Martin Edwards & Associates, Inc. ( 2015 )


Menu:
  •                  ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                  )
    )
    Martin Edwards & Associates, Inc.             )      ASBCA No. 57718
    )
    Under Contract No. W91247-11-D-0004           )
    APPEARANCES FOR THE APPELLANT:                       H. Addison Winters, Esq.
    J. Thomas Neville, Esq.
    Yarborough, Winters & Neville, P.A.
    Fayetteville, NC
    APPEARANCES FOR THE GOVERNMENT:                      Raymond M. Saunders, Esq.
    Army Chief Trial Attorney
    Erica S. Beardsley, Esq.
    Trial Attorney
    OPINION BY ADMINISTRATIVE JUDGE MCILMAIL
    The U.S. Army contracted with appellant, Martin Edwards & Associates, Inc.
    (MEA), for the installation and service of clothes washers and dryers at military installations
    in North Carolina. The Army terminated the contract for cause, then entered into a bilateral
    modification with MEA to convert the termination to a "no-cost" termination for the
    convenience of the Army that included mutual releases of all claims arising from the
    contract. 1 MEA contends that the modification was induced by misrepresentation and,
    therefore, is voidable. MEA also contends that the termination of the contract was
    improper, and that the Army breached the contract. While the Board heard eight days of
    testimony and the parties filed extensive briefs on the merits, we need not discuss many of
    the arguments because, as discussed below, we deny the appeal based upon the
    modification's release language. 2
    1
    We earlier denied a government motion for summary judgment with respect to the release
    in that modification, finding sufficient evidence to raise a triable issue of fact
    whether alleged government misrepresentation induced MEA's agreement to the
    release. Martin Edwards & Associates, Inc., ASBCA No. 57718, 12-2 BCA
    ~ 35,058 at 172,210.
    2
    Judge Grant, who presided over the hearing in this appeal, has since retired.
    FINDINGS OF FACT
    1. On 31 March 2011, the United States Army awarded to MEA Contract
    No. W91247-11-D-0004, for the delivery, installation, and 12-month lease of (an estimated)
    3,970 washers and dryers at Fort Bragg, Simmons Army Airfield, and Camp Mackall,
    North Carolina, for $489,351.48 (R4, tab 8 at 1, 4-6, tab 38 at 4).
    2. Also on 31 March 2011, the Army issued Task Order No. 0001, requiring MEA to
    deliver and install the appliances by 15 May 2011 (R4, tab 9 at 3), the end of the contract's
    45-day "phase-in" period (R4, tab 7 at 3, ~ 2.6.1.1 ).
    3. The contract's performance work statement provides:
    HOURS OF OPERATION. The Contractor shall perform
    services during the following hours: Monday through Friday,
    7:30 a.m. through 4:00 p.m. except Federal Holidays, unless
    otherwise authorized by the Contracting Officer or the
    Contracting Officers [sic] representative.
    (R4, tab 7 at 3, ~ 2.4)
    4. On 4 April 2011, representatives ofMEA and the Army attended a contract
    post-award meeting (tr. 1150). Among the attendees was Mr. Rickie Day, MEA's president
    (R4, tab 49). Mr. Day informed the Army that MEA would not have any appliances to
    install for three weeks, until approximately 25 April 2015 (tr. 1154-55; R4, tab 49 at 4).
    According to Mr. Day, he asked that MEA be allowed to work on weekends or "after
    hours," and the Army informed him that MEA would not be allowed to do so (tr. 1157-58).
    That account is generally corroborated by two other attendees, one an MEA employee and
    the other the owner of the company whose appliances MEA had been contracted to replace
    (tr. 11169, 11248). However, according to the contracting officer who awarded the contract,
    Mr. Day rejected any suggestion that MEA work on weekends or after hours (tr. 2/86), an
    account that three other Army representatives who attended the meeting generally
    corroborate (tr. 51113, 6171, 7/24). A fifth Army representative who attended the meeting
    does not recall any discussion of weekend or after-hours work (tr. 4/42-43).
    5. During the post-award 4 April 2011 meeting, MEA and the Army discussed the
    possibility of extending the phase-in period, perhaps to 30 June 2011 (tr. 1/55-56, 58), but
    before the meeting ended the Army decided that it would not extend the phase-in period
    (tr. 1/63). MEA then informed the Army that it "would probably be impossible to get all
    that equipment in, in just 21 days"; that is, the 21 days remaining during the expected
    25 April 2011 arrival of the appliances and the 15 May 2011 end of the phase-in period
    2
    (tr. 1/63). However, by the end of the meeting, Mr. Day informed the Army that he would
    "do everything that [he] had to do to make sure [the Army's] equipment was installed in
    that 24 days that [he] had"; that is, that MEA would install the appliances by 15 May 2011
    (tr. 1/72).
    6. Later on 4 April 2011, the contracting officer contacted other vendors, including
    Inventory Accounting Service, Inc. (IAS), regarding their ability to provide and service
    washers and dryers (see tr. 2/89-90). IAS represented that it "would require to work on the
    weekends as well as after hours in order to be able to complete the installation" within a
    45-day phase-in period (tr. 2190, 225).
    7. The next day, 5 April 2011, the contracting officer requested that MEA "confirm
    whether you can and will comply with the contract's phase-in period of performance ending
    May 15, 2011" (R4, tab 15). MEA responded the same day, stating that "[i]t is MEA's
    intent to meet and fulfill all terms and conditions of the contract" (R4, tab 16). Despite that
    response, the Army, on 5 April 2011, terminated the contract for cause, finding that "the
    contractor failed to provide adequate assurance of performance, specifically in reference to
    the completion of the Phase-in period" (R4, tab 17 at 1). Also on 5 April 2011, the Army
    entered into a contract with IAS for washers and dryers at Fort Bragg, Simmons Army
    Airfield, and Camp Mackall, with a phase-in period to be completed by 20 May 2011
    (R4, tab 72 at 4, tab 73).
    8. On 6 April 2011, MEA, through Mr. Day, requested that the contracting officer
    rescind the termination of the contract with MEA, or, in the alternative "convert the
    termination for cause into a no-cost convenience termination" (R4, tab 98 at 1; tr. 1/95-96;
    see tab 153 at 10, ~ 28, tab 153 at 17-18, `` 11, 15). The written request did not mention
    weekend or after-hours work (R4, tab 98). On 8 April 2011, MEA and the Army entered
    into bilateral Modification No. P00002 (Modification No. 2) (R4, tab 18). The modification
    recites that its purpose is to convert the termination for cause "to a no-cost Termination for
    the Government's Convenience," and that "(i]n consideration of the promises set forth
    herein and for good and valuable consideration, the parties agree as follows:"
    a. This supplemental settlement agreement modifies the
    contract to reflect a no-cost settlement agreement of $0.00
    and Contract Number W91247-11-D-0004 is Terminated in
    its entirety for the Government's Convenience.
    b. The Contractor agrees that any and all claims which the
    Contractor, and its assigns, officers, directors, employees,
    agents and subcontractors may have or acquire against the
    Government or its present and former agents, employees, or
    agencies, arising under or relating to this Contract, and are
    3
    [sic] hereby fully and irrevocably releases and forever
    discharges the Government and anyone claiming by, through
    or under it, from any and all claims, actions, causes of action,
    obligations, costs, expenses, damages, losses and liabilities,
    of any kind or nature, whether known, unknown or
    unforeseen, vested or contingent, either encompassed by or
    which hereafter can arise out of or result from the
    performance or termination of the Contract.
    c. The Government, in consideration for the Contractor
    providing the release set forth in paragraph b, above, on behalf
    of itself, and anyone claiming by, through or under it, does
    hereby fully and irrevocably release and forever discharge the
    Contractor, its members, officers, employees and related
    entities, and anyone claiming by, through or under them, from
    any and all claims, actions, causes of actions, obligations,
    costs, expenses, damages, losses and liabilities, of any kind or
    nature, whether known, unknown or unforeseen, vested or
    contingent, either encompassed by or which hereafter can arise
    out of or result from the performance, termination, or
    non-performance of the Contract.
    (R4, tab 18 at 1-2 (emphasis added))
    9. Modification No. 2 was negotiated by attorneys for MEA and the Army
    (tr. 1/96-97, 5/33). The attorneys did not testify at the hearing, and no first-hand account of
    their negotiations - except the modification itself (R4, tab 18) - appears in the record. The
    modification does not mention weekend or after-hours work (id.).
    10. Mr. Day signed the modification for MEA (R4, tab 18 at 1), and testified that
    with respect to the negotiations that produced the modification, "whatever [the attorneys]
    talked about I really don't recall"; however, he testified that a condition of the agreement
    was that Mr. Day persuade the contractor whose appliances were to be replaced "to leave
    her machines in place until all the other machines were installed" (tr. 1/97). Mr. Day and
    MEA learned on 30 April 2011, that IAS would be permitted to work on weekends (R4,
    tab 153 at 11, ~ 30; tr. 1/99-100). Mr. Day testified that he would not have signed the
    release if he had known that IAS was going to be allowed to work weekends and after
    hours, because, as he understood it, IAS was "being treated different than [MEA] was"
    (tr. 11100).
    11. On 4 May 2011, MEA filed a certified claim with the contracting officer for
    $850,000 (R4, tab 20). MEA stated that:
    4
    This improper [termination for convenience] claim, and breach
    of contract claim, as noted above, is based on:
    1.    Bad faith by the Army (as shown by an intent to injure
    MEA by clear and convincing evidence)
    11.   Clear abuse of discretion by the Army in terminating
    the contract
    m. The Army's award of the Contract with no intention of
    fulfilling its promises, and subsequent improper
    convenience termination.
    (R4, tab 20 at 9) MEA claimed that it had requested permission to work on Saturdays, but
    that the contracting officer had refused (id. at 4, 9).
    12. On 29 June 2011, the contracting officer issued a final decision denying the
    claim, finding that during the post-award conference MEA had "rejected the idea of
    working on weekends" (R4, tab 21 ).
    13. On 27 July 2011, MEA timely appealed to this Board.
    DECISION
    In Modification No. 2, MEA released all claims against the Army arising from the
    contract (finding 8). 3 Martin Edwards, 12-2 BCA ~ 35,058 at 172,209, 172,210 n.l.
    Although MEA asserts that the release is voidable because, MEA contends, the Army
    induced its assent by misrepresenting that weekend and after-hours work would not be
    allowed, that assertion fails. If a party's manifestation of assent is induced by either a
    fraudulent or a material misrepresentation by the other party upon which the recipient is
    justified in relying, the contract is voidable by the recipient. RESTATEMENT (SECOND) OF
    CONTRACTS § 164( 1) ( 1981 ). Here, the contract that MEA asserts is voidable is
    Modification No. 2, which includes the release of claims against the Army (finding 8).
    3
    The Army challenges whether we possess jurisdiction to entertain MEA' s breach claims
    and challenge to the termination of the contract for cause, contending that MEA did
    not present those claims to the contracting officer (gov't hr. at 64). We disagree:
    MEA's claim to the contracting officer specifically alleges that the Army breached
    the contract, and chall.enges both the Army's exercise of discretion "in terminating
    the contract," as well as, in MEA' s view, the "subsequent improper convenience
    termination" (finding 11).
    5
    MEA asserts that its manifestation of assent to the modification was induced by fraudulent
    and material misrepresentations by Army representatives who, MEA asserts, stated that
    MEA would not be allowed to work on weekends or "after hours." In Martin Edwards,
    12-2 BCA ii 35,058 at 17,209, we stated that "[i]f the government denied MEA the
    opportunity to work weekends knowing it would allow weekend work in a later contract,
    then this could constitute a material misrepresentation" (emphasis added). However, upon
    consideration of the entire record, including the testimony elicited during the hearing, we
    determine that MEA fails to demonstrate that any misrepresentation regarding weekend or
    after-hours work was fraudulent or material. 4
    As an initial matter, we find it unnecessary to decide whether the Army actually
    represented that it would not permit MEA to work on weekends or after hours. Assuming
    without deciding that the Army misrepresented that weekend work would not be allowed,
    MEA does not demonstrate that the misrepresentation was fraudulent. For a
    misrepresentation to be fraudulent, the maker must intend his assertion to induce a party to
    manifest his assent. RESTATEMENT (SECOND) OF CONTRACTS§ 162(1). MEA contends that
    the Army made the misrepresentation on 4 April 2011 (finding 4), but the Army did not
    even terminate the contract until 5 April 2011 (finding 7). MEA does not demonstrate that
    the Army intended, before even terminating the contract, to induce MEA into an agreement
    to convert the termination from one for cause to a no-cost, no-claims, termination for
    convenience. Indeed, it would require a substantial stretch of the imagination for us to
    arrive at such a conclusion.
    Nor does MEA demonstrate that such a misrepresentation was material. A
    misrepresentation is material if it would be likely to induce a reasonable person to manifest
    his assent, or ifthe maker knows that it would be likely to induce the recipient to do so.
    RESTATEMENT (SECOND) OF CONTRACTS§ 162(2). The materiality of a misrepresentation is
    determined from the viewpoint of the maker. 
    Id. cmt. c.
    First, MEA fails to demonstrate that
    the Army knew it would be likely that a prohibition on weekend and after-hours work would
    induce MEA to agree to Modification No. 2; MEA points to no evidence, for example, that it
    communicated in any way to the Army before signing the modification that a factor in its
    decision to sign was that the Army would not allow work on weekends or after hours. For
    example, MEA's request to the contracting officer that the termination be converted to a
    no-cost convenience termination does not mention weekend and after-hours work (finding 8).
    Second, MEA does not demonstrate that such a prohibition would be likely to induce a
    reasonable person to manifest his assent to Modification No. 2. Indeed, we find no objectively
    reasonable connection between an Army statement that it would not allow weekend or after-
    4
    At page 25 of its opening brief, MEA contends that the Army also misrepresented
    whether it would allow an extension of the phase-in period, but points to no evidence
    that such a representation induced it to sign Modification No. 2.
    6
    hours work, and a contractor's later decision after the termination of its contract for cause to
    agree to a no-cost, no-claims conversion of the termination to one for the convenience of the
    Army. To begin with, Modification No. 2 does not mention weekend or after-hours work, nor
    does the record, except for the modification itself, contain any first-hand evidence (that is,
    from the attorneys who negotiated the modification) of the content of the negotiations that
    produced the modification (finding 8). 5 In addition, MEA left the 4 April 2011 meeting
    assuring the Army that the appliances would be installed by 15 May 2011, even (according to
    Mr. Day's account of the meeting) knowing that weekend and after-hours work would not be
    allowed (findings 4, 5). We do not find it likely that a reasonable contractor that had
    determined that it could meet an installation date without working weekends or after hours
    would be induced later to assent to Modification No. 2 by a prohibition on weekend and after-
    hours work that had been announced before the contractor determined that the appliances
    could be timely installed. That is, we do not see how such a statement, made when and in the
    context it is alleged to have been made, would matter to a reasonable contractor deciding
    whether to sign Modification No. 2. In other words, because, according to MEA, it could have
    timely installed the appliances during only regular, weekday hours (finding 5), whether
    weekend and after-hours work would be allowed would have been immaterial to a reasonable
    contractor, in MEA's position, deciding whether to assent to Modification No. 2.
    Indeed, Mr. Day's explanation of the significance to him of the issue of weekend and
    after-hours work indicates not that a statement prohibiting such work induced him to sign
    the modification, but that had he known that the Army was going to allow IAS to work on
    weekends and after hours, he would not have signed it, because, as he understood it, IAS
    was "being treated different than [MEA] was" (finding 10). That is, having learned after
    signing Modification No. 2 that the Army was allowing IAS to do what, according to him,
    MEA was not allowed to do (work on weekends and after hours), Mr. Day felt unfairly
    treated by comparison. However, the evidence does not demonstrate that the Army made
    any representations to MEA regarding how it would administer a follow-on contract. Citing
    RESTATEMENT (SECOND) OF CONTRACTS§ 161, MEA contends that the Army
    misrepresented the facts by failing to disclose to MEA that IAS would be allowed to work
    on weekends and after hours (app. reply at 161), but the contracting officer and IAS only
    discussed such work after the Army had met with MEA on 4 April 2011, and did so before
    the contract was terminated and MEA requested a conversion (findings 6, 8). Therefore,
    there was nothing about IAS's possible work schedule for the Army to disclose to MEA
    during the 4 April 2011 meeting, and no conversion request for the Army even to consider
    until more than a day later. As for what the Army did not disclose between the 4 April 2011
    meeting and the 7 April 2011 conversion, MEA failed to establish what, if anything, the
    5
    Mr. Day's testimony evinces that the Army conditioned agreement to a conversion on
    MEA persuading the previous contractor to allow existing appliances to remain in
    place during the phase in of new appliances (finding 10).
    7
    Army held back in the lead up to Mr. Day signing Modification No. 2, by failing to present
    any testimony by the attorneys whose negotiations resulted in that modification.
    Because MEA failed to demonstrate that the Army induced MEA's assent to
    Modification No. 2 by a fraudulent or material misrepresentation, that modification is not
    voidable; consequently, the modification releases MEA's claims against the Army arising
    from the washer and dryer contract. For these reasons, the appeal is denied.
    Dated: 10 March 2015
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                                                      I concur
    /
    /,,,-~---/-7-
    /
    /__       A
    /        ,·
    /. / ·"      //       (o
    )4          /'
    MARK N. STEMPLER                                    /
    Administrative Judge                                                          Administrative Judge
    Acting Chairman                                                               Vice Chairman
    Armed Services Board                                                          Armed Services Board
    of Contract Appeals                                                           of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the Armed
    Services Board of Contract Appeals in ASBCA No. 57718, Appeal of Martin Edwards &
    Associates, Inc., rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    8
    

Document Info

Docket Number: ASBCA No. 57718

Judges: McIlmail

Filed Date: 3/10/2015

Precedential Status: Precedential

Modified Date: 3/23/2015