Certified Construction Company of Kentucky, LLC ( 2015 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                  )
    )
    Certified Construction Company of             )      
    ASBCA No. 58782
    Kentucky, LLC                                )
    )
    Under Contract No. W9124D-06-D-0001           )
    APPEARANCES FOR THE APPELLANT:                       Thomas E. Roma, Jr., Esq.
    G. Alan Oliver, Esq.
    Ackerson & Yann, PLLC
    Louisville, KY
    APPEARANCES FOR THE GOVERNMENT:                      Raymond M. Saunders, Esq.
    Army Chief Trial Attorney
    CPT Harry M. Parent, III, JA
    CPT Tyler L. Davidson, JA
    Trial Attorneys
    OPINION BY ADMINISTRATIVE JUDGE PAGE ON THE PARTIES'
    CROSS-MOTIONS FOR SUMMARY JUDGMENT
    This appeal arises under Contract No. W9124D-06-D-0001 (contract) between
    the Department of the Army (Army or government) and Certified Construction
    Company of Kentucky, LLC (Certified or contractor). Certified appeals from a
    contracting officer's (CO's) final decision (COFD) denying Certified's monetary
    claim resulting from an increase in the costs of liquid asphalt during performance. In a
    previous decision, we dismissed for lack of jurisdiction the portion of Certified's claim
    accruing prior to 22 March 2007 as time-barred under the Contract Disputes Act's
    (CDA's), 
    41 U.S.C. §§ 7101-7109
    , six-year statute oflimitations. Certified
    Construction Co. ofKentucky, LLC, 
    ASBCA No. 58782
    , 14-1BCA~35,662. The
    parties have filed cross-motions for summary judgment on the portion of Certified's
    claim over which we exercised jurisdiction.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTIONS
    The parties have submitted a Joint Stipulation of Material Facts (Jt. Stip.). The
    following facts are not in dispute.
    1. On 24 October 2005, the Anny awarded the requirements contract to
    Certified via sealed bidding procedures (Jt. Stip. ~ 1; R4, tab 17 at 3 1). Through task
    orders issued under the contract, Certified provided road construction and repair
    including concrete placement, asphalt surface treatments, and pavement markings at
    Fort Knox, Kentucky (Jt. Stip. ~ 4; R4, tab 20 2 at 1-2, 4). The period of performance
    was from 1 November 2005 to 31 October 2006, with a single one-year option period
    (R4, tab 20 at 1, 4).
    2. The contract included the following relevant Federal Acquisition Regulation
    (FAR) clauses: 52.233-1, DISPUTES (JUL 2002)-ALTERNATE I (DEC 1991);
    FAR 52.216-21, REQUIREMENTS (OCT 1995)-ALTERNATE I (APR 1984);
    FAR 52.217-8, OPTION TO EXTEND SERVICES (Nov 1999); FAR 52.217-9, OPTION TO
    EXTEND THE TERM OF THE CONTRACT (MAR 2000) (R4, tab 20 at 49, 51-52). The
    contract also included Defense Federal Acquisition Regulation Supplement (DFARS)
    clause 252.243-7002, REQUESTS FOR EQUITABLE ADJUSTMENT (MAR 1998) (id. at 50).
    3. The contract required work to be performed in accordance with technical
    specifications contained in the document identified as "P.E. 3-05," dated 6 July 2005
    (R4, tab 20 at 79). The provisions within "P.E. 3-05" entitled "PART I
    TECHNICAL PROVISIONS DIVISION 2 - SECTION 2B GENERAL
    CONSTRUCTION" (General Construction specifications) provided, in relevant part:
    1. APPLICABLE PUBLICATIONS: The following
    publication is hereby incorporated by reference into the
    specifications for this project:
    Standard Specification for Road and Bridge
    Construction,
    Kentucky Department of Highways, latest edition
    www.kytc.state.us/construction/spec2000l 3l
    1
    Citations of this document in the Rule 4 file are to the Bates-numbered pages unless
    indicated otherwise.
    2 The Rule 4 file includes two different copies of the awarded contract under tabs 1
    and 20. The contract under tab 1 contains 361 pages and is only signed by the
    CO; the copy under tab 20 contains 14 7 pages and is signed by both parties.
    Since block 28 of Standard Form 1442 is checked and requires the signature of
    the contractor, citations are to the copy under tab 20. The two versions of the
    contract do not differ with respect to relevant provisions.
    3 Appellant submitted a bound copy of the Kentucky Transportation Cabinet/Department
    of Highways, Standard Specifications for Road and Bridge Construction (2004
    ed.) (KDOH Specifications), and the parties agree that this edition is applicable
    (Jt. Stip. ~ 3). We mark this copy for the record as Rule 4, tab 22.
    2
    2. GENERAL: All work and materials shall conform to
    the applicable requirements of Section 200 through Section
    800 of the Kentucky Department of Highways (KDOH)
    Specifications except as noted in these specifications or
    contract documents. In case of difference between KDOH
    Specifications and the CONTRACT CLAUSES the
    CONTRACT CLAUSES shall govern.
    3. ABBREVIATIONS AND DEFINITIONS: Standard
    abbreviations shall be in accordance with Section 101.01
    of the KDOH Specifications. Where such terms as
    "Chairman'', "Commission'', "Engineer", or "Department"
    are used, they shall mean "Contracting Officer".
    Whenever the works [sic] "Extra Work" or similar phrase
    is used, it shall mean "Changes" as defined in the
    CONTRACT CLAUSES.
    4. CONTROL OF MATERIALS: Control of materials
    shall be in accordance with Section 106 ofKDOH
    Specifications in addition to the requirements of the
    CONTRACT CLAUSE.
    5. EXCEPTIONS TO KDOH SPECIFICATIONS:
    5.1 Measurement and Payment paragraphs shall not
    mmlY· All work shall be included in the unit price items listed
    in the bid schedule that is part of these contract documents.
    (R4, tab 20 at 97; Jt. Stip.   ~   2) (Emphasis added)
    4. The KDOH Specifications, Divisions 100-800 contain a number of
    references to "Measurement" and "Payment" provisions. See, e.g., Division 100,
    General Provisions, § 109 Measurement and Payment (R4, tab 22 at 109-1-109-12);
    Division 200, Earthwork, § 201 Staking, ~ 201.4 Measurement and ~ 201.05 Payment
    (id. at 201-2); § 202 Clearing and Grubbing,~ 202.04 Measurement and~ 202.05
    Payment (id. at 202-1-202-2); and§ 303 Pavement Drainage Blanket,~ 303.04
    Measurement and~ 303.05 Payment (id. at 303-4-303-5).
    5. The contract included numerous contract line item numbers (CLINs)
    providing estimated quantities and unit pricing for various work to be performed. In
    accordance with the General Construction specifications, CLINs 0072 and 1072
    provided for the installation of a "Bituminous concrete surface course," and CLINs
    0073 and 1073 provided for the installation of a "Bi[t]uminous concrete binder course"
    (R4, tab 20 at 15-16, 37).
    3
    6. On 30 October 2006, the CO executed Modification No. P00005, exercising
    the option period and extending the term of the contract to 31 October 2007 (R4, tab 7).
    7. On 3 October 2007, the CO executed unilateral Modification No. P00009,
    extending the period of performance of the contract to 30 April 2008 (R4, tab 11 ).
    8. By letter dated 17 September 2012, Certified submitted a request for
    equitable adjustment (REA), seeking an equitable adjustment to the contract in the
    amount of $839,052.31 for additional incurred costs resulting from the increase in
    prices of petroleum products, specifically liquid asphalt, used for the production of
    asphalt hot mixes under CLINs 0072, 0073, 1072, and 1073 (R4, tab 15; Jt. Stip. `` 3,
    6). In calculating its request, Certified relied on Section 109.07 of the KDOH
    Specifications entitled "PRICE ADJUSTMENTS" which provides in relevant part:
    109.07 PRICE ADJUSTMENTS. Due to the fluctuating
    costs of petroleum products, the Department will adjust the
    compensation of specified liquid asphalt items ....
    109.07.01 Liquid Asphalt. The Department will
    list a base price for liquid asphalt products in the Bid
    Proposal for applicable projects. The Department will
    compare the Kentucky Average Price Index, for the month
    that the Contract is let, to the index for the month that the
    Contractor places the material on the project to determine
    the percent change. When the original contract quantity
    for asphalt items is equal to or greater than 3,000 tons and
    when the average price of the liquid asphalt products
    increases or decreases more than 10 percent, the
    Department will adjust the Contractor's compensation.
    (Id.; R4, tab 22)
    9. By letter dated 19 October 2012, the CO denied Certified's REA, asserting
    that subparagraph 5 .1 of the General Construction specifications in the contract
    specifically excluded Section 109 of the KDOH Specifications (R4, tab 16; SOF ~ 3;
    Jt. Stip. ~ 7).
    10. By letter dated 22 March 2013, Certified converted its REA into a certified
    claim for $839,052.31, demanding, as a matter of right, the amount requested in its
    REA (SOF ~ 7). Certified asserted that it was entitled to the difference in "increased
    cost of performance resulting from the unprecedented increase in the price of Liquid
    4
    Asphalt" from the time it submitted its bid pricing to performance of the contract.
    Certified disagreed with the CO's interpretation, maintaining that Section 109 of the
    KDOH Specifications was not explicitly excluded, and that the intent of subparagraph
    5.1 of the General Construction specifications was to exclude the measurement and
    payment paragraphs within Sections 200 thru 800 of the KDOH Specifications as
    provided under paragraph two of the General Construction specifications. (R4, tab 17
    at 1-2; SOF ~ 3; Jt. Stip. ~ 8)
    11. On 31 May 2013, the CO issued a final decision denying Certified's claim
    in its entirety. The COFD asserted that the relevant technical provisions did not
    incorporate the KDOH Specifications in their entirety, and specific sections of the
    KDOH Specifications applicable to the contract were explicitly incorporated. Lastly,
    the CO asserted that measurement and payment paragraphs of the KDOH
    Specifications, including Section 109, did not apply. (R4, tab 18; Jt. Stip. ~ 9)
    12. On 16 July 2013, Certified appealed the 31May2013 CO's final decision
    to the Board (Jt. Stip. ~ 10).
    13. On 8 July 2014, the Board granted the government's partial motion to
    dismiss with respect to the portion of Certified's claim that accrued prior to
    22 March 2007, more than six years before Certified's 22 March 2013 claim date.
    That portion of the appeal was dismissed for lack of jurisdiction under the CDA.
    14. The parties stipulate that Certified's claim accruing after 22 March 2007 is
    for a sum certain amount of $606,707.55 (Jt. Stip. ~ 12).
    DECISION
    On 8 July 2014, we issued our opinion, Certified Construction Co. of Kentucky,
    LLC, 14-1BCA~35,662, partially dismissing the portion of Certified's claim accruing
    prior to 22 March 2007 for lack of jurisdiction because that portion was time-barred
    under the CDA's six-year statute oflimitations (SOF ~ 12). Subsequent to the
    issuance of our decision, the United States Court of Appeals for the Federal Circuit in
    Sikorsky Aircraft Corp. v. United States, 
    773 F.3d 1315
     (Fed. Cir. 2014), reversed its
    line of cases holding that the CDA' s statute of limitations was jurisdictional. By
    correspondence dated 26 March 2015, we directed the parties to provide supplemental
    briefing on the effect of the Sikorsky decision on the parties' cross-motions for
    summary judgment. The government responded that Sikorsky did not impact the
    parties' cross-motions and "the rationale of the Partial Motion to Dismiss is still valid"
    (gov't supp. hr. at 2). While asserting that the Board's 8 July 2014 partial dismissal
    was erroneous in light of the Sikorsky decision, Certified agreed that the cross-motions
    are ready for adjudication as Sikorsky's effect would bear on the issue of quantum
    rather than entitlement (app. supp. hr.). After consideration of the parties' views and
    re-examining our 8 July 2014 decision, based on Sikorsky and the findings in our
    5
    decision, we conclude that on the merits, the portion of Certified's claim dismissed in
    that decision for lack of jurisdiction is properly time-barred by the CDA. We next
    proceed toward resolution of the parties' cross-motions for summary judgment.
    1. Summary Judgment
    Matters of contract interpretation are questions of law and are amenable for
    resolution through summary judgment. Varilease Technology Group, Inc. v. United
    States, 
    289 F.3d 795
    , 798 (Fed. Cir. 2002). The guidelines for summary judgment are
    well established; the granting of summary judgment is appropriate where there are no
    genuine issues of material fact and the movant is entitled to favorable judgment as a
    matter oflaw. Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    , 255 (1986); DIRECTV
    Group, Inc. v. United States, 
    670 F.3d 1370
    , 1374 (Fed. Cir. 2012); Osborne
    Construction Co., 
    ASBCA No. 55030
    , 09-1 BCA ii 34,083 at 168,512. The parties'
    cross-motions are evaluated on their own merits, and we are not obligated to "grant
    judgment as a matter of law for one side or the other; summary judgment in favor of
    either party is not proper if disputes remain as to material facts." Mingus
    Constructors, Inc. v. United States, 
    812 F.2d 1387
    , 1391 (Fed. Cir. 1987). While the
    parties have jointly stipulated that there are no genuine issues of material fact to their
    respective positions on the issue of contract interpretation, we are "not bound by the
    concessions or stipulations by either party that are contrary to the evidence or the law."
    General Atronics Corp., 
    ASBCA No. 37923
    , 91-3 BCA ii 24,047 at 120,360 (citing
    Kaminer Construction Corp. v. United States, 
    488 F.2d 980
     (Ct. CL 1973)).
    The movant has the burden to establish that there are no material facts in
    dispute. A material fact is one which may affect the outcome of the case. Liberty
    Lobby, 
    477 U.S. at 248
    . At the summary judgment stage, we do not resolve
    controversies, weigh evidence, or make determinations of credibility. 
    Id.
     at 25 5. All
    reasonable inferences are drawn in favor of the nonmovant. Id.
    2. The Parties' Contentions
    The parties filed, with their cross-motions for summary judgment, a Joint
    Stipulation of Material Facts, and thus, aver that there are no genuine issues of
    material fact. The disputed matter is over the proper interpretation of subparagraph
    5.1 of the General Construction specifications. Each party asserts that it is entitled to
    judgment as a matter oflaw, with each arguing that its respective interpretation of the
    subparagraph is plainly supported and reasonable. Certified largely contends that the
    subparagraph did not expressly exclude Section 109 of the incorporated KDOH
    Specifications upon which it relied as the basis for its claim. In reaching this
    interpretation, Certified argues that the intention of the first sentence of the
    subparagraph, which states "Measurement and Payment paragraphs shall not apply,"
    was a limitation applicable to Sections 200 thru 800 of the KDOH Specifications,
    sections referenced under paragraph two of the General Construction specifications.
    6
    (App. mot. at 4-7) According to Certified, this is the correct reading because the
    CLINs in the contract contain unit pricing for the type of work to be accomplished in
    accordance with those specific KDOH Specifications (app. mot. at 7-8).
    The government disagrees with Certified' s interpretation, arguing that
    Certified's interpretation is unreasonable because it would render meaningless the
    exclusion of measurement and payment provisions explicitly stated in the first
    sentence of subparagraph 5.1. Additionally, the government argues that Certified's
    interpretation would subject the firm-fixed unit pricing in the contract to adjustments
    under the payment provisions in the KDOH Specifications inconsistent with the
    second sentence that states "[a]ll work shall be included in the unit price items listed."
    (Gov't mot. at 4-6) Therefore, the government contends that the only reasonable
    interpretation of subparagraph 5 .1 is the express exclusion of any payment provisions
    in the KDOH Specifications, including Section 109 (gov't mot. at 6-7).
    The parties also present alternative arguments if the underlying language of the
    subparagraph is deemed ambiguous, and they disagree as to the type of ambiguity.
    The government argues that any ambiguity regarding excepted contract provisions
    pertaining to "Measurement and Payment" should be considered patent, and imposing
    upon Certified the duty to inquire and seek clarification prior to submitting its bid for
    the contract (gov't mot. at 8). Certified counters that such an ambiguity should be
    considered latent, arguing that the ambiguity did not become apparent until Certified
    became aware of the CO's position concerning whether Section 109 of the KDOH
    Specifications was excluded (app. resp. to gov't mot. at 7). Certified argues that it
    should recover under the doctrine of contra proferentem as the ambiguity should be
    construed against the government (id.).
    3. Contract Interpretation
    Contract interpretation begins with examination of the plain language of the
    written agreement. LAI Services, Inc. v. Gates, 
    573 F.3d 1306
    , 1314 (Fed. Cir. 2009).
    The terms are given their plain and ordinary meaning. If the contract language is clear
    and unambiguous, the plain language controls, extrinsic evidence is not allowed to
    contradict the plain language, and resolution through summary judgment is amenable.
    Coast Federal Bank, FSB v. United States, 
    323 F.3d 1035
    , 1040 (Fed. Cir. 2003);
    Pacific Coast Community Services, Inc., 
    ASBCA No. 56754
    , 10-1BCA~34,421 at
    169,912. The contract terms are interpreted and read as a whole, giving reasonable
    meaning to all of its parts, and without leaving "a portion of the contract useless,
    inexplicable, void, or superfluous." NVT Technologies, Inc. v. United States, 
    370 F.3d 1153
    , 1159 (Fed. Cir. 2004).
    Contract language is clear and unambiguous when there is only one reasonable
    interpretation consistent with the plain meaning. LAI Services, 
    573 F.3d at 1314
    . A
    contract term is not rendered ambiguous just by the parties' disagreement as to the
    7
    interpretation alone; a party's respective interpretation "must fall within a 'zone of
    reasonableness.'" Metric Constructors, Inc. v. NASA, 
    169 F.3d 747
    , 751 (Fed. Cir.
    1999). If the contract language supports more than one reasonable interpretation, and
    the weighing of extrinsic evidence is required to determine the parties' intent to
    resolve the ambiguity, summary judgment is not appropriate. MIC/CCS, Joint
    Venture, 
    ASBCA No. 58023
    , 14-1 BCA ii 35,678 at 174,637-38.
    Ambiguities fall under two categories - an ambiguity is either patent or latent.
    If there is an ambiguity, the general rule of contra proferentem is to construe the
    ambiguous contract language against the drafter. Metric Constructors, 
    169 F.3d at 751
    . However, a patent ambiguity is an exception to the general rule where the
    ambiguity is "sufficiently glaring to trigger" a contractor to inquire before a bid is
    submitted. HPl/GSA-3C, LLC v. Perry, 
    364 F.3d 1327
    , 1334 (Fed. Cir. 2004). The
    patent ambiguity is construed against the contractor. 
    Id.
     If an ambiguity does not
    meet the patent ambiguity exception and is latent, the general rule may be applied, but
    the contractor's interpretation must be determined to be reasonable. Id.
    4. Analysis
    We agree that there are no material facts in dispute for these cross-motions, and
    the issue involves a matter of pure contract interpretation. Initially, we must determine
    whether the parties' interpretations are reasonable based on the plain language of the
    contract, and then, if more than one reasonable interpretation is supported, whether the
    existing ambiguity is patent or latent. Upon closer examination of the language within
    subparagraph 5 .1 of the General Construction specifications, and taking into account
    that we must interpret the terms as a whole and give reasonable meaning to all parts of
    the contract, we find that the government's interpretation is the only reasonable
    interpretation of the subparagraph. It is clear that the KDOH Specifications were
    expressly incorporated by reference into the contract under paragraph one of the
    General Construction specifications. Subparagraph 5 .1 contains the following two
    sentences: "Measurement and Payment paragraphs shall not apply. All work shall be
    included in the unit price items listed in the bid schedule that is part of these contract
    documents." (SOF ii 3) Generally, Sections 200 thru 800 of the KDOH Specifications
    contain separate paragraphs entitled "measurement" and "payment" for the type of
    construction work to be completed (SOF ii 4). Certified's interpretation that the
    measurement and payment paragraphs under these sections are excluded, but
    Section 109 entitled "MEASUREMENT AND PAYMENT" is not, is an inconsistent
    and unsupported reading, and hence, not within the "zone of reasonableness." First,
    Section 109, in and of itself, contains "measurement" and "payment" paragraphs,
    which the language of the first sentence in subparagraph 5.1 explicitly excludes.
    Certified relied on those "payment" paragraphs to calculate its REA and claim
    (SOF iiii 8, 10). Second, subparagraph 5.1 falls beneath the heading of paragraph five,
    entitled "EXCEPTIONS TO KDOH SPECIFICATIONS." The KDOH Specifications
    include all sections, not just Sections 200 thru 800. Nothing in the plain language of
    8
    subparagraph 5.1 limits its application to Sections 200 thru 800 of the KDOH
    Specifications, and therefore, we determine that Certified's contrary interpretation is
    unreasonable as it conflicts with the plain language.
    Further, even if we found arguendo that an ambiguity existed, Certified's
    pursuit for recovery would not prevail because we would consider the ambiguity
    patent. The contract as awarded did not include a provision providing for an economic
    price adjustment. CLINs 0072, 0073, 1072, and 1073 contained fixed-unit pricing for
    the work to be completed as described (SOF, 5). For Certified to now argue that it
    could not know that Section 109 of the KDOH Specifications was excluded under the
    contract until the CO communicated his position is unpersuasive. Assuming without
    deciding that the language created an ambiguity, Certified had a duty to seek
    clarification prior to submission of its bid. Certified knew that the contract would be
    awarded through sealed bidding procedures, unit prices under the respective CLINs
    were fixed price, the contract lacked an express economic price adjustment clause, and
    subparagraph 5.1 of the General Construction specifications contained express
    language restricting the application of "measurement" and "payment" provisions of the
    incorporated KDOH Specifications. Thus, if Certified believed that Section 109 was
    not excluded, it was unreasonable for Certified to not seek clarification first due to the
    inconsistency between its interpretation and the face of the contract terms. Since
    Certified failed to do so, the patent ambiguity would be construed against Certified.
    CONCLUSION
    We conclude that the government's interpretation of subparagraph 5.1 of the
    General Construction specifications, excluding all "measurement" and "payment"
    paragraphs of the KDOH Specifications, including Section 109, is the only reasonable
    interpretation for the reasons stated above. Therefore, we grant the government's
    motion and deny Certified's motion. The appeal is denied.
    Dated: 12 August 2015
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    (Signatures continued)
    9
    I concur                                       I concur
    /
    N. STEMPLER                            RICHARD SHACKLEFORD
    Administrative Judge                           Administrative Judge
    Acting Chairman                                Vice Chairman
    Armed Services Board                           Armed Services Board
    of Contract Appeals                            of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 58782
    , Appeal of Certified
    Construction Company of Kentucky, LLC, rendered in conformance with the Board's
    Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    10
    ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                  )
    )
    Certified Construction Company of             )      
    ASBCA No. 58782
    Kentucky, LLC                                )
    )
    Under Contract No. W9124D-06-D-0001           )
    APPEARANCES FOR THE APPELLANT:                       Thomas E. Roma, Jr., Esq.
    G. Alan Oliver, Esq.
    Ackerson & Yann, PLLC
    Louisville, KY
    APPEARANCES FOR THE GOVERNMENT:                      Raymond M. Saunders, Esq.
    Army Chief Trial Attorney
    CPT Harry M. Parent, III, JA
    CPT Tyler L. Davidson, JA
    Trial Attorneys
    OPINION BY ADMINISTRATIVE JUDGE PAGE ON THE PARTIES'
    CROSS-MOTIONS FOR SUMMARY JUDGMENT
    This appeal arises under Contract No. W9124D-06-D-0001 (contract) between
    the Department of the Army (Army or government) and Certified Construction
    Company of Kentucky, LLC (Certified or contractor). Certified appeals from a
    contracting officer's (CO's) final decision (COFD) denying Certified's monetary
    claim resulting from an increase in the costs of liquid asphalt during performance. In a
    previous decision, we dismissed for lack of jurisdiction the portion of Certified' s claim
    accruing prior to 22 March 2007 as time-barred under the Contract Disputes Act's
    (CDA's), 
    41 U.S.C. §§ 7101-7109
    , six-year statute of limitations. Certified
    Construction Co. ofKentucky, LLC, 
    ASBCA No. 58782
    , 14-1BCAii35,662. The
    parties have filed cross-motions for summary judgment on the portion of Certified's
    claim over which we exercised jurisdiction.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTIONS
    The parties have submitted a Joint Stipulation of Material Facts (Jt. Stip.). The
    following facts are not in dispute.
    1. On 24 October 2005, the Army awarded the requirements contract to
    Certified via sealed bidding procedures (Jt. Stip. ii 1; R4, tab 17 at 3 1). Through task
    orders issued under the contract, Certified provided road construction and repair
    including concrete placement, asphalt surface treatments, and pavement markings at
    Fort Knox, Kentucky (Jt. Stip. ii 4; R4, tab 20 2 at 1-2, 4). The period of performance
    was from 1 November 2005 to 31 October 2006, with a single one-year option period
    (R4, tab 20 at 1, 4).
    2. The contract included the following relevant Federal Acquisition Regulation
    (FAR) clauses: 52.233-1, DISPUTES (JUL 2002)-ALTERNATE I (DEC 1991);
    FAR 52.216-21, REQUIREMENTS (OCT 1995) - ALTERNATE I (APR 1984 );
    FAR 52.217-8, OPTION TO EXTEND SERVICES (Nov 1999); FAR 52.217-9, OPTION TO
    EXTEND THE TERM OF THE CONTRACT (MAR 2000) (R4, tab 20 at 49, 51-52). The
    contract also included Defense Federal Acquisition Regulation Supplement (DFARS)
    clause 252.243-7002, REQUESTS FOR EQUITABLE ADJUSTMENT (MAR 1998) (id. at 50).
    3. The contract required work to be performed in accordance with technical
    specifications contained in the document identified as "P.E. 3-05," dated 6 July 2005
    (R4, tab 20 at 79). The provisions within "P.E. 3-05" entitled "PART I
    TECHNICAL PROVISIONS DIVISION 2 - SECTION 2B GENERAL
    CONSTRUCTION" (General Construction specifications) provided, in relevant part:
    1. APPLICABLE PUBLICATIONS: The following
    publication is hereby incorporated by reference into the
    specifications for this project:
    Standard Specification for Road and Bridge
    Construction,
    Kentucky Department of Highways, latest edition
    www.kytc.state.us/construction/spec2000l 3l
    1
    Citations of this document in the Rule 4 file are to the Bates-numbered pages unless
    indicated otherwise.
    2
    The Rule 4 file includes two different copies of the awarded contract under tabs 1
    and 20. The contract under tab 1 contains 361 pages and is only signed by the
    CO; the copy under tab 20 contains 14 7 pages and is signed by both parties.
    Since block 28 of Standard Form 1442 is checked and requires the signature of
    the contractor, citations are to the copy under tab 20. The two versions of the
    contract do not differ with respect to relevant provisions.
    3
    Appellant submitted a bound copy of the Kentucky Transportation Cabinet/Department
    of Highways, Standard Specifications for Road and Bridge Construction (2004
    ed.) (KDOH Specifications), and the parties agree that this edition is applicable
    (Jt. Stip. ii 3). We mark this copy for the record as Rule 4, tab 22.
    2
    2. GENERAL: All work and materials shall conform to
    the applicable requirements of Section 200 through Section
    800 of the Kentucky Department of Highways (KDOH)
    Specifications except as noted in these specifications or
    contract documents. In case of difference between KDOH
    Specifications and the CONTRACT CLAUSES the
    CONTRACT CLAUSES shall govern.
    3. ABBREVIATIONS AND DEFINITIONS: Standard
    abbreviations shall be in accordance with Section 101.01
    of the KDOH Specifications. Where such terms as
    "Chairman'', "Commission'', "Engineer", or "'Department"
    are used, they shall mean "Contracting Officer".
    Whenever the works [sic] "Extra Work" or similar phrase
    is used, it shall mean "Changes" as defined in the
    CONTRACT CLAUSES.
    4. CONTROL OF MATERIALS: Control of materials
    shall be in accordance with Section 106 ofKDOH
    Specifications in addition to the requirements of the
    CONTRACT CLAUSE.
    5. EXCEPTIONS TO KDOH SPECIFICATIONS:
    5 .1 Measurement and Payment paragraphs shall not
    .rumIY. All work shall be included in the unit price items listed
    in the bid schedule that is part of these contract documents.
    (R4, tab 20 at 97; Jt. Stip.   ii 2) (Emphasis added)
    4. The KDOH Specifications, Divisions 100-800 contain a number of
    references to "'Measurement" and "Payment" provisions. See, e.g., Division 100,
    General Provisions, § 109 Measurement and Payment (R4, tab 22 at 109-1-109-12);
    Division 200, Earthwork, § 201 Staking, ii 201.4 Measurement and ii 201.05 Payment
    (id. at 201-2); § 202 Clearing and Grubbing, ii 202.04 Measurement and ii 202.05
    Payment (id. at 202-1-202-2); and§ 303 Pavement Drainage Blanket, ii 303.04
    Measurement and ii 303.05 Payment (id. at 303-4-303-5).
    5. The contract included numerous contract line item numbers (CLINs)
    providing estimated quantities and unit pricing for various work to be performed. In
    accordance with the General Construction specifications, CLINs 0072 and 1072
    provided for the installation of a "Bituminous concrete surface course," and CLINs
    0073 and 1073 provided for the installation of a "Bi[t]uminous concrete binder course"
    (R4, tab 20 at 15-16, 37).
    3
    6. On 30 October 2006, the CO executed Modification No. P00005, exercising
    the option period and extending the term of the contract to 31 October 2007 (R4, tab 7).
    7. On 3 October 2007, the CO executed unilateral Modification No. P00009,
    extending the period of performance of the contract to 30 April 2008 (R4, tab 11).
    8. By letter dated 17 September 2012, Certified submitted a request for
    equitable adjustment (REA), seeking an equitable adjustment to the contract in the
    amount of$839,052.31 for additional incurred costs resulting from the increase in
    prices of petroleum products, specifically liquid asphalt, used for the production of
    asphalt hot mixes under CLINs 0072, 0073, 1072, and 1073 (R4, tab 15; Jt. Stip. iii! 3,
    6). In calculating its request, Certified relied on Section 109.07 of the KDOH
    Specifications entitled "PRICE ADJUSTMENTS" which provides in relevant part:
    109.07 PRICE ADJUSTMENTS. Due to the fluctuating
    costs of petroleum products, the Department will adjust the
    compensation of specified liquid asphalt items ....
    109.07.01 Liquid Asphalt. The Department will
    list a base price for liquid asphalt products in the Bid
    Proposal for applicable projects. The Department will
    compare the Kentucky Average Price Index, for the month
    that the Contract is let, to the index for the month that the
    Contractor places the material on the project to determine
    the percent change. When the original contract quantity
    for asphalt items is equal to or greater than 3,000 tons and
    when the average price of the liquid asphalt products
    increases or decreases more than 10 percent, the
    Department will adjust the Contractor's compensation.
    (Id.; R4, tab 22)
    9. By letter dated 19 October 2012, the CO denied Certified's REA, asserting
    that subparagraph 5.1 of the General Construction specifications in the contract
    specifically excluded Section 109 of the KDOH Specifications (R4, tab 16; SOF if 3;
    Jt. Stip. if 7).
    10. By letter dated 22 March 2013, Certified converted its REA into a certified
    claim for $839,052.31, demanding, as a matter of right, the amount requested in its
    REA (SOF if 7). Certified asserted that it was entitled to the difference in "increased
    cost of performance resulting from the unprecedented increase in the price of Liquid
    4
    Asphalt" from the time it submitted its bid pricing to performance of the contract.
    Certified disagreed with the CO's interpretation, maintaining that Section 109 of the
    KDOH Specifications was not explicitly excluded, and that the intent of subparagraph
    5.1 of the General Construction specifications was to exclude the measurement and
    payment paragraphs within Sections 200 thru 800 of the KDOH Specifications as
    provided under paragraph two of the General Construction specifications. (R4, tab 17
    at 1-2; SOF ~ 3; Jt. Stip. ~ 8)
    11. On 31May2013, the CO issued a final decision denying Certified's claim
    in its entirety. The COFD asserted that the relevant technical provisions did not
    incorporate the KDOH Specifications in their entirety, and specific sections of the
    KDOH Specifications applicable to the contract were explicitly incorporated. Lastly,
    the CO asserted that measurement and payment paragraphs of the KDOH
    Specifications, including Section 109, did not apply. (R4, tab 18; Jt. Stip. ~ 9)
    12. On 16 July 2013, Certified appealed the 31May2013 CO's final decision
    to the Board (Jt. Stip. ~ 10).
    13. On 8 July 2014, the Board granted the government's partial motion to
    dismiss with respect to the portion of Certified's claim that accrued prior to
    22 March 2007, more than six years before Certified's 22 March 2013 claim date.
    That portion of the appeal was dismissed for lack of jurisdiction under the CDA.
    14. The parties stipulate that Certified's claim accruing after 22 March 2007 is
    for a sum certain amount of $606,707.55 (Jt. Stip. ~ 12).
    DECISION
    On 8 July 2014, we issued our opinion, Certified Construction Co. of Kentucky,
    LLC, 14-1 BCA ~ 35,662, partially dismissing the portion of Certified's claim accruing
    prior to 22 March 2007 for lack of jurisdiction because that portion was time-barred
    under the CDA's six-year statute oflimitations (SOF iJ 12). Subsequent to the
    issuance of our decision, the United States Court of Appeals for the Federal Circuit in
    Sikorsky Aircraft Corp. v. United States, 
    773 F.3d 1315
     (Fed. Cir. 2014), reversed its
    line of cases holding that the CDA' s statute of limitations was jurisdictional. By
    correspondence dated 26 March 2015, we directed the parties to provide supplemental
    briefing on the effect of the Sikorsky decision on the parties' cross-motions for
    summary judgment. The government responded that Sikorsky did not impact the
    parties' cross-motions and "the rationale of the Partial Motion to Dismiss is still valid"
    (gov't supp. br. at 2). While asserting that the Board's 8 July 2014 partial dismissal
    was erroneous in light of the Sikorsky decision, Certified agreed that the cross-motions
    are ready for adjudication as Sikorsky's effect would bear on the issue of quantum
    rather than entitlement (app. supp. br.). After consideration of the parties' views and
    re-examining our 8 July 2014 decision, based on Sikorsky and the findings in our
    5
    decision, we conclude that on the merits, the portion of Certified's claim dismissed in
    that decision for lack of jurisdiction is properly time-barred by the CDA. We next
    proceed toward resolution of the parties' cross-motions for summary judgment.
    1. Summary Judgment
    Matters of contract interpretation are questions of law and are amenable for
    resolution through summary judgment. Vari/ease Technology Group, Inc. v. United
    States, 
    289 F.3d 795
    , 798 (Fed. Cir. 2002). The guidelines for summary judgment are
    well established; the granting of summary judgment is appropriate where there are no
    genuine issues of material fact and the movant is entitled to favorable judgment as a
    matter oflaw. Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    , 255 (1986); DIRECTV
    Group, Inc. v. United States, 
    670 F.3d 1370
    , 1374 (Fed. Cir. 2012); Osborne
    Construction Co., 
    ASBCA No. 55030
    , 09-1BCA,34,083 at 168,512. The parties'
    cross-motions are evaluated on their own merits, and we are not obligated to '"grant
    judgment as a matter of law for one side or the other; summary judgment in favor of
    either party is not proper if disputes remain as to material facts." Mingus
    Constructors, Inc. v. United States, 
    812 F.2d 1387
    , 1391 (Fed. Cir. 1987). While the
    parties have jointly stipulated that there are no genuine issues of material fact to their
    respective positions on the issue of contract interpretation, we are "not bound by the
    concessions or stipulations by either party that are contrary to the evidence or the law."
    General Atronics Corp., 
    ASBCA No. 37923
    , 91-3 BCA, 24,047 at 120,360 (citing
    Kaminer Construction Corp. v. United States, 
    488 F.2d 980
     (Ct. Cl. 1973)).
    The movant has the burden to establish that there are no material facts in
    dispute. A material fact is one which may affect the outcome of the case. Liberty
    Lobby, 
    477 U.S. at 248
    . At the summary judgment stage, we do not resolve
    controversies, weigh evidence, or make determinations of credibility. 
    Id. at 255
    . All
    reasonable inferences are drawn in favor of the nonmovant. Id.
    2. The Parties' Contentions
    The parties filed, with their cross-motions for summary judgment, a Joint
    Stipulation of Material Facts, and thus, aver that there are no genuine issues of
    material fact. The disputed matter is over the proper interpretation of subparagraph
    5.1 of the General Construction specifications. Each party asserts that it is entitled to
    judgment as a matter of law, with each arguing that its respective interpretation of the
    subparagraph is plainly supported and reasonable. Certified largely contends that the
    subparagraph did not expressly exclude Section 109 of the incorporated KDOH
    Specifications upon which it relied as the basis for its claim. In reaching this
    interpretation, Certified argues that the intention of the first sentence of the
    subparagraph, which states "Measurement and Payment paragraphs shall not apply,"
    was a limitation applicable to Sections 200 thru 800 of the KDOH Specifications,
    sections referenced under paragraph two of the General Construction specifications.
    6
    (App. mot. at 4-7) According to Certified, this is the correct reading because the
    CLINs in the contract contain unit pricing for the type of work to be accomplished in
    accordance with those specific KDOH Specifications (app. mot. at 7-8).
    The government disagrees with Certified' s interpretation, arguing that
    Certified's interpretation is unreasonable because it would render meaningless the
    exclusion of measurement and payment provisions explicitly stated in the first
    sentence of subparagraph 5 .1. Additionally, the government argues that Certified' s
    interpretation would subject the firm-fixed unit pricing in the contract to adjustments
    under the payment provisions in the KDOH Specifications inconsistent with the
    second sentence that states "[a]ll work shall be included in the unit price items listed."
    (Gov't mot. at 4-6) Therefore, the government contends that the only reasonable
    interpretation of subparagraph 5.1 is the express exclusion of any payment provisions
    in the KDOH Specifications, including Section 109 (gov't mot. at 6-7).
    The parties also present alternative arguments ifthe underlying language of the
    subparagraph is deemed ambiguous, and they disagree as to the type of ambiguity.
    The government argues that any ambiguity regarding excepted contract provisions
    pertaining to "Measurement and Payment" should be considered patent, and imposing
    upon Certified the duty to inquire and seek clarification prior to submitting its bid for
    the contract (gov't mot. at 8). Certified counters that such an ambiguity should be
    considered latent, arguing that the ambiguity did not become apparent until Certified
    became aware of the CO's position concerning whether Section 109 of the KDOH
    Specifications was excluded (app. resp. to gov't mot. at 7). Certified argues that it
    should recover under the doctrine of contra proferentem as the ambiguity should be
    construed against the government (id.).
    3. Contract Interpretation
    Contract interpretation begins with examination of the plain language of the
    written agreement. LAI Services, Inc. v. Gates, 
    573 F.3d 1306
    , 1314 (Fed. Cir. 2009).
    The terms are given their plain and ordinary meaning. If the contract language is clear
    and unambiguous, the plain language controls, extrinsic evidence is not allowed to
    contradict the plain language, and resolution through summary judgment is amenable.
    Coast Federal Bank, FSB v. United States, 
    323 F.3d 1035
    , 1040 (Fed. Cir. 2003);
    Pacific Coast Community Services, Inc., 
    ASBCA No. 56754
    , 10-1 BCA ~ 34,421 at
    169,912. The contract terms are interpreted and read as a whole, giving reasonable
    meaning to all of its parts, and without leaving "a portion of the contract useless,
    inexplicable, void, or superfluous." NVT Technologies, Inc. v. United States, 
    370 F.3d 1153
    , 1159 (Fed. Cir. 2004).
    Contract language is clear and unambiguous when there is only one reasonable
    interpretation consistent with the plain meaning. LAI Services, 
    573 F.3d at 1314
    . A
    contract term is not rendered ambiguous just by the parties' disagreement as to the
    7
    interpretation alone; a party's respective interpretation "must fall within a 'zone of
    reasonableness."' Metric Constructors, Inc. v. NASA, 
    169 F.3d 747
    , 751 (Fed. Cir.
    1999). If the contract language supports more than one reasonable interpretation, and
    the weighing of extrinsic evidence is required to determine the parties' intent to
    resolve the ambiguity, summary judgment is not appropriate. MIC/CCS, Joint
    Venture, 
    ASBCA No. 58023
    , 14-1 BCA ~ 35,678 at 174,637-38.
    Ambiguities fall under two categories - an ambiguity is either patent or latent.
    If there is an ambiguity, the general rule of contra proferentem is to construe the
    ambiguous contract language against the drafter. Metric Constructors, 
    169 F.3d at 751
    . However, a patent ambiguity is an exception to the general rule where the
    ambiguity is "sufficiently glaring to trigger" a contractor to inquire before a bid is
    submitted. HPl/GSA-3C, LLC v. Perry, 
    364 F.3d 1327
    , 1334 (Fed. Cir. 2004). The
    patent ambiguity is construed against the contractor. 
    Id.
     If an ambiguity does not
    meet the patent ambiguity exception and is latent, the general rule may be applied, but
    the contractor's interpretation must be determined to be reasonable. Id.
    4. Analysis
    We agree that there are no material facts in dispute for these cross-motions, and
    the issue involves a matter of pure contract interpretation. Initially, we must determine
    whether the parties' interpretations are reasonable based on the plain language of the
    contract, and then, if more than one reasonable interpretation is supported, whether the
    existing ambiguity is patent or latent. Upon closer examination of the language within
    subparagraph 5 .1 of the General Construction specifications, and taking into account
    that we must interpret the terms as a whole and give reasonable meaning to all parts of
    the contract, we find that the government's interpretation is the only reasonable
    interpretation of the subparagraph. It is clear that the KDOH Specifications were
    expressly incorporated by reference into the contract under paragraph one of the
    General Construction specifications. Subparagraph 5 .1 contains the following two
    sentences: "Measurement and Payment paragraphs shall not apply. All work shall be
    included in the unit price items listed in the bid schedule that is part of these contract
    documents." (SOF ~ 3) Generally, Sections 200 thru 800 of the KDOH Specifications
    contain separate paragraphs entitled "measurement" and "payment" for the type of
    construction work to be completed (SOF ~ 4). Certified's interpretation that the
    measurement and payment paragraphs under these sections are excluded, but
    Section I 09 entitled "MEASUREMENT AND PAYMENT" is not, is an inconsistent
    and unsupported reading, and hence, not within the "zone of reasonableness." First,
    Section I 09, in and of itself, contains "measurement" and "payment" paragraphs,
    which the language of the first sentence in subparagraph 5.1 explicitly excludes.
    Certified relied on those "payment" paragraphs to calculate its REA and claim
    (SOF `` 8, I 0). Second, subparagraph 5 .1 falls beneath the heading of paragraph five,
    entitled "EXCEPTIONS TO KDOH SPECIFICATIONS." The KDOH Specifications
    include all sections, not just Sections 200 thru 800. Nothing in the plain language of
    8
    subparagraph 5.1 limits its application to Sections 200 thru 800 of the KDOH
    Specifications, and therefore, we determine that Certified's contrary interpretation is
    unreasonable as it conflicts with the plain language.
    Further, even if we found arguendo that an ambiguity existed, Certified's
    pursuit for recovery would not prevail because we would consider the ambiguity
    patent. The contract as awarded did not include a provision providing for an economic
    price adjustment. CLINs 0072, 0073, 1072, and 1073 contained fixed-unit pricing for
    the work to be completed as described (SOF i-1 5). For Certified to now argue that it
    could not know that Section 109 of the KDOH Specifications was excluded under the
    contract until the CO communicated his position is unpersuasive. Assuming without
    deciding that the language created an ambiguity, Certified had a duty to seek
    clarification prior to submission of its bid. Certified knew that the contract would be
    awarded through sealed bidding procedures, unit prices under the respective CLINs
    were fixed price, the contract lacked an express economic price adjustment clause, and
    subparagraph 5 .1 of the General Construction specifications contained express
    language restricting the application of "measurement" and "payment" provisions of the
    incorporated KDOH Specifications. Thus, if Certified believed that Section 109 was
    not excluded, it was unreasonable for Certified to not seek clarification first due to the
    inconsistency between its interpretation and the face of the contract terms. Since
    Certified failed to do so, the patent ambiguity would be construed against Certified.
    CONCLUSION
    We conclude that the government's interpretation of subparagraph 5.1 of the
    General Construction specifications, excluding all "measurement" and "payment"
    paragraphs of the KDOH Specifications, including Section 109, is the only reasonable
    interpretation for the reasons stated above. Therefore, we grant the government's
    motion and deny Certified's motion. The appeal is denied.
    Dated: 12 August 2015
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    (Signatures continued)
    9
    I concur                                       I concur
    RICHARD SHACKLEFORD
    Administrative Judge                           Administrative Judge
    Acting Chairman                                Vice Chairman
    Armed Services Board                           Armed Services Board
    of Contract Appeals                            of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 58782
    , Appeal of Certified
    Construction Company of Kentucky, LLC, rendered in conformance with the Board's
    Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    10