to the government at the end of contract performance:
    For the avoidance of doubt any costs associated with
    transferring ownership to the Government at the end of the
    Contract will be for the Government's account.
    (App. supp. R4, tab 1 at 8319) To be clear, what Aegis meant was that costs incurred
    in transferring ownership to the government would be paid by the government (tr. 1/36).
    The second material provision in the Aegis proposal states that, "the [LAVs]
    would be ~he property of the Government (as CAP), [but] Aegis would hold the
    vehicles to the Government's order, but in Aegis name" for purposes of getting them
    registered with the Iraqi government (app. supp. R4, tab 1 at 8320). Ms. White
    testified that she, herself, was not particularly well-acquainted with the term, CAP,
    which she took to mean "contractor acquired property," as utilized by the Federal
    Acquisition Regulation (FAR), but that she included it in an attempt to conform the
    proposal to the FAR (tr. 1175-76).
    The third, and final, material provision provided that:
    At the end of the Contract Aegis will be given the right of
    first refusal to purchase the vehicles in the event the
    Government has no further use for them. We propose a
    straight line amortization over a 2 year period with a 5%
    residual value.
    (App. supp. R4, tab 1 at 8320 (footnote omitted))
    Notably, Ms. White testified that, when she drafted the proposal on behalf of
    Aegis, she envisioned the LAVs as being owned by the government, notwithstanding
    their being titled to Aegis with the Iraqi government (tr. 1176).
    3   The pages in appellant's supplemental Rule 4 file include consecutive numbers both
    at the upper right-hand comers of each page and at the bottom right-hand
    comers of the pages, which appear to be the numbers utilized when the
    government produced the documents in discovery. Because, during the trial,
    counsel and the witnesses tended to reference the consecutive number on the
    bottom right-hand comer of the document, that is the number we use herein.
    4
    On 19 December 2011, Ms. Burant sent an email to Ms. White of Aegis,
    forwarding a notice to proceed (NTP) with the purchase of 14 LAVs at the
    11 December proposal price of $138,375 each (app. supp. R4, tab 2 at 227-29;
    see also tr. 1/40). Funding issues, apparently, were the reason for the discrepancy
    in the number of LAVs proposed on 11 December and the number ordered
    through the NTP (tr. 1/40). On 20 December 2011, as requested by Ms. Burant
    (see app. supp. R4, tab 2 at 227), Aegis acknowledged acceptance of the terms of the
    NTP (which was to be formalized by a modification to the TO), but added a
    handwritten note above the signature block from Ms. White:
    Except with respect to numbers of vehicles to be
    purchased, which is limited by the value of funding in this
    NTP all other terms included in Aegis' proposal dated
    11 December 2011 apply to this purchase.
    (App. supp. R4, tab 2 at 230; tr. 1/41)
    Ms. White continued discussions with government personnel in an attempt
    to reach agreement upon the terms of the contract modification so that it could be
    completed and Aegis's invoices for the LAVs could be paid before the New Year
    (app. supp. R4, tab 4). On 23 December 2011, the parties executed Modification
    No. 06 to TO 2 (Mod 6) (R4, tab 13 at 385). The purpose of Mod 6 was to fund the
    purchase of the 14 LAVs, and it expressly provided that, "Aegis proposal, submitted
    via e-mail, dated 19 December 2011 is incorporated to the award" (id. at 387). We are
    aware of no proposal from Aegis to the government dated 19 December 2011 as
    referenced in this modification, but Mod 6 includes the 11 December 2011 proposal as
    an attachment (id. at 390-94).
    In the meantime, the parties negotiated amendment of the terms of the TO 2
    PWS to provide for the use of the Aegis-acquired LAVs. As communicated to Aegis
    in a 19 December 2011 email, the government's view about the sentence in its
    proposal that Aegis would have the right of first refusal if the government had "no
    further use for" the LAVs was that the condition was acceptable, inasmuch it was
    stated to be "incorporated" into the government-proposed PWS revision without
    further comment (R4, tab 15 at 408). The government, however, did not agree to the
    proposed straight-line depreciation for the LAVs, and preferred language simply
    specifying that the government would negotiate with Aegis at the end of the contract if
    it were not taking the vehicles (id.). Ms. White's response to the government's draft
    did not address these particular matters (id. at 403), tacitly suggesting that Aegis was
    satisfied with the proposed revised PWS provisions regarding the right of first refusal
    and pricing issues. The record includes no further correspondence regarding the right
    of first refusal language prior to the conclusion of negotiations over the PWS revision.
    5
    Modification No. 07 to TO 2 (Mod 7), effecting the revision of the PWS to
    account for the purchase of the LAVs, was executed on 9 January 2012 (app. supp. R4,
    tab 7 at 1977). The modified PWS (dated 3 January 2012) incorporated into TO 2 by
    Mod 7, provided in relevant part:
    All LAVs purchased by the contractor for use on this
    contract will be registered and licensed in contractor's
    name to facilitate [Government of Iraq] licensing. Govt
    will provide reimbursement for costs associated with
    licensing, registration, taxes, renewal fees and title transfer
    fees imposed by the Government of Iraq. At the end of
    contractor's performance period on this Task Order, USG
    will retake title to LAV s. If USG does not wish to take
    title to the vehicles, contractor will be given first right of
    refusa1£4l on negotiating and possible procurement of said
    vehicles.
    (App. supp. R4, tab 7 at 1983) Nothing in this modification referenced Mod 6 or
    addressed what was to be done in the event that its terms were inconsistent with the
    terms of Mod 6 (see app. supp. R4, tab 7).
    The government obtained more funding for LAVs shortly thereafter, and on
    25 January 2012, presumably at the government's request, Aegis submitted an updated
    proposal to Ms. Burant for the purchase of an additional 38 LAVs (app. supp. R4,
    tab 8 at 571-72). The terms of the proposal were similar to those in Aegis's
    11 December 2011 proposal, with a few variances not relevant to the present dispute.
    In particular, the 25 January proposal included, word-for-word, the clause providing
    for Aegis's "right of first refusal" to purchase the LAVs at the end of performance if
    "the Government has no further use for them" (app. supp. R4, tab 8 at 573). On
    30 January 2012, Ms. Burant sent Ms. White an email forwarding an NTP to purchase
    the additional 38 LAVs "in accordance with" the 25 January proposal (id. at 570).
    On 13 February 2012, the parties executed Modification 10 to TO 2 (Mod 10),
    to effect the purchase of the 38 LAVs provided for in the 30 January NTP (R4,
    tab 23 at 615). Like Mod 7, it included an amendment to the TO 2 PWS using the
    same exact language stating that at the end of performance period, the government
    would retake title of the LAV, but that if the government "does not wish to take title to
    the vehicles, contractor will be given first right of refusal on negotiating and possible
    4
    Here, the language departed from the "right of first refusal" used in earlier
    correspondence to become "first right of refusal." Neither party has remarked
    upon the difference, and we see no material difference in the phrases, which we
    consider to be interchangeable.
    6
    procurement of said vehicles" (R4, tab 23 at 623). The record includes no
    intermediate modification affecting the NTP for the 38 LAVs in the way that Mod 6
    did for the first 14 LAV s. In any event, nothing in Mod 10 referenced the NTP or
    addressed what was to be done in the event that Mod 10' s terms were inconsistent with
    the terms of the NTP (see R4, tab 23).
    Aegis purchased the 52 LAVs embraced by Mods 6, 7, and 10, took title
    to them, and successfully registered them with the appropriate Iraqi authorities
    (tr. 1152-53). There were no disputes between the parties regarding their use.
    III.   The Government Refuses to Sell the LAVs to Aegis
    As contract performance neared completion, Aegis expressed a desire to
    negotiate the purchase of the LAVs from the government. The first evidence of this
    expression in the record is an internal Army email dated 4 June 2013 in which an
    Army contracting specialist named Trisha Polfliet notified her chain of command of
    Aegis's wish to obtain the LAV s, and inquired whether the government wanted to
    keep the LAVs for itself (R4, tab 33 at 722; see also tr. 1158 (Ms. White recalls
    making inquiries regarding keeping the LAVs approximately July 2013)).
    In response to Ms. Polfliet' s email, the government began the process of
    deciding whether it had a use for the vehicles (R4, tab 33 at 719-21). The Defense
    Contract Management Agency (DCMA) property managers to whom this task was
    forwarded were taken by surprise, to say the least (see generally, R4, tab 34). On
    6 June 2013, Jeff Garrett, the Department of Defense (DoD) Demilitarization Program
    Manager, responded to the internal inquiry by stating that DoD was "not authorized to
    sell excess military equipment in Iraq especially Armored vehicles" and explained that
    the LAVs needed to be "turned in to OSC-I" (id. at 724).
    By 21June2013, however, it appeared that those being consulted were in
    favor of selling the vehicles to Aegis and that any internal obstacles to the sale
    had been overcome. On that date Army L TC John Turner, in an email on behalf
    of OSC-1, responded to renewed questions about the LAVs by stating, "If Aegis
    wants the vehicles, that is their right IA W the contract. No argument from OSC-1."
    (R4, tab 36 at 731) After a few additional email exchanges about the mechanics of the
    LAV sale to Aegis, on 25 June 2013, Ms. Polfliet asked LTC Turner for confirmation
    regarding their use before she could move forward: "Basically we need the USG
    to state they don't need them." She also expressed her desire to sell the LAVs to
    Aegis so that the government could obtain the money to put towards the contract.
    (R4, tab 37 at 734) LTC Turner's response later the same day was, "please use this
    email to serve as official notice that the USG will not require the 52 purchased
    vehicles for operations post site closure and normalization." He then offered to
    provide a memorandum more formally stating the same if the email were insufficient.
    7
    (Id.) Ms. Polfliet forwarded this email to Mr. John Gorman, the DCMA Property
    Manager for Iraq, who responded that it satisfied him and told her to go ahead and
    "negotiate directly with Aegis on the purchase of these vehicles" (R4, tab 39 at 752).
    That was not, however, the end of the story. On 2 July 2013, in an email
    response to Ms. Pol:fliet, who was ensuring that she "cross[ed] all of our T's" for the
    negotiation with Aegis (R4, tab 40 at 755), Mr. Garrett, the DoD Demilitarization
    Program Manager, who earlier sent the email stating that such sales were forbidden,
    again voiced his concerns. In short, Mr. Garrett explained that up-armored SUVs were
    considered to be subject to the Department of Commerce Arms Export Regulation,
    and, as such, DCMA had no authority to release them to Aegis. He did hold out the
    possibility that a purchase could be coordinated through the "LM&R" office of the
    Office of the Secretary of Defense. (Id. at 754)
    Apparently unaware of any flies in the ointment, on the 4th of July 2013, Aegis
    sent ACC-RI additional information regarding the 52 LAVs that it wished to purchase
    (R4, tab 41 at 772). An internal government discussion followed (see, inter alia, R4,
    tab 44). In a 10 July 2013 email that was part of this discussion, an OSC-I
    representative explained that OSC-I's need to rapidly wind down sites meant that its
    :flexibility in dealing with the vehicles continually diminished, and that the "default
    position" was to "FEPP"5 the vehicles to the Government of Iraq (id. at 806-07). In a
    further email exchange the same day, after agreeing that the export controls on the
    armored vehicles had an exception that allowed their transfer to the Government of
    Iraq, Mr. Garrett reiterated to Ms. Pol:fliet that, "[c]urrently DOD can't sell or release
    Demil Code Q/3 (sensitive) [which is the category that he earlier explained applied
    to the LAVs] out DOD [sic] to civilians" (id. at 804-05). He further noted that the
    DoD policy on the matter was being updated, but that he expected "no major change"
    (id. at 804). Ms. Pol:fliet forwarded the material part of Mr. Garrett's email to
    Ms. White, of Aegis, the next day (R4, tab 45 at 826).
    In her email response to Ms. Polfliet sent on 12 July 2013, Ms. White
    thanked her for the information and informed her that she would have Aegis's
    American attorneys look into the issue "to see if they have any bright ideas" (R4,
    tab 45 at 825-26). In a follow-up email sent the 23rd of July, Ms. White inquired about
    why the LAVs were considered to be "Demil Code Q/3 and whether they [had] ever
    officially been classified as such by the US Government." She further shared that
    Aegis was of the opinion that the LAVs should not be considered to be subject to
    the Department of Commerce demilitarization classifications since they were
    purchased, titled, and registered to Aegis, not the United States. (R4, tab 45 at 825)
    Responding to Ms. Polfliet's email forwarding this exchange on the 24th of July,
    5
    "FEPP" stands for Foreign Excess Personal Property. "FEPPing," in this context,
    means transferring ownership of property to the Government oflraq. {Tr. 1/84)
    8
    Mr. Gorman, the DCMA Iraq Property Manager, appeared to agree that the LAV s
    were contractor-furnished equipment and thus not covered by the demilitarization rules
    (id. at 824).
    Nevertheless, by the next day, the 25th of July, Ms. Polfliet received new
    direction that would end up as the final government position. As she explained to
    Ms. White, since the LAVs were bought with government funds, they were considered
    to be government-furnished equipment to which the demilitarization rules applied.
    And noncombat commercial armored vehicles were apparently classified as "Q."
    (R4, tab 49 at 872) Although the record is unclear, it appears to us that Ms. Polfliet's
    position was based upon direction given to her by the new CO, Ms. Jodie Bennett
    (see tr. 11141-43).
    According to her testimony, which we find to be credible, Ms. Bennett's
    decision-making with respect to the disposition of the LAVs was driven almost
    completely by the advice she received from Mr. Garrett, the DoD demilitarization
    expert, who had communicated that the sale of the LAVs would be contrary to
    governing regulations (tr. 11143). She did not FEPP the LAVs to the Government of
    Iraq because the United States had a particular need to give them to the Iraqis; rather,
    she did so because the vehicles needed to be disposed of at the end of the contract and
    FEPPing them to the Iraqis was preferred to simply destroying them, which was also
    an option (tr. 11143-44). Thus, we specifically find that the decision to FEPP the
    LAVs, rather than sell them to Aegis, was not made for reasons involving national
    security or foreign policy, but was simply the path taken to dispose of them once the
    government, rightly or wrongly, internally decided that it could not transfer them to
    Aegis on contract completion.
    We also find that the government had no use for the LAVs upon contract
    completion. This finding is based upon CO Bennett's earlier-discussed testimony
    regarding her motivation for disapproving the sale as well as her testimony, in
    response to the Board's questions, that nobody had actually particularly wanted to give
    the LAVs to Iraq, except as a means of their disposal (tr. 11143-44) and OSC-l's
    earlier-noted statement that the government had no further use for the LAVs. 6
    Interestingly, in early August 2013, some government personnel explored the options
    available for exporting at least some of the LAVs to other countries in the region for
    use in security contracts so that the money already spent on them would not be wasted.
    To that end, the persons involved in this discussion affirmatively did not wish for the
    6   To the government's credit, the CO's final decision in response to Aegis's non-monetary
    claim upon this matter did not assert that there was a use for the vehicles; stating,
    instead, that the future use of the vehicles was irrelevant to the government's
    decision-making (R4, tab 63 at 1042-43).
    9
    LAVs to be FEPP'd to the Iraqis (see R4, tabs 47-48). Unfortunately, however, the
    export of these LAVs proved to be impracticable (see R4, tab 48).
    Through a series of emails in early to mid-August 2013 to Ms. Bennett and her
    supervisor, Ms. Christine Berry, Ms. White attempted to persuade the government to
    change its mind regarding the LAVs prior to their transfer to the Iraqis (R4, tabs 49,
    52-53). One matter of particular concern to Ms. White was the possibility that LAVs
    FEPP'd to the Government of Iraq might simply be handed over to a different security
    contractor by that government (R4, tab 53 at 934-35). CO Bennett agreed that such a
    thing had happened, though it should not have (app. supp. R4, tab 24 at 4428-29). In
    the end, however, the government felt that it could not budge (R4, tab 53 at 936). On
    17 September 2013, Ms. White submitted a non-monetary claim to the CO seeking a
    contractual interpretation permitting the sale of the LAVs to Aegis as part of an effort
    to get the government to reconsider and make a definitive decision7 (see R4, tab 56;
    tr. 1/60). This claim was denied in due course in a final decision by CO Bennett dated
    25 October 2013 (R4, tab 63). That decision was appealed on 20 December 2013 and
    docketed as ASBCA No. 59082.
    In the end, the LAVs were a11 8 FEPP'd to the Iraqis in April 2014 (supp. R4,
    tab 95). The FEPP paperwork included a statement by the Deputy Chief of OSCI-C
    that the FEPP transfer was "for the benefit of both the [Government of Iraq] and the
    United States (US) Government," and ''will contribute significantly to [US] efforts [to
    help] Iraqi Security Forces" (supp. R4, tab 95 at 2936).
    Aegis submitted two monetary claims to the CO in 2015. The first, in the
    amount of$3,709,843.75, was submitted on 7 May 2015 for 37 LAVs (supp. R4,
    tab 96). It was denied by the CO on 4 June 2015 (supp. R4, tab 97), appealed by
    Aegis on 27 July 2015, and docketed as ASBCA No. 60111. The second monetary
    claim, in the amount of$1,081,187.50, for 13 LAVs, was submitted by Aegis on
    7
    The claim turned out not to be quite the last effort on Aegis's part. In early
    October 2013, Aegis's director, Brigadier James Ellery, sent an email directly
    to L TG John Bednarek, chief of OSC-I in an attempt to get the government to
    change its mind. The two engaged in what appears to have been a friendly and
    constructive colloquy about the issue, with L TG Bednarek ultimately
    explaining that the government would have liked to have sold the LAVs to
    Aegis and been paid for them, but had felt compelled to follow its interpretation
    of the regulations that precluded such a sale. (R4, tab 62)
    8
    The FEPP paperwork indicates that only 50 LAVs were FEPP'd to the Government
    of Iraq (app. supp. R4, tab 28 at 463), rather than the full 52 at issue in the
    contract. The discrepancy is likely resolved by the fact that at least 1, and
    perhaps 2 of the original 52 LAVs had become inoperable by the time of
    contract completion (see tr. 1/61-62).
    10
    27 July 2015 (supp. R4, tab 98). The record does not include a CO's final decision
    upon this claim, and its deemed denial was appealed by Aegis on 2 October 2015 and
    docketed as ASBCA No. 60259.
    DECISION
    We do not second guess the government's motives in its apparently sincerely held
    belief that it was precluded from selling the LAVs to Aegis, as contrary to common sense
    as it may seem. The consequence of acting upon that belief, however, is that the
    government broke its contractual promise to Aegis to give it a right of first refusal to
    purchase the LAVs if the government had no use for them. As the government, in fact,
    had no use for the LAVs and as the contract was definite enough to pass legal muster and
    no other circumstances were proved to excuse performance, we rule in favor of Aegis on
    entitlement.
    I.     The Contractual Language Required the Government to Offer to Sell the
    LAVs to Aegis if the Government had No Use for Them
    The terms of the contract material to this dispute are, at first blush, not as clear
    as we would like them to be. The government argues, consistent with the terms of the
    amended PWS, that the sole determinant of triggering Aegis's right of first refusal was
    whether the government wished to take back "title" to the LAVs (gov't br. at 19-24).
    This would make Aegis's rights tum upon the subjective desires of the government
    and have nothing to do with whether the government had an alternate use for the
    LAVs. The contract terms, however, are not so plainly focused upon the term, ''title,"
    as the government would like and, as will be seen, ultimately support Aegis's
    preferred reading: that Aegis had the right of first refusal if the government had no
    further use for the LAV s.
    To resolve this issue, we begin with the law of contract interpretation. Under
    basic principles of the law, a contract is interpreted "in terms of the parties' intent, as
    revealed by language and circumstance." United States v. Winstar Corp., 
    518 U.S. 839
    ,
    911 (1996) (citations omitted). Generally, this process begins and ends with the
    language of the contract. TEG-Paradigm Environmental, Inc. v. United States,
    
    465 F.3d 1329
    , 1338 (Fed. Cir. 2006). And in reviewing this language, the Board
    should read the contract "as a whole and [interpret it] to harmonize and give reasonable
    meaning to all its parts," if possible, leaving no words "useless, inexplicable,
    inoperative, insignificant, void, meaningless or superfluous." Precision Dynamics, Inc.,
    ASBCA No. 50519, 05-2 BCA ~ 33,071at163,922; see also Hercules, Inc. v.
    United States, 
    292 F.3d 1378
    , 1381 (Fed. Cir. 2002) ("contract must be construed to
    effectuate its spirit and purpose giving reasonable meaning to all parts of the contract");
    Hunkin Conkey Constr. Co. v. United States, 461F.2d1270 (Ct. Cl. 1972) (rejecting
    contract interpretation that would render a clause in the contract meaningless).
    11
    With this in mind, we tum to the terms of the contract, which are more expansive
    than admitted by the government. The government's insistence that we are limited to
    the terms of the PWS is contradicted by the parties' adoption of the terms of Aegis's
    11 December 2011 proposal into Mod 6 as well as the government's adoption of those
    terms into the NTP that preceded Mod 6 and into the NTP that preceded Mod 10. That
    proposal, of course, included the language granting the right of first refusal to Aegis if
    the government had no use for the LAVs. Because Mod 6 is part of the contract9 and
    because Mod 7 made the revised PWS part of the contract (without explicitly replacing
    or rejecting the terms of Mod 6), we are presented with a requirement to reconcile these
    contractual terms. See, e.g., Hunkin Conkey, 461F.2d1270.
    The most direct way to reconcile the seemingly different contract terms ("no
    further use" in the proposal versus the government's '\vish[ing] to take title" LtJ. the
    PWS) is to interpret the title language in the PWS as the equivalent of the use language
    in the earlier-drafted proposal. To understand how this can be so, we digress slightly to
    discuss the meaning of "title" in the PWS. Although the parties were both of the belief
    that, as property acquired under the contract, the LAVs were the government's
    property, both parties also recognized that the LAVs had to be titled to Aegis so that it
    could engage with the Iraqi government to obtain the necessary sticker. At the end of
    the contract, even if the government had always equitably owned the LAVs, in order to
    use them in Iraq or elsewhere, it would need to take title to them. To the contrary, ifthe
    LAV s were only to be destroyed or handed to a different contractor (or the Government
    of Iraq), there would be no need for the government to take title for itself. Thus, taking
    title, as a practical matter, would only be done in the event that the government had use
    for the LAVs, and would not be done if it did not. We do not perceive - and the
    government does not present - an alternate interpretation of the contract that reconciles
    the two writings. Moreover, this interpretation has the great merit of being exactly
    what the parties intended 10, as reflected in the government's previously-discussed 19
    December 2011 email correspondence with Aegis, in which it informed Aegis that its
    proposal, regarding a right of first refusal to purchase the LAVs if the government had
    no use for them, had been incorporated into the PWS except for the straight-line
    depreciation issue. See Blinderman Constr. Co. v. United States, 
    695 F.2d 552
    , 558
    9
    The government asserts, without support, that the PWS in Mods 7 and 10 "superseded"
    the incorporation of Aegis's proposal by Mod 6 (gov't hr. at 20). Nothing in
    Mod 7 or Mod 10 supports this conclusion with respect to the terms at issue here.
    10
    Aegis asks us to make an adverse inference against the government with respect to its
    intent because of its failure to produce Ms. Burant as a witness (app. br. at 25-27).
    Drawing such an inference is unnecessary here, given that the documentary
    evidence amply explains the parties' intents and there is no reason to believe
    that Ms. Burant's testimony would be materially any different than Ms. White's.
    The government's failure to call a witness that the appellant believes would be
    helpful to appellant's case, without more, does not justify an adverse inference.
    12
    (Fed. Cir. 1982) (contemporaneous construction of an agreement prior to dispute is
    entitled to great weight).
    Additionally, we reject the government's attempt to make hay of the fact that
    there was no equivalent to Mod 6, incorporating the terms of the Aegis proposal for
    the purchase of the first 14 LAVs (which preceded Mod 7), for Mod 10, involving the
    later 38 LAVs (see gov't br. at 22). Through reconciliation of the terms of Mods 6 and
    7, the meaning of the revised PWS was already established by the time of Mod 10;
    there is simply no need to revisit its interpretation.
    II.     The Government Had No Use for the LAVs After Contract Performance
    Althoug.li the government asserts that its handing the LAV s to the Iraqi
    government furthered a valid national security aim and thus advanced a legitimate
    government purpose (see gov't br. at 22), the overwhelming weight of the evidence is
    to the contrary. LTC Turner's emails on behalf of OSC-I certifying that the
    government had no use for the LAVs are convincing evidence that there was no
    government need for them. Ms. Bennett's candid testimony that her decision to FEPP
    the vehicles was based completely upon the advice she received forbidding their sale,
    and had nothing to do with any government need for them constitutes further
    persuasive evidence that the government had no remaining use for them. There is also
    the notable absence in the email correspondence of any argument, whatsoever, that
    FEPPing the LAVs to the Iraqi government would be of any use to the United States
    Government.
    To counter this evidence, the government presents the fact that the apparently
    standard government memorandum to justify the FEPPing of the LAVs included
    language stating that it was done in the interest of the government and for Iraqi
    security (gov't br. at 13). The government also states, in one sentence of its brief
    that, in being transferred to the Iraqi government, the LAVs were being legitimately
    used by the United States (id. at 22). There is nothing in the FEPPing memorandum
    that gives us any reason to believe that the statement about the use of the LAVs
    was anything more than a standard incantation with little evidentiary worth. The
    contemporaneous statements of LTC Turner; the extensive email thread; and
    Ms. Bennett's sworn testimony all prove otherwise.
    Under the terms of the contract, the government had no use for the LAVs and was
    obligated to give Aegis the right of first refusal for their purchase, which it did not do.
    13
    III.   Aegis May be Entitled to Monetary Damages
    Due to prior agreement at the pretrial stage of these appeals, we only decide
    entitlement at this stage of the proceedings. Nevertheless, the government has argued
    that the terms of the contract are such that the damages are too speculative to support a
    finding of entitlement to money damages, as sought in Aegis's second and third claims
    and appeals (gov't hr. at 27-30). In response, Aegis contends that arguments about
    damages are premature at this point in the litigation and that it is not seeking
    speculative damages; only the difference between what it paid for replacement LAVs
    and what it would have paid for the LAVs had the government complied with the
    contract and sold them to Aegis (app. reply hr. at 11-13). Neither side's argument is
    completely correct.
    We start by noting that the theory upon which Aegis appears to be seeking
    damages is flawed. That damages theory is that, in accepting Aegis's 11 December
    2011 proposal, the government agreed to a straight-line depreciation of the price of the
    LAVs over a two-year period with a 5% residual value. Damages, then, would be
    calculated by subtracting the depreciated price of the contractually obtained LAVs
    from the price that Aegis ultimately paid on the market for other LAVs that it bought
    to replace them for use in its post-contract Iraqi business (see supp. R4, tab 96 at 4
    (damage analysis in first monetary claim), tab 98 at 1 (second monetary claim,
    adopting analysis of first)). But the contract did not mandate that the government
    depreciate the LAVs to almost nothing as Aegis first proposed.
    To be sure, as we discussed at length above, the contract incorporated both
    Aegis's 11December2011 proposal and its revised PWS. But while the proposal was
    firm that the right of first refusal would be triggered if the government had no use for
    the vehicles, it was not so firm about the means of calculating their price. With respect
    to use, the language was: "At the end of the Contract Aegis will be given the right of
    first refusal to purchase the vehicles in the event the Government has no further use for
    them" (app. supp. R4, tab 1 at 8320 (emphasis added)). By contrast, the price
    language, which immediately followed was: "We propose a straight line amortization
    over a 2 year period with a 5% residual value" (id.). Moreover, unlike the terms of the
    PWS that could be harmonized with the use language of the proposal, the PWS
    language on the terms of the sale specifically rejected the set price proposed by
    Aegis's proposal, and stated: "If USG does not wish to take title to the vehicles,
    contractor will be given first right of refusal on negotiating and possible procurement
    of said vehicles" (app. supp. R4, tab 7 at 1983 (emphasis added)). This was consistent
    with the government's written response to Aegis's proposal in which it specifically
    rejected the set depreciation rate and proposed negotiations, instead (R4, tab 15 at
    408). We thus interpret the contract modifications together, to provide that Aegis and
    the government agreed to negotiate a price for the LAVs if the government had no use
    for them, but not to adopt the pricing formula proposed by Aegis.
    14
    Although this interpretation might diminish Aegis's damages - and certainly
    makes them less easily quantifiable - it does not prevent us from finding a breach of
    contract or making a monetary award. What we are presented with in this contract is
    an agreement to negotiate over a matter- in other words, an "agreement to agree,"
    which imposes upon the parties an obligation to negotiate in good faith. North Star
    Steel Co. v. United States, 
    477 F.3d 1324
    , 1332 (Fed. Cir. 2007). Such agreements to
    agree have been held to be sufficiently definite to support the finding of the existence
    of a contract, see, e.g., Gardiner, Kamya & Assocs., P.C. v. Jackson, 
    369 F.3d 1318
    ,
    1322 (Fed. Cir. 2004) (citing cases), and we see no reason to depart from this
    precedent at this time. Of course, ifthe parties are unable to resolve the quantum of
    this appeal upon remand, Aegis will be obligated to present evidence of the value of its
    agreement that was breached by the government, but we have no need to further
    address the measure of damages here and now.
    IV.    The Government Has Not Presented a Legal Impossibility Defense
    Finally, we briefly address the matter of a defense that has not been raised by
    the government, but is so implicit in the facts leading up to the contract breach that we
    feel obligated to acknowledge it: was the government legally barred from selling the
    LAVs to Aegis? If so, does this suggest that both parties were under the
    misapprehension when they agreed to Mods 6, 7 and 10, that the government could
    sell the LAVs to Aegis when, in fact, it could not, thus presenting the defense of
    mutual mistake of law?
    Mutual mistake is an affirmative defense. See, e.g, K-Con Building Systems,
    Inc. v. United States, 
    131 Fed. Cl. 275
    , 332 (2017); Ameriserv Trust v. United States,
    
    125 Fed. Cl. 733
    , 747 (2016); see also East-Wind Industries, Inc., ASBCA No. 25684,
    86-1 BCA ~ 18,698 at 93,987 (holding that mutual mistake is "not merely" an
    affirmative defense, but also, effectively, a counterclaim). As an affirmative defense,
    it must be pied and proved. See Board Rule 6(b) (requiring affirmative defenses to
    be pied in the government's answer); Northrop Worldwide Aircraft Services, Inc.,
    ASBCA Nos. 45216, 45877, 96-2 BCA ~ 28,574 at 142,630-31 (failure to timely
    raise affirmative defense may waive it); Kellogg Brown & Root Services, Inc.,
    ASBCA No. 58175, 15-1BCA~35,988 at 175,823 (burden of proof). The
    government did neither here.
    The defense of mutual mistake is not present in the government's answer or in
    any pre- or post-trial filing in this appeal. Moreover, even when Aegis raised a related
    matter in its opening post-trial brief (primarily arguing that, because it had not been
    raised as a defense, the government could not rest upon a DoD regulation to excuse its
    performance (see app. br. at 36)), the government never claimed that it was presenting
    such a defense. Finally, at the hearing, the government presented no evidence (such as
    proof that the regulation actually prohibited the sale versus whether it was merely
    15
    perceived to do so) to prove such a defense. 11 The defense is thus both waived and
    unproved.
    CONCLUSION
    The government agreed to give Aegis a "right of first refusal" to negotiate a
    purchase of the LAVs obtained under the contract after the contract was over, so long
    as the government had no use for them. The government, in fact, had no use for the
    LAVs, but declined to sell them to Aegis because of its belief that it was not permitted
    to do what it had agreed to do under the contract. This was a breach of the contract for
    which the government has presented and proved no defense. Accordingly, Aegis is
    entitled to those damages it can properly prove came from that breach. The appeals
    are sustained and remanded to the parties to negotiate quantum.
    Dated: 15 November 2017
    J. REfDPROUTy
    Administrative Judge
    Vice Chairman
    Armed Services Board
    of Contract Appeals
    I concur
    RICHARD SHACKLEFORD
    Administrative Judge
    Acting Chairman
    Armed Services Board
    of Contract Appeals
    11
    We do not know or speculate why the government chose this strategy, but recognize
    that there may have been very good reasons for it to do so.
    16
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA Nos. 59082, 60111, 60259,
    Appeals of Aegis Defense Services, LLC, f/k/a/ Aegis Defence Services Ltd., rendered
    in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    17