Environmental Chemical Corporation ( 2015 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                 )
    )
    Environmental Chemical Corporation           )     ASBCA No. 58871
    )
    Under Contract No. FA8903-06-D-8511          )
    APPEARANCES FOR THE APPELLANT:                     R. Dale Holmes, Esq.
    Amy M. Kirby, Esq.
    Justin J. Williams, Esq.
    Cohen Seglias Pallas
    Greenhall & Furman PC
    Philadelphia, PA
    Kevin J. Kelly, Esq.
    Corporate Counsel
    APPEARANCES FOR THE GOVERNMENT:                    Lt Col Matthew J. Mulbarger, USAF
    Air Force Chief Trial Attorney
    Anna F. Kurtz, Esq.
    Capt Christopher M. Kovach, USAF
    Trial Attorneys
    OPINION BY ADMINISTRATIVE JUDGE MCILMAIL ON APPELLANT'S
    MOTION TO AMEND COMPLAINT
    INTRODUCTION
    Appellant moves to amend its complaint to add two counts: one alleging
    unabsorbed overhead resulting from delay to the contract work, and one alleging
    breaches of the implied duty of good faith and fair dealing. We grant the motion in
    part, and deny the motion in part.
    STATEMENT OF FACTS FOR PURPOSES OF THE MOTION
    In April 2006, Air Force Materiel Command (Air Force) awarded Contract
    No. F8903-06-D-8511, an indefinite delivery, indefinite quantity Heavy Engineering
    and Repair (HERC) contract, to Environmental Chemical Corporation (ECC) (R4,
    tab 9 at 1-2). On 2 September 2011, the Air Force awarded Task Order 81 to the
    contract to ECC, for the design and construction of buildings and parking lots at
    Kandahar Air Field (KAF), in Afghanistan, for the fixed price of $22,974,828 (R4,
    tab 21at1-2). Task Order 81 required the construction of several buildings on KAF
    by 2 September 2012 (id. at 3). On 23 August 2012, the Air Force unilaterally issued
    Modification No. 3 to Task Order 81, combining some of the buildings, reducing the
    size of other buildings, and making other changes to the work (R4, tab 24 at 1, 39-40).
    Modification No. 3 also increased the contract price by $1,526,345, and extended the
    construction completion date by 129 days, to 9 January 2013 (id. at 2-3).
    On 24 January 2013, ECC presented to the contracting officer a claim for
    $4,363,296, for subcontractor costs associated with Modification No. 3, and for costs
    incurred during a 174-day period of alleged delay that ECC asserted was caused by the
    late issuance of Modification No. 3 from 2 March 2012 through 24 August 2012 (R4,
    tab 81 at 1-2, 13). 1 The claim references "substantial Govt.-initiated changes to the
    project design which were introduced soon after award of the Task Order on
    September 2, 2011" (id. at 1). The claim also references specific "design delays,"
    including ( 1) a proposal during a 19 September 2011 "initial design charrette" to
    combine several buildings into one complex; 2 (2) the issuance by the Air Force on
    21September2011 of a new statement of requirements (SOR) for Task Order 81; (3) a
    delay through 31 October 2011 of the submittal of the 3 5% design due to the new
    SOR; (4) the approval by the Air Force of the 35% design on 4 November 2011;
    (5) the issuance by the Air Force of further revisions to the SOR on 19 January 2012,
    and 23 February 2012; and (6) the issuance of Modification No. 3 and a notice to
    proceed (NTP) with that modification in August 2012 (id. at 11-13). On 8 March
    2013, ECC resubmitted its claim, reducing the claim amount to $4,274,135, and
    certifying that amount (R4, tab 84 at 3-4). On 28 March 2013, ECC submitted the
    claim for a third time, increasing the claim amount to $4,282,762 (R4, tab 89 at 8-9).
    On 25 April 2013, ECC certified the 28 March 2013 claim amount (R4, tab 92 at 6).
    From 2 April 2013 through 16 October 2013, two Air Force program managers
    provided the contracting officer a series of advice memoranda regarding the claim (R4,
    tabs 90, 96, 99, 100); the final memorandum recommended that an award to ECC of
    303 days (the 129 days awarded in Modification No. 3 plus the 174 days identified in
    the claim) was appropriate (R4, tab 100 at 6). On 11 September 2013, ECC filed this
    appeal from the deemed denial of its claim. On 15 October 2013, ECC filed its
    complaint, requesting $4,282,762 and a time extension of 181 days. On 6 November
    2013, the contracting officer issued a final decision awarding to ECC the $1,526,345
    amount set forth in Modification No. 3 (R4, tab 101 at 1, 9).
    On 8 June 2015, ECC filed a document, styled "Amended Complaint," which
    added two counts: (1) a request for breach damages for alleged violations of the
    1
    The claim letter erroneously refers to Modification No. 3 as "Modification No. 2"
    (R4, tab 81 at 1).
    2
    A "charrette" is a type of meeting. NEW OXFORD AMERICAN DICTIONARY 293
    (3d ed. 2010).
    2
    implied duty of good faith and fair dealing (Count 11), and (2) a request for "Eichleay"
    damages for allegedly unabsorbed overhead during the period 19 September 2011
    through 10 May 2012 (Count III). On 17 June 2015, the Air Force filed its opposition
    to amendment of the complaint, pointing out that ECC had not requested leave to
    amend, and contending that ( 1) amendment would prejudice the Air Force because
    discovery was scheduled to close on 27 June 2015, and because a hearing was
    scheduled to commence on 13 July 2015; and (2) the claims that were the subject of
    the amendment had not been presented to the contracting officer. The Air Force
    requested that if the motion were granted the hearing be postponed to allow it to
    conduct further discovery. On 24 June 2015, the Board rejected the motion because
    ECC had not requested leave to amend its complaint.
    On 26 June 2015, ECC requested leave to amend its complaint to add Counts II
    and III. The Air Force opposed the motion on 6 July 2015. On 9 July 2015, the Board
    deferred indefinitely a decision upon the motion. 3 During the period 13-17 July 2015,
    the Board conducted five days of hearing upon the issue of entitlement, including the
    taking of evidence on Counts II and III of the proposed amended complaint. At the
    conclusion of the fifth and final scheduled day of the entitlement hearing, the Air
    Force asserted that the prejudice to it if the motion to amend were granted would be
    erased if it were allowed to conduct further discovery upon, and have an opportunity to
    present further evidence upon, Counts II and III. ECC consented that the Air Force be
    able to conduct further discovery. The Board adjourned the hearing pending a
    decision regarding further proceedings. On 20 July 2015, the Board issued an order
    that the record would remain open pending, at the earliest, a decision upon appellant's
    motion to amend, but that no further evidence would be presented to the Board until
    further notice.
    DECISION
    Jurisdiction to entertain the proposed amendments to the complaint
    We have jurisdiction to entertain the appeal pursuant to the Contract Disputes
    Act, 41 U.S.C. §§ 7101-7109. The Board may permit a party to amend its pleading
    upon conditions fair to both parties. Board Rule 6(d) (revised 21 July 2014).
    However, the Board will deny a request to amend a complaint to add to the appeal
    what is tantamount to a new claim; that is, a claim that is based upon operative facts
    not already presented in the claim that is the subject of the appeal. GSC Construction,
    Inc., ASBCA No. 59046, 15-1BCA~35,882 at 175,429. That is because the Board
    does not possess jurisdiction, within a given appeal, to entertain a claim that is new to
    the appeal. 
    Id. at 175,430.
    3
    Board Rule 7(b) (2014) authorizes the Board to defer ruling on motions as
    appropriate.
    3
    However, rigid adherence to the exact language or structure of the original
    claim is not required. Scott Timber Co. v. United States, 
    333 F.3d 1358
    , 1365 (Fed.
    Cir. 2003). The Board possesses jurisdiction to entertain claims that arise from the
    same operative facts as those presented to the contracting officer, claim essentially the
    same relief, and merely assert differing legal theories for that recovery. 
    Id. New or
    modified allegations in an amended complaint that do not change the operative facts of
    the claim to the contracting officer, or change the essential nature of those facts, do not
    constitute a new claim. See Lockheed Martin Aircraft Center, ASBCA No. 55164,
    07-1BCA~33,472 at 165,934.
    Count II: Breach of the implied duty ofgood faith and fair dealing
    Count II of the proposed amended complaint seeks unquantified breach
    damages for the following alleged breaches of the implied duty of good faith and fair
    dealing by the Air Force: (1) failure to issue a timely revised SOR, (2) issuance of
    multiple, revised SOR over a period of months, (3) refusal to issue a "full" NTP to
    allow construction to proceed until 356 days into contract performance, and
    (4) "refusal to issue a modification for [ECC's] delay costs when those costs had been
    found to be due, and instead signing an arbitrary Final Decision denying those costs"
    (am. compl. `` 79-80). The claim to the contracting officer includes references to
    some of the events that Count II alleges. For example, the claim references the wait
    for a revised SOR, the receipt of more than one revised SOR, and the issuance-nearly
    a year after the award of the Task Order 81 and more than 11 months after the initial
    design charrette--of a notice to proceed with Modification No. 3. Accordingly, we find
    that the claim to the contracting officer presents the operative facts from which arise
    items (1), (2), and (3) of paragraph 79 of Count II of the proposed amended complaint,
    providing the Board's jurisdiction to entertain those elements of Count II.
    However, the Board does not possess jurisdiction to entertain ECC's claim that
    the Air Force breached the implied duty of good faith and fair dealing by signing an
    "arbitrary" final decision subsequent to refusing to issue a modification for certain
    delay costs. From the proposed amended complaint, we understand that claim to rest
    upon allegations that the contracting officer signed a final decision awarding to ECC
    only the same $1,526,345 and 129 delay days set forth in Modification No. 3, despite
    the advice of Air Force program managers that that ECC was entitled to more delay
    days (am. compl. `` 73-78). However, the claim to the contracting officer does not set
    forth those facts, which is not surprising because ECC prepared the final version of its
    claim on 28 March 2013, before the program managers provided their advice, and
    before the contracting officer signed his final decision. Consequently, the Board does
    not possess jurisdiction to entertain ECC's Count II claim that the Air Force breached
    the implied duty of good faith and fair dealing by "refus[ing] to issue a modification
    for [ECC' s] delay costs when those costs had been found to be due, and instead
    signing an [allegedly] arbitrary Final Decision denying those costs" (am. compl. ~ 79).
    4
    Count III: Eichleay damages
    The Board possesses jurisdiction to entertain ECC's Eichleay claim. Count III
    of the proposed amended complaint seeks $446,060.16 in Eichleay damages to recover
    for allegedly unabsorbed home office overhead during what ECC alleges was a
    government-created indefinite suspension of work that began on 19 September 2011
    and ended on 10 May 2012 (am. compl. `` 81-88). ECC alleges that "[o]ther than
    mobilization to the project site, and limited work on the 35% design, [the Air Force's]
    actions during the September 19, 2011 Design Charrette, and contract administration
    decisions thereafter, placed [ECC] in a near total indefinite suspension of work on the
    project, until [the Air Force] issued a partial NTP on May 10, 2012," and that
    "[b]ecause of the indefinite suspension of work during the Design Charrette, [ECC]
    was greatly limited, after mobilization, in work and contract earnings that were
    available, until [the Air Force] issued the partial NTP at [ECC's] request on May 10[,]
    2012" (am. compl. `` 82-83).
    In our view, the Eichleay claim arises from the same set of operative facts that
    were presented in the claim submissions to the contracting officer, adds some new or
    modified allegations that do not change those facts or their essential nature, claims
    essentially the same relief, and merely asserts a differing legal theory for that recovery.
    Therefore, the Eichleay claim is not new to the appeal. The Eichleay claim is
    essentially consistent with the account presented to the contracting officer that ECC
    was entitled to recover the cost of delays that began with a proposal on 19 September
    2011 to change the statement of requirements, and ended in August 2012 with the Air
    Force issuing a notice to proceed with Modification No. 3. Although the claim to the
    contracting officer seeks costs for only one period of specific delay-from 2 March
    2012 through 24 August 2012-the allegations in the proposed amended complaint that
    ECC was in a near-total suspension with limited earnings can be reasonably inferred
    from ECC's account in the claim presented to the contracting officer that before the
    issuance of the notice to proceed with Modification No. 3, ECC performed only
    35% design work. The allegation in Count III that the Air Force issued a partial NTP
    on 10 May 2012, although new, merely limits the Eichleay claim to a portion of the
    19 September 2011through24 August 2012 timeline presented to the contracting
    officer. Indeed, 69 days of the 19 September 2011through10 May 2012 Eichleay
    period alleged in the amended complaint overlap with the 2 March 2012 through
    24 August 2012 "schedule impact" period that the claim to the contracting officer calls
    out expressly. That is, the two periods have 2 March 2012 through 10 May 2012 in
    common. Finally, Count III requests essentially the same relief requested in the claim
    to the contracting officer: costs that ECC contends it incurred as a result of what it
    characterizes as the Air Force's delay of the project.
    Trepte Construction Co., ASBCA No. 38555, 90-1BCA~22,595, upon which
    the Air Force relies, is meaningfully distinct from these circumstances. In Trepte, the
    5
    Board struck from an amended complaint a constructive acceleration claim, finding
    that the claim had not been presented in the delay claim submitted to the contracting
    officer. 
    Id. at 113,385-86.
    The Board rejected the contractor's contention that the
    constructive acceleration claim was not new, explaining that the basic operative facts
    necessary to establish such a claim (including an express or implied government order
    to overcome excusable delay or to complete performance by a date earlier than that by
    which the contractor was entitled to perform) "are substantially different than those by
    which entitlement to delay costs can be ascertained." 
    Id. at 113,386.
    Here, too, ECC
    presented a delay claim to the contracting officer; however, unabsorbed overhead
    resulting from suspension of work by the government, such as that sought in Count III,
    is a form of delay damages. See Ricway, Inc., ASBCA No. 29983, 86-2 BCA ii 18,841
    at 94,955. Moreover, we have found that the claim presented to the contracting officer
    sets forth the facts from which the allegations in Count III that Air Force delays placed
    ECC in a near-total, indefinite suspension of work can be reasonably inferred.
    Prejudice
    In consideration of the evidence taken during the five days of entitlement
    hearing, the Air Force has advised that the prejudice that it contends it would suffer
    from the amendment of the complaint to add Counts II and III would be erased if it
    were allowed to conduct some limited discovery upon those counts. In view of the
    Board's jurisdictional ruling, the Air Force may conduct such discovery and present
    additional evidence upon entitlement regarding items (1), (2), and (3) of paragraph 79
    (from Count II), as well as upon Count III.
    CONCLUSION
    For these reasons, the motion to amend the complaint is granted in part, and
    denied in part. The motion is denied with respect to the claim in Count II of the
    proposed amended complaint that the Air Force breached the implied duty of good
    faith and fair dealing by "refusal to issue a modification for [ECC's] delay costs when
    those costs had been found to be due, and instead signing an arbitrary Final Decision
    denying those costs" (am. compl. iii! 73-78, item (4) ofiJ 79). 4 The motion is
    otherwise granted. The Air Force may conduct additional discovery, and present
    additional evidence regarding entitlement, upon the new claims, consistent with this
    4
    We express no opinion on whether such a claim without the jurisdictional issue
    involved here is a claim within the meaning of the Contract Disputes Act.
    6
    op1mon. The evidentiary record upon entitlement regarding those items remains open.
    The Board will address a schedule for further proceedings in a separate order.
    Dated: 14 September 2015
    Administrati e Judge
    Armed Services Board
    of Contract Appeals
    I concur                                         I concur
    ``
    Administrative Judge
    Rl~KLEFORD
    Administrative Judge
    Acting Chairman                                  Vice Chairman
    Armed Services Board                             Armed Services Board
    of Contract Appeals                              of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA No. 58871, Appeal of
    Environmental Chemical Corporation, rendered in conformance with the Board's
    Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    7
    

Document Info

Docket Number: ASBCA No. 58871

Judges: McIlmail

Filed Date: 9/14/2015

Precedential Status: Precedential

Modified Date: 9/28/2015