New Iraq Ahd Company ( 2014 )


Menu:
  •                 ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeals of --                               )
    )
    New Iraq Ahd Company                        )      ASBCA Nos. 58763, 59286
    )
    Under Contract No. M20133-06-M-6065         )
    APPEARANCE FOR THE APPELLANT:                      Mr. Abbas Abed Mohsin
    Owner
    APPEARANCES FOR THE GOVERNMENT:                    Raymond M. Saunders, Esq.
    Army Chief Trial Attorney
    CPT Vera A. Strebel, JA
    Trial Attorney
    OPINION BY ADMINISTRATIVE JUDGE TUNKS ON THE GOVERNMENT'S
    MOTION TO DISMISS FOR LACK OF JURISDICTION
    New Iraq Ahd Company (NIAC) appeals from the denials of its alleged claims for
    payment of the contract amount regarding its contract to supply gravel to the government.
    
    ASBCA No. 58763
     concerns NIAC's uncertified claim for $180,800. 
    ASBCA No. 59286
    concerns NIAC's certified claim for $144,000. The government has moved to dismiss both
    appeals for lack of jurisdiction based on the failure to certify (
    ASBCA No. 58763
    ) and
    failure to comply with the Contract Disputes Act (CDA) statute of limitations (both
    appeals). 1
    STATEMENT OF FACTS FOR PURPOSES OF THE MOTION
    1. On 31 December 2005, the Joint Contracting Command/Iraq (JCC/I),
    PARC-Forces, Contracting Office, Fallujah, Iraq, awarded commercial items Contract
    No. M20133-06-M-6065 to NIAC to deliver 1,600 cubic meters of crushed gravel. The
    unit price was $113 per cubic meter resulting in a contract price of $180,800. (
    ASBCA No. 59286
     (59286), R4, tab 1at1-16) Delivery was required within ten days after
    "ADC" (after date of contract).
    2. The JCC/I terminated the contract for cause on 24 February 2006 for failure to
    deliver (59286, R4, tab 2). 2
    1
    The government's motion of 9 June 2014 to consolidate the appeals and consider its
    motion as applicable to both appeals was granted by Order dated 28 August 2014.
    2
    No appeal was filed from the Termination for Cause.
    3. On 8 December 2012, NIAC submitted a request to the contracting officer
    4
    (CO) for payment of the contract proceeds 3 (
    ASBCA No. 58763
     (58763), R4, tab 1 at 1).
    4. On 8 April 2013 the CO informed NIAC that she was not able to locate any files
    on the contract and would not make the requested payment to NIAC (58763, R4, tab 1 at 2).
    5. On 6 July 2013, NIAC filed a notice of appeal from the CO's refusal to make
    the requested payment. The appeal was docketed as 
    ASBCA No. 58763
    .
    6. On 13 November 2013, the government filed a motion to dismiss 
    ASBCA No. 58763
    .
    7. NIAC submitted a certified claim to the CO on 16 March 2014, eight years
    after the termination seeking $144,000 5 (
    ASBCA No. 59286
    , R4, tab 14 at 4, 5).
    8. On 24 March 2014, Ms. Christine A. Fricke, the CO, issued a final decision
    denying the claim.
    9. On 20 April 2014, NIAC appealed that final decision and 
    ASBCA No. 59286
    was docketed on 5 May 2014.
    DECISION
    It does not require citation that contractor claims under the CDA and FAR must be
    certified pursuant to that statute and regulation. If a claim is uncertified, this Board lacks
    jurisdiction because a proper claim has never been filed. NIAC's claim and appeal in
    
    ASBCA No. 58763
     suffers from this infirmity and must be dismissed without prejudice
    for lack of jurisdiction.
    Under the CDA, 
    41 U.S.C. § 7103
    (a)(4)(A), a contract claim, whether that of the
    contractor or the government, must be "submitted within 6 years after the accrual of the
    claim." We do not have jurisdiction over a claim that fails to meet this requirement.
    NIAC, as the proponent of our jurisdiction here, bears the burden of proving the facts
    sufficient to support our jurisdiction. Raytheon Missile Systems, 
    ASBCA No. 58011
    ,
    13 BCA if 35,241.
    3
    NIAC's complaint in 
    ASBCA No. 58763
     explains that it did not deliver any gravel
    because of security problems.
    4
    
    ASBCA No. 58763
    , Rule 4, tab 1 is a 13 November 2013 statement by the CO,
    addressed to the Board. It is neither an affidavit nor a declaration. We cite to this
    document only when it does not appear that the fact being found is in dispute.
    5
    The difference, according to NIAC's complaint in 
    ASBCA No. 59286
     is that $144,000
    represents only the cost of the gravel to NIAC.
    2
    Although the CDA does not define "accrual of a claim," FAR 33.201 defines the
    phrase as follows:
    Accrual of a claim means the date when all events, that
    fix the alleged liability of either the Government or the
    contractor and permit assertion of the claim, were known or
    should have been known. For liability to be fixed, some
    injury must have occurred. However, monetary damages
    need not have been incurred.
    In order to determine when liability becomes fixed for purposes of claim accrual,
    we first examine the legal basis of the claim. Gray Personnel, Inc., 
    ASBCA No. 54652
    ,
    06-2 BCA ii 33,378 at 165,475. The legal basis for NIAC's claim is that it has not been
    paid the contract proceeds. We know little else regarding the legal theory under which
    NIAC claims entitlement. 6 NIAC's claim accrued on the date when all events that fixed
    the government's alleged liability and permitted assertion of the claim, were known or
    should have been known. In this case, all events that fix the liability of the government
    and permit NIAC to assert a claim were known on 24 February 2006, the date on which
    the government terminated NIAC for cause. No material events have occurred since that
    date. 7 In order for NIA C's claim to be timely under the CDA, it had to have been filed
    on or before 24 February 2012. NIAC did not file its certified claim until 16 March
    2014, two years after the expiration of the statute of limitations. As a result, we lack
    jurisdiction to decide 
    ASBCA No. 59286
    .
    CONCLUSION
    The government's motion to dismiss for lack of jurisdiction is granted. The
    appeals are dismissed for lack of jurisdiction.
    Dated: 22 October 2014
    (Signatures continued)
    6
    As stated earlier, NIAC did not appeal the termination of its contract.
    7
    Certainly the date when the CO first told NIAC that it would not be paid the contract
    proceeds cannot fix the relevant date. Otherwise, NIAC could put off indefinitely
    the accrual rate by not requesting the contract proceeds.
    3
    I concur                                       I concur
    /~~
    ifuU<~'                                        RICHARD SHACKLEFORD
    Administrative Judge                           Administrative Judge
    Acting Chairman                                Vice Chairman
    Armed Services Board                           Armed Services Board
    of Contract Appeals                            of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA Nos. 58763, 59286, Appeals of
    New Iraq Ahd Company, rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    4
    

Document Info

Docket Number: ASBCA No. 58763, 59286

Judges: Tunks

Filed Date: 10/22/2014

Precedential Status: Precedential

Modified Date: 11/3/2014