Lael Al Sahab & Co. ( 2014 )


Menu:
  •                 ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeals of --                               )
    )
    Lael Al Sahab & Co.                         )      ASBCA Nos. 58344, 59009
    )
    Under Contract No. W91GFC-07-M-0399         )
    APPEARANCE FOR THE APPELLANT:                      Mr. Alie Sufan
    Owner
    APPEARANCES FOR THE GOVERNMENT:                    Raymond M. Saunders, Esq.
    Army Chief Trial Attorney
    CPT Vera A. Strebel, JA
    Erica S. Beardsley, Esq.
    Trial Attorneys
    OPINION BY ADMINISTRATIVE JUDGE MELNICK ON THE GOVERNMENT'S
    MOTIONS TO DISMISS FOR LACK OF JURISDICTION
    In these appeals, Lael Al Sahab & Co. (Lael Al Sahab) seeks payment for the
    government's alleged use of an additional truck not contemplated in the contract. The
    government moves to dismiss the appeals for lack of jurisdiction.
    STATEMENT OF FACTS (SOF) FOR THE PURPOSES OF THE MOTIONS
    1. The Army MNF-1/Regional Contracting Center (Al-Taji) awarded Contract
    No. W91GFC-07-M-0399 to Lael Al Sahab on 18 April 2007. Under the contract,
    appellant was to provide various motor vehicles for 6 month leases. Contract Line Item
    Number (CLIN) 0004 was for the lease of 11 small pickup trucks at a price of $1,800 per
    truck per month. The government had the option to extend the term of the contract for an
    additional six months. (R4, tab 1 at 1-2, 8 of 11)
    2. Lael Al Sahab was to deliver the vehicles to Camp Taji, Iraq. Lael Al Sahab
    was required to submit a Vehicle Inspection and Receiving Report (VIRR) for each
    vehicle prior to delivery. The VIRRs included identifying information for each vehicle
    and were to be signed by the receiving official. (R4, tab 1 at 4 of 11)
    3. Lael Al Sahab was required to submit invoices on a monthly basis to the
    end-user and the contracting officer (CO). Upon receipt of the invoice, the end-user was
    to prepare a Material Inspection and Receiving Report, Form DD250, and provide a copy
    to the CO within 48 hours. The contracting office would then prepare the appropriate
    payment package for the finance office. (R4, tab 1 at 5-6 of 11)
    4. The contract incorporated by reference FAR 52.212-4, CONTRACT TERMS AND
    CONDITIONS - COMMERCIAL ITEMS (SEP 2005) (R4, tab 1 at 8 of 11 ). Paragraph ( d) of
    FAR 52.212-4 stated that the contract was subject to the Contract Disputes Act of 1978
    (CDA), as amended.
    5. Beginning in May 2007, Lael Al Sahab delivered numerous vehicles required
    under the contract. The vehicles were identified on the VIRRs by make, model, and
    chassis number. (R4, tabs 2, 3, 6, 8, 12) 1
    6. In a 12 August 2007 email, appellant stated that the government had 12 pickup
    trucks (R4, tab 19). Appellant again referenced an extra pickup truck and a 12th pickup
    truck in two 15 October 2007 emails to the government (R4, tabs 22, 23).
    7. Modification No. P00003 extended the term of the contract through
    21 December 2007 (R4, tab 26). The government returned the leased vehicles to
    Lael Al Sahab by 8 January 2008 (R4, tabs 32, 34).
    8. The record contains appellant's monthly invoices for the lease of the vehicles
    from 22 May 2007 through 8 January 2008. The invoices identify the specific vehicles
    by type and chassis number. All of the monthly invoices reference 11 pickup trucks.
    (R4, tabs 15, 18, 20 2, 21, 24, 25, 28, 31) Of the chassis that became an issue, (see SOF
    iJ 14) only chassis no. 53831 appears on the invoices.
    9. By email dated 14 January 2008, appellant notified CO Tracy A. Stoughton
    that "your unit been using an extra pick up for 5 months (the contract was for 11 small
    Pick up)." 3 Appellant also stated that it was preparing an invoice. The hard copy of the
    email in the record contains handwritten notes asking: "Who told him to send this xtra
    vehicle? Did MAJ Holmes know about vehicle?" (R4, tab 32)
    10. In a 20 January 2008 email to CO Stoughton, appellant stated that it was
    "sending our Invoice for the Vehicle rent until the 8th on Jan." Appellant attached two
    documents to the email. Handwritten notes on the hard copy of the email identify one of
    the documents as relating to "Extra Vehicle $9,240.00." (R4, tab 33) The record
    contains a copy of Invoice No. 2005CCIE-N00798, which is dated 20 January 2008 and
    addressed to CO Stoughton. The invoice contained the following description: "Extra
    Pick up been used for 5ive month Chassi no 53831 (the contract was for 11 small pick
    1
    The VIRRs in the record do not necessarily represent all vehicles leased under the
    contract.
    2
    The invoice at Rule 4, tab 20 is largely illegible, but it looks like 11 pickup trucks are
    listed.
    3
    Syntax and punctuation are in original quotes.
    2
    up)." The invoice sought payment of $9,240.00 for the use of the alleged extra pickup
    truck for 154 days at a rate of $60 per day. (R4, tab 37) We conclude that this invoice
    was submitted to CO Stoughton with appellant's 20 January 2008 email.
    11. In a 20 January 2008 email to MAJ Holmes regarding the contract,
    CO Stoughton stated: "There is also the issue of an 'extra vehicle' that I'm very
    displeased with" (R4, tab 34). In a subsequent email the same day to appellant, with
    copy to MAJ Holmes, CO Stoughton wrote:
    This is regarding the issue of the "extra vehicle". I need to
    know from the both of you:
    --Why you gave us an extra vehicle
    --Who from the contracting office authorized this extra
    vehicle--How long the customer has known they've had this
    extra vehicle
    As it stands right now, if nobody from the contracting office
    authorized this extra vehicle, then you are not authorized
    payment for this extra vehicle.
    (R4, tab 35) Appellant responded the same day stating that the government knew about
    the extra pickup truck (R4, tab 36).
    12. By email dated 10 September 2012, a contract specialist with the Army
    Contracting Command - Rock Island contacted appellant and requested that it execute a
    release of claims "certifying that the contract has been paid in full." Appellant responded
    by email dated 11 September 2012 stating: "As you can see we had an extra vehicle they
    used for 5 months but they did not pay us .... " (R4, tab 42) Appellant resubmitted Invoice
    No. 2005CCIE-N00798 on 21 September 2012 (58344, gov't mot., Wysoske aff. ii 5).
    13. CO Joan Wysoske issued a 29 September 2012 contracting officer's final
    decision regarding Invoice No. 2005CCIE-N00798 in which she "recommend[ed]" that
    the invoice not be paid because the pickup truck with chassis no. 53831 had been listed
    on previous invoices that had been paid in full. She concluded that appellant had "failed
    to provide appropriate documentation for additional payment." (R4, tab 44 at 1)
    14. Appellant appealed by email dated 2 October 2012, which the Board docketed
    as ASBCA No. 58344. Along with its notice of appeal, appellant submitted a revised
    copy of Invoice No. 2005CCIE-N00798. As with the previous version, the revised copy
    sought $9,240 for the use of an extra pickup truck for 154 days. The revised invoice,
    however, referenced chassis no. 003326 instead of chassis no. 53831. The revised
    invoice also included an additional demand of $150,000 as a "Claim for delay and not
    pay us on time for almost 5 years."
    3
    15. By motion dated 19 February 2013, the government moved to dismiss
    ASBCA No. 58344, arguing that appellant had failed to submit a claim to the CO.
    Appellant responded to government trial counsel and the Board by letter dated 25 April
    2013 explaining when and how the government was provided an extra truck.
    16. By email dated 24 May 2013, appellant submitted a second letter dated
    25 April 2013, addressed to government counsel but also sent to the Board, stating:
    I felt I was unfair with my claim. As you know and it is very
    clear I have outstanding Balance for the extra vehicle amount
    $9250 where I claimed for this amount since 2007. If you
    don't wish to consider my claim but at least I can accept to
    get paid my balance due Since four years.
    By this letter it appears appellant may have withdrawn the $150,000 demand for delay in
    payment (see SOF ~ 14) from ASBCA No. 58344.
    17. In a 28 June 2013 Order, the Board noted that the issues raised in the
    government's motion to dismiss ASBCA No. 58344 might be resolved, without a
    decision on the motion, if appellant were to submit a claim to the CO meeting the
    requirements of the CDA and file a new appeal should the claim be denied or deemed
    denied by the government. The Board therefore directed appellant to indicate whether it
    would attempt to submit a claim to the CO.
    18. By email to the Board dated 5 July 2013, appellant submitted multiple
    documents in apparent response to the Board's Order. Among the documents submitted
    by appellant was a third copy of Invoice No. 2005CCIE-N00798. Like the copy
    submitted with appellant's notice of appeal in ASBCA No. 58344, this copy of the
    invoice sought $9 ,240 for the use of an extra pickup truck for 154 days and referenced
    chassis no. 003326; however it omitted the $150,000 demand. This third copy of the
    invoice was also signed by appellant's representative, and included the following
    statement: "the claim is made in good faith; the supporting data are accurate and
    complete."
    19. By reply dated 26 August 2013, the government renewed its motion to
    dismiss, arguing that appellant's three invoices were three substantively different routine
    requests for payment, not claims under the CDA (58344, gov't reply at 3).
    20. In a 9 October 2013 Order, the Board directed appellant, to the extent it
    considered its 5 July 2013 submission to be a claim, to notify the Board whether it
    intended to file a new appeal based upon the submission.
    4
    21. In response, appellant submitted a 15 October 2013 letter to the Board and
    government counsel in which it stated that it "would Like to claim for my outstanding
    Due Payment since 2008 for the amount $9,240" (ASBCA No. 59009, notice of appeal).
    The Board determined that the letter was a notice of appeal, and docketed the matter as
    ASBCA No. 59009 and consolidated it with ASBCA No. 58344.
    22. By motion dated 24 February 2014, the government moved to dismiss
    ASBCA No. 59009, arguing that appellant's 15 October 2013 letter was not a claim
    because it was not submitted to the CO (59009, gov't mot. at 3). Appellant did not
    respond to the government's motion despite two opportunities to do so.
    DECISION
    Appellant, as the proponent of the Board's jurisdiction, bears the burden of
    establishing jurisdiction by a preponderance of the evidence. Hanley Indus., Inc.,
    ASBCA No. 58198, 14-1BCAii35,500 at 174,015. The facts supporting jurisdiction are
    subject to our fact-finding upon a review of the record. Raytheon Missile Sys., ASBCA
    No. 58011, 13 BCA ii 35,241 at 173,016; Green Dream Grp., ASBCA No. 57413 et al.,
    12-2 BCA ii 35,145 at 172,520.
    The Board's jurisdiction under the CDA is dependent upon the contractor's
    submission of its claim to the CO and a final decision on, or the deemed denial of, the
    claim. 41 U.S.C. §§ 7103-7105; Mawaraa AlBihar Co., ASBCA No. 58585, 13 BCA
    ii 35,426 at 173,783. Because the CDA does not define the term "claim," we look to the
    definition in the FAR. See, e.g., Taj Al Safa Co., ASBCA No. 58349, 13 BCA ii 35,278
    at 173,158. The FAR defines a "Claim" as follows:
    Claim means a written demand or written assertion by
    one of the contracting parties seeking, as a matter of right, the
    payment of money in a sum certain, the adjustment or
    interpretation of contract terms, or other relief arising under
    or relating to the contract.... A voucher, invoice, or other
    routine request for payment that is not in dispute when
    submitted is not a claim. The submission may be converted
    to a claim, by written notice to the contracting officer as
    provided in 3 3 .206( a), if it is disputed either as to liability or
    amount or is not acted upon in a reasonable time.
    FAR 2.10 I. A claim need not be submitted in any particular format; the contractor need
    only submit "a clear and unequivocal statement that gives the contracting officer
    adequate notice of the basis and amount of the claim." Contract Cleaning Maint., Inc. v.
    United States, 
    811 F.2d 586
    , 592 (Fed. Cir. 1987). We determine whether a contractor's
    communication is a CDA claim on a case-by-case basis and apply a common sense
    5
    analysis. Todd Pac. Shipyards Corp., ASBCA No. 55126, 06-2 BCA i133,421 at
    165,687. In determining the sufficiency of a claim, we may examine the totality of the
    correspondence between the parties. Vibration & Sound Solutions Ltd., ASBCA
    No. 56240, 09-2 BCA i134,257 at 169,270.
    ASBCA No. 58344
    The government moves to dismiss ASBCA No. 58344 for lack of jurisdiction on
    the ground that appellant failed to submit a proper CDA claim. In its original motion, the
    government merely states that there "is no record that appellant filed a claim prior to
    filing a notice of appeal or complaint with the Board" (58344, gov't mot. at 2). The
    government elaborates in its reply, contending that appellant's invoices are mere routine
    requests for payment that do not rise to the level of CDA claims (58344, gov't reply at 3).
    Whether a request for payment is a routine or a non-routine request is a factual
    question dependent on the circumstances in which the request arose. Parsons Global
    Servs., Inc. ex rel. Odell Int'!, Inc. v. McHugh, 
    677 F.3d 1166
    , 1170 (Fed. Cir. 2012).
    Routine requests for payment are those "submitted for work done or equipment delivered
    by the contractor in accordance with the expected or scheduled progression of contract
    performance." James M Ellett Constr. Co. v. United States, 
    93 F.3d 1537
    , 1542 (Fed.
    Cir. 1996). Non-routine requests for payment, by contrast, seek compensation "for
    unforeseen or unintended circumstances." Reflectone, Inc. v. Dalton, 60 F .3d 1572, 1577
    (Fed. Cir. 1995) (en bane). Although FAR 2.101 identifies invoices as examples of
    routine requests for payment, that a contractor submitted its request for payment as an
    invoice is not dispositive. See RO. Vl.B. Sri, ASBCA No. 56198, 09-1 BCA i134,068
    at 168,457 (finding invoices to be claims); Am. Serv. & Supply, Inc., ASBCA No. 50606,
    00-1BCAi130,858 at 152,335 ("In light of these facts, Invoice No. 1345 could not be
    considered a routine request for payment"). A common thread of non-routine requests
    for payment "is the presence of some unexpected or unforeseen action on the
    government's part that ties it to the demanded costs." Kellogg Brown & Root Servs., Inc.,
    ASBCA No. 58492, 14-1BCAi135,713 at 174,866-67 (quoting 
    Parsons, 677 F.3d at 1171
    ).
    Under CLIN 0004 of the contract, Lael Al Sahab was required to provide the
    government 11 small pickup trucks for lease (SOF i-11 ). The contract required Lael Al
    Sahab to invoice on a monthly basis (SOF i13). Appellant's monthly invoices reference
    only 11 pickup trucks (SOF i18). By email dated 14 January 2008, appellant notified
    CO Stoughton that the government had used an extra truck for 5 months, noting that the
    contract was only for 11 trucks (SOF i19). Less than a week later, appellant submitted
    Invoice No. 2005CCIE-N00798 to CO Stoughton seeking $9,240.00 as compensation for
    the government's use of an extra pickup truck for 154 days (SOF i-110). The invoice
    sought payment for the provision of a pickup truck not contemplated by the contract.
    CO Stoughton's 20 January 2008 response, inquiring as to who authorized the extra
    6
    vehicle (SOF ~ 11 ), recognized the non-routine nature of appellant's request. Therefore,
    Invoice No. 2005CCIE-N00798 was not a routine request for payment.
    The invoice also otherwise meets the definition of a claim. The invoice is a
    written demand seeking, as a matter of right, the payment of money in a sum certain. See
    
    Reflectone, 60 F.3d at 1575
    . Invoice No. 2005CCIE-N00798 is similar to the letter in
    Tecom, Inc. v. United States, which the court determined met the requirements of a claim.
    
    732 F.2d 935
    , 937 (Fed. Cir. 1984) ("[The letter] first reiterated that appellant viewed the
    newly demanded bus service as beyond the contract's requirements, and then specifically
    asked 'compensation of $11,000.04 per year, to be billed at $916.67 per month.' That
    was quite enough specificity for the claim, under both statute and regulation.").
    CO Wysoske treated Invoice No. 2005CCIE-N00798 as a claim and issued a final
    decision thereon (SOF ~ 13).
    Appellant, however, does not pursue the claim presented to the COs in this appeal.
    As submitted to CO Stoughton and CO Wysoske, Invoice No. 2005CCIE-N00798 cited
    chassis no. 53831 (SOF `` 10, 12-13). On appeal, however, appellant's submissions to
    the Board refer to a truck with chassis no. 003326 (SOF ~ 14). "We lack jurisdiction over
    claims raised for the first time on appeal, in a complaint or otherwise." The Pub.
    Warehousing Co., ASBCA No. 56022, 11-2 BCA ~ 34,788 at 171,227. "Whether a claim
    before the Board is new or essentially the same as that presented to the CO depends upon
    whether the claims derive from common or related operative facts." Dawkins Gen.
    Contractors & Supply, Inc., ASBCA No. 48535, 03-2 BCA ~ 32,305 at 159,844. If the
    Board "will have to review the same or related evidence to make its decision, then only
    one claim exists." Placeway Constr. Corp. v. United States, 
    920 F.2d 903
    , 907 (Fed. Cir.
    1990). Appellant's reliance on a different chassis number on appeal introduces a
    different, unrelated material operative fact not presented to the COs. Each vehicle
    provided by Lael Al Sahab was accompanied by separate documentation identifying the
    vehicle by, inter alia, chassis number (SOF `` 2, 5). Lael Al Sahab's monthly invoices
    similarly identified the specific trucks for which it sought payment by chassis number
    (SOF ~ 8). Determining whether appellant is entitled payment for the provision of an
    allegedly extra truck requires a review of the documentation related to the specific truck.
    Appellant's claim as to chassis no. 003326 is therefore a different claim than its claim as
    to chassis no. 53831. Its claim for chassis no. 53831 was denied because it had been
    listed on prior invoices that had been paid (SOF ~ 13). Appellant has not pursued its
    claim as to chassis no. 53831 on appeal, and we consider it abandoned. Put simply,
    whether appellant was paid for chassis no. 003326 involves different operative facts than
    whether it was paid for chassis no. 53831. Because appellant did not submit its claim as
    to chassis no. 003326 to a CO prior to its appeal to the Board, we lack jurisdiction to
    entertain it.
    7
    While appellant may have withdrawn its demand for $150,000 from this appeal
    (SOF ii 16), there is no evidence that appellant submitted its $150,000 demand to a CO
    prior to its appeal to the Board. Accordingly, we also dismiss this portion of the appeal.
    ASBCA No. 59009
    ASBCA No. 59009 arises from appellant's 5 July 2013 submission. The
    government moves to dismiss ASBCA No. 59009 for lack of jurisdiction, arguing that
    appellant failed to submit a claim to the CO (59009, gov't mot. at 3).
    The Board's 28 June 2013 Order informed the parties that appellant might be able
    to resolve the issues raised in the government's motion to dismiss ASBCA No. 58344 by
    filing a claim with the CO (SOF ii 17). Although appellant knew the identity of the
    current CO, appellant did not file a claim with CO Wysoske. Appellant's 5 July 2013
    submission to the Board cannot substitute as a submission to the CO. Appellant's failure
    to submit a claim to the CO as required by the CDA deprives us of jurisdiction. Bruce E.
    Zoeller, ASBCA No. 55654, 07-1 BCA ii 33,581 at 166,347. We therefore also dismiss
    ASBCA No. 59009.
    CONCLUSION
    The government's motions to dismiss for lack of jurisdiction are granted.
    Dated: 13 November 2014
    ~l&f:/l
    MARKAMELNICK
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                         I concur
    ``
    Administrative Judge
    RICHARD SHACKLEFORD
    Administrative Judge
    Acting Chairman                                  Vice Chairman
    Armed Services Board                             Armed Services Board
    of Contract Appeals                              of Contract Appeals
    8
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    J\.nned Services Board of Contract J\.ppeals in J\.SBCJ\. Nos. 58344, 59009, J\.ppeals of
    Lael J\.l Sahab & Co., rendered in confonnance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    R..ecorder, J\.nned Services
    Board of Contract J\.ppeals
    9