Tokyo Company ( 2015 )


Menu:
  •                  ARMED SERVICES BOARD OF CONTRACT APPEALS
    Petition of --                                )
    )
    Tokyo Company                                 )      ASBCA No. 59709-953
    )
    Under Contract No. W90U3Z-08-M-803 l          )
    APPEARANCE FOR THE PETITIONER:                       Mr. Beniamen Monadhil
    Owner/General Manager
    APPEARANCES FOR THE GOVERNMENT:                      Raymond M. Saunders, Esq.
    Army Chief Trial Attorney
    CPT Melvin A. Lee, JA
    Trial Attorney
    ORDER PURSUANT TO BOARD RULE l(a)(5)
    DIRECTING CONTRACTING OFFICER TO ISSUE DECISION
    Pursuant to Board Rule l(a)(5), Tokyo Company petitions the Board to direct
    the contracting officer (CO) to issue a decision on its 12 May 2014 claim. In response,
    the government requests that it not be ordered to do so, asserting it already has issued a
    final decision. The government also argues petitioner lacks privity of contract and
    thus a new final decision is not warranted.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE PETITION
    1. By email dated 27 November 2014, Tokyo Company filed the instant
    petition, stating the CO "does not send me his decision on this case," and listing
    several dates that petitioner's owner, Mr. Beniamen Monadhil, purportedly sent emails
    to named individuals at the Reachback Contracting Command at Rock Island, Illinois.
    Petitioner listed dates from 8 May 2014 to 11November2014, and indicated he
    received a response from only one inquiry, dated 14 May 2014. Petitioner's email
    request to the Board contained numerous attachments, including what appears to be a
    contract and modifications, a 15 February 2010 invoice for $920,602, and a signed
    claim certification dated 9 May 2014.
    2. By Order dated 3 December 2014, the Board directed the government to
    show cause why an order directing the CO to issue a final decision should not be
    issued or indicate when a decision would be issued.
    3. The government responded by letter dated 22 January 2015, requesting that
    it not be ordered to produce a new CO's final decision in this matter because a
    decision has already been issued by the CO on 11 September 2013 and attached a copy
    of the decision. Further, the government argued that
    [T]he government has serious doubts that a contract ever
    existed with the petitioner. A review of the government's
    contract retrieval and archival system shows that the
    subject contract was awarded, terminated, and closed out
    with an entirely separate company. There is no
    documentation within this system showing that the
    petitioner was awarded the subject contract or performed
    any work on the contract.... Since petitioner is not a
    contractor as defined by the CDA and lacks privity of
    contract with the government, a new contracting officer's
    final decision on this matter is not warranted.
    4. By Order dated 27 January 2015, the Board informed the government that
    the final decision dated 11 September 2013 was the subject of ASBCA No. 59059,
    which was dismissed by the Board on 23 April 2014 for Tokyo Company's failure to
    properly sign or execute its claim certification in accordance with the requirement of
    FAR 33.207(e). Tokyo Company, ASBCA No. 59059, 14-1BCAif35,590. The
    Board pointed out that "[i]t appears from the current record that petitioner is seeking a
    final decision on a different claim than the one at issue in ASBCA No. 59059."
    5. The Board further stated in the 27 January 2015 Order, it was unclear which
    documents attached to petitioner's 27 November 2014 email constituted the claim,
    whether the 9 May 2014 certification related to any particular claim, or if the
    certification or any claim was submitted to a CO. Petitioner was directed to provide:
    ( 1) a copy of the claim documents that it submitted to the CO, including any
    certification; (2) evidence that the claim and any certification were actually submitted
    to a CO; and (3) evidence of the date of claim submittal.
    6. By email dated 28 January 2015, petitioner responded to the 27 January
    2015 Order with the following:
    On 12 May 2014, Tokyo [C]ompany has submitted its
    claim as well as the signed Certification of Claims to the
    Contracting Officer, Andrea Kalb, Branch C Chief, Global
    Reachback Contracting Division, Army Contracting
    Command - Rock Island, CCRC-RC. She replied on
    14 May 2014 stating that "I have received your request."
    Copies of these e-mails are attached with this letter. After
    that we sent her several e-mails in different dates to remind
    her about our request because we did not receive any
    2
    update[.] Copies of these e-mails are also attached with
    this letter.
    7. Petitioner's documents indicate that on 12 May 2014, Mr. Monadhil
    submitted a claim via email to the CO, Andrea Kalb, Branch C Chief, Global
    Reachback Contracting Division, Army Contracting Command - Rock Island Arsenal,
    Illinois, stating, "The ASBCA has dismissed our appeal... the ASBCA lacks the
    jurisdiction because my claim certification lacks the required signature."
    Mr. Monadhil's 12 May 2014 correspondence included several attachments, listed
    seriatim in his cover email. These included a contract (no. 6), a 15 February 2010
    invoice for payment of $920,602 (no. 7), and a signed claim certification dated 9 May
    2014 (no. 12). In the last paragraph of his email, Mr. Monadhil appears to be asking
    the CO to reconsider her original decision because of what he calls "these new
    evidences and proofs."
    8. By email dated 14 May 2014, the CO responded to petitioner with the
    following:
    I have received your request. Please stop bombarding me
    with emails. I have 220,000 contracts to manage. Your
    actions are only making your case worse. I will review
    your information again. However, it is unlikely I will
    overturn a Contracting Officer decision.
    9. By email dated 4 June 2014, petitioner sent another email to the CO, which
    read:
    Ma'am,
    I just talked to you by phone, you advised me to go to
    ASBCA, but in order to do that, I need you to provide me
    with new final decision about this case, so I can submit my
    appeal on this final decision to ASBCA. I am waiting for
    your reply. Thanks.
    10. Petitioner provided copies of additional emails sent to the CO dated
    21August2014, 5 November 2014, 6 November 2014, 7 November 2014,
    10 November 2014 and 11 November 2014 requesting a response. There is no
    indication petitioner received anything further from the CO.
    11. In lieu of appealing from a deemed denial of its claim (41 U.S.C.
    § 7103(f)(5)), by email dated 27 November 2014, petitioner filed the instant petition
    before us pursuant to 41 U.S.C. § 7103(f)(4) and Board Rule l(a)(5).
    3
    DECISION
    When a CO receives a certified claim over $100,000, the Contract Disputes Act
    (CDA), 41 U.S.C. §§ 7101-7109, requires that within sixty days of receipt of the
    claim, the CO shall either (a) issue a decision or (b) notify the contractor of the time
    within which a decision will be issued. 41 U.S.C. § 7103(f)(2). In this instance, the
    CO acknowledged receipt of petitioner's documents by email dated 14 May 2014
    (SOF ii 8). To date, the CO has not issued a final decision on the 12 May 2014 claim.
    The government now argues it should not have to issue another final decision
    because it issued one dated 11 September 2013. Additionally, the government argues
    it should not have to issue a final decision because Tokyo Company is not in privity of
    contract with the government. (SOF ii 3)
    At the outset, we note the 11 September 2013 final decision in ASBCA
    No. 59059 was dismissed by the Board on 23 April 2014 because Tokyo Company
    failed to "properly sign or execute its claim certification in accordance with the
    requirement of FAR 33.207(e)" (SOF ii 4). Tokyo Company, 14-1BCAii35,590
    at 174,392. There, we held the lack of a signature on a certification is not a defect that
    can be cured under FAR 33.201, and the fact that the CO rendered a decision on the
    Tokyo Claim is inconsequential, citing Paul E. Lehman, Inc. v. United States, 
    673 F.2d 352
    , 356 (Ct. Cl. 1982), wherein the court stated, "The contracting officer... had no
    authority to waive a [certification] requirement that Congress imposed." The
    government should not be allowed to rely on a previous CO decision found to be
    inconsequential based on a jurisdictional defect to avoid issuing a decision now that
    the jurisdictional defect has been corrected.
    The government also argues that it should not have to issue a decision on what
    appears to be a properly certified claim because "the government has serious doubts
    that a contract ever existed with the petitioner." The government goes on, "Since
    petitioner is not a contractor as defined by the CDA and lacks privity of contract with
    the government," it should not be ordered to issue a new final decision. (SOF ii 3)
    The government is confusing the merits of petitioner's claim with the CO' s
    obligation to issue a decision. On 12 May 2014, petitioner submitted a properly
    certified claim to the CO (SOF ii 7). According to the CDA, 41 U.S.C. § 7103(d), the
    CO "shall issue a decision in writing and shall mail or otherwise furnish a copy of the
    decision to the contractor." The government's argument that it doubts the validity of
    Petitioner's alleged contract and should be entitled to refuse to issue a final decision
    ignores the decisions by the Board and courts that hold a contractor initially need only
    plead a valid contract, not prove it. "[T]he law is clear that, [for us] to have
    jurisdiction, a valid contract must only be pleaded, not ultimately proven." Dongbuk
    R&U Engineering Co., ASBCA No. 58300, 13 BCA ii 35,389 at 173,637 (quoting
    4
    Total Medical Mgmt, Inc. v. United States, 
    104 F.3d 1314
    , 1319 (Fed. Cir.), cert,
    denied, 
    522 U.S. 857
    (1997)); accord Engage Learning, Inc. v. Salazar, 
    660 F.3d 1346
    , 1353 (Fed. Cir. 2011); Lewis v. United States, 
    70 F.3d 597
    , 602, 604 (Fed. Cir.
    1995); Gould, Inc. v. United States, 
    67 F.3d 925
    , 929-30 (Fed. Cir. 1995). Tokyo
    Company has made a non-frivolous, assertion of an express contract with the
    government, and has provided copies of the alleged contract to the CO. The
    government's contention-that the government does not believe that a contract existed
    with this petitioner-is a challenge to the merits of the claim. As such, the CO may so
    state in her final decision if she decides to deny the claim. At this stage in the
    proceedings we do not decide the merits of petitioner's claim. See, e.g., Ironhorse
    Ltd., ASBCA No. 56455-920, 09-1BCAi!34,096 at 168,591.
    CONCLUSION
    For the reasons stated we direct the CO, pursuant to 41 U.S.C. § 7103(t)(4), to
    issue a decision no later than 30 days from the date of this decision.
    This Order completes all necessary action by the Board. If the CO fails to
    comply with this Order, such failure will be deemed a decision by the CO denying the
    claim and the contractor may appeal to this Board or sue in the United States Court of
    Federal Claims pursuant to 41 U.S.C. § 7103(f)(5) or§ 7104.
    Dated: 12 February 2015
    ~#
    Administrative Judge
    Acting Chairman
    Armed Services Board
    of Contract Appeals
    I concur                                             I concur
    ......
    ~--~
    RICHARD SHACKLEFORD
    Administrative Judge                                 Administrative Judge
    Vice Chairman                                        Armed Services Board
    Armed Services Board                                 of Contract Appeals
    of Contract Appeals
    5
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA No. 59709-953, Petition of
    Tokyo Company, rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals