Combat Support Associates ( 2014 )


Menu:
  •                 ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeals of --                                     )
    )
    Combat Support Associates                         )      ASBCA Nos. 58945, 58946
    )
    Under Contract No. DASA02-99-C-1234               )
    APPEARANCES FOR THE APPELLANT:                           Karen L. Manos, Esq.
    Owen E. Whitehurst, Esq.
    Gibson, Dunn & Crutcher LLP
    Washington, DC
    APPEARANCES FOR THE GOVERNMENT:                          E. Michael Chiaparas, Esq.
    DCMA Chief Trial Attorney
    Douglas R. Jacobson, Esq.
    Trial Attorney
    Defense Contract Management Agency
    Bloomington, MN
    OPINION BY ADMINISTRATIVE JUDGE MCILMAIL
    ON APPELLANT'S MOTION TO DISMISS FOR LACK OF JURISDICTION
    Appellant moves to dismiss these appeals from government claims for lack of
    jurisdiction, contending that the government's claims are barred by the statute of
    limitations. The Board denies the motion, without prejudice.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
    1. On 13 July 1999, the Department of the Army (government) awarded
    Contract No. DASA02-99-C-1234 to appellant, Combat Support Associates, for the
    provision of support and security services in Kuwait (R4, tab 1 at 1; app. mot. at 1, ~ 1;
    gov't opp'n br. at 1).
    2. On 30 August 2007, appellant submitted to the government its fiscal year
    (FY) 2006 incurred cost submission (ICS) (app. mot., ex. 1 at 2).
    3. On 10 May 2007, the government requested that appellant submit three
    additional items: (1) a formal letter confirming the submission of the ICS; (2) a compact
    disc containing ''the same information"; and (3) a "Schedule T" (app. mot., ex. 2).
    4. On 14 May 2007, appellant submitted to the government a formal letter
    confirming its ICS submission (app. mot., ex. 3).
    5. On 20 May 2007, appellant submitted to the government its "Schedule T,"
    and a compact disc with a copy of that schedule (app. mot., ex. 4).
    6. On 25 August 2007, appellant submitted to the government revised
    Schedules A and B of its ICS (app. mot., ex. 5).
    7. On 17 June 2013, the Defense Contract Audit Agency (DCAA) issued a
    report on an audit of the ICS (app. mot., ex. 6).
    8. On 23 August 2013, the administrative contracting officer (ACO), having
    reviewed the DCAA audit report, issued two final decisions, one demanding that
    appellant pay the government $332,167 in disallowed direct costs (app. mot., ex. 7), and
    the other disallowing indirect costs and unilaterally determining appellant's indirect cost
    rates for FY 2006 (app. mot., ex. 8).
    9. The ACO's payment demand consists of two categories of disallowed direct
    costs: (1) $308,889 in equipment costs, and (2) $23,278 in telephone and fax expenses
    (app. mot., ex. 7 at 1-2). The ACO disallowed and demanded repayment of$164,008 of
    the equipment costs because it determined that appellant had failed to provide
    documentation that justified the purchase of Caterpillar equipment from Winner
    International Trading Company (Winner), as opposed to from whom the ACO identified
    as the sole authorized distributor of Caterpillar equipment in Kuwait in FY 2006,
    Mohamed Adulrahman Al-Bahar (id. at 1). The amount disallowed was the difference
    in price between the two suppliers (app. mot., ex. 6 at 33). The ACO disallowed and
    demanded repayment of $144,881 of the equipment costs because it determined that
    appellant had failed to provide documentation that justified "the selection of Volvo
    Motor Road Grader rather than the lowest bidder supplier" (app. mot., ex. 7 at 1-2).
    10. The ACO also disallowed and demanded repayment of $23,278 in telephone
    and fax expenses "to adjust for personal use of [the] telephones and fax machines by
    [appellant's] employees" (app. mot., ex. 7 at 2). The ACO explained that "[d]uring
    DCAA audit, [appellant] acknowledged" that the $108,777 in telephone and fax
    expenses that appellant had proposed "includes unallowable telephone/fax expenses
    costs [sic] that were not voluntarily deleted" (id.). Such personal-use telephone and fax
    expenses also comprise $13 3, 779 (of $625, 13 5 such expenses proposed) of the
    $1,409,464 in indirect cost disallowances that form the basis of the CO's unilateral
    determination of appellant's FY 2006 indirect cost rates (app. mot., ex. 8 at 1-3).
    Including telephone and fax expenses, those indirect cost disallowances consist of seven
    distinct categories (id. at 1).
    11. On 2 October 2013, appellant timely filed an appeal docketed as 
    ASBCA No. 58945
     (appealing the CO's final decision demanding payment of disallowed direct
    costs), and filed an appeal docketed as 
    ASBCA No. 58946
     (appealing the CO's final
    decision disallowing indirect costs and determining indirect cost rates).
    2
    12. On 20 March 2014, DCAA Supervisory Auditor Kathryn Adamson declared
    under penalty of perjury that:
    I have reviewed the DCAA files related to [appellant's ICS]
    and, to the best of my knowledge, the supporting data related
    to those costs identified in the two (2) Government
    contracting officer final decisions dated August 23, 2013 was
    not provided to the auditors until after August 23, 2007.
    (Gov't opp'n, ex. G-1)
    DECISION
    Appellant seeks the dismissal of these appeals for lack of jurisdiction, contending
    that they are time barred pursuant to the Contract Disputes Act, 
    41 U.S.C. § 7103
    (a)(4).
    That section requires a contract claim to be "submitted within 6 years after the accrual
    of the claim." 
    Id.
     The government opposes, making it the proponent of the Board's
    jurisdiction, with the burden of proving that the Board possesses jurisdiction to entertain
    the appeals. 1 Raytheon Missile Systems, 
    ASBCA No. 58011
    , 13 BCA if 35,241 at
    173,016. The government must establish, by a preponderance of the evidence, facts
    sufficient to invoke the Board's jurisdiction. See Reynolds v. Army & Air Force
    Exchange Service, 
    846 F.2d 746
    , 748 (Fed. Cir. 1988).
    In deciding the motion, the Board has presumed undisputed facts to be true;
    disputed jurisdictional facts have been subjected to our fact-finding based upon a review
    of the record. Raytheon Missile Systems, 13 BCA if 35,241at173,016. A claim accrues
    under the CDA when "all events, that fix the alleged liability ... and permit assertion of
    the claim, were known or should have been known." Id. at 173,017 (citing
    FAR 33.201). Given the CDA's six-year limitation, to be timely, the government's
    23 August 2013 claims must have accrued on or after 23 August 2007.
    The government has met its burden, at least upon the record currently before the
    Board. Appellant contends that the government's claims accrued no later than 20 May
    1
    At page 2 of its brief, the government cites Sikorsky Aircraft Corp. v. United
    States, 
    105 Fed. Cl. 657
     (2012) (the government's citation mistakenly reports
    that the court issued its opinion in 2013), an opinion that is not binding precedent
    for the Board. MA. Mortenson Co., 
    ASBCA No. 53346
    , 05-2 BCA if33,014 at
    163,616 n.3. In addition, the government follows that citation with a quotation
    (at page 3 of its brief) that does not appear in the opinion that begins at 
    105 Fed. Cl. 657
    , but in Sikorsky Aircraft Corp. v. United States, 
    110 Fed. Cl. 210
    , 220
    (2013). The government provides "Sikorsky at 11" as the citation for the
    quotation.
    3
    2007 (app. mot. at 4), when (except for revisions to Schedules A and B) appellant
    completed the submission of its ICS (SOF ifif 5-6). The government contends that it "had
    no knowledge, and had no reason to know, whether the costs were allowable until
    [appellant] provided the detailed information (adequate supporting data) showing the
    costs were allowable" (gov't opp'n br. at 7). In support of that contention, the
    government relies upon the declaration of DCAA Supervisory Auditor Adamson, who
    states that "the supporting data related to those costs identified in the two
    (2) Government contracting officer final decisions dated August 23, 2013 was not
    provided to the auditors until after August 23, 2007" (SOF if 12). Appellant does not
    counter by demonstrating that, even without any supporting data, the government had, on
    20 May 2007, the information it needed to know that it had the claims set forth in the
    ACO's 23 August 2013 final decisions (that is, a demand for payment of disallowed
    direct costs, and the unilateral determination of indirect cost rates based upon the
    disallowance of indirect costs), or that the government had additional information before
    23 August 2007 from which it knew or should have known of its claims.
    For example, appellant does not demonstrate that the ICS informed the
    government that appellant had purchased Caterpillar equipment from Winner instead of
    Mohamed Adulrahman Al-Bahar; the reason that the ACO demanded the repayment of
    $164,008 in billed equipment costs (SOF if 9). Nor does appellant demonstrate that the
    ICS informed the government that appellant had selected Volvo Motor Road Grader
    rather than "the lowest bidder supplier," the reason that the government demanded the
    repayment of $144,881 in billed equipment costs (id.). Indeed, the ICS does not appear
    to indicate that appellant purchased Caterpillar equipment from Winner, or that it had
    selected Volvo Road Grader (app. mot., exs. 1, 4). In addition, although the ICS
    proposes $625,135 in telephone and fax expenses (app. mot., ex. 1), it does not appear
    also to indicate that some of those expenses were the result of personal use by
    appellant's employees. Finally, appellant does not counter Ms. Adamson's declaration
    by demonstrating that any of the disallowances that form the bases for the government's
    claims was otherwise determinable prior to 23 August 2007 (perhaps, for example, by
    reference to the Federal Acquisition Regulation), even without any of the "supporting
    data" to which Ms. Adamson refers.
    Appellant replies that a contractor is not required to submit supporting data with
    an ICS. That misses the point. The issue raised by appellant's motion is when the
    government knew or should have known of its claims; not whether the ICS satisfied the
    requirements for an JCS. Upon the record currently before the Board, the government
    has established that it knew or had reason to know of its claims only after 23 August
    2007, upon appellant's submission of the "supporting data" from which the government
    learned, or had reason to learn, of its claims. Because it brought those claims on
    23 August 2013, within six years of 23 August 2007, those claims are not time barred,
    and the Board possesses jurisdiction to entertain them.
    4
    For these reasons, appellant's motion to dismiss these appeals is denied, without
    prejudice. This decision is interlocutory. See Checker Moving, 
    ASBCA No. 32654
    ,
    87-1BCAif19,357 at 97,904. Therefore, it is subject to modification. E.I. du Pont de
    Nemours & Co. v. United States Camo Corp., 
    19 F.R.D. 495
    , 498 (W.D. Mo. 1956).
    Indeed, the Board has a special obligation to satisfy itself of its own jurisdiction, see
    Weeks Marine, Inc. v. United States, 
    575 F.3d 1352
    , 1359 (Fed. Cir. 2009), and will be
    mindful of that obligation as the record develops further regarding the several
    components of the government's claims. Accordingly, the jurisdictional evidentiary
    hearing currently scheduled for 18-19 November 2014 is canceled, to be rescheduled to
    coincide with any hearing upon the merits of these appeals.
    Dated: 22 October 2014
    1IM0THYPCiiL
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                         I concur
    ~~~
    ~      N. STEMPLER
    Administrative Judge
    RICHARD SHACKLEFORD
    Administrative Judge
    Acting Chairman                                  Vice Chairman
    Armed Services Board                             Armed Services Board
    of Contract Appeals                              of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA Nos. 58945, 58946, Appeals of
    Combat Support Associates, rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    5
    

Document Info

Docket Number: ASBCA No. 58945, 58946

Judges: McIlmail

Filed Date: 10/22/2014

Precedential Status: Precedential

Modified Date: 11/3/2014