Equine Architectural Products, Inc. ( 2015 )


Menu:
  •                 ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                    )
    )
    Equine Architectural Products, Inc.             )      
    ASBCA No. 59743
    )
    Under Contract No. W91ZLK-12-P-0037             )
    APPEARANCE FOR THE APPELLANT:                          Donald J. Walsh, Esq.
    Offit Kurman, P.A.
    Owings Mills, MD
    APPEARANCES FOR THE GOVERNMENT:                        Raymond M. Saunders, Esq.
    Army Chief Trial Attorney
    MAJ Cameron R. Edlefsen, JA
    Trial Attorney
    OPINION BY ADMINISTRATIVE JUDGE DELMAN ON THE GOVERNMENT'S
    MOTION TO DISMISS FOR LACK OF JURISDICTION
    The Department of the Army (government) has moved to dismiss this appeal for
    lack of jurisdiction under the Contract Disputes Act (CDA), 
    41 U.S.C. §§ 7101-7109
    ,
    contending that Equine Architectural Products, Inc. (EAP or appellant) has failed to
    submit a claim in a sum certain to the contracting officer (CO). EAP has filed in
    opposition to the motion.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
    1. In February 2012, the government awarded Contract No. W91ZLK-12-P-0037
    to EAP for the demolition and removal of railroad and related facilities at Aberdeen
    Proving Ground (APG), Maryland (comp I., ex A).
    2. By Modification No. P00002 dated 25 July 2012, the government issued a
    Stop-Work Order to appellant in accordance with FAR 52.242-15 (AUG 1989) (compl.,
    ex. A). According to appellant, approximately 51 days later the government notified
    appellant that the contract was being terminated for convenience (compl. ~ 15). 1
    By cover letter dated 21December2012, appellant submitted a termination proposal to
    the government (compl., ex. B). The record is unclear as to the disposition of this
    termination proposal.
    1
    The Board is unable to locate the contract modification that terminated the contract
    for convenience in the government's Rule 4 file.
    3. By letter to the government dated 7 January 2014, appellant stated as
    follows:
    Please accept this letter as an official claim under the
    above contract pursuant to the [CDA].
    This claim is for return to Equine of all property which
    existed within that 15 foot area, including the 14 miles of
    rail, at the time of that mobilization. Much of this
    equipment is noted per drawings titled APG: North Rail
    Lines dated March 27, 2012. By the direct language of the
    contract, title to this property passed to Equine at the time
    of contracting. This claim is for possession and return of
    all such property which now belongs to Equine and which
    it has been prevented from removing by the government.
    Appellant's claim letter concluded as follows:
    I certify that I have reviewed this claim and that it is made
    in good faith, the supporting data is accurate and complete
    to the best of my knowledge and belief, that the property
    requested is accurately reflected in the contract under
    which Equine believes the Government is liable; and that I
    am duly authorized to certify this claim on behalf of
    Equine.
    (Compl., ex. C at 1-2) Appellant did not provide any "sum certain" in its claim letter,
    nor did it reference any other document that contained a "sum certain."
    4. In the ensuing weeks, the parties discussed the quantum of appellant's
    "claim." By email to the government dated 28 January 2014, appellant's counsel
    advised as follows:
    Thanks for the update. I also had my client put
    together ~ list of what he knew was on the tracks based on
    his observations and conversations. Attached is a listing of
    materials and equipment within the 15' footprint that my
    client pieced together based on those observations and
    conversations. It does not currently include buildings or
    structures within that footprint nor does it include property
    on the rails in the Edgewood Arsenal Area since Equine
    2
    was not given any maps and or the opportunity to do a
    detailed site survey. Based on this limited area, we believe
    the scrap in this area totals approximately $6,986,832.00.
    (Gov't reply, ex. 1) Appellant did not certify this amount.
    5. By letter to the government dated 7 May 2014, captioned "FOR
    SETTLEMENT PURPOSES ONLY," appellant's counsel stated:
    [I]f the Garrison is not willing to release the property to
    Equine as contracted, we feel that the total claims
    presented by Equine consist of the following costs and
    expenses:
    -   Value of the rail, ties and ballasts - $2,220,000;
    -   Value of the equipment within the 15 foot radius to
    the rail - $4,400,000;
    -   The carrying cost of equipment Equine purchased for
    this project which has been sitting idle since the stop
    work notice was issued but had to remain ready and
    available to remove Equine's equipment from the base
    once released - $1,300,000;
    If the above values are not computed at 2012 prices, the
    damages will also include the decreased value of the
    scrap because of the Government's delay - $1,300,000;
    and
    -   the legal costs in preparing and resolving the claims - $50,000.
    We estimate that the total value of these costs and impacts
    is $9,250,000.00.
    (Compl., ex. D) Appellant did not certify this amount.
    6. Having failed to receive a CO's decision, appellant, on or about
    12 December 2014, filed a notice of appeal to this Board on a "deemed denial" basis,
    stating that its total losses exceeded $10,000,000.00.
    7. By letter to EAP dated 15 December 2014, the CO denied appellant's claim
    dated 7 January 2014, referencing a property list provided by appellant with an
    estimated total scrap value of $6,986,832.00 (comp I., ex. E).
    3
    DECISION
    Under the CDA, a prerequisite to our jurisdiction over a contractor claim is the
    submission of the claim for decision to the CO and either the issuance of a decision
    denying the claim in whole or in part, or the failure to issue a decision within a
    reasonable time as defined by the CDA, 
    41 U.S.C. § 7103
    (t).
    The CDA does not define "claim", but the FAR does. Insofar as is pertinent
    here, FAR 2.101 provides as follows:
    Claim means a written demand or written assertion
    by one of the contracting parties seeking, as a matter of
    right, the payment of money in a sum certain, the
    adjustment or interpretation of contract terms, or other
    relief arising under or relating to the contract. However, a
    written demand or written assertion by the contractor
    seeking the payment of money exceeding $100,000 is not a
    claim under the Contract Disputes Act of 1978 until
    certified as required by the Act.
    In accordance with this definition, it is well settled that for purposes of our
    jurisdiction a contractor's monetary claim must be submitted to the CO in a "sum
    certain." Northrop Grumman Computing Systems, Inc. v. United States, 709 F .3d
    1107, 1112 (Fed. Cir. 2013). We believe that appellant's claim is essentially a
    monetary claim. Therefore, appellant was required to submit its claim to the CO in a
    sum certain.
    Appellant's letter of 7 January 2014, which it expressly identified as its "claim,"
    did not contain a "sum certain," nor did it refer to any document asserting a sum
    certain, nor did it describe its monetary claim with such particularity as to enable the
    CO to easily compute a sum certain (SOF ir 3). We believe that appellant failed to
    submit its claim letter dated 7 January 2014 in a sum certain as required by law, and
    hence we have no jurisdiction over this appeal based on this submission alone.
    Appellant suggests that we go beyond the confines of the 7 January 2014 letter
    and view other communications to the government to determine whether appellant
    submitted a proper claim under the CDA. Appellant's subsequent email to the
    government, dated 28 January 2014, asserted a value of the scrap in a limited area in
    the approximate amount of $6,986,832.00 (SOF ir 4). Appellant's letter to the
    government dated 7 May 2014, which appellant states represents the total value of its
    claim, was in the amount of $9,250,000.00 (SOF ir 5).
    4
    Assuming, arguendo, that EAP's subsequent quantification of7 May 2014
    constitutes a legally sufficient "sum certain," it nevertheless runs afoul of the CDA's
    certification requirement. Under the CDA, a monetary claim in excess of $100,000
    must be certified, 
    41 U.S.C. § 7103
    (b)(l). Appellant's monetary claim of7 May 2014,
    based on appellant's later submissions, is in excess of $100,000. However, appellant
    failed to provide any certification of the monetary amount it requested. 2 We are
    without jurisdiction over the appeal for this reason.
    CONCLUSION
    For reasons stated, we conclude that we are without jurisdiction over this
    appeal. We dismiss 
    ASBCA No. 59743
     without prejudice to appellant's submission of
    a properly certified claim to the CO.
    Dated: 4 June 2015
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                            I concur
    MARK N. STEMPLER                /     /             RICHARD SHACKLEFORD
    Administrative Judge                                Administrative Judge
    Acting Chairman                                     Vice Chairman
    Armed Services Board                                Armed Services Board
    of Contract Appeals                                 of Contract Appeals
    2
    See 
    41 U.S.C. § 7103
    (b)(l)(C), requiring that a contractor's certification provide that
    "the amount requested accurately reflects the contract adjustment for which
    the contractor believes the Federal Government is liable" (emphasis added).
    5
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 59743
    , Appeal of Equine
    Architectural Products, Inc., rendered in conformance with the Board's Charter.
    Dated:
    JEFFREYD. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    6
    

Document Info

Docket Number: ASBCA No. 59743

Judges: Delman

Filed Date: 6/4/2015

Precedential Status: Precedential

Modified Date: 6/16/2015