Freedom Systems, LLC ( 2015 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                 )
    )
    Freedom Systems, LLC                         )      ASBCA No. 59259
    )
    Under Contract No. W912C6-12-C-0005          )
    APPEARANCE FOR THE APPELLANT:                       Mr. Reginald B. McFadden
    President & CEO
    APPEARANCE FOR THE GOVERNMENT:                      Raymond M. Saunders, Esq.
    Army Chief Trial Attorney
    CPT Ahsan M. Nasar, JA
    Trial Attorney
    OPINION BY ADMINISTRATIVE JUDGE THRASHER ON THE
    GOVERNMENT'S MOTION FOR SUMMARY JUDGMENT
    Appellant, Freedom Systems, LLC (Freedom), appealed a contracting officer's
    final decision (COFD) denying appellant's sponsored claim of its subcontractor
    Wyndham Hotel Management, Inc. (Wyndham), in the amount of $820,800.00 in
    cancellation fees. The government asserts Wyndham provided appellant and the
    government a written release fully releasing appellant from any claims Wyndham
    might pursue against appellant related to the contract. Therefore appellant's appeal is
    barred by the Severin doctrine, entitling the government to a judgment as a matter of
    law. Freedom opposes the motion. We grant the government's motion.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
    1. On 10 November 2011, the Army Reserve Contracting Center - Fort Jackson,
    South Carolina (government), awarded Contract No. W912C6-12-C-0005 to Freedom to
    provide support services for eight Yell ow Ribbon Reintegration Programs (Events)
    scheduled to occur between 18 November 2011 and 16 September 2012 (R4, tab 1 at 1,
    13 ). The Yellow Ribbon Events are Congressionally mandated programs that assist
    National Guard and Reserve Soldiers and their families in transitioning back to civilian
    life from a military deployment (mot. ii 2).
    2. On 5 December 2011, Freedom entered into a Hotel Group Event Agreement
    with Wyndham (R4, tab 7 at 12). The agreement included a cancellation clause permitting
    Freedom to cancel a scheduled event upon providing notice to Wyndham prior to the
    scheduled event and payment of $136,800.00 per each canceled event (id. at 8).
    3. The government held the contracted events in Orlando, Florida, from
    November 2011 to September 2012 (R4, tab 1 at 13; app. resp. to answer ii 16). On
    9 January 2012, the contracting officer (CO) informed Freedom of numerous
    complaints received regarding the poor quality of services offered at the Wyndham
    Orlando Resort during the December 2011 event and asked Freedom to propose a new
    hotel for the remaining events (R4, tab 9). Thereafter, on 23 January 2012, the
    contract administrator informed Freedom that the customer had decided to reschedule
    the February 2012 event to 27-29 April 2012 and had "decided on the Rosen for all
    trips" (R4, tab 14 at 1).
    4. By email, on 25 January 2012, appellant confirmed that it was able to accommodate
    the change in venue and the new date (R4, tab 16 at 1).
    5. Freedom completed performance of the remaining events by 30 September
    2012 (app. resp. to answer ii 16).
    6. On 31July2013, appellant submitted a claim in the amount of$820,800.00
    stating:
    [T]his claim [is] for payment of subcontract
    cancellation damages to Wyndham pursuant to the
    "Cancellation Policy" provision of the committed
    subcontracts executed in the performance of the prime
    contract W912C6-12-C-0005.
    Freedom Systems, LLC is the interested party filing the
    claim. Freedom Systems, LLC is the prime company
    supporting execution of the subject contract.
    (R4, tab 22 at 2)
    7 .. On 11 September 2013, the CO informed Freedom that its claim was not
    properly certified as required for claims over $100,000.00 (R4, tab 24 at 1). Freedom
    resubmitted its claim with accompanying certification on 11 September 2013 (R4,
    tab 25 at 3).
    8. The CO issued a COFD denying Freedom's claim on 21 January 2014 (R4,
    tab 26). Freedom timely appealed the COFD to the Board on 11 April 2014 (R4,
    tab 27 at 1).
    2
    I
    9. Freedom filed its complaint on 8 May 2014 asserting the basis for its appeal,
    as follows:
    10. Government breached the contract when
    Appellant was directed to change venue by the
    Government despite our contractual obligation with the
    Wyndham. The Government was fully aware of these
    obligations but directed a change of venue despite such
    knowledge or necessity for a contract change to
    implement. At no time did the Appellant agree to release
    the Government from any and all liability under the
    contract for further equitable adjustments attributable to
    this change. Given that no contract modification was
    executed, Appellant was still under obligation to utilize
    the Wyndham in execution of the contract and had no
    standing to mitigate any subcontract damages with
    Wyndham. Conversely, Appellant can find no contractual
    requirement or obligation to notify Wyndham for
    mitigation of damages to reduce the claim as implied by
    the Government.
    11. Given that there was no termination,
    Appellant is not seeking liquidated damages resulting
    from termination of the contract as referred to by the
    government. Appellant is however seeking claims and
    equitable adjustments under FAR 52.212-4, Paragraph d.
    Disputes, for damages resulting from the breach of contract
    per item 9.
    12. Given that there was no termination, the
    Appellant asserts that it complied with all contract terms
    and conditions, and provided the Government, upon
    request, with adequate assurances of future performance.
    Where deficiencies were cited by the Government,
    Appellant provided satisfactory corrective actions and
    remedies.
    13. On September 11, 2013, Appellant submitted a
    certified claim and request for a contracting officer's
    final decision in the amount of $820,800.00. Appellant
    has and will submit documentation from Wyndham
    3
    compelling the Appellant to pay these amounts upon
    request by the Government or the Board pursuant to
    ASBCA Rule 14 or Rule 15 requests or actions.
    (Compl. ilil 10-13)
    10. On 14 July 2014, Freedom provided the government a copy of a letter
    dated 1March2012 that Freedom represented it had received from Wyndham's
    outside counsel. The letter asserted a claim of $820,800.00 against Freedom and
    threatened suit should Freedom fail to pay. Freedom also informed the government
    that Wyndham delayed filing a suit against appellant pending the outcome of its claim
    against the government. (App. resp. to answer il 22)
    11. Ms. Jennifer E. Constantinou, Vice President-Legal of Wyndham,
    executed a general release to Freedom on 21 April 2015 releasing any and all claims
    against Freedom related to Freedom's claim against the government, as follows:
    Wyndham Hotel Management, Inc., its agents,
    officers, parent corporations, employees, directors,
    servants, shareholders, representatives, predecessors,
    successors, heirs, executors, administrators and all other
    persons, firms, corporations, subsidiaries, affiliates,
    associations, partnerships, and the predecessors, successors
    and assigns of any of them (collectively, "Wyndham"),
    hereby fully and forever releases and discharges Freedom
    Systems, LLC ("Freedom") of and from any and all claims,
    actions, causes of action, demands, rights, costs, loss of
    service, expenses and compensation whatsoever, which
    the undersigned now has/have or which may hereafter
    accrue on account of or in any way growing out of
    Freedom's contract with the U.S. Army, Contract
    No. W912C6-12-C-0005 (or any contract related thereto)
    which form the basis for Freedom's appeal to the Armed
    Services Board of Contract Appeals ("ASBCA"),
    docketed as ASBCA No. 59259. Wyndham remises,
    releases, and discharges Freedom and Freedom's officers,
    agents, and employees, of and from all civil liabilities,
    obligations, claims, appeals, and demands which
    Wyndham has or may have, whether known or unknown,
    administrative or judicial, legal or equitable, including
    attorney's fees, arising under or in any way related to
    Contract No. W912C6-12-C-0005 or the disputes which
    form the basis of ASBCA No. 59259.
    4
    The undersigned further declare(s) and represent(s)
    that no promise, inducement or agreement not herein
    expressed has been made to the undersigned, and that the
    terms of this Release are contractual and not a mere recital.
    This Release and any party that succeeds to the
    rights and responsibilities of a party, such as predecessors,
    successors and assigns shall be bound by the terms and
    conditions of this Release.
    This Release constitutes the entire understanding
    and agreement of Wyndham respecting the resolution of
    this action. This Release may not be changed or modified.
    The undersigned represents that she has the
    authority to bind Wyndham.
    (Mot., ex. G-1)
    DECISION
    Summary judgment is appropriate when there is no genuine issue of material
    fact and the moving party is entitled to judgment as a matter of law. Anderson v.
    Liberty Lobby, Inc., 
    477 U.S. 242
    , 247-48 (1986). When considering a motion for
    summary judgment, the Board's function is not to weigh the evidence and determine
    the truth of the matter but to determine whether there is a genuine issue for trial. 
    Id. at 249.
    The moving party bears the burden of establishing the absence of any genuine
    issue of material fact and all significant doubt over factual issues must be resolved in
    favor of the party opposing summary judgment. However, the party opposing
    summary judgment must show an evidentiary conflict on the record; mere denials or
    conclusory statements are not sufficient. Mingus Constructors, Inc. v. United States,
    
    812 F.2d 1387
    , 1390-91 (Fed. Cir. 1987).
    The government contends Wyndham's 21April2015 general release provides
    the government with sufficient basis to invoke the Severin doctrine entitling the
    government to judgment as a matter of law (gov't mot. at 3). The Severin doctrine,
    which is taken from Severin v. United States, 
    99 Ct. Cl. 435
    (1943), cert. denied, 
    322 U.S. 733
    (1944), is based upon the principles of sovereign immunity and privity of
    contract. It generally precludes a prime contractor from sponsoring a subcontractor
    claim against the government if the prime contractor is not liable to the subcontractor
    for the costs or damages in question. 
    Severin, 99 Ct. Cl. at 442-44
    . Later precedent
    has narrowed the Severin doctrine clarifying that the doctrine is narrowly construed
    and the government bears the burden of showing the Severin doctrine applies. E.R.
    5
    Mitchell Construction Co. v. Danzig, 
    175 F.3d 1369
    , 1371 (Fed. Cir. 1999). As
    applied to releases, the government must show an unconditional iron-clad release that
    clearly protects the contractor from any and all liability to the subcontractor for the
    conduct in question. MA. Mortenson Co., ASBCA No. 53761, 06-1BCAii33,180
    at 164,439 (government must establish an iron-clad release); E.R. 
    Mitchell, 175 F.3d at 1371
    ; WG. Yates & Sons Construction Co. v. Caldera, 
    192 F.3d 987
    , 990-92 (Fed.
    Cir. 1999) (allowing prime contractor sponsorship in instances where the prime
    contractor is only conditionally liable to the subcontractor for whatever it can recover
    from the government).
    Appellant asserts three reasons why the Severin doctrine does not apply to the
    facts of this appeal. First, appellant argues, "Neither the Government nor Wyndham
    have provided guarantees or proof of any iron clad release sufficiency.... Because
    there is no validation of the release, Appellant asserts it (the Prime) remains liable to
    the subcontractor on the claim based upon the subcontract provisions provided as
    material facts under the appeal." (App. opp'n at 3) We disagree. Wyndham has
    provided appellant with an iron-clad general release that clearly protects appellant
    from any and all liability to Wyndham for appellant's conduct regarding the contract.
    Specifically, Wyndham's release "fully and forever" releases appellant from any all
    claims, causes of action, or variations that Wyndham currently has or may later have
    against appellant pertaining to appellant's contract with the government or this
    contract appeal. Wyndham's release is on behalf of its agents and subsidiaries to
    include the Wyndham Orlando Resort. Additionally, Wyndham's release is not
    conditional nor does it have limited time applicability. Wyndham's release applies to
    appellant, its agents, and its officers acting in an official capacity for appellant.
    Wyndham's release also clarifies that it did not receive consideration from either the
    government or appellant for granting its release against appellant. Furthermore,
    Wyndham's release indicates that it received no inducement to provide this release to
    appellant. Wyndham's release also binds its successor and is applicable to appellant
    and its successors. (SOF ii 11) The release was also executed by an officer of
    Wyndham with authority to bind the company (id.). Consequently, appellant can rely
    upon this release as an unconditional iron-clad shield from further liability to
    Wyndham related to the contract or the underlying issues of this claim.
    Second, appellant asserts the Severin doctrine does not bar its appeal because
    appellant's claim is not based upon its liability to its subcontractor but rather based
    upon a government breach of contract with the prime which caused the prime to incur
    damages from one of its subcontractors. The damages occurred when the government
    changed the event locations and dates but never memorialized the changes by
    modifying the contract. (App. opp'n at 4) The record before us on the motion
    establishes appellant's claim is, in fact, appellant's sponsorship of Wyndham's claim.
    Appellant's argument contradicts the only asserted rationale for its claim which was its
    liability to Wyndham under the subcontract agreement cancellation policy clause
    6
    (SOF iI 6). In addition, the only stated basis for its claim articulated in its complaint is
    its liability to Wyndham for cancellation of the events (SOF iI 9). Additionally, the
    only damages appellant's claim asserts against the government are for the exact
    amount that Wyndham would claim against appellant under the terms of their
    subcontract agreement (SOF iI 10). Appellant has not presented any evidence
    indicating an independent prime contractor claim and the record on the motion before
    us is devoid of any such evidence.
    And finally, appellant argues the Severin doctrine does not apply because of the
    government's wrongful failure to issue contract modifications for the changes in venue
    and time of events constituted a constructive contract termination of the subcontract
    under the termination clause, stating:
    Although Appellant's claim does not expressly seek
    recovery on a "constructive convenience termination"
    basis, Appellant may advance a legal theory on appeal
    that was not expressly raised in the claim if it relates to
    the same set of operative facts as the claim, which is the
    case here, J & J Maintenance, Inc., ASBCA No. 50984,
    00-1 BCA iI 30,784. Appellant['s] claim and resulting
    appeal establishes that the Government constructively
    terminated the prime and supporting contracts by its
    breach. Appellant's liability to Wyndham could be
    established under the Termination for Convenience clause
    in the subcontract. Under such circumstances the
    Severin doctrine clearly does not apply.
    (App. opp'n at 5) To the extent appellant is arguing the government's actions
    constructively terminated the prime contract, the facts in the record on this motion
    contradict appellant's argument. Appellant completed all contracted events and there
    is no evidence in the record on the motion before us supporting a constructive
    termination of the prime contract (SOF iI 5). Additionally, appellant's complaint
    contradicts this argument; appellant twice in its complaint stated there was no
    termination (SOF iI 9). To the extent appellant is arguing the government's actions
    constructively terminated Wyndham's subcontract, appellant has been released from
    any and all liability to Wyndham for the government's actions by the general release
    (SOF iI 11).
    7
    CONCLUSION
    We conclude appellant's sole claim is a subcontractor pass-through claim on
    behalf of its subcontractor Wyndham, based upon its liability to its subcontractor as a
    result of government actions. Because appellant's subcontractor, Wyndham, has fully
    and unconditionally released appellant from any and all claims related to this contract,
    we conclude appellant's claim is barred by the Severin doctrine. As a result, this
    release falls within the Severin doctrine barring this appeal as a matter of law. The
    government's motion for summary judgment is granted.
    Dated: 3 September 2015
    dministrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                         I concur
    //1~ at-------~-~,.___--_ _
    MARK N. STEMPLER"'                               RICHARD SHACKLEFORD
    Administrative Judge                             Administrative Judge
    Acting Chairman                                  Vice Chairman
    Armed Services Board                             Armed Services Board
    of Contract Appeals                              of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA No. 59259, Appeal of Freedom
    Systems, LLC, rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    8