Rex Systems Inc. ( 2016 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                   )
    )
    Rex Systems Inc.                               )       
    ASBCA No. 59624
    )
    Under Contract No. SPRMM1-12-P-YH36 )
    APPEARANCE FOR THE APPELLANT:                          Ms. Nicole L. Kornesczuk
    President
    APPEARANCES FOR THE GOVERNMENT:                        E. Michael Chiaparas, Esq.
    DCMA Chief Trial Attorney
    Kara M. Klaas, Esq.
    Trial Attorney
    Defense Contract Management Agency
    Chantilly, VA
    OPINION BY ADMINISTRATIVE JUDGE PROUTY
    In this appeal, we consider what compensation appellant, Rex Systems, Inc.
    (Rex), is entitled to for the government's termination of its contract for convenience.
    Although the contracting officer made an offer to settle Rex's termination costs, Rex
    alleges that the government imposed significant costs upon it through delay during the
    performance period and seeks payment of an amount greater than it would have been
    entitled to had the contract been completed in a timely manner. The parties also
    dispute Rex's entitlement to other components of its termination claim. For the most
    part, the government prevails, although Rex is entitled to some relief, as will be
    detailed below.
    The parties waived a hearing and submitted the case upon the record pursuant
    to Board Rule 11. We granted Rex's request to have the declaration of its corporate
    officer Nicole Komesczuk (which had been previously submitted in tab 9 of its
    supplement to the Rule 4 file) stand in for its opening brief, rather than requiring it to
    submit a more formal brief. Ms. Komesczuk also filed a reply brief. The government
    filed an opening brief, but did not file a reply, stating that it believed that its opening
    brief addressed all the issues raised in the Kornesczuk affidavit.
    FINDINGS OFF ACT
    1. On 2 August 2012, the Defense Logistics Agency (DLA) awarded to Rex
    Contract No. SPRMM1-12-P-YH36 (the contract) in the amount of$42,096 for the
    production of certain semiconductor devices (R4, tab 1). These devices were
    electronic assemblies utilized to support the MK-49, a Department of Defense legacy
    system and provided electro-magnetic pulse protection (app. supp. R4, tab 9, ~ 5, tab 6
    (provision of electro-magnetic pulse protection)). Rex had delivered the same
    assemblies for DLA in a previous contract (app. supp. R4, tab 9, ~ 10).
    2. The contract required first article testing prior to the delivery of the eight
    devices (R4, tab 1 at G-2). It thus included the following schedule:
    Submission of test procedures for first article and
    production lot items: 60 days after contract award.
    Approval oftest procedures: 120 days after contract
    award.
    Submittal of first article test sample and first article test
    report: 180 days after contract award.
    Approval of first article: 270 days after contract award.
    Shipment of production quantity and production lot test
    report: 360 days after contract award.
    (Id.)
    3. The contract also contained a number of standard Federal Acquisition
    Regulation (FAR) clauses, including FAR 52.213-4, TERMS AND CONDITIONS-
    SIMPLIFIED ACQUISITIONS (OTHER THAN COMMERCIAL ITEMS (OCT 2010), paragraph
    (f) Terminations clause (R4, tab lat G-18); and FAR 52.209-3, FIRST ARTICLE
    APPROVAL-CONTRACTOR TESTING (SEP 1989) (id. at G-20-21 ).
    4. Relevant here, the termination clause in FAR 52.213-4(f) provides, in part,
    that, upon notification of termination for the convenience of the government:
    [T]he Contractor shall immediately stop all
    work ... and ... cause ... all of its suppliers and subcontractors
    to cease work. Subject to the terms of this contract, the
    Contractor shall be paid a percentage of the contract price
    reflecting the percentage of the work performed prior to
    the notice of termination, plus reasonable charges that the
    Contractor can demonstrate ... have resulted from the
    termination.
    (See R4, tab 1 at G-18)
    2
    5. Also relevant to this matter, are two portions of the First Article Testing
    clause, FAR 52.209-3, the first of which provides in part:
    (b) The Contractor shall submit the first article test
    report within 180 calendar days from the date of this
    contract.... Within 90 calendar days after the Government
    receives the test report, the Contracting Officer shall notify
    the Contractor... ofthe conditional approval, approval, or
    disapproval of the first article ....
    ( f) If the Government does not act within the time
    specified in paragraph (b ) ... the Contracting Officer shall,
    upon timely written request from the Contractor, equitably
    adjust under the Changes clause of this contract the
    delivery or performance dates and/or the contract price,
    and any other contractual term affected by the delay.
    (R4, tab 1 at G-20)
    6. The second material portion of the First Article Testing clause, FAR 52.209-3(g),
    relates to recoverable costs and warns that:
    Before first article approval, the acquisition of materials or
    components for, or the commencement of production of,
    the balance of the contract quantity is at the sole risk of the
    Contractor. Before first article approval, the costs thereof
    shall not be allocable to this contract for ... termination
    settlements if the contract is terminated for the
    convenience of the Government.
    (R4, tab 1 at G-20-21)
    7. The contract also contained a standard Navy supplemental provision
    regarding pre-manufacturing test procedures (NAVSUPWSSIA05) further limiting the
    government's liability in a termination settlement for the contractor's acquisition of
    materials, which provided that:
    Prior to approval of [first article test procedures], the
    acquisition of materials or components for ... the contract
    items (including first article samples) shall be at the sole
    risk of the contractor, and costs incurred on account
    thereof shall not be allocable to this contract...for the
    3
    purpose of termination settlement if this contract is
    terminated for convenience of the Government prior to
    approval of the [first article test procedure].
    (R4, tab 1 at G-16)
    8. In light of its having furnished the same items to the government in an
    earlier contract, on 14 August 2012, Rex requested that the government waive the
    contract's first article testing requirement (app. supp. R4, tab 1, tab 9, if 15). On
    19 September 2012, the government denied this request (app. supp. R4, tab 1).
    9. Before receiving the government's response to the first article test waiver
    request, on 30 August 2012, Rex contacted a parts supplier (USI Electronics) and ordered
    the production materials (the diodes) necessary to construct the first article and the other
    seven semiconductor devices required by the contract (supp. R4, tab 24 at G-195-96).
    Rex's pre-bid estimate noted that the diodes required a 24-week lead time (R4, tab 23 at
    G-170-71 ). Nevertheless, the materials were requested for delivery on 15 October 2012,
    and were received by Rex on 24 September 2012 (id. at G-195-97). The cost of these
    items was $8,979 (id.).
    10. On 27 September 2012, Rex timely submitted its first article and
    production test procedures to the government for its approval (app. supp. R4, tab 2).
    11. Without waiting for government approval of its test procedures, on
    28 October 2012, Rex built the first article semiconductor device and conducted tests
    upon it (app. supp. R4, tab 5, see also tab 6 (photograph of completed semiconductor
    device)).
    12. The government did not approve the proposed testing procedures within
    120 days of contract award (or by 30 November 2012), as required by the contract.
    Rex contacted the government on 6 December 2012 and inquired about the status of
    the approval (app. supp. R4, tab 3 at 4). The contracting officer (CO) forwarded Rex's
    correspondence to the appropriate technical personnel for review and noted, in an
    email on 13 December 2012, that "we [the government] are in breach of the delivery
    schedule in the contract" (id. at 2).
    13. On 14 January 2013, a government technical representative contacted Rex and
    requested that Rex provide him with a technical data package for the contract items as
    well as a list of the drawings that had been provided in Rex's 27 September 2012
    submittal (app. supp. R4, tab 1 at 2, tab 9, if 17). He explained that his concern was that
    4
    Raytheon had changed some of the specifications in the six years since Rex last provided
    the semiconductor devices 1 (id.). This information was duly provided by Rex (id.).
    14. The government made a follow-up request to Rex for additional
    information regarding the drawings and specifications on 18 January 2013 (app. supp.
    R4, tab 4 at 4-5). When this request was forwarded by Rex's contract administrator to
    Rex's engineering personnel, Rex's founder and senior director, Mr. G. Rex Rathbun,
    became aware of it and decided that it was an inappropriate request (app. supp. R4,
    tab 9, ~ 18). Accordingly, on 23 January 2013 Mr. Rathbun sent a letter to the CO,
    complaining that the documents sought by the government on 14 January 2013 and
    provided by Rex that same date were proprietary, not required by the contract, and
    never should have been provided (app. supp. R4, tab 4 at 3-4). Mr. Rathbun further
    conveyed his view that, if the government felt that the specifications that it provided in
    the contract (and which Rex was following) were deficient and that it wished Rex to
    provide documents that would remedy that problem, it should do so by change order
    (id.). On the same date, Mr. Rathbun also sent a letter to the government technical
    personnel who had been involved in the technical conversation and informed them of
    his view that it was improper and beyond the scope of the contract (id. at 10-11).
    15. There was no written government response to these letters until 4 March
    2013 when the CO sent Rex a contract modification terminating the contract for
    convenience (app. supp. R4, tab 9, ~ 19). 2 This modification specified that the contract
    was being terminated, in full, pursuant to FAR 13.302-4 and FAR Part 49 (id.).
    16. The parties attempted to settle the termination costs, but were unsuccessful.
    In its termination settlement proposal dated 16 July 2014, Rex sought in total
    $57,381.50 (R4, tab 13 at G-79). On 1August2015, the government's termination
    contracting officer (TCO) offered $25,231.94 to Rex (supp. R4, tab 24 ). This
    $25,231.94 represents $24,614.08 for costs deemed allowable that were incurred in
    performing the contract prior to termination minus a $64.41 projected loss on those
    costs plus settlement expenses of $1,218.00 and minus disposal credits of$535.73 for
    the materials purchased to perform the contract (supp. R4, tab 24 at G-189-93).
    1
    The record is not particularly clear, but we believe the Raytheon specifications
    referenced involved the MK-49 legacy system for which the semiconductor
    devices were being built.
    2   The modification terminating the contract for convenience is dated 25 February 2013
    (R4, tab 3 at G-46). Whether this modification was provided to Rex on
    25 February or 4 March as alleged in the declaration provided by Rex (see app.
    supp. R4, tab 9, ~ 19) is of no material difference to the outcome of this appeal.
    Rex's internal records indicate that it was informed by telephone of the intended
    termination for convenience on 22 February 2013 (app. supp. R4, tab 1at2).
    5
    17. Although Rex did not agree to this lower government figure, it did invoice
    and collect that amount from the government (supp. R4, tab 25), thus, $32,149.56
    remains in contention here. We thus conclude, that on 1August2015, the parties were
    at an impasse with respect to Rex's termination settlement proposal and it ripened into
    a claim. Matters of dispute that remain to be resolved here were Rex's request for
    payment (minus a small credit for re-use) for the materials that were obtained for the
    entirety of the production of the contract, which the TCO disallowed as being
    precluded by the First Article Test clause; Rex's "'DELAY" damages, which the TCO
    found non-applicable; Rex's request for profit, which the TCO determined
    inapplicable because he believed that Rex would have lost money on the contract; and
    the extent of Rex's settlement costs (R4, tab 13 at G-76).
    18. With respect to Rex's demand for profit, the TCO created a table projecting
    the costs to complete the contract that will prove important below. In this table, he
    determined that:
    a. The costs of materials to complete the contract were incurred prior to
    termination and were $10,714.68 (supp. R4, tab 24 at G-190). With the addition of the
    material burden of 15.99%, the material costs increased to $12,427.96 (id.).
    b. Labor to complete the contract was determined to be $1,194.62 in direct labor
    costs already incurred (for creating the first article), plus the anticipated cost of
    producing the remaining seven articles, which was calculated at $546.21 in direct costs
    for a total of $1,740.83 (supp. R4, tab 24 at G-190). This number came from taking
    Rex's estimate of $68.27 in projected labor costs for producing each unit3 and
    multiplying by 8, the number of units to be produced (id.). 4 The manufacturing burden
    in this table was 394.85% of labor costs, which, when multiplied by the already-incurred
    and projected direct labor costs ($1,740.83 x 394.85%), produces a total of $6,873.67 in
    indirect costs attributable to labor (id.). Adding the direct labor costs of $1,740.83 to its
    indirect costs of $6,873.67 to the fully burdened material costs of $12,427.96 sums to
    $21,042.46 (id.).
    c. General and administrative (G&A) costs of90.10% of the above total added
    $18,959.26 to the costs in the TCO's table (supp. R4, tab 24 at G-190). The TCO also
    included the miscellaneous costs ofUID marking ($50.00), labels ($16.00), the cost of
    money ($197.20), and delivery ($1,941.52) (id.).
    d. In sum total, then, the TCO found that the estimated cost to Rex for
    completing the contract would have been $42,206.44, which was $110.44 more than
    the contract price of $42,096.00 (supp. R4, tab 24 at G-190).
    3
    (See SOF ii 19, below).
    4
    There is a 5 cent discrepancy due to rounding errors.
    6
    19. The most significant costs in the TCO's profit calculation table came
    directly from information provided by Rex. The direct material costs in the TCO's
    table of $10,714.68 are consistent with Rex's allegations in this case (see app. supp.
    R4, tab 9, ~ 20). The already-incurred direct labor costs in the TCO's table come from
    Rex's claim (see app. supp. R4, tab 7, ex. 1). The per unit cost of manufacturing the
    production items come from Rex's bid estimate that the production units would each
    require 3.08 hours to assemble and 1.28 hours to test (supp. R4, tab 23 at G-172). At
    the labor rates in Rex's estimate ($15.14 for assembly, $16.91 for testing (id.)), each
    assembly would then cost $68.27 in direct labor ($46.63 in assembly labor plus $21.64
    for testing labor). The material and manufacturing burden rates in the TCO's table
    came from Rex's settlement proposal (see supp. R4, tab 24 at G-190), and were higher
    than those in its bid estimate (compare burden rates in bid estimate, supp. R4, tab 23 at
    G-172 to those in Rex's settlement proposal, app. supp. R4, tab 7, ex. 3 and R4, tab 16
    at G-109). Finally, the G&A rate also came from Rex's settlement proposal (app.
    supp. R4, tab 7, ex. 4).
    20. Turning to the settlement expenses, Rex submitted to the TCO termination
    settlement expenses of $2,717.55 for the labor of individuals who assembled the
    termination settlement proposals (multiplied by the proper G&A factor) plus the costs
    of its outside attorneys, who performed work on the proposal prior to this litigation
    (app. supp. R4, tab 9, ~ 21e.). The TCO disallowed all of the costs of Rex's salaried
    employees ($1,137.05) under the beliefthat their salaries were already being paid by
    G&A for the contract and thus were precluded by FAR 31.205-42(c)(5), but allowed
    almost all of the legal fees except for a small amount ($362.50) that involved litigation
    before the Board, which the TCO considered not to be recoverable (supp. R4, tab 24 at
    G-192-93). Rex has since submitted unrefuted evidence that the salaries of the
    employees for the time that they worked on settlement of this dispute were not part of
    the G&A pool applied to this contract, nor were they paid by any other contract (app.
    supp. R4, tab 9, ~ 2le.).
    21. On 27 October 2014, Rex filed a notice of appeal from the deemed denial
    of its claim which was docketed as 
    ASBCA No. 59624
    .
    DECISION
    Typically, entitlement to compensation for costs in a termination for convenience
    is determined by those applicable clauses of the FAR that are incorporated into the
    contract at issue. With respect to the FAR clauses governing termination costs, the
    parties appear to have, sub silentio, treated this case for the most part as ifthe termination
    were covered by the termination clause for firm-fixed-price contracts in FAR Part 49 5
    (see, e.g., gov't br. at 17). In fact, however, the termination clause contained in the
    5
    This is not surprising, given that the contract modification terminating it referenced
    FAR Part 49 (SOF , 15).
    7
    contract is that for simplified acquisitions other than commercial items, FAR 52.213-4(f)
    (see SOF ~ 4). Under FAR Part 49, contracts are "essentially converted into cost-
    reimbursement contracts, when terminated for convenience." See Dellew Corp., 
    ASBCA No. 58538
    , 15-1 BCA ~ 35,975 at 175,783-84. Here, the standard for recovery of
    termination costs is somewhat different: subject to other terms of the contract, the
    contractor is entitled to "be paid a percentage of the contract price reflecting the
    percentage of the work performed prior to the notice of termination, plus reasonable
    charges that.. .have resulted from the termination" (see SOF ~ 4 ).
    In prior decisions, we have considered the scope of the materially-identical
    termination clause for commercial items, FAR 52.212-4(t), see, e.g., SWR, Inc., 
    ASBCA No. 56708
    , 15-1 BCA ~ 35,832, and we will apply the same reasoning to the termination
    clause presented by FAR 52.213-4(t) for simplified non-commercial acquisitions. In
    these earlier decisions, we analyzed the clause as providing for reimbursement under two
    prongs: the first prong being for the percentage of work performed prior to the notice of
    termination; the second prong being for costs (including settlement costs) "resulting from
    the termination." See Dellew, 15-1BCAii35,975 at 175,784 (citing SWR, 15-1 BCA
    ii 35,832 at 175,223). In the case before us, because there were never any semi-conductor
    devices tested and deemed acceptable and delivered to the government, there is no way to
    pay Rex a percentage of its performance and the parties have made no attempt to set forth
    a percentage of performance. 6 Nevertheless, when (as here) the contractor incurs costs
    prior to termination without completing any percentage of the contract, we have read an
    equivalent FAR clause to permit the contractor to recover reasonable expenses incurred
    prior to termination under the theory that they constitute "costs resulting from the
    termination." SWR, 15-1BCA~35,832 at 175,277-28; Dellew, 15-1 BCA ~ 35,975 at
    175,784. These costs (but not the settlement costs) are subject to profit. See SWR, 15-1
    BCA ~ 35,832 at 175,233. We examine each category of costs below.
    I.        Rex is not Entitled to Costs of Production Materials Ordered Prior to First
    Article Acceptance
    A contractor's entitlement to termination costs as set forth in FAR 52.213-4(f)
    is "subject to the terms of this contract." Under FAR 52.209-3, First Article Approval
    - Contractor Testing, which is included in the contract (SOF ~ 3), Rex was explicitly
    warned that, "[b]efore first article approval, the acquisition of materials or components
    for ... production of, the balance of the contract quantity is at the sole risk of the
    Contractor" and not allocable to the contract for purposes of a termination settlement
    (SOF ~ 6). The NA VSUPWSSIA05 clause, also included in the contract (SOF ii 7),
    included similar provisions that prohibited compensation in a termination settlement
    6
    But see TriRAD Technologies Inc., 
    ASBCA No. 58855
    , 15-1 BCA ii 35,898. Under
    the proper circumstances (not presented here) the government could be liable
    for a percentage completion of partially assembled items, even if they were not
    delivered to the government. 
    Id. at 175,497
    .
    8
    for materials obtained for the assembly of production and even first article test devices
    ifthe materials were obtained prior to approval of first article test procedures (id.).
    Thus, by the terms of the contract, Rex was not entitled to compensation in a
    termination settlement for production materials purchased prior to approval of the first
    article testing. Indeed, under NAVSUPWSSIA05, Rex was not entitled to
    compensation of any materials purchased for production of the test article prior to
    approval of the test procedure.
    The TCO, nevertheless, agreed to compensate Rex for materials purchased for
    the fabrication of the first article for testing (see supp. R4, tab 24 at G-176), and,
    because the government does not seek to revisit that determination here, we will not
    disturb it.
    Rex argues that it should be compensated for the early purchase of the diodes
    because it had no choice in the matter if it wished to deliver the semiconductor devices on
    time (app. supp. R4, tab 9, ~ 2la.). Rex argues the diodes had a 24-week lead time for
    delivery, which meant that production would not have met the contractual deadline if it had
    waited until first article approval prior to ordering them (id.; see also app. reply br. at 2-3 ).
    Although this long lead time concern could explain why Rex initially expected
    to make an early diode order (see SOF ~ 9 (24-week lead time initially anticipated)), it
    does not provide us a basis for ignoring the plain terms of the contract when
    determining what compensation is owed to Rex for the termination. Indeed, in
    multiple prior cases, we held that, absent waiver from the CO, a contractor was not
    entitled to payment for such costs incurred prior to first article acceptance. See, e.g.,
    Basic Tool Co., 
    ASBCA No. 29683
    , 88-2 BCA ~ 20,638 at 104,321 (citing Century
    Electronics, 
    ASBCA No. 29123
    , 85-3 BCA ~ 18,232 at 91,550); Aerospace Swaging
    & Mfg., Inc., 
    ASBCA No. 38534
    , 90-2 BCA ~ 22,834 at 114,656. Neither party
    alleged a waiver by the CO here, and when Rex entered the contract, it was well aware
    of the risks it would undertake if it chose to order its diodes prior to first article
    acceptance. It took those risks and must live with the consequences. Rex's argument
    that "[t]he Government Should Not Be Allowed to Hide Behind the [First Article Test]
    Clauses" (see app. reply hr. at 3), is not persuasive. The terms of the contract are
    binding upon the parties unless waived, and the unsupported allegation that the
    government withheld approval of the test procedures "in pursuit of this improper
    purpose" (see id.), even if true (but which we find unproven) would not change the
    simple fact that the contract forbids payment for production items obtained prior to
    such approval.
    Moreover, although the contract terms are sufficient to preclude recovery to Rex
    on this issue, we further note that the evidence demonstrates that Rex was not, in fact,
    saddled with a 24-week lead time for the subject diodes. When Rex contacted the diode
    supplier in August 2012, it was offered a delivery with a six-week lead time (see SOF
    ~ 9), although the diodes were actually delivered in less than four weeks (id.). Thus, at
    9
    the time that it placed its order for the diodes, Rex was on notice that it need not worry
    about a 24-week lead time, and that the diodes could be delivered in plenty of time to
    meet its production time-lines if ordered subsequent to first article testing approval.
    II.     Rex is Not Entitled to the Delay Damages that it Seeks
    While Rex submitted a claim for delay damages as part of its termination
    settlement proposal, we do not have evidence that such costs resulted from the
    termination. We do however consider whether Rex is otherwise entitled to such costs
    under some other contract provision. Undoubtedly, the government was delinquent in
    responding to Rex's first article and production test procedures submitted on
    27 September 2012 (finding 10)-indeed, there was no response at all from the
    government except that the contract was terminated some three months after the response
    was due. This lack of response might justify a change to the contract delivery dates (see
    SOF ii 5) and potential damages, if they could be proved. But the delay damages sought
    by Rex are limited to unabsorbed overhead (see app. supp. R4, tab 9, ii 21b.) and there is
    simply no basis to award such damages based upon the record before us.
    The government's responsibility for unabsorbed home office overhead in a
    delay case was principally articulated in Eichleay, 7 and in numerous cases that later
    followed in the United States Court of Appeals for the Federal Circuit. See, e.g.,
    Interstate Gen. Gov 't Contractors, Inc. v. West, 
    12 F.3d 1053
    , 1058 (Fed. Cir. 1993);
    Melka Marine, Inc. v. United States, 
    187 F.3d 1370
     (Fed. Cir. 1999); P.J Dick Inc. v.
    Principi, 
    324 F.3d 1364
     (Fed. Cir. 2003); Nicon, Inc. v. United States, 
    331 F.3d 878
    (Fed. Cir. 2003). The general notion is that the government is liable to the contractor
    for a proportionate share of the general costs of operating the contractor's business
    (things like accounting and payroll services, salaries for upper-level managers, general
    insurance, utilities, taxes and depreciation, see Interstate, 
    12 F.3d at 1058
    ), during the
    time that the contractor was forced to do little but twiddle its thumbs due to the delay.
    See Melka Marine, 
    187 F.3d at 1374-75
    . A prerequisite to this entitlement, however,
    is that the contractor truly was forced to remain on standby during the delay period and
    was precluded from obtaining new business. Melka Marine, 
    187 F.3d at
    1375 (citing
    Interstate, 
    12 F.3d at 1056
    ); P.J. Dick, 
    324 F.3d at 1370
    ; Nicon, 
    331 F.3d at 883
    . Rex
    was not so affected by the government.
    Rex argues in the Kornesczuk declaration that it could not obtain new work
    during the delay period because it was "required to standby" at that time and maintain
    its resources at the ready to perform and that, in any event, its business model was to
    sit by and let its customers place orders - a matter over which it argues that it had no
    control (app. supp. R4, tab 9, ii 2lb.). Perhaps its passive business model did not lend
    itself to Rex's seeking new work during the delay period, but that was not the fault of
    the government. Moreover, nothing about the government delay here imposed upon
    7   Eichleay Corp., 
    ASBCA No. 5183
    , 60-2 BCA ii 2688.
    10
    Rex a standby that required it to incur additional costs. In P.J. Dick, the Federal
    Circuit discussed, at length, the meaning of "standby" for purposes of Eichleay
    damages. See 
    324 F.3d at 1371-72
    . This discussion makes clear that a contractor is
    considered to be on standby if, "during that delay it was required to be ready to resume
    work on the contract, at full speed as well as immediately." 
    Id. at 1371
    . Thus, there
    would be no standby ifthe government permitted the contractor "a reasonable amount
    of time" to remobilize once the suspension was lifted. 
    Id.
     Factually, Rex had ample
    time to complete the little work necessary to fulfill the requirements of the contract
    and need not have been on standby.
    Our basis for this conclusion is two-fold. First, the First Article Testing clause,
    FAR 52.209-3(t), requires the CO to provide for an extension of time ifthe
    government was late in approving the first article test procedure (SOF ~ 5) ("If the
    Government does not act within the time specified [for approval of first article test
    procedure] the Contracting Officer shall...equitably adjust...the delivery or
    performance dates."). This provision thus gave Rex every reason to believe that the
    government would have given it "reasonable time," see P.J. Dick, 324 F .3d at 13 71, to
    complete the work.
    Our second factual reason to conclude that Rex had ample time to complete the
    contract without needing to keep its work force "ready to resume work on the contract,
    at full speed as well as immediately," P.J. Dick, 
    324 F.3d at 1371
    , is based upon a
    straightforward review of the calendar and the minimal work remaining to be
    performed upon the contract. At the time that the contract was terminated, it was
    approximately seven months into performance, with the first article having been
    already (and prematurely) fabricated and tested by Rex (SOF ~ 11). After delivery and
    approval of the first article and its tests, all that remained for the next five months of
    performance was the fabrication, testing, and delivery of the seven remaining
    semiconductor devices. In the Kornesczuk declaration that serves as its opening brief,
    Rex characterizes the work remaining to be done on these devices as "insubstantial"
    (app. supp. R4, tab 9, ~ 2lb.). We agree. Rex estimated that the production units
    would each require 3.08 hours to assemble and 1.28 hours to test (SOF ~ 19), which
    would yield slightly more than 30 hours of work to fabricate and test the remaining
    7 devices (7 x (3.08 + 1.28) = 30.52). We cannot conclude that Rex kept its workforce
    on tenterhooks to immediately ramp up "at full speed" in order to perform 30 hours of
    work in the coming 5 months (even if the CO had refused to grant the extension
    required by FAR 52.209-3(t)). 8 Thus, by no meaning of the word applicable to the
    8   In its reply brief, Rex argues that it needed to keep its workforce on standby because
    time was of the essence and it needed to avoid a negative performance rating
    that would follow if it were late (see app. reply br. at 2). Given the ample time
    remaining on the contract and the minimal work remaining upon the contract,
    we find this argument farfetched.
    11
    Eichleay analysis, was Rex on "standby." Accordingly, Rex has not proved itself
    entitled to delay damages for unabsorbed overhead.
    III.    Rex was Entitled to Very Little Profit in the Termination Settlement
    Even though Rex is entitled to profit for its "costs resulting from termination,"
    see SWR, 15-1BCA,-[35,832 at 175,233, there is no basis for compensating Rex at a
    higher profit margin than it would have earned had the contract not been terminated.
    The facts here demonstrate that that margin would have been far smaller than claimed
    by Rex. The documents that Rex submitted to support its claim for expenses incurred
    prior to the termination of the contract reflected higher labor and material costs than
    anticipated in its bid. In particular, the burdens for both were substantially higher than
    expected9 and, when the remaining labor required to complete the contract is factored
    in to our calculations, we find that Rex would have barely eked out a profit on the
    contract, had it been completed.
    The accounting supporting this conclusion comes from a straightforward review
    of the costs already incurred upon the contract added to the remaining costs for the
    contract. The TCO included a depiction of this calculation in a table contained in his
    1August2015 determination (SOF ,-[ 18). We have reviewed the numbers in this table
    and find them to be (mostly) supported and accurate (see SOF ,-[ 19), but depart from
    them in one instance that changes the negative profit to a very small profit: the TCO
    calculated the wrong number of production items remaining on the contract.
    Because Rex had already completed its first article at the time of contract
    termination (see SOF ,-[ 11), it only needed to make seven more of the semiconductor
    devices required by the contract, but the TCO' s table assumed that eight more devices
    needed to be made (see SOF ,-[ 18). Accordingly, the labor costs (fully burdened and
    subjected to G&A markups) for one device should be subtracted from the TCO's
    projected bottom line. The direct labor costs for one item were $68.27 (id.), to which
    should be added the 394.85% labor burden and the 90.10% G&A cost (id.).
    Mathematically, we may represent that as $68.27 x 4.9485 x 1.901. The result is
    $642.22 in extra costs for the one over-counted production item. We thus change the
    TCO's projected $110.44 loss (see id.) into a $531.78 profit.
    Since the contract price was $42,096 (see SOF ,-[ 1), by application of simple
    division, we can see that the proper expected profit rate would have been 1.26% instead
    of the TCO's negative profit rate. We multiply this profit rate against the TCO's
    9
    Rex argues that its past experience and its estimate demonstrate that it would have
    made substantial profit on this contract (see app. reply br. at 3-4). The problem
    with this contention is that it utterly ignores the reality of its contract
    performance, which encountered vastly increased burden rates than those used
    to formulate Rex's bid (SOF ,-[ 18).
    12
    calculated allowable costs incurred prior to termination, $24,614.08 (SOF ii 16), and
    determine that the TCO should have paid $3 10 .14 in profit to Rex, rather than
    withholding $64.41 in loss, which is a net difference of $374.55.
    IV.      Rex was Entitled to Additional Reimbursement for Settlement Expenses
    Rex submitted termination settlement expenses of $2,717.55 for the labor of
    individuals who assembled the termination settlement proposals (multiplied by the
    proper G&A factor) plus the costs of its outside attorneys, who performed work on the
    proposal prior to this litigation (SOF ii 20). The TCO disallowed all of the costs of
    Rex's salaried employees ($1,137.05) under the beliefthat their salaries were already
    being paid by G&A for the contract, but allowed almost all of the legal fees except for a
    small amount ($362.50) that involved litigation before the Board and would be
    precluded by FAR (id.). Rex does not appear to challenge the determination regarding
    legal fees, but does take issue with the notion that it should not be able to charge for the
    time of its employees whose salaries were part of the G&A pool (app. supp. R4, tab 9,
    ~ 21e.). Because the work on the settlement proposal took place in a different year than
    performance of the contract and the evidence of record is that it was not charged to any
    other government contract (SOF ~ 20), Rex is entitled to the money.
    Without getting too far into the weeds of cost accounting, the general premise
    of FAR 31.205-42(c)(3), which was relied upon by the TCO to deny this portion of
    Rex's claim (SOF ~ 20) 10 is that, if particular labor costs were incurred for work on a
    particular contract and paid as a direct cost on that contract for its termination, those
    labor costs cannot also be placed into the pool of costs used to generate G&A
    expenses. See FAR 31.205-42(c )(3 ). To put a finer point on it, a contractor cannot be
    paid twice for the same labor expense. In a somewhat obscure manner, the TCO found
    and the government argues that the personnel who performed work on the termination
    settlement were all persons whose positions would have placed their salaries into the
    G&A expense pool (SOF ~ 20). The TCO then alleges that, because these expenses
    were incurred prior to 2015 and not, apparently, charged to the contract, they were part
    of the G&A pool and presumably recovered in the years in which they were incurred
    (id., see also gov't br. at 19-20). The flaw in this reasoning is that the government has
    not demonstrated that G&A costs were ever recovered by Rex from the government
    (or any other customer, for that matter) during the years that Rex incurred its
    settlement expenses. Rex has provided unrefuted evidence that it did not otherwise
    recover these settlement expenses (SOF ~ 20). Accordingly we find that Rex did not
    recover its internal settlement expenses of $1,137.05 (SOF ~ 20), and that this expense,
    10
    Under the applicable termination clause, FAR 52.213-4(f), cost accounting
    standards are not necessarily applicable to this termination settlement. Neither
    party raises the issue and because we rule in favor of Rex here, we need not
    decide whether it was appropriate for the CO to consider FAR 31.205-42(c)(3)
    in the first instance.
    13
    which we find to be reasonable under the circumstances, should have been paid.
    Accordingly, Rex is entitled to an additional $1,137.05 in settlement expenses.
    CONCLUSION
    We find that Rex is entitled to an additional $374.55 for lost profit and
    $1,137.05 in settlement expenses for a total of$1,511.60, plus CDA interest from
    1 August 2015, the date the termination settlement proposal matured into a claim.
    Dated: 15 April 2016
    J.~ OUTY
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                         I concur
    RICHARD SHACKLEFORD
    Administrative Judge                             Administrative Judge
    Acting Chairman                                  Vice Chairman
    Armed Services Board                             Armed Services Board
    of Contract Appeals                              of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 59624
    , Appeal of Rex
    Systems Inc., rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    14
    

Document Info

Docket Number: ASBCA No. 59624

Judges: Prouty

Filed Date: 4/15/2016

Precedential Status: Precedential

Modified Date: 5/9/2016