Potomac Electric Corp. ( 2019 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                  )
    )
    Potomac Electric Corp.                        )      
    ASBCA No. 61371
    )
    Under Contract No. SPRRA2-l 7-D-0028          )
    APPEARANCE FOR THE APPELLANT:                        Mr. Leny Chertov
    V.P. Operations
    APPEARANCES FOR THE GOVERNMENT:                      Daniel K. Poling, Esq.
    DLA Chief Trial Attorney
    Edward R. Murray, Esq.
    Trial Attorney
    DLA Aviation
    Richmond, VA
    OPINION BY ADMINISTRATIVE JUDGE YOUNG
    ON THE GOVERNMENT'S MOTION FOR SUMMARY JUDGMENT
    The Defense Logistics Agency (DLA or government) moves for summary
    judgment arguing that the undisputed facts before the Board support that no
    contract existed. Appellant counters that the government did in fact award a
    contract to Potomac Electric Corp. (Potomac). As there are genuine issues of
    material fact in dispute, we deny the motion.
    STA TEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
    1. On June 19, 2017, DLA issued Standard Form 33, Solicitation, Offer and
    Award No. SPRRA2-l 7-R-0053 (solicitation) as a small business set-aside for an
    indefinite-delivery, indefinite-quantity (IDIQ) type contract for direct current motors.
    The solicitation provided for the purchase of 200 motors in the base year, and 150
    motors in each of four option years. The guaranteed minimum was 150 motors. The
    solicitation required delivery of the 200 motors in the base years 255 days after
    contract award. The solicitation closed on July 7, 2017. (R4, tab 1)
    2. On July 7, 2017, Potomac submitted a proposal. The total price for the base
    and four option years was $3,319,786.22. The base year contemplated the delivery of
    200 motors for $784,476.00. (R4, tab 2 at 1, 29 of 29)
    3. On July 13, 2017, DLA contract specialist Harrison A. Mayfield (the contract
    specialist) sent Potomac an email confirming receipt of its proposal (R4, tab 3).
    4. On August 15, 2017, the contract specialist sent an email to Potomac,
    stating: "Attached is a draft copy of contract SPRRA2-l 7-D-0028 and delivery
    order 0001. Please review, if everything is ok, have [sic] sign both, the basic contract
    and delivery order and return to me for processing." (R4, tab 3)
    5. The Standard Form (SF) 26, Award/Contract, No. SPRRA2-l 7-D-0028
    (contract) stated that it was awarded to Potomac Electric Corp. The DD Form 1155,
    Order for Supplies or Services (delivery order or DO) attached to the contract
    specialist's email, ordered 200 motors for $784,476.00. The DO set a delivery date of
    January 31, 2018, and provided a line of accounting for $784,476.00. (R4, tab 3 at 4,
    49-52 of 53)
    6. The contract and delivery order the contract specialist provided to Potomac
    were unsigned. They identified the name of the contracting officer (CO) as
    Angela L. Clark and included her email and phone number. (R4, tab 3 at 4 of 53)
    7. On August 15, 2017, Potomac emailed the contract specialist, stating: "The
    solicitation ... requested [delivery of] (200 units) ... 255 days after the award.Pl The
    document we received this morning, SPRRA2-l 7-D-0028/0001...states delivery date
    of200 units as January 31, 2018.£21 Potomac Electric's price proposal is based on the
    Solicitation's 255 days delivery request. Could you please clarify?" (R4, tab 4 at 2-3)
    8. On August 16, 2017, the contract specialist responded: "You are correct, I
    adjusted the delivery date. Attached is the corrected delivery schedule, if everything is
    ok, have [sic] sign both the basic contract and delivery order 0001 and return to me for
    processing." 3 (R4, tab 4 at 2)
    9. Later that same day, August 16, Potomac emailed the contract specialist
    posing three technical questions about the electric motors. The contract specialist did
    not respond to Potomac's technical questions. Instead, on August 17, 201 7, he
    forwarded them internally to other DLA personnel. (R4, tab 4 at 1-2)
    1
    Assuming that award was made on August 15, 2017, 255 days after award would be
    April 27, 2018.
    2
    Assuming that award was made on August 15, 201 7, January 3 1, 2018, would be
    169 days after award.
    3
    The amended contract and amended DO mentioned in the contract specialist's email
    are not currently in the Rule 4 file, so the adjusted delivery date is unknown to
    the Board at this time.
    2
    10. On August 18, 2017, the CO signed a Final Price Negotiation Memorandum
    (FPNM). 4 The FPNM, section I, stated: "Item/Service: This acquisition is for spare
    supplies in support of the Patriot Weapon System. The requirement is a 5 Year
    Indefinite Delivery, Indefinite Quantity (IDIQ), Firm Fixed Price (FFP) type contract,
    for a DIRECT CURRENT MOTOR ... with a minimum quantity of 200 each and a
    maximum quantity of 800 each.'' (R4, tab 5 at 1) Section II stated: "The Government
    will accept Potomac Electric proposed price. as is" (id. at 2). As to Delivery Schedule,
    the FPNM stated in section IV.,~ A.: "The agreed to delivery schedule was
    negotiatedl 5 1 and confirmed for an expedited delivery by 20 January 2018 and no later
    than 6 February 2018" (id. at 5). In its conclusion paragraph. the FPNM stated:
    II                 The award of this requirement is based on adequate
    competition. Therefore, award will be made to the
    following contractor: The responsive offer received from
    Potomac Electric Corp at a total price of $3,319,785.00 is
    I                  considered fair and reasonable based on adequate price
    competition.... Contract number is SPRRA2- l 7-D-0028.
    II   The FPNM shows a signature line for the Branch Chief, Tactical Missile, DLA
    Aviation, Huntsville, Alabama, but is not signed by her. (Id. at 7-8)
    l
    I!         11. On August 18, 2017, Potomac signed and dated the contract and DO, and
    on August 19, 2017, forwarded them in an email to the contract specialist stating
    "Attached please find signed pages of the contract" (R4, tab 6 at 1, 7).
    12. In the August 19, 2017 email to the contract specialist, Potomac also stated:
    "The 200 units release has extremely tight schedule and Potomac must get started right
    away.'' Potomac also asked DLA to address the technical questions it had posed on
    August 16, 2017. (R4, tab 6)
    13. On August 23, 2017, the contract specialist forwarded the contract and DO
    signed by Potomac as well as Potomac's technical questions to the CO, stating:
    "Potomac has signed the basic contract and delivery order, but still wants the questions
    address[ed] below. If you can sign these two documents and award it in PADDs,1 61 I
    can get distribution out hopefully today." (R4. tab 7)
    4 The CO signed the FPNM on August 18, 2017, at 10:51 AM. The contract specialist,
    who prepared the FPNM, signed it later that day at 2 :4 7 PM, after the CO
    affixed her signature. (R4, tab 5 at 7-8)
    5
    However, the FPNM in Section V., ~ C. l Evaluation of the Proposals, states that
    "award was made without discussions" (R4, tab 5 at 6).
    6
    Believed to be Procurement Automated and Documents System.
    3
    I
    14. On August 28, 2017, the chief of DLA tactical division sent an email to the
    DLA Aviation deputy chief counsel 7 requesting review of an "Urgent Requirement
    D&F [Determination and Findings]." The D&F attached to the email seeks to justify a
    contract award exceeding one year under unusual and compelling urgency. The D&F
    states that the five-year IDIQ contract to be awarded to Potomac was not synopsized
    pursuant to FAR 6.302-2 (which provides that full and open competition is not
    required when the agency's need is urgent and compelling). However. the D&F in the
    next sentence states that the requirement was solicited competitively, posted on
    FedBizOpps, and proceeds to discuss the competitive offers received. The D&F also
    states that the purchase of the 800 motors over 1,825 days is urgent and compelling
    because the motors are on backorder. Finally, the D&F states that DO 0001 will be
    issued to fulfill an initial backorder of 200 motors in the amount of $784,476 followed
    by four additional delivery orders of 150 motors each. (R4, tab 8 at 1, 4 of 7)
    15. On August 28, 2017, the deputy chief counsel responded in an email that a
    Justification and Approval (J&A) would be the appropriate document for an
    acquisition on an urgent and compelling basis instead of a D&F. He also stated that an
    IDIQ contract, which would allow for future orders of non-urgent material, would not
    be the appropriate instrument under FAR 6.302-2. Rather, he recommended that the
    initial backorder of 200 motors be fulfilled as urgent and compelling and justified in a
    J&A, and that future quantities be procured under full and open competition resulting
    in the award of an IDIQ contract. (R4, tab 9)
    16. On August 28, 2017, the CO signed a Contract Clearance Request (CCR)
    requesting review and approval of the FPNM attached to the CCR8 (R4, tab 10).
    17. On August 29, 2017, the contract specialist sent an email to Potomac,
    stating:
    Please see attached solicitation amendment. Sorry to
    inform you. Subject solicitation had to be changed due to
    this requirement being Urgent and Compelling. Instead of
    7 The government asserts that the communications contained in tabs 8 and 9 of the
    Rule 4 file are covered by the attorney-client privilege. Further, that DLA
    waives the privilege for these documents for the limited purpose of
    demonstrating that the government had not reached a decision to enter into a
    contract, that a final approval had not been obtained, and to show the rationale
    of amending and canceling the solicitation.
    8
    The FPNM is not attached to the CCR provided in the Rule 4 file. It is not clear
    whether it is the same FPNM signed by the CO on August 18, 2017, which
    appears in tab 5 of the Rule 4 file.
    4
    a 5 year Indefinite Delivery Indefinite Quantity (IDIQ), it
    is now a One-Time Buy for a quantity of 200 each.
    When proposal is submitted, please copy everyone on
    email.
    Any questions, notify Contracting Officers, Henry Daniels
    and Angela Clark.
    (R4, tab 11 at 1)
    18. On August 2 9, 201 7, Potomac sent an email responding to the government,
    stating:
    Only after our phone conversation with Mr. Daniels this
    morning we realized the following: The DLA sent us the
    amendment of the solicitation SPRRA2-l 7-00531.l
    1. The solicitation SPRRA2-l 7-0053 had closed on July 7.
    4:30PM, 2017 ET.
    2. The government did not conduct any discussions or
    negotiations with Potomac Electric in reference to our
    proposal [.]
    3. We received the award letter from Mr. Harrison on
    August 16th, 2017. We signed the contract ( and first year
    release) a few days later and proceeded with procurement
    of materials.
    We also wrote to Mr. Harrison several times on contractual
    matters.
    It appears to Potomac Electric that the government decided
    to nullify our award, reopen the solicitation that has been
    closed a month ago, amended it and is now seeking new
    proposals from suppliers.
    We respectfully ask the government to clarify its position
    and actions toward Potomac Electric.
    (R4, tab 12)
    19. On September 7, 2017, the chief of DLA tactical division emailed Potomac
    ·'apologizing for all of the hardships we have put you through with this requirement"
    and stated that due to government errors the initial solicitation SPRRA2-17-R-0053 had
    not been synopsized which constituted a violation of the FAR. The government stated:
    "We mistakenly thought we could avoid a synopsis because the first delivery order
    5
    would be issued to satisfy an urgent requirement.'' The government further stated:
    "We discovered these errors after we had evaluated responses and sent you a 'DRAFT'
    copy of the award for review" (capitalization in the original text) and thus the
    government had ··cancelled the prior solicitation." The government concluded: "Since
    the solicitation was never awarded, a debriefing was not and shall not be conducted
    with any other interested bidders." (R4, tab 14 at 2-3)
    20. On October 2, 2017. Potomac submitted a claim to the CO for $27.000 for
    costs incurred in performance of the contract between August 16, 2017. the date of
    contract award, and August 29.2017. the date Potomac stopped working on the
    contract (R4, tab 15 ).
    21. On October 4, 2017, the CO sent an email to Potomac stating that since no
    contract had been awarded to Potomac, she "lack[ ed] jurisdiction" to resolve
    Potomac's request for monetary compensation and that no further action would be
    taken upon Potomac's request (R4, tab 16).
    22. On October 15, 2017, Potomac filed an appeal with the Board, docketed as
    
    ASBCA No. 61371
    .
    23. On February 2, 2018. the government filed an answer accompanied by the
    instant motion, arguing that undisputed facts before the Board prove that no contract
    ever existed and as such. the government is entitled to summary judgment.
    24. In support of its motion for summary judgment, the government submitted
    an affidavit by the contract specialist stating that he does not have a contracting
    officer's warrant and that he does not have authority to make a final award decision
    (gov't mot., encl. 1,, 3). The contract specialist affirmed that he typically sends out a
    draft award to the contractor after he has decided which contractor he will recommend
    for award, to ensure the terms and conditions are acceptable to the contractor before he
    moves forward with the approval process and that he asks for the contractor's
    signature so that, after the award is approved, the CO can sign the same document
    signed by the contractor (id. , 5). The contract specialist also stated that he prepared
    and signed the FPNM on August 18, 201 7, and then forwarded it to the CO for
    signature (id. , 8).
    DECISION
    Should the Board decide that no contract existed it would have no jurisdiction
    to entertain this appeal, as the Board's jurisdiction stems from the Contract Disputes
    Act, 
    41 U.S.C. §§ 7101-7109
    , which requires a contract between appellant and the
    United States. However, an appellant ··need only make a non-frivolous allegation" of
    a contract to establish the Board's jurisdiction. Leviathan Corporation, ASBCA
    6
    I
    No. 58659, 16-1 BCA ,i 36,372 at 177,294 (citing Engage Learning, Inc. v. Salazar,
    
    660 F.3d 1346
    , 1353 (Fed. Cir. 2011)). "This burden does not require appellant to
    prove that a contract actually exists. as that question goes to the merits of appellant's
    claim rather than the Board's jurisdiction."' Anis Avasta Construction Co., 
    ASBCA No. 61107
    , 17-1 BCA ,i 36,838 at 179,517 n.2. Here, Potomac has met this low
    burden alleging it was awarded Contract No. SPRRA2-l 7-D-0028 on August 15, 2017
    ( comp!. at 1). However, the government has moved for summary judgment on the
    "dispositive threshold question" of whether there was a contract between the parties
    (gov't mot. at 1).
    I. Summary Judgment Standard
    Summary judgment is appropriate when there is no genuine issue as to any
    material fact, and the moving party is entitled to judgment as a matter of law. Mingus
    Constructors, Inc. v. United States. 
    812 F.2d 1387
    , 1390-91 (Fed. Cir. 1987). A
    material fact is one that may affect the outcome of the decision. Anderson v. Liberty
    Lobby, Inc., 4 
    77 U.S. 242
    , 248-49 (1986 ). A genuine issue of material fact arises
    when the non-movant presents sufficient evidence upon which a reasonable fact finder,
    drawing the requisite inferences and applying the applicable evidentiary standard,
    could decide the issue in favor of the non-movant. C. Sanchez & Son, Inc. v. United
    States, 
    6 F.3d 1539
    , 1541 (Fed. Cir. 1993). The moving party bears the burden of
    establishing the absence of any genuine issue of material fact, and all significant doubt
    over factual issues must be resolved in favor of the party opposing summary judgment.
    Celotex Corp. v. Catrett, 
    477 U.S. 317
    , 322 (1986).
    II. There is a Genuine Dispute as to Whether There was a Contract
    The government contends that summary judgment is appropriate because the
    undisputed facts support that there was no contract between the parties (gov't mot.
    at 2). Although not directly addressing the government's argument head first,
    appellant disputes this assertion (app. reply at 1; app. supp. reply at 1).
    Relying on D&N Bank v. United States, 
    331 F.3d 1374
     (Fed. Cir. 2003), the
    government argues that the four elements necessary to prove the existence of a
    contract with the Federal Government, i.e., mutuality of intent to contract;
    consideration; lack of ambiguity in offer and acceptance; and authority on the part of
    the government representative to bind the government, are absent in this case. We
    examine whether undisputed facts support the absence of each of these elements.
    A. Mutuality of Intent to Contract
    The government argues that the parties never reached an agreement based on
    the facts that the contract specialist provided a "draft'' contract to Potomac (gov't mot.
    7
    II
    r
    l
    I
    at 5); that government personnel never believed that the government had entered into a
    contract (id. at 5-6); and that the government never signed the contract (id. at 7).
    It is undisputed that the contract specialist stated on his email to Potomac that
    the document he was forwarding was a draft (SOF, 4 ). It is also undisputed that the
    document that the contract specialist sent to Potomac showed on its face the legend
    '·Award/Contract" and bore a contract number (SOF, 5) as distinguishable from the
    previous document that had been sent to Potomac, which on its face showed the legend
    "Standard Form 33, Solicitation, Offer and Award'' and bore a solicitation number
    (SOF  ,,i1, 5). Potomac believed that DLA awarded it a contract (SOF ,, 11, 18).
    Whether the document was a contract or a draft is a fact in dispute that may affect the
    outcome of this appeal, and thus precludes summary judgment. Liberty Lobby, 
    477 U.S. at 249
    .
    The government argues that there was not mutuality of intent because
    government personnel did not believe they had entered into a contract, as evidenced by
    the DLA branch chief not signing the FPNM (SOF ,i 10), and by the statements of the
    chief of DLA tactical division in her email to the attorney containing the D&F
    (SOF ,i 14 ). On the other hand, documents in the record suggest that Potomac believed
    a contract had been awarded. For example, Potomac pointed out that the delivery date
    was mistaken and the contract specialist corrected the delivery date (SOF, 8);
    Potomac signed and returned the corrected contract and DO (SOF ,i 11 ); and
    proceeded to procur,e the motors to meet the tight delivery schedule (SOF ,r 12). To
    paraphrase the court in D&N Bank, 
    331 F.3d at 1377
    , there must be more than a "cloud
    of evidence" to prove the government's lack of intent to enter into a contract. Here,
    the parties' opposing beliefs whether they were entering into a contract create a
    reasonable doubt as to whether there existed mutuality of intent to contract. Such
    doubt should be resolved in favor of the non-moving party. Mingus Constructors, 812
    F .2d at 13 91. The government has not shown that undisputed facts support that
    absence of mutuality of intent to contract in this appeal.
    DLA also asserts that there was no mutuality of intent because the government
    never signed the contract. It is undisputed that the government did not sign the
    contract (SOF ,i 6). Whether the contract was signed, however, is not "essential to the
    consummation of the contract." Anis Avasta, 17-1 BCA ,i 36,838 at 179,516 (quoting
    United States v. Purcell Envelope Co., 
    249 U.S. 313
    , 319 (1919)). What is necessary
    is evidence ofan intent to be bound. Anis Avasta, 17-1 BCA ,i 36,838 at 179,517
    (citations omitted). Here, a reasonable fact finder may conclude that the conduct of
    the parties suggests an intent to be bound. For example, the contract specialist issued a
    modification to the purported contract and DO to correct the delivery date as requested
    by Potomac (SOF ,i 8); Potomac signed the contract as corrected (SOF ,i 11 ); Potomac
    stated it must start procuring materials right away (SOF ,i 12); and the CO signed the
    FPNM in terms mirroring Potomac's offer and expressed her intent to award the
    8
    I
    I
    contract to Potomac ··as is"' (SOF ,i I 0). These are material facts that support opposing
    views that may affect the outcome of the decision. Liberty Lobby, 
    477 U.S. at 249
    .
    Accordingly, the government has not met its burden of showing that uncontroverted
    facts support the absence of mutuality of intent to contract.
    B. Consideration
    The government, in discussing the elements necessary to prove the existence of
    a contract, states: "Appellant here lacks all of these elements except consideration'"
    (gov't mot. at 2). The government offers no further discussion, and the Rule 4 file is
    devoid of relevant documentation. As the record is not clear with regard to this issue,
    summary judgment is not appropriate. See CiyaSoft Corp., ASBCA Nos. 59519,
    59913, 17-1 BCA ,i 36,731. Accordingly, the government has failed to meet its
    burden.
    C. Lack of Ambiguity in Offer and Acceptance
    The government asserts that undisputed facts show that there was ambiguity in
    offer and acceptance in that Potomac was still seeking clarification of the contract
    terms during the times relevant to this appeal (gov't mot. at 9). Potomac directly
    disputes this assertion (app. reply at 1-2; app. supp. reply at 1).
    Relying on Russell Corp. v. United States, 
    537 F.2d 474
     (Ct. Cl. 1976), the
    government avers that a definite offer and an unconditional acceptance must be
    established. While it is uncontroverted that Potomac sought clarification of technical
    details in its email of August 19, 2017 (SOF ,i 12), the facts in the record show that
    Potomac signed and returned to the government what Potomac believed to be a
    contract (SOF ,i 11 ). Other documents in the record suggest that the terms of
    Potomac's offer were mirrored in documents generated by DLA. For example, the
    SF 26, Contract Award (SOF iJ 5): the FPNM (SOF ,i 10); and the D&F (SOF ,i 14) all
    mirror the price of Potomac's offer, i.e., 200 motors in the base year for $784,476. We
    concur in principle with the court in Russell that a definite offer and an unconditional
    acceptance must be established. However, whether DLA unambiguously accepted
    Potomac's offer is a material issue of fact in dispute, precluding summary judgment in
    this appeal.
    D. Authority on the Part of the Government Representative to Bind the Government
    The government argues that summary judgment must be granted because it is
    an undisputed fact that Potomac never communicated with a CO (gov't mot. at 3). 9
    9
    The government also argues that the CO lacked authority because DLA failed to
    comply with regulatory requirements, such as obtaining contract clearance and
    9
    The government relies on Federal Crop Ins. Corp. v. Merrill, 
    332 U.S. 380
    ( 194 7), for the proposition that anyone entering into an arrangement with the
    government takes the risk of ascertaining that the official purporting to act for the
    government stays within the bounds of his authority. 
    Id. at 384
    . In the appeal at hand,
    it is uncontroverted that the contract specialist did not have authority to bind the
    government (SOF c; 24 ). However, the shadow of the CO looms large over the actions
    of the contract specialist. The CO was aware of the terms of Potomac's offer, which
    were reflected in the FPNM (SOF ,r 10) (signed before Potomac forwarded its signed
    contract to DLA) and in the D&F (SOF ,i 14) ( formulated after Potomac signed the
    contract), thus begging the question whether and to what extent the contract specialist
    acted as directed by the CO. In his affidavit, the contract specialist stated that he
    generally sends the contract to the contractor to sign first, so the CO can sign the same
    document (SOF ,i 24 ), which suggests the contract specialist sends out the document at
    the CO's direction. The contract specialist also stated in his affidavit that he prepared
    and signed the FPNM and then forwarded it to the CO for signature (id.). but the
    FPNM shows it was signed first by the CO and hours later by the contract specialist
    (SOF ,i 10 n.5), again raising the question whether it was the CO drafting the
    document with the contract specialist in the limited capacity of conveying information.
    Documentation of the communications between the contract specialist and the
    CO are notably absent from the record. While the facts in the record are not sufficient
    to answer these questions one way or another, they are sufficient to create doubt in the
    mind of a reasonable fact finder. C. Sanchez & Son, 6 F .3d at 1541. Such doubt must
    be resolved in favor of the non-movant. Celotex, 
    477 U.S. at 322
    . The government
    has not carried the burden of establishing the absence of genuine issue of material fact
    showing that the government representative lacked authority to bind the government.
    We have carefully considered DLA's argument that a valid contract does not
    exist between the parties. We conclude that there are genuine issues of material fact
    that preclude summary judgment, inter alia, whether the instruments in the current
    record document a contract between the parties, whether the exchanges and conduct of
    the parties support the existence of an agreement between DLA and Potomac, and
    whether the government official involved had authority to bind the government.
    'These issues are fact intensive and, based on the current record, are not ripe to be
    resolved by summary judgment.'' CiyaSoft, 17-1 BCA ,i 36,731 at 178,896 (citing
    Cooley Constructors, Inc., 
    ASBCA No. 57404
    . 11-2 BCA ~ 34.855 at 171.457).
    selecting the appropriate type of contract for an urgent and compelling purchase
    (gov't mot. at 8-9). We do not need to reach these issues, as the authority of the
    government representative is a material fact in dispute as discussed in the main
    text of this opinion.
    10
    CONCLUSION
    The motion is denied.
    Dated: March 11, 2019
    ~/
    /
    LIS B. YOUNG
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                        I concur
    RICHARD SHACKLEFORD                             OWEN C. WILSON
    Administrative Judge                            Administrative Judge
    Acting Chairman                                 Vice Chairman
    Armed Services Board                            Armed Services Board
    of Contract Appeals                             of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 613
     71, Appeal of Potomac
    Electric Corp., rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    11
    I