American International Contractors, Inc. ( 2018 )


Menu:
  •                 ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeals of --                                  )
    )
    American International Contractors, Inc.       )      ASBCA Nos. 60948, 61166
    )
    Under Contract No. W912ER-14-C-0002            )
    APPEARANCES FOR THE APPELLANT:                       Scott M. Heimberg, Esq.
    Mark J. Groff, Esq.
    Elise A. Farren, Esq.
    Akin Gump Strauss Hauer & Feld LLP
    Washington, DC
    APPEARANCES FOR THE GOVERNMENT:                      Michael P. Goodman, Esq.
    Engineer Chief Trial Attorney
    Rebecca L. Bockmann, Esq.
    Sarah L. Hinkle, Esq.
    Engineer Trial Attorneys
    U.S. Army Engineer District, Middle East
    Winchester, VA
    OPINION BY ADMINISTRATIVE JUDGE O'CONNELL
    ON THE PARTIES' CROSS-MOTIONS FOR SUMMARY JUDGMENT
    Pending before the Board are the parties' cross-motions for summary judgment
    on appellant's claim seeking the return of liquidated damages withheld by the
    government. We grant the government's motion in part and deny it in part. We deny
    appellant's motion.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTIONS
    Unless otherwise noted, the following facts are undisputed or uncontroverted.
    1. On 21 January 2014, the U.S. Army Corps of Engineers, Middle East
    District (Corps), and American International Contractors, Inc. (AICI) entered into a
    contract for a project entitled United Kingdom Maritime Component Command
    (UKMCC) Development, Mina Salman Port, NSA II, Kingdom of Bahrain, at a price
    of$9,788,000 (ASUMF 1 ,i 1; GSMF 2 ,i 1; R4, tab 8 at 2-3). A limited number of
    contract provisions are relevant to the pending motions.
    1
    Appellant's Statement of Undisputed Material Facts.
    2
    Government's Statement of Material Facts.
    2. As awarded, the contract had 12 contract line item numbers (CLINs). The
    largest of these were CLIN 0002 providing for the construction of a Forward Support
    Services (FSU)/Forward Logistics Site (FLS) facility priced at $4,354,184, and
    CLIN 0004 providing for the construction of a Command Headquarters (HQ) facility
    priced at $4,255,742 (ASUMF i1 1; GSMF i1 1; R4, tab 8 at 4-9).
    3. The contract required AICI to complete the HQ facility and related CLINs
    by 7 March 2015 and the FSU/FLS facility and related CLINs by 6 April 2015 3 (R4,
    tab 8 at 9-10, 32-33).
    4. The contract contained the Federal Acquisition Regulation (FAR) 52.21 i-12,
    LIQUIDATED DAMAGES-CONSTRUCTION (SEP 2000) clause. Pursuant to FAR l l .503(b ),
    the contracting officer has the authority to revise this clause to provide for different
    liquidated damages amounts for separate parts of the work, but she did not do so here.
    Accordingly, the contract did not differentiate liquidated damages for the HQ facility
    work to be completed on 7 March 2015 and the FSU/FLS work to be completed on
    6 April 2015. It simply provided: "If the Contractor fails to complete the work within
    the time specified in the contract, the Contractor shall pay liquidated damages to the
    Government in the amount of $2,447.00 for each calendar day of delay until the work is
    completed or accepted." (ASUMF ,-r 2; GSMF ,-r 2; R4, tab 8 at 33)
    5. Finally, the contract also contained FAR 52.211-13, TIME EXTENSIONS
    (SEP 2000), which provides:
    Time extensions for contract changes will depend
    upon the extent, if any, by which the changes cause delay
    in the completion of the various elements of construction.
    The change order granting the time extension may provide
    that the contract completion date will be extended only for
    those specific elements related to the changed work and
    that the remaining contract completion dates for all other
    portions of the work will not be altered. The change order
    also may provide an equitable readjustment of liquidated
    damages under the new completion schedule.
    (App. mot. at 9; R4, tab 8 at 33)
    6. AICI did not complete the original contract work on time. In a 5 February
    2015 letter, the contracting officer (CO) notified AICI that she would assess liquidated
    3
    These are the dates listed at page 10 of the contract and the dates used by the parties
    in their briefs (ASUMF ,-i 1; GSMF ,-r 1). As discussed below, the Corps did not
    use these dates for assessing liquidated damages.
    2
    damages starting on 10 March 2015 at a daily rate of $1,223.50 (one-half the rate
    specified in the contract) for failure to complete the HQ facility (R4, tab 22). After
    AICI failed to complete the HQ facility by 9 March 2015 the Corps subsequently
    withheld $26,917 in liquidated damages (22 x $1,223.50) from AICI's March 2015
    invoice (ASUMF ,r 3; GSMF ,r 3 ).
    7. AICI also failed to complete the FSU/FLS facility on time. In AICI's
    April 2015 invoice, the Corps withheld an additional $63,622 in liquidated damages.
    This amount consisted of $9,788 for the HQ facility only from 1-8 April 2015
    (8 x $1,223.50), and $53,834 for both facilities for the remainder of the month at the
    contractual rate of $2,447 per day (22 x $2,447). 4 (ASUMF ,i 4; GSMF ,i 4; R4,
    tab 151) Finally, the CO withheld an additional $68,516 from 1-28 May 2015 (28 x
    $2,447), at which point the Corps agreed that the facilities were substantially complete
    (ASUMF ,i 7; GSMF ,i,i 6-7; R4, tab 152 at 1). The Corps withheld a total of
    $159,055 in liquidated damages.
    8. There is a material dispute of fact as to whether the buildings were
    sufficiently complete on 18 May 2015 to stop the assessment of liquidated damages
    (ASUMF ii 6; GSMF ,r 6; R4, tab 3 at 3-4).
    9. On 5 January 2016, after AICI had demobilized from the site, the Corps
    issued RFP-0007 seeking a proposal from AICI for a variety of work in the HQ facility
    (R4, tab 128). AICI submitted an original and then a revised proposal (R4, tabs 84,
    92). The parties engaged in negotiations but ultimately were unable to agree upon a
    final price for the work (GSMF ,i 8; app. reply to GSMF ,i 8).
    10. Neither party has directed the Board to any extrinsic evidence indicating
    that the parties discussed or contemplated remission of the previously withheld
    liquidated damages as part of the modification for the RFP-0007 work.
    11. After the conclusion of these negotiations, on 11 March 2016, the CO
    issued unilateral Modification No. POOOl 1 for $168,710. The modification required
    AICI to do the following in the HQ facility: add cooling in the server and operations
    room; add a security grill in Room 204; remove a window in Room 102; and modify
    cabinets in Room 208. Modification No. POOO 11 contained the following language:
    4
    The parties have not explained why the liquidated damages assessment began slightly
    later than the completion dates identified above (see ASUMF ,i 1; GSMF ,i 3).
    One explanation is that the contract also provided for completion within 395
    and 425 days for the HQ and FSU/FLS facilities, respectively, after receipt of
    the notice to proceed (on 7 February 2014) (see R4, tab 8 at 32, tab 23).
    3
    The Period of Performance has increased for CLIN 0004
    for a period of two-hundred-thirty-two (232) days from the
    effective date ofthis modification of March 11, 2016. This
    results in a Period of Performance end date of October 29,
    2016. This Period of Performance covers work under this
    modification only, not for the overall contract.
    (ASUMF ,r 8; GSMF     ,r 8; app. reply to GSMF ,r 8; R4, tab   19 at 2)
    12. Modification No. P00012 extended the completion date a further 59 days.
    It stated:
    [T]he Period of Performance is extended for the work
    under modification POOO 11 on CLIN 0004 from October
    29, 2016 to December 27, 2016. This Period of
    Performance covers work under modification POOOl 1 only,
    the Period of Performance for the overall contract remains
    unchanged.
    (ASUMF ,r 9; GSMF ,r 9; gov't resp., attach. 4 at 5-6)
    13. AICI completed the Modification Nos. POOOl land P00012 work prior to
    the 27 December 2016 deadline (ASUMF ,r 10; GSMF ,r 10).
    14. On 6 September 2016, AICI submitted an uncertified claim to the CO
    seeking return of the liquidated damages. AICI contended, among other things, that by
    issuing Modification Nos. POOOl 1 and P00012, the Corps could no longer assess
    liquidated damages based on a superseded completion date. AICI also contended that,
    even if these modifications did not extend the contract completion date, there was no
    contractual basis for the assessment of one-half of the liquidated damages for failure to
    complete the HQ facility in March 2015, nor was there any basis for assessment after
    18 May 2015, the date on which it contends it reached substantial completion. (R4,
    tab 3)
    15. The CO issued a final decision on 7 November 2016 (R4, tab 2). She
    rejected AICI's main argument that the government could not assess liquidated
    damages before the completion dates established by Modification Nos. POOOl l and
    P00012 (id. at 6-7). She also disagreed with AICI's contention that it reached
    substantial completion on 18 May 2015 because she found that it did not complete
    testing and balancing ofthe HVAC system until 28 May 2015 (id. at 6). But the CO
    agreed with AICI' s alternate argument that there was no provision in the contract that
    allowed for the assessment of half liquidated damages because the contract established
    only one rate. She ordered the release of $31,811 in liquidated damages. (Id. at 7-8)
    4
    16. It is not clear how the CO calculated the $31,811. This amount is equal to
    26 days at $1,223.50. However, it appears that the Corps actually withheld 30 days of
    liquidated damages at $1,223.50, which would total $36,705 (see SOF 116-7).
    17. After AICI filed a timely appeal docketed as 
    ASBCA No. 60948
    , it
    submitted to the CO a claim certification dated 23 March 2017 (R4, tab 164). The CO
    again denied the claim on 19 April 2017 (R4, tab 165). AICI then filed a second
    appeal docketed as 
    ASBCA No. 61166
    .
    DECISION
    AICI moves for summary judgment on the ground that, as a result of
    Modification Nos. POOOl 1 and P00012, the government could not assess liquidated
    damages before the revised 27 December 2016 completion date. Because AICI
    completed the work prior to this date, it seeks remission of all liquidated damages
    previously withheld by the government. (App. mot. at 1-2) In its cross-motion, the
    government essentially contends that Modification Nos. POOOI 1 and P00012 had no
    effect on the liquidated damages it had already withheld.
    Summary judgment is appropriate when there is no genuine issue of material
    fact and the moving party is entitled to judgment as a matter of law. Anderson v.
    Liberty Lobby, Inc., 
    477 U.S. 242
    , 247-48 (1986). When considering a motion for
    summary judgment, the Board's function is not to weigh the evidence and determine
    the truth of the matter but to determine whether there is a genuine issue for trial. 
    Id. at 249
    . Conclusory statements and mere denials are not sufficient to ward off
    summary judgment. Mingus Constructors, Inc. v. United States, 
    812 F.2d 1387
    ,
    1390-91 (Fed. Cir. 1987). The fact that both parties have moved for summary
    judgment does not mean that the Board must grant judgment as a matter of law for one
    side or the other. Rather, the Board must evaluate each party's motion on its own
    merits, taking care in each instance to draw all reasonable inferences against the party
    whose motion is under consideration. 
    Id. at 1391
    .
    We start with the plain language of the contract, which we must interpret to
    give reasonable meaning to all its parts. Gardiner, Kamya & Assocs., P. C. v. Jackson,
    
    467 F.3d 1348
    , 1353 (Fed. Cir. 2006). We may not use extrinsic evidence to change
    the terms of a contract that are clear on its face. Interwest Construction v. Brown,
    
    29 F.3d 611
    ,615 (Fed. Cir. 1994).
    We first consider whether the government under any circumstances could have
    added work to the contract in March of 2016 while retaining liquidated damages it had
    already withheld. We conclude that it is possible because the incorporated
    FAR 52.211-13 clause allows the CO to grant a time extension "only for those specific
    5
    elements related to the changed work" and provide "that the remaining contract
    completion dates for all other portions of the work will not be altered."
    AICI contends that FAR 52.211-13 cannot be relied upon to authorize the
    Corps' actions because FAR 11.503(c) provides that the clause "should be used only
    when the liquidated damages clause of FAR 52.211-12 has been revised to state the
    amount of liquidated damages for delay of each separate part or stage of the work"
    (app. mot. at 8-9). This is inaccurate. While FAR 11.503(c) requires the insertion of
    FAR 52.211-13 when the liquidated damages clause has been revised to reflect
    different liquidated damages amounts for the various stages of the work, it does not
    prohibit its use in other circumstances.
    Sundt Construction, Inc., 
    ASBCA No. 57358
    , 
    11-1 BCA 134,772
    , ajf'd,
    
    469 F. App'x 916
     (Fed. Cir. 2012), is an example of an appeal where the government
    modified the contract to add time to a discrete aspect of the project but retained
    liquidated damages already withheld. The Sundt contract required the construction
    of a number of housing units and contained a liquidated damages clause that provided
    for separate liquidated damages assessments for late completion of the project and
    for each individual housing unit. 
    Id. at 171,115
    . One of the units was subject to
    government-requested changes and the parties entered into a bilateral modification that
    extended the completion date for that unit only. 
    Id. at 171, 116-17
    . When the contractor
    later challenged the assessment of liquidated damages prior to completion of the
    changed unit, we denied the appeal based on the language in the bilateral modification,
    which we read to preserve liquidated damages that had already been assessed. 
    Id. at 171, 118-19
    .
    The second question then is whether the government in this appeal added time
    and work to the contract but preserved already assessed liquidated damages. We
    conclude that it did so because, read as a whole, Modification No. POOO 11 clearly
    carved out a separate completion date for the new work while preserving liquidated
    damages already assessed. We focus on the three sentences of the paragraph granting
    the time extension. Read in isolation, the first sentence would suggest that the time
    extension was for all of CLIN 0004 (the HQ facility): "The Period of Performance has
    increased for CLIN 0004 for a period of two-hundred-thirty-two (232) days" (SOF
    111). But the final sentence of the paragraph clarifies that "[t]his Period of
    Performance covers work under this modification only, not for the overall contract"
    (id.). Elsewhere, the modification identifies four discrete pieces of work, all in the HQ
    facility. Thus, the time extension paragraph of Modification No. POOOl 1 does nothing
    more than carve out a separate completion date for the discrete work items added by
    the modification, while maintaining the completion date for the bulk of the work under
    CLIN 0004. Modification No. P00012, which contained similar language as POOOl 1,
    does not change this analysis.
    6
    AICI contends in its motion that "[b]y issuing Modification Nos. POOO 11 and
    POOO 12, the Government effectively changed the contract completion date for all
    work" (app. mot. at 2). We disagree. Appellant's interpretation would read the
    sentence "[t]his Period of Performance covers work under this modification only, not
    for the overall contract" out of the contract, or render the modified contract internally
    contradictory, which is inconsistent with the rules of contract interpretation. Gardiner,
    
    467 F.3d at 1353
    .
    Because the contract is clear there is no reason for us to resort to extrinsic
    evidence. However, the Court of Appeals for the Federal Circuit has used extrinsic
    evidence to confirm its determination that the language of a modification was clear.
    Gardiner, 
    467 F.3d at 1354
    . In Gardiner, the Court of Appeals held that a
    modification clearly did not provide for a retroactive pricing adjustment. The Court
    nevertheless examined the negotiating history of the modification and found the
    silence to be telling:
    [I]t seems inconceivable that the parties would have agreed
    to retroactive pricing without making that intent explicit
    either during the negotiations leading to the agreement or
    in the agreement itself. Since they did neither, we
    conclude that even if there were an ambiguity in the
    language, it should be resolved in favor of the
    government's position.
    
    Id.
    So too here. Under these facts, specifically, where the contractor completed the
    work and demobilized from the site before the government issued an RFP for a
    relatively small amount of work, it is inconceivable to us that the government would
    simply forgive liquidated damages, except perhaps as consideration for the additional
    work. If the parties had contemplated this, we would expect to see it documented in
    either the negotiation history or the modification itself. It is not in the modification
    and neither party has directed us to any such negotiation history (see SOF ,i 10).
    Finally, the cases that AICI cites do not lead to a different result. Abcon
    Associates, Inc. v. United States, 
    49 Fed. Cl. 678
     (2001) is based on some facts similar
    to the present matter but its differences ultimately are more important. In Abcon, the
    contract provided for separate completion dates for phases 1a, 1b, and 2, but just as in
    this appeal the contract did not specify unique liquidated damages amounts for failure
    to complete on each of these dates. Nevertheless, the CO, also like the CO here, began
    assessing liquidated damages when the first of these dates passed. 
    Id. at 688
    . The
    Court of Federal Claims held that this assessment was not authorized by the contract.
    
    Id. at 689
    . But in this appeal the CO conceded this point in her final decision
    7
    (SOF ,r 15). A more fundamental difference is that in Abcon ther~ was nothing like
    Modification No. POOO 11 where the government attempted to carve out a separate
    completion date for a small subset of new work. Thus, we do not have the benefit of
    any analysis by the Court of Federal Claims on the central issue in this appeal.
    Schuster Engineering, Inc., 
    ASBCA No. 28760
     et al., 87-3 BCA ,r 20,105, also
    does not support appellant's position. The salient point in that very long opinion boils
    down to this: if it is impossible to complete the work by the contract completion date,
    the government cannot assess liquidated damages based on that impossible completion
    date. We held that by requiring the contractor to complete the work, the government
    effectively changed the completion date until ali the work could be completed. 
    Id. at 101,798-99
    . Accordingly, because Schuster involved the original contract work, we
    conclude it does not speak to the work added after contract completion in this appeal.
    CONCLUSION
    AICI's motion for summary judgment is denied. We grant the government's
    motion exeept as to the period from 19-28 May 2015 for which there is a material
    dispute of fact as to whether appellant had completed the work (SOF ,r 8) and with
    respect to the precise amount of liquidated damages to be remitted due to the CO's
    concession on one-half liquidated damages days (SOF ,r 16).
    The parties shall submit a joint status report four weeks from the date of this
    opinion proposing further proceedings.
    Dated: 29 May 2018
    tyY)   ~co.
    MICHAEL N. O'CONNELL
    (9   'GJi         '
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur
    RICHARD SHACKLEFORD                                0
    Administrative Judge                               Administrative Judge
    Acting Chairman                                    Vice Chairman
    Armed Services Board                               Armed Services Board
    of Contract Appeals                                of Contract Appeals
    8
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA Nos. 60948, 61166, Appeals of
    American International Contractors, Inc., rendered in conformance with the Board's
    Charter.
    Dated:
    JEFFREYD. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    9
    

Document Info

Docket Number: ASBCA No. 60948, 61166

Judges: O'Connell

Filed Date: 5/29/2018

Precedential Status: Precedential

Modified Date: 6/11/2018