Watts Constructors, LLC ( 2019 )


Menu:
  •                 ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeals of --                                  )
    )
    Watts Constructors, LLC                        )      ASBCA Nos. 61518, 61961
    )
    Under Contract No. W9128F-14-C-0024            )
    APPEARANCES FOR THE APPELLANT:                        Sara Beiro Farabow, Esq.
    David A. Blake, Esq.
    Michael E. Wagner, Jr., Esq.
    Seyfarth Shaw LLP
    Washington, DC
    APPEARANCES FOR THE GOVERNMENT:                       Michael P. Goodman, Esq.
    Engineer Chief Trial Attorney
    Erin K. Murphy, Esq.
    Stanley E. Tracey, Esq.
    Engineer Trial Attorneys
    U.S. Army Engineers District, Omaha
    OPINION BY ADMINISTRATIVE JUDGE MELNICK
    ON THE GOVERNMENT'S MOTION FOR SUMMARY JUDGMENT 1
    In ASBCA No. 61518, Watts Constructors, LLC (Watts), has appealed from the
    government's termination for default of a construction contract at Fort Carson, Colorado.
    First, it says it was excusably delayed beyond the contract completion date. Second, it
    contends the government waived its right to terminate. Third and fourth, it argues that
    the contracting officer abused her discretion by relying upon materially erroneous
    information and permitting herself to be influenced by a government inspector who made
    derogatory comments. Fifth, it maintains that, prior to terminating Watts, the government
    breached the implied duty of good faith and fair dealing by overly inspecting its work.
    The government has moved for summary judgment, arguing that the Board may
    not exercise jurisdiction over the portions of the amended complaint asserting excusable
    delay or breach of contract. It also suggests that the undisputed facts fail to support either
    waiver, abuse of discretion, or breach of the duty of good faith and fair dealing. The
    government's jurisdictional objections are rejected. Summary judgment is entered in
    1
    The motion also sought a stay while this request for summary judgment remained
    pending. That was addressed in response to other filings by the parties. We also
    note as discussed more below that the motion for summary judgment also included
    portions that were a motion to dismiss.
    favor of the government upon Watts' waiver and abuse of discretion counts. Summary
    judgment is denied regarding Watts' allegation of breach of the duty of good faith and
    fair dealing arising from over inspection.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
    The following facts are not the subject of genuine dispute.
    1. On July 17, 2014, the United States Army Corps of Engineers (government)
    awarded the contract identified above to Watts for the design and construction of buildings
    on Fort Carson (am. compl. 11 18-20; gov't mot. at 2; R4, tabs 3-4). Among the
    incorporated clauses were Federal Acquisition Regulation (FAR) 52.243-4, CHANGES
    (JUN 2007); FAR 52.246-12, INSPECTION OF CONSTRUCTION (AUG 1996); and
    FAR 52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984) (R4, tab 3 at 155-56).
    After extensions, and except for tangential issues not relevant, the parties established
    November 22, 2016, as the deadline for contract completion (am. compl. 1140-45; gov't
    mot. at 3-4).
    2. Watts failed to complete performance by November 22, 2016, but continued
    working (am. compl. and answer 11102-03). 2 On June 19, 2017, the government
    assessed and withheld from payment to Watts, liquidated damages for the period
    December 22, 2016 through April 30, 2017 (am. compl. and answer 1103). On July 13,
    2017, the parties bilaterally modified the contract, establishing December 21, 201 7 as the
    new contract completion date (am. compl. and answer 11102, 105; R4, tab 176). The
    terms of the modification provided that it "allow[ed] continued performance without
    waiving the Government's rights, including the right to assess liquidated damages until
    contract completion" (R4, tab 176). Eventually, the government released some
    previously withheld liquidated damages but continued to assess them going forward,
    leading to a net assessment ofliquidated damages from January 3 until November 30,
    2017 (am. compl. and answer 1108; gov't prop. findings 16; app. stmt. gen. issues 16).
    3. In a September 6, 2017 letter to the contracting officer, Watts described a
    meeting in which the government requested the designer to consider a new wall cavity for
    a building under construction. Watts noted that if the government elected to proceed it
    would submit a request for the costs and time related to the extra work (R4, tab 220).
    4. On September 20, 2017, the contracting officer sent Watts a cure notice based
    upon its lack of progress and failure to maintain schedule milestones. According to the
    notice, Watts 'jeopardized the successful completion of the contract by the contract
    completion date of December 21, 2017." The contracting officer gave Watts ten days to
    2
    The answer cited is the one filed November 19, 2018, in ASBCA No. 61518, which
    responds to the amended complaint of October 19.
    2
    cure the condition, requiring that Watts provide a recovery plan to complete the work,
    including an updated project schedule and description of mitigation efforts. She warned
    that failure to comply could result in notification to Watts' surety of performance issues.
    She also explained that Watts could be liable for reprocurement costs should the contract
    be terminated for default. (Am. compl. and answer ,r 113; R4, tab 228) Watts'
    September 30 response stated it would not complete the project until May 25,.2018,
    because of labor shortages, government direction to refrain from energizing electrical
    panels, and the government's suspension of work due to the wall cavity issue (am. compl.
    and answer ,r 114; R4, tab 234). On December 20, 2017, the contracting officer notified
    Watts' surety that a termination for default appeared imminent and inquired into whether
    the surety would arrange to complete the work (gov't prop. findings ,r 7; app. stmt. gen.
    issues ,r 7; R4, tab 268).
    5. Watts did not complete the project by the final extended completion date of
    December 21, 2017 (am. compl. 115(a), 49; gov't prop. findings ,r 8; app. stmt. gen.
    issues 1 8). On that date, the contracting officer informed Watts by letter that the
    government deemed the schedule and completion date to remain in effect. She
    emphasized that it was not waiving any of its contract rights, expressly reserving the right
    to terminate for default and to continue assessing liquidated damages (gov't prop.
    findings ,r 9; app. stmt. gen. issues ,r 9; R4, tab 270).
    6. During a January 8, 2018 meeting with Watts, the government agreed to review
    a resource loaded schedule, to be provided by Watts by January 24, describing how Watts
    would complete performance by May of 2018. The government doubted Watts could
    complete the project by that time, but stated it was looking for a realistic proposal. (Am.
    compl. and answer 11 116-18) A January 16 follow up letter from the contracting officer
    found that Watts' response to the government's cure notice was not compelling or its
    delay excusable. It did confirm the agreement to review a resource loaded schedule. The
    contracting officer emphasized that the December 21, 201 7 completion date remained in
    effect, that the government did not waive any of its contract rights, and it reserved the
    right to terminate the contract for default. (Gov't prop. findings ,r 11; app. stmt: gen.
    issues 1 11; R4, tab 281) On January 24, Watts submitted its proposed schedule for
    completion by May 24 (am. compl. and answer ,r 120; R4, tab 294 at 8129).
    7. On January 30, 2018, the contracting officer terminated the contract for default
    (gov't prop. findings 1 13; app. stmt. gen. issues 1 13; R4, tab 294). Repeating her
    finding that Watts had failed to provide compelling reasons not to terminate, she
    concluded that the delay in completion did not arise from unforeseeable causes beyond
    the control and without the fault of both Watts and its subcontractors. She also found that
    termination for default was in the government's best interest. The contracting officer
    rejected the January 24 schedule, saying that it was not fully resource loaded since it did
    not specify crew size for a given activity. She also concluded that the schedule
    inaccurately listed activities as complete, that its forecasted durations for activities were
    3
    unrealistic given prior progress, and it failed to provide adequate time to correct
    deficiencies. The contracting officer concluded that it was not possible for Watts to
    complete the project by May 24. (R4, tab 294) Watts appealed the termination on
    February 6, 2018, which the Board docketed as ASBCA No. 61518.
    8. In addition to the above facts about contract performance, resolution of this
    motion also requires consideration of the following facts regarding the proceedings
    before us. The government has moved for summary judgment and to stay proceedings.
    Among its arguments, the government seeks dismissal of Count I of Watts' amended
    complaint, which contends that the default was excusable due to government delays,
    because Watts had not submitted that defense as a claim to the contracting officer for a
    decision. The Board ultimately granted an unopposed request by Watts for an extension
    of time to respond to the government's motion until after Watts submitted a delay claim
    to the contracting officer and sufficient time had elapsed for a decision. Watts then
    submitted a certified delay claim to the contracting officer seeking $863,021.99 and a
    154-day time extension until May 24, 2018. The contracting officer responded that she
    lacked jurisdiction over the claim because the alleged delay was already at issue in
    ASBCA No. 61518. (App. opp'n, ex. A4) Watts appealed from that letter, contending
    that its claim should be deemed denied, which was docketed as ASBCA No. 61961. The
    Board then granted Watts' unopposed request for consolidation with ASBCA No. 61518.
    DECISION
    Though only titled a motion for summary judgment, the government also seeks
    dismissal of some of the counts of Watts' complaint for lack of jurisdiction. As the
    proponent of the Board's jurisdiction over the defenses advanced in its complaint, Watts
    bears the burden of proving jurisdiction by a preponderance of the evidence. However,
    the Board must accept as true the complaint's undisputed facts and draw all reasonable
    inferences in favor of Watts. See Trusted Integration, Inc. v. United States,
    
    659 F.3d 1159
    , 1163 (Fed. Cir. 2011). For those counts subject to the request for
    summary judgment, it should be granted when there are no genuine issues of material fact
    and the moving party is entitled to judgment as a matter of law. Celotex Corp. v. Catrett,
    477 U.S. 317,322 (1986). A non-movant seeking to defeat the suggestion that there are
    no genuine issues of material fact may not rest upon its pleadings, but "must set forth
    specific facts showing that there is a genuine issue for trial." Anderson v. Liberty Lobby,
    Inc., 
    477 U.S. 242
    , 248 (1986) (quoting First Nat. Bank of Ariz. v. Cities Serv. Co., 391
    U.S. 253,288 (1968)). Summary judgment may be used "to isolate and dispose of
    factually unsupported claims or defenses." 
    Celotex, 477 U.S. at 323-24
    . Thus, it may be
    entered upon individual portions of the appeal. See FED. R. CIV. P. 56(a).
    "Time is of the essence in any contract containing fixed dates for performance."
    De Vito v. United States, 
    413 F.2d 1147
    , 1154 (Ct. Cl. 1969). This contract's default
    clause permitted termination if Watts failed to complete the work within the time specified
    4
    in the contract, including any extension. FAR 52.249-lO(a); ECC CENTCOM
    Constructors, LLC, ASBCA No. 60647, 18-1 BCA ,i 37,133 at 180,718, appeal docketed,
    No. 19-1157 (Fed. Cir. Nov. 5, 2018). Watts did not complete the project by the final,
    extended completion date (SOF ,i 5). However, Watts' right to proceed could not be
    terminated if the delay arose from "unforeseeable causes beyond the control and without
    the fault or negligence of' Watts. FAR 52.249-lO(b)(l). Watts bears the burden to show
    that its nonperformance was excusable. Marshall's Elec., Inc., ASBCA No. 59749, 16-1
    BCA ,i 36,300 at 177,017. To defeat summary judgment, Watts "must 'make a showing
    sufficient to establish the existence of an element essential to' any matter 'on which
    [Watts] will bear the burden of proof at trial."' Third Coast Fresh Distribution, L.L.C.,
    ASBCA No. 59696, 16-1 BCA ,i 36,340 at 177,194 (quoting 
    Celotex, 477 U.S. at 322-23
    ).
    I.    Count I
    Watts' first basis to excuse its failure to perform on time is that it encountered
    excusable delays. According to Watts, the government directed changes and a
    suspension of work to the project's SCIF walls, door hardware, and to the security
    system. 3 The government also failed to timely review and approve submittals for the
    project's Hazardous Energy Control Plan, which delayed commissioning the project's
    mechanical and electrical systems. (Am. compl. ,i,i 5(a), 49-101) Count I of the
    amended complaint contends these delays were unforeseeable, beyond Watts' control,
    and without its fault or negligence, entitling it to an extension of the contract completion
    date past December 21, 2017 (am. comp 1. ,i,i 167-73 ).
    The government suggests the Board must dismiss Count I because it lacks
    jurisdiction to consider Watts' allegations of excusable delay. Its reason is that Watts did
    not submit its delay claim to the contracting officer in accordance with the terms of the
    Contract Disputes Act (CDA), 41 U.S.C. § 7103, prior to appealing the default. It relies
    upon three cases as support. They are M Maropakis Carpentry, Inc. v. United States,
    
    609 F.3d 1323
    , 1331 (Fed. Cir. 2010) ("[A] contractor seeking an adjustment of contract
    terms must meet the jurisdictional requirements and procedural prerequisites of the CDA,
    whether asserting the claim against the government as an affirmative claim or as a
    defense to a government action"); Securiforce Int'/ Am., LLC v. United States,
    
    879 F.3d 1354
    , 1363 (Fed. Cir.), cert. denied, 
    139 S. Ct. 478
    (2018) ("[T]o the extent the
    affirmative defense seeks a change in the terms of the contract-for example, an
    extension oftime .. .it must be presented to the [contracting officer]"); and ECC
    CENTCOM, 18-1 BCA ,i 37,133 at 180,713 ("[A] contractor contesting ... a default
    termination due to excusable delay must submit a claim for a time extension before
    appealing to the Board").
    3   A SCIF is a sensitive compartmented information facility.
    5
    Watts first responds that it did not have to submit a delay claim to defend against
    the default on that ground, inviting the Board not to follow its recent decision in ECC
    CENTCOM. It is not necessary to proceed down that path because, as Watts alternatively
    emphasizes, it in fact submitted a delay claim to the contracting officer after the
    government moved for summary judgment (SOF ,r 8). When the contracting officer
    refused to decide it, claiming lack of authority to do so, Watts appealed to this Board.
    Hence, Watts' delay claim is before the Board and, with the consent of the government,
    that appeal has been consolidated with its appeal from the default termination.
    In an attempt to preclude this delay defense, the government advances two
    objections to the validity of Watts' delay claim. First, the government suggests the
    contracting officer lacked authority to decide the claim, implying therefore that it was
    neither submitted nor deemed denied. The government advances a variation of a
    principle applicable to suits in the United States Court of Federal Claims. There,
    "[b]elatedly submitting a certified claim to a [contracting officer] once a claim is in
    litigation is not a cure for failing to present a claim to the [contracting officer] before
    filing suit." Emiabata v. United States, 135 Fed. Cl. 213,218 (2017). This is because
    once a claim is before that court, even if not proper because it was not first submitted to
    the contracting officer, federal law divests the agency of authority to decide it. See
    K-Con Bid. Sys., Inc. v. United States, 
    778 F.3d 1000
    , 1005 (Fed. Cir. 2015). The
    government suggests one of the Army's own regulations, AFARS 5133.212-90, a
    provision of the Army FAR Supplement, imposes the same rule for appeals here. That
    regulation vests authority and responsibility for the conduct and control of Corps contract
    litigation before this Board to the Army or Engineer Chief Trial Attorneys. However,
    AFARS 513 3 .212-90 is not nearly as sweeping as the absolute transfer to the Department
    of Justice "the function of decision whether and in what manner to prosecute, or to
    defend, or to compromise, or to appeal, or to abandon prosecution or defense" of "any
    case referred ... for ... defense." Exec. Order No. 6166 § 5 (1933), reprinted in 5 U.S.C.
    § 901, cited in Durable Metal Prods., Inc. v. United States, 
    21 Cl. Ct. 41
    , 45-46 (1990);
    see also 28 U.S.C. §§ 516-20. AFARS 5133.212-90 does not transfer authority over
    matters that are the subject of litigation here to an agency other than the Department of
    the Army, nor does it purport to divest the contracting officer of her usual role as the
    agency counsel's client official with authority over the claim's ultimate disposition.
    Historically, Corps contracting officers have normally retained that power. See, e.g., J W
    Bateson Co., ASBCA No. 24425, 84-1 BCA ,r 16,942. The government cites no
    precedent interpreting the regulation as it suggests and its position is therefore rejected.
    The contracting officer possessed authority to decide Watts' delay claim and her refusal
    to do so is a deemed denial. See 41 U.S.C. § 7103(f)(5).
    The government's second objection to Watts' delay claim rests upon ECC
    CENTCOM's statement that a defense to a default premised upon excusable delay "must
    [be] submit[ ed] as a claim for a time extension before appealing to the Board." 18-1
    BCA ,r 37,133 at 180,713. Watts did submit its certified delay claim to the contracting
    6
    officer before appealing it to the Board (SOF 18). Contrary to the government's
    suggestion, ECC CENTCOM did not squarely hold that, to pursue delay as a defense to
    default, a contractor must submit its delay claim before it appeals the default termination.
    No delay claim was submitted there. Additionally, nothing in the CDA constricts the
    time period for submitting a delay claim to less than 90 days (the time period for
    appealing a default termination to this Board under 41 U.S.C. § 7104(a)) when proffered
    as a defense to a timely appealed default termination. Under 41 U.S.C. § 7103(a)(4),
    contractors have six years after accrual to submit a claim.
    It is true that, after hearing ECC CENTCOM 's challenge to its default termination,
    the Board raised the possibility that it lacked jurisdiction to consider a delay defense due
    to the absence of a claim. 18-1 BCA 137,133 at 180, 711-13. After resisting that
    prospect, ECC CENTCOM alternatively requested a stay so that it could pursue the claim
    and consolidate a subsequent appeal with the existing one. The Board did not hold that
    such a claim would be time-barred; it simply denied a stay due to the lateness of the
    request. 4 It also emphasized that such a claim would be futile because the alleged delay
    would not affect the validity of the default. ECC CENTCOM, 18-1BCA137,133
    at 180,715. Here, the government agreed to an extension of time for Watts to respond to
    the government's dispositive motion based upon the absence of a delay claim so that
    Watts could submit that claim to the contracting officer. The time necessary for Watts to
    submit the claim has already been granted with the government's consent. ECC
    CENTCOM's reasoning for denying the time is therefore inapplicable.
    The government's request to dismiss Count I for lack of jurisdiction is denied.
    IL     Count II
    The second basis Watts advances to excuse its failure to perform on time is that
    the government waived the contract completion date (am. compl. 11102-28, 174-86;
    app. stmt. gen. issues 1127-43). Watts complains that the government waited seven
    months after Watts missed its earlier, November 22, 2016 deadline before it assessed
    liquidated damages in June of 2017. Similarly, it observes the government waited
    4
    The Board's denial of a stay reflected its retention of power to control its docket and
    protect the parties from undue prejudice. See ECC CENTCOM, 18-1 BCA
    137,133 at 180,715. Thus, a delay claim submitted to the contracting officer long
    after a termination for default is appealed, though possibly not time-barred under
    the CDA, might be too prejudicial to the government to permit its consolidation
    with the default appeal and entertained as a defense. Conversely, the
    government's threat that it might game the proceedings and purposely postpone a
    motion to dismiss until late in the litigation, to avoid consolidation with the appeal
    of a subsequent delay claim, is beneath the standards expected of it (see govt.
    reply br. at 9). Such a strategy would likely fail.
    7
    eight months, until July 13, 2017, to execute a bilateral modification with Watts to extend
    the completion date to December 21, 2017. It contends that the government's net
    assessment ofliquidated damages on January 3, 2017, is the date the government
    believed Watts was in default. It suggests the government acquiesced to its eventual
    declaration that the project would not be complete until May 25, 2018, by not objecting
    to that date, agreeing to review a resource loaded schedule to support it, and stating it was
    looking for a realistic completion date. In Count II of the amended complaint Watts
    maintains that all of these facts show the government did not consider time of the essence
    and induced Watts to incur additional costs performing the contract between
    December 21, 2017, and January 30, 2018. It adds in response to the government's
    motion that it was over 90 percent complete as of December 21 and spent over $1 million
    after that date (app. stmt. gen. issues ,r,r 42-43). Watts argues that a failure by the
    government to immediately terminate for default under those circumstances was also a
    manifestation that it did not intend to enforce the completion date. The government seeks
    summary judgment upon Count II, contending that the undisputed facts fail as a matter of
    law to support a finding that it waived the completion date.
    Waiver is an affirmative defense that Watts bears the burden to prove. See
    DayDanyon Corp., ASBCA No. 57681, 15-1BCAi136,073 at 176,152, aff'd,
    
    673 F. App'x 997
    (Fed. Cir. 2017). "The ... waiver doctrine ... protect[s] contractors who
    are led to believe that time is no longer of the essence" when allowed '"to continue
    [substantial] performance past a due date,' under circumstances that justify a conclusion
    that the default has been excused." Fla. Dept. ofIns. v. United States, 
    81 F.3d 1093
    ,
    1096 (Fed. Cir. 1996) ( quoting De Vito, 413 F .2d at 1153-54 ). But, waiver of default does
    not normally apply to construction contracts absent unusual circumstances. HK&S
    Constr. Holding Corp., ASBCA No. 60164, 19-1BCAi137,268 at 181,352;
    AmerescoSolutions, Inc., ASBCA No. 56811, 10-2 BCA ,r 34,606 at 170,549-50.
    Essentially, waiver is only recognized in the case of such a default when the government
    manifests that it no longer considers the contract completion date enforceable.
    Technocratica, ASBCA No. 47992 et al., 06-2 BCA i133,316 at 165,187.
    Watts has failed to make a showing that there is anything unusual here. It is not
    relevant that seven months passed before the government assessed liquidated damages for
    Watts' failure to comply with the prior November 22, 2016 completion date. Nor does it
    matter that the government waited eight months before it extended the completion date.
    What matters is that the July 13, 2017 modification consented to by Watts established
    December 21, 2017 as the new completion date "without waiving the Government's rights,
    including the right to assess liquidated damages until contract completion" (SOF ,r 2). See
    De 
    Vito, 413 F.2d at 1154
    (noting the government may reestablish that time is of the
    essence after waiving a prior completion date by setting a new date). From then on, the
    government consistently maintained that the December 21 date was binding. The
    government's September 20 cure notice warned Watts that its lack of progress jeopardized
    completion of the contract by December 21. On December 20, the contracting officer
    8
    notified Watts' surety that termination for default appeared imminent. (SOF 14) On
    December 21, upon Watts' failure to complete on time, the government informed Watts
    that it deemed the schedule and completion date in effect, it was not waiving its contract
    rights, and it reserved the right to terminate for default (SOF 1 5). On January 16, 2018,
    the government stated that it did not find Watts' response to its cure notice compelling or
    its delay excusable. While acknowledging that it would review a resource loaded schedule
    for completion in May, the government repeated that it considered the December 21, 2017
    completion date in effect, it did not waive its contract rights, and it reserved the right to
    terminate the contract for default. (SOF 16) Two weeks later the government terminated
    for default (SOF 17). Neither the government's willingness to consider Watts' resource
    loaded schedule, nor its comment that it was looking for it to be realistic, retracted its
    consistent communications that it was waiving nothing. See ASFA Int'! Constr. Indus. and
    Trade, ASBCA No. 57880, 14-1BCA135,736 at 174,912 (stating that a government
    encouragement to complete performance during a forbearance period is not a waiver absent
    further indication that the completion date is considered unenforceable); see also
    McDonnell Douglas Corp. v. United States, 
    182 F.3d 1319
    , 1327 (Fed. Cir. 1999)
    (observing that a manifestation of desire to proceed with the contract is not itself a waiver).
    These undisputed facts refute any suggestion that, to the extent Watts performed any work
    after December 21, it was against the backdrop of a government manifestation that it no
    longer considered that to be the completion date.
    Watts has not established a genuine issue of material fact respecting any of the
    elements of Count II's waiver defense. The government is entitled to summary judgment
    upon that count as a matter of law.
    III.   Count III
    Watts' third basis for relief challenges the validity of the termination for default on
    the ground that the contracting officer erroneously interpreted its January 24, 2018
    resource loaded schedule. Watts contests the contracting officer's conclusion that the
    schedule was incomplete and that it was not possible to complete the project by May 25.
    It also attacks the contracting officer's statement that the schedule inaccurately reflects
    certain activities as complete, reduced the time for testing, air balancing and
    commissioning activities, and eliminated required reviews (am. compl. 11 129-42). It
    relies upon a letter it sent to the contracting officer challenging her conclusions. It also
    relies upon the preliminary report of a consultant to its surety stating that the contracting
    officer was in error. It further cites the opinion of the government's construction chief
    that the schedule did not reduce testing time, appeared reasonable, and was resource
    loaded. (App. stmt. gen. issues 1144-53) Count III of the amended complaint therefore
    alleges that the contracting officer's decision to terminate was based upon materially
    erroneous information, adding that the government's decision failed to consider Watts'
    excusable delays. Watts says the contracting officer abused her discretion and that its
    default termination should therefore be set aside. (Am. compl. 11187-93) The
    9
    government seeks summary judgment on this count, arguing that Watts' evidence fails to
    amount to an abuse of discretion.
    "The level of discretion that must be exercised by the government before
    terminating a contract for default is a question of law." McDonnell Douglas, 182 F .3d
    at 1325. The extent of that discretion is broad, but the decision can be set aside if it is
    abused. 
    Id. at 1326;
    Third Coast Fresh Distribution, 16-1 BCA 1 36,340 at 177,194.
    "[T]he government may not use default as a pretext for terminating a contract for reasons
    unrelated to performance; instead, there must be a nexus between the government's
    decision to terminate for default and the contractor's performance." McDonnell 
    Douglas, 182 F.3d at 1329
    .
    Much of Watts' argument flows from its contention that the contracting officer
    partially based the default decision upon a belief that Watts' proposed new completion
    date was unrealistic (app. opp'n, ex.Cat 104-05). That the contracting officer may have
    been incorrect about Watts' proposal for a new completion date does not demonstrate that
    she abused her discretion terminating it for defaulting upon the existing completion date.
    That proposal was for the contracting officer's consideration. She made clear that her
    willingness to review it was not a waiver of the government's rights, including the right
    to terminate for default (SOF 16). The contracting officer could have terminated for
    default regardless of whether Watts could complete the work later. See HK&S Constr.,
    19-1 BCA 1 37,268 at 181,352 ("However the contracting officer arrived at her
    termination decision, the government may rely upon appellant's failure to do its job to
    justify the termination.").
    Additionally, to find that a default termination reflects an abuse of discretion
    because it was based upon "materially erroneous information" normally requires bad
    faith. See Delfasco LLC, ASBCA No, 59153, 17-1 BCA 136,659 at 178,527-28; see also
    McDonnell 
    Douglas, 182 F.3d at 1326
    (identifying bad faith as an element of abuse of
    discretion). The contracting officer "is presumed to have acted in good faith." Empire
    Energy Mgmt. Sys., Inc., ASBCA No. 46741, 03-1 BCA 132,079 at 158,553, ajf'd,
    
    362 F.3d 1343
    (Fed. Cir. 2004). To prove bad faith, Watts would have to "show with
    convincing clarity a high probability that she acted from personal animus with specific
    intent to injure" it. Id.; see also ADT Constr. Grp, Inc., ASBCA No. 55358,
    13 BCA 135,307 at 173,313 ("[A]ppellant makes no assertion, and there is no evidence,
    that the contracting officer acted out of a personal sense of bad faith"). Watts has failed
    to even allege such facts, much less "make a showing sufficient to establish the existence
    of [this] element...on which [Watts would] bear the burden of proof at trial." 
    Celotex, 477 U.S. at 322
    . Furthermore, there is no evidence the termination was pretextual. See
    McDonnell 
    Douglas, 182 F.3d at 1326
    -27. There is also no evidence the contracting
    officer exceeded the scope of the discretion vested in her, and Watts has not alleged that
    the contracting officer violated any regulations or law. See Shubhada Indus., Inc.,
    ASBCA No. 54016, 08-1BCA133,733 at 167,019. Finally, the contracting officer was
    10
    not presented with an excusable delay claim at the time of the default. Her mere rejection
    of Watts' allegations of it is not, by itself, bad faith.
    Watts has not established a genuine issue of material fact respecting any of the
    elements of Count III' s allegations. The government is entitled to summary judgment
    upon that count as a matter of law.
    IV.    Counts IV and V
    A. Request for Dismissal
    Both Counts IV and V assert breach of the implied duty of good faith and fair
    dealing. The government contends that Watts must submit a CDA claim to the
    contracting officer to pursue breach of contract as a defense to the contract's termination
    for default and seeks dismissal of the counts for that reason. That is incorrect.
    Securiforce Int'! 
    Am., 879 F.3d at 1362-63
    (stating that a common law affirmative
    defense to a termination for default, such as prior material breach, is not a claim that must
    be presented to the contracting officer). Accordingly, the request to dismiss is denied.
    B. Request for Summary Judgement upon Counts IV and V
    1. Count IV
    Watts' fourth basis for relief alleges that the government's quality assurance
    representative (QAR) made offensive comments to it. Watts has presented the
    declaration of a manager who states that the QAR threatened to "get rid" of Watts and
    asked whether Watts was bankrupt. According to the declaration, the QAR referred to
    Watts' project manager as a "liar" and said that the manager acted in "Watts' interest
    only." The QAR also more generally called Watts' personnel "liars" and "crooks" and
    said he was "going to take care of the government because the government always wins."
    The QAR asked if "Watts had gone bust yet." He asked Watts to leave discussions,
    excluded it from meetings, cancelled meetings, and declined to allow Watts to record
    information in accordance with its preferences. He called one of Watts' superintendents
    "fat." (App. opp'n, ex. B; app. supp. R4, tabs 108, 113-14) 5 Count IV of the amended
    complaint alleges that these statements and actions show animus, improper motive, and
    an intent to harm Watts, reflecting an abuse of discretion in terminating the contract that
    breached the implied duty of good faith and fair dealing ( am. compl. ,i,i 194-202 ). The
    government seeks summary judgment, observing that the QAR's behavior says nothing
    about the motive of the contracting officer terminating the contract and therefore does not
    demonstrate abuse of discretion.
    5
    Additional allegations contained in the declaration of Watts' manager are rejected
    because they are not made on personal knowledge. FED. R. CIV. P. 56(c)(4).
    11
    Though rude conduct by the QAR might be unpleasant, it does not demonstrate
    that the contracting officer abused her discretion terminating the contract for default.
    Watts does not allege that the contracting officer was influenced by the QAR, even knew
    about the QAR' s behavior toward it, much less that she shared any animosity that he
    might have harbored. The QAR' s allegedly poor demeanor does not show that Watts'
    default termination was issued by the contracting officer for reasons unrelated to Watts'
    failure to perform on time. It does not demonstrate she "acted from personal animus with
    specific intent to injure" it. Empire Energy Mgmt., 03-1BCA132,079 at 158,553.
    Similarly, the covenant of good faith and fair dealing contained in every contract
    imposes a "duty not to interfere with the other party's performance and not to act so as to
    destroy the reasonable expectations of the other party regarding the fruits of the
    contract."' Dobyns v. United States, 
    915 F.3d 733
    , 739 (Fed. Cir. 2019) (quoting Centex
    Corp. v. United States, 
    395 F.3d 1283
    , 1304 (Fed. Cir. 2005)). Mean behavior alone
    would not destroy Watts' expectations regarding the contract's fruits. Watts has not
    established a genuine issue of material fact respecting any of the elements of Count IV' s
    allegations. The government is entitled to summary judgment upon that count as a matter
    of law.
    2. Count V
    Watts' fifth basis for relief asserts that the government's inspectors were
    overzealous. Its manager's declaration states the QAR "interfered" with stucco installation
    and arbitrarily rejected it. The QAR allegedly over-inspected waterproofing, lathe and
    finish. He made Watts scrape glue resin without justification, cleanout and brush the
    interior of an electrical box, and paint wires. The QAR directed subcontractors without
    Watts' knowledge. Also, government inspectors were slow, repetitive, covered work that
    they should not have, and performed "multiple inspections." (App. opp'n, ex. B) Count V
    alleges that over inspection by the government breached the implied duty of good faith and
    fair dealing (am. compl. 11203-10).
    The government's request for summary judgment upon Count V contends that an
    element of a claim for breach of the duty of good faith and fair dealing is bad faith or
    improper motive. It says Watts cannot make that showing. Breach of the covenant of
    good faith and fair dealing does not require the violation of an express term of the
    contract, "[b Jut a specific promise must be undermined for the implied duty to be
    violated." 
    Dobyns, 915 F.3d at 739
    . Contrary to the government's suggestion, improper
    motive is not an element of such a breach. The duty may be breached "even if 'the actor
    believes his conduct to be justified."' Labatte v. United States, 
    899 F.3d 1373
    , 1379
    (Fed. Cir. 2018) (quoting RESTATEMENT (SECOND) OF CONTRACTS§ 205 cmt. d (1981)).
    12
    The Inspection of Construction clause permits just that. But, "confusing and
    vacillating" inspections, "multiple inspections to differing standards," or "arbitrary and
    capricious" inspections leading to additional "work not required by the contract," have
    established a basis for contractual recovery under a constructive change theory. See
    WF. Kilbride Constr., Inc., ASBCA No. 19484, 76-1 BCA ,-r 11,726 at 55,884
    (pre-CDA decision). There is precedent finding that a breach of contract theory is
    foreclosed when a contract provision such as the Changes clause grants the necessary
    remedy. See Hoel-Steffen Constr. Co. v. United States, 
    456 F.2d 760
    , 768 (Ct. Cl. 1972).
    That said, the government does not contend that overzealous inspection fails to support a
    breach of the implied duty of good faith and fair dealing, and the Board has somewhat
    acknowledged the possibility while also entertaining a possible constructive change. See
    Die-Matic Tool Co., ASBCA No. 31185, 89-1 BCA ,-r 21,342 at 107,601-03, ajf'd,
    
    889 F.2d 1100
    (Fed. Cir. 1989) (Table). Watts has presented adequate evidence of
    interference, over-inspection, slow, redundant, and multiple inspections, to require more
    factual development to determine the application of the good faith and fair dealing
    doctrine. See Tkacz Eng'g, LLC, ASBCA No. 60358, 18-1 BCA ,-r 36,940 at 179,962-63
    (concluding that mixed questions of fact and law preclude summary judgment).
    Accordingly, summary judgment upon Count Vis denied.
    CONCLUSION
    The government's request to dismiss Count I of the amended complaint is denied.
    The government's request for summary judgment upon Counts II and III is granted. The
    government's request to dismiss Counts IV and Vis denied. The government's request
    for summary judgment upon Count IV is granted. The government's request for
    summary judgment upon Count V is denied.
    Dated: June 24, 2019
    ~    Administrative Judge
    Armed Services Board
    of Contract Appeals
    (Signatures continued)
    13
    I concur
    J. REID PROUTY
    Administrative Judge
    Vice Chairman
    Armed Services Board
    of Contract Appeals                            of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA Nos. 61518, 61961, Appeals of
    Watts Constructors, LLC, rendered in conformance with the Board's Charter.
    Dated:
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    14