Vertex Construction & Engineering ( 2014 )


Menu:
  •                 ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                   )
    )
    Vertex Construction & Engineering              )      
    ASBCA No. 58988
    )
    Under Contract No. W56SGK-13-C-7048            )
    APPEARANCE FOR THE APPELLANT:                         Mr. Hedayatullah Zaheb
    CEO/President
    APPEARANCES FOR THE GOVERNMENT:                       Raymond M. Saunders, Esq.
    Army Chief Trial Attorney
    MAJ Cameron R. Edlefsen, JA
    Trial Attorney
    OPINION BY ADMINISTRATIVE JUDGE WILSON
    ON THE GOVERNMENT'S MOTION FOR SUMMARY JUDGMENT
    This matter arises from the contracting officer's (CO's) decision to terminate
    Vertex Construction & Engineering (VCE or appellant) for default due to appellant's
    submission of a fraudulent master electrician certificate in order to secure the contract.
    Appellant admits the allegation but blames the subcontractor from which it purchased the
    certificate, the difficulty it had as a foreign company in verifying U.S. certifications, and
    the government's own failure to verify the certificate and disqualify appellant from
    consideration. The government moves for summary judgment on the grounds of fraud in
    the inducement, asserting the misrepresentation rendered the contract void ab initio. For
    the reasons stated below, the government's motion is granted.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
    1. On 1January2013, the U.S. Army's Phoenix Regional Contracting Center at Camp
    Phoenix, Kabul, Afghanistan, issued Solicitation No. W56SGK-13-R-7024 (solicitation), to
    disassemble and reassemble 44 re-locatable buildings (RLBs) (gov't mot., ex. 1 at 1, ex. 2,
    if 1.1).
    2. The solicitation contained the following provisions in Section L, Instruction to
    Offerors:
    1v. Proof of Electrican [sic] Certification: The contractor
    shall submit a current and active U.S. State Certified
    Electrician License for their proposed certified
    electrician. The offeror shall also provide the email and
    phone number of the licensed electrician with their
    proposal. The proposed electrician's license will be
    reviewed and verified to ensure validity during proposal
    evaluations, as well as at the construction site. Failure to
    provide an electrician certificate as outlined above
    could result in your proposal being found technically
    unacceptable and eliminate your proposal from contract
    award consideration.
    (Gov't mot., ex. 1 at 55-56)
    3. The Evaluation Factors in Section M of the solicitation, in discussing the
    acceptability of the electrician license, state:
    The acceptability of [the] electrician[']s license will be based
    upon whether the proposed electrician has an active license
    and the proposed employment by the offeror has been verified
    and reasonably demonstrates to the Government that quality
    requirements will be effectively met, in providing an
    acceptable level of electrical work under the contract. As the
    Government intends to award a contract without discussions,
    offerors that do not provide certified electricians in meeting
    the requirements of the Statement of Work, may result in an
    unacceptable rating for this Technical Capability sub-factor,
    and therefore, such offerors may be removed from
    consideration for award.
    (Gov't mot., ex. 1 at 59)
    4. The Statement of Work (SOW) in the solicitation called for a master
    electrician:
    All Electrical components shall be re-installed by a Master
    Electrician; electrical licensing and certification shall be
    presented to the Contracting Officer prior to work beginning.
    All electrical shall be install[ ed] in accordance with Standard
    Specifications Attachment Division 16 Electrical.
    (Gov't mot., ex. 2, ii 2.8.1)
    2
    5. VCE submitted its proposal on 20 February 2013 1, stating that the company
    had electrical designers familiar with the National Electrical Code (NEC) and an NEC
    certified electrician (gov't mot., ex. 3 at 1, 4). Appellant included, as proof of electrical
    certification, a license for a Mr. Donnie Frank (Mr. Frank) of Albuquerque, New Mexico,
    issued by the New Mexico Regulation and Licensing Department. The license indicated
    it was for a classification EE98-J, with certificate number 13653, and would expire
    30 November 2013. (Gov't mot., ex. 3 at 17) There is no evidence in the record that
    appellant indicated when it submitted its bid, that it did not have computer access to
    license verification sites in the United States, nor is there evidence that appellant
    complained of not having enough time to properly prepare its bid. We find that
    classification EE98-J is for a journeyman electrician, not a master electrician as required
    by the solicitation (see SOF ~ 14).
    6. The government evaluated four offerors for the solicitation, finding two of the
    four offers technically acceptable. One of the offers provided no electrical certification
    and was deemed unacceptable. (Gov't mot., ex. 7 at 2)
    7. On 23 February 2013, the government awarded Contract No. W56SGK-13-C-7048
    (contract) to VCE (gov't mot., ex. 8; compl. ~ 1).
    8. On or about 14 June 2013, problems arose concerning the electrical work on
    the contract. On 14 June 2013, CO Mark Penwell (CO Penwell) notified VCE that the
    wire installed on the L Row is "NOT approved," and directed VCE to remove the wire
    and install UL approved wire. (Gov't mot., ex. 9)
    9. On 16 July 2013, CO Penwell informed appellant he wanted to meet with
    Mr. Frank, VCE's certified electrician, the next day and that VCE and the government
    needed to come to an agreement to change the electrical wires. By email dated 17 July
    2013, VCE's CEO, Mr. Hedayatullah Zaheb (Mr. Zaheb), emailed Mr. Frank, "As per
    our agreement. I will be needing you to visit our construction site, can you please let me
    know when you are available." CO Penwell was copied on the email. (Gov't mot.,
    ex. 10)
    10. By email dated 17 July 2013, U.S. Army Criminal Investigative Division
    (CID) Special Agent (SA) Due Nguyen (CID SA Nguyen) contacted CO Penwell,
    expressing interest "in the RLB electrical issue regarding VCE," and requested a meeting
    (gov't mot., ex. 11 at 3).
    1
    Since the solicitation was dated 1January2013, the "2012" date on VCE's proposal
    was evidently mistaken. Subsequent pages in the proposal were dated "2/20/13"
    (R4, tab 3 at 11-12, 25-36).
    3                                                  I
    11. In emails dated 21 July 2013, VCE's CEO, Mr. Zaheb, was reminded by the
    government that the SOW required a U.S. licensed master electrician. Mr. Zaheb
    responded, "The qoute [sic] is not for master electrician to change the wires. If you insist
    on his presense [sic] we have to add 23000 in our quote. The electrician we had will not
    be present for couple of months." By email that same day, CO Penwell responded, "I
    remind you again. All work must be accomplished by a Licensed Master electrician."
    He went on to say that ifVCE did not have one, he would have to terminate the contract.
    (Gov't mot., ex. 12 at 1-2)
    12. By email the same day, Mr. Zaheb replied:
    I will find you the master electrician! Some of them will send
    you their certificates. Please give me a week of time and I
    will get you the final answer.
    NOTE: THE QOUTATION [sic] FOR WIRING CHANGE
    IS NO LONGER VALID UNTIL THEN AND I WILL
    SEND YOU THE FINAL QOUTE [sic] RIGHT AFTER
    THE CONTRACT WITH MASTER ELECTRICIAN.
    (Gov't mot., ex. 12 at 1)
    13. Immediately following Mr. Zaheb's email, CO Penwell received an email
    signed by Mr. Claude Watson, Jr., regarding electrical work:
    ... I was asked by Vertex Construction to send you a copy of
    my Electrical License. I am only a Journeyman Electrician
    with about 40 years experience, but agreed to send it to you.
    He tells me you require a Masters License and I only have
    Masters Experience.
    I have worked all over Afghanistan and just finished a
    contract one year ago August 16th. I do wish you can use me
    on this project instead of a Master. I need the work and want
    to work. It would be almost impossible to get a Master there
    for a one to two month project, as you know.
    (Gov't mot., ex. 13)
    14. On or about 23 July 2013, CID SA Nguyen tried to verify the electrician's license
    VCE had submitted, and informed the CO that in searching the New Mexico E-services for
    contractor licensing, discovered that the VCE certificate had expired 30 November 2006, and
    the status was listed as cancelled. "Furthermore, the classification EE-98J on the proposal's
    certification is for a Journeyman Residential and Commercial Electrician, not a Master
    4
    Electrician." He also informed the CO he was checking the government's personnel system
    to determine ifthe referenced individual, Mr. Frank, had ever been at Camp Phoenix or even
    in Afghanistan. (Gov't mot., ex. 4 at 1, 5)
    15. The CID completed its initial Report of Investigation 24 July 2013. It stated,
    in part:
    FURTHER INVESTIGATION REVEALED THE PERSON
    NAMED ON THE CERTIFICATE SUBMITTED BY
    MR. ZAHEB HAD NEVER BEEN ON SITE. ACCORDING
    TO THE SYNCHRONIZED PRE-DEPLOYMENT
    OPERATIONAL TRACKER-ENTERPRISE SUITE,
    THIS INDIVIDUAL HAS NEVER SET FOOT IN
    AFGHANISTAN. AS THE CERTIFICATE WAS GIVEN IN
    THE STATE OF NEW MEXICO, A CHECK OF THE
    STATE'S CONTRACTOR WEBSITE REVEALED THE
    CERTIFICATE HAD BEEN EXPIRED SINCE 30 NOV 06,
    AND WAS IN A CANCELLED STATUS.
    (Gov't mot., ex. 14 at 3)
    16. CO Penwell issued his CO's final decision 13 August 2013, informing VCE
    the contract was terminated for default on the grounds the electrician's license provided
    in VCE's offer to the solicitation was not one of a United States certified electrician as
    required by Section L of the Request for Proposal (RFP) (gov't mot., ex. 18).
    17. On 17 August 2013, CID SA Nick Saunders interviewed Mr. Fawad Sakhi
    (Mr. Sakhi), VCE's vice president, regarding his knowledge of the electrician's
    certificate submitted in VCE's proposal. Mr. Sakhi stated he was familiar with the
    specifications of the contract, specifically that a master electrician with proper
    documentation was required in order to receive consideration for award. Mr. Sakhi said
    that VCE did not employ a master electrician and it solicited Kabul area companies for a
    qualified electrician to fulfill the contract requirements. The report went on:
    Sakhi stated VCE forwarded the Scope of Work for the
    contract to a Kabul area company identified as Kabul Global
    Construction Company (KGCC) (NFI). Sakhi stated KGCC
    provided VCE with a certificate identifying an electrician
    named Donnie Frank as a qualified electrician that would be
    sufficient for VCE to submit with their proposal to the
    Government. Sakhi stated no one at VCE knew anything
    about Donnie Frank or if anyone named Donnie Frank was
    even in Afghanistan. Sakhi stated VCE paid KGCC an
    5
    unknown amount of money for the certificate only. Sakhi
    stated officials at VCE were unaware the certificate KGCC
    provided had been altered or that the certification number on
    the certificate identified [F]rank as a Journeyman Electrician
    and not a Master Electrician. Sakhi stated VCE did nothing
    to verify the information on the certificate KGCC provided
    was accurate and to ensure a master electrician was on-site to
    verify the work being done at Camp Phoenix was properly
    done.
    (Gov't mot., ex. 20)
    18. Appellant filed a timely notice of appeal with the Board by email dated
    1 November 2013, contesting the termination for default.
    19. The government filed a motion for summary judgment on the grounds that the
    contract awarded to VCE was procured through fraud in the inducement, and thus the
    contract was void ab initio. Both parties have filed reply briefs.
    CONTENTIONS OF THE PARTIES
    According to the government, the admission by appellant's vice president that
    VCE paid another company to provide a master electrician's certificate in order to
    include it with its bid, knowing without the certificate it would not be considered for
    award, established that the contract award was procured through misrepresentation, thus
    tainting the entire contract with fraud, rendering it void ab initio (gov't mot. at 1, 10).
    Appellant responded that it did not knowingly misrepresent the validity of the
    certificate at issue. It "subcontracted the master electrician to Kabul Global Construction
    Company (KGCC) and the contract stated that KGCC will provide the master electrician
    certificate and ... within 30 days of Notice to Proceed KGCC will bring the Master
    Electrician to the JOB site." Appellant agreed with Mr. Sakhi's statement that VCE paid
    "for a certificate only ... but, we would have given him more money ifhe would have
    come to the job site according to contract." (App. resp. at 2)
    VCE admitted it had done nothing to determine the authenticity of the certificate
    but justified not doing so because it was a local company and did not have access to "US
    certificate issuing authorities." Further, the solicitation required the government to
    review and verify the proposed electrician's license during proposal evaluations.
    According to appellant, since the government would evaluate the license "and if the
    license is not. .. valid they will not award the project," it would not make sense for VCE
    6
    to "go for a long term process of verifying the license because maybe during this
    evaluation I would not meet the deadline of proposal submission." (App. resp. at 2)
    Appellant also argued it should not be "blamed for writing a falsified proposal"
    regarding its master electrician because it "had an agreement with legal entity in
    Afghanistan about the electrician I could easily state that I have and anybody instead of
    me would have done the same" (app. resp. at 3). Appellant admitted in its complaint that
    "fraud happened" (compl. if 12), but declared, "we trusted the KGCC and there is no fault
    ofVCE in this case" (app. resp. at 4). Appellant, however, did not submit a copy of its
    subcontract with KGCC. Nor did appellant's response include any information about
    Mr. Frank or the presence of any master electrician on-site. There were no affidavits
    from VCE's CEO or vice president substantiating their assertions about appellant's
    subcontract with KGCC or dealings with Mr. Frank.
    The government's reply took exception to VCE's assertions that it subcontracted
    with KGCC for a master electrician, not just a certificate, pointing out those statements
    are inconsistent with its answers in an interview with the CID that it paid for a certificate
    only. The government noted VCE has not offered any evidence of a subcontract with
    KGCC. (Gov't reply br. at 1-2) The government also disagrees with VCE's argument
    that VCE is absolved from the consequences of its conduct by the government's failure to
    verify the certificate presented in the bid, arguing a government failure to verify does not
    negate appellant's misrepresentation in its proposal (id. at 3).
    DECISION
    Summary judgment is appropriate when there is no genuine issue of material fact
    and the movant is entitled to judgment as a matter of law. Mingus Constructors, Inc. v.
    United States, 
    812 F.2d 1387
    , 1390-91 (Fed. Cir. 1987); Lockheed Martin Aircraft
    Center, 
    ASBCA No. 55164
    , 08-1BCAif33,832 at 167,445. The moving party bears the
    burden of proof and all significant doubt over factual issues must be resolved in favor of
    the nonmoving party. Lockheed, 08-1 BCA if 33,832 at 167,445. There is a genuine
    issue of material fact ifthe evidence is such that a reasonable fact finder could find in
    favor of the nonmovant. Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    , 248-49 (1986).
    A nonmoving party may not simply rest upon vague allegations of disputed facts
    in opposing such a motion; it must present sufficient evidence to show evidentiary
    conflicts exist on the record as to "material fact[ s]" at issue. Armco, Inc. v. Cyclops
    Corp., 791F.2d147, 149 (Fed. Cir. 1986); Barmag Barmer MaschinenfabrikAG v.
    Murata Machinery, Ltd., 731F.2d831, 835-36 (Fed. Cir. 1984).
    Generally, "a Government contract tainted by fraud or wrongdoing is void ab initio."
    Godley v. United States, 
    5 F.3d 1473
    , 1476 (Fed. Cir. 1993) (citing United States v.
    Mississippi Valley Generating Co., 
    364 U.S. 520
    , 564 (1961)); JE.TS., Inc. v. United
    7
    States, 
    838 F.2d 1196
    , 1200 (Fed. Cir. 1988). In holding a contractor's false small business
    certification barred its subsequent claim, the Federal Circuit explained:
    The contract ... was procured by and therefore permeated with
    fraud .... J.E.T.S. obtained this contract by knowingly falsely
    stating that it was a small business. Had it stated the truth ... it
    would not have received the contract. A government contract
    thus tainted from its inception by fraud is void ab initio, like
    the government contracts held void because similarly tainted
    by a prohibited conflict of interest in United States v.
    Mississippi Valley Generating Co., 
    364 U.S. 520
    , 
    5 L. Ed. 2d 268
    , 
    81 S. Ct. 294
     (1961) and K & R Eng 'g Co. v. United
    States, 
    222 Ct. Cl. 340
    , 
    616 F.2d 469
     (1980).
    J.E.TS., 
    838 F.2d at 1200
    .
    Holding a contract void is a harsh penalty, but as the Supreme Court has said, the
    primary purpose of holding a contract tainted by fraud void ab initio is to "guarantee the
    integrity of the federal contracting process and to protect the public from the corruption
    which might lie undetectable beneath the surface of a contract conceived in a tainted
    transaction." Mississippi Valley, 
    364 U.S. at 564-65
    ; see also Godley, 
    5 F.3d at
    1475
    (citing Mississippi Valley in stating that "general rule [of a government contract tainted
    by fraud or wrong-doing is void ab initio] protects the integrity of the federal contracting
    process and safeguards the public from undetectable threats to the public fisc").
    Use of this remedy is not limited to "situations where the contractor has been
    convicted in a criminal action stemming from the misrepresentation." Servicios y Obras
    Isetan S.L., 
    ASBCA No. 57584
    , 13 BCA ii 35,279 at 173, 162. In Servicios, a
    contractor's material misrepresentations in its bid for a construction project at Moran Air
    Base in Spain, upon which the government had justifiably relied, met the standard for
    holding the contract void ab initio. The contractor had forged both a subcontractor
    agreement with another company that possessed most of the specialized certifications
    required to be possessed by the successful contractor's team and the required bank
    guarantees. The contractor did not possess the requisite certifications on its own, and had
    it not misrepresented itself to the government, it would not have been considered for
    award. We concluded the contract was void ab initio and the contractor's appeal of its
    termination for default was denied. 
    Id. at 173,162-63
    .
    The government presented evidence that VCE's vice president told an investigator
    appellant paid only for a master electrician certificate to submit with its bid (SOF ii 17).
    VCE does not dispute that it did so. Rather, it admits the statement is true but that "we
    would have given him more money ifhe would have come to the job site according to
    contract" (app. resp. at 2). Appellant also acknowledges that it knew if it did not include
    8
    evidence of a master electrician certificate in its bid, it would not have been considered
    for award (SOF ~ 17). VCE admitted it did nothing to verify the certificate it submitted
    with its bid, as required by the solicitation, or ensure the presence of a master electrician
    on site during performance of the contract (id.). According to appellant, it trusted KGCC
    and "there is no fault ofVCE in the case" (app. resp. at 4).
    Appellant's primary defense is that that the government had an obligation to verify
    the certificate and had it done so, appellant's misrepresentation would have been
    discovered, and the government could have disqualified VCE from the bidding process
    (app. resp. at 2). The argument that bids can present misinformation, and the burden is
    on the government to ferret it out, is not persuasive. The government analogizes the
    effects of its failure to verify the master electrician certificate to those situations in which
    the government's right to revoke acceptance under the Inspection of Construction clause
    is not barred by government inspection failures as in Chi/stead Building Company,
    
    ASBCA No. 49548
    , 00-2 BCA ~ 31,097 (gov't reply br. at 3). In Chi/stead, a roofing
    contractor's representations that it was proceeding in accordance with the drawings
    followed shortly thereafter by installation of deviant trusses was a gross mistake
    amounting to fraud in spite of the government inspector's failure to measure or inspect.
    
    Id. at 153,575-76
    . We reached the same conclusion in Z.A.N. Company, 
    ASBCA No. 25488
    , 86-1 BCA ~ 18,612 at 93,489 (holding that delivery of improperly marked
    watches was a gross mistake amounting to fraud despite the fact that government
    representatives may not have acted "with a maximum of circumspection") and in Jo-Bar
    Mfg. Corporation, 
    ASBCA No. 17774
    , 73-2 BCA ~ 10,311 at 48,684-85 (finding a
    contractor's decision that aircraft bolts did not have to be heat treated and failure to treat
    them, along with the misrepresentation to the government inspector that it had been
    advised heat treatment was not required was a gross mistake amounting to fraud despite
    possible lack of in-process inspection by the government).
    However, more fundamental is that the requirement for the government to verify
    the certificate submitted by VCE was for the benefit of the government, not for VCE.
    The law is clear that when contractors try to shift responsibility for their deficiencies not
    discovered when the government has conducted a pre-award survey, a contractor's
    obligation to verify information submitted in its bid remains. We have repeatedly held
    pre-award surveys are conducted for the government's benefit and even if they are
    inadequately performed, they do not confer rights upon contractors. Laumann
    Manufacturing Corporation, 
    ASBCA No. 51249
    , 01-2 BCA ~ 31,517; T.M Industries,
    
    ASBCA No. 19090
    , 75-1BCA~11,075. It is the contractor's responsibility, not the
    government's, to determine its own capability to perform a contract and, thus, even if a
    government pre-award survey is conducted negligently, "that circumstance can be of no
    consequence or benefit to the contractor." Venice Maid Company, ASBCA Nos. 20546,
    20792, 76-2 BCA ~ 12,045 at 57,810 (citing Aerospace Support Equipment, Inc.,
    
    ASBCA No. 13579
    , 71-1 BCA ~ 8904). In Venice Maid, the Board applied the same
    principles to the government's failure to perform an adequate post-award orientation
    9
    conference in upholding a termination for default wherein appellant complained the
    mistake it made which rendered it unable to perform would have been discovered by the
    government if an adequate pre-award survey or post-award orientation conference had
    been conducted. Venice Maid, 76-2 BCA ii 12,045 at 57,810.
    The same result was reached in Tri-States Service Company, 
    ASBCA No. 31139
    ,
    90-3 BCA ii 23,059, when a contractor sought reformation of a contract due to a mistake
    it made which would have been discovered had the government conducted a required
    pre-award survey. The Board found the argument without merit, stating:
    Pre-award surveys are for the benefit of the Government and
    not for the benefit of the contractor. Appellant has no
    standing to require the conduct of such survey. Accordingly,
    there is no basis for charging the Government with
    constructive notice of something that might have been found
    in the course thereof.
    
    Id. at 115,773
    .
    The solicitation in the present appeal did state that the government would review
    and verify the proposed electrician's license during proposal evaluations and at the
    construction site (SOF ii 2). This did not make the government the guarantor of
    appellant's bid, however, or free VCE from the requirements of the solicitation.
    Appellant's misconduct is not absolved by any government failure.
    In the present case, appellant has presented no evidence contradicting the
    government's facts, only unsupported arguments as to why its misrepresentations should
    be excused. In addition to blaming the government for not discovering VCE's fraud by
    verifying the master electrician's certification as discussed above, appellant justifies its
    failures by pointing to its small size, its status as a local company, and its lack of
    computer capability (app. resp. at 2). However, even if these assertions were relevant, no
    evidence is presented upon which these statements rest (SOF ii 5).
    Nor can solicitation requirements be ignored because compliance would be
    difficult, take time, or be expensive. Similar arguments were made by a contractor trying
    to justify overstating the credentials of its personnel in its bid because the requirements
    that certain technicians hold Class I licenses was "unrealistic and over burdensome." The
    contractor also complained providing such a technician would have been ''very
    expensive." Dongbuk R&U Engineering Co., 
    ASBCA No. 58300
    , 13 BCA ii 35,389
    at 173,638. VCE's justifications imply essentially the same - because it was too hard to
    find a certified master electrician in Afghanistan and would have cost more money - the
    requirement should be excused. This we cannot do. As we said in Dongbuk, relying on
    10
    the Court of Claims explanation in Prestex Inc. v. United States, 
    320 F.2d 367
    , 371-72
    (Ct. Cl. 1963):
    [T]he Comptroller General repeatedly has held that a
    specification deviation in a contractor's proposal affecting
    price, quality or quantity offered is a major deviation which
    cannot be waived. 
    39 Comp. Gen. 570
     (1960); 
    36 Comp. Gen. 251
     (1956); 
    30 Comp. Gen. 179
     (1950). The effect of
    statutes and regulations pertaining to the letting of public
    contracts is that the contract awarded must be the contract
    advertised and, if not, the government is not bound because
    its contracting agent cannot bind the government beyond his
    or her actual authority. The rejection of nonresponsive bids is
    necessary if the purposes of the competitive procurement are
    to be attained, that is, to give everyone an equal right to
    compete for Government business, to secure fair prices, and
    to prevent fraud.
    Dongbuk, 13 BCA, 35,389 at 173,638.
    The solicitation was clear that without submission of a master electrician
    certification a bid would not be considered (SOF ,, 2, 3). This in fact was the case, as
    another bid, which did not include a master electrician certification, was disqualified
    from consideration of award (SOF , 6). Therefore, it is clear that VCE obtained the
    contract through a material misrepresentation, providing only a certificate (that itself
    proved to be fraudulent), with no realistic intention of employing a master electrician, to
    the other bidders "disadvantage, and to the detriment of the federal government and its
    procurement system." Dongbuk, 13 BCA, 35,389 at 173,638.
    It appears there are no material facts in dispute. VCE has set forth no evidence
    that would allow a reasonable fact finder to conclude otherwise. See Liberty Lobby,
    
    477 U.S. at 248
     (issues of fact are genuine for summary judgment purposes only "if the
    evidence is such that a reasonable jury could return a verdict for the nonmoving party");
    Opryland USA Inc. v. The Great Am. Music Show, 
    970 F.2d 847
    , 849-50 (Fed. Cir. 1992)
    (a fact is "material" if it may affect the outcome, i.e., the finding of that fact is relevant
    and necessary to the proceeding); see also Long Island Savings Bank v. United States,
    
    503 F.3d 1234
    , 1251 (Fed. Cir. 2007).
    Based on the uncontested evidence presented by the government, drawing all
    reasonable inferences in favor ofVCE, and accepting as true the statement in the
    complaint wherein appellant has admitted "fraud happened," we have to conclude that the
    contract which was entered into between VCE and the government is void ab initio. See
    11
    Long Island Savings Bank, 
    503 F.3d at 1246
    ; C&D Construction, 90-3 BCA ~ 23,256
    at 116,683. Accordingly, the government's motion for summary judgment is granted.
    CONCLUSION
    The appeal is denied.
    Dated: 7 November 2014
    OWEN C. WILSON
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                        I concur
    Administrative Judge                            Administrativ
    Acting Chairman                                 Acting Vice C · an
    Armed Services Board                            Armed Services Board
    of Contract Appeals                             of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 58988
    , Appeal of Vertex
    Construction & Engineering, rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    12