Swinerton Builders Northwest ( 2017 )


Menu:
  •               ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of--                                 )
    )
    Swinerton Builders Northwest                )     . 
    ASBCA No. 57329
    )
    Under Contract No. NAF26-04-C-0025          )
    APPEARANCES FOR THE APPELLANT:                     Durward E. Timmons, Esq.
    Milton L. Smith, Esq.
    Ryan J. Klein, Esq.
    Sherman & Howard L.L.C.
    Colorado Springs, CO
    Arnold R. Hedeen, Esq.
    Hedeen & Caditz, PLLC
    Seattle, WA
    APPEARANCES FOR THE ARMY LODGING FUND:
    Raymond M. Saunders, Esq.
    Army Chief Trial Attorney
    LTC Lawrence P. Gilbert, JA
    Robert T. Wu, Esq.
    MAJ John C. Dohn II, JA
    Erica S. Beardsley, Esq.
    Trial Attorneys 1
    OPINION BY ADMINISTRATIVE JUDGE DICKINSON
    This appeal arises from a contract awarded by CFSC 2 on behalf of respondent
    Army Lodging Fund (AL, ALF or Fund), a Nonappropriated Fund Instrumentality
    (NAFI), to Swinerton Builders Northwest (appellant or SBN) to build a 185-room
    1
    Mr. Wu and MAJ Dohn represented the Fund at the hearing and Ms. Beardsley
    represented the Fund at the time the briefs were filed.
    2 The U.S. Army Family and Morale, Welfare and Recreation Command, known at all
    times relevant to the matters before us as the U.S. Army Community and
    Family Support Center (CFSC), is a field operating activity of the U.S. Army
    and the organization responsible for contracting on behalf of the Army Lodging
    Fund (answer`` 2, 3).
    lodging facility at Fort Lewis, Washington. 3 Only entitlement is before us for
    decision. 4
    JURISDICTION
    It is undisputed that CFSC has never issued a contracting officer's final
    decision addressing SBN's 2005 and 2008 Requests for Equitable Adjustment (REAs)
    or SBN' s 3 June 2010 certified claim. It is further undisputed that SBN appealed to
    the Board from a deemed denial on 18 August 2010.
    Under the Disputes clause of the NAF contract at issue, the Board has
    jurisdiction over an appeal from the denial of a claim arising under the contract
    (finding 25). The contract's Disputes clause, however, does not contain a provision
    for an appeal from a deemed denial of a contractor's claim. Under certain
    circumstances we have taken jurisdiction in the absence of a final decision under a
    NAF contract.
    It is well established that the purpose of the Disputes
    clause is to provide the parties with a rapid and
    inexpensive means of resolving disputes between the
    parties. Mite Corporation, 
    ASBCA No. 18534
    , 73-2 BCA
    ,10,312.
    Prior to the CDA's enactment and under contracts
    where the CDA does not apply, we have taken jurisdiction
    over disputes that have existed for lengthy periods without
    a final decision. See Mite Corp., supra; Atlantis
    Construction Corp., ASBCA No[s]. 44044, 44860, 96-1
    BCA, 28,045. As the Board explained in Mite Corp.,
    supra, at 48,687, failure or r~fusal by the CO to issue a
    final decision within a reasonable time constitutes a final
    decision [denying the appeal and] giving jurisdiction to the
    Board.
    Charitable Bingo Associates, Inc., d/b/a Mr. Bingo, 
    ASBCA No. 53249
    , 01-2 BCA, 31,478.
    The situation before us is even more compelling than the one the Board
    addressed in Charitable Bingo. From the 3 June 2010 submission of SBN's claim to
    the September 2012 hearing, not only did CFSC not issue a contracting officer's final
    3 Fort Lewis and McChord AFB were combined and became Joint Base Lewis-McChord as
    of 1 October 2010. http://www.military.com/base-guide/joint-base-lewis-mcchord.
    4 The number of days of any delay are considered to be part of entitlement (tr. 119).
    2
    decision, but the contracting officer never formally acknowledged receipt of SBN's
    6,800-page claim, nor did he ever meaningfully respond to the many pleas from SBN
    and its counsel in letters and phone calls seeking a response to the claim. We find
    CFSC's near-complete failure of response to SBN's claim in more than two years to
    constitute a refusal to issue a final decision which, if not deemed to be a denial of
    SBN' s claim, would effectively deprive SBN of its right of appeal under the contract's
    Disputes clause (see finding 25). We, therefore, hold that we have jurisdiction over
    this appeal from a deemed denial. 5
    FINDINGS OF FACT
    A. Background and Pre-Contract Matters
    1. Appellant SBN is a corporation organized and existing under the laws of the
    State of Delaware and has its principal place of business in San Francisco, California.
    The company was originally started as a small construction business in 1888 and at the
    time they were awarded the contract which is the subject of this appeal they were
    performing over a billion dollars in construction business per year. (R4, tab 3 at
    1964 6, tab 127 at 2873; tr. 1121-22, 45, 5/173)
    2. Under a pre-existing indefinite-delivery, indefinite quantity (IDIQ) contract
    between CFSC and ORB 7, ORB was tasked with providing a 10% concept design for
    the F ~rt Lewis Lodge design-build project that included a site plan drawing, followed
    by ORB' s drafting of the Request for Proposals (RFPs), within which the 10% concept
    design and site plan drawing were incorporated. John Patterson, 8 ORB's Vice
    5 Neither party alleges that our jurisdiction is based on the Contract Disputes Act
    (CDA). Since we have held that we have jurisdiction pursuant to the Disputes
    clause of the contract and the basis of our jurisdiction is not material to our
    consideration of the entitlement issues presented, we do not address the issue of
    CDA jurisdiction.
    6 Page number references are to the consecutively-numbered pages unless specified
    otherwise.
    7
    ORB was an architectural firm on contract to CFSC to prepare the RFP for the Lodge
    project and to be CFSC's on-site representative during contract performance
    (tr. 2/102-03, 120, 8/39-40, 42, 9/30-33, 10/12-13, 15-16). ORB, in tum,
    contracted with BCE Engineers (BCE) to review the mechanical design,
    starting with the 35% design review (tr. 21120, 123, 9/39-40, 46).
    8 Mr. Patterson has 23 years of active military duty, reaching the rank ofChiefMSgt,
    and had been a military project manager/designer) (tr. 10/6-11, 123-24). He is
    not a licensed professional engineer (tr. 10111-12), however, he has worked
    very closely with Fort Lewis since 1984 on "engineering and construction
    3
    President and military projects manager, was the individual responsible for drafting the
    RFP. (Tr. 10/14, 18, 27; see also R4, tabs 171, 1001 (SOW for AIE preparation of
    RFP)) Mr. Patterson specifically developed RFP Sections C-1 through C-5 and
    portions of Sections J and L, leaving other sections unchanged as "standard language"
    (tr. 10/19-28, 136-47, 168). He testified that he was particularly concerned with the
    "site layout plan, utility plan" (tr. 10/19).
    1.     Request for Proposals
    3. On 20 October 2003, the Fund issued RFP No. NAF26-04-R-0004 for the
    design and construction of a four-story, 100,500 square foot, 185-room Army lodging
    facility (Lodge) at Fort Lewis, Washington (R4, tabs 2, 169 at 3122, 3353, tab 1012).
    The RFP included the following language:
    No appropriated funds of the United States will become
    due or be paid to the Contractor or Concessionaire by
    reason of this contract. This contract is governed
    exclusively by the provisions of Army Regulation 215-4}91
    (R4, tab 2 at 866) The RFP identified contracting officer (CO) Bartholomew, who was
    assigned to the CFSC, NAF Contracting Directorate (CFSD-NC), and stated that CFSC
    was located in Alexandria, Virginia. SBN's Montoya testified that he scheduled many
    meetings with CO Bartholomew, "but I never had meetings" (tr. 3/183). It is a matter of
    record that CO Bartholomew's office (as well as that of COR Dyer) was located in
    Alexandria, Virginia, and the project was under construction in Tacoma, Washington.
    Further, the record is replete with instances of CO Bartholomew participating in meetings
    and other conversations by phone, as well as some face-to-face meetings. Both parties
    dealt with the challenges of being on opposite coasts. (Ex. A-9; see, e.g., tr. 3/201, 204,
    256-57, 4/108-09, 111) The RFP further advised as to CO Bartholomew's authority
    under any resultant contract:
    The Contracting Officer is the only person authorized to
    approve changes to any of the requirements under this
    contract, and notwithstanding any provision contained
    elsewhere in this contract, said authority remains solely
    projects, primarily maintenance and repair projects on existing facilities,
    renovations, small additions perhaps, but all disciplines and all cost brackets."
    9
    SBN's counsel used a copy of AR 215-4 during cross-examination of CO Wallace
    but did not offer the document into the record. After the testimony, appellant's
    counsel asked that the Board take judicial notice of the current version of AR
    215-4; without objection from government counsel, the request was granted
    (tr. 12/216).
    4
    with the Contracting Officer. In the event the Contractor
    effects any change at the direction of any person other than
    the Contracting Officer, the change will be considered to
    have been without authority and no adjustment will be
    made in the contract price to cover any increase in changes
    incurred as a result thereof.
    (R4, tab 2 at 954; see also R4, tab 2 at 1034, 1036, 1043; tr. 12/156) CO Bartholomew
    was not called to testify at the hearing by either party.
    4. The Fund's Project Manager for the Lodge project, as well as being identified
    as the contracting officer's representative (COR) in the RFP, was Drew Dyer. COR Dyer
    has a degree in civil engineering (1976) and has been a licensed professional engineer
    since 1989. He has extensive construction project management experience from 1978
    through the time of his hearing testimony in 2012, including being the manager of the
    engineering branch of the Washington (DC) Airport Authority responsible for Dulles
    International Airport and Washington National Airport (now Washington Reagan
    Airport) as well as several smaller airports in Texas and Florida. From 1998-2001 he was
    employed by CFSC as one of 3 project managers, together with 2 COs to manage
    14 Navy NAF design-build projects around the world. Since 2001 he has been employed
    by CFSC to manage Army Lodging NAF projects around the world. He was involved
    with the project now at issue at Fort Lewis beginning in 2003 during development of the
    RFP. (Tr. 8/13-33, 52, 9/8-11, 77-81, 12/175-76) As the COR, he was a technical
    advisor to the CO (tr. 12/157, 175).
    5. Both CO Bartholomew and COR Dyer were CFSC employees and were
    based in Alexandria, Virginia, however, their jobs required frequent travel to various
    project locations. Their visits to the jobsite at issue in this appeal were infrequent and
    their involvement in the matters now before us was primarily by phone, email and letter
    (tr. 1/114-15, 181-82, 2/107, 115, 7/269-70, 271-74, 9/8-10, 81-8, 105-08, 116-17,
    131-32, 134, 10/153, 11117, 39, 63-65, 96, 101-02, 103-05, 12/25-26, 66; ex. A-9).
    6. ORB's Monson was hired to be CFSC's representative at the jobsite (see
    finding 2) and was described as CFSC's "eyes and ears." Mr. Monson was retired
    from the Corps of Engineers where he had worked from 1973-2001 and had been
    involved in construction projects, including some for CFSC. He is a licensed architect
    in the state of Washington (tr. 11/6, 33-37). Mr. Monson attended "99%" of the
    project meetings but had no contractual authority. (Tr. 1/180-83, 233-34, 2/107,
    115-16, 4/108-09, 5/10, 39, 7/270-72, 9179, 86-89, 10/114, 119, 121-22, 11/6-7, 21,
    38-44, 46, 100-02, 106, 12/156) His first involvement with the project was in October
    2004 (tr. 11/6, 9), and his primary duties were to observe the construction activities on
    a daily basis and be the on-site point of contact for SBN's quality control personnel
    (tr. 1117; see also finding 18, § 3.14). Mr. Monson was also responsible to review
    5
    SBN' s pay applications for the purpose of coming to agreement as to the percentage of
    project completion and to sign them before SBN submitted them to CFSC (R4,
    tab 1215 at 2327-28; tr. 11117-19, 52-55, 69-70, 93-94). He left the project in January
    2007 (tr. 11/9).
    7. RFP SECTION C-1, GUIDANCE TO CONTRACTORS, PROJECT
    INFORMATION, included the following information pertinent to the matters now
    before us:
    1.2 Project Description: The project includes all design and
    construction necessary to construct a new 185-Room Lodging
    Facility. The project includes all demolition, site grading and
    preparation, site utilities and improvements and construction
    necessary to provide a complete and useable facility.
    1.3 Scope of Work:
    A. Lodging Facility:
    1. Design and construct a new Lodging Facility that will
    include 185 guest rooms, lobby and registration areas,
    breakfast room, fitness room, administrative offices,
    public toilets, guest laundries and vending areas, support
    storage and maintenance areas, an in-house laundry, a
    delivery dock, parking for 100 vehicles, and
    miscellaneous ancillary support areas.
    2. The work includes coordinating with the installation of
    Government Furnished Government Installed (GFGI)
    equipment, finishes and furnishings.
    B. Design Work:
    1. Conceptual architectural and site plan drawings are
    included in this Request for Proposal (RFP). The design
    solution represented by the RFP concept level
    drawings[ 10l is acceptable to the Government. However,
    innovative, creative, or cost-saving proposals that meet
    or exceed the RFP-specified requirements are
    encouraged and will be rated accordingly. Offerors who
    choose to submit alternate building or site
    configurations must meet all requirements in the
    RFP.
    10
    The RFP contained 10% concept design and drawings (finding 2).
    6
    2. The following is a list of mandatory features for the
    design of the facility in addition to other criteria required
    in the RFP:
    d. Maximum building height is 4-stories. Maximum
    ridge height is 55 feet.
    f. Guest Room floor plan, layout and sizes shall be in
    accordance with the concept guest room drawings
    provided in the RFP. Mechanical chases, plumbing
    chases, etc. are to be integrated without reducing
    net areas shown or specified.
    3. The conceptual plans provided in the RFP represent the
    Government's effort to communicate one possible
    design solution that meets the Owner's requirements.
    These plans are acceptable to the Government but
    Offerors may submit alternate plans that they believe
    maximize the benefit to the Government. Those Offerors
    who decide to use the Government's layout are still
    required to submit these layouts as part of their proposal.
    The successful Offeror shall execute the design using the
    layouts approved by the Government. PDF files of the
    RFP concept drawings will be made available for the
    Offerors' use in preparing their proposals. A CADD file
    is available for the Site Utilities Plan.
    4. The requirements in the RFP are minimum standards
    and may be exceeded by the Offerors. Deviations from
    these technical or functional requirements shall be
    clearly identified for Government review and may be
    approved if considered by the Government to be in
    its best interest.
    5. The extent of development of these documents in no
    way relieves the successful Offeror from his
    responsibility of completing the design, construction
    documentation and construction of the facility in
    7
    conformance with applicable criteria, codes and
    standards.
    6. The Contractor will be required to meet with the
    Government during the design phase of the project
    (Design Kick-off Meeting and Submittal Review
    Meetings, etc.). Discussions and reviews during the
    meetings will further refine the accepted design solution.
    The Contractor should anticipate adjustments to the
    conceptual layouts during the design process.
    7. See Section Hof the RFP for Design Submittal
    Requirements and Design Meeting Requirements after
    award.
    C. Concept Room Construction:
    I. Design and construct a temporary water resistant
    mock-up concept room[llJ for each guest room type to
    demonstrate the intended construction and layout,
    including any variations in room size/configuration
    caused by seismic/structural bracing, columns, etc. The
    mock-ups shall be located on the project site where
    directed by the Owner. The mock-ups shall consist of
    floors, walls and ceilings of the intended construction
    and include representations of windows, doors,
    kitchenette equipment, casework, specialties, fixtures,
    lighting, switches, outlets, grilles, registers, thermostats
    and sprinkler heads. Sample plumbing fixtures, outlets,
    grilles, registers, thermostats, kitchenette equipment and
    sprinkler heads shall be in place but need not be
    operational. Mock-furnish each concept room mock-up
    in accordance with FF&E list in Section J.
    2. Mock-up concept room construction can begin after the
    Project Kick-Off Meeting. The Contractor shall provide
    for a Government walkthrough of rough construction
    (framing, drywall, no finishes) to coincide with the 35%
    Design Review Meeting. A final Government
    walk-through of the completed concept room Mock-ups
    shall be scheduled by the Contractor at an appropriate
    time to allow for design corrections and adjustments
    prior to submission of the final design. All changes to
    design during the design process must be physically
    11
    SBN understood that the mock-up concept rooms were to be temporary structures
    external to the lodge it was building (app. br. at 147-48).
    8
    presented in mock-ups prior to submission of final
    design. The Contractor shall be responsible for removing
    the mock-ups after completion of new building
    construction. Contractor may re-use salvageable FF&E,
    plumbing fixtures and kitchen unit in the construction.
    3. Final Concept RoomC 121: The Contractor shall provide
    one fully finished, fully furnished (including GFCI and
    CFCI items) guest room of each type during
    construction phase for final approval of finishes and
    workmanship, before the remaining rooms are finished.
    This milestone item will be shown in the Project
    Construction Schedule at a point in the construction
    progress as mutually agreed upon. These rooms will be
    approved by the Government before remaining final
    finishes are begun.
    1.4    Special Conditions:
    A. This project will be awarded as a "design/build" project.
    The Design/Build Contractor entity will bear full
    responsibility for development of the final facility
    architectural/engineering designs and of the construction
    of a complete and usable facility. The Design/Build
    Contractor's architect/engineer will be "the
    Architect/Engineer of Record" and as such, will bear
    full responsibility for the design and construction
    Quality Assurance. Construction may be authorized
    prior to completion of design on project segments
    provided that the Contracting Officer considers that
    design of the segment of construction to be started is
    sufficient to permit the construction start.[ 13] Changes
    during construction due to design changes that were
    not requested by the Government will be the
    responsibility of the Design/Build Contractor, including
    situations where the Contracting Officer permits
    construction of segments prior to the completion of
    design.                         •
    12
    SBN understood that the Final Concept Rooms were to be internal to the lodge it
    was building (app. br. at 147-48).
    13
    We interpret this sentence as permitting the issuance by the CO of Limited Notices
    to Proceed (LNTP) for various portions of the project (see also finding 20).
    9
    C. The Contractor shall engage registered architects and
    professional engineers licensed in the State of Washington
    and LEED certified to design the facilities and oversee the
    design and construction work. See Section H for
    sustainable design evaluation requirements.
    1.5    Construction Scheduling:
    A. Offerors shall submit a Project Schedule as part of their
    response to this Request for Proposal in accordance with
    the requirements of Section L. The schedule shall include
    the anticipated monthly adverse weather days indicated in
    Section H.
    (R4, tab 2 at 867-71) (Emphasis added)
    8. RFP SECTION C-1, GUIDANCE TO CONTRACTORS, GENERAL
    INFORMATION, included the following information pertinent to the matters now
    before us:
    2.2   Definitions: Throughout this [RFP], certain terms,
    abbreviations and acronyms are used. The definitions for
    these items are as follows:
    B. AL: Army Lodging activity
    C. Contracting Officer: A person with the authority to enter
    into, administer, and/or terminate contracts on behalf of
    the Non-Appropriated Fund Instrumentality which is party
    to this contract and make related determinations and
    findings. The term includes certain authorized
    representative[ s] of the Contracting Officer acting within
    the limits of their authority as delegated by the
    Contracting Officer.
    10
    E. COR (Contracting Officer's Representative): The on-site
    representative of the Contracting Officer with authority to
    act for the Contracting Officer in areas specified by letter
    of designation.
    H. DOIM: Directorate of Information Management at Ft.
    Lewis, Washington.
    GP 41 DPW: Directorate of Public Works at Ft. Lewis,
    Washington. [l 5J
    HP 41 FDS: Facility Data Sheet(s).
    I. FF&E: Furnishings, Fixtures and Equipment
    J. The Fund: The Non-Appropriated Fund Instrumentality of
    the U.S. Army, also referred to as NAF or NAFI that is a
    party to this contract.
    K. Government: The term will generally refer to the NAFI or
    Fund. The use of the term "Government" shall not be
    construed to infer that appropriated funds of the United
    States are involved in this project. No appropriated funds
    of the United States shall become due, or be paid, to the
    Contractor by reason of this contract.
    0. Installation: Ft. Lewis, Washington.
    P. NAFI: Same as "The Fund"
    R. Owner: Same as "The Fund".
    S. Post: Ft. Lewis, Washington
    14
    The duplication of the definition references "G" and "H" is in the original document.
    15
    DPW was responsible for the maintenance of the Fort Lewis infrastructure
    (buildings, roads, etc.) and was ''the keeper of the utility maps, the as-built
    records of all the facilities" at Fort Lewis. A division of DPW coordinated the
    locating and marking of existing utilities by base personnel before it issued
    digging permits. (Tr. 9/14-15, 24-25)
    11
    V. User/Using Agency: The AL activity at the installation
    that will be the ultimate user activity when the facility is
    completed· £161
    2.4   Validity of Information Provided:
    A. A topographic drawing of the site showing locatjons of
    various utility lines has been incorporated as an
    attachment to this RFP under Section J. The information
    regarding underground utility lines was obtained from
    DPW. This information is provided for the Contractor's
    convenience. It is not a part of the contract and is not a
    warranty of actual conditions. Basic information maps and
    any other data obtained from DPW or other installation or
    other Government sources are provided for information
    only, and must be verified by site investigation. The
    Government will not be responsible for erroneous data if
    the errors can be reasonably detected through site
    investigation.
    B. While the sizes and materials included on the utility maps
    are generally accurate, the exact location of underground
    systems cannot be guaranteed and must be verified by the
    Offeror through site investigation prior to submitting an
    offer.
    C. No site-specific soil investigation of the site has been
    conducted by the Government. The information included
    in Section J is of a general nature and is included only for
    general guidance. This document is not part of the
    Contract Documents and is not a warranty of subsurface
    conditions. The Government does not assume
    responsibility for subsurface conditions. The selected
    Contractor shall conduct his own soil investigation to
    establish the design criteria for foundations and
    pavements.
    16
    See definition 2.2B quoted just above, where "AL" is Army Lodging, the entity for
    whom the Fort Lewis Lodge was being constructed (R4, tab 2 at 860). The
    Army Lodging Fund was the source of nonappropriated funds used to fund the
    project now at issue. COR Dyer was responsible for managing the Army
    Lodging funds associated with this project (tr. 8/30-31, 52, 9/26-30, 117-18).
    12
    D. The Offeror may at his own expense, provide other
    investigations, surveys, etc. that are necessary to prepare a
    proposal, complete the design, and/or construct the
    project. Any such site investigation activities shall be
    coordinated with appropriate installation personnel. Prior
    to contract award, all inquiries shall be made of the
    Contracting Officer only.
    2.5   Information Verification:
    A. Offerors shall examine the site and determine for
    themselves the existing conditions and general character
    of the site. Claims for additional costs due to conditions
    that could have been verified by site investigation will not
    be permitted.
    B. The Offeror shall be responsible to determine that all of
    the existing service utilities are of sufficient capacity to
    accommodate all of the design loads for this total facility.
    Should the Offeror determine that one or more of the
    existing service utilities are not adequate to accommodate
    the design loads for this total facility, then the Offeror
    shall submit with his initial and any subsequent proposal,
    the requirements, design data and the price for increasing
    the capacity of each existing service utility system or for
    providing a new service utility system. Design loads for
    this facility shall be calculated in accordance with the
    criteria specified in this Request for Proposals with the
    most stringent criteria governing. The Offeror shall be
    responsible for verification and field location of any and
    all information provided in the RFP and on any attached
    or enclosed drawings or other documents. The capacity
    information provided is for reference only.
    C. Independent consultation with the AL and the installation
    concerning the project requirements is prohibited since
    evaluation of proposals will be based on requirements
    stated in the Request for Proposals. Verification of data
    can be obtained by contacting the Contracting Officer.
    D. Questions regarding design, coordination, or interpretation
    of RFP requirements during the proposal phase shall be
    directed to the Contracting Officer.
    E. The Contracting Officer will hold a Pre-Proposal meeting
    and site visit at Fort Lewis (See Section L, Pre-Proposal
    Conference). Any subsequent requests for site visits will
    13
    be directed to and coordinated with the Contracting
    Officer.
    (R4, tab 2 at 871-73; tr. 10/28-33, 157-59)
    9. RFP SECTION C-1, GUIDANCE TO CONTRACTORS, SITE
    INFORMATION, included the following information pertinent to the matters now
    before us:
    3.1    Property:
    A. The project will be located on US Army land, Ft.
    Lewis, Washington.
    B. The existing site was originally developed as an
    area for administrative buildings. These
    buildings and their foundations have been or will
    be demolished by DPW, but the underground
    utilities were not removed. It is believed that all
    former water and sewer lines have been capped
    and abandoned.
    C. Easements have not been recorded for the
    utilities located throughout the site.
    3 .2   Utilities:
    D. Electricity: There is an existing 13.8KV, 3-phase
    primary electrical distribution line on the
    perimeter of this site. Coordinate the services
    drop location with DPW during design and
    construction. An existing underground feeder
    line and pad-mount transformer exists on the site
    and may have to be rerouted/relocated
    depending on the final site plan arrangement.
    E. Telephone: Telephone wiring will be run into
    and through a Communications Manhole
    adjacent to the site. An existing ductbank travels
    west from this manhole to Bldg 2003, DOIM
    main switch building. Coordinate installation of
    new twisted pair bundle in this ductbank back to
    14
    2003. The Contractor will make cross-
    connections at 2003 under DOIM
    supervision/direction. Coordinate all
    requirements with Post DOIM during design and
    construction.
    F. Natural Gas: Natural Gas is available at the site.
    Puget Sound Energy (PSE) owns the lines.
    Coordinate connection points and construction
    requirements with DPW and PSE during design
    and construction.
    (R4, tab 2 at 873-74; tr. 10/33-35)
    10. RFP SECTION C-1, GUIDANCE TO CONTRACTORS, PRODUCTS
    AND SUBSTITUTIONS, included the following information pertinent to the matters
    now before us: '
    A. Products are generally specified by ASTM or
    other referenced standards and/or by
    manufacturer's name, model number, or trade
    name. When specified only by referenced
    standard, the Offeror may submit for approval
    any product meeting this standard by any
    manufacturer.
    B. Products listed by manufacturer's name, model
    number, or trade name generally are for design
    guidance criteria. The Offeror has the option of
    providing the listed product or submitting an
    equal substitute (see 5.2 below) product for
    approval by the Contracting Officer.
    1. If a product is listed with the annotation "no
    substitution", the Government has
    determined that the particular product is the
    only one that will satisfy the project
    requirements, and no substitute product will
    be acceptable.
    5.2    Substitution:
    A. A product proposed as an "equal" shall be such
    that all its salient characteristics conform to
    those of the listed brand name product. These
    salient characteristics may include, but are not
    15
    limited to: design, function, size, quality,
    durability, color, style, texture, and other
    attributes which, given the nature of the project,
    may significantly affect its acceptability as a
    substitute for the listed product. The
    Contracting Officer will make the final
    determination as to whether a proposed
    substitute product is equal and/or acceptable.
    B. Offerors who propose to provide substitute
    products shall submit an itemized list of all
    proposed substitutions with their proposal. This
    list shall include the name of the listed product,
    the name and model of the proposed
    substitution, and the name and address of its
    manufacturer, and the quantity involved. With
    this list, provide the following for each proposed
    substitute item, as applicable:
    1. Catalog cuts completely describing the
    product and its physical characteristics.
    2. Performance and test data and specifications.
    3. Color and/or pattern selections.
    4. Recommended uses.
    5. Installation recommendations.
    6. Maintenance instructions.
    7. Copy of warranty.
    C. If no proposed substitutions are included with
    the proposal the Offeror shall provide the
    products listed in the RFP.
    (R4, tab 2 at 876) (Emphasis added)
    11. RFP SECTION C-1, GUIDANCE TO CONTRACTORS,
    ATTACHMENTS, included the following information pertinent to the matters now
    before us:
    6.1   The following documents are included as
    attachments to this RFP under Section "J" and shall
    be considered a part of the requirements for design
    and construction of the facility:
    J-1    Low Voltage Schematic Drawings
    J-2    Geotechnical Information
    J-3    Installation Design Guide (IDG)
    16
    J-4    Fort Lewis Design StandardsC 171
    J-5    Fort Lewis Guide Specification 01410
    J-6    Galaxy System Equipment
    J-7    UFC-4-010-01 DoD Antiterrorism Standards
    for Buildings
    J-8    UFC 3-600-01 Fire Protection Engineering
    for Facilities
    J-9    Construction Sign Specifications
    J-10   Drawings
    Utilities Plan
    Suggested Site Plan
    Suggested Main Floor Plan
    Suggested Upper Floor Plan
    [Guest Room Layout PlansC 181
    J-11      Breakfast Service Area Requirements
    J-12      Department of Labor Wage Determination
    J-13      Prefabricated Dwyer Kitchen Units
    Guidelines
    J-14      FF and E I Lists and Product Data
    (R4, tab 2 at 876-77)
    12. RFP SECTION C-2, CODES AND STANDARDS, included the following
    information pertinent to the matters now before us:
    1.1    The project shall be designed and constructed in
    accordance with the applicable codes, standards,
    design parameters or regulations noted in this
    section or other sections of the [RFP]. In case of
    conflict between codes, standards, or regulations,
    the Fort Lewis Installation Design Standards shall
    apply.
    17
    The Fort Lewis Design Standards were drafted by ORB's Patterson in 1995-96
    under an IDIQ contract between ORB and DPW (tr. 10/143-46).
    18
    This drawing is listed and included in Section J-10 of the contract but is not included
    in this list in the contract. We presume that its omission here was unintentional
    and is immaterial to the matters before us.
    17
    2. I      General: Design and construction shall be in
    accordance with the most stringent requirements of
    the following codes, standards, and regulations:
    A. Fort Lewis, WA Installation Design Guide
    (IDG)
    B. Fort Lewis, Washington Public Works Design
    Standards
    (R4, tab 2 at 878)
    I3. RFP SECTION C-3, FUNCTIONAL REQUIREMENTS, included the
    following information pertinent to the matters now before us:
    I.I       Scope:
    A. This section includes descriptions of the basic
    functional and operational requirements for the
    Lodging Facility.
    fl. The requirements included herein provide
    general guidance and minimum standards for the
    overall operational features desired by the
    Government. The Offeror should develop a
    design for the new Lodging Facility that meets
    or exceeds these requirements.
    5.        LODGING FACILITY I BUILDING
    5.I       General
    C. The Guest Rooms shall be designed and
    constructed as indicated in RFP documents.
    (R4, tab 2 at 885-89)
    I4. RFP SECTION C-4, DESIGN REQUIREMENTS, included the following
    information pertinent to the matters now before us:
    I8
    1     GENERAL
    1.1   The requirements included in this Section establish
    the basic parameters for design of the various .
    project elements. Additional requirements related to
    construction activities and products are included in
    Sections C-1, C-3 and C-5. Codes and standards are
    referenced in C-2.
    1.2   The Contractor shall design all necessary
    architectural, civil, structural, mechanical, and
    electrical systems in accordance with the
    requirements and parameters established in this
    [RFP].
    1.4    See the Fort Lewis Design Standards in Section J
    for minimum design standards. Where design
    standards specified herein are in conflict with the
    [IDG], the IDG shall apply.
    4.     ARCHITECTURAL DESIGN
    4.1    General:
    A. This Lodging Facility shall be composed of one
    building, designated #2107, only except that the
    Grounds Maintenance Storage Building,
    designated #2108, shall be a separate
    stand-alone building.
    G. The maximum height of the building shall not
    exceed 4 stories or 55 feet.
    8.     HEATING VENTILATION & AIR
    CONDITIONING (HVAC) DESIGN
    19
    8.3    HVAC Systems:
    A. General: The HVAC system shall attain the
    following main objectives: Occupant Comfort;
    Indoor Air Quality; Acceptable Noise Levels;
    Energy Efficiency, Reliable Operation; Ease of
    Maintenance; and Prevention of humidity
    problems within the building envelope. The
    Contractor shall develop a HVAC system from
    the following:
    1. Self contained {PTAC)P 91through the wall
    air to air heat pumps for all guest rooms and
    any public spaces with exterior exposures,
    unless otherwise indicated in FDS: The
    DOIM Comm Room will be conditioned
    using an independent, wall mounted PTAC
    unit with independent controls. Other spaces
    to be air conditioned shall be part of a VA V
    system utilizing constant volume fan
    powered terminal bo·xes, air cooled chiller
    and hot water boiler for primary air
    handler and re-heat at the terminal unit.
    Code-required outside air ventilation and
    make up air shall be provided [to] the
    primary air handling unit using chilled water
    cooling and hot water heating to precondition
    all outside air before delivery through
    ductwork to each space. The outside air
    handling unit shall have the outside air intake
    at least 10 feet above grade. The central
    AHur2o1 shall be provided with minimum
    30% efficiency prefilters followed by 65%
    efficiency filters. PTAC units to be provided
    with throw- away filters.
    19
    A photograph of a PTAC unit (inside wall and outside wall) can be found in the
    record at Ex. A-3 at EK-36.
    20
    Air handling unit (tr. 1/80).
    20
    D. Controls: The HVAC system shall be controlled
    by a DDC system that complies with the Fort
    Lewis Design Standard DDC Design Guide
    Specification (See Section J). Each AHU and
    terminal unit shall have a Lon WORKS or
    BACnet DDC controller connected to a Tridium
    JACE[21 1 controller. The JACE controller shall
    be connected to the building LAN (Ethernet
    Cat 5) and routed to a desk-top computer, with
    Tridium Niagra Web Supervisor and Workplace
    Pro, installed in the mechanical room. The
    maintenance staff shall have access to the
    system through any computer connected to the
    Network via use of a web browser that is
    password protected.
    E. . .. An existing ONITY "Senercomm" InnPulse
    On-line system will be relocated from the
    Check-in point in existing Building 2111 to the
    new facility. Senercomm "SensorstatDDC"[221
    programmable digital thermostats or equal will
    be provided in new guest rooms. Connect all
    new room thermostats and Bldg 2111 thermostat
    system to the relocated InnPulse Server, update
    software/system as required .... Coordinate with
    comm./data requirements and electrical
    capacities.
    (R4, tab 2 at 890-902; tr. 11126-28, 4/8, 29-30, 30-32, 8/36-37, 12/67-74) ORB's
    Patterson, who drafted this section of the RFP, testified that:
    The majority of the lodge is made up of individual guest
    rooms served by individual terminal units, or AC units.
    The intent of [8 .3 .A. I] was to heat and cool the remaining
    back [of] house and front of house spaces such as the front
    lobby, desk, back of house areas, breakfast bar, etcetera,
    etcetera, etcetera, with a single system with a central boiler
    21
    A photograph of the JACE controller and the ONITY room-control system is in the
    record at Ex. A-3 at EK-41 (top).
    22
    A photograph of such a thermostat with an occupancy sensor is in the record at
    Ex. A-3 at EK-37 (top).
    21
    and chiller fed by I an[] air handler I suppose, and fed by
    terminal boxes within each space .... A VA V system.
    Fort Lewis specifically, and other military installations in
    general, have limited staffs when it comes to maintenance.
    The Fort Lewis HVAC shop currently only has about three
    or four people. At that time, there were maybe 10 or 12.
    They demand, if you will, they require a single central
    maintainable boiler and chiller ....
    So, the basic intent of those sentences was to provide a
    mechanical room with a boiler chiller that could be easily
    visited by DPW maintenance personnel for filter changes,
    strainer cleaning, etcetera, etcetera, in one location. And
    then, the remainder of the system would be a variable air
    volume, VAV, unit type system, that would feed
    conditioned air to the remaining public spaces.
    Fort Lewis was built and rebuilt starting in 191 7 to present
    day. If you look at the older systems on Fort Lewis, they
    are oil fired furnaces with perimeter heat. There are HVAC
    systems. The one common thread, with the exception of
    some Army Air Force exchange facilities that operate
    under different rules and do their own maintenance, the
    one common thread is that all of these facilities have a
    central furnace or heating source with either a hydronic
    loop or a VAV system or whatever.
    There are several quasi-commercial facilities on
    Fort Lewis that are operated by the Army Air Force
    exchange service, the commissary services, etcetera, and
    they do have some package units, storefront type rooftop
    units on them. But, the overall norm is the central boiler
    chiller system.
    (Tr. 10/35-39) With respect to ,-r,-r 8.3.D-E, ORB's Patterson testified that:
    22
    I incorporated that language. Paragraph D, the basic
    description of the required DDC system, was essentially
    dictated or written by the Fort Lewis public works controls
    shop, so that the system would be compatible with the Fort
    Lewis net for design or for digital systems. The Paragraph
    E, guest room thermostats, is a unique paragraph to
    lodging facilities, in that Army lodging uses an ONITY
    [S]ensorStat, what they call an [I]nnPULSE[] system, to
    further control guest room heating and cooling.
    That was essentially provided by Army lodging, and
    tweaked a little bit, if you'll note the last sentence,
    "Connect new room thermostats and Building 2111." It is
    site specific in that respect, but it is more or less a standard
    paragraph for lodging facilities.
    So, depending on the definition of draft, I did not
    draft those two paragraphs, I incorporated them. But, I
    modified them to show the Fort Lewis condition on the
    existing head end equipment.
    The intent at the time that this document was
    generated, was that the I Building 2111 was where the
    existing lodge check-in desk was located and etcetera, and
    it was where the Onity head end equipment was located.
    So, the intent of this was that when the new lodge was
    built, the check-in desk and the associated equipment
    would be moved into the new facility, but the head end
    equipment that had been relocated was still required to talk
    to the thermostats in Building 2111. The intent was that
    2111 would continue to operate next to the new lodge.
    [Paragraph D] was included at the request of the Fort
    Lewis DDC shop, John Timmers and Dale Brigham, as
    being a requirement to ensure that the new lodge would
    talk to their base DDC system.
    23
    [The Fort Lewis DDC system] is a [Tridium]-based digital
    control system that allows John Timmers and/or his people
    to be able to nionitor what's going on from a remote
    location, a laptop, with various aspects of the installed
    system in any building. Ideally they would be also able to
    control from a remote location. I'm not sure how well that
    worked out, or is working out ....
    (Tr. 10/39-41; see also tr. 12/61-62) BCE's Heiberg testified:
    [T]he common areas and the central mechanical systems
    are turned over to Public Works for ongoing maintenance,
    and as a result, they need to see what's happening with
    them so that integration is real important. It's like the
    building has two different control systems; this one goes to
    Public Works, they take care of it; the other Onity control
    units, the PTACs, that's something that MWR or MCOM
    takes care of. So that's where that whole standard
    reference document of what the Tridium is and how it
    needs to work and what the requirements are and that was
    our main concern about that, and there was some concerns
    on the Onity side, but that was-this is the one that many
    contractors, very large contractors have failed to do out at
    Fort Lewis, so there's a-it's a difficult process, and we
    wanted to make sure that this one would have a reasonable
    chance of success.
    (Tr. 111140-41) With respect to the basewide system at Fort Lewis, Heiberg testified:
    It is a large network that is controlled primarily out of
    Building 2012, with a series of PCs that are managed by
    the Public Works that communicate with the various
    buildings. Some they don't communicate at all with, all the
    newer ones do. It's a base standard in progress, if you will.
    They've been building on it for 10 or 15 years, and
    probably prior to this project, it was probably less than 10
    years old at the time of this project. Tridium using an open
    protocol network for controllers, they would accept
    BACnet or Lonworks based controllers; that was the thing
    back then. BACnet wasn't developed as much as Lon was,
    so that there's a lot more buildings using Lonworks out on
    24
    the base. It's just a way to integrate it in, and then Tridium
    and JACE was a very flexible graphics program that
    brought this information in to PCs and allowed them to
    customize access into each building with floor plans and
    graphics and so forth. And each time a building was being
    planned out at Fort Lewis, it would be, the controls
    companies would be referred to a standard by which to
    bring this new building into the base standard.
    They were very particular about a R2 version of software
    that they were running at the time. Tridium R2, very large
    program from a software standpoint, not super expensive,
    but nevertheless anybody doing work out there would need
    to buy a software package to license that site and bring it
    into the network. R2 was a version; they subsequently
    came out with an AX, which is more of a fragmented
    version. I don't get into a lot of details of the capabilities
    and differences between the software, but the R2 was more
    of a legacy type of control system. By that, kind of the big
    offering from the Tridium people. If you had R2, you
    could be at Building 2012 and look at a building XYZ on
    base, and download software all the way down to an
    individual room's heat pump. So you had from the top
    down, you had full capability of programming down to the
    last device.
    The AX system broke that apart and said okay,
    you'll need another little controller or software version to
    write to the little heat pump or an intermediate global
    controller. It wasn't logging on from the top and going all
    the way down; you had to get a laptop out and fire up other
    software to do local programming.
    (Tr. 111141-43)
    17. RFP SECTION C-5, OUTLINE SPECIFICATIONS, included the
    following information pertinent to the matters now before us:
    1      GENERAL
    I. I   Purpose:
    25
    A. Unless otherwise indicated, the
    Offeror/Contractor has the option of selecting all
    materials, systems, and equipment for use in the
    project. The technical requirements included in
    these Outline Specifications establish the
    minimum acceptable standards for the various
    products that may be used in the project. The
    Fort Lewis Public Works Design Standards (See
    Section J) also specify minimum acceptable
    standards and criteria for certain materials and
    systems for use on Fort Lewis. In the event of a
    conflict between these outline specifications and
    the Fort Lewis Design Standards the most
    stringent interpretation will apply.
    B. Unless otherwise indicated, the inclusion of an
    item in these specifications does not require that
    the item be included in the project. In similar
    fashion, the omission of an item from these
    standards does not indicate that the item cannot
    or should not be included in the project.
    C. See Section C-1, paragraph 5, "PRODUCTS
    AND SUBSTITUTIONS" for guidance
    regarding substitutions.
    1.2   Work Included in This Contract:
    A. The work includes design and construction of all
    architectural, civil, structural, mechanical,
    electrical, plumbing and fire protection items
    required to provide a complete facility that can
    be used satisfactorily for its intended purpose
    without excessive maintenance or operational
    costs.
    2.    SITE WORK
    2.1   Selective Demolition:
    26
    C. Utilities: Maintain existing utilities that are to
    remain in service and protect them against
    damage during demolition operations ....
    Utilities that are not in service and are not in
    conflict with new construction may be left in
    place. Contractor shall be responsible for
    removing capped utilities that are in conflict.
    2.4     Site Development:
    A. Surveys and Layout of Work
    3. The Contractor shall coordinate with DPW to
    locate and mark underground utilities.
    15.     MECHANICAL
    15.1    General:
    G. The contractor shall have the responsibility to coordinate
    Mechanical equipment as it interfaces internally with
    DDC controls and externally with Division 16[231.
    15 .4   HVAC Equipment
    A. General: All HVAC equipment and systems shall be of
    good quality, easy to maintain and conform to the
    standards listed below where applicable. HVAC
    equipment shall be controlled and monitored by the DDC
    system as referenced herein. Where possible provide
    23
    We understand "Division 16" to be commonly used prior to 2004 in the construction
    industry to refer to "Electrical" work.
    27
    HVAC equipment that has a direct interface with the
    existing Post system. If equipment is provid.ed that
    does not have a direct interface then the contractor is
    required to provide the equipment for interface to
    perform the necessary control functions as called out
    in paragraph on Automatic Temperature Controls.
    B. Chiller: Air-cooled heat rejection for equipment shall be
    Trane, McQuay, or Carrier.
    C. Air-Handling Units: Horizontal.. ..
    D. PTAC Heat pumps: Air-cooled. Through the wall at Guest
    Rooms, wall-mount at Comm. Room. Complete with
    compressor, fan, coils, and controls to make a compiete
    and operable system. Outside air intakes shall not be
    provided at individual PTACS. Contractor shall select
    PTAC heat pumps based on quality and maintainability.
    Acceptable products include GE I Zoneline and McQuay I
    ComfortPac.
    E. Unitary Heating Equipment: Individual heaters for
    ancillary areas shall be hot water.
    15.6   Automatic Temperature Controls: Controls shall be stand-
    alone DDC and compatible with the Fort Lewis EMS
    "Tridium" system. The system will be connected to the
    Post-wide EMS system at a later date. The DDC system
    shall monitor HVAC equipment as defined in the
    paragraph herein. See Design Requirements in Section C3
    & C4 for additional information regarding the control
    system. The DDC control system shall monitor, report
    and/or alarm the following HVAC functions and any
    other points required to control, operate and maintain the
    critical areas of the facility.
    28
    F. Direct Digital Control (DDC) Points List: The following
    is a list of the minimum required DDC points:
    1. Air Handling Units (AHU)
    4. PTAC Heat Pump Units
    5. Fans (other than AHU system fans)
    6. Terminal Units
    7. Boiler System
    8. Chiller System
    G. The DDC system shall provide automatic control of the
    common area HVAC system. This includes the AHU's
    their zone terminal units and associated exhaust fans
    and heating/cooling equipment.
    1. In addition, provide for DDC control of individual
    PTAC heat pump units. This shall be a sub-DDC
    system designed specifically for the hospitality
    industry (ONITY "SenerComm" SensorstatDDC or
    equal), yet compatible with Tritium EMS for future
    connection to the Post system. Contractor shall be
    required to provide information about the DDC
    system submitted including: history, capabilities,
    compatibilities, useful life, maintenance costs,
    experience and reliability for use in this PT AC I
    heat pump application. The intent is to
    29
    control/adjust each guest PTAC from a central
    control point using the ONITY "lnnPulse" on-line
    monitoring/reporting system at the front desk, in
    addition to providing occupied/unoccupied sensing
    and setbacks and allowing the individual guest to
    control/adjust at the guest room.
    (R4, tab 2 at 908-09, 932, 934-41) (Emphasis added)
    18. RFP SECTION H-3, CONTRACT QUALITY CONTROL/QUALITY
    ASSURANCE, included the following information pertinent to the matters now
    before us:
    3. I   Definitions:
    A. Contractor Quality Management System
    (CQMS): The means by which the contractor
    assures himself that his design and construction
    comply with the requirements of the contract.
    B. Contractor Quality Control (QC): The
    Contractor's inspection, examination and control
    of his own, his suppliers', and his
    subcontractors' work and activities to ensure
    compliance with contract requirements.
    C. Contractor Quality Assurance (QA): The means
    by which the Contractor fulfills his
    responsibility for assuring that the QC system is
    functioning effectively.
    3.2     General: The Contractor shall establish and
    maintain an effective [CQMS] in compliance with
    contract clauses, professionally accepted design and
    professionally accepted inspection of construction
    practices and as herein provided. The CQMS
    consists of plans, procedures, and organization
    necessary to provide a design and materials,
    equipment, workmanship, fabrication, construction
    and operations which comply with contract intent
    and specific requirements. The system shall cover
    both design services and construction operations,
    both on site and off site, and shall be keyed to the
    30
    proposed design and construction sequence. The
    Contractor will designate a Professional Architect
    or Engineer (AIE), registered in the State where
    the work is being performed, as the responsible
    CQMS authority. Different professionals may be
    appointed for the separate design and construction
    phases ....
    3.7    Quality Control Organization:
    A. Design: Design quality control shall be the
    responsibility of the Architect/Engineer who will
    seal all drawings and specifications as the
    "Architect/Engineer of Record." The Design
    Professional (Architect/Engineer of Record)
    responsible for the design of any project element
    shall also be the final approval authority for
    shop drawings and any other tests and submittals
    effecting [sic] the final design of that element. ...
    The Architect/Engineer of Record shall certify in
    writing to the Contracting Officer that the
    required design quality reviews have been
    completed and that to the best of his knowledge
    and belief the design meets the requirements of
    the RFP. The Architect/Engineer of Record shall
    review and approve (seal) all engineering
    calculations and designs unless otherwise
    approved by the Contracting Officer.
    3.14   Government Quality Assurance: The Government's
    quality assurance activities will consist of
    construction project observation, review of CQC
    activities and records, and discussions of area where
    contract deviations appear evident.
    3-14.1 Request for deviations shall be presented in a RFI
    format to the Architect of Record for approval.
    Subsequent to approval by the Architect of Record a
    31
    copy of the request for deviation shall be submitted
    to the contracting officer for review and acceptance.
    (R4, tab 2 at 955-56, 960) (Emphasis added)
    19. RFP SECTION H-10, RESPONSIBILITIES OF THE CONTRACTOR,
    included the following information pertinent to the matters now before us:
    I 0-1   This project will be awarded as a "design/build"
    project. The design/build Contractor entity shall
    bear full responsibility for development of the final
    designs and construction of a complete and usable
    facility. The design/build Contractor's architect (or
    engineer) shall be the "Architect (or Engineer) of
    Record" and as such, shall bear full responsibility
    for the design.
    10-2 The successful Offeror shall proceed to finalize the
    proposed design upon issuance of the Notice to
    Proceed for Design by the Contracting Officer, after
    Award of the contract.
    I 0-3   Unless otherwise permitted by the Contracting
    Officer in writing, the Contractor shall engage
    professional architects and engineers registered in
    the state the work is being performed (for each
    discipline) to oversee all aspects of the design and
    construction work as set forth herein. The proposal
    submittal materials shall indicate the proposed
    designer's qualifications and design competence
    relative to the project. At final submission,
    construction drawings shall be signed and bear the
    designer's professional seal.
    10-4 The Architect (or Engineer) of Record is required to
    become thoroughly familiar with the site through
    site visits ....
    10-5 Neither the NAFI's review, approval or acceptance
    of, nor payment for, any of the services required
    under this contract shall be construed to operate as a
    waiver of any rights under this contract, and the
    Contractor shall be and remain liable to the NAFI in
    32
    accordance with applicable law for all damages to
    the NAFI caused by the Contractor's negligent acts
    or omissions in connection with designs, drawings
    and specifications furnished under this contract.
    (R4, tab 2 at 965)
    20. RFP SECTION H-15, CONTRACTOR DESIGN SUBMITTAL AND
    DESIGN MEETING REQUIREMENTS AFTER AWARD, included the following
    information pertinent to the matters now before us:
    A. Pre-Design Conference: Within 14 calendar days
    after Design NTP, prior to commencing work,
    the Contractor shall meet with Government
    representatives at Ft. Lewis for a two-day
    predesign conference.
    The Contracting Officer will review
    administrative and technical requirements for the
    contract during the pre-design conference ....
    The Contractor shall keep and distribute
    conference meeting minutes to attendees.
    B. Design Submittals:
    The Contractor shall make four design
    submittals for this project in addition to any
    required by the Contracting Officer for fast track
    approval. The first submittal will be at the 35%
    design stage, the second at the 65% stage, the
    third at the 95% stage, and the fourth at the
    100% stage. Each submittal will incorporate all
    comments made regarding the previous
    submittal. The Contracting Officer will review
    designs for compliance with contract
    requirements but not for design validity. The
    Contractor remains fully responsible for the
    design. Any portions of the overall design
    submitted must be sufficient in detail to permit
    professional evaluation as to the extent that the
    elements to be constructed meet contract
    requirements. Design submittals will include, at
    33
    the appropriate level (35%, 65%, 95%, or 100%
    design submittals), the items noted herein.
    C. Review Meetings:
    After Government review of each design
    submittal has been completed, meet with the
    Contracting Officer at Ft. Lewis, Washington for
    a I /day conference to discuss review comments
    and the Design/Build Team's responses for the
    specific design submittal. The responses to
    review comments shall be submitted to the
    Government in writing one week after receipt by
    Contractor.
    D. General Design Data:
    I. Design analysis and calculations. (The Fund
    will review the design analysis or
    calculations to assure they have been
    accomplished). The Design Analysis shall
    include as minimum:
    2. A description of the general parameters,
    functional and technical requirements, and
    objectives and provisions of the design shall
    be described. A summary of economic
    factors influencing the design choice of
    systems used in the project will be provided
    along with an indication of how initial and
    life cycle costs were considered.
    3. Design calculations and supporting
    documentation shall be done to support
    design considerations .... Calculations and
    data for the following shall be included in the
    analysis:
    a. Civil Site Design/Site Utility Design
    b. Structural Design/Foundation Design
    c. Building Code/Life Safety Analysis
    d. Mechanical Systems Design
    [e.] Electrical Systems Design
    4. Design drawings showing the name of the
    Contractor's Architect/Engineer of Record.
    Drawings shall be prepared on acceptable
    34
    Mylar drafting material and shall include a
    minimum:
    a. Drawing scales: ... .
    b. Utility Drawings ... .
    c. Site Landscaping plans ....
    d. Building plans: Floor plans for the
    Lodging Facility building(s) showing
    overall dimensions, room dimensions,
    typical layouts, plumbing fixtures, door
    swings, location of electrical lights,
    switches, outlets, fans, etc., heating and
    air conditioning diagrammatic layout,
    building and food service equipment, and
    the calculated gross and net floor area ....
    e. Structural drawings ....
    f. Mechanical drawings shall include, in
    addition to layout drawings for all
    systems, single line diagrams of each type
    of piping and duct system. Type and
    capacity of all mechanical equipment
    shall be clearly indicated including
    necessary schedules listing operating
    data.
    g. Electrical Drawings and Criteria: ....
    5. Specifications: The technical provisions
    shall be in sufficient detail so that, when used
    with the applicable construction drawings,
    construction can be completed without
    additional specifications except as necessary
    to deal with unforeseen conditions or to
    accomplish changes made during
    construction. The specifications may require
    furnishing additional information such as
    shop drawings, manufacturers' literature,
    certificates of compliance, material samples,
    and guarantees to assure that the work can be
    completed and conforms with the contract
    requirements and that supervision of the
    project can be maintained.
    35
    F. If the Contractor elects to obtain additional
    topographic surveys or soil investigations
    beyond those furnished with the RFP, this data
    shall be submitted for review with the other
    design data.
    1. Topographic survey shall include contour
    lines of sufficient frequency for development
    of construction plans. Horizontal and vertical
    control shall be shown.
    2. Soil investigations shall include any boring
    logs, testing results, or design analyses
    performed by the Contractor.
    H. Design reviews will be held at Ft. Lewis,
    Washington. The [CO] will review the
    Contractor's submittal for compliance with the
    contract requirements and the proposal on which
    the award was based. If the submittal is not
    approved, the Contractor shall make the
    necessary corrections or revisions and submit a
    completed corrected design not later than
    fourteen ( 14) calendar days after being returned
    by the [CO]. No additional time extensions will
    be granted for the processing of re-submittals.
    The Contractor shall make a minimum of four
    (4) design submittals in addition to any others
    required for fast track approval (i.e. limited
    Notice to Proceed) or for correction,
    clarification, etc. The first scheduled submittal
    shall be at 35 percent design completion and the
    second scheduled submittal shall be at 65
    percent completion.
    1. Minimum requirements for 35% design
    submittal:
    a. All drawings and items required by
    paragraph H-15 [D.] (General Design
    Data) developed to approximately 35
    percent completion.
    b. Specifications: table of contents and draft
    outline specifications.
    36
    c. List of all requested substitutions for
    review and approval.
    d. Design analysis developed to the extent
    required to support the design or that
    portion of architectural, civil, utility
    distribution, structural, electrical, and
    mechanical systems included in this
    submittal.
    e. Additional soils report and topographic
    survey if completed or required.
    2. Minimum Requirements for 65% design
    submittal:
    a. All drawings and items required by
    paragraph H-15 [D.] (General Design
    Data) developed to approximately 65
    percent completion, except that all Civil
    and Structural foundation drawings shall
    be developed to approximately 100
    percent completion. Fully developed
    civil/site plans including required SWPPP
    and storm water management plans will
    be required before consideration of
    advanced (or limited) Notice to Proceed
    (LNTP).
    b. Completed specifications for site work,
    site utilities, and a draft of the
    specifications for the remaining work,
    including index, general conditions, and
    technical sections.
    c. Design analysis developed to the extent
    required to support the design or that
    portion of architectural, civil, utility
    distribution, structural, electrical, and
    mechanical systems inc1uded in this
    submittal.
    3. Minimum Requirements for 95% design
    submittal:
    a. All drawings and items required above
    completely developed.
    b. Completed specifications. Interior signage
    specification shall include a professional
    ''wayfinding" plan for approval.
    c. Completed designs analysis.
    37
    d. Equipment Schedules: Based on the
    results of calculations, provide a complete
    list of the material and equipment
    proposed for the building including
    heating, plumbing and cooling with the
    manufacturers published cataloged
    product installation specifications and
    roughing-in data.
    e. Shop drawing submittal register.
    4. Minimum Requirements for 100% submittal:
    a. All drawings and items required above,
    completely developed and incorporating
    all comments and revisions from the 95%
    review.
    (R4, tab 2 at 966-70)
    21. RFP SECTION H-21, CONTRACTOR-PREPARED PROGRESS
    SCHEDULE, included the following information pertinent to the matters now before us:
    In accordance with the Contract Clause I-48,
    "Schedules for Construction Contracts," the
    Contractor shall submit as part of the initial design
    submittal, a critical path progress schedule showing
    the manner in which he intends to prosecute the
    work. Preparation and updating of the schedule
    shall be as follow[s]:
    21-1   The progress schedule shall be prepared in the form
    of time-scaled (Gannt Chart) summary network
    diagram graphically indicating the sequence
    proposed to accomplish each work operation and
    appropriate inter-dependencies between the various
    activities. The chart shall show the starting and
    completion dates of all activities on a linear
    horizontal time scale beginning with the dates of
    Notice to Proceed for Design and indicating
    calendar days to completion. Each significant
    activity in both design and construction phases of
    the project shall be represented and a cost for the
    activity indicated. The sum of the activity costs
    shall total to the contract amount for the project.
    The Contractor shall indicate on the chart the
    38
    important work activities that are critical to the
    timely overall completion of the project. Key dates
    for important features or portions of work features
    are milestone dates and shall be indicated on the
    chart. Based on this chart, the Contractor shall
    prepare an earnings-time curve (''S" curve) showing
    the rate of progress in terms of money and percent
    completion. Schedule progress may not include the
    value of materials or equipment delivered to the job
    site but not yet incorporated into the work. This
    schedule shall be the medium through which the
    timelessness [sic] of the Contractor's construction
    effort is appraised, and periodic payment estimates
    are processed pursuant to the Contract Clauses.
    21-4 .1 Failure by the Contractor to maintain adequate
    progress in accordance with the progress schedule
    may result in withholding of progress payments, as
    determined by the Contracting Officer.
    (R4, tab 2 at 972-73)
    22. Section I of the RFP included contract clauses specific to Nonappropriated
    Fund (NAF) construction. Section 1-2, NONAPPROPRIATED FUND
    INSTRUMENTALITY (FEB 1997), included the following information pertinent to
    the matters now before us:
    The Nonappropriated Fund Instrumentality (NAFI) which
    is party to this contract is a nonappropriated fund
    instrumentality of the Department of the Army. NO
    APPROPRIATED FUNDS OF THE UNITED STATES
    SHALL BECOME DUE OR BE PAID THR
    CONTRACTOR BY REASON OF THIS CONTRACT.
    This contract is NOT subject to The Contract Disputes Act
    of 1978.
    (R4, tab 2 at 975) In addition, Army Regulation (AR) 215-1, Military Morale,
    Welfare, and Recreation Programs and Nonappropriated Fund Instrumentalities,§ II,
    Terms, defines a nonappropriated fund instrumentality (NAFI) as:
    39
    A U.S. Government organization and fiscal entity that
    performs essential Government functions. It is not a
    Federal Agency. It acts in its own name to provide, or
    assist other DOD organizations in providing MWR and
    other programs for military personnel, their Families, and
    authorized civilians. It is established and maintained
    individually or jointly by two or more DOD components.
    As a fiscal entity, it maintains custody of and control over
    its NAFs, equipment, facilities, land, and other assets. It is
    responsible for the prudent administration, safeguarding,
    preservation, and maintenance of those APF resources
    made available to carry out its function. With its NAFs, it
    contributes to the MWR programs of other authorized
    organizational entities, when so authorized. It is not
    incorporated under the laws of any State or the District of
    Columbia, but has the legal status of an instrumentality of
    the United States. NAFis are not "persons" subject to
    federal trade and antitrust laws, and they are not subject to
    State regulation or control in the absence of specific
    authorization in a Federal statute.
    AR 215-1 defines nonappropriated funds (NAFs) as:
    Cash and other assets derived from sources other than
    Congressional appropriations, primarily the sale of goods
    and services to DOD personnel and the Family members
    are used by the NAFI to support or provide authorized
    programs. NAFs are Government funds used for the
    collective benefit of those who generate them. These funds
    are separate and apart from funds that are recorded in the
    books of the Treasurer of the United States.
    "There are no tax dollars involved in this project. All the funding comes from
    Soldier's dollars generated from other Lodging stays." (R4, tab 127 at 2872;
    tr. 12/148-50)
    23. The RFP included Section I-4, CHANGES-CONSTRUCTION (FEB
    1997) (R4, tab 2 at 975-76); RFP Section I-21, PROMPT PAYMENT FOR
    CONSTRUCTION CONTRACTS (FEB 1997) (id. at 987-95).
    24. RFP Section I-20, PAYMENTS UNDER FIXED-PRICE
    CONSTRUCTION CONTRACTS (FEB 1997), included the following information
    pertinent to the matters now before us:
    40
    (c) If the Contracting Officer finds that satisfactory
    progress was achieved during any period for which a
    progress payment is to be made, the Contracting Officer
    shall authorize payment to be made in full. However, if
    satisfactory progress has not been made, the Contracting
    Officer may retain a maximum of 10 percent of the amount
    of the payment until satisfactory progress is achieved.
    When the work is substantially complete the Contracting
    Officer may retain from previously withheld funds and
    future progress payments that amount the Contracting
    Officer considers adequate for protection of the NAFI and
    shall release to the Contractor all the remaining withheld
    funds. Also, on completion and acceptance of each
    separate building, public work or other division of the
    contract, for which the price is stated separately in the
    contract, payment shall be made for the completed work
    without retention of a percentage.
    (R4, tab 2 at 986-87)
    25. RFP Section I-25, DISPUTES (FEB 1997), stated:
    (a) This contract is subject to the rules and
    regulations promulgated by the Secretary of Defense and
    Secretary of the Army for NAF contracting.
    (b) The contract is not subject to the Contract
    Disputes Act of 1978 (41 U.S.C. 601-613).
    (c) All disputes arising under or relating to this
    contract shall be resolved under this clause.
    (d) "Claims," as used in this clause, means a
    written demand or written assertion by one of the
    contracting parties seeking, as a matter of right, the
    payment of money in a sum certain, the adjustment or
    interpretation of contract forms, or other relief arising
    under or relating to this contract. A claim arising under a
    contract, unlike a claim relating to that contract, is a claim
    that can be resolved under a contract clause that provides
    for the relief sought by the claimant. A voucher, invoice, or
    other routine request for payment that is not in dispute
    41
    when submitted is not a claim under this clause. The
    submission may be converted to a claim under this clause,
    by complying with the submission requirements of this
    clause if it is disputed either as to liability or amount or is
    not acted upon in a reasonable time.
    (e) ( 1) A claim by the Contractor shall be made in
    writing and submitted to the Contracting Officer for a
    written decision. A claim by the NAFI against the
    Contractor shall be subject to a written decision by the
    Contracting Officer.
    (2) For Contractor claims exceeding $50,000,
    the Contractor shall submit with the claim a
    certification that-
    (i) The claim is made in good faith;
    (ii) Supporting data are accurate and
    complete to the best of the Contractor's
    knowledge and belief; and
    (iii) The amount requested accurately .
    reflects the contract adjustment for
    which the contractor believes the NAFI
    is liable.
    (f) ... For Contractor-certified claims over $50,000,
    the Contracting Officer must, within 60 days, decide the
    claim or notify the Contractor of the date by which the
    decision will be made.
    (g) The Contracting Officer's decision shall be
    final unless the contractor appeals as provided in paragraph
    (h) of this clause.
    (h) The Contract[ing] Officer's final decision may
    be appealed by submitting a written appeal to the Armed
    Services Board of Contract Appeals within 90 days of
    receipt of the Contracting Officer's final decision.
    Decisions of the Armed Services Board of Contract
    Appeals are final and are not subject to further appeal.
    42
    (i) The Contractor shall proceed diligently with
    performance of this contract, pending final resolution of
    any request for relief, claim, appeal, or action arising under
    the contract, and comply with any decision of the
    Contracting Officer.
    (R4, tab 2 at 996-97)
    26. RFP Section I-35, REMOVAL OF CONTRACTOR'S EMPLOYEES
    (FEB 1997), provided:
    The Contractor agrees to utilize only experienced,
    responsive and capable people in the performance of the
    work. The Contracting Officer may require that the
    Contractor remove employees who endanger persons or
    property, or whose continued employment under this
    contract is inconsistent with the interest of military security.
    (R4, tab 2 at 1001)
    27. RFP Section I-40, DIFFERING SITE CONDITIONS (FEB 1997), included
    the following information pertinent to the matters now before us:
    (a) The contractor shall promptly, and before the
    conditions are disturbed, give a written notice to the
    Contracting Officer of ( 1) subsurface or latent physical
    conditions at the site which differ materially from those
    indicated in this contract, or (2) unknown physical
    conditions at the site of an unusual nature, which differ
    materially from those ordinarily encountered and generally
    recognized as inhering in work of the character provided
    for in this contract.
    (b) The Contracting Officer shall investigate the site
    conditions, promptly after receiving the notice. If the
    conditions do materially so differ and cause an increase or
    decrease in the Contractor's cost of, or the time required for,
    performance of any part of the work under this contract,
    whether or not changed as a result of the conditions, an
    equitable adjustment shall be made under this clause and the
    contract modified in writing accordingly.
    (R4, tab 2 at 1002-03)
    43
    28. RFP Section 1-41, SITE INVESTIGATION AND CONDITIONS
    AFFECTING THE WORK (FEB 1997), included the following:
    (a) The contractor acknowledges that it has taken
    steps reasonably necessary to ascertain the nature and
    location of work, and that it has investigated and satisfied
    itself as to the general and local conditions which can
    affect the work, or its cost, including but not limited to ( 1)
    conditions bearing upon transportation, disposal, handling,
    and storage of materials; (2) the availability of labor,
    water, electric power, and roads; (3) uncertainties of
    weather, river stages, tides or similar physical conditions at
    the site; (4) the conformation and conditions of the ground;
    and (5) the character of equipment and facilities needed
    preliminary to and during work performance. The
    Contractor also acknowledges that it has satisfied itself as
    to the character, quality and quantity of surface and
    subsurface materials or obstacles to be encountered insofar
    as this information is reasonably ascertainable from an
    inspection of the site, including all exploratory work done
    by the NAFI, as well as from drawings and specifications
    made a part of this contract. Any failure of the Contractor
    to take the actions described and acknowledged in this
    paragraph will not relieve the Contractor from
    responsibility for estimating properly the difficulty and
    cost of successfully performing the work, or for proceeding
    to successfully perform the work without additional
    expense to the NAFI.
    (R4, tab 2 at 1003)
    29. RFP Section 1-44, SUSPENSION OF WORK (FEB 1997), included the
    following information pertinent to the matters now before us:
    (a) The Contracting Officer may order the
    Contractor in writing to suspend, delay, or interrupt all or
    any part of the work of this contract for the period of time
    that the Contracting Officer determines appropriate for the
    convenience of the NAFI.
    (b) If the performance of all or any part of the work
    is, for an unreasonable period of time, suspended, delayed,
    44
    or interrupted ( 1) by an act of the Contracting Officer in
    the administration of this contract, or (2) by the
    Contracting Officer's failure to act within the time
    specified in this contract (or within a reasonable time if not
    specified) an adjustment shall be made for any increase in
    the cost of performance of this contract (excluding profit)
    necessarily caused by such unreasonable suspension,
    delay, or interruption and the contract modified in writing
    accordingly. However, no adjustment shall be made under
    this clause for any suspension, delay, or interruption to the
    extent that performance would have been so suspended,
    delayed or interrupted by any other cause, including the
    fault or negligence of the Contractor, or for which an
    equitable adjustment is provided for or excluded under any
    other term or condition of this contract.
    (c) A claim under this clause shall not be allowed
    ( 1) for any costs incurred more than 20 days before the
    Contractor shall have notified the Contracting Officer in
    writing of the act or failure to act involved (but this
    requirement shall not apply as to a claim resulting from a
    suspension order), and (2) unless the claim, in an amount
    stated, is asserted in writing as soon as practicable after the
    termination of the suspension, delay, or interruption, but
    not later than the date [of] the final payment under the
    contract.
    (R4, tab 2 at 1004)
    30. RFP Section I-51, LIQUIDATED DAMAGES I CONSTRUCTION (FEB
    1997), provided that:
    (a) If the Contractor fails to complete the work
    within the time specified in the contract, or any extension,
    the Contractor shall pay to the NAFI as liquidated
    damages, the sum of $1,500.00 for each day of delay.
    (R4, tab 2 at 1006) We have found no evidence that the government assessed any
    liquidated damages under this contract.
    31. RFP Section I-56, SUPERINTENDENCE BY CONTRACTOR(FEB
    1997), included the following information pertinent to the matters now before us:
    45
    At all times during the performance of this contract and
    until the work is completed and accepted, the Contractor
    shall directly superintend the work or assign and have on
    the work [site] a competent superintendent who is
    satisfactory to the Contracting Officer and has authority to
    act for the Contractor.
    (R4, tab 2 at 1012)
    32. RFP Section L set forth the requirements for the initial design proposals.
    In particular, Section L-20-1 required:
    A.       The following technical data shall be submitted as
    part of the technical proposal. Appropriate parts of
    the accepted proposal will be incorporated into the
    contract. Offerors are advised that the required data
    listed below will be utilized for technical review and
    evaluation. Requirements, codes, standards and
    any other information contained or specified in
    SECTION C and elsewhere in this RFP will be
    assumed to be included and to be a part of the
    Offeror[']s proposal. It need not be repeated
    therein. All alternates shall be specifically addressed
    and expanded upon in the proposal. The criteria
    specified in this RFP are binding contract criteria and
    in cases of any conflict, subsequent to award, between
    RFP criteria and Contractors['] submittals, the RFP
    criteria shall govern unless there is a written
    agreement between the Contracting Officer and
    the Contractor waiving the specific requirement or
    accepting a specific condition pertaining to the
    offer.
    C.   Proposals will be evaluated for conformance to the
    minimum criteria in the RFP and for quality scoring.
    While the intent is to keep pre-award design effort to
    a minimum, proposals must provide enough design
    for the evaluation team to determine whether the
    proposed design meets the functional requirements
    for operational use during the anticipated life of the
    facility and to show engineering sufficiency and
    46
    soundness and the degree to which the proposal may
    exceed the minimum requirements. It must also form
    sufficient basis for developing a fair and reasonable
    price proposal.
    D.   In general, the proposal will be considered technically
    responsive if it includes the following:
    (f)   HVAC System:
    (i) Provide a brief narrative description of
    proposed system design and why the
    particular system was selected. Address
    thermal envelope design and operating
    characteristics of the HVAC system and the
    control system for guest rooms and other
    areas.
    (ii) Basic mechanical plan: Indicate on the
    architectural drawings major equipment
    locations and sizes.
    (v) Provide catalog cuts of proposed chillers,
    boilers, cooling towers, heat pumps and
    guest room units as applicable.
    (vi) DDC Controls: Provide narrative         "
    description of intended EMS Control
    system and catalog cuts of equipment to
    be provided.
    (R4, tab 2 at 1036-39; tr. 12/132-37) (Emphasis added) CO Wallace24, the original
    author ofL-20-1 A. and C., testified that:
    What we're basically telling the contractors is we've
    basically given you what our minimum requirements are
    and offerors may or may not be, depending on the other
    portions of the RFP, may be allowed to submit
    alternatives, alternative systems, alternative equipment,
    but that they have to specify that equipment separately in
    writing to the contracting officer. And the contracting
    24
    (See finding 262)
    47
    officer has to incorporate that deviation in writing into
    the contract.
    (Tr. 12/134-35)
    33. RFP Section M, EVALUATION FACTORS FOR AWARD, provided:
    M-1. PROPOSAL EVALUATION AND SELECTION
    PROCESS:
    a. A technical evaluation team will be established
    to evaluate each offer (proposal) in response to this
    Solicitation (RFP). The technical portion (Volume I I Parts
    1, 2, and 3) of each offer will be evaluated independently
    and objectively by the evaluation team (See M-2 below for
    the factors).
    b. Volume II, the Pricing and Financial offers will
    be evaluated separately by the Contracting Officer.
    c. Award will be based on an integrated assessment
    of the evaluation factors. The Contracting Officer will
    award the contract to that offeror that is the most
    advantageous and offers the best value to the NAFI, price
    and other factors considered.
    M-2. EVALUATION OF OFFERS: All offers
    (proposals) will be evaluated by the following factors.
    Price evaluation, M-2a is as important as all the factors
    under M-2b combined. Under Technical Evaluation
    (M-2b), Factor a is of the greatest importance. Factor bis
    less important than Factor a and slightly more important
    than Factor c. Factor c is less important than Factors a orb.
    See Section L-20 for descriptions and required submittals.
    M-2b. TECHNICAL EVALUATION:
    Factor a.     Vol 1 I Part 1 I Functional and
    Aesthetic Design
    48
    Factor b.    Vol 1 I Part 2 I Project Management
    Plan
    Factor c.    Vol l I Part 3 I Team Qualifications
    and Experience
    (R4, tab 2 at 1044)
    34. A Pre-Proposal Conference and site visit was held on 30 October 2003 (R4,
    tab 2 at 1045-51; tr. 1149-52, 2/9-10, 36-38, 43-48, 7/228-33, 255-57, 286-87, 290-92,
    298-99, 8/44, 9/172). A second site visit took place on 18 December 2003 (R4,
    tab 1012; tr. 1152-53).
    35. SBN's Henrickson testified that:
    [Botting]C25 l ask[ed] for a[ n] amendment to submit
    alternate systems, because we couldn't meet the price with
    the boiler and chillers.
    And it didn't fit the design. And we got the
    amendment that allowed for alternate systems.
    (Tr. 1/131-32) He then clarified that he did not know whose question about alternative
    systems resulted in the issuance of Amendment 5 (finding 36; tr. 11132). Botting's
    Burrus testified that, if Amendment 5 had not been issued, Botting would have
    proposed the RFP-required boiler/chiller system with the alternate system as a separate
    line item (tr. 4/39-41 ).
    36. RFP Amendment No. 00005 dated 22 December 2003 included the
    following information pertinent to the matters before us:
    7      NOTE: There is a pad-mount transformer on the
    site which will be removed by DPW with demolition of the
    two wood buildings on site. Removal of existing wood
    poles, OH electrical lines, and the transformer pad will be
    accomplished by the Contractor. There is also an
    underground secondary electrical feeder, communications
    conduits and water lines running through the site which
    will have to be rerouted around the building footprint as
    required. Existing water laterals, sanitary and storm sewers
    no longer in use may be removed and capped.
    25
    (See finding 44)
    49
    These questions and answers supersede or update any other
    stated requirements. Please note some questions/answers
    are similar.
    Q13 Section C-4 item 8.3.A.l The 3rd sentence mentions
    fan powered terminal units. Are non-fan powered units
    acceptable?
    Al3 Alternative systems may be submitted by Offerors
    for consideration.
    Q34 Can the ceilings in the corridors be chanted to lay-in
    acoustical to facilitate the install of the systems, example
    fire alarm, telephone, computer, etc ....
    A34 Corridors may be lay-in acoustical but must meet
    minimum height requirements ....
    (R4, tab 2 at 1052, 1055, 1062, 1063, tabs 176, 177; tr. 1/54, 8/38-43) Amendment
    No. 00005 also included the requirement that corridor ceilings be a minimum of 8 feet,
    4 inches high (R4, tab 2 at 1093).
    37. RFP Amendment No. 00006 dated 20 January 2004 included the following
    information:
    1.      Outside air shall be supplied to the guest suites by a
    separate HVAC system. Outside air intakes shall not
    be provided at individual PTAC units (See Section
    C-5 Page 32).
    (R4, tab 2 at 1126)
    38. RFP Amendment No. 00007 dated 21January2004 included the following
    information:
    50
    1. There have been a number of requests for
    clarification of air intake and centralized air distribution
    system requirements since the question and answer
    (Q/A #61) in Amendment #005, and the clarification in
    Amendment #0006. The new lodge requires a central air
    distribution system, to distribute fresh air to the rooms.
    Individual PTAC units in the rooms are not to be used for
    make up or outside air intake, as stated in Section
    C-5.15.4d.
    (R4, tab 2 at 1129, tab 178) This verbatim language was reiterated in RFP Amendment
    No. 00009 dated 9 March 2004 (R4, tab 2 at 1129).
    39. Volume II of the RFP contained SECTION J, a compilation of various
    drawings and documents including the following which are pertinent to the matters
    before us:
    J-2    Geotechnical, Site Information
    J-3    Installation Design Guide (Excerpts)
    J-4    Fort Lewis Design Standards (Excerpts)
    J-10 · Drawings I Separate Attachment
    • Utilities Plan
    • Suggested Site Plan
    • Suggested Main Floor Plan
    • Suggested Upper Floor Plan
    • Guest Room Layout Plans
    (R4, tab 2 at 1145-53 (J-2), 1154-1355 (J-3), 1356-1508 (J-4), 1721-26 (J-10))
    40. The J-2, Geotechnical, Site Information, document contained a narrative
    description of the various existing utilities in the project area as well as what was
    required to be provided under any resulting contract (R4, tab 2 at 1145-53).
    Specifically, ORB's Patterson, who drafted the RFP (finding 2), testified:
    [I essentially wrote paragraph C-1, 2.4.A. which]
    describes the topographic drawing, which I did include
    under Section J. It's a compilation of known information
    51
    that was developed from [DPW] showing the location of
    known utility lines ....
    Within public works, there is a record drawing room
    with a huge amount of old, as-built drawings, utility
    layouts, topographic maps, etcetera, going back to 1917.
    And essentially, I went through all known information on
    that site and the utilities on that site.
    I spoke to the superintendents of the various utility
    shops, water and waste, electric shop, both interior and
    exterior electric shops, etcetera, and did what I call some
    brain picking, and that drawing, which was included in
    Section J represented my best effort to I compiling
    everything that was known on that site from the as-built
    records.
    (Tr. 10/28-29; see also tr. 10/43, 129-31; R4, tab 1000)
    41. Among the J-10 drawings included in the RFP (R4, tab 2 at 1721-26 (Vol.
    4of22); findings 11, 39) was the utilities plan. ORB's Patterson testified:
    Drawing number one, the utilities plan, was drafted by me
    based on available information. Item two and three and
    four, the suggested site plan, main floor plan, and upper
    floor plan, was drawn by ORB, me, and that is the 10
    percent concept design of one suggested solution that I
    alluded to earlier....
    Drawing five is standard guest room layouts that
    were provided by Army lodging.
    [J-10] is a site and utility plan of the construction
    site and surrounding area, showing all known utilities and
    features as developed from available utilities drawings at
    public works. It's a compilation of several different base
    sheets that were provided by public works, and
    communications line as provided by DOIM .... [Data was
    obtained from] public works, water waste utilities
    52
    department, electric shop, and the DOIM, the directorate of
    information management, with respect to communications
    lines, so two different agencies on Fort Lewis.
    (Tr. 10/43-46; see also tr. 9/18-21, 48-49, 70-72)
    2. SBN's Proposal
    42. On 27 January 2004, SBN submitted a proposal in response to the RFP.
    The proposal included both a pricing proposal and a technical proposal and had 16-17
    parts contained in two binders (R4, tabs 3, 4; tr. 1154-57; app. br. at 15). The entire
    narrative describing the proposed HVAC system was:
    The proposed HVAC system includes multiple high
    efficiency packaged terminal heat pumps (PTAC) units
    serving the guest rooms. Studio rooms will have one
    PTAC unit and one-bedroom guest rooms will have two
    PTAC units. One unit will be located in the bedroom and
    the other in the living area. Tempered ventilation air is
    ducted to each guest room space from a central packaged
    rooftop 100% outside air make-up unit with cooling and
    gas heat.
    The lobby and administrative areas are served from a
    packaged variable volume rooftop unit located on the top-
    level roof well. Air is distributed to fan powered terminal
    units with electric heat to provide energy efficient comfort
    zonmg.
    A split system cooling only unit provides cooling for the
    data room.
    The laundry area is served from a packaged rooftop unit
    with adequate make-up air to offset the laundry exhaust.
    This unit has gas fired heating and is located on the lower
    level roof.
    The maintenance, storage, and receiving office are served
    by a packaged rooftop unit with gas heating. This unit is
    located on the lower level roof.
    A central exhaust fan (located on the top level roof well)
    serves the guest room toilets and provides potential for
    53
    energy recovery to the guest room ventilation system thru
    an air-to-air heat exchanger.
    Other exhaust systems will serve guest laundry room,
    management toilets, support area toilets, janitor, large
    laundry, and elevator machine rooms.
    (R4, tab 3 at 1849; tr. 3/59-60, 79-80) Nowhere in the narrative did SBN or Botting
    state that they were proposing an HVAC/mechanical system for the common areas that
    was not the boiler/chiller system required by the RFP, but was a deviation or alternate
    system.
    43. Eight years later at the hearing, Jensen/Fey's Fritzmeier testified that:
    Our collective experience found that installing a boiler-
    chiller in a facility like this was really kind of a step back
    in terms of quality. It was not something that is routinely
    done in hotel facilities, hospitality facilities of that type.
    And we looked at projects that we had done in the
    hospitality range that were comparable and the kind of
    systems that were used. And basically they're package
    systems. That's what's pretty routinely done in quality
    hotel facilities because they have advantages to tlie client,
    not only in terms of overall maintenance beyond the
    chiller, a boiler-chiller installation which has I with a
    boiler-chiller facility you have to have redundancy because
    if the boiler-chiller goes down, you have no way of
    maintaining any of the facility at a proper temperature.
    When you're doing package units, you maybe have
    to close down a portion of the facility because it will be
    uncomfortable, but you still have the majority of the
    facility available for your clients. So we generally find that
    to be a really strong driver in how you design the
    mechanical system for these buildings. That's something
    that we also routinely did in all of our other projects of all
    qualities.
    [The building is] a fixed size. So in order for us to
    be able to provide some of the extra amenities [like a
    54
    breakfast room], we had to be very efficient in terms of our
    use of space.
    The boiler-chiller system didn't allow us to do that.
    The package units really did allow us to do that, to give,
    we thought, not only a better project in terms of
    contemporary design and maintainability, but it also
    allowed us to give those amenities that we felt so strongly
    about.
    (Tr. 7/234-37) SBN did not include any of this information in either its initial proposal
    or its Best and Final Offer (BAFO) (see finding 50).
    44. SBN' s proposal identified the following entities as among their proposed
    subcontractors for the Lodge project:
    Architect                   Jensen/Fey Architecture & Planning [Jensen/Fey]
    Civil & Structural          DCI Engineers, Inc. [DCI]
    Mechanical Design           W.A. Botting, Inc. [Botting or WAB]
    Electrical Design           SME Inc. of Seattle [SME]
    (R4, tab 3 at 1963, 2070) Jensen/Fey had designed over 60 hotels and motels in the
    seven years prior to SBN's proposal (R4, tab 3 at 1966). SBN's proposal identified
    Jensen/Fey employees Charles Fritzmeier (Architect of Record), Kurt Jensen (Chief of
    Construction Quality Management System (CQMS)), Shauna Spencer (Chief of
    Construction Quality Control (CQC)), and Dan Rasmusson (Chief of Design Quality
    Control (DQC)). (R4, tab 3 at 1980-81, 1992-94; R4, tab 5 at 2287). SBN's proposal
    also identified the following SBN project management employees:
    Principal-in-Charge          Keith Henrickson
    Project Executive            Eric Holopainen
    Project Manager              Chris Bischoff
    Superintendent               Tom Zeman
    (R4, tab 3 at 2070)
    45. The initial Evaluation of Proposals took place 28-30 January 2004 at
    Fort Lewis by a Technical Evaluation Board (TEB) made up of the following
    individuals:
    R. Drew Dyer, P.E.    CFSC, Project Manager, moderator, non-scoring
    Steve Coulson         CFSC, Lodging Program Manager, evaluator, scoring
    Denis Senftner        Northwest Region, MWR Director, evaluator, scoring
    55
    Cindy Moinette[261 Ft. Lewis, Assistant Lodging Manager, evaluator, scoring
    John PattersonP.EP71ORB Organization, RFP AE firm, evaluator, scoring
    Eve Hebb            CFSC, Interior Designer, evaluator, scoring
    Gary Stedman[2 s1   Ft. Lewis, DPW, evaluator, scoring
    (R4, tabs 183, 1012, 1014; tr. 8/43-44, 48-54, 76, 9/38-39, 51-61, 66-69, 10/48-67,
    12/11-13, 25, 38-39, 107-10) After receiving in-person instructions from
    CO Bartholomew, a total of9 proposals were evaluated over 2Yz days, with
    approximately two hours spent with each proposal (tr. 10/55-56). SBN's proposal was
    ranked fifth on the total score. One weakness listed about SBN' s proposal was "Lack
    of clarity on mechanical systems; where located?" SBN was given the lowest score of
    all 9 proposals (a score of26 out of a possible 40) for "Building Design (Structural,
    HVAC, Mechanical, Plumbing, Electrical, Telecommunications, Force Protection)"
    but was scored second out of9 for "Project Management Plan" and "D/B Team
    Qualifications/Experience." (R4, tabs 198, 199) Unlike SBN's proposal that
    contained a short, general description of its HVAC/mechanical design and nothing on
    the subject ofDDC design, several of the other proposals received in response to the
    RFP included lengthy, detailed descriptions of their proposed HVAC/mechanical
    designs, including DDC design information (see, e.g., supp. R4, tab 181 at 9960-66,
    tab 182 at 9978-97, tab 192 at 10045-47, tab 193 at 10058-59).
    46. On 29 January 2004 SBN provided the following clarifications to CO Bartholomew
    in response to the CO's questions:
    Question #2. From first glance there does not appear
    that there [is a] boiler room on the first floor. Is this
    correct?
    Response to Question #2: .... The boiler room is located
    adjacent to Maintenance Room J 70A. The boilers are not
    26
    Cindy Moinette became the Lodging General Manager in 2005 and was responsible
    . for managing approximately 930 rooms at Fort Lewis, McChord AFB and
    Yakima Training Center on behalf of Army Lodging, the owner of the new
    Lodge built under the contract now at issue (tr. 12/9, 11). Ms. Moinette was the
    POC for post passes (R4, tab 25 at 2409; tr. 12/26-27).
    27
    The typewritten "P.E." was crossed out and a handwritten "INCORRECT" was
    annotated (R4, tab 1014). Mr. Patterson testified that he does not have an
    engineering degree and has no engineering certifications (tr. 10/11-12, 132-34).
    His primary experience is in architecture and construction (tr. 101133).
    28
    Gary Stedman has been in the Planning Division of Fort Lewis DPW since the
    mid-1990s; for 10-12 years prior to that he was in the Environmental Division
    ofDPW at Fort Lewis (tr. 12/94).
    56
    detailed on the architectural plans. They are shown in
    Room l 70A at this time on the mechanical drawings. The
    intent is to have a room adjacent to Room 170A dedicated
    to the boilers.
    Question #4. We did not find Maintenance
    Specifications and other narratives but we assume that
    you will be fully compliant with all technical
    requirements of the RFP.
    Response to Question #4: Yes, per our revised pricing
    schedule attached we are fully compliant with the technical
    requirements ofthe RFP. None of the VE alternates
    [attached at SBN0032320] need to be incorporatedfor full
    compliance.
    Question #5. Will you meet all applicable required
    codes for the design and construction of this project?
    Response to Question #5: Yes, we will meet all applicable
    required codes for the design and construction ofthis
    project.
    Question #6: Are you compliant with the square foot
    requirements of the RFP?
    Response to Question #6: Yes, per Drawing A.2.1 area
    analysis, the total square footage ofthe project as
    proposed is 100, 700 square feet.
    (R4, tab 1013; tr. 1/73-77, 80-82, 1/133-34)
    47. Both ORB's Patterson in his preparation of the RFP and SBN's Architect
    of Record, Jensen/Fey, reasonably assumed that, since the DOIM ductwork was
    installed by base personnel, the Fort Lewis standard of 3 feet of cover had been
    accomplished (R4, tabs 184, 185; tr. 7/294-95).
    48. A telephone conference was conducted on 5 March 2004 in which
    CO Bartholomew participated with SBN's Henrickson and Bischoff and Jensen/Fey's
    Jensen and Fritzmeier. Jensen/Fey's notes from the call included:
    57
    1. $1.5m has been added to the project budget.
    2. Our proposal must be at $17,361,000 or less.
    6. Fo[u]r additional changes have been made and are
    outlined in the Amendment:
    b. Structure can be located over utilities.
    7. Our Proposal was ''technically acceptable" and "fully
    acceptable".
    11. The exterior architecture design and narrative was
    considered excellent.
    12. The interior narrative was considered good.
    15. The plans were well detailed.
    16. The schedule was realistic.
    18. Significant hospitality experience was outstanding.
    19. Personnel were outstanding.
    24. The specification maintenance plan needs to be
    included.
    58
    27. There needs to be a force protection narrative.
    33. Mechanical room appears undersized.
    3 5. The mechanical system needs to be clarified
    (narrative).
    (R4, tab 1017; tr. 7/238-42) The copy of the notes in the record include handwritten
    marginalia added by an unidentified author sometime between 5-12 March 2004.
    Items 24, 27 and 35 were identified as items for Botting (WAB). In particular, Item 35
    was annotated by circling the word "narrative" and placing a star above the circle as
    well as a handwritten note in the margin stating: "WAB REVISIT I ADJUST FOR
    REVISIONS." (R4, tabs 186, 1017; tr. 1/80) Over eight years later Jensen/Fey's
    Fritzmeier testified that:
    I think one of the other things that since it was something
    that we were particularly concerned about because we
    thought it was a real benefit and I'm pretty sure Keith
    [Henrickson] is the one who brought it up was the
    mechanical system. And the response from [CO
    Bartholomew] was as long as you're meeting the
    performance requirements of the RFP, we can make it
    work. And there may have been some additional discussion
    about well, this mechanical system allows us to do other
    things and there are some financial aspects that come into
    play if we can provide this system and so on and so forth.
    (Tr. 7/241) None of this information was included in the notes of the 2004 conference
    call. Contrary to Mr. Fritzmeier's testimony, SBN's Henrickson testified:
    Q       ... Was there a discussion of the HVAC
    alternative proposal during this conversation?
    A      Not that I'm aware of.
    Q      What did the mechanical, ... Item Number
    35, what do you recall about that issue?
    59
    A      They just wanted us to clarify. We had
    already stated that was a package, but they wanted more
    clarification.
    (Tr. 1/82) Henrickson further testified that there is no documentation to memorialize
    Fritzmeier's alleged discussion and there is nothing in the record to show that later,
    when the 35% HVAC/mechanical design was objected to (finding 60), SBN ever
    argued that the now-alleged discussion of the HVAC/mechanical system with the CO
    had taken place (tr. 11144-46). We, therefore, give little weight to Mr. Fritzmeier's
    non-contemporaneous testimony.
    49. On 9 March 2004 CO Bartholomew requested BAFOs:
    2. As a result of the technical evaluations and the resulting
    discussions with offerors, all offerors are hereby provided
    the opportunity to submit a [BAFO] to clarify, correct,
    update or revise offers to comply with the RFP
    requirements, including all amendments. Only changes to
    the prior technical submissions are required.
    6. No further changes to the solicitation (RFP) shall be
    made without the expressed [sic] written approval of the
    [CO]. ...
    (R4, tab 188) The only change to the RFP referred to in paragraph 6 that is pertinent
    to the matters before us was memorialized in RFP Amendment No. 00009 dated
    9 March 2004 and dealt with the DOIM ductbank (R4, tab 2 at 1129).
    50. On 23 March 2004, SBN submitted its one-volume BAFO (R4, tab 5; app.
    br. at 23). SBN's BAFO identified 17 items that had been revised since SBN's initial
    27 January 2004 proposal (R4, tab 5 at 2227-28; tr. 1/83-85). The BAFO included an
    "expanded, added and clarified" HVAC System Description (R4, tab 5 at 2229). The
    entire text of the HVAC System Description in the BAFO was:
    •   The proposed HVAC system includes a total of
    (260) high efficiency packaged terminal heat pumps
    (PTAC) units serving the guest rooms. Studio units
    will have one PTAC heat pump and one-bedroom
    guest rooms will have two PTAC heat pumps. One
    heat pump will be located in the bedroom and the
    other in the living area.
    60
    •   Tempered ventilation air is ducted to each guest
    room space from central packaged 100% outside air
    make-up units with cooling and gas heat[29l located
    on grade.
    •   The lobby and administrative areas are served from
    a packaged variable volume unit located on grade as
    indicated on the mechanical concept drawings. Air
    is distributed to fan powered terminal units with
    electric heat[29l to provide energy efficient comfort
    zonmg.
    •   A split system air conditioning unit provides
    cooling for the data room.
    •   The laundry area is served from a packaged air
    conditioning unit with adequate make-up air to
    offset the laundry exhaust. This unit has gas fired
    heating and. is located on the ground level.
    •   The maintenance, storage, and receiving office are
    served by a packaged rooftop unit with gas
    heating. [291 This unit is located on the lower level
    roof.
    •   Two central exhaust fans (located in the attic space)
    with exhaust duct extending to exhaust grilles in
    each guest room toilet.
    •   Other exhaust systems will serve guest laundry
    room, management toilets, support area toilets,
    janitor, large laundry, and elevator machine rooms.
    (R4, tab 5 at 2257; tr. 3/79-80, 100-13) SBN's expert witness Kommers testified that
    "packaged" to a mechanical engineer/contractor means "self-contained" (tr. 3/34-38,
    59-60; see also, tr. 3/72). However, Kommers also agreed that there are "packaged"
    boilers and "packaged" chillers and "packaged" boiler/chiller systems (tr. 3/40-41,
    44-46, 52, 8/155-156; see also R4, tab 349 at 11151 (packaged terminal heat pump
    29
    We find that the use of the words "gas" and/or "electric" does not indicate the
    presence or absence of a boiler in the design for these areas.
    61
    units can be used with a boiler/chiller system)). Butting's Burns testified that his
    design did not include a boiler/chiller system for the non-guest-room areas specified in
    the RFP because:
    [I]t was about 10 percent of the system's capacity, was
    what was the issue. It wasn't that it was the majority. You
    know, the majority of the equipment was packaged
    terminal heat pump equipment [for the guest rooms].
    What we were proposing was additional packaged
    equipment, mainly driven by the geometry of the building,
    being kind of a long spread out building, because there is a
    lot of cost involved in having to run piping between those,
    and there is no I there was no piping involved in this 90
    percent of the capacity, anyhow.
    (Tr. 3/92-93; see also tr. 4/8-9, 36)
    51. By letter dated 26 March 2004, SBN assured the Fund that:
    Our proposal complies with the RFP and if awarded a
    contract we ensure material compliance with the RFP
    requirements. We have reviewed and verified our pricing
    and it is acceptable for the basis of a firm fixed price
    contract if awarded this project.
    (R4, tab 1 at 5, tab 200; tr. 1189-90) Again, SBN made no mention of its inclusion of
    an alternative HVAC/mechanical design in its BAFO. SBN provided the following
    clarifications, among others, in response to questions from the Fund:
    Question #4: We note that your proposal is silent in
    several key areas where the RFP called for specific work.
    We assume this silence is because you inten[ d] to provide
    the required work/equipment and are not proposing
    alternatives that would have required
    submittals/catalogue/cut sheets. Is this correct:
    Response to Question #[4]: Yes_X_ No_ _
    (R4, tab 1 at 6, tab 200; tr. 1186-89 ("you're just submitting on a very preliminary
    design ... we hadn't even determined a lot of the items that we're going to use yet ....
    It's that early in the design .... We didn't put in cut sheets"), tr. 11104 ("You're
    designing as you're building."), tr. 11123-124)
    62
    52. The technical evaluation ofBAFOs took place in April 2004 (R4, tab 169
    at 3221-25, 1018-19; tr. 8/56-64, 9/61-66, 64, 69, 10/67-91, 12/110-12; see also R4,
    tabs 198, 199). ORB's Patterson testified that, at the time he reviewed SBN's BAFO:
    I did not have that concern [about whether or not SBN' s
    BAFO included a boiler/chiller system] because [SBN]
    expressed a willingness to redesign the system to move the
    air handling units off the roof down to the main floor, and
    did not say that they were not providing a boiler chiller, so
    I assumed they were. My concerns were alleviated at that
    point.
    (Tr. 10/166, 177-78)
    I did not recognize that a packaged VAV system meant
    that the heat and cooling source were built in part and
    parcel with the air handler. I didn't realize what that was,
    and there was no indication in the proposal that this was an
    exception to the RFP requirement for a central boiler and
    chiller.
    There is no note that the equipment listed is a variation
    from the boiler chiller, central boiler chiller. There is,
    however, now in hindsight, indication that packaged
    cooling and heating units were being called out in various
    spaces. It's not uncommon to get incomplete mechanical
    equipment schedules on a 10 percent [de]sign], so that may
    not have rung a bell without a note saying, "This is a
    variation."
    Depending on the submittal and the contractor, proposals
    can be incomplete in some areas, complete in others. You
    will routinely see contractors pulling together their
    submittals from all of their various subs at the last minute
    to get them to the room on time.
    Some routinely I or not routinely I some,
    occasionally, are incomplete. So, the fact that I didn't see a
    central chiller on this schedule doesn't in itself indicate we
    63
    weren't getting one without a note saying, "You're not
    getting one," if that makes any sense.
    [If I had recognized that SBN was submitting an alternate
    system] [t]hat would have been commented on or
    annotated on my score sheet, my review sheet. I actually
    bumped them up on mechanical systems. If I had thought
    they were proposing any sort of an unsatisfactory
    alternative mechanically, I would have lowered their score,
    perhaps even zeroed it.
    (Tr. 10/96-100)
    B. Contract Award
    53. On 11 May 2004, the Fund awarded design/build Contract No. NAF26-04-C-0025
    in the firm-fixed-price amount of$17,359,397 to SBN. 30 The notification letter to SBN
    advised that an Award Meeting/Pre-Design/Build Conference was scheduled for 20 May
    2004. Receipt of the letter was acknowledged by SBN's Henrickson on 27 May 2004.
    (R4, tabs 1, 6, 203-04) CO Bartholomew authorized a Limited Notice to Proceed (LNTP) for
    35% design effective 21May2004 (R4, tabs 7, 203, 1021). The contract expressly
    incorporated the following by reference:
    (1) Request for Proposal (RFP) NAF26-04-R-0004,
    as revised by Amendments 0001, 0002, 0003, 0004, 0005,
    0006, 0007, 0008, 0009, including all attachments,
    specifications, drawings and enclosures thereto.
    (2) Contractor's Offer, dated 27 January 2004,
    including all attachments, drawings and enclosures thereto.
    (3) Contractor's BAFO offer, dated 23 March
    2004, including all attachments, drawings, BAFO Pricing,
    and enclosures thereto, which take precedence over the
    27 January 2004 Offer.
    30   Other copies of the DA FORM 4069-R, SOLICITATION, OFFER, AND AWARD
    (Nonappropriated Funds), contained in the record, Rule 4, tabs 204, 1021, are
    identical to Rule 4, tab 1 at 1, except that the signature of CO Bartholomew is
    inexplicably dated 12 May 2004.
    64
    (4) Contractor's Price Clarification that the optional
    grounds maintenance building, with a value of$96,386.00,
    is included in their base bid [design and construction], and
    Other Clarifications, dated 26 March 2004, (1 Page).
    (5) Contractor's Pricing Verification and Statement
    of Material Compliance, dated 26 March 2004 ( 1 Page).
    (6) Contractor's Final Bid Extension and
    Clarifications, dated May 6, 2004 (2 Pages).
    (7) Contract Number NAFBAl-04-C-0025, DA
    Form 4069-R Solicitation, Offer and Award
    (Nonappropriated Funds), dated 23 March 2004, signed by
    Keith Henrickson, Sr. V.P., Division Manager, Swinerton
    Builders, and signed by the Contracting Officer, D.F.
    Bartholomew, Jr., on 11May2004.
    (R4, tab 1 at 2) The contract further specified the Order of Precedence that, in the
    event of any inconsistencies between the contract and SBN' s proposal, the terms and
    conditions of the contract would prevail (id.).
    54. The contract contained the following schedule for design and
    construction:
    Total number of calendar days after Notice to Proceed for         145 Days
    Design (Does not include Government Review Time)
    35% Design Completion and Submittal                               1.l_Days
    65% Design Completion and Submittal                               49 Days
    95% Design Completion and Submittal                               ll._Days
    100% Design Completion and Submittal                             35 Days
    Total Number of Calendar days for Construction after              425 Days
    Limited Notice to Proceed for Construction
    (R4, tab 1 at 8)
    55. SBN hired Mr. Roberts as its Senior Project Manager in June 2004 and
    assigned Tom Zeman as its on-site superintendent (tr. 1191, 178-80, 2/96-103, 117,
    65
    173). At the time of his testimony Mr. Roberts had been in construction for 40 y~ars,
    20 of which had been as a project manager for various construction companies
    (tr. 2/89-90, 92-96).
    C. Performance
    56. After the contract had been awarded to SBN, ORB's contract with CFSC
    was modified to include ORB's review of SBN's various design submittals. ORB
    formed a team to perform the design reviews that included BCE to review mechanical
    and electrical designs, AHBL Engineers to review structural and civil designs and
    ORB to review the architectural design and "overall" issues. (Tr. 10/100-01, 111148)
    Patterson selected BCE on the basis of his 28 years of working with them on several
    hundred projects (tr. 10/101-02, 140-43).
    Q:     When you engaged BCE to perform the
    scope of work we just discussed, did you know that they
    had participated as members of off1 erors] who offered
    proposals on this project?
    A:        I saw at the [TEB], and it took me by
    surprise, ... that BCE was on one of the teams. I couldn't
    tell you which team that was. As I say, BCE is a multi-
    discipline, fairly large firm. There are 54 or 55 people.
    They routinely propose on design-build work with a lot of
    contractors. They don't clear that with me first. They don't
    work for me, so. They were, in fact, apparently on one of
    the proposals as the MEPP 1l
    Q:     When you engaged BCE to perform the
    design submittal review scope of work, did you have any
    concerns as to their objectivity in conducting those
    reviews?
    A:     Absolutely no, no.
    Q:     In your review ofBCE's work on the
    project, did you see any evidence of bias or impaired
    objectivity?
    31
    "MEP" is an acronym for "Mechanical, Electrical and Plumbing" (tr. 13/15).
    66
    A:     No, sir. They are professional engineers, and
    professional in every sense of the word. That would not
    have entered into it.
    (Tr. 10/102-03; see also tr. 111131-32)
    57. BCE's work was primarily in the areas of mechanical and electrical
    engineering and, at the time of its involvement in the project now at issue, its work
    consisted of approximately 50% public schools work and 50% military projects at
    Fort Lewis and McChord AFB (tr. 11/112-14, 150). The ORB contract tasked BCE to
    perform a peer review of SBN' s various design submittals with particular attention to
    be paid to the mechanical, electrical, plumbing and fire protection portions of the
    submittals (tr. 111116-17). Among the specific BCE employees that performed
    services under ORB' s contract with BCE were Randy Heiberg32 , principal in the firm,
    and John Justice 33 , referred to variously as a junior engineer or a production engineer
    (tr. 111114-17, 129-31, 174-76). Mr. Heiberg testified that he was aware of the project
    before the ORB contract for design review but he wasn't directly involved prior to
    SBN's 35% design submittal (tr. 111114-16, 130-31, 150-51, 161; see also finding 59).
    Mr. Justice was also first involved in the project now at issue after SBN's 35% design
    submittal (tr. 111172-73, 185-88). SBN alleges that BCE was a direct competitor of
    Botting at the time of proposal submissions and that ORB's employmentofBCE to
    conduct the peer review of SBN/Botting's HVAC/mechanical design submittals
    created a potential for bias. SBN admits it has no proof of actual bias. (R4, tab 169 at
    3355; tr. 7/243-244; finding 66) After careful examination of the record before us, we
    find no evidence that the actions, opinions and recommendations of BCE were based
    on anything other than its professional consideration of the factual information
    presented to it.
    1. 35% Design
    58. SBN's 35% Design was submitted to the Fund on 10 June 2004, which was
    acknowledged by COR Dyer as being on schedule and a review meeting was
    scheduled for 8 July 2004 (R4, tabs 8, 9; tr. 9/41-46, 12/14-17).
    32
    Mr. Heiberg, with BCE since 1992, has experience as an electrical engineer,
    mechanical electrical consultant, construction management, mechanical HVAC
    contracting, and automation controls (tr. 111108-11).
    33
    Mr. Justice is a mechanical engineer who worked for Boeing from 1996-1999 and
    had been with BCE since 1999. He was licensed as a Professional Engineer in
    2006. (Tr. 111169-72)
    67
    59. At the time of the 35% design review, BCE's Binh (or Ben) Nguyen was
    the BCE project lead and point of contact. Mr. Heiberg was brought onto the project
    at this point to assist and eventually replace Mr. Nguyen as the project lead:
    [M]y role responsibility was to ensure when submittals
    came in that they were organized. We'd get a set of plans,
    we'd have to pull the set of plans, reduce-pull the
    plumbing out, pull the HVAC drawings out and distribute
    it to the people who had time and expertise to do the
    review. So once I collected all the reviews, organized them
    into the forms that ORB had given us to use, and return
    those comments to them.
    (Tr. 111117-18; see also tr. 111164) Mr. Nguyen left BCE between the 35% and 65%
    design submittals (tr. 111119).
    60. The Fund provided ten pages of detailed review comments to SBN on
    1 July 2004. Comments M2 and M6, respectively, stated:
    Note the ventilation air for the guest rooms; and heating,
    ventilation, and air conditioning of all other spaces is to be
    provided by primary air handlers utilizing chilled and hot
    water coils per the RFP. The design does not indicate this
    type of system.
    The fan powered terminal unit schedule shows units with
    electric coils. Per the RFP these units are to be provided
    with hot water coils for reheat.
    (R4, tabs 10 at 2314, tabs 207, 210) On 5-6 July 2004 the Fund provided more than
    ten additional pages of detailed comments to SBN, including:
    65% design submittal is due Fri., 27 August. Design
    review meeting will be on/about Tues., Sept.21. It is our
    goal to issue a [LNTP] for construction to allow
    mobilization and site work (civil, utility, foundation, and
    structural activities) upon completion of that meeting and
    acceptance of the exterior structural mock-up rooms. With
    the same Limited NTP, we'd like to release Swinerton to
    order long lead items (HVAC units, elevators, etc.). In
    order to provide the a [sic] Limited NTP, the 65% design
    68
    submittal shall contain civil, structural, and long lead items
    to be 100% designed and with the engineer of record's
    professional seal and signature.
    (R4, tab 11 at 2328, tab 12)
    61. SBN's responses to the Fund's review comments M2 and M6 (finding 60)
    were understood to be:
    [B]asically, "WILL COMPLY" or "AGREE" except:
    [The response to M2] was: "Primary air handling units
    provide centralized ventilation system with direct
    expansion cooling, and combination of natural gas, electric
    and heat pump system for heating based on most energy
    efficient application"
    [The response to M6] was: "Based on our energy analysis,
    electric heating was selected based on lowest energy
    cost.["]
    (R4, tab 14 at 2352) This is the first evidence we find in the record of SBN providing
    any explanation for its submission of an alternative design.
    62. A list of decisions made and action items identified at the 8 July 2004 35%
    design review meeting was prepared by the Fund's Dyer and provided to Fund and
    SBN personnel. The following listed items are pertinent to the matters before us:
    20.    Swinerton to utilize Ft. Lewis standard construction
    specifications whenever possible (posted on the
    FL W IDG web site).
    24.    Corridor ceiling heights are shown 8'-4". There may
    be cases where corridor ceiling heights are adjusted
    downward to account for piping and ductwork. In
    those cases, CFSC will be advised beforehand.
    Swinerton will not design or construct any
    corridor ceiling heights less than 8'-0".
    69
    27.    [SBN] to provide justification for HVAC systems
    proposed for use or change to comply with RFP.
    If I have overlooked or mis-stated something important,
    please let me know.
    (R4, tabs 13, 211-14, 1024; tr. 7/275-77)
    63. By email dated 13 July 2004, Dyer forwarded to SBN and its Architect of
    Record the "thoughts of the peer review engineers" concerning SBN's responses to
    comments M2 and M6 regarding the mechanical system design.
    The system proposed does not meet the RFP requirements.
    If the contractor's design was based on the most energy
    efficient application, in our opinion the contractor needs to
    prove to the team that the original RFP allows the
    contractor to follow "that path" instead of designing per
    the RFP requirement.
    Secondly the contractor needs to prove that his design in
    fact is the MOST energy efficient design with the lowest
    energy AND OPERATING cost. We need to have the
    contractor include all calculations in the package for our
    review at 65% (If, and only if, the "more energy efficient
    mech system" is allowed and approved by AL.)
    (R4, tab 14 at 2351, tabs 216-17) In a second email to the same recipients less than an
    hour later, Dyer expressed his concerns after receiving much more detailed input from
    BCE's Heiberg (R4, tab 15 at 2353-55, tab 217; tr. 111164-68) on the subject of SBN's
    proposed mechanical system:
    Here's the other msg. I promised to forward ... this one is
    from a senior principal of BCE Engineers (subcontract to
    ORB) ... his views are "eye-opening" for me especially
    when he says you are asking us to accept a heating and
    cooling system that costs less initially, costs more to
    operate & maintain annually, and has a shorter life.
    Doesn't sound like something we really want to consider
    on our long term investment. As the choice of HVAC
    systems has space planning and structural considerations, I
    agree with Mr. Heiberg that you need to provide the type
    of system defined in the RFP or else defend your choice
    and convince Mr. Heiberg that his analysis on the negative
    70
    attributes was in error. This could possibly be resolved
    with a conference call. Let me know your course of action
    ASAP.
    (R4, tab 15 at 2353, tab 217)
    64. On 14 July 2004 a phone conversation between Botting and SBN was
    memorialized in handwritten notes by SBN that:
    [Batting's] Burns called: says what we have at 35% is
    what we proposed. It's true that it isn't in complete RFP
    compliance but we have always been up front with that
    and they accepted our proposal and design with the system
    that Randy Heiberg of BCE is now criticizing. Burns will
    work up a positive response and get us a draft by this
    Friday explaining [the] way this system is a good one, how
    the owner already [received] the value in the pricing and
    what they will do to make some more RFP accomodations
    [sic].
    (R4, tabs 219, 1025) (Emphasis added) Contrary to SBN's statement that it had
    "always been up front with that," we have found that none of SBN's proposals, its
    BAFO or later discussions and assurances had identified to CFSC that SBN intended
    to provide something other than what the RFP required (see findings 42, 48, 50-51).
    65. On 28 July 2004 COR Dyer requested CO Bartholomew's assistance in
    resolving the mechanical system design issues:
    Bart, need your help to correct the mechanical approach to
    heating and cooling the common spaces in the new
    Lodging facility at Ft. Lewis. This has been discussed in
    detail since we had the 35% design review meeting July 8.
    ORB prepared the technical sections of the RFP.
    Mr. Patterson described a particular approach to heating
    and cooling the common spaces that helps the Base meet
    their sustainability goals and objectives. I have discussed
    this issue with DPW and am convinced that we need to
    have [SBN] change their approach immediately. Pis.
    instruct [SBN] that they must design and provide the
    mechanical systems described in the RFP (Sections C-4,
    8.3, 8.4, & 8.5 and C-5, 15.4, 15.5, 15.6, & 15.7).
    71
    Space planning issues are still in motion. I met with [SBN]
    today in their main office, Bellevue, WA. We discussed
    DOIM room sizing, housekeeping rooms sizes, a 2nd guest
    laundry, and consolidating the administration spaces. I will
    be expecting a series of sketches soon showing how all of
    this can be accomplished and meet the functional and
    operational objectives of AL.
    (R4, tabs 16, 1027)
    66. SBN's Roberts prepared a Summary Report dated 29 July 2004 in which he
    agreed that the HVAC/mechanical system in SBN' s proposal was an alternate design not
    in compliance with the RFP but also took the position that providing the RFP-required
    boiler/chiller HVAC/mechanical system for the non-guestroom areas was a change to
    the contract:
    Subject: 35% Mechanical Review Comments for Air
    Conditioning in the Common Areas
    At this time, the design for the common areas of the
    building uses a warm air heating system. That system
    does not comply with the original RFP for the project.
    The COR is recommending to the Contracting Officer that
    he issue direction to [SBN] to provide a mechanical air
    conditioning system for the common areas of the building
    that uses boilers, chillers and fan powered terminal units as
    called for in the RFP.
    Subsequent research shows that the mechanical system
    Botting showed in the 35% design was the same system
    [included] in the technical proposal submission on January
    27, 2004 .... It is correct that this system does not meet
    the specific requirements of the original issued RFP.
    Comments by BCE Engineers after the 35% design review
    meeting continued to make the point that the proposed
    mechanical systems do not meet the RFP. More
    importantly, the comments state that the proposed system
    will consume more electrical energy and fuel than the
    72
    centralized system called for in the RFP, that the
    maintenance costs will be higher and that the equipment
    life of the proposed system will be shorter.
    W.A. Botting countered that their system was at least as
    efficient as the system called for in the RFP, that the
    energy costs were comparable, and that the equipment life
    was also comparable. In addition, there is a very desirable
    redundant capability in their system, that does not exist in
    the RFP system. Upon receiving BCE' s review comments,
    Tim Bums of W.A. Botting, re-evaluated their system, and
    re-checked their previous calculations. Tim determined
    that the system Botting proposed has an energy
    performance capability that is as good as the RFP system,
    and is probably a little better. The equipment life of their
    system is in the 10 to 15 year range, which is essentially
    the same as the RFP equipment. In addition, the fact that
    they do not rely on a chiller or boiler that is common to all
    systems, gives them a redundant capability of several
    systems that have an overlap, which gives their proposed
    system a desirable capability that the RFP system does not.
    At a meeting at [SBN]'s office on 28 July 2004, a
    telephone conference was held between Randy [Heiberg]
    of BCE Engineers, Tim Bums, ofW.A. Botting,
    Drew Dyer of Army CFSC, and Bill Roberts of[SBN].
    Mr. [Heiberg] stated that he had been charged with
    reviewing the system for compliance with the RFP and had
    found that it did not comply. He stated that he would need
    new criteria to evaluate what was proposed by [SBN],
    because the system did not comply with any of the Fort's
    design standards. He stated that the mechanical system in
    every building on Fort Lewis uses a boiler, or was hooked
    to a campus steam system. He stated that the design
    standards for Fort Lewis do not allow any system that does
    not employ a boiler.
    Looking at the Fort Lewis design standards that are on line,
    we found a division 15566 listed that is titled "Warm Air
    Heating System." This system does not require a boiler.
    Mr. [Heiberg] may not have been aware of this section
    73
    when he made the statement that the Fort Lewis design
    standards do not allow any system that does not employ a
    boiler, because this appears to be a relatively new section,
    as it is dated 14 November 2003. Nevertheless, it appears
    that the Fort Lewis design standards do allow air
    conditioning systems that do not employ a boiler.
    According to Tim Bums ofW.A. Botting, a warm air
    heating system is what they proposed.
    It came to [SBN] 's attention after this meeting that BCE
    Engineers, who were doing the peer review of [SBN] 's
    mechanical design, had been the mechanical design
    member of one of the other design/build teams that had
    offered on the project. It seems inappropriate for a designer
    who was unsuccessful in its attempt to be awarded this
    project with its design to then be one of the peer reviewers
    of the successful designer.
    Mr. Dyer returned to the Fort after the meeting and
    conference call on 7/28/04 and met with the [DPW]
    managers, who informed him that they were not interested
    in having the system proposed by the [SBN]/Botting team.
    Mr. Dyer then called Bill Roberts and informed him that he
    was trying to contact the Contracting Officer,
    Mr. Bartholomew, and tell him that he needed to provide
    written direction to [SBN] to comply with the RFP for the
    mechanical systems, and to disregard the amendment #5
    direction in the event that [SBN] thought that direction
    allowed them to vary from the RFP system.
    Subsequent investigation into how the mechanical
    design became what it became, shows that Botting was
    using boilers and chillers in its design through
    November 19, 2003, but on January 5, 2004, the boilers
    and chillers were no longer in the design. It is still not
    clear what happened between 11/19/03 and 1/05/04 that
    caused the system to change. There is some speculation
    that when the silver LEEDs requirement was dropped,
    the system change was made, but that can't be proven
    at this point.
    74
    This research produces a number of questions:
    Why did Botting change the system from RFP compliant to
    what they submitted?
    Tim Burns did not know as of 11:30 A.M, 7129104.
    He is researching.
    Does the fact that the Fort Lewis design standards allow a
    warm air heating system give Botting the latitude to use
    such a system?
    Yes. It is a Fort Lewis design standard, and an
    alternate system.
    If the Owner insists on changing the system to one with
    chillers and boilers like the RFP, what would it cost?
    Afirst pass for mechanical came up with an
    estimate of $246,200.00. There would be additional costs
    for electrical andfinish systems to conceal all the
    additional piping such a system would require. An initial
    rough guess estimate is approximately $400, 000. 00.
    If the Owner insists on changing the system to one with
    chillers and boilers like the RFP, what other costs and
    impacts would be encountered beyond mechanical?
    Electrical, Sprinklers, Building Height, Ceilings,
    Delay?
    If the Owner insists on changing the system to one with
    chillers and boilers like the RFP, should that be the subject
    of an equitable adjustment to the Contract?
    That is reasonable.
    (R4, tab 17 at 2377-80, tabs 222-23, 275; tr. 1/99-100, 2/123-25; see also R4, tab 323)
    (Emphasis added)
    67. On 30 July 2004 Botting responded to SBN's Roberts' request for
    information about the proposed alternative system:
    We believe that our proposed system meets the RFP
    objectives. The RFP allows for packaged air cooled DX
    systems to serve the guest rooms as well as other spaces.
    15
    Our proposed system will provide better indoor air quality,
    noise levels and energy efficiency in these other spaces by
    means of packaged dx units with better air filtration
    potential. Our proposed system does not compromise
    LEED certification and contributes to the cost efficiency in
    meeting project budgets.
    We are more than willing to entertain other system
    approaches. The cost of going to a chilled water I hot water
    heating system is being priced up and should be available
    this afternoon.
    (R4, tab 224) Later the same day Botting provided an estimated cost of providing "a
    chilled water I hot water heating system" to be $246,200 and also noted that doing so
    would create a "serious problem" with "pipe congestion in the 1st floor ceiling" (R4,
    tab 225; tr. 2/127-28).
    68. SBN's Henrickson forwarded Robert's summary report (finding 66) to
    CO Bartholomew several days before they planned to meet on 4 August 2004 to
    discuss the matter (R4, tab 17 at 2371; tr. 1/100). We find nothing in the voluminous
    record before us to document that a meeting actually took place on 4 August 2004.
    69. A meeting was scheduled for 16 August 2004 at which SBN/Botting was to
    make its case for its proposed alternative mechanical design to Fort Lewis DPW
    personnel and with COR Dyer attending via teleconference (R4, tab 17 at 2375,
    tab 227). A presentation was made at the meeting by Botting for which the following
    information was contained in a handout:
    1. Purpose to explain WA Botting heating system design,
    function, maintenance and equipment choices.
    2. Tim Burns: PE Received Engineering degree from
    University of Washington ....
    3. 90% of building heated by self-contained heat pump[]
    units with ventilation air supplied by unitary units. 10%
    of building heated by other types of heat. (Lobby,
    Maintenance, Laundry.[)]
    4. Basis of design.
    76
    a.    Reasonable Energy usage and L[EED] certification
    b.    Allowed by Fort Lewis design standards
    c.    WA Botting energy study graph charts
    d.    Ease of Maintenance. Replacement parts available
    at local supply houses
    e.    Redundant equipment
    f.    Life expectancy between small unitary units, splits
    and large chillers/boilers. Compressors would be the
    same as contained in small air cooled chillers.
    g.    Info from Washington Air Reps
    h.    Other ideas that WA Botting rejected. Why a chiller
    and boiler plant was not a reasonable choice for this
    project.
    (R4, tab 1030; tr. 3/92-96 (the total of the areas served by the alternate design was about
    11 % of the total building)) The record contains notes from the 16 August 2004 Mechanical
    HVAC Design Review Meeting; the author of the notes is not specified but, based upon the
    content of the notes we find that the notes were authored by SBN's Roberts:
    Attendees:
    Tim Burns                     [Botting]
    Dave Fillo                    [Botting]
    Michael Hawkins               Washington Air Reps
    Matt Adkins                   Washington Air Reps
    Gary Stedman                  Fort Lewis Public Works [DPW]
    Bernadette Rose               Fort Lewis Public Works [DPW]
    Dale Brigham                  Fort Lewis Public Works [DPW]
    ?                             Fort Lewis Public Works [DPW]
    John Patterson                The ORB Organization
    Randy Heiberg                 BCE Engineers
    Drew Dyer                     Army CFSC (via telephone)
    Bill Roberts                  [SBN]
    Points:
    1. Dale Brigham is the person for DPW who has to
    buy in to the system that the building will receive.
    2. Prior to the meeting, Dale Brigham had never seen
    the drawings or mechanical narrative for the project.
    Other people in Public Works had previously
    reviewed the drawings, without significant
    comment, but Dale had not.
    77
    3. As a rule, Dale prefers boilers and chillers to
    packaged units.
    4. Washington Air Reps and [Botting] pointed out that
    the small areas of this building that could get boiler
    and chiller systems, would only call for very small
    boiler and chiller equipment, not the large plant type
    facilities that would normally serve an entire
    building. 90% of this building is served by warm air
    heating systems in the form of PTAC units and
    packaged DX systems as allowed by the RFP.
    5. Brigham and Patterson acknowledged that warm air
    heating systems are allowed by the Fort Lewis
    Standards.
    6. Brigham acknowledged that there were numerous
    buildings on Fort Lewis that were heated by warm
    air heating systems instead of boiler systems and
    one of his greatest concerns with those buildings
    was that the warm air equipment that had been
    provided for them was from the low end of the
    quality spectrum. Air Reps stated that the
    equipment that was being proposed for this building
    was of greater quality than that. On scale of 1 to [5],
    with 5 being the best, the equipment proposed for
    this project is in the 3 to 4 range.
    7. [Botting] pointed out that the piping that a
    boiler/chiller system would require would be a
    problem because the ceiling spaces where such
    piping would be housed was already full. This
    would require us to split up an already small
    boiler/chiller system into two to four even smaller
    systems, which would probably not give the Owner
    the kind of system that was desirable, however, it
    would be in strict compliance with the RFP.
    8. [Botting] confirmed that the building[']s DDC
    system will monitor the equipment, whether it is
    packaged units, terminal units, or boiler/chiller
    units.
    10. Brigham opined that the equipment that was being
    manufactured today is not as sturdy as the
    equipment that was manufactured 20 or more years
    78
    in the past, however, he acknowledged that his
    observation applies to boilers and chillers just as
    much as it does to any other piece of mechanical
    equipment.
    11. Botting stated that the system it has proposed for
    the building makes the most sense because it allows
    redundancy, has many advantages over a
    boiler/chiller operation, such as lower maintenance
    and operations costs and a comparable equipment
    life expectancy.
    12. Brigham asked to see the most advanced drawings
    that were available showing the piping, and to see
    product data of the equipment that was being
    proposed for installation in the building, so he could
    see if he could find a comfort level with the
    proposed system. It was agreed that Botting and Air
    Reps would compile that information and get the
    entire package to Mr. Brigham by Friday,
    20 August 2004 .
    .13. Mr. Brigham agreed to expedite his review of the
    proposed system for acceptability and to provide his
    answer in the shortest possible time.
    Summary:
    • Fort Lewis standards allow warm air heating
    systems.
    • The RFP through its amendments allowed
    alternate systems to the boiler/chillerNAV
    initially called for in the RFP.
    • Batting's proposed system is a warm air heating
    system.
    • Batting's proposed system is in material
    compliance with the modified RFP.
    • If the DPW does not want to allow Batting's
    proposed system, and insists on the boiler/chiller
    direction, the boiler/chiller system provided will
    be a split system with several small
    boiler/chillers dotted throughout the building,
    unless DPW provides more specific direction.
    That system may not be desireable [sic] to DPW
    either, but it will comply with the RFP, so is
    allowable.
    79
    •   If the Owner wishes any system other than that
    proposed by Botting, they need to provide
    direction in writing of what system they want,
    and provide an equitable adjustment for the cost
    and time that a change like that will produce.
    (R4, tabs 230, 232; tr. 2/132-33; see also R4, tabs 231, 233 at 10261; tr. 2/133)
    70. In an 18 August 2004 email SBN's Roberts gave the following direction
    regarding SBN's preparation of its 65% design due on 27 August 2004:
    Just a reminder to everyone that we have our last design
    coordination meeting before the 65% submittal, tomorrow
    at 2:00 P.M. here at [SBN]'s Bellevue office. Everyone
    should have their specifications figured out by this
    meeting. Civil has completed their 100% design and it has
    been submitted. Remember that at 65% the structural
    and any mechanical or electrical underground, and
    architectural site is to be at 100%. The plan is to
    assemble everything at Jensen/Fey's office on the 26th and
    ship it out at the end of the day so that the Owner receives
    it on the 27th. [SBN] needs time to review everything for
    budget, constructability and coordination before assembly,
    to give us a window to make revisions, so we really need
    the different packages to be ready and in to us by Monday,
    the 23rd.
    (R4, tab 234) (Emphasis added) SBN's Roberts further expressed to Jensen/Fey his
    understanding that, as of23 August 2004, the government had not approved Botting's
    proposed alternative HVAC/mechanical design but that SBN was still going to include
    the alternative design, not the RFP-required design, in its 65% design submission (R4,
    tab 235; tr. 2/133-35).
    71. On 24 August 2004 Automated Controls, Botting's DDC subcontractor,
    submitted its input for the 65% design (R4, tab 236). Automated Controls is a dealer
    for Johnson Controls equipment in the Pacific Northwest (tr. 7/168-69, 11/139-40).
    We're a system integrator. So as a control contractor, when
    we come into a project, we're pulling chillers, boilers, air
    handlers, cooling towers, you have all these different
    systems, some with different protocols and we all marry
    them all into one system. That's how we kind of define it
    80
    as the brain of a building and we make them all work, talk
    to each other.
    (Tr. 7/170)
    Q:     And do you recall that the specification, the
    RFP called out a specific thermostat type?
    A:     It called out Onity or equal as the base
    system associated with I it's all one for us. It's just all one
    system.
    Q:     What was your belief about what the product
    information that you talked to, the Johnson Controls
    product, what was your belief about whether that was an
    equal to the Onity?
    A:      It was definitely I hotel system, just like in
    4
    this hotel,[3 1they have a hotel system that I I mean they're
    an equal system. So the intent was that we would bring
    ours and do a comparison of theirs. Once we walked
    around the facility, they showed us into the rooms. They
    showed us their thermostats. They went and showed us the
    front end of their system and they said it's Onity. And then
    we all sat down to review okay, how are we going to look
    at this project as a design-build. We quickly knew that the
    or equal side of that was not an option. They wanted Onity.
    They made it really clear to us they wanted Onity. I don't
    even know ifl got my [Johnson Controls] product
    submittal out of my bag to even show them at that point in
    time.
    Q:      What was the cost of the Onity products
    compared to the JCI equal product?
    A:     It's substantially more. I think they looked at
    it as a proprietary system. It was only one option. And so it
    was roughly $50,000 plus.
    Q:     So that was an impact to you?
    A:     That was an impact to WA Botting.
    34
    The hearing in this appeal was held in a hotel in Seattle.
    81
    Q:     And so what did you do after that? After you
    told it had to be Onity?
    A:      We followed the submittal process and
    submitted on _the or equal.
    Q:     Why did you do that?
    A:     We wanted it to be documented that they
    weren't accepting the or equal from the project, so there
    would be a justification for the costs associated with going
    to the Onity.
    (Tr. 7/177-79; see also R4, tab 1074; tr. 7/179-84, 205-06) The contract reserved to
    the CO the decision as to whether a proposed "equal" product was acceptable
    (finding 10).
    72. On 24 August 2004 SBN requested permission to mobilize to the jobsite
    the week of 13 September 2004 (R4, tab 21 ). The CO and Dyer were concerned that it
    might not be wise to grant a LNTP for mobilization before the HVAC/mechanical
    system design issues were resolved (R4, tabs 20-21, 242).
    73. On 25 August 2004 SBN's Roberts expressed concern to Jensen/Fey about
    the state of the specifications to be submitted with the 65% design:
    I'm really concerned about the specifications. Starting with
    the index, it is still full of items that the 35% review
    commented on and doesn't reflect all of the sections
    submitted by DCI, Patriot Fire, and SME, or has sections
    mentioned for SME that they didn't submit. Other
    specification comments from the past are not addressed
    either, nor are the sections that I listed in the index I made
    up over a month ago.
    [Roberts then listed 32 specification sections and identified
    the work needed to be performed in each.]
    It would be pretty embarrassing to submit these specs
    without these revisions being made. In fact, we won't.
    (R4, tab 237)
    82
    74. On 26 August 2004 DPW's Brigham rejected Botting's proposed
    alternative HVAC/mechanical design, directing that the system specified in the RFP be
    provided (R4, tabs 238, 241, 1031, 1033). On the same date SBN's Roberts.forwarded
    that information to Jensen/Fey and Botting:
    At this time, Mr. Dyer (and unofficially) [ORB's]
    John Patterson, think that what you have proposed makes
    sense, and that providing boilers and chillers for 10% of
    the building isn't such a great idea, however, that does not
    mean that reason will ultimately prevail. I have suggested
    to Mr. Dyer that he ask John Patterson to provide a
    statement that your system makes more sense than that
    described in the RFP, or is at least as good, because
    Patterson's opinions are very highly respected by the
    Fort Lewis engineers. That is asking a lot of Patterson,
    since he wrote the RFP, but he may be willing to do that.
    I don't know which way this will go but I suggest that you
    get all of the material together that you e-mailed
    Mr. Brigham, (plans, product data, equipment cuts, energy
    studies, etc.), in hard copy form, and anything else you
    think could help if we were to get another opportunity to
    present on your system, (particularly some drawings of
    what they would see with boilers and chillers), and be
    ready to meet with Mr. Brigham's superiors should we get
    the opportunity.
    (R4, tab 239; tr. 2/136-37) The rejection ofBotting's proposed design by The Fund
    required Botting to:
    [R]edo our load calculations and the coordination for
    getting equipment room and routing for piping for the
    boiler and chiller and the air handlers and go through that
    whole coordination process, and it was ... not ... a simple
    task.
    (Tr. 3/97) Jensen/Fey's Fritzmeier testified that:
    Well, it was a significant concern because it really
    impacted a number of things, not only the design work that
    had been done to date. Going back to a boiler-chiller
    system meant that we would essentially have to rearrange
    the entire building and eliminate some things to try to get it
    83
    to work. A lot of the amenities would go away [see
    finding 43]. And really, one of the other major concerns in
    terms of a boiler-chiller are not only the I well, the ducts
    and chases that need to be led all over the building, not
    only take up ceiling space, overhead space, but they also
    require penetrations through the floors that take up even
    more space. So we were not real happy to hear that that's
    the direction that things were going to go in.
    (Tr. 7/245-46) We find that, by making the business decision to go forward with a
    building design that incorporated Botting's proposed alternative HVAC/mechanical
    system without first getting CO approval of that design in writing as required
    (finding 32), SBN assumed the risk that the alternative design would not be approved
    and that the building design would be required to accommodate the RFP-required
    HVAC/mechanical system.
    2. 65% Design
    75. SBN submitted its 65% design to the Fund on 27 August 2004 (R4, tab 23
    at 2397, tab 24 at 2405, tab 249).
    76. On 2 September 2004, after reviewing Botting's proposed alternative
    HVAC/mechanical system again, DPW rejected the alternative design because it did
    not include the boiler and chiller design required by the RFP (R4, tabs 22, 243, 1033).
    COR Dyer notified SBN's Roberts and further stated:
    Personally, I disagree, but then again I am not the one who
    will be maintaining the system after construction is over.
    Pis. initiate design for a system as described in the RFP. I
    have instructed the Government's team of reviewers to
    terminate their review of the mechanical portion of the
    65% design package. Ifwe need to stop review of other
    disciplines as a result of this decision, pis. advise
    immediately. I have targeted 15 September to receive the
    review comments. As you know, we are hoping to meet for
    a design review meeting on/about 21 September.
    (R4, tabs 22, 243 at 10356, tabs 247, 1033; tr. 8173-76) SBN's Roberts immediately
    notified Botting:
    84
    Here is the final word from our client on the mechanical
    design for Army Lodging. Please expedite your resolution
    of this issue, and provide us a schedule for that resolution.
    Dave [Fillo], you mentioned a number of ideas that would
    provide a fairly low cost ($30K +/-)boiler/chiller solution
    for the areas that the RFP requires it in. How soon can a
    design be prepared to the 65% design level, so we can get
    it into the Army's hands for review? Please get back to me
    today with your plan, so I can let [COR Dyer] know what's
    up. Obviously we cannot let this delay the client's review
    of the 65% documents, so time is of the essence.
    (R4, tab 243 at 10355, tab 1033) Botting replied:
    I will contact Tim [Bums] and have him start making
    changes. I will forward the cost impacts of the change. The
    ceiling space on the first floor will be subject that will need
    to be cordinated [sic] with electrical, fire protection,
    plumbing and heating. My plan is to install chill and heat
    lines down the hall but only for the office area. Size would
    be 2" and 1-2" plus pipe insulation.
    (R4, tab 243 at 10355, tabs 246, 1033) SBN's Roberts responded:
    We will discuss cost impacts, as well as time impacts. It is
    our opinion that we were teamed with Botting to provide a
    design that meets the RFP for a specific cost that you
    previously quoted us. We expected each member of the
    team to accept the risk for their portion of the design, and
    we still do. First and foremost, we need an approved
    design. We couldn't even consider a discussion about
    costs, without first having an approved design.
    (R4, tabs 244, 1033) Botting's Fillo provided the following background information
    to other Botting personnel as well as comments with respect to the way forward:
    As you may be aware, for the last month Tim [Bums] and I
    have been dealing with the HVAC system at the Fort
    Lewis Lodge. Our March 31, 2004 proposal was based on
    using packaged air handler's [sic] and wall mounted heat
    pumps. 90% of the building is being heated and cooled by
    the guest room wall mounted heat pumps. The RFP called
    85
    fur a chiller/boiler system for the remaining 10% of the
    heating system. Some time last December the decision by
    [Botting] was made to use packaged units for this last 10%.
    This small remaining heating and cooling load was not a
    [sic] cost effective using a boiler/chiller system. Our
    proposal to [SBN] was specific in the use of wall mounted
    heat pumps in the guest rooms and packaged units for the
    office, lobby, laundry, maintenance guest room ventilation
    and storage rooms. [SBN] received the advantage in there
    [sic] proposal to the Army of this system. Since the first
    review, the Fort Lewis Maintenance department is adamant
    that the RFP calls for the boiler/chiller except in the guest
    rooms and that is what they want and are getting. The
    objection seems to be by the maintenance department only.
    Tim and I have come up with 3 alternate designs that
    would meet the language of the RFP but not a rational
    solution that is good for the government but does meet the
    RFP. All three of these solutions will involve additional
    cost to WAB that I feel we should be [sic] pass on to
    [SBN]. As you see from the E Mail train [sic] below
    [SBN] does not agree. Tim and I at this time are
    proceeding on these 3 alternative designs and I will put a
    number to them. I feel though we need to get a
    commitment from [SBN] that they bear some risk too in
    being the General contractor on the project and they took
    our very cost effective HVAC system to the table with the
    Army. I feel though we might have a weak hand. We
    don't have an email or document that points out that
    our proposal did not meet the RFP when we proposed
    it to them. WAB does not have e mails or documents
    that showed who made the decision to change to
    packaged units. If we go ahead and get a design done to
    the RFP and it is accepted do we have any bargaining
    advantage left? Our [sic] do we start talking then. I also
    need to address with them there [sic] design change from a
    steel constructed building to a post tension concrete
    building system. I feel that the post tension will add about
    6 hours per room. That is about 810 hours. [SBN]'s reason
    for going to post tension was the cost of steel has risen
    sharply. Post tension was a cost effective way for them to
    , build the building at there [sic] budget amount.
    (R4, tab 244 at 10358, tabs 245, 625, 1033; tr. 3/118-21) (Emphasis added)
    86
    77. On 4 September 2004 COR Dyer provided SBN with the first comments on
    "the 100% Civil package distributed in advance of the 65% design submittal" (R4,
    tabs 23, 249). SBN's Roberts forwarded the comments to Jensen/Fey, expressing
    embarrassment that the 65% design submittal was "not ready":
    These are the first comments. A large number of them
    indicate that we did not pay attention to the 35% submittal
    comments and basically were not ready with our 65%
    submittal. (Standardizing fonts margin, tabs ... , language
    not specific to this project, specs. Not relevant to this
    project, etc.) This is why we needed the submittal done
    with enough time left to review it and fix it before we
    submitted. Not only is this not encouraging, it is somewhat
    embarrassing. Do we need more manpower on this design?
    What do you propose to get this cleaned up? At this rate,
    the 65% review meeting will not go well, and we are not
    going to be in any condition to receive our LNTP or go out
    with bid packages.
    (R4, tab 249) CFSC's suspense date for completion of its review of the 65%
    submission was 15 September 2004 with the 65% design review meeting set for
    21 September 2004 (R4, tab 24 at 2405).
    78. On 10 September 2004, SME advised SBN that it had not received the
    electrical specifications for equipment and was, therefore, unable to make any
    revisions to its portion of the 65% review (R4, tab 250).
    79. On 15 September 2004 SBN notified Dyer that plans and specifications for
    an alternative mechanical re-design had been included in SBN's second 65% design
    submittal (R4, tab 26). Botting's amended alternative design for the HVAC system
    was comprised of 4 small boilers and 4 small chillers:
    [I]n order to maximize the efficiency of the building, rather
    than just providing one boiler-chiller, we'll provide
    multiple boiler-chillers throughout the building so that the
    impact on the architecture can be minimized so that we
    don't have to have huge openings of the floor and big ducts
    running under the ceiling. We can minimize the size.
    (Tr. 7/246, 3/21-22 (multiple units required smaller pipes)) This alternative
    HVAC/mechanical design was not approved, after which a third 65% design submittal
    was prepared that included a single boiler-chiller system (tr. 7/246-49, 253-54;
    87
    finding 87). The ongoing issue with Botting's alternative HVAC/mechanical system
    design and its impact on the overall building design affected all of the other disciplines
    and their designs:
    Well, there's actually quite a lot of work that goes into
    each one of those revisions because of their significant
    impact on every level. It's not just the architecture. It's all
    of the other disciplines that are impacted as well. Structural
    needs to do a revised design to accommodate changes in
    wall locations, ensure wall locations, and to make the
    structure work. Everybody needs to redo their calculations.
    The mechanical system needs to be redone. I mean
    electrical needs to be looked at, everything they're doing.
    So there's a significant impact. Every submittal, not to
    mention just needing to revise all the drawings beyond the
    engineering and architectural requirements, there's just
    revising, physically revising the drawings and doing
    another submittal and then sitting back and waiting for that
    submittal to be reviewed, responding to review
    comments .... So there is a lot of time involved.
    (Tr. 7/249-50)
    80. On 21 September 2004 Dyer told SBN that, even though the Fund was
    "reluctant to allow the start of mobilization U.ntil all aspects of the mechanical re-design
    are understood and impacts defined," they could begin the process of having two
    trailers moved from another jobsite to Fort Lewis (R4, tab 27; tr. 11172-73, 179-80; see
    also R4, tab 1034; tr. 11176-78, 230-31).
    81. In the 22 September 2004 65% Design Review Comments, COR Dyer
    included:
    "See a ceiling height of 7'-11" above the Lobby area?
    Thought we were not going below 8'-0"?
    (R4, tab 1215 atFOIA35 -31)
    82. On 23 September 2004 BCE/ORB provided comments with respect to
    SBN's mechanical system re-design (finding 79):
    35
    (See findings 231-32)
    88
    As annotated throughout our review comments, many
    elements of the RFP submittal requirements were absent
    from the package and[,] as a result, our review is
    incomplete ....
    Because the missing information is such a critical element
    in the review of equipment selections, heating capacities,
    cooling capacities, energy performance and so forth, we
    are recommending that the submittal be returned "not
    approved" until the missing information can be provided
    and the review completed.
    (R4, tabs 29, 30 at 2431-33; tr. 111118-25, 132-33, 176-80, 190; see also R4, tab 1037)
    83. The 65% Design Review Meeting took place on 28 September 2004. The
    minutes of the meeting, prepared by SBN' s Roberts, included:
    Major issues, and points covered:
    1. The mechanical re-design [#2] was not approved.
    The Owner provided direction that the mechanical
    system must be re-designed using a single boiler
    and single chiller. The design is to be submitted to
    the Owner for review on 7 October 2004. This is an
    interim submission that will occur between the 65%
    and 95% review submittals.
    2. The Owner stated that the [LNTP] will not be issued
    at this time. The Owner stated that the pre-
    construction conference is scheduled for 13 October
    2004, on Fort Lewis. Part of the purpose of that
    meeting will be to determine when the [LNTP] will
    be issued. A complete mechanical re-design along
    with the architectural, structural and civil design to
    accommodate it (see paragraph 1 above), will be
    part of the requirement for the issuance of the
    LNTP.
    24. [CO] Bartholomew agreed to issue [SBN] the
    authorization to mobilize to the site, set up its camp,
    fence the perimeter, and perform minor operations
    such as clear and grub, site demolition, silt fence
    89
    installation, etc. The letter will be issued this
    coming Friday, authorizing [SBN] to begin
    mobilizing on Monday, 4 October 2004.
    (R4, tab 253; see also R4, tab 323)
    84. Also on 28 September 2004 Botting stated its understanding of SBN's
    agreement to meet the CFSC's requirements for the boiler/chiller system as well as
    first floor ceiling height:
    The owner has insisted that a single heating and chilled
    water system is required. The domestic water heating
    system should be by itself. They asked [SBN] to provide
    extra height to the first floor ceiling space to accommodate
    the additional pipe count and sizes. [SBN] agreed. All
    required changes, calculation, [LEED] compliance
    summary, control system and sequence of operation, and
    details need to be submitted on October 4 at [SBN] to
    complete the 65% review process.
    (R4, tab 252; see also R4, tab 1038) Botting's re-design drawings, dated
    29 September 2004, included several showing corridor ceiling heights no greater than
    8'-0" (R4, tab 254). At a mechanical re-design meeting at SBN on 30 September 2004:
    [P]rovisions [were made] for the single boiler and single
    chiller system and the piping required to make it work. The
    piping was accommodated by making all corridor ceilings
    no higher than 8'-0" and by raising the second floor by four
    inches, and taking two inches off of the distance between
    the third and fourth floors.
    (R4, tab 323 at 10817; tr. 3/184-86)
    85. On 2 October 2004 SBN forwarded Subcontract Agreement No. 623902-0S
    to Botting for signature (R4, tab 261).
    86. On 7 October 2004 SBN submitted its third 65% design that included
    Botting's third HVAC/mechanical redesign utilizing the RFP-required single
    boiler/chiller system for the common areas and on 8 October 2004 BCE's Heiberg
    provided the following "short heads up comment" to CO Bartholomew and
    CORDyer:
    90
    We actually received our set of re-submittals yesterday
    afternoon. We have begun our review and we are finding
    that [SBN]/Botting have made a substantial amount of
    design progress and improvements to the mechanical
    design. I doubt if we will have more than one page of
    comments .... No controls information has been
    provided though. Hopefully they are working on that
    submittal. There could be some issues that will need to get
    worked with that discipline so the sooner we get started,
    the sooner we can finish.
    A couple of other items to think about in the meantime:
    1. I am going to recommend final or official approval of
    the 65% submittal ONLY after the missing controls
    submittal have been received and approved. There are two
    independent control systems in the project of which we
    have seen nothing yet on them. Controls are a very
    important element of the project. Their silence [in] this
    area makes me a little suspicious.
    I hope this helps. At least the mechanical systems are
    getting back on track.
    (R4, tab 260; tr. 7/79-101, 147-48) (Emphasis added)
    87. On 11October2004 BCE/ORB completed their review of SBN's third
    mechanical system re-design:
    Most of our concerns from the first 65% re-submittal have
    been addressed. The DDC system drawings, sequences,
    and specification, however, are still missing. We
    recommend the missing controls information be submitted
    for review before proceeding past 65%.
    (R4, tab 30) (Emphasis added)
    88. The Pre-Construction Conference was held at Fort Lewis on 13 October
    2004 (R4, tabs 31, 323 at 10817). At this meeting Botting' s third HVAC/mechanical
    redesign submittal for a single boiler/chiller system for the common areas was
    91
    determined to be acceptable to CFSC and SBN, as was Botting's promise that DDC
    would be "fully addressed in the 95% submittal" (R4, tab 260).
    89. On 15 October 2004 SBN submitted its revised Quality Management Plan
    in which it designated certain principals of Jensen/Fey Architects as its quality
    management organization. SBN also advised that it had "added the services of WJA
    Architects" to "beef up the QA/QC effort on the design side." (R4, tab 32;
    tr. 1/116-17, 7/250-51)
    90. On 19 October 2004 SBN again sent a subcontract to WAB for signature
    (R4, tab 323 at 10817; finding 85).
    91. On 22 October 2004 SBN forwarded to CFSC a letter from its electrical
    subcontractor, SME, on the subject of an alleged differing site condition in the form of
    existing transformer, vault and power lines running through the site. SME's Ellwood
    testified that he walked the site prior to submitting a proposal for the electrical work to
    SBN and at that time he had with him the RFP, including the drawing depicting the
    existing site conditions (R4, tab 2 at 1722). He further testified that he observed
    "[j]ust minor things." (Tr. 6/125-26, 186-91, 197-200) After contract award he again
    walked the site and testified he found nothing inconsistent with the RFP site drawing
    (tr. 6/192-96, 220-21; R4, tab 1034 at PH008) and requested contact information for
    base and utility personnel for the purpose of establishing temporary power on the
    jobsite (tr. 6/127, 196-97). During a meeting with a DPW employee, Mr. Ellwood
    testified that he was told that the existing site drawing in the RFP was not current: .
    And then he, out of his records, pulled out a drawing to
    show me his drawing of the site that showed an additional
    primary line that came across the site in connection to a
    vault in the middle of the site that we were, on our
    drawing, to remove and abandon, and it couldn't be
    because it was a primary I he stated it was something
    added later. It was called a primary cross-connect and
    could not be removed but would have to be relocated.
    (Tr. 6/129-131; see also tr. 6/198-200, 202) Upon inquiry from Judge Dickinson, it
    was determined that the drawing described as being in Mr. Buck's possession and
    allegedly shown to Mr. Ellwood has not been offered into the record as evidence by
    either party. The RFP/contract identified a primary electrical distribution line on the
    perimeter of the project site (finding 9) and a secondary electrical feeder that ran
    through the project site that would have to be rerouted (finding 36). On the basis of
    the opinion of ORB, the drafter of the RFP, that the RFP utility plan was not clear (R4,
    tab 263) and that COR Dyer testified that he learned after contract award that the
    information supplied by DPW for the RFP was not accurate (tr. 9/20-21, 73), we find
    92
    that the RFP/contract did not adequately identify the primary electrical interconnect
    (also referred to in the record as a cross-connect) that is now at issue.
    92. Contract Modification No. POOOOl, with an effective date of25 October
    2004, authorized an LNTP for construction of foundations, slag, underground utilities
    and the building structure and established a completion date of 23 December 2005
    (R4, tabs 34, 323), 425 days after LNTP for construction (see finding 54). SBN's
    Superintendent Zeman testified that it was not permitted to start any contract work,
    including site investigation, until the LNTP for construction was received (tr. 11238).
    93. As of a meeting on 27 October 2004 between SBN and its subcontractors
    regarding the 95% design, SBN acknowledged that all the guest room dimensions
    were too small and that the ceiling heights in all the public corridors were at a
    maximum height of 8'-0" (R4, tab 266).
    94. On 28 October 2004 ORB's Patterson advised CO Bartholomew that DPW
    "will not allow the primary power interconnect to remain under the building, the
    Contractor must relocate it around the building footprint per the RFP" (R4, tab 268;
    see also finding 91).
    95. SBN's Superintendent Zeman and Mr. Gonzales (QC) were on the jobsite
    full time starting on 29 October 2004 (R4, tab 268) and requested a Fort Lewis digging
    permit. The digging permit was issued on 1November2004. (R4, tab 1042;
    tr. 1/193-96,223-26)
    96. On 15 November 2004 it was reported that a gas line that had not been
    marked by PW was ruptured while a tree was being removed. The gas company
    repaired the ruptured line. (R4, tab 1044; tr. 11191-92, 196-98, 12/39-41)
    97. On 19 November 2004 SBN' s Roberts advised COR Dyer of a meeting
    on-site the previous day:
    Tom Zeman and I met on site yesterday with
    CliffHawkswood, of Fort [Lewis] DOIM, and John
    Patterson of ORB to look at the options available to us to
    solve the problem created by the differing site conditions
    associated with the existing concrete encased
    communication ducts. Mr. Hawkswood approved our
    suggested method to "lower" the ducts so they would be
    well below our designed finish grades. Our preliminary
    ROM price to accomplish that change is $45,000~00. That
    price does not include the delays that this issue has and is
    93
    creating for us. We cannot tabulate those costs until we
    have the delay behind us.
    Per John Patterson's suggestion, we will prepare a detailed
    work plan describing how we will accomplish this work
    for Mr. Hawkswood's review and comment, before any
    work actually starts. We will, of course, need the proper
    authorization under the change provisions of the Contract,
    to proceed, so we ask that Mr. Bartholomew provide us
    that authorization at earliest convenience.
    We will also need to resolve the electric primary relocation
    change, as the existing primary duct parallels the
    communication ducts all the way through the site in the
    north/south direction, and crosses the east/west
    communication duct where it ties into the communications
    manhole east of the proposed building location.
    Consequently, the communication duct conflict cannot be
    resolved unless the electric primary conflict is resolved at
    the same time. At this time, we have no contractual
    authorization to act on this changed condition, although we
    provided timely notice of the problem to CFSC, with cost
    and delay notices over a week ago.
    (R4, tab 280; tr. 11244)
    98. SBN's hearing Exhibit A-7 presents a summary chart of the critical path
    showing the contract work through which the critical path flowed, in what periods of
    time the critical path changed and delays it claims to have experienced on the critical
    path as follows:
    Dates                            Work on the critical path
    [alleged delays)
    Pre-Construction   May 2004 - 24 Oct 2004           Mechanical Design
    [Mechanical Design]
    Period l           25 Oct 2004 - 28 Mar 2005        Grading and utilities, excavation, foundation, concrete
    structure, roof systems, trade rough-in, activities leading
    to gypsum wall board (GWB)
    [DOIM and phone cable reroute]
    Period 2           29 Mar 2005 - I Aug 2005         Foundation, concrete structure, roofing systems, trade
    rough-in, activities leading to GWB, completion of the
    95% design, 100% design and mock-up room completion
    [trickle vent proposal and overexcavation]
    Period 3           2 Aug 2005 - 6 Dec 2005          Framing completion, installation of roofing systems,
    activities leading to GWB, completion of the 95% desiim,
    94
    100%design
    [framing LNTP and DDC spec resolution]
    Period 4        7 Dec 2005-4 Jun 2006           Trade rough-in, activities leading to GWB, completion of
    GWB, millwork, painting and finishes
    [mock-up resolution and portion ofelectrical durations]
    Period 5        5 Jun 2006 - 26 Oct 2006        Completion ofGWB, millwork, painting and finishes
    [mock-up, 100% design review]
    Period 6        27 Oct 2006 - 6 Feb 2007        Completion of interior finishes, punch list and inspections
    fportion offront desk modifications]
    Period 7        7 Feb 2007 - 25 May 2007        Completion of interior finishes, punch list and
    inspections, completion sign-off
    fpre-final inspection, resequence punch list]
    (Ex. A-7; app. br. at 279-81, App'x 3) Mr. Kerr, hired by SBN to review SBN's
    schedule analysis, differed from SBN' s assessment of delay days by only one day
    (tr. 7/9-10, 17-19, 32-39, 73-74; ex. A-1). The Fund's expert witness, Mr. Coffin,
    agreed "in principal" with SBN's breakdown into the eight Periods and their durations
    as listed above. Mr. Coffin did not agree with SBN's assignment of responsibility for
    the various claimed delays. (Ex. G-5) We adopt neither SBN's nor Mr. Coffin's
    assignment of responsibility for delays on the critical path in Exhibit A-7. We address
    specific alleged delays and the responsibility for them in the various sections of our
    decision below.
    99. The record contains SBN' s "Work Plan For Additional Work to Mediate
    Differing Site Conditions at Army Lodging, Fort Lewis" dated 29 November 2004:
    Primary Electric Ducts:
    Existing Condition: An underground 15KV Primary
    Electrical duct bank was found to traverse the entire site
    from Pendleton Avenue to Utah A venue, parallel to Maple
    Road, approximately fifteen feet east of it. This duct bank
    has to be relocated from the area that the new building is to
    be constructed in, as it may not be located beneath the
    building, however, the Fort Lewis Public Works
    Department requires that the tie through from Pendleton
    Avenue to Utah Avenue that was not shown in the RFP
    documents must be maintained, so the primary cannot be
    cut off and abandoned, as was the Contractor's original
    plan.
    95
    To maintain the primary electric tie through, the existing
    duct bank must be abandoned, and a new route must be
    established. The new route for the primary electrical lines
    will start at the point where the primary duct bank enters
    the site on the south boundary at Pendleton Avenue. From
    there it will be routed west, parallel to Pendleton A venue,
    then tum north parallel to Seventh Street to Utah A venue,
    where it will tum east parallel to Utah Avenue to an
    existing handhold located approximately fifteen feet east of
    Maple Road and twenty feet south of Utah Avenue.
    Relocation of Gas Lines:
    Existing Condition: There is buried existing 2" diameter
    high pressure gas line in place located in the area that is 1
    to 3 feet east of gth Street and extends the length of the site
    from Pendleton Avenue to Utah Street. In the one place it
    was exposed it was found to be buried approximately 22".
    That places it at an elevation of +271.50' +/-.
    This line passes through the area where we are installing
    the stormtech system, and the invert elevation of the lowest
    storm piping in that area is elevation +267.50'. If the gas
    line were installed deeper, in its present, location, it would
    need to be buried a minimum of seven feet deep.
    In addition to the storm sewer system conflicts, the
    existing water line that passes under the future building
    pad must be relocated to the east of the proposed building
    location. The gas line in its present location will have to be
    crossed twice by this water line, but if the gas line is buried
    seven feet deep, that should eliminate the problem of
    elevation conflicts. If the gas line is rerouted to the east,
    instead of buried deeper, that too, will prevent conflicts
    with the rerouting of the water line.
    Communication Duct Banks
    96
    Existing Condition: There arc two existing underground
    concrete encased communications duct banks crossing the
    building pad, one in a north/south direction at grid 13, and
    another in an east/west direction, diagonally from grid E to
    grid G. Both ducts tie into a concrete vault that is located
    in the future drive/parking area, northeast of the new
    building entry. A third underground concrete encased
    communications duct ties into that vault as well. This duct
    leaves the vault in a northerly direction and ties into
    another underground vault at the north side of the property,
    just south of Utah Avenue. The elevation of the top of the
    concrete encasement of the ducts that pass under the
    building pad, is +273' to +273.15" [sic]. The elevation of
    the top of the communications vault in the future parking
    area is +274.86'. The elevation of the new building first
    floor slab on grade is +276.00'. The elevation of the bottom
    of the concrete spread footings that the duct banks pass
    under is +273.50'. The planned elevation of the future
    parking lot where the existing communications vault is
    located is +273.00' +/-.The elevation of the bottom of
    swale where the duct passes through in the east/west
    orientation is +270.75'. The invert elevation of the storm
    line that the north/south oriented duct passes under is
    +268.78'.
    The Fort Lewis DOIM has approved lowering the
    communication ducts and revising the vault in order to
    allow the proposed new finish grades to work. They agreed
    to allow a variance for cover over the duct banks from 36"
    [to] 18" in planted areas, and to the thickness of the base
    course and asphalt in the paved areas.
    Removal of Telephone Lines
    Existing Condition: Several underground telephone lines
    have been identified by DPW on the site, and we have
    been advised that EDP will remove them, however,
    nothing has happened in the several weeks since we made
    contact and were advised that DPW will. The lines pass
    through the building pad in three locations, and their
    operable status is not clear.
    97
    (R4, tabs 282, 1046; tr. 2/151-53) A meeting was held on 30 November 2004 to
    discuss DSCs and mechanical changes (R4, tab 50 at 2516).
    100. By letter dated 30 November 2004 to SBN, Botting took the position that
    its originally-proposed alternative HVAC/mechanical system for the non-guestroom
    areas "met the requirements of the RFP," despite its earlier admissions to the contrary
    (findings 64, 66, 76). Botting further stated that it should be compensated for the
    additional cost of providing the RFP-required boiler/chiller system (R4, tabs 283-84;
    tr. 3/121-23, 4111-12, 60-61). SBN immediately forwarded WAB's letter, stating that
    SBN believed Botting's position "to be reasonable and to have merit" and further
    requesting "proper direction in accordance with the provisions of the Contract,
    specifically Article I-4, and I-23, for Botting to furnish the original mechanical system
    they proposed for the project, or for a change order to provide the system that employs
    the boiler/chiller assembly" (R4, tabs 285, 323).
    101. As of 1 December 2004 the Architect of Record had not reviewed the ID
    drawings 36 nor integrated them into the architectural drawings and SBN had not
    provided a complete set of 65% design documents (R4, tabs 40, 306). CFSC's
    definition of an integrated design package was "all plans and specifications, developed
    for the project to the 65% level, which includes of course, the 100% civil and
    structural, that were the basis for the [LNTP], effective 25 October 2004" (R4, tab 41).
    102. On 2 December 2004 SBN's Roberts memorialized a meeting on-site the
    previous day regarding a telephone line:       ·
    [Y]esterday we were informed by Mr. Clowers, of the Fort
    Lewis DOIM division, that the phone line that the locator
    had identified on the east end of the project, may not be
    abandoned and removed as we were previously told. That
    phone line is active, and provides phone service to the
    existing hotel that is located to the east of the site, to the
    l.G.'s office building on the north side of Utah Avenue,
    north of the site, to the Headquarters building on the south
    side of Pendleton A venue, south of the site, and to
    numerous other buildings in the area. Mr. Clowers guessed
    that the line was buried approximately three to four feet
    deep.
    36   We have found nothing in the record that defines the acronym of"ID." The Fund's brief
    describes "ID drawings" as "interior architecture material" (gov't br. at 85).
    98
    The line is located under the east end of the new building,
    and passes through the loading dock area. That area is
    scheduled to receive some of the deeper footings on the
    project. We will be excavating five feet deep for the
    footings around the loading dock so these phone lines will
    need to be relocated for us to construct the building.
    We did contact [COR Dyer] and Mr. Bartholomew
    immediately, and the fact that both of you were available
    on post, was helpful for you to see first hand, yet another
    of the previously unidentified buried utility conditions that
    we have been encountering. This is your written notice of a
    changed condition, involving differing site conditions, that
    is delaying our ability to start the foundation, utility and
    underground work on the project. Please forward direction
    from the Contracting Officer at your earliest convenience
    as to how we are to proceed with this issue. At the present
    time, this is one more issue that is delaying our work on a
    day for day basis.
    This notice will be followed by an RFI to provide us a
    reference number.
    (R4, tab 286)
    103. In an internal Fort Lewis communication dated 7 December 2004, DPW's
    Stedman provided the following information regarding "Utility Issues":
    We held a meeting to discuss the utility issues with
    the New Army Lodge. Present were Colonel Perrenot
    (presiding), Ronald Schmidt (DCA Director),
    Cliff Hawkswood (DOIM), Steve Hart (SJA Civil Law),
    Paula Wofford (Deputy DPW), Steve Glover (Chief
    Planning Division), Jim Benson (Acting Chief Work
    Management), and Gary Stedman (PW Planning).
    Natural Gas Line: At issue here is who pays for
    relocating the natural gas line that was not identified in the
    Digging Permit. Since Fort Lewis does not own the gas ·
    system, this is an issue between CFSC and the gas
    company.
    99
    The gas line was identified in the RFP (see page 3
    Section J-2 (c)[)]. "Gas: An underground gas line appears
    to run through the center of the site east to west. Size and
    capacity are unknown at this time. The local Utility is
    Puget Sound Energy."
    Underground electric line: The issue is what must
    be done with the underground electric line. CFSC has
    proposed two suggested courses of action: ( 1) change the
    line from underground to above ground. No. An overhead
    line cannot be secured. (2) build the lodge over the
    underground line. No. PW does not want the building built
    over the underground line.
    This underground line was identified in the RFP as
    an underground eclectic [sic] line that would be relocated.
    (See Site Plan, Utility Plan drawings, Section J-10). [SBN]
    was aware of the line and the requirement to relocate the
    line in the RFP. The contractor is responsible for relocating
    and paying for the relocation.
    Underground Communications Ducts: The issue is
    what to do with the DOIM communications ducts on the
    Army Lodge site. Initially DOIM agreed to have the ducts
    lowered in place (not a desirable situation, but
    acceptable), if it could be done without damaging the
    conduits and cables. Lowering the ducts was acceptable
    until it was determined the site preparation would remove
    so much surface material that existing man holes would be
    left more than 18 inches above the surface, and the
    comm[ unication] ducts too near the surface. Also, when
    DOIM approved lowering in place, it was not known that
    the ducts would be under planned water detention
    systems. Communications ducts cannot be routed under
    water detention systems. The contractor will have to
    relocate the DOIM communication ducts, cables and
    manhole.
    (R4, tab 1048; tr. 12/123-24)
    100
    104. As of 8 December 2004 SBN's sitework, utility and excavation
    subcontractor notified SBN that it was unable to proceed with its work due to "many
    underground obstacles discovered on site" identified as "electrical primary ducts, the
    communication ducts, the phone lines, and the gas line." SBN's Roberts did not pass
    this information on to CO Bartholomew and COR Dyer until 23 December 2004 in an
    email in which he further stated:
    Olympic Construction is ready to return to work with only
    one days [sic] notice, so once direction is provided, we will
    be able to respond immediately.
    (R4, tab 309; see also Bd. ex. B-2; tr. 13/5-7)
    105. The CO stated it was difficult to keep the various design submissions
    straight because SBN submitted documents "in pieces" and that none of the 35% or
    65% comments had been tracked by SBN (R4, tab 42; see also finding 107). When
    SBN's Roberts indicated that the "old 65% drawings have been developed to the 95%
    point," CO Bartholomew on 9 December 2004 explained the design submittal process
    as follows:
    [Y]ou may not understand that contract deliverables are
    just that. There have been extensive delays experienced
    because we did not get the deliverables as required by the
    contract. Quality Control is unacceptable. I trust there are
    65% electronic drawings being retained since they will
    likely be the basis for offsets if we continue to have
    difficulty getting what we contracted for.
    We want integrated 65% drawings submitted as required
    by the contract. If they are now at 95% integrated, submit
    what you will as the requirement for the 65% integrated
    drawings. We will then comment on what was to be an
    integrated 65% submission so you can then formally issue
    the 95% with our complete comments on the 65%.
    (R4, tab 43; see also R4, tab 287)
    106. On 10 December 2004 ORB's Monson reported to COR Dyer and
    CO Bartholomew a variety of government responses to the "underground" issues
    previously reported by SBN. He also reported that:
    101
    Gonzales is keeping a record of all RFl's and is tracking
    the questions and the answers; and is keeping a hard copy
    in his office of all RFI' s ....
    Gonzales is making daily reports and is filing them in his
    office. He is up to 9 December 04 on his copies. They are
    averaging 2-3 laborers out here on a daily basis. One of
    these belongs to [SBN] and the other two are either
    Olympia Construction or SME. Narratives are stating land
    stripping and grubbing; and waiting on utility
    resolution ... nothing more.
    Gonzales will have his submittal register in place and up to
    date, on information he knows about, by the end of the day
    or Monday the 13th of December. I told him lightning will
    strike him and he will die ifhe doesn't. He is tracking the
    submittal from the time the construction folks give it to
    him until he receives a reviewed answer from the
    appropriate designer or government entity.
    Aside from this ... nothing has happened on this site aside
    from minor stripping and tree removal. This has been
    going on since before Thanksgiving when the first utility
    issue surfaced.
    (R4, tab 288; tr. 11161, 65-66, 95-96) ORB's Monson testified that Jensen/Fey, as
    Architect of Record, initiated RFis which were then routed through him for
    distribution within the government; he had no authority to resolve any of the RFis
    (tr. 11116-17, 46-48, 98, 12/156).
    107. As of 15 December 2004 a re-submission of SBN's original 65%
    HVAC/mechanical design continued to create confusion as to whether SBN's
    mechanical" design included the RFP-required boiler/chiller system (R4, tabs 44, 292).
    SBN's Roberts claimed that SBN had been directed by CFSC to resubmit the original
    65% design that included Botting's alternative HVAC/mechanical design (R4, tabs 45,
    292, 1051 ). We find no evidence in the record of such a direction. After continued
    discussion between SBN, CFSC and Jensen/Fey (R4, tabs 45, 296), CO Bartholomew
    stated:
    We are not asking for anything other than an integrated
    65% document that was used for the LNTP for
    102
    construction. We must have it to deal with any proposed
    design changes and deal with the site issues we have on
    our plate at present.
    (R4, tab 296) On 21December2004 SBN's Roberts agreed to submit an integrated
    65% design that included the RFP-required boiler/chiller design as well as interior
    design (R4, tabs 46-49, 301). CO Bartholomew responded:
    I cannot understand why this is such a big deal and so hard
    to do. We have an almost $18M project that we issued an
    LNTP for based on multiple submissions and then have
    great difficulty getting it in one set for a baseline
    document. It also seems to be very difficult to track and
    incorporate the comments we made at each iteration and
    with the interims.
    (R4, tab 301; see also R4, tab 311at10775-77) SBN's architect expressed its
    understanding of what was required (R4, tab 303; see also R4, tab 311 at 10775).
    108. As of20 December 2004, two months after SBN had twice sent a
    subcontract to Botting for signature on 2 October and 19 October 2004 (R4, tab 323 at
    10817; findings 85, 90), there was still no signed subcontract agreement between SBN
    and Botting and Botting was delinquent in providing its input for the 95% mechanical
    design submittal (R4, tabs 294, 295; tr. 2/145). Also as of 20 December 2004 Botting
    stated that "to continue in the construction phase of the project [it would] need a
    contract with a contract value that reflects the equitable adjustment detailed in our
    November 30th letter" and that failure to do so would impact Botting's submission of
    95% design documents (R4, tabs 297, 1052; tr. 3/122-23). In a 17 December 2004
    internal email Botting stated that:
    Part of our leverage with the 95% docs is to stop the
    coordination process in its tracks and start effecting [sic]
    the ability of others to proceed with the project.
    (R4, tab 1052; tr. 3/123-24, 4/36-37, 55)
    109. On Monday, 20 December 2004, CFSC received RFI #17 (gas line) and
    RFI #18 (phone line), both dated Thursday, 16 December 2004, and RFI #19
    (communication lines), dated 20 December 2004 (R4, tabs 299-300, 310). Just one
    day later, on 21 December 2004 SBN' s Roberts notified SBN management personnel
    about delays associated with differing site conditions reported in RFI ##15-19:
    103
    To give you some time frames for the delays we are
    experiencing, on October 22, 2004, we provided our first
    notice about differing site conditions and delay. That
    notice was for the electric primary problem and was
    actually submitted 3 days prior to the government issue of
    the LNTP. We have furnished notice after notice, since
    then, about all five[ 371 differing site conditions, via emails,
    RFI' s, updated schedules, superintendent and CQC daily
    reports, and meeting minutes. The most recent string of
    notices were via RFI's 15, 16, 17, & 18, submitted on
    12/16, and RFI 19, submitted yesterday. Each of those 5
    RFI' s tracks one of the 5 differing site conditions issues,
    and reiterates the day for day delay we are experiencing as
    a result of them. We also distributed the meeting notes
    from the December 15th progress meeting yesterday, that
    speaks of the delays in several places. We distributed our
    updated CPM schedule at the 12/15 progress meeting,
    which showed the delays, which we discussed at that time,
    and noted in the meeting notes.
    Our files are bulging with notices. As yet, we have no
    direction on any of it, nor have we seen DPW out here
    doing something about the things that they could do
    something about, like moving the phone lines that run
    through our loading dock area, or relocating the gas line
    that runs through our storm detention area. Why we are not
    getting direction and why DPW is not taking care of some
    of these issues is anybody's guess. In the meantime, we are
    sitting here on an unbuildable and unacceptable site,
    undergoing a day for day delay.
    (R4, tab 304) The following information about the alleged differing site conditions
    was included in the 5 January 2005 Progress meeting minutes (R4, tab 318):
    Description                RFI distr.date    Other information
    RFI #15       Primary electrical duct    16Dec04           1Dec04 DPW involved; RFI
    "confirmed delay"; discussed at
    37
    SBN seeks compensation in this appeal for four alleged differing site conditions (see
    Section II below). The fifth alleged differing site condition was the potential
    for water lines to contain transite pipe at the point of connection. It was later
    determined that transite pipe was not encountered and is not now before us for
    consideration (R4, tab 460).
    104
    5Jan05 progress meeting
    RFI #16   Transite pipe             17Dec04         1Dec04 DPW involved; RFI
    "confirmed delay"; discussed at
    5Jan05 progress meeting
    RFI #17   Gas line                  16Dec04         1Dec04 DPW involved (gas line
    owned by the gas company); RFI
    "confirmed delay"; discussed at
    5Jan05 progress meeting
    RFI #18   Phone line                17Dec04         1Dec04 DOIM involved; RFI
    "confirmed delay"; discussed at
    5Jan05 progress meeting
    RFI #19   Communications ducts 20Dec04              1Dec04 DPW involved; RFI
    "confirmed delay"; discussed at
    5Jan05 progress meeting
    110. By email dated 22 December 2004, COR Dyer suspended review of
    SBN's 65% design submittal (see finding 107):
    Most of you by now realize that the recently received
    integrated 65% design submittal is NOT integrated at all.
    It does not include the mechanical system of a centralized
    boiler and chiller required by the RFP and Ft. Lewis DPW.
    Therefore, you can immediately suspend any review
    you're doing, until [CO Bartholomew] and I are satisfied
    that we finally receive a truly integrated 65% design
    submittal upon which the [LNTP] was issued. We are
    currently in discussions with [SBN] as to what should be
    included in a totally integrated design package, as they are
    having internal difficulties with understanding what they
    need to provide us before they are allowed to move
    forward to 95%.
    I apologize for [SBN]' s incompetence on the design
    process. Their Project Manager is totally inept and I am the
    first to say he needs to be removed from his '1itled"
    position on this project. I personally don't see how we can
    move this vital project forward with him at [SBN]'s helm.
    The time and energy we've wasted so far would be
    frightening to calculate! Once we clarify with [SBN] what
    is required, and receive a time of distribution, you'll be
    notified as always. It's ridiculous to think we've reached
    this point with a group that was well regarded and had
    attained acclaim on other projects.
    105
    (R4, tab 306)
    111. After several disagreements between CFSC and SBN's Roberts about the
    proper procedure for the processing ofRFis (R4, tabs 50, 307-08), CO Bartholomew,
    on 27 December 2004, sent the following email to SBN' s Henrickson:
    Our relationship is in serious jeopardy. We will in no way
    accept Mr. Roberts' statements below about RFI's and may
    ask you to have him removed from the project. He has
    been an impediment at most turns and will not pick up the
    phone and call instead of this childish behavior. Swinerton
    Corporate should be advised that our holdings of your
    stock is [sic] dropping like a rock into an abyss. I may have
    to make a formal notification that I do not want to make.
    The issue with RFI' s is we want them fully researched and
    submitted/sealed/approved by the AIE of Record I who is
    the Chief [of] your Quality Control Management System I
    not Bill Roberts. Your on-site QC for construction has also
    been of concern. We have a multi-faceted customer who
    accepts/rejects any design changes that [COR Dyer] and I
    consult/review. Ifwe had a set of consolidated and agreed
    upon 65% drawings, much of this would not be taking
    place.
    (R4, tab 50 at 2515, tab 312)
    112. The 65% design package submitted by SBN on or about 30 December
    2004 contained only drawings and was not a "complete package of drawings,
    specifications and design analysis/calc[ulations] showing the accepted design as of
    65%" (R4, tabs 313, 318 at 10804).
    113. Progress Meeting #3 was held on 5 January 2005, the minutes of which
    were prepared by SBN and included the following: SBN was awaiting direction from
    CFSC regarding differing site conditions (finding 109); the project completion date on
    the project schedule had been updated to 7 March 2006 or 10 March 2006 38 ; and, the
    RFI review process was explained (R4, tabs 318, 1055).
    38
    Both dates are contained in the minutes without explanation as to the conflict.
    106
    114. A "Site Issues" meeting was held on 10 January 2005 at the jobsite and
    was attended by CO Bartholomew, representatives from ORB, SBN, Jensen/Fey and
    SME, among others. The minutes of the meeting, prepared by SBN, included:
    1-01. Update From the Friday 117/05 Meeting between
    CFSC and the Fort I 1111/05 I Bart Bartholomew
    with CFSC provide[ d] an overview of discussion
    from the Friday 1/7/05 meeting between CFSC and
    Fort Officials. The following was provided:
    1.) Bart indicated that the gas line would probably
    be lowered. Direction may be given to [SBN] to
    proceed with this work as an added scope to the
    contract. [SBN] awaits a Change Directive from
    CF[SC] on this issue.
    2.) Bart indicated that the phone lines will probably
    also be lowered. [SBN] addressed that the phone
    lines may not be lowered, as they are under a
    footing. Further determination may be necessary for
    this issue. A Change Directive may be given to
    [SBN] for this work as well. [SBN] awaits direction
    from CFSC on this issue.
    3.) Bart indicated that Keith Henrickson of [SBN]
    and himself had previous discussions regarding the
    existing electrical duct bank. It was discussed that
    the Contractor is responsible for the portion of the
    reroute, which is shown on the SME electrical
    drawings, however the additional rerouting will be
    added scope per a Change Directive from CFSC.
    SME Electric was in attendance to confirm this
    understanding, and SME will provide the design for
    the reroute from their new transformer vault to the
    connection at Utah Street. CFSC is to include this
    direction in a Change Directive.
    5.) Bart indicated that rerouting the DOIM lines
    would probably delay the project at least 60 days
    and will have considerable cost impacts. In an effort
    to reduce these impacts, CFSC wants to present a
    107
    civil re-design to Fort Officials for consideration.
    Bart indicated that a new meeting with the Garrison
    Commander has been set up for next Thursday,
    1/13/05 at 2:00 P.M., to review such plans. See 1-02
    below for details about this exercise. Action: CFSC
    1-02. Civil Re-design Directive: 1/7/05 I Bart
    Bartholomew of CFSC has requested a civil
    re-design of the site to accommodate the existing
    DOIM ducts and vault. It was discussed that
    changing grades, drainage and some of the parking
    and driveway layouts may be necessary for this
    design change. Bart has requested that such
    re-design be provided within 48 hours of this
    meeting and made it clear that this exercise is
    additional work to the contract, which everyone will
    be reimbursed for. It was requested that the design
    be available for Bart's review by the end of the day
    on Wednesday, 1112/05 (design to be delivered to
    Bart's hotel). After reviewing this possibility at the
    meeting, Darren Simpson ofDCI Engineers
    indicated that they could probably come up with a
    re-design within this time frame. In order to do this,
    Darren has requested that top and bottom elevations
    of the duct bank be provided for this exercise.
    [SBN] will contact the earthwork Subcontractor
    immediately to start the necessary potholing£391.
    Once the potholes are dug, the Surveyor will
    determine elevation at the given locations. At the
    end of the meeting DCI, ORB and [SBN] reviewed
    the site and identified the areas where elevations
    will be provided [see, R4, tab 1056]. It is noted that
    Olympic Construction was on site to start digging
    within Yi hour of this request and the Surveyor was
    tentatively scheduled for 1111/05 A.M. to verify
    elevations. Action: [SBN], DCI Engineers
    1-03. Electrical Duct Rerouting: 117/05 I Bart confirmed
    that the existing electrical primary power duct bank
    39
    "Potholing" was described by SBN's Superintendent as hand excavation by shovel;
    "[g]ingerly trying to expose lines [horizontally and vertically] so you don't
    damage anything" (tr. 1/198-200).
    108
    will be rerouted, as necessary, to allow for the
    construction of the new building. It was confirmed
    by CFSC, [SBN] and SME[], that there is a split
    responsibility for this rerouting. The Contractor is
    responsible for the portion of the rerouting that is
    included in the SME[] design drawings and CFSC is
    responsible for the additional rerouting to make the
    interconnection from Pendleton A venue to Utah
    Street. The additional rerouting includes the portion
    of the duct bank from SME's transformer vault
    around to the Utah A venue side of the site. SME
    will provide a drawing showing the new
    interconnect arrangement. CFSC has a Contractor to
    do the work. The additional scope for [SBN] will be
    included in a Change Directive from CF[SC]. Pat
    Ellwood of SME[] suggested that relocating the
    existing cross-connect vault would save some
    money. Action: CFSC/SME
    1-04. Building Foundations: 117/05 I [SBN] indicated
    that, at this point, it is not known if the building
    foundations will have to be put in deeper than
    shown on the current design. A Geotech report for
    the site has been developed to assist in determining
    this. If copies of this report are needed for design
    purposes, it is available from [SBN]. The answer to
    RFI # 1, that provided the design for structural
    reinforced concrete bridges over the DOIM lines
    that are located directly under grid 13 was reviewed.
    That additional work will need to be included in the
    forthcoming change directive from CFSC as well.
    1-05. 65°/o Submittal Specifications: 117/05 I There was
    discussions confirming the contents of the 65%
    submittal specifications. Bart Bartholomew of
    CFSC confirmed that the 65% specification should
    include the boiler/chiller, since that system will be
    used in the new building. Bart confirmed that
    having the boiler/chiller system included in the 65%
    submittal does not give away any of the
    Contractor[']s rights in regard to the Boiler/Chiller
    Request for Equitable Adjustment, which is
    currently being reviewed by CFSC.
    109
    (R4, tab 1057; tr. 6/217-20) A follow-up meeting was held on 13 January 2005 at the
    jobsite (R4, tab 1061; tr. 11106-08).
    115. As of 14 January 2005 SBN expected direction from the Fund on the differing
    site conditions within a week. It was also reported that Botting was still refusing to sign a
    subcontract, refusing to provide any input for the 95% design and refusing to provide
    submittals until SBN "guarantees them payment" for providing a boiler/chiller system,
    whether or not CFSC agrees to compensate SBN. (R4, tabs 322, 1062)
    116. In internal CFSC, AL and DPW emails dated 18-21January2005 there is
    recognition of the incurrence of additional costs and delays to performance due to
    differing site conditions; the only question was which organization's funds should be
    used to pay for the work.
    [P]ayment for relocation of utilities misrepresented on the
    installation site plans provided in support of the Fort Lewis
    Lodging new construction project.
    Our folks/construction contractor have identified a
    redesign solution that will overcome the need to relocate
    the DOIM telecommunications trunks running through the
    proposed lodging parking area. This will result in an
    approximately $40K cost to the project for redesign and
    site work. It does however make moot the vast majority of
    the cost previously identified in utilities relocation that had
    been identified as necessary.
    Two other utilities remain outstanding. One is a
    communications line (600 pair telephone) and the other is a
    2" gas line. The gas and communication lines are directly
    impeding our contractor's ability to proceed with
    excavation work I estimated cost to relocate
    comm[unication] and gas lines is $25K. Current cost of the
    delay associated with the inability of our contractor to
    proceed is $1 OOK I some portion of this is associated with
    the time to identify the redesign solution to the DOIM
    telecommunications trunks. A separate issue (also not
    previously identified) costing about $90K is associated
    with an identified requirement to re-route and connect an
    electrical feeder (cross connect that goes around the site).
    110
    We have no choice but to absorb the redesign/site
    work (associated w/DOIM trunks) increase of $40K as a
    project cost. Similarly we are stuck with funding the delay
    costs of $1 OOK (associated with work stoppage due to all
    the unidentified/misrepresented utilities). However, as we
    discussed it seems unreasonable for the project to bear the
    total $115K cost associated with the previously
    unidentified/misrepresented communication and gas lines
    as well as to fund any requirement for back-up power tie in
    to another building when such was not represented in the
    plans the installation provided as a departure point for our
    contractor's design effort.
    (R4, tab 1064)
    117. In the 19 January 2005 Progress Meeting #4 meeting notes, it was reported
    by SBN that it was still waiting for direction from CFSC as to the differing site
    conditions and that it had been delayed in proceeding with work on the project since
    1 November 2004 as a result; SBN also noted that it was still waiting for a response from
    CFSC to Botting's 30 November 2004 request for additional compensation for providing
    the RFP-required boiler/chiller system (R4, tab 324; see also R4, tab 55).
    118. On or about 24 January 2005 Botting submitted to SBN an REA:
    In accordance with the contract and because of the
    showing it has made herein, Botting hereby requests that
    an Equitable Adjustment to its subcontract be issued in the
    amount of$579,681 for designing and installing a
    boiler/chiller system. As noted above, this request includes
    only the direct costs of engineering, labor, material,
    equipment, subcontractors, other direct job costs and
    markup. We have not included any indirect costs,
    inefficiency costs or extended duration costs.
    (R4, tab 333)
    119. On 26 January 2005 SBN's Roberts submitted three REAs to CFSC: an
    REA for Differing Site Conditions (REA 031 ); REA for Differing Site Conditions
    Delay (REA 035); and, REA for Mechanical System Upgrade (REA 014) (R4, tab 341;
    tr. 1/103, 2/162-65, 3/147-49).
    111
    a. REA 031 requested direct costs associated with twelve enumerated
    differing site conditions in the amount of$406,751 plus 32 calendar days (R4,
    tabs 335, 339). On 8 February 2005 SBN submitted a revised REA 031 (finding 124).
    b. REA 035 for delay costs claimed to be due to alleged differing site
    conditions in the amount of$259,617.00 and 92 calendar days:
    The progress of the work on site was stopped on
    1November2004, by the differing site conditions we
    encountered. The consequence of the delay has been no
    progress with any of the work on the project critical path,
    yet we have experienced extended general conditions
    expenses for each day of the delay for maintaining an on
    site staff to assist CFSC in solving the site problems, and
    to perform other administrative and managerial duties
    required by the Contract. The unfortunate aside of this
    delay is that we must request a time extension and an
    equitable adjustment for the costs that we have incurred
    as a result of it. At this time, if we were to receive a
    change order for the additional work to correct the site
    problems by the end of this week, we anticipate the delay
    to extend through Monday, 31 January 2005, which
    would be a total delay of 92 calendar days. Our extended
    general conditions have been reduced to a minimum
    during the delay period, which has kept our costs per
    calendar day down to $2,387.51 (including mark up).
    Other costs we have incurred are for the on site CQCC,
    standby time and some fixed costs for Olympic
    Construction, and a few cost increases that we have been
    apprised of by a few subs or suppliers. There are more
    escalation costs, and we will submit them separately,
    once we have the complete picture of them. We have
    enclosed a summary sheet that itemizes the known costs
    for this issue through 31 January 2005, along with a
    detailed breakdown of how we arrived at our extended
    general conditions number. The total cost that we request
    for the equitable adjustment to our Contract, ifthe delay
    were to stop and allow us to start the corrective site work
    on 1 February 2005, is $259,617.00, and 92 calendar
    days. Please cause a change order to be issued for that
    amount, or an adjusted amount if the delay continues past
    1 February, to compensate [SBN] for the delay.
    112
    Once the delay has ended, we will be able to determine
    what other impacts our subcontractors and suppliers have
    incurred due to the delay. We are particularly concerned
    about price increases, as we have received several notices
    lately regarding such increases. We will keep you apprised
    of those costs, as we receive them, and compile a
    comprehensive package of them for CFSC to provide in a
    future change order.
    (R4, tabs 334, 338)
    c. REA 014 for the provision of what it characterized as a "mechanical
    system upgrade to a boiler/chiller central HVAC system ... as requested by Fort Lewis
    DPW and Army CFSC" in the amount of $807 ,454.00 with no time extension:
    This is the mechanical system that is represented in the
    7 October 2004, interim mechanical system design
    documents. If this upgraded system is desired for this
    project, we will require an equitable adjustment to our
    Contract for the additive amount of... $807,454.00 .... The
    change has been priced using additional manpower on
    straight time to compress the work into the same time
    frame as the originally proposed system, therefore, no time·
    extension will be required to perform the additional work
    required by this change. We do, however, reserve our
    rights to a time extensions [sic] and impact costs for this
    issue, should additional future changes create impacts that
    are not ascertainable from this single change. Our detailed
    costs estimate and backup documentation is enclosed for
    your review.
    Due to the significant cost of this change, we will require a
    change order to our Contract in order to proceed with this
    additional work. We also request an expedited answer to
    this issue, as we must change the documents and revert to
    the originally proposed design if CFSC decides that they
    do not want to make the change to the upgraded system.
    Due to the fact that this issue has been before the
    Contracting Officer for more than 60 days, we ask that the
    expedited response to this [REA] be provided no later than
    10 February 2005, which is 10 working days from this
    submission. If a change order is not received by that date,
    we must proceed with the work required to revise the
    113
    documents to the originally proposed design, and move
    forward from there, in order to mitigate delays and
    minimize additional costs. Please be advised that if we do
    not receive a change order for the upgraded system, we
    will require an equitable adjustment in the $100,000.00
    range to revert to the originally proposed system, and to
    cover all of the additional costs for the multiple designs,
    and multiple design submissions that we have provided
    over the past several months, at CFSC's direction.
    (R4, tabs 336, 337, 340)
    120. The date of 27 January 2005 was set for the final design review meeting
    of the 65% design (R4, tab 53).
    121. On 31January2005 SBN's Roberts notified COR Dyer that Gonzales had
    resigned and would be replaced by David Lee (R4, tab 67). COR Dyer "demand[ed]"
    that he be afforded a one-on-one discussion with any new candidate because of the
    "many issues with the Quality Control program" (R4, tab 56).
    122. In a letter dated 3 February 2005 directly to CO Bartholomew, Botting
    offered the foliowing items to CFSC as additional inducements for acceptance of
    Batting's originally proposed alternative HVAC/mechanical design:
    Because we are confident that the packaged DX .option is
    the best solution for the Fort Lewis Lodge, we are offering
    comprehensive warranties and service on the system,
    excluding the PTAC's. This includes a 5-year warranty on
    the compressors, a 25-year warranty on the stainless steel
    heat exchangers, substantial owner training, and 1-year
    preventative maintenance service by [Botting] qualified
    personnel on the packaged units.
    Additional services available include:
    • Preventative maintenance for PTACs
    • Enhanced maintenance training materials
    (CD/DVD format, etc.)
    (Supp. R4, tabs 346, 349) We find no evidence that the offered items were included in
    any of Batting's previous proposals or designs and Batting's letter did not indicate that
    it sought additional compensation for the provision of the offered items. We find that
    the amended alternative HVAC/mechanical design offered by Botting on 3 February
    2005 was different from Batting's original alternative HVAC/mechanical design
    114
    included by SBN in its proposals. In handwritten notes dated 3 February 2005,
    Botting stated:
    - Include 1 yr Preventative Maint.
    - Packaged DX System
    - PTAC's
    - ethef
    - Forward Engineer Stamp & Narrative that we
    stand behind system & offer 1 yr Preventative
    Maintenance+ 5 yr comp. warranty and SS HE
    w/ 25 yr warranty
    (Supp. R4, tab 340) CO Bartholomew40 also made handwritten notes on 3 February
    2005:
    Urgent - [fax number omitted]
    Please pass to [Botting's] Tim Burns
    powder coat on cover
    see stainless heat exch - not aluminized
    modulating burner
    ddc - Ion works included in unit (Honeywell)
    maintenance per maintenance schedule
    on presentation package
    1 year warranty begins after acceptance
    supply all maintenance records to
    P.W. Fort Lewis
    Final annual maintenance
    completed prior to turning
    over at end of 1st year.
    [signature]                 3 FEB 05
    cc: [SBN]
    (Supp. R4, tabs 346, 348) CO Bartholomew requested additional information from
    Botting on the proposed AAON RM Series packaged units, the modulating burner for
    the make-up air units, the controller for the burners and the "compatibility for open
    protocol controls (i.e. Lonmark). The Fort uses Honeywell XL-10 for small air
    40   After comparing the signature on these notes to the CO's signature on numerous
    documents throughout the record, we find that the signature on these notes is
    that of CO Bartholomew.
    115
    conditioners and XL-15 for larger AHU's etc." (R4, tab 347) On 4 February 2005
    Botting forwarded to CO Bartholomew eleven ( 11) pages of information in response to
    questions about AAON packaged units (R4, tab 350).
    123. By letter dated 8 February 2005 CO Bartholomew advised Botting of
    concerns about its DDC proposal, stating:
    The Ft. Lewis specific question/concern is: "Is the system
    Lonworks based and Lonmark [sic] registered and can the
    contractor use Honeywell series XL 10 and XL 15 for the
    controllers?" It will be a big deal to the Ft. Lewis folks if
    these specific controllers and EMCS communications
    protocol are not provided.
    The other minor issue is to provide some specific AAON
    installations near Ft. Lewis where the base technical folks
    may go and see the packaged DX system. A few sites are
    all that is necessary since your letter indicates there are
    hundreds of installations in the region.
    (R4, tabs 352, 354)
    124. Also on 8 February 2005 SBN submitted a revised REA 031, reducing the
    amount sought as compensation for differing site conditions to $254,728.00:
    In preparing this proposal, we based our pricing on the
    assumption that it would take an additional four weeks to
    complete the site work to the point that we could restart
    our previous construction schedule, plus we included an
    additional three days time extension for the work to bridge
    the DOIM ducts under the structural columns at grid 13.
    We have now eliminated the phone line relocation and gas
    line relocation from our proposal, as CFSC requested, for
    others to perform the work, and have reorganized the
    electrical interconnect work per CFSC's request. This does
    create a greater potential for disruption of our work
    schedule by CFSC, therefore CFSC will need to pay close
    attention to expediting the work to meet our time line. All
    time extensions discussed herein are expressed in calendar
    days. The four week time extension assumption will be
    modified once we have received a written change order
    with direction to proceed with the changed work, and have
    been able to determine the total scope of the change and
    116
    the time required to complete it, and the completion of the
    Work undertaken by CFSC is analyzed.
    Another issue raised by CFSC at our 2 February meeting
    was the responsibility they felt [SBN] had for survey and
    potholing of the site to prevent or mitigate site problems
    due to unknown and differing site conditions. The reality is
    that there is no way that any Contractor could do the
    exploratory work CFSC believes should have been done
    before turning in their respective proposal. One reason is
    that the Contract does not allow any work to be done on
    site, excavation included, until a site specific SWPP and
    the EPP are submitted and approved by the Fort, and a
    digging permit is obtained. On Fort Lewis, the digging
    permit is the vehicle for obtaining utility locates, and only
    after those locates have been done, may any excavation be
    performed on a site. In addition, a Contract must exist for
    the Fort Lewis DPW to review SWPP and EPP
    submissions and issue a digging permit. Further, prior to
    the issuance of a Contract for the project, we were not
    provided a survey of the existing site, beyond the very
    limited 11" X 17" drawings that were provided with the
    RFP and accounted for in our proposal. It wasn't until
    several weeks after the Contract was executed, before we
    were provided a survey by the base. Unfortunately that
    survey failed to locate the communications lines, phone
    lines, gas lines, and electrical primary lines that have
    created the majority of the problems we have encountered
    thus far. We did confirm that the elevations of the
    topography that the survey provided were reasonably
    close, which is what then enabled us to determine that all
    of the existing lines except the phone lines, were installed
    much shallower than Fort Lewis and other code standards
    required, thus creating numerous problems for our site
    grading solutions and our structural foundation work at
    grid 13 and elsewhere. None of that information was
    available to us until long after the Contract was signed,
    therefore, there was no opportunity for us, or any other
    Contractor, to include the cost for dealing with these
    differing site conditions in our design/build offer. That is
    why the Contract contains clause 1-40, Differing Site
    117
    Conditions, which provides the means to address the items
    that we are now aware of since the inception of our
    agreement.
    Package Number la: Electrical Primary Work, No
    Cost.
    This item involves only Contract work, which involves
    intercepting the existing l 5KV electric primary at
    Pendleton Avenue, and extending it around the comer to a
    point west of the building parallel to 7th Street, from which,
    it will feed a new interconnect vault, provided by others,
    and not in this contract. From the interconnect vault we
    will feed a new transformer vault, that is part of our
    contract work, that will service the new building. There is
    no additional work involved in this item, but the
    interconnect vault that CF SC shall have furnished and
    installed by others, will now be installed in a location that
    will cause our power feed to our new transformer vault to
    be disrupted, therefore, the interconnect vault must be
    installed before we can start our electrical power work.
    Our electrical power work must be among the first work
    items to start, as soon as we are authorized to proceed with
    this change. We will also remove the existing wire from
    the existing primary power duct bank at Pendleton A venue
    to the existing interconnect vault located in the center of
    the site. We will do no work at the existing interconnect
    vault or to the existing primary duct bank and wiring from
    the interconnect vault to the north of it. SME will not
    remove the existing transformer vault that is located in this
    vicinity and reuse it as the transformer vault from which to
    feed the new lodge. A new vault will be provided for that
    purpose, and the existing vault will be demolished in place.
    The additional costs involved with this item for the
    electrical design work that were authorized by [CO]
    Bartholomew at our on site civil and electrical redesign
    meeting on 10 January 2005, have been applied to the costs
    for the interconnect work that is outlined under package
    number 11. We have been advised that DPW will pay for
    the interconnect work, and that ORB is presently
    coordinating the scope and payment issues with them.
    118
    SME Electric has provided a detailed scope and price for
    the interconnect work, and we have no problem with SME
    contracting direct with DPW. We are standing by to help
    facilitate getting the work done.
    Package Number lb: Interconnect Vault Option,
    Electrical Primary Work, No Direct Cost from (SBN] if
    the work is Contracted directly with SME Electric. If
    Contracted directly with SME Electric, their quote for
    the work is $4,615. 72.
    This is an alternate that SME Electric has offered to
    prevent the interconnect vault work from impacting the
    electrical primary installation Contract work and probably
    the project schedule. Under this arrangement, SME will
    remove and relocate the existing electrical interconnect
    vault to integrate with their electrical primary installation.
    Their complete scope of work for this change is outlined in
    the backup information attached for this package.
    Package Number 2: Phone Cable Reroute, No Direct
    Cost if Performed by a Contractor other than [SBN].
    $12,694.26 if performed by [SBN].
    In accordance with CFSC's direction at our meeting on
    2 February 2005, the work to reroute the existing 600 pair'
    direct bury cable that presently exists below the building
    footings at grid 25, and in the loading dock area will be
    performed by others of CFSC's choosing. Our previous
    proposal for this change included layout and survey of the
    reroute to miss all of our utilities and footings, including
    grade hop duties to ensure that the relocated work would
    be installed at the correct depth to not adversely effect [sic]
    any new utility installation in addition to the costs for
    Cannon Construction to do the cable reroute. CFSC will
    now be responsible for the survey, layout, grade hop,
    safety, insurance and supervision of this work. Please be
    advised that the cable material for this work may be a long
    lead item, and that the work is projected to take
    approximately one week to complete, so the coordination
    of this work with [SBN]'s work is critical to prevent
    delays, impacts and disruptions to [SBN]' s Contract and
    Change Order work. The building footings at the east end
    119
    of the building, around the loading dock and mechanical
    room area cannot be started until this phone cable reroute
    work is completed. [SBN] has provided a price of
    $12,694.00 if CFSC decides they want [SBN] to do the
    work.
    Package Number 4: Reroute Gas Line, No Direct Cost
    if Performed by a Contractor other than [SBN].
    $23, 793.31 if Performed by [SBN].
    In accordance with CFSC's direction at our meeting on
    2 February 2005, the work to reroute the existing live 2"
    gas line that is presently buried 22" deep, and traversing
    the site parallel to gth [S]treet, approximately two feet east
    of the road will be the responsibility of CFSC. This line
    must be relocated as the gas company will not allow itto
    be buried any deeper than four feet, and they will not allow
    it to be buried under pavement or site structures, such as
    our "stormtech" storm drainage structure or the truck
    access road leading to the loading dock. The gas company
    provided a time and material estimate to do this work,
    which they estimate to contain 650 lineal feet of new gas
    line. This will reroute the gas line around the new grounds
    maintenance building. The gas line subcontractor has
    stated that it may take three or more weeks to start the
    work, from the time they receive the executed paperwork
    to proceed, so we require CFSC to expedite this work to
    prevent it from impacting [SBN] 's Contract work. [SBN]
    has provided a price of $23,793.00 if CFSC decides they
    want [SBN] to do the work.
    Package Number 5: DOIM DuctNault/Site Grading
    Changes, $121,447.49.
    This change covers the work to perform the revisions to
    the site grading and drainage per the revised civil drawings
    dated 1/19/05, delta 1. The additional costs in this change
    for potholing and quantity survey work have already been
    incurred by the Contractor to arrive at the design solutions
    for this issue. The costs for this change have been revised
    because the previous proposal from our earthwork and
    120
    utility subcontractor did not contain sales tax on materials.
    The costs included in this proposal only cover the delta
    between what was previously shown for the site grading
    and drainage, and what the engineering changes changed
    the system to, with 75% of the costs of the change paying
    for the additional fill to comply with the new grading
    elevations. The Contractor's responsibility for removing
    and replacing unsuitable soil encountered in the areas of
    the changed work has not changed. If such soil conditions
    are encountered, they will be removed and replaced at no
    additional cost to the Owner, before the additional fill that
    is part of this change is placed.
    Package Number 6: RFI #1, Foundation Work to
    Bridge Comm. Ducts at Grid 13, $17,597.00.
    We have reduced the pricing for this change from
    $22, 197 .00 to $17 ,597 .00 by changing the time extension
    required to three days instead of four, and by streamlining
    some of the work items. This change covers the design and
    construction costs for the structural foundation work at
    grid 13, where the communications duct passes directly
    underneath the four reinforced concrete spread footings
    and support columns, in accordance with the instructions
    provided by the structural engineer in RFI # 1. Analysis of
    this change concluded that a three calendar day time
    extension would also be necessitated by this change, and
    the costs for that time extension are included in this
    proposal as well. The additional costs in this change for
    survey work and design engineering have already been
    incurred by the Contractor to arrive at the design solutions
    for this issue. This change is the result of differing site
    conditions, and is a compensable change under Contract
    clause 1-40.
    Package Number 7: Civil and Structural Engineering
    Design, $15, 759.00.
    We have reduced the pricing for this change from
    $16,673.00 to $15,759.00 by reducing some of the
    markups. This change pays the civil and structural
    engineers for the additional design work they provided to
    engineer a solution to the differing site issues, particularly
    121
    as they relate to leaving the existing communications ducts
    in place. All of the costs for this change have already been
    incurred by the Contractor as this effort is what provided
    the design solutions for the DOIM duct and vault
    corrective site grading and drainage work.
    Package Number 11: Electrical Primary Interconnect,
    Phase 2, No Direct Cost from [SBN] if the work is
    Contracted directly with SME Electric. If Contracted
    directly with SME Electric, their quote for the work is
    $83,313.37 and needs to be combined with Package
    Number lb, for a complete electrical interconnect
    system.
    This item covers the electrical work required to provide the
    interconnect from the relocated interconnect vault that is
    included in the electrical phase 1b work, and will be
    located west of the new lodge, next to 7th Street, then
    underground to the existing handhold located on site, south
    of Utah A venue, and then north, across Utah Avenue
    through the existing underground conduits and then up the
    existing power pole to the connection point at the top of
    the pole. It is important that all parties understand that once
    the electrical phase 1 work is started, the interconnect
    between the system on Pendleton Avenue and the system
    on Utah A venue will be out of commission and will not be
    back in commission until the phase 2 work is completed.
    DPW has indicated that they do not want the interconnect
    to be out of commission any more than two weeks,
    however, if the phase 1 work is authorized by change
    order, and the phase 2 work is not, the interconnect may be
    out of commission for a very long time. We understand
    that ORB is presently coordinating this with DPW, with
    the intention of having SME Electric do this work for
    DPW. We are available to assist ORB and DPW as
    necessary.
    Package Number 12: [SBN]'s Extended General
    Conditions for Time to Perform the Corrective Work,
    $66,850.00.
    122
    This item addresses only [SBN]'s extended general
    conditions for 28 calendar days for the additional time that
    it is presently thought that it will take to perform the
    additional work to correct the site issues to the extent that
    the work will be back to the point that it was when the.
    work was stopped due to the differing site conditions. The
    additional costs for the CQCC is included in item 8, with
    the architectural added costs for the change, and another 4
    calendar days time extension with the extended general
    conditions is included in item 6, for bridging the DOIM
    lines per RFI # 1. The entire time extension requested for
    this change is 32 calendar days, 28 for the time to complete
    the corrective site work, and four for the time to complete
    the RFI #1 additional work. We do, however, qualify this
    proposal, as we do not know the entire scope of work that
    will be authorized by the change order for this work,
    defining the total scope, we will be able to schedule the
    work accurately, and an adjustment in the time and costs
    must be made at that time, to either add or credit more time
    and cost, as the schedule dictates.
    (R4, tabs 351, 353; tr. 2/78-86, 164)
    125. On 9 February 2005 SBN notified CO Bartholomew that DPW personnel
    arrived on the jobsite:
    Disconnecting and removing wire from the existing
    underground primary power interconnect that crosses the
    site, however, we were not informed that they were
    coming, nor do we know in any detail, what it is they are
    planning on doing. (They asked us to lay their work out for
    them, but we don't know what their work is, nor are we
    receiving any compensation to supervise or lay out their
    work.)
    (R4, tab 1069) CO Bartholomew agreed with SBN that nothing should be done
    without proper coordination (R4, tab 1069).
    126. By email dated 11February2005 CO Bartholomew advised SBN to
    "Please Start Your Engines!" and that the following work was authorized:
    1. Effective ... (14 February 2005), [SBN] is authorized to
    begin all electrical site reroute work and will coordinate
    123
    other electrical work by the garrison DPW as appropriate.
    Any legitimate additional change costs for this piece of
    work shall be negotiated but the work is directed.
    2. The contractor is authorized and directed to perform the
    600 pair telephone cable reroute at a cost Not to Exceed
    $12,694.26.
    3. The contractor is authorized to perform the transit[ e]
    pipe taps, by a licensed asbestos abatement contractor, as
    proposed, for the firm fixed price of $1,922.00.
    4. The contractor is authorized and directed to perform the
    gas line reroute for a Not To Exceed cost of$23,793.00.
    Contractor is asked to coordinate this reroute to the extent
    necessary to avoid impacted site features and the new
    building. Request that unnecessarily longer reroutes by the
    gas utility subcontractor be strongly discouraged and
    coordinated with our on-site representative Mr. Bob
    Monson and/or John Patterson.
    All other requests for changes and adjustments are under
    review. Other directives and change agreements will be
    under separate cover.
    As soon as we receive a response from [Botting] on my
    8 February 2005 letter on the building mechanical HVAC
    system controls and locations of local AAON installations,
    I will be prepared to accept the proposed systems at no
    additional costs.
    (R4, tabs 32041 , 355, 1070) CO Bartholomew also formally accepted SBN's 65%
    design submission and authorized a Notice to Proceed with the 95% design. SBN's
    Roberts thanked CO Bartholomew for the direction and responded: "This is good
    news! All we need now is a decision on the mechanical system to know which
    direction to take." (R4, tabs 58-59)
    127. On 11February2005 Botting again provided to CO Bartholomew the
    information about the AAON packaged units previously provided on 4 February 2005
    41
    This copy of the document includes a handwritten notation (author unidentified)
    with an arrow pointing to the underlined words "no additional costs" and "No,
    $200,000 +/-" (R4, tab 320).
    124
    (finding 122), but it did not provide the requested information about the DDC controls
    (R4, tab 57).
    128. By letter dated 14 February 2005 Automated Controls provided the
    following information about the DDC design to Botting:
    Base Mechanical System:
    A LonWORKS registered supervisory controller that is
    tied into Johnson Controls Field Controllers. The
    supervisory controller (NAE) is a WEB based controller
    that will allow the maintenance staff to have access to the
    system through any computer connected to the network via
    use of a web browser that is password protected. The NAE
    supervisory controller also has the capability to be
    networked into the FT. Lewis EMS system for future
    connection to the post system.
    The DDC system will provide automatic control of the
    common area HVAC system[.] This includes the AHU's,
    their zone terminal units, exhaust fans and heating/cooling
    equipment.
    Hotel Room System:
    Will provide DDC control of individual PTAC heat pump
    units. System is a sub-DDC system designed specifically
    for the hospitality industry (Johnson Controls, Modular
    Room Control (MRC) system), which we can provide
    information about history, capabilities, compatibilities, and
    useful life. Each guest PTAC can be controlled/adjusted
    from a central control point in the hotel system. On-line
    monitoring/reporting can also be done from the front desk,
    in addition to providing occupied/unoccupied sensing and
    setbacks and allowing the individual guest to control/adjust
    at the guest room.
    (R4, tab 1072; tr. 71171-72)
    129. Contract Modification No. P00002, with an effective date of 14 February
    2005, was issued to memorialize the parties' agreement to the following work:
    125
    Following our many meetings and discussions the past
    several weeks, the garrison/contractor electrical/other
    issues coordination meeting Drew [Dyer] and I participated
    in via teleconference earlier today, and a just concluded
    meeting with the Chief, Army Lodging, the following
    work is hereby authorized.
    1.     Effective this date (14 February 2005), Swinerton is
    authorized to begin all electrical site reroute work and will
    coordinate other electrical work by the garrison DPW as
    appropriate. Any legitimate additional change costs for this
    piece of work shall be negotiated but the work is directed.
    2.     The contractor is authorized and directed to perform
    the 600 pair telephone cable reroute at a cost Not to
    Exceed $12,694.26.
    3.     The contractor is authorized to perform the transite
    pipe taps, by a licensed asbestos abatement contractor, as
    proposed, for the firm fixed price of $1,922.00.
    4.      The contractor is authorized and directed to·perform
    the gas line reroute for a Not to Exceed cost of$23,793.00.
    Contractor is asked to coordinate this reroute to the extent
    necessary to avoid impacted site features and the new
    building. Request that unnecessarily longer reroutes by the
    gas utility subcontractor be strongly discouraged and
    coordinated with our on-site representative Mr. Bob
    Monson and/or John Patterson.
    All other requests for changes and adjustments are under
    review. Other directives and change agreements will be
    under separate cover.
    As soon as we receive a response from W.A. Botting on
    my 8 February 2005 letter on the building mechanical
    HVAC system controls and locations of local AAON
    installations, I will be prepared to accept the proposed
    systems at no additional costs.
    (R4, tab 60 at 2546) Sometime in early February 2005 CFSC accepted Botting's
    3 February 2005 amended alternative HVAC/mechanical design using AAON
    packaged units as well as the negotiated modulating burners, powder coating and the
    126
    additional maintenance, warranty and training (R4, tab 390, ~ 2-04; see also
    findings 160, 164, 174). CO Bartholomew's acceptance of the amended alternate
    HVAC/mechanical system necessitated the submission of a fourth HVAC redesign to
    be included in SBN's 95% design submission:
    We will have to change the building back to the
    way it was originally designed, with the exception of the
    distance between floors that we changed to accom[m]odate
    the piping that the boiler/chiller system required. We will
    leave the floor heights as they presently are. We will not
    change them.
    (R4, tab 359) Jensen/Fey's Fritzmeier testified that:
    It was not particularly easy because a lot of things had
    already been set in motion in terms of other design,
    disciplines clarifying their systems, particularly structural,
    a lot of architectural design had been done around the
    layout that was required to meet the requirements of that
    last 65 percent design submittal. So going back to the
    package units, there were things that were set in place that
    needed to be accommodated with a change in the
    mechanical system.
    (Tr. 7/254)
    130. On 16 February 2005 Automated Controls, Botting's DDC subcontractor,
    informed Botting that, even though Botting had not provided it with a copy of the RFP
    as it related to the DDC, it had provided Botting with an amount to include in
    Botting's HVAC/mechanical proposal to SBN for the entire DDC system
    (tr. 7/180-181, 197-201). However, after later being provided the RFP design
    requirements, Automated Controls admitted to Botting that it had made incorrect
    assumptions:
    Project History:
    •   We quoted our standard DDC system .. .including
    [thermo]stats for the rooms but not a hotel system as
    called out in the design build spec. We were not
    given the design spec ....
    •   Dave [Fillo] and I met to figure out how to cover
    the cost of the flat spec' ed Onity Hotel System
    127
    (terms in spec also list "or equal" but after meeting
    with the Lodge personnel and review the existing
    facility they will be going with Onity).
    •   Dave and I submitted on the JC1£421 Hotel System
    (equal) with the intent it would be rejected and then
    we would request a scope change to cover the cost
    of the Onity Hotel System.
    This is a government spec and a tough one to work around.
    (R4, tab 1074; tr. 7/177-84 (even Automated Controls' proposed price to Botting for a
    non-hotel system was understated by $10-20,000.00), tr. 71197-201)
    131. On 17 February 2005 COR Dyer forwarded to the CO, DPW and
    ORB/BCE responses received from SBN/Botting regarding "the last 2 open issues
    with the mechanical design" which dealt with DDC design. DPW's response was:
    The submitted variance on the DDC Controls is
    COMPLETELY UNSATISFACTORY! DPW, Fort Lewis
    position is non-concur. The language in the RFP &
    contract spec, as well as the Fort Lewis Design Standards
    require all DDC Controls to utilize LonWorks or Bacnet
    protocol devices directly integrated into a Honeywell or
    Tridium JACE (Java Application Control Engine), which
    is a (NAC) network area controller, communicating on the
    Ethernet protocol over Fort Lewis LAN/WAN
    infrastructure for remote control and monitoring. This
    project specifies a computer workstation to be located in
    the mechanical room, with Tridium Web
    Supervisor/Workplace pro engineering software installed,
    configured and programmed for schedule, energy, log,
    alarm and database services from a single seat. The use of
    alternative control solutions is not in compliance with our
    standards or vision and will not simply "tie-in" to the base
    EMCS. Our specified system has been refined to provide
    reliable and intuitive Graphical user interfaces that do not
    require software and is accessible with a standard web
    browser. There is also a misunderstanding that Johnson
    Controls, i.e. DX-9100 are our standard. This is false. The
    42
    We understand this, within the context of the entire record, to be a reference to
    Johnson Controls.
    128
    DX-9100 actually does not meet our spec as the
    communications protocol is proprietary N2 Comm.
    (R4, tab 61) BCE's Heiberg responded:
    I hope I am not the only one that is uncomfortable with
    what is transpiring here but it seems like there is no end to
    the liberties they are planning [to] take with the RFP.
    Dale Brighams' request that the Lonworks controllers
    being furnished for the project be the Honeywell XLlO and
    XL 15 controllers seemed like a minor request in light of
    the elimination of the central boiler and chilled water
    system. Based on the [Botting] and Automated BCS
    letters, it appears they intend to use another Lonworks
    certified product instead. Related to this also, is the use of
    Non-Lon based controllers such as the AHU and UNT
    controllers. They typically use the Johnson "N2" bus over
    which they communicate with the DX9100. It appears that
    they are creatively navigating through the specs by putting
    a complicated DDC network configuration together. This
    is worrisome and may result in certain capabilities being
    lost in the shuffle. Features like being able to download a
    new program to a controller from Dale's workstation
    resulting in having to send a tech to the site with a laptop
    to reprogram a piece of equipment. Dale will probably
    want WAB to submit a network riser diagram and
    component data sheets on network equipment before being
    allowed to continue.
    Technically speaking: The Johnson Controls NAE web
    controller, in my opinion, is not equal to the Tridium JACE
    controller connected to a workstation running Tridium
    Niagra We[b] Supervisor and Workplace Pro. In fact, the
    way I read the RFP, this is a proprietary specification. The
    words ["] or equal" do not exist in this spec section.
    The 14 FEB letter from Automated goes on to explain
    future capability of being connected to the network and
    post system when according the RFP, it is a requirement of
    the project. The capabilities of the Tridium Niagra Web
    129
    Supervisor supports the feature of downloading new DDC
    programs to an individual controller, using the WEB.
    To not provide this exact system and features constitutes
    non-conformance with the RFP.
    The substitution of the Onity system with the Johnson
    MRC system raises several concerns. Is it really equal?
    Will integration of both the old and new buildings into one
    front end systems [sic] be possible? There is just not
    enough information on Johnson's solution for the
    hospitality industry. I think you are on the right path in
    having someone look into a detailed comparison of the two
    systems. I have my doubts that there is a true equal to the
    Onity system. In the following excerpt taken from the RFP,
    it is essentially a proprietary system specification as the
    contractor must "connect all new room thermostats and
    Bldg 2111 thermostat system to the relocated InnPulse
    Server, update software system as required." This is a
    performance specification that requires uniformity between
    the two building control systems that can only be provided
    with a proprietary Onity solution.
    (R4, tab 62) John Patterson (ORB) responded:
    Just spoke to Tod Smith ofONITY ... and he attempted to
    clarify his system to me.
    The short version is that the Johnson MRC digital
    thermostats proposed will not work with the ONITY
    InnPulse system. ONITY builds all their own hubs, etc.
    From my limited understanding their system runs on an
    RS45 protocol (Sensorstat DDC2) and the Johnson MRC
    stats require a LonWorks BACNET protocol to
    communicate. The ONITY system is proprietary. The new
    room controllers to be provided under the Contract must
    talk to the ONITY system which is to be relocated from
    2111 to the new front desk, we can't have two systems.
    There does not appear to be an "or equal" to the required
    t[hermo]stat.
    The RFP language is pretty specific as to what the room
    control system must do, the Contractor needs to comply
    with the RFP.
    130
    (R4, tab 63) Botting's Burrus testified that no one at Botting did an independent
    review of Automated Controls' proposed DDC submission; they trusted that
    Automated Controls was proposing a system compliant with the RFP (tr. 4/45-51).
    132. On 24 February 2005 COR Dyer sent the following email to SBN's
    Henrickson and Montoya, with a copy to CO Bartholomew:
    Ron [Montoya], I (we) need your help to find out what's
    going on with your subcontractor, WA Botting. It is quite
    simple. Either you provide us the mechanical controls
    described in the RFP, or not. It is NOT a negotiable item.
    Bart and I have gone to the mat with DPW to allow the
    use of Botting's packaged HVAC units. The conditions
    we were given to allow that are satisfied, except for the
    controls issue. I don't seem to understand why the
    reluctance on this?? If you think another meeting with
    DPW is in the cards, you're mistaken. [SBN] has been
    directed to start work anew, and from all reports, nothing
    has happened except for some coordination to relocate the
    gas and comm[unication] line. Your credibility is (to use
    Mr. Bartholomew's word) in the crapper. I could use a few
    other choice words ... you're making yourself known at the
    Base in a most negative way! We are going to have an
    uphill struggle to transfer this project to them at the end!!
    I'm tired of Hard. Let's get beyond the controls issue,
    establish a date to receive the 95% design, and please get
    busy constructing the building!
    (R4, tab 64) (Emphasis added)
    133. On 24 February 2005 SBN's Roberts prepared a summary report on a
    variety of issues. With respect to alleged differing site conditions, he reported:
    1. Electrical Primary Interconnect, Phase 1: Fort Lewis
    DPW elected to do this work, as well as the work listed for
    item number 11. They started working on it on 9 February
    2005 and look like they are going to finish the work today.
    [SBN] received direction from CFSC (Bartholomew) on
    2/11105 for the performance of this work. [SBN]
    coordinated the work with DPW, and provided layout and
    other miscellaneous services to DPW. There are no
    additional costs to the Owner for [SBN's part in this issue,
    131
    however, CFSC still needs to provide [SBNJ a change
    order for this item.
    2. Phone Cable Reroute: On 2/11105, CFSC
    (Bartholomew) provided [SBN] direction to proceed with
    this work for a not to exceed price of $12,694.26. [SBN]
    immediately ordered Cannon Construction to order the
    material and schedule the work. [SBN] has issued a
    subcontract to Cannon, the material is tentatively
    scheduled to arrive on site Monday, 28 February 2005.
    Cannon is obtaining their digging permit today, and the
    work will begin as soon as the material arrives. The work
    will take approximately 5 days to complete. CFSC needs
    to provide [SBNJ a change order for this item.
    4. Gas Line Reroute: On 2/11105, CFSC (Bartholomew)
    provided [SBN] direction to proceed with this work for a
    not to exceed price of $23,793.00. [SBN] immediately
    contacted Pilchuck Mechanical, the Gas Company's
    Contractor and ordered the work. [SBN] has issued a
    subcontract to Pilchuck, and Pilchuck is in the process of
    preparing design drawings for their crew, and for obtaining
    their digging permit. Pilchuck anticipates starting the work
    next week or the following week. The work will take four
    to five days to complete. CFSC needs to provide [SBNJ a
    change order for this item.
    5. DOIM DuctNault/Site Grading Changes: Revised
    pricing for this change was submitted on 2/08/05, for
    $121,44 7.49. These costs are for the actual performance of
    the earthwork and storm utility work that was changed by
    the civil engineer to solve the problem of the location and
    elevation of the DOIM ducts and vault. On 2111105 CFSC
    (Bartholomew) provided instructions that all other
    changes, (presumably those not covered under items 1
    through 4, above), were under review and that other
    directives and change agreements would be under separate
    cover. At this time, there has been no directive or change
    agreement issued by CFSC authorizing this changed
    work to proceed.
    132
    6. RFI #1 DOIM Line Bridges @ Grid 13: Revised
    pricing for this change was submitted on 2/08/05, for
    $17,597.00. These costs are for the additional work
    required to bridge the DOIM ducts that pass under four
    column footings at gridline 13, that the Contractor could
    not have know[ n] of when designing the building. On
    2/11105 CFSC (Bartholomew) provided instructions that
    all other changes, (presumably those not covered under
    · items 1 through 4, above), were under review and that
    other directives and change agreements would be under
    separate cover. At this time, there has been no directive or
    change agreement issued by CFSC authorizing this
    changed work to proceed.
    11. Electrical Primary Interconnect, Phase 2: Fort
    Lewis DPW elected to do this work, as well as the work
    listed for item number 1. They started working on it on
    9 February 2005 and look like they are going to finish the
    work today. [SBN] received direction from CFSC
    (Bartholomew) on 2111105 for the performance of this
    work. [SBN] coordinated the work with DPW, and
    provided layout and other miscellaneous services to DPW.
    There are no additional costs to the Owner for [SBN' s part
    in this issue, however, CFSC still needs to provide {SBNJ
    a change order for this item.
    12. General Contractor's Time Extension for the Time
    to Perform the Differing Site Conditions Corrective
    Work: Pricing for this change was submitted on 1/26/05,
    and resubmitted on 2/08/05, for $66,850.00. These costs
    address only [SBN] 's extended general conditions costs for
    an estimated 28 calendar days for the time estimated to
    perform the additional work necessitated by the differing
    site conditions changes. As is the case with the CQCC,
    which we discussed under item 8 9above0, due to the fact
    that a small part of the changed work was authorized, but
    that a large part of it has not been authorized, it is likely
    that 28 days are no longer enough to cover the additional
    time required for the Contractor's General Conditions, and
    this item will need to be increased. On 2111105 CFSC
    (Bartholomew) provided instructions that all other
    133
    changes, (presumably those not covered under items 1
    through 4, above), were under review and that other
    directives and change agreements would be under separate
    cover. At this time, there has been no directive or change
    agreement issued by CFSC authorizing payment for this
    change.
    With respect to the HVAC/mechanical system and DDC design, he reported:
    On 2111105, CFSC (Bartholomew) advised that once a
    response was received from W.A. Botting to a controls
    question and to a AAON equipment installation location
    question, he would be prepared to accept the proposed
    systems at no additional costs .... Due to all of the
    additional work that CFSC had required [SBN] and its
    designers to do to change to the boiler/chiller upgrade, it
    was not possible to provide the [AAON] system at no
    additional cost, since the additional costs [in the
    $100,000.00 range] had already been incurred.
    On 2116105, W.A. Botting's response to the two remaining
    questions regarding the mechanical system was forwarded
    to CFSC from [SBN]. That information was forwarded to
    DPW by Drew Dyer on 2/17/05 with a comment that once
    [CFSC] receives DPW's concurrence, [CFSC] will modify
    [SBN]'s contract allowing installation of the AAON
    equipment. The comments provided to Botting's controls
    response by ORB, DPW, and BCE, on 2/18/05, did not
    approve Botting's controls system, and [CFSC] has not
    notified [SBN] that the AAON equipment is to be
    installed. Since the controls system is a separate system
    from the AAON equipment, the AAON equipment could
    be approved immediately, while clarification of the
    controls system is being provided. It makes no difference
    to the controls system whether the mechanical equipment
    is boiler/chiller or DX-AAON units. Selection of the
    mechanical system needs to be made as soon as possible so
    the design work can proceed.
    On 2123105, Botting agreed that the controls system they
    were proposing had been selected by approaching the RFP
    as a performance specification, (based on project budget
    issues), not a proprietary one. Botting understands what
    134
    the RFP is calling for, and they will provide it, if they
    have to. They would like to present their case for an
    alternate system, and if after they are given a fair hearing
    by DPW, the Tridium JACE and Onity system are
    determined to be the only acceptable system, Botting
    will provide it. That being said, [SBN] still needs direction
    from [CFSC] on which mechanical system the project is
    going to go with.
    (R4, tab 1076)
    134. On 25 February 2005 CO Bartholomew and SBN's Montoya discussed
    what the CO characterized as "Bill Roberts ... continues to be the communication
    problem" (R4, tab 1077). After the call, Montoya sent the following email to the CO
    (with a copy to COR Dyer, SBN's Henrickson and ORB's Monson):
    I appreciate the insight you have given me on the project.
    As we discussed, we believe it would be in our best
    interest if I became your main point of contact. As I said
    earlier, I might not have an immediate answer for you but I
    will gather the information and provide same as best and as
    timely as I can.
    We agree that we need to resolve these items once and for
    all so we can move forward with construction and not
    continue to "carry this baggage" any longer. The process
    you described with regards to the handling of these items
    also seems reasonable. Therefore, we will prepare a
    summary of the items under separate cover and address
    how they will be resolved .... We understand that the
    information we provided previously was merely an
    estimate and that CFSC would prefer to reimburse us for
    the actual costs incurred. We will prepare the information
    in such a manner that will facilitate a coc43 1 being issued to
    us, which will allow us to authorize our
    designers/subcontractors to commence with the Work
    immediately.
    (R4, tab 1078)
    43
    We understand this, in this instance, to be an acronym for "change order."
    135
    135. On 2 March 2005 COR Dyer provided the following information to
    CO Bartholomew:
    Here's what I can address from the March 1 telephone
    conversation with Mr. Montoya:
    1.     Mr. Montoya affirmed that the HVAC mechanical
    equipment controls will comply with the RFP and be
    compatible with the Ft. Lewis DPW computer and
    interface programs. This was the last condition yet to be
    satisfied by [SBN] and their mechanical subcontractor for
    the AAON packaged mechanical equipment. Therefore, all
    8 conditions imposed by DPW to gain their approval of
    [SBN]'s approach to heating and cooling the common
    spaces has been satisfied. Pis. direct [SBN] to move
    forward on the now accepted mechanical design, using
    AAON [HVAC] equipment, manufactured exclusively for
    the FLW Lodge. No other manufacturer's equipment will
    be accepted or approved for substitution.
    2.     [SBN] should now direct the Architect and
    Engineers to prepare and deliver us a 95% design. There
    are no other outstanding issues (to my knowledge)
    precluding the 95% design moving forward post haste. Pis.
    have [SBN] provide me a proposed submittal date for
    planning purposes.
    3.      [SBN] is delinquent of initiating any site work
    associated with their electrical work and the redesign work
    necessitated because of the telecommunications duct
    banks. I hereby ask you once again direct [SBN] to man
    the site and get busy on their underground electrical, work
    associated with the redesign of the parking lot, porte
    cochere, drainage, etc., and laying out the work for
    foundation excavations (the foundations were released
    with the limited NTP, effective 25 October, 2004 ) .... All
    site work shall commence in earnest as I thought we had
    done with your previous directive (effective 14 February).
    Since [SBN] has trouble with using email for contract
    direction, I suppose a "hard" modification is in order. Pis.
    include in the mod a negotiated settlement for the design
    effort already expended to leave the DOIM duct banks in
    136
    place. I want to pay for those services rendered. In my
    view, the +$15k for that task is not unreasonable.
    Ron and I agreed to begin the effort of resolving the delay
    and contract time issues soon. I will be coordinating a
    West coast visit with you and Ron in an effort to get this
    accomplished. The black cloud over this project has got to
    be removed; reaching a settlement on the delay and time
    extension will (I believe) remove most of the cloud.
    (R4, tab 66)
    136. On 2 March 2005 SBN's Project Manager Roberts' base pass was
    rescinded (R4, tab 169 at 3269-70; tr. 2/160, 3/151-52, 8/88, 9/98-101, 134-36,
    11/21-23).
    It was totally out of the blue actually. Cindy Moinette from
    the hotel and Bob Monson came over to our trailer, and
    this was on the 1st ofMarch. And Cindy explained that she
    had gotten a call or an email or something from Drew Dyer
    telling her to go pull my pass and have me get off the
    base .... Tom Zeman and Tim Hanson were there.
    I told her and Monson that I wouldn't turn over anything
    until I had an opportunity to talk to my office .... Well, I
    talked to my office and the next day Cindy came over and
    said that Dyer was apoplectic about the whole thing and
    was going to call the MPs and have me arrested and
    escorted off the base. She was pretty upset, so I just gave
    her my pass.
    [After they took the badge] I met with my team,
    Tim Hanson and Tom Zeman and I would meet almost
    every other day for coffee in the morning in a restaurant
    off base. And just talk about what we were going to do that
    day.
    And subcontractor meetings that we had previously
    had onsite, Botting had an office with a meeting room in
    137
    downtown Tacoma that they let us use. So we would have
    subcontractor meetings there.
    [SBN] had another project at Tacoma Community
    College and they had a meeting room so we could have
    meetings there. But it became just too cumbersome.
    I mean we actually had to have subcontractors from
    the project, off the project half an hour away to have
    meetings and go back. And it just kind [of] watered down
    everything. So pretty much, it was pretty unworkable so I
    found another job ... [in] mid-May ....
    (Tr. 21166-69) SBN's Roberts and Montoya both testified that they have never gotten
    an explanation from CFSC as to why Roberts' badge was rescinded (tr. 2/168, 171-72,
    3/154, 155, 158). Ms. Moinette also testified that COR Dyer never gave her a reason
    for taking Mr. Roberts' base pass (tr. 12/27, 42). Upon an invitation from Judge
    Dickinson to expand on this subject, Montoya testified that:
    The only thing that I could discern from my
    observation of the interaction between the two, is that there
    was a very strong personality conflict[] between the two,
    and I don't know, it was two personalities that they
    couldn't get to mesh.
    [Roberts] didn't really have many issues with other
    people, but he did rub [Dyer] the wrong way, but I didn't
    know what the hot buttons were of [Dyer], that [Roberts]
    was hitting.
    I couldn't see them, but I knew [Dyer] would
    always get upset, and on occasion, [Dyer] would get upset
    with me, personally, as well, very upset, and to the point
    where he would raise his voice and argue with me, but I
    didn't argue back.
    Once he realized I wouldn't engage, he would
    apologize to me, and his voice would calm down and we
    could continue on with the discussion, and I would just let
    him vent.
    So, I don't know if I knew how to manage his
    personality a little bit different, but even what I said at a
    point sometimes, pushed his buttons, but I guess because
    of the way I dealt with him, and did not get excited about
    his disposition, I guess that seemed to be the way to
    manage [Dyer].
    138
    Q [Judge Dickinson]:         So, I understand you to
    say that the issues that you were aware of, you viewed as
    personality conflict and not anything more that you could
    point to, specific situation or something?
    A:     I didn't see anything where [Roberts] had
    done anything to antagonize the relationship, in any
    manner, where he produced anything that was antagonistic
    or made accusations to [Dyer] or anything like that.
    But there always seemed to be tension between the
    two. A lot of times, even when [Dyer] would first enter a
    room with us, and even just being myself, there always
    seemed to be tension, and I don't know what brought that
    on, that tension.
    Eventually, I learned how to deal with [Dyer] and
    could try to get him to calm down, and I think he got more
    comfortable with me, that I was wanting to listen, to see
    what he was saying, and that he would approach me a little
    bit, more relaxed, but if I said, and I couldn't tell you what
    the trigger word was, but if I said something at certain
    times, he would go off on the deep end and get upset and
    start yelling and arguing and I'd just let him vent it out and
    then, pull the phone away from my ear a little bit, and then
    when he got calmed down, I said, "All right, are you
    read[y] to get back to the conversation," and more often
    than not, he would apologize for his outburst and say,
    "Yes, let's talk about it.["]
    (Tr. 3/158-60; see also tr. 3/171-73) COR Dyer testified:
    Q:     What did you hope to achieve with
    Mr. Roberts being removed from the project?
    A:     I wanted personally, to achieve a more
    favorable working relation environment so that we could
    get the project done on time and with quality, and
    preferably within our budgetary range. That was my goal.
    Q:     And did that occur?
    139
    A:      It, ... wound up not occurring. But the folks
    who came in after Mr. Roberts' departure were more
    inclined to understand the design-build process and
    became very focused and work~d things the right way.
    Mr. [LaSharr] came in, was a very determined
    individual, to try to set the course, chart the course a
    different direction. But we certainly didn't meet our
    schedule. The budget, I think we got real close to the top
    end of the contingency and, but I think it was a more
    positive step than have to deal with Mr. Roberts for the
    balance.
    (Tr. 8/88-89)
    137. On 8 March 2005 CO Bartholomew provided the following direction by
    email:
    The 95 percent design shall be completed with all due
    haste. All issues shall be coordinated directly with [COR]
    Dyer.
    Proceed with all redesigned site work. Costs will be
    negotiated or reimbursed based on actual costs.
    The mechanical system proposed and accepted at no
    additional costs shall be used in construction.
    Proceed with all appropriate construction. This is a blanket
    directive.
    No changes have been denied- only costs and entitlements
    requested deferred until we can meet face-to-face.
    Coordinate all work with Bob Monson on site and
    communicate everything with [COR] Dyer.
    I did not intend to leave anything out of this directive.
    Proceed post haste and let's get this new Army Lodge built
    as a Team!
    (R4, tab 169 at 3512)
    140
    138. On 10 March 2005 SBN's Roberts advised COR Dyer and
    CO Bartholomew that the telephone line reroute work would require additional time
    and cost because it was discovered that it was not direct-buried but encased in steel
    pipe (R4, tab 357).
    139. In emails dated 9-10 March 2005 COR Dyer advised SBN' s Montoya that
    he did not recognize Roberts as SBN's Project Manager (R4, tab 169 at 3272,
    tabs 357, 1079-80; tr. 31155-58, 10/117-19). There is no evidence that SBN objected
    or otherwise challenged CFSC, in writing or otherwise, on the subject of rescinding its
    Project Manager's base pass (tr. 11111-12, 212-14). ORB's Monson, CFSC's on-site
    representative (finding 6) testified that he did not notice any difference in SBN's work
    on the project as a result of Roberts absence because work at the jobsite was not that
    far along and there wasn't much work to be impacted (tr. 11123, 28-29, 80-81).
    Nevertheless, SBN now claims that the removal of Roberts from the jobsite had a
    "[t]remendous impact on SBN:
    [W]e lost all that history. We had moral[e] issues. Our
    subcontractors all of a sudden, they get very upset when
    you change person[nel] in the middle of a job. Especially a
    job that's got a few pending issues like this one. Our
    superintendent ended up quitting over this [see,
    finding 157]. So it was a tremendous impact to the
    company, to the project.
    [On a normal project, it would typically take] [t]hree or
    four months minimum [to get a new project manager and
    new superintendent up and running. And this] was not [a
    normal project].
    (Tr. 11113; see also tr. 11215-16, 220-21, 239)
    140. As of 17 March 2005 SBN's architect expressed concern about the status
    of the mechanical system to be used in the 95% design submission (R4, tab 362 at
    11250). SBN's Roberts replied that:
    The mechanical redesign is still a question mark, as
    [Botting has] not committed to a date, and their proposal to
    change the make up air system [see, finding 145] could
    slow up structural and/or architectural design, along with
    the mechanical design.
    (R4, tab 362 at 11249; see also R4, tab 71 at 2577-78, tabs 363, 365-66)
    141
    141. On 21March2005 after being informed by ORB's Patterson that SBN's
    Roberts was at the jobsite that day (R4, tabs 1082-83; tr. 10/120-21), CO Bartholomew
    informed Patterson and COR Dyer by email that:
    I will send an e-mail to appropriate authorities that
    identifies Mr. Roberts as an objectionable employee and
    possible security threat to Ft. Lewis and seek to have him
    denied access. He can appeal and I will be happy to
    respond to the Garrison and/or Corps Commander. They
    will have to take responsibility for him if he is
    subsequently allowed access to the installation.
    (R4, tabs 368, 1083-84; tr. 9190-92; see also tr. 10/123-27) COR Dyer responded,
    with copies to Monson, Patterson, Cindy Moinette and DPW's Stedman:
    I have informed [CO Bartholomew] of Mr. Roberts'
    blatant disregard of his disbarment from the Installation of
    Ft. Lewis. He and the person who allowed him access
    today are in big trouble. How he got on the jobsite today is
    beyond me. Anyway, ifhe shows up again, pis. summon
    the military police discreetly and explain that an
    objectionable person who is a security threat has been seen
    on site and must be immediately escorted off the premises.
    I am not going to put up with this, nor should anyone
    associated with the project.
    (R4, tabs 369, 1084; tr. 9/91-94, 98-100) When referred to contract clause I-35
    (finding 26), COR Dyer testified that:
    I believe that Mr. Roberts did not fulfill sentence
    number one, experienced, responsive and capable.
    Q:     And Mr. Roberts was never provided any
    reason in writing whatsoever that he was inexperienced,
    irresponsible or incapable of performing the project. Isn't
    that correct?
    A:    I do not know. I am not the contracting
    officer.
    Q:      Okay. And you testified a moment ago that
    you didn't believe and didn't agree with [CO]
    142
    Bartholomew's characterization of Mr. Roberts as being a
    national security threat, correct?
    A:     I do not believe he was a security threat, no.
    (Tr. 9/97-98; see also tr. 9/134-36)
    142. On 22 March 2005 Ms. Moinette expressed concern to Steve Coulson,
    Chief of Army Lodging Operations:
    I am very concerned about the issues we have with
    [SBN] and moving forward with the new lodge. I do
    not want this project cancelled I Ft Lewis Soldiers and
    families need the additional lodging. This is the focus
    we all should be working to achieve. Mr. Roberts,
    Project Manager for [SBN] has caused many delays
    and problems with the project. Drew wants him off the
    job and is supported by Bart. [SBN] need[ s] to make
    this happen. I have pulled Bill Robert[ s]' s pass and
    auto sticker and he still managed to get on post and the
    job site yesterday. I feel Bill should respect Drew's
    action of having his pass pulled until the meeting
    scheduled 18 Mar with Bart, Drew and [SBN].
    Hopefully some decisions will be made and finalized. I
    do not believe Bill Roberts is a security risk I but he
    has certainly caused problems for Drew and the project
    moving forward.
    (R4, tabs 370, 1085) Coulson responded:
    The [SBN] [REA] meeting that was scheduled for next
    week is contractual negotiation that has no bearing on the
    work which was directed to begin on 14 Feb 05; if you're
    not seeing significant evidence of site clearing, survey
    stakes, excavation and utilities re-route, please inform
    Drew ASAP. Our Contracting Officer, Bart, requested
    postponement of the [REA] review meeting due to both
    personal and professional obligations that must be
    addressed 28-31 March. I'm anticipating receipt of the
    95% design NL T 1 April and would expect a side bar for
    contract resolution during an on-site review sometime the
    week of25 April 05. The Project Manager personnel issue
    143
    was resolved in Jan 05; however, it appears as though Bart
    needs to issue a written directive.
    (Id.)
    143. As of 22 March 2005 the gas line subcontractor advised that it was still
    waiting for a digging permit from Fort Lewis (R4, tab 367).
    144. On 25 March 2005 ORB's Monson forwarded the following information
    to Dyer, Patterson, Bartholomew, Stedman and Moinette:
    Drew ... as you requested of me I talked to Gary Stedman
    whom in tum talked to a Larry Freeman, Head of Physical
    Security Fort Lewis, yesterday; and this is what
    Mr. Freeman told Gary:
    An individual having access to Fort Lewis can only be
    barred entry due to the committment [sic] of a crime or
    other violation. (I nor Gary know what "other violation"
    entails.) According to Mr. Freeman, the original sponsor
    (Cindy) [Moinette] can remove or take possession of an
    individual's ID pass card and vehicle sticker so he cannot
    obtain entry. If he gets another pass through other
    temporary means then the original sponsor can have the
    MP' s come and take his ID and vehicle passes again and
    escort him off the base .... According to Mr. Freeman, the
    "list of undesirables" at the main gate guard house is for
    those individuals that have committed a crime or "other
    violation".
    (R4, tabs 372, 1095; tr. 9/101-03)
    145. On 30 March 2005 SBN "showed up with ... a proposal for 'trickle vents'
    rather than tempered forced air ventilation" (R4, tabs 69-70, 1088). 44 Botting
    represented to SBN that the trickle vent system met both code requirements and RFP
    requirements (R4, tab 70 at 2573, tab 1092). Botting's Bums testified that the trickle
    vents were proposed with ''the intent ... to simplify the system ... , eliminating a couple
    of fan systems and all the duct work that had to compete for space going down the
    corridors" (tr. 3/97-98; see also tr. 4/13, 37-39, 52-54, 68, 7/258-60). SBN's Montoya
    44
    SBN had already expressed its belief several weeks earlier that this proposal could
    further delay "structural and/or architectural design, along with the mechanical
    design" (finding 140).
    144
    forwarded the proposal, requesting that it be approved so it could be included in
    SBN's 95% design submission (R4, tab 70 at 2572, tab 1092; see also R4, tab 375;
    tr. 3/175-80, 51126-27). The ORB/BCE team provided same-day input to COR Dyer,
    the bottom-line of which was that, while the trickle vents may meet code requirements,
    they did not meet the RFP requirements to provide "forced, tempered makeup air" as
    well as positive pressure ("overpressure") makeup air in the guest rooms which was
    considered important (R4, tabs 69, 1088).
    146. On 6 April 2005 Jensen/Fey notified ORB's Monson that it had requested
    layout information for electrical, interior equipment and furnishings from CFSC in
    November 2004 and, to date, had not received the information which was essential to
    ordering long lead time items (R4, tabs 1096-97). Monson followed up with CFSC on
    13 May 2005 (R4, tab 1108).
    147. SBN's proposal to use a trickle vent system was rejected on 7 April 2005:
    Your idea was reviewed by ORB and Ft. Lewis [DPW].
    Both groups came up with basically the same comments.
    The simple vent does not provide what is specified in the
    RFP, that a constant volume of air is introduced to the
    guest rooms creating a positive pressure. Other reasons
    include:
    a.      Concern about moisture being introduced into the
    room through the vent and wall structure. Could cause
    conditions to promote mold growth.
    b.      In the winter, the vent will present an avenue for the
    introduction of cold air directly into the room, making it
    uncomfortable for occupants.
    c.      Concern about wind and traffic noise introduced
    into the rooms. Also, the amount of fresh air introduced
    will vary during high or gusty winds.
    d.      While the idea does meet code, we think it is a
    cheaper solution. If you really wanted to sell the solution,
    an equitable credit should be offered. Depending upon the
    amount of the credit, we could then go about solving the
    perceptions of the above potential issues.
    Any overtures to discuss this further shall be directed to
    me.
    (R4, tab 70 at 2574, tab 379; tr. 3/180-82, 4/14-15, 41-45, 51127-28, 9/177-78) SBN's
    Montoya agreed on cross-examination that a trickle vent system "is not a central
    145
    ventilation system" (tr. 3/252). SBN's expert witness, Mr. Kommers, agreed
    (tr. 3/23-245, 27-29, 63, 65-70).
    148. On 13 April 2005 Botting advised that, without the trickle vents it had
    proposed, the HVAC system did not meet the required DoD Antiterrorism standards
    and further:
    We will continue to move forward with the trickle vent
    concept as it would be irresponsible to proceed in any
    other manner. As previously stated, we have an obligation
    to provide a mechanical design that complies with the DoD
    standards that are intended to keep the occupants safe from
    terrorist activities.
    (R4, tabs 389, 1090; tr. 4/15-18)
    149. Items of note discussed at the 13 April 2005 Progress Meeting #7 were:
    Old Business
    1-03. Existing Telephone Lines: 4/13/05 I This work has
    been completed, as directed by CFSC. It is noted
    that it was necessary to work an overtime night shift
    in order to complete this work due to an additional
    unforeseen condition associated with the existing
    telephone line. Upon excavation of the existing line,
    it was discovered that the line was not direct bury
    cable, but instead was encased in steel pipe. This
    changes the scope of work, as it will now involves
    [sic] a cable changeover after hours (at night). This
    work involves cutting the pipe, removing it and
    disposing it. Upon discovery of this unforeseen
    condition, SB[N] notified CFSC about the
    additional work. They were notified that the costs
    associated with the work would be $2,200. In a
    good faith effort to get the work finished, SB'[N]
    proceeded with the added scope. SB[N] expects full
    compensation for the additional costs ($2,200 in
    addition to the previously submitted amount of
    $12,700). SB[N] still awaits a change order from
    CFSC for this work ....
    146
    1-04. Primary Electrical Duct Location: 4/13/05 I The
    primary electrical relocation has been completed.
    This item will be removed from the notes ....
    1-05. Existing Unmarked Gas Line Relocation: 4/13/05
    I This work has been completed, as directed by
    CFSC. SB[N] still awaits a change order for this
    work. ...
    1-06. Existing Communication Ducts: 4/13/05 I SB[N]
    still awaits a change order for this work. It is noted
    that some of this work has proceeded (i.e. work
    associated with RFI # 1 for duct bridging) and
    SB[N] expects full compensation for the added
    work. ... The CFSC position of this request is that
    is non-compensable.
    1-09. Schedule Update: 4/13/05 I The current overall
    schedule update, as well as the 4-week look-ahead
    schedules were distributed for review and
    discussion. It was discussed that the Substantial
    Completion date on the current schedule update is
    May 4, 2006. It was also discussed that all of the
    schedule impacts are being tracked on the schedule.
    It was noted that there will be impacts to the
    schedule with regards to the underground
    conduit/piping if the Owner does not provide the
    required information necessary to complete the
    design. Pending information has been submitted in
    RFI's #35 and #40. CFSC has not made any
    contractual changes to reflect a revised contract
    completion date. Therefore no impacts are
    capable of being tracked. Owner has requested
    full-size, scaled, clean, design plans to be able to
    answer the questions posed on the RFl's.
    2-04. Boiler/Chiller Design Change: 4/13/05 I CFSC
    has indicated that the original proposed system
    would be used on the project. However CFSC has
    not acknowledged or accepted the additional costs
    141
    associated with the boiler/chiller design, and then
    the redesign back to the original system. SB [N] still
    awaits a change order from CFSC for this
    additional work. CFSC position on this is that all
    costs incurred to comply with RFP are
    non-compensable.
    2-07. 95%, Design Submittal: 4/13/05 I It was discussed
    that once the Trickle Vent System has been
    reviewed and accepted by CFSC, the 95% submittal
    date can be established. SB[N] will advise of this
    date when it is established. CFSC has rejected the
    trickle vent system.
    5-01. Resolution and Change Orders: 4/13/05 I It is
    SB[N]'s understanding that Drew Dyer and/or Bart
    Bartholemew [sic] of CFSC will be in town
    sometime the week of 4/25/05. At this time there
    will be a meeting to discuss and resolve all of the
    outstanding change order issues. It is noted that
    most change order issues have been outstanding for
    several months. CFSC has not even issued change·
    orders for the items and costs they accepted and
    gave direction on almost three months ago. Change
    Orders must be issued so the appropriate parties can
    be paid for all of their additional efforts. Mr.
    Bartholomew has the action on items he directed.
    He is not attending this week's progress meeting.
    All other outstanding changes or alleged changes
    will be negotiated at a yet unscheduled date.
    The next Progress Meeting will occur April 28, 2005 ....
    Notes prepared by [SBN's] Tim Hanson
    CFSC comments prepared by Drew Dyer
    (R4, tab 390)
    148
    150. The parties continued to discuss the issue of trickle vents (R4, tabs 391,
    1092; tr. 3/179-80). COR Dyer denied the use of trickle vents "once and for all"
    and SBN' s Montoya responded that SBN planned to go forward with them in its
    design (R4, tabs 396, 1094). As of 19 April 2005 SBN's design was not yet
    complete and Botting was still asking about areas/items to discuss/redesign (R4,
    tabs 393-95).
    151. On 22 April 2005 SBN's Roberts reported to SBN's Montoya, Hanson
    and Zeman that on-site subcontractors were reporting "a significant amount of
    overexcavation for our footings" (i.e. more than six feet deep) and that SBN should
    report it to CFSC as a differing site condition:
    I would do that, but the ridiculous conditions we are
    working under on this project because of CFSC's
    improper actions in regard to my pass and position,
    prevent me from doing what needs to be done. So, I will
    provide you with the information you need to start the
    ball. Unfortunately, this information is second and third
    hand, because I have not been able to personally observe
    the conditions, determine the quantities involved, or
    discuss the issues first hand with the majority of the
    participants.
    Fortunately, for both [SBN] and the Owner, depending on
    who pays for it, the geotechnical engineer has determined
    that the existing unsuitable material that has to be
    overexcavated, is only unsuitable because it is loose, so
    that same material can be placed back in the overexcavated
    footings and compacted to 95% density. This reduces the
    need for imported structural fill.
    We are encountering buried piping that was not shown on
    the information furnished us by the Owner or marked by
    locates done for the digging permits, and that the trench
    lines that those pipes were buried in are filled with
    unsuitable material that we have to, at a minimum, remove
    and either replace or recompact to achieve suitable density
    149
    for bearing. That too, is a differing site condition that
    should be held to the Owner's account.
    (R4, tab 169 at 3766-67, tabs 397-99, 1093)
    152. On 23 April 2005 both CO Bartholomew and COR Dyer advised SBN
    that its Quality Control Management program managed by Jensen/Fey was not being
    implemented as required by the contract (R4, tab 1098).
    153. On 25 April 2005 ORB's Monson provided input to CFSC for a response
    to SBN about over-excavation:
    Disagree with the term "significant" and" ... most of the
    excavations .... " One has to look at the overall project to be
    able to define the extent of "over excavations". At the date
    of this RFI [#42 (22 April 2005)] it is true the Division
    One contractor is experiencing excavations below the 6
    foot line along Grid lines Q and R from column line 24 to
    approximately 14. It is expected that this will hold to be
    true along the entire[ty] of Grids Q and R.
    "Over excavations" must be evaluated on the basis of all
    footing excavations, when completed, for this project.
    (R4, tab 1099)
    154. As of27 April 2005, SBN was aware that Botting's last-minute proposal
    to use trickle vents was holding up completion of the 95% design submittal:
    I have now seen three written rejections from Drew Dyer
    of the trickle vent system, and nothing from Botting for us
    to relay to Drew, that offers the credit he has requested.
    I'm not sure that Botting understands that until it is
    determined which way we are going, i.e., trickle vent, or
    ducted make up air, we cannot complete our 95% design
    submittal. This is the only item that we need resolution on
    to release everyone on the design, and we cannot release
    them without this decision. The trickle vent decision
    affects the building footprint at all four floors and the
    roof. It affects the electrical design, and the fire
    sprinkler piping. It affects partition types and chase
    locations on all four floors. No one can make the changes
    to the drawings that are necessary to accomodate [sic] the
    150
    trickel [sic] vent, until we know which system we are
    using. It is the single largest issue on the project, and
    has been for a month now. [Botting's] Burrus will not
    return my calls or my emails. We have written direction
    from the Owenr [sic] to provide the gas pack system we
    originally proposed, with ducted make up air to the guest
    rooms. If you can't get Burrus to respond with a credit so
    we can get approval from Drew for the trickle vent, then
    we are going to have to tell all the designers to proceed to
    95% with the original system. The issuance of the 95%,
    submittal is critical to getting this job bought out, and
    to preventing it from stopping because we don't have
    the subs and materials to continue the work beyond the
    structural phase.
    (R4, tabs 403, 1094) (Emphasis added) Botting did not believe a credit was warranted
    (R4, tab 404), and on 29 April 2005, Botting again expressed its intention to include
    the trickle vent design in the 95% design submission despite the express disapproval of
    it by COR Dyer (R4, tab 405):
    Ron Montoya is working behind the scenes with Bart and
    Drew to get them to accept a credit and the trickle vent
    concept. I am somewhat hopeful that there will not be
    another resubmission of the design. If the Trickle vent is
    rejected, there will be an REA submitted to capture our
    additional costs as well as other members of the design
    team.
    (R4, tab 406)
    155. SBN's Roberts prepared a Project Progress Report dated 2 May 2005 that
    included the following information pertinent to the matters before us. SBN's project
    staff and the percentage of time each was assigned by SBN to the project was listed as:
    Project Manager:    Bill Roberts              100 Off Site
    Superintendent:     Tom Zeman                 100
    Asst. Project Mgrs: Tim Hanson                50
    Is staff adequate for this project? .... No    Ifno, explain:
    The staff would probably be adequate if we had all of the
    staff working full time on this project, and working
    together. Presently, we still have Tim Hanson, the
    151
    Assistant Project Manager, working part time on this
    project, and part time on his previous project. He is needed
    full time on this project. We also have the team split up
    because the Project Manager has illegally been denied
    access to the base, and that problem has not been rectified.
    (R4, tab 409 at 21498-99, tab 1103 at 21498-99) Under the heading of Construction
    the following Challenges were listed:
    This is a design/build hotel for the U.S. Army on Fort
    Lewis Army Post, Fort Lewis, Pierce County, Washington.
    It is a 100, 100 square foot, four story building, that will be
    constructed on a 6.19 acre site, on the fort. The building
    footprint is approximately 29,600 square feet. There are
    185 guest rooms in the building, with a front
    desk/lobby/breakfast area on the first floor, housekeeping,
    laundry, and administrative office support areas included.
    Site development includes 110 parking spaces, covered
    entry walks, storm water detention systems and
    landscaping. The exterior of the building is a mixture of
    CMU, brick veneer and stucco, with windows in every
    room and a storefront entry and breakfast area. The roof is
    a red standing seam metal roof that matches the other roof
    structures in the vicinity.
    Ran into some over excavation issues due to encountering
    a certain amount of unsuitable existing soils. The over
    excavation is impacting the schedule by a few days. Will
    have to try to gain it back, as we were into the delay before
    we realized it, and then it was over before we could try to
    counter it with additional equipment. The unsuitable soil is
    a condition that the documents warned could be
    encountered with the exception of areas where we
    encountered buried debris, and trash. Those areas represent
    areas that will require a change order from the Owner for
    additional excavation, removal, disposal and replacement
    with suitable material, however, they are not significant,
    from what I have been told.
    152
    The architect is still preparing the 95% design for this
    work at this time. The design process has been agonizingly
    slow, as the architect does not appear to be the caliber that
    is needed to do this level of design work. This process
    should finally be completed in the next couple of weeks.
    The Electrical primary site work is complete, a temporary
    transformer is being energized, and the electrical
    underground work is underway. The missing information
    from the Owner has impacted underground electrical work
    the most, but the electrician is roughing in according to his
    best guess, and that will have to be sufficient.
    The Owner directed us to proceed with the installation of
    the mechanical system that was originally proposed by our
    mechanical design/build partner. Our mechanical partner
    has proposed one variation to the original system, a trickle
    vent outside· air system for the guest rooms. The Owner has
    rejected that proposal in writing three times now, however,
    mechanical insists that it complies with the RFP and that
    the original system it proposed, and the Anny insists on
    having, does not. The largest issue here does not seem to
    be the functionality of the trickle vent system, as much as
    the amount of credit that will be offered to provide it.
    [SBN] has directed all of the design team to proceed to the
    95% design submittal, utilizing the trickle vent system, and
    be ready to submit the design by 19 May 2005, at the
    latest. Due to the fact that the building construction is
    progressing, ifthe Owner rejects the 95% submittal
    because of the trickle vent system, it will be too late to
    revert to the original ducted system without suffering
    severe cost and schedule problems.
    Construction re-started on the 28th of March 2005. To date,
    no change orders have been received for the additional
    costs, delays and impacts for the delay, differing site
    conditions, and additional design due to the mechanical
    153
    system issues. The work that has been re-started is only the
    work that we were to proceed with previously under the
    [LNTP] issued 25 October 2004. The total REA for all of
    these issues is $1,288,211.00, and includes 152 calendar
    days of time extension. The Owner was scheduled to
    review and negotiate the many issues that make up this
    REA at the end of March, and then at the end of April, but
    has not done so yet. The idea of traveling back to Virginia
    to meet with the Owner to negotiate the REA is being
    considered, for the third week in May.
    The Owner has still not reinstated the project manager's
    pass, and the combination of no change orders from the
    Owner, showing good faith on its part, and no backing
    from [SBN's] management to support its project manager
    has created a morale problem on the job. The subs and
    staff are concerned that if [SBN] will not support its
    project manager, that it won't support them if and when
    they need it either. It is an extreme hardship to try to
    manage a project that you are not allowed to visit, more
    [sic] less work on.
    (R4, tab 409 at 21497-98, tab 1103 at 21497-98) On the subject of"potential cost
    and/or schedule impact issues" SBN reported:
    We have a problem here. Up to the first of March, the
    Owner had been notified of all potential cost and or
    schedule impact issues, however, on 1 March the Owner
    decided to shoot the messenger and took our project
    manager's pass to get on site away. We heard it was
    because our project manager asked the Owner a question
    about when we would receive direction regarding the
    mechanical system issue. This creates a concern that
    providing the Owner notification of changes and impacts
    may cause additional retribution on the Owner's part. Part
    of the Owner's action in taking our P .M.' s pass was to
    threaten to have the Military Police escort our P .M. off
    base, and to take all of our team's passes if our P .M. did
    not surrender his. The team is now concerned that
    providing contractual required notices may put another
    [SBN] team member in jeopardy of being removed from
    the base. This is an untenable situation, that has now
    existed for the entire month of March and April, without
    154
    resolution. No notices were provided during the past
    month.
    The on site Quality Control representative, who is a
    licensed architect employed by the project architect, is the
    vehicle that is presently being utilized to at least give
    initial notice via RFI' s, of issues, as the Army has stated
    that the Q.C. must be the initiator of issues for them to
    recognize them. Unfortunately, this person has no real
    knowledge of contractual relationships, or notice
    requirements, so we have to tell him what to do from
    behind the scenes, which often leads to it not getting done
    timely, or correctly, or at all.
    (R4, tab 409 at 21499-500, tab 1103 at 21499-500]; tr. 5/11-14) On the subject of
    "Fee" it was reported:
    The project is still under design. The fee opportunities and
    the risks lie in the quality of the estimate, the frugality of
    the design and the success of the buyout. We have
    identified numerous budget shortfalls, and have determined
    that the project will lose a considerable amount of money.
    We are still exploring a kitchen unit substitution to plug
    some of the holes, even though the Owner has now
    rejected the substitute. In the rest of the buyout, we will be
    aggressive to see what opportunities we may uncover but
    the outlook is grim.
    (R4, tab 409 at 21500, tab 1103 at 21500) It was also reported, with respect to the
    project schedule:
    The project is not behind schedule at this time, and
    there are no critical schedule issues. We have submitted
    an REA for the issues and delay, and have requested a 152
    calendar day time extension and the extended general
    conditions direct costs associated with that delay. The
    resolution of the mechanical system that we are to provide
    has delayed the completion of the 95% design submittal,
    which has delayed the buyout of the project significantly.
    This is going to cause problems with procurement of
    materials to build into the work. Miscellaneous metal is of
    particular concern. at this time. The completion of the 95%
    design that is scheduled for just over two weeks from now,
    155
    will help this problem, but some impacts will result from
    it.
    Is there enough General Conditions to finish the job? ....
    No     If no, explain:
    The general conditions provided in the estimate are not
    sufficient for the project. The project team has submitted
    an estimate of what they believe to be sufficient, which is
    $500,000.00 +more than is presently in the budget.
    (R4, tab 409 at 21501, tab 1103 at 21501) The following items were listed under the
    heading "CHALLENGES I RISKS I ISSUES I OPPORTUNITES" [sic]:
    [Mechanical trickle vent outside air system] We are
    proceeding with the completion of the design utilizing the
    trickle vent system as it is purported to be superior to the
    previously proposed system, it complies with the RFP, and
    it complies with DOD force protection requirements ·where
    the previously proposed ducted system does not appear to.
    The Army has rejected the trickle vent system to date,
    however, they have not agreed to accept the responsibility
    for the ducted system's failure to comply with the force
    protection requirements of the Contract, either. We are
    gambling on the force protection issue, combined with the
    credit that the subcontractor is offering for the trickle vent
    to be sufficient for the Owner to ultimately accept the
    trickle vent. To date, the credit offer has not been sufficient
    for the Army to approve the trickle vent, and the Army has
    stated that ifthe 95% design is submitted with the trickle
    vent included, the entire submittal will be rejected. If that
    happens, the notice to proceed beyond the structural shell
    will not be issued, and the job will ultimately stop dead,
    waiting for a design resubmittal with different mechanical
    system, or some other approach, such as arbitration, to
    produce a solution that will cause the Army to issue the
    full NTP. The decision to switch to the trickle vent system
    as a design basis for the project, rather than propose it as a
    V.E.C451 issue, has now delayed the 95% design submittal
    45
    We understand this to refer to the term "Value Engineering."
    156
    by two months, so it is imperative that the Army accept the
    trickle vent design.
    [Concrete subcontractor issues] Our concrete formwork,
    rebar, place and finish subcontractor has recently absorbed
    some serious financial setbacks on other projects, and we
    are concerned that his financial health may be in jeopardy.
    We have given him instructions on how to proceed
    financially, and are getting the financial controls in place
    with which to monitor his financial health on the project.
    (R4, tab 409 at 21501-02, tab 1103 at 21501-02) Under the heading "RECENT
    ACCOMPLISHMENTS I MILESTONES" it was reported that:
    The mechanical design continued to delay the completion
    of our 95% design submittal for the entire month of April.
    We have now concluded how the mechanical design is to
    proceed and the entire design team has been released to
    complete the design work. The 95% design is now
    scheduled to be completed by 19 May 2005. The
    completion of that design will allow us to bid out the
    remainder of the project, and determine what the total cost
    and schedule picture will be.
    (R4, tab 409 at 21502, tab 1103 at 21502) In the section of the report labeled
    "RELATIONSHIPS" the following was reported:
    OWNER:
    What is the quality of the relationship with owner?
    Not Good
    Owner had our project manager's pass to enter the base
    and access the jobsite revoked. (No real explanation of this
    action has been received.) This is seriously impacting the
    project team's efficiency and productivity. Owner has not
    provided any change orders for additional work that they
    have directed us to perform, or agreed to a firm date and
    time to discuss and negotiate the REA issues.
    ARCHITECT:
    What is the quality of the relationship with architect?
    Good
    157
    This is a design/build project so the architect in this
    instance is a subcontractor to us. The significant issues we
    have with the architect is keeping him on schedule, within
    the budget, and providing quality control to the design.
    This Architect is not sophisticated enough for projects of
    this size and complexity, so getting an adequate
    performance from him has proven to be impossible. We
    have examined the option of replacing him on more than
    one occasion, but have never been allowed to follow
    through with that action, which is, in all likelihood [sic], a
    serious mistake. [See, e.g., R4, tabs 414-15, 420-21,
    423-26, 440, 482-83, 503, 593 at 5572]
    CONSTRUCTION MANAGER:
    What is quality of the relationship with construction
    manager?
    The Owner is the construction manager.
    The construction manager has a volatile personality. He
    has expelled our project manager from the base by having
    his base pass revoked. The construction manager has not
    provided any explanation for his action. This has created
    huge morale problems with the job team, and the
    subcontractors. Everyone feels they are working under a
    cloud with the possibility of a hammer dropping on them
    any time the Army's construction manager feels like it.
    The negative ramifications of this could be significant, and
    it has polarized the project. Now that the work has re-
    started, the absence of the project manager from the jobsite
    is causing considerable problems for the project due to the
    absence of the on site decision making ability of the P .M.
    This is an additional risk that is a major concern of the job
    team, and a number of the subcontractors. The fact that the
    job team and the subcontractor's [sic] have seen no action
    on this issue from [SBN]'s management is further
    deteriorating morale, and dividing the team.
    PROJECT STAFF:
    What is quality of the relationship with project staff?
    Not Good
    The staff has not heard any word from management on
    how the expulsion of the P .M. is going to be handled, and
    that it, in fact will not be tolerated. This issue has now
    festered for two entire months, March and April. At this
    158
    time, the staff feels that management is not backing them
    up. Management needs to address this issue, as it is
    seriously damaging the morale and commitment of the
    project team.
    SUBCONTRACTORS:
    What is the quality of the relationship with subcontractors?
    Very Good
    (R4, tab 409 at 21502-03, tab 1103 at 21502-03)
    156. As of9 May 2005 SBN's Henrickson had advised CO Bartholomew that
    Montoya had been promoted to Division Manager for Seattle and that Henrickson's
    role would be "more regional from now on but I will be keeping my hand in the
    contracts we have" (R4, tab 1100). CO Bartholomew replied:
    Congratulations to Ron [Montoya]; however, my
    suggestion was that even though he had little or no design
    build experience, he was a good communicator, non-
    confrontational, and was able to grasp what was needed
    light years before Bill Roberts and Bill's handling of the
    earlier design submissions for Ft. Lewis.
    (R4, tab 1100)
    157. As of 20 May 2005 SBN Project Manager Roberts had resigned (R4,
    tab 169 at 3123). Montoya testified about the impact on the project of Roberts'
    resignation:
    The project manager is the orchestrator of the entire
    project. So, he tries to keep everything functioning in
    harmony, which would be the subcontractors, the design
    team and the owner team, everything working in concert.
    He typically holds the most knowledge on the
    project, and even no matter how much documentation you
    put in the project, there is still those nuances that he
    retains, whether it be personality styles, how to deal with
    certain individuals on the project team, what types of
    communication strategies work best with people, and also,
    one of the most important things, he has already built up
    trust with the team.
    So you take that out of the project, now, everybody,
    not only our immediate project team, but subcontractors
    159
    alike, are trying to figure, okay, so, where are we going?
    Who is doing what, and more importantly, who is the next
    guy going to be coming in, and what is going to happen
    and what is he going to do? What is his style like? Do we
    know him? Do we not know him?
    So, there is a lot of confusion that goes on, when a
    project manager leaves the project.
    Q:     Did that same confusion occur ... when
    Mr. Roberts left [SBN]'s employment?
    A:      Yes, absolutely, to the point that it caused
    some concern with the other two team members, Tim
    Hanson and Tom Zeman, as well, and I did get some phone
    calls.
    Fortunately, I had some relationships in the past,
    working with some of the subcontractors, so, when they
    understood what was going on, they would call me
    personally saying, you know, what is going to happen, and
    I said, "I'm still involved with the project. We just got to
    work through it."
    So, I tried to smooth everything out, as best as I
    could, but there is other subcontractors that I had never ·
    worked with on that project, as well.
    (Tr. 3/163-64; see also tr. 3/235-39, 244-45, 6/121-24, 209-11, 239-47) SBN's Senior
    Superintendent Zeman resigned effective 27 May 2005 "[due] to the recent resignation
    of Bill Roberts and other issues at Ft. Lewis" (R4, tab 1207 at SUPP-130; tr. 11221,
    31164-67, 6/122-24, 240-44). By 20 July 2005 SBN's Assistant Project Manager
    Hanson, who had worked part time on this project, had also resigned (R4, tab 81;
    finding 155; tr. 3/164-67). By email dated 23 May 2005 SBN's Chris Bischoff was
    "tentatively" identified as SBN's new Project Manager (R4, tab 1102).
    158. As of24 May 2005, the Fund was still waiting for SBN to submit a 95%
    design package (R4, tab 72 at 2583). CO Bartholomew responded to questions from
    SBN and Jensen/Fey about the 95% design submittal:
    Why are you sending this to us in pieces and why are we
    just getting this request? We need a concerted effort on
    your part. The design time under the contract has long
    since passed and will be impacting the construction GC's
    which we will not cover.
    160
    To refresh everyone's memory of the contract:
    (Does not include govt review time):
    35% design completion and submittal I 21 days
    .65% design completion and submittal I 49 days
    95% design completion and submittal I 12 days!!!!!
    100% design completion and submittal I 35 days
    TOTAL DESIGN TIME WITHOUT GOVT REVIEW
    TIME: 145 DAYS
    The contract was awarded 11 May 2004 and design started
    shortly thereafter. I will dig out the contract files if needed,
    but let's all be sensitive to getting this thing moving.
    (R4, tab 72 at 2581-82, tab 437 at 11397, tab 1104)
    159. By letter dated 27 May 2005 SBN's new Project Manager Bischoff
    advised COR Dyer that SBN intended to submit for review and approval a
    HVAC/mechanical system design that included PTAC outside air dampers instead of
    the contract-required "forced, tempered makeup air" system (finding 145):
    We are confident this system will be [sic] meet the
    requirements of the project and eventually will be
    accepted. We will also be including this system in the 95%
    design package.
    (R4, tab 436)
    160. On 1June2005 COR Dyer acknowledged receipt of"yet another change
    in the mechanical system design approach" (R4, tab 72 at 2581, tab 437 at 11395, tab
    1104) and advised SBN's Bischoff that:
    The 95% submittal is not a point to be introducing a new
    design approach. The time to discuss approaches to design
    is long over.
    (R4, tab 72 at 2581, tab 1104) ORB's John Patterson also responded to SBN's
    Montoya that:
    At this point your 95% design should depict the
    mechanical systems as approved back in February .... If
    you seriously want my assistance in staffing the PTAC
    161
    damper option I need information, similar in depth to the
    package you brought me regarding your trickle vent idea.
    It is between [SBN] and CFSC/Lodging what this does or
    doesn't do to your 95% schedule.
    (R4, tabs 73, 438)
    161. By email dated 3 June 2005, CO Bartholomew advised SBN that:
    Drew just advised the 95% was to be shipped with
    mechanical changes. This is a CONTRACTING OFFICER
    DIRECTIVE: Do not distribute to any Army players or
    consultants. We will not review unless there is a
    considerable cost value to us to do so.
    You are otherwise directed to correct your drawings to
    include the mechanical system approved with the 65%. If
    you need to replace W.A. Botting, or anyone else, then you
    should do so. Our contract shall prevail.
    (R4, tab 74 at 2588, tab 1107; tr. 5/20-21) SBN's Montoya replied:
    It was represented to us that a considerable cost savings
    would be around $100,000. We informed CFSC that we
    would be able to achieve that and address the other three
    items noted in the original response as well ....
    We will continue with the completion of the 95% drawings
    based on the foregoing that everyone we [sic] will be
    treated fairly. We are not asking any more from CFSC than
    what has been asked of us.
    (R4, tab 74 at 2588) CO Bartholomew replied:
    You are missing a "O" on the number that I would consider
    a considerable cost savings. The additional maintenance
    and potential for mold with 7 CFM outside air, that cannot
    be electronically controlled by the required control system,
    would eat up $1 OOK in maintenance and extra room checks
    before we were much out of warranty. Cost savings to us
    are life cycle costs from every perspective.
    162
    I am the one that would ultimately determine what a
    considerable savings is. The back and forth with the
    mechanical system, the design rejections at the 35%, 65%,
    and now 95%, since last summer, will likely cost you over
    $200,000 in various costs including extra design, extended
    general conditions for the late delivery of the design
    documents, and other construction delays.
    We hope to get on with this soonest and save you money
    that you should not be expending!
    (R4, tab 74 at 2587)
    162. On 8 June 2005 SBN's Montoya notified CO Bartholomew by phone of
    significant SBN personnel changes for this project:
    Lots of changes this week at [SBN]. Keith Henrickson
    abruptly resigned and sold his house. There is to be a
    replacement for [Bischoff] as PM and there will be a new
    Super[ intendent].
    (R4, tab 75) SBN's Montoya hired Rick LaSharr as Project Manager in June 2005 and
    Scott Bowman as Superintendent in August 2005, with both of whom he had worked in
    the past (tr. 3/167-70, 4/90-97, 5/9-10). LaSharr testified that when he came on as
    SBN's new Project Manager, SBN's ability to "move forward with the project" was not
    impacted by the absence of Roberts and Zeman (tr. 4/104). On 10 June 2005
    CO Bartholomew sent the following email to J. Hoopes at SBN corporate offices:
    Subject: U.S. Army I Ft. Lewis, WA I 185 Room Army
    Lodge I Swinerton Months Behind Schedule in both
    Design and Construction
    We need your immediate help on an Army Lodge project
    awarded to [SBN] at Ft. Lewis, WA in May 2004.
    We have had multiple [SBN] PM's [sic], including the
    newest one showing up unannounced two days ago at a
    progress meeting, multiple QC managers, a new project
    exec, serious issues with the mechanical design and design
    quality control, the recent unannounced departure of the
    project Superintendent we had great respect for, and this
    163
    week's unannounced departure of Keith Henrickson, the
    one person we have had a strong relationship with at
    [SBN]. for a number of years. There is virtually no one now
    on the project with design-build experience. This must be
    corrected immediately.
    I have left you a lengthy message about our PM and I
    meeting with you next Thursday afternoon, in your San
    Francisco office, about this project, in advance of likely
    negative actions against your firm and bonding company.
    (R4, tabs 76, 1107) CO Bartholomew also forwarded his email to Henrickson (who had
    resigned from SBN) and Henrickson responded that he believed the CO was "taking the
    correct approach" (R4, tab 76). In a later email on 14 June 2005, Henrickson also
    suggested that the Fund get SBN president, Gordon Marks, involved (R4, tab 78).
    163. As of 11June2005 there still had not been agreement between CFSC and
    SBN regarding the mechanical system design and the slab subcontractor was
    concerned about proceeding with its work until the design was resolved (R4, tab 446).
    164. On 13 June 2005 COR Dyer replied to ORB's Monson's 13 May 2005
    request regarding a CFSC response to Jensen/Fey's request for information
    (finding 146):
    Bob, thanks for your interest in keeping the concrete work
    going in earnest. I went back and checked my electronic
    records. All I've rec'd from David [Lee] were the breakfast
    bar serving and prep area layouts, a couple of weeks after
    my last visit (April 28). I have seen no scaled,
    dimensioned, full size floor plans on the Lobby and
    administration areas. As was discussed during that
    progress meeting, the 95% design was going to be
    delivered by the middle ofMay ... now we're in the middle
    of June and NOTHING.
    Even if we have the documentation to provide [SBN] the
    answers that they need, I have expressed many times (and
    very clearly) that I am not going to staff each and every
    design issue separately until we get a fully integrated 95%
    design. [SBN] has had over 4 months since the mechanical
    design approach was accepted by all concerned to provide
    us the 95% design. If they find themselves not being able
    164
    to produce in the field under the Limited NTP, they have
    only themselves to blame. Any construction hold up is
    entirely the fault and blame of [SBN]. We, the Gov't, are
    not going to be caught up in designing by the seat of our
    pants.
    (R4, tab 1108) Mr. Monson agreed with COR Dyer's approach (R4, tab 1109).
    165. On 15 June 2005 SBN notified the Fund of its staffing plan for the project:
    Senior Project Manager:      Rick LaSharr
    Interim Project Manager:     Chris Bischoff (see note below)
    Assistant Project Manager:   Tim Hanson
    Assistant Project Manager:   John Elswick
    Superintendent:              Pat Fry
    Safety:                      Christine Russell
    Scheduling:                  Jeff Pinter (Bellevue office)
    Chris Bischoff, as Interim Project Manager, will be
    involved through the 95% design approval, buyout, and a
    full transition to Rick LaSharr. He will be available beyond
    that to help when needed.
    (R4, tab 79) Also on 15 June 2005 Botting acknowledged its receipt of the "directive
    to proceed with a fully ducted system for each floor" (R4, tab 452; tr. 5/128).
    166. Progress Meeting #12 took place on 22 June 2005. Meeting notes were
    prepared by SBN' s Hanson and included:
    1-05. Existing Unmarked Gas Line Relocation: 6/22/05
    I A change modification has been issued by CFSC.
    SB[N] has billed for this work and awaits payment
    from CFSC. There are outstanding invoices due to
    Subcontractors, which have been past due since
    April. SB[N] will pay the Subs once the Funds are
    received from CFSC ....
    (R4, tab 460)
    3. 95% Design
    167. SBN's 95% design was submitted to CFSC on 14 July 2005 (R4, tab 479).
    SBN's Montoya admitted the submission was incomplete (R4, tabs 80, 82; tr. 5/36) ..
    165
    168. By internal email dated 18 July 2005 Botting acknowledged that its DDC
    design incorporated in the 95% design submission did not comply with the RFP:
    Our published specification in our 95% submittal does not
    match the RFP in any way shape or form! Our
    specification is a complete substitution geared around
    Johnson Controls and I don't think it is going to fly. I do
    not want to waste any time going down a dead end road,
    especially since we are out of time. The RFP clearly states
    that "An existing ONITY "Senercomm" InnPulse On-line
    System will be relocated from the existing building to the
    new facility. The entire facility operation is specified
    around ONITY. They are using ONITY electronic door
    locks and ONITY electronic controls to the room Safes. It
    only makes sense to me that the Programmable
    "Senercomm Sensor-stats" are used and not a substituted
    product. The owner probably will not consider a substitute
    and we will only lose more time.
    In addition, the specifications that we wrote don't cover
    the RFP Section "J-4". The specifications clearly state that
    the specified Tridium JACE network area controller will
    be provided for the network interface to provide global
    supervisory control functions. Our controls specification
    doesn't even address the requirement for network
    interface. It is clearly stated in the RFP that the Tridium
    JACE system will be provided and no other systems or
    gateway-based technologies will be acceptable. Johnson
    controls would need an interface panel to communicate
    with the Tridium processor and there is no way the Army
    will accept that. In my opinion, this is heading down a
    dead end road and I think we should proceed with
    Honeywell system from Sound Energy. I need your
    thoughts on this ASAP because I need the Controls guy
    onboard now!
    (R4, tabs 480, 1114; tr. 4/52) SBN's expert witness, Mr. Kommers testified that the
    Johnson Controls thermostats could not communicate with the existing ONITY
    Senercomm InnPulse system (tr. 7/152-54, 161, 164-65 (bldg. 2111 ONITY which
    was Unix-based couldn't communicate with Lonworks/BACnet protocol controllers
    like the Johnson Controls thermostats), tr. 71154-57). Automated Controls' Magruder
    described the lack of communication between the existing ONITY system and the
    166
    proposed Johnson Controls thermostats by analogy to spoken languages, i.e. both
    components spoke Spanish but one component spoke the Mexican Spanish dialect and
    the other spoke the Castilian Spanish dialect (tr. 7/193-94).
    169. On 26 July 2005 BCE completed its review of SBN's 95% Design
    Submittal:
    Because the list of comments is rather extensive, and their
    resolution will require inter-discipline coordination, we are
    recommending that the submittal be returned "not
    approved". Review comments that could possibly affect
    the sizing of major system components need to be
    addressed and the missing information needed for
    evaluation of the design, need to be submitted before the
    review can be completed.
    Major mechanical elements in question are:
    •   The specification still reflects a 4-pipe fan
    coil system with gas-fired boiler and
    air-cooled chiller.
    •   The ventilation airflow rates shown on the
    plans do not meet ASHRAE standard
    62-1999 (see attached .pdffile).
    •   Design Analysis: Some major equipment
    sizing calculations are missing. Sizing of the
    domestic hot water heaters and storage, air
    equipment external static pressure
    calculations, etc. can't be confirmed.
    •   EMCS information: No DDC system
    drawings or diagrams have been provided.
    Major electrical elements are:
    •   Electrical load calculations must be coordinated
    with revised mechanical equipment electrical
    requirements.
    •   Emergency lighting system inverter system has not
    been specified nor indicated on the drawings.
    •   The room panel risers need to be recalculated
    showing actual mechanical loads and room
    configurations.
    167
    (R4, tabs 83, 485-86; tr. 111125-27, 180-85) BCE's Heiberg testified that:
    [T]here were specifications that were provided with this
    submittal; however, the specifications reflect a four-pipe
    fan coil system and gas fired boiler and air cooled chiller,
    which wasn't on that submittal.
    So you had a Chevrolet here and you had a Ford
    that was shown on the drawings. The specs didn't match
    up with the drawings. The design analysis and major
    equipment siting calculations were missing. Domestic hot
    water heaters, ... but we still didn't have that roadmap to be
    able to confirm that they were on the right track, or at this
    point had a big enough room for the hot water storage
    system. ENCS information, no DDC system drawings or
    diagrams had been provided yet.
    And we're getting to a point, and I think there's
    some notes here, load calculations must be revised with the
    mechanical contractor and designer. We're basically
    reviewing electrical drawings at the same time, and we're
    able to follow the electrical drawings fairly well, but we're
    getting towards the end here, and we haven't seen
    calculations, and at 95%, drawings should be really just
    pick up some typographical errors and whatever review
    comments and go to 100% and publish it, but they were
    still in a design development stage, it was obvious.
    No one had thought through the controls yet, it was
    evidenced by their absence. We're still missing energy
    calculations to confirm that they're even going to meet the
    energy goals required by the RFP, and we're really
    concerned as to the impact on the electrical side of things
    because SME's 95% electrical design, at 95% is reasonable
    to assume that they've got all the loads that they need, and
    that they've taken every diversity factor to get that size of
    service down. A lot of times it starts big, and through the
    design process, it goes down and then dial it in. Well the
    mechanical equipment was still up in the air, and
    mechanical represents a very large portion of the electrical
    service requirements.
    So we're going uh oh, you know, if they come back
    and put a bigger pump in and so forth, we're going that's
    going to upset the electrical design, and it's going to cause
    delays and problems with getting to issue for [the]
    construction set.
    168
    [W]e're still looking at specification sections that are
    blank, we're looking at no development or any content on
    the mechanical drawings that shows any-that anyone has
    given any thought to the DDC controls for the system.
    We're simply trying to bring it up; it's unusual not to have
    it to be in a 95%, and to have this information still missing.
    I guess at this point we're as concerned with that as we are
    with the electrical service being adequately sized when the
    mechanical equipment is still changing.
    (Tr. 111127-29, 133)
    170. On 28 July 2005 Botting reported internally that it had awarded the DDC
    work to Automated Controls and that a purchase order had been written for ONITY
    components (R4, tab 487).
    171. On 5 August 2005, BCE provided the following "overview" of the 95%
    review meeting held on 2 August 2005:
    Representatives for WA Botting, SME Electric, Patriot
    Fire and [SBN] were present at the meeting.
    The overall consensus was that the MEP documents, both
    specs, drawings, supporting calculations, need a lot of
    work. Mechanical and electrical design coordination needs
    to happen. [COR Dyer] verbalized his displeasure with the
    status of the 95 [%] design and that promises made at the
    65% (to get things coordinated and fixed by the 95%) were
    broken. [SBN] assigned a new PM to the Project and there
    was some visible optimism and hope that the lost ground
    will be made up between the 95% and 100% submittal.
    [SBN] is proceeding to the 100% with a whole lot of work
    to do. We can expect to see a lot of new material in the
    documents at the next submittal, which may generate a
    series of new comments. This will be especially true for
    the specs because they are were [sic] not in a reviewable
    state at the 95% submittal.
    169
    SME Electric was the only designer that had developed and
    distributed written responses to the electrical comments ....
    Mechanical:
    Botting accepted most of the comments.
    WAB to provide Onity controls and Tridium DDC Controls.
    WAB to fix full load electrical data with SME.
    Specifications will be fixed, UFGS guide specs will be
    used.
    [W]e can expect to review corrected submittal data in the
    next few weeks.
    (R4, tabs 86, 497, 1122; tr. 111135-38) BCE's Heiberg testified that:
    I guess I'll summarize by saying the quality of the
    submittals were-the representative produc[t] where
    everybody, all the designers seemed to go do their own
    thing and then merge documents without any coordination.
    So they were poorly coordinated, they were behind
    schedule because it seems like systems were changing and
    sizing was changing, and I've never seen such a poor
    design submittal before.
    I would limit that to the mechanical. We had a few
    electrical issues, but for the most part, you could follow the
    design and it was where it needed to be at each particular
    phase of the design.
    (Tr. 111138)
    170
    172. In an internal Botting email dated 9 August 2005, Botting's Wade Bailor
    responded to an internal suggestion that the controls subcontractor edit Botting's specs
    for the next submittal:
    [T]here is something seriously wrong with this picture!!!
    Automated [Controls] is not obligated to edit Botting's
    specification so that it complies with the RFP. We have
    and always have had an obligation to design the project to
    the RFP. Our engineering department didn't even write a
    Sequence of Operation and [if] they would have
    thoroughly explored the RFP requirements, we never
    would have written our specification around Johnson
    Controls. This is very frustrating!! I am not going to ask
    [Automated Controls] to write his own specification!
    (R4, tab 498)
    173. SBN promised to submit for re-review the "mechanical items that are
    missing/need revised" as well as associated electrical load calculations on 12 August
    2005 (R4, tab 85 at 2679).
    174. On 15 August 2005 SBN met with ORB/BCE to provide its resubmittal
    of the 95% design. With the concurrence of SBN's LaSharr, the resubmittal was
    rejected. While SBN and its electrical subcontractor, SME, "made a good faith effort"
    in the resubmittal, Botting's HVAC/mechanical design still had no DDC drawings and
    the DDC specification was '~ery sketchy and incomplete overall":
    [Botting] admitted that they have some distance to go with
    DDC and controls in general and expected to have a more
    complete submittal "in two or three weeks". He stated that
    Botting had gotten a "late start" in changing over [to] the
    required control systems. Both [SBN' s LaSharr] and
    [ORB/BCE] told him that was unacceptable. [LaSharr] is
    working closely with Botting to generate an acceptable
    submittal.
    (R4, tab 89 at 2688-89) COR Dyer expressed "shock[] that the Mechanical design
    remains so disjointed" and disappointment that SBN did not review Botting's design
    before incorporating it into SBN's submittal. As a result, COR Dyer recommended
    that CO Bartholomew issue a cure notice:
    171
    [I]t is apparent that [SBN] has no clue how to get their
    mechanical subcontractor, Botting, to perform. [SBN] also
    has no clue on how to QC a deliverable .... We demand a
    full and complete 95% mechanical submittal. We have
    been asking for this since early February 2005. It has been
    SIX months! Nothing we've said or done has worked ....
    [SBN] has to understand that they are responsible for the
    DESIGN. Where was Jensen-Fey, the Architect of Record
    on this deliverable? Are they even involved?
    (R4, tab 89 at 2688, tab 1120) In an internal email Botting's Bailor provided the
    following input from the meeting with SBN and ORB of the same date:
    I transmitted the Re-submittal to [SBN] this morning and
    had a brief review meeting with ORB. It looks like we
    need to do a few more things before they will submit for
    official review. The following is a list of actions that need
    to be taken:
    1. They are expecting a complete control system
    design that is at least 95% as a standalone submittal.
    They are furious that this is not farther along in the
    process. I informed them that we will expedite a
    "Sequence of Operation" for the BMS and the Onity
    System and that's all we can give them this week. I
    said that product data for the control devices will be
    available next week but they probably want to look
    at that in conjunction with the engineered drawings
    and the engineered drawings won't be complete for
    two or three weeks.
    Status: I have Automated Controls dropping
    everything they are working on to expedite a
    sequence of operation. Brad said ifhe puts
    everything else aside, he can get it to me by
    Wednesday or Thursday.
    2. We need to clean up our DDC Temperature
    Controls Specification 15900. The specification still
    makes reference to the Onity "SennerComm"
    System or equal. We need to get rid of the "or
    equal". The specification still makes reference to the
    MRC digital thermostat in several locations. This is
    172
    a Johnson product and needs to be removed from
    specification.
    4. The Army will not accept notes on the equipment
    schedule that describes the features of the AAON
    Equipment. They are looking for an entire
    specification that describes what they are getting
    with each AC-Unit. The specification should
    include makes, models, sizes, construction methods,
    performance criteria, bells & whistles and so on!
    They have the impression that all these
    requirements were conveyed to us in a meeting
    clear back in February[.]
    Action: Botting to write a detailed specification for
    the AC-Units that conforms to their expectations.
    [SBN's] Rick LaSharr made it very clear that this submittal
    is critical to the next partial notice to proceed.
    (R4, tabs 501, 504)
    17 5. After email discussion of what was required for mechanical resubmission
    to comply with the RFP (R4, tabs 90-91 ), COR Dyer forwarded ORB/BCE input to
    SBN on 17 August2005:
    Rick [LaSharr], I see your message below on what's being
    planned for delivery tomorrow .... Unless you have all of
    the below information, don't bother submitting. The deal is
    all or NOTHING. No more piecemeal. We are supposed to
    see all major mechanical systems and components fully
    designed at 95%. Between 95-100[%], it should be just
    dotting i's and crossing t' s ....
    We normally don't do what we're doing with your
    designers ... pointing out EXACTLY what they should be
    doing! All one would have to do is to follow the comments
    to understand what is expected. I'm beginning to think
    your designers don't really understand what they're doing!
    That would be a worrisome sign for me, to say the least.
    173
    The folks I pay to perform peer review are not to design
    for you.
    (R4, tabs 92, 507; tr. 8/82-83, 87) As of 18 August 2005, ORB/BCE was still
    providing information to SBN and Botting to assist them in understanding their design
    responsibilities (R4, tabs 93, 509). On 19 August 2005 SBN advised that it intended to
    resubmit its 95% design on 25 August 2005 (R4, tabs 94, 508, 513). On 26 August
    2005 SBN notified CO Bartholomew that the 95% design resubmittal from Botting
    still "did not include the corrected DDC spec" (R4, tabs 513, 1123).
    176. ORB/BCE received the updated 95% design resubmittal from SBN on
    Saturday, 27 August 2005. On Monday, 29 August 2005, ORB/BCE advised
    CO Bartholomew and COR Dyer that:
    Again I find myself in the position of recommending
    refusal of[SBN's] latest 95% resubmittal. [ORB/BCE] are
    somewhat encouraged in that we are at least seeing some
    movement in the quantity of information provided by
    Botting, but we are STILL not seeing acceptable
    specifications. I don't know how much clearer we can
    make it, the designers need to go to the Fort Lewis Design
    Standards website, download all appropriate specifications
    and guidance for HVAC and DDC, and use them to create
    compliant specifications. The RFP and all review
    comments to date have been crystal clear on this issue.
    Neither Fort Lewis or BCE will accept anything less.
    I am also disappointed in the lack of review and QC
    performed by [SBN] and the QCM. [S]houldn't someone
    have insured compliance with our comments before we
    were asked to make a third review? We would appreciate
    some assurance from [SBN] that they have compared the
    next submittal with the requirements BEFORE we are
    asked to look at the 4th go-round.
    (R4, tabs 95, 514, 1128) The next day COR Dyer advised CO Bartholomew of the
    situation and how COR Dyer planned to address it:
    I'm going to call corporate headquarters in Los Angeles
    and attempt to get someone to listen to me. Rick LaSharr is
    unable to accomplish the task of providing the requisite
    95% design of the mechanical system and integrated
    controls. We have repeatedly tried to help these folks, to
    174
    no avail. After three strikes, I'm no longer going to waste
    [ORB/BCE's] time. I asked you to issue a design cure
    notice weeks ago, but you convinced me it would do no
    good. Fine, then I will find a way to get their attention, and
    but good!! Their invoice for August will be arriving any
    day now. I will sit on the entire sum until the requisite
    design is provided and accepted by the Fund. No further
    monies will be authorized from my hand.
    We have wasted many hours and dollars with our effort to
    help [SBN]. I'm through with help! [SBN] is capable of
    handling a job of this magnitude. They have unfortunately
    allowed themselves to be held hostage by a mechanical
    subcontractor who is totally incompetent and a non-team
    player.
    (R4, tab 96)
    177. Handwritten notes on a hard copy of a 30 August 2005 email printed from
    SBN' s Morris's email account included:
    W A Botting I 4 weeks after 95% review (3 submittals) all
    rejected. Rick cannot make this happen
    We cannot proceed w/100% until complete.
    Drew will not release pay to SB[N] until 100% complete.
    will sit on next requisition
    Honeymoon is over w/ Rick I Mechanical is Issue I
    (R4, tab 515; tr. 9/118-20)
    178. On 31August2005 Botting emailed SBN's LaSharr voicing Botting's
    objection to the format in which it was being required to draft its HVAC/mechanical
    specification and asking for direction from SBN (R4, tabs 516, 1128; see also R4,
    tab 169 at 3894-943]; tr. 5/47-51, 71130-31, 191-93, 265-66, 111157-61). By letter
    dated 6 September 2005 SBN responded:
    Please accept this letter as formal direction to immediately
    proceed with the completion of the mechanical design
    documents as outlined within e-mail correspondence, dated
    August 29, 2005 by John Patterson of ORB. This
    correspondence has been previously forwarded and is
    175
    herewith attached. It is the understanding of the Owner that
    the methods outlined in this e-mail are necessary for WA
    Botting to complete their design and allow for an
    expeditious review and approval of the mechanical design
    documents, and are furthermore clearly outlined in the RFP
    documents.
    Be advised that WA Botting's inability to obtain approval
    is currently impacting our schedule and has exposed [SBN]
    and others to potential non-recoverable costs. These
    impacts will be substantial if WA Botting does not obtain
    100% design approval, thus allowing [SBN] to receive a
    full notice to proceed with the Work. Please be aware that
    [SBN] will seek full recovery from WA Botting for all
    associated delays and impacts.
    Furthermore, be advised that the Owner has notified us that
    they will be withholding all payments due [SBN] and
    associated Subcontractors until this submission is
    approved.
    Please produce your re-submittal no later than
    September 9, 2005. A failure to complete all
    documentation as noted above may require that [SBN]
    direct all subcontractors to proceed with the work in
    advance of full approval from the Army to avoid further
    delays to the schedule. If this were to occur, [SBN] will
    seek full recovery from WA Botting for changes that may
    be necessary as a result of the final approval documents.
    (R4, tab 520; tr. 9/118-20) Botting objected to SBN's direction (R4, tabs 523, 1124, 1128).
    179. On 8 September 2005 SBN's Chris Morris provided the following
    information to COR Dyer:
    Thank you for the e-mail. WA Botting was directed to
    complete the design and specifications. The format for the
    submittal was to be as requested in the recent
    correspondence from your consultants on August 29 and
    the RFP. This will be complete by Friday, Sept 9, 2005.
    Rick [LaSharr] will review this information with
    Jensen-Fey and WA Botting to make sure it is complete
    prior to forwarding this to your group for review and
    176
    approval. Your assistance would be appreciated in the
    expediting of this approval. I know this has been
    frustrating and we should be coming to an end and moving
    to the next phase. Let us know if there is anything we can
    provide to assist with this process.
    Is it possible to get approval for the framing as an
    extension to our current limited notice to proceed to allow
    the work to progress? If so, what is the process[?]
    (R4, tabs 97, 524) COR Dyer denied the issuance of another limited NTP and stated
    that the full NTP for construction would be issued only upon satisfactory completion,
    review and acceptance of SBN's 100% design (R4, tabs 97, 98; tr. 8/83-85).
    180. On 8 October 2005 COR Dyer provided to SBN the consolidated
    comments on its 95% design resubmittal (R4, tab 99). As of 17 October 2005 SBN's
    Montoya acknowledged that the mechanical portion of the 95% design resubmittal was
    still not complete and agreed that its completion should take precedence over any
    discussion of SBN's existing REA (R4, tabs 100-01). That same day SBN's LaSharr
    provided SBN's responses to the 95% design comments by email and requested a
    meeting to discuss them on 20 October 2005 (R4, tab 103). The review meeting was
    set for 26 October 2005 at Fort Lewis with all parties present, including Botting's
    DDC subcontractor, Automated Controls (R4, tab 103).
    181. By email dated 19 October 2005, SBN's LaSharr again requested a further
    limited NTP, which was denied by CO Bartholomew:
    We do not concur with the issuance of any additional
    LNTP's until the mechanical and 95% design issues are
    settled. We have now been in design on this project almost
    17 months! The delays in design are affecting the
    government's ability to get this needed project completed
    for the Soldier's at Ft. Lewis!
    .... We also need to get on with the REA. Further delays in
    the design affect both of us and will impact the REA
    issues/their resolution.
    (R4, tab 104 at 2739; tr. 5/41-42) As of20 October 2005 COR Dyer reported that "the
    structure is almost done" yet SBN "has not received the Final NTP as the 100% design
    has not been accomplished" (R4, tab 1130).
    177
    182. On 21 October 2005 SBN's Morris acknowledged that:
    The 95% approval is critical. We are all aware that the
    mechanical contractor has dragged this process out,
    however, the exterior skin and roofing completion is
    critical for the other elements of the work to proceed
    timely until the 95% documents are approved. By not
    approving this work we are being exposed to additional
    risk and costs that will only create problems and claims
    from the other subcontractors. This action seems punitive
    and does not support the future success we are both trying
    to achieve.
    Again, we are committed to moving forward to the
    successful completion of this project. We respectfully
    request that the elements of the work not effected [sic] by
    the mechanical design move forward so that we do not lose
    additional time on the project schedule.
    (R4, tab 104 at 2737-38, tab 535) CO Bartholomew responded:
    I have empathy just as I hope you have empathy that our
    side has spent almost $200K extra dealing with the
    mechanical issues and have lost a year. We all need to
    focus. There is nothing punitive. Every project we do is
    executed almost the same way. Our side is at a greater risk
    if your mechanical guy plays more games. Only you can
    deal with that at this point. ... No one on our side wants to
    risk going forward without some better assurances that
    things are on track I which they have not been for a year on
    the design side.
    (R4, tab 104 at 2737, tab 536)
    183. On 26 October 2005 the Fund authorized an additional LNTP as follows:
    This limited notice to proceed supplements the original
    notice to proceed to include the installation of the mock-up
    (rooms 139 and 141) complete, exterior facade, interior
    framing, electrical rough in, plumbing rough in, and Fire
    Protection rough in. LNTP also allows for installation of
    178
    pre-rock drywall at locations to allow for rough-in
    activities to proceed (typically above ceiling).
    (R4, tab 105; tr. 5/42) The document was signed by CO Bartholomew and COR Dyer
    and also contains the following handwritten language above CO Bartholomew's
    signature:
    Authorized to proceed contractually with the above LNTP,
    subject to no HVAC authorization.
    (R4, tabs 105, 1132; tr. 5172-73)
    184. On 27 October 2005 SBN's LaSharr notified SBN, Jensen/Fey and
    subcontractor personnel that:
    In a somewhat surprise outcome, we have been able to
    obtain an additional [LNTP] from the Army. It was
    understood via our meeting with the Army on 10/25/05
    that they would not issue any [NTP] until resolution of the
    95% documents. Currently the issues remaining to resolve
    the 95% documents are associated with two RFl's that are
    being reviewed by [Botting] at this time [see, finding 186].
    It is our understanding, that upon resolution of those two
    RFI' s I we will be able to obtain an additional NTP
    associated with the HVAC work.
    At this time, all parties associated with the 100%
    documents, should complete their documents such that
    same can be reviewed by [SBN] and resubmitted to the
    Owner by 9 Nov 2005.
    Please advise of any questions.
    All parties, be advised that we are intending to start
    framing as soon as possible and will be having site
    meetings to discuss scheduling of the framing and
    plumbing, electrical and fire protection rough-in.
    (R4, tabs 539, 1132) Botting took issue with SBN's position regarding the 26 October
    2005 LNTP and what effect it had on Botting's work (R4, tabs 544, 1133). On
    30 October 2005 there was an internal Botting meeting during which there was
    discussion of Botting pulling out of the project (R4, tab 1131).
    179
    185. On 2 November 2005 COR Dyer confirmed that the 26 October 2005
    LNTP signaled the approval of the 95% design "with the exception of the comments
    reviewed on-site 8/1/05 and 8/2/05 and comments addressed on 10/26/05. Each of
    these comments will be addressed within the final 100% documents." However, he
    also reminded SBN' s LaSharr that the CO had not yet issued a NTP to produce the
    100% design. "This will not be issued until the mechanical and controls issues raised
    in last week's meeting are submitted and accepted by the owner's team." (R4,
    tabs 107, 541-42)
    186. Also on 2 November 2005, SBN advised that:
    [W]e need to revise the suspense dates as outlined below:
    5.     WA Botting has taken exception to certain items in
    the RFP. We need to receive a consolidated list of these
    items for a determination if they are in or out of the
    contract. [SBN] to provide this list ASAP. Suspense:
    Friday, October 28. Revised suspense date Wednesday
    November9
    6.     Prepare RFI submitting a red-lined, edited, version
    of the Ft. Lewis DDC design specification, 15910 for
    preliminary acceptance. Suspense: November 2 Revised
    suspense date Wednesday, November 9
    7.      Prepare a 2nd RFI that describes the level of detail
    for the DDC graphics package to be provided per the RFP.
    Suspense: November 2 Revised suspense date Wednesday
    November9
    (R4, tabs 106, 113 7) On 2 November 2005 CO Bartholomew responded:
    Please be advised that every day we are delayed over
    the mechanical system is a day we lose in getting the
    building built. For all, we are in our 17th month of
    design.
    We reserve all of our rights to compensation for the design
    delays and will likely have to involve our lawyers if this is
    not squared away soon.
    180
    We do not have a warm fuzzy with the mechanical systems
    and urge you to look at all your options as this may
    become an even costlier proposition for you.
    (R4, tabs I08, I 137, I I43)
    I87. A 13 November 2005 internal Botting email stated:
    In an attempt to save the $85k we are spending on Onity
    controls, it was my intention to use the flawed controls
    specification to try and get out of buying the ONITY
    Controls and put them on the owner. After spending the
    afternoon going through all the correspondence from last
    year on this issue, it would be foolish for me to go down
    this path now. Ifwe attempted to take this position at the
    start of the project, we might have had a slim chance.
    However, the project record clearly indicates that we were
    planning on providing an alternate system from day one
    and we had several opportunities in the past to put this on
    the owner. We don't need to lose anymore credibility on
    this project.
    (R4, tab I 136)
    I88. On 28 November 2005 SBN submitted a revised DDC specification which
    it said included revisions to address the previous review comments (R4, tabs I09,
    579). The revised DDC specification was reviewed by the next day and determined to
    "look[] good." BCE recommended it be incorporated verbatim into the IOO% design
    submittal. (R4, tab I I 0)
    I89. The CFSC inspection of the mock-up units took place on 13 December 2005
    (R4, tabs 574, 576; tr. 5/54-6I, 85-87, I2/19-22, 47-48, 138-39). On I4 December 2005
    SBN sent an email to CO Bartholomew regarding corridor ceiling heights:
    It is my understanding from conversations with [COR
    Dyer] on site yesterday, that the LNTP for the HVAC
    rough-in is currently being held up based on the corridor
    ceiling height being 8'-0" shown on the construction
    documents in lieu of the 8'-4" shown on the FDS sheets.
    Previously, it was my understanding that the issue was
    within the rooms and as you know we have acknowledged
    and revised those ceiling heights at the entries. We are
    currently reviewing the issue at the corridors and the
    I8I
    correspondence that has resulted in the ceiling heights
    being at 8'-0", upon determination of same we will advise.
    It should be noted that we are being impacted by being
    unable to proceed with the HVAC work at this time.
    (R4, tab 570)
    190. As of no later than 15 December 2005 SBN was authorized to proceed
    with 100% design documents. COR Dyer reiterated that the design documents were to
    show '"all RFP ceiling heights being attained." (R4, tab 112)
    191. On 19 December 2005 comments from the mockup unit inspection were
    collected and forwarded to SBN:
    No.                               REVIEW COMMENT
    Extended
    Stay
    1                    SBNW admitted room was approx. 293 SF,
    below the 300 SF standard. The reason is
    apparently due to the shear wall adjacent to the
    adjoining ES room. SBN[] was requested to
    issue RFI informing Lodging how many rooms
    in the entire building fall below the standard.
    VERY IMPORTANT!
    I   Family
    Suite
    5         NOTE:       Provide RFI-Non-loading bearing steel studs
    installed 24" on center. RFP specifically calls
    for studs at 16" on center. SBN[] was
    advised until this is reviewed and acted
    upon, continuing the 24" on center was at
    their own risk.
    8         NOTE:       After the inspection, we returned to the
    conference trailer for further discussion.
    Items decided or actions to be taken include:
    1. Proceed to produce the 100% design. The
    mechanical controls spec. 15910, and graphics
    182
    I example were accepted by review team.
    3. Columns-Lodging doesn't want column
    protrusions in any room. Lodging's typical
    layout furniture plans show no bump-outs or
    other interferences that interferes with furniture
    placement. The word "flush" was used vs.
    "furr" when speaking about a wall. SBN[]
    agreed to "flush" out walls where the columns
    protruded 3-4" into the finished room, as long
    as Lodging agreed to the loss of SF. This was
    agreed. In every other room where a column
    can not be "flushed" with the wall, a Y4" scaled
    plan, on 8 Yi" x 11 ",will be provided. This will
    allow Nancy and Sheryl the opportunity to
    make furniture placement decisions on a
    room-by-room basis. Since the mockup room
    furniture requires immediate ordering to
    comply with SBN[] 's schedule, Lodging
    requests the plans on the non-standard
    configured rooms immediately! All rooms
    that are not "normal" per the RFP shall
    · have individual scaled plans produced
    immediately.
    (R4, tab 576; tr. 5/61, 63-65) SBN's electrical subcontractor, SME, informed SBN of
    how SME's work was impacted by SBN's unilateral decision to change the stud spacing:
    Truss design was not finished or approved at the time of
    the deck pours. Because of the lack of structural detail
    SME could not give consideration to the placement of
    structural studs and no verbal direction to do so was
    provided by either Jens en Fey or SB []N.
    (R4, tab 784)
    We would have questioned the use of narrow studs because
    of the difficulty of install %"conduit in them. This
    problem also occurs wherever the conduit has to go around
    a comer as the radius of%" conduit does fitaround a
    narrow stud comer. This total of this issue about doubles
    183
    our labor costs for the guest rooms, which also impacts the
    schedule.
    (R4, tab 591; see also R4, tab 578)
    192. On 20 December 2005 SBN forwarded to Botting the revised
    specification for the DDC system that included annotations characterized as
    "now ... accepted by the Owner. Please insure that same is incorporated into your
    design." (R4, tab 579)
    193. By letter dated 22 December 2005 to CO Bartholomew, SBN stated its
    position regarding the corridor ceiling heights and the delayed HVAC LNTP:
    As has been noted through various e-mail's [sic], it is
    understood that the [LNTP] for the HVAC has been held
    up due to the elevations within the corridors being 8'-0". It
    was originally understood that the HVAC LNTP would be
    released upon the resolution of the HVAC controls issue
    on two separate occasions. Currently the continued delay
    to release the HVAC LNTP is adversely affecting the
    project.
    In our follow up of the latest issue (i.e. 8'-4" on FDS sheets
    vs. 8[']-0" on the construction documents), it is apparent
    that this issue was specifically discussed at the 35% design
    review meetings. Reference the attached pdf document
    from the Army in which item #24 clearly indicates that a
    discussion was held and it was apparent that ceilings would
    have to be lowered and it was acknowledged that same
    would not be below 8'-0". In review of the 65%
    documents, it once again was specifically addressed again
    in notes dated 9/17 /2004/9/22/2004 [sic] from the Army
    where in item #44 (attached pdt) it is specifically noted
    regarding a 7'-11" ceiling height in the lobby and it was
    specifically understood that the heights would not go
    below 8'-0". In follow-up, the 65% interim documents
    clearly identified the ceiling heights to be at 8'-0" in the
    corridors.
    Based on the aforementioned, it was clear that all parties
    understood and agreed that the 8'-4" ceiling heights within
    the corridors were unachievable with the design
    requirements and this was accepted at the early stages of
    184
    the project which is evident by the documents provided by
    the Army. As noted in same I it is true that this item has
    not been changed via the change process, but it is clear that
    all parties were amiable to the revision. It is our belief that
    this revision at the 35% documents and 65% document
    review provide agreement with the revised ceiling
    elevations and allowed for the reduction in the ceiling
    height to 8'-0". As such, we request the release of the
    [LNTP] with the HVAC based on the prior agreement of
    the 8'-0" ceilings being acceptable.
    (R4, tab 581; tr. 51147-50)
    194. On 22 December 2005 CO Bartholomew reminded SBN that:
    Your contract technically ends tomorrow and I have yet to
    see your schedule for project completion which I have
    repeatedly requested this fall. This is a contract
    requirement and I need this to issue an interim, non-
    compensable extension, until such time as we meet/resolve
    (hopefully in January 06) on your Request for Equitable
    Adjustment.
    (R4, tab 113)
    195. On 23 December 2005 CO Bartholomew advised SBN that:
    I would have an incredibly hard time believing anyone on
    our end would permit a lowering of ceiling heights without
    a serious discussion and a significant credit. This issue has
    come up on a number of other projects in the past and is a
    Lodging "Hot Button". While the reduction of 4" may not
    have been picked up in our reviews, there has been no
    contractual action taken to lessen the contract requirement
    for ceiling heights in this building. I refer back to a letter
    that is part of the contract signed by an ind[iv]idual who
    signed the bid that [SBN] would be materially compliant
    with the RFP.
    (R4, tabs 114, 586) A week later on 30 December 2005 the CO further advised SBN
    on the subject of ceiling heights:
    185
    Lodging has advised the lowered ceiling height is not
    acceptable I period. You will have to address this prior to
    producing the 100% drawings I even if it delays them. You
    also need to address in RFI 's any areas you think you may
    not comply with RFP before expending time and resources
    (yours and ours).
    (R4, tabs 114, 586; tr. 5174-75, 12/17-18)
    196. On 5 January 2006 COR Dyer advised that:
    The 100% design shall show all corridor ceiling heights at
    8'-4". Also, we are waiting to hear of how many rooms are
    being constructed under the programmed sq footage of 300
    and 450 respectively.
    (R4, tab 590 at 11794; tr. 5/65-67)
    197. By letter dated 10 January 2006 to CO Bartholomew, SBN's Architect of
    Record weighed in on the subject of corridor ceiling heights:
    We acknowledge receipt of your e-mail regarding the
    requirement for 8'-4" ceiling heights. It should be
    specifically noted that the 8'-0" ceiling heights were
    included in the 35% submittal documents and are very
    clearly shown in the 65% and 95% documents and were
    subsequently discussed during the review conferences with
    the Army Team at each phase. The agreement on this issue
    was relied upon to develop the progress drawings and
    therefore shown on the drawings and constructed in the
    field.
    In an effort to accommodate your latest request to revert
    back to the 8'-4" ceiling height, a design meeting was held
    at the site on January 5, 2006 to review options available.
    After numerous discussions and strategies we were unable
    to come up with any solutions to revert to the 8'-4" ceiling
    height (short of tearing the building down and starting
    over).
    Therefore, we believe that the 8'-0" ceiling heights
    aesthetically have no significant impact on the quality or
    186
    performance of the facility and shall remain as previously
    noted.
    (R4, tab 599; tr. 7/278-79; see also tr. 5/53-54, 142-44, 7/236, 9/23)
    198. By letter dated 12 January 2006 SBN responded to CO Bartholomew:
    It is our position that the revision to the 8'-0" ceiling
    heights had previously been accepted through the design
    process, and now we are to understand same not to be the
    case. Therefore, it is requested that a change be issued to
    resolute [sic] the ceiling heights to 8'-0".
    [SBN] is currently delaying the submission of the 100%
    documents per your direction and upon resolution of this
    issue it is understood that we will be able to proceed with
    submission of the applicable documents. In addition, it is
    requested that the LNTP for the HVAC be released at this
    time.
    (R4, tab 115 at 2815, tab 604) COR Dyer considered SBN's position unacceptable:
    The Architect has nothing to corroborate his story that the
    ceiling heights were discussed in each of the design
    meetings. As I stated in the MFR from the 35% design
    meeting, the ceilings in the corridors were shown at ... 8'-4"
    in the design. Therefore, Mr. F[r]itzmeier's assertion that
    the ceilings have always been shown at 8'-0" is false. My
    only suggestion at this point [is] to seek a form of
    compensation for the error and omission. I know this is a
    copout, but what other option do we have except to tear
    down the building and start again? What is really
    disturbing is that Lodging is being asked to accept
    something different than was specifically stated in their
    requirements (again). Why do we always have to bend
    over, especially when it's a clearly written requirement in
    the proposal that we send to hand selected design-builders?
    (R4, tab 115 at 2813, tab 632)
    187
    199. On 20 January 2006 COR Dyer reported:
    [T]he need to go to Ft. Lewis is no more. We had hoped to
    have a 100% design review conference [on 30-31 January].
    Bart and I were also targeting that week to begin the effort
    to sort through the issues composing the REA. Since we're
    at an impasse with the corridor ceiling heights, I have
    asked Bart to intercede with the highest levels of [SBN]
    management in the corporate office in San Francisco. We
    are all tired of being asked to accept things outside the
    scope of the RFP. Once a contract is signed, the Contractor
    is contractually bound to follow the guidance in the RFP
    during the design. We are not responsible to double check
    every little thing when we perform the reviews. Any
    changes to the RFP must be incorporated by means of a
    contract modification.
    [SBN] has reached the end of the rope with me on both the
    Dugway and Lewis projects. I am currently sitting on $1M
    in pay requests and will not process until we reach
    acceptance on the outstanding issues at both projects ....
    [SBN]'s lack of management at both projects is costing the
    Army (Lodging) immeasurable amounts of lost time and
    money.
    (R4, tab 1154; tr. 9/118-20) SBN's LaSharr testified that he was not aware of any
    delays to project performance as a result of a delay in processing of SBN' s pay
    applications (tr. 51151).
    200. On 23 January 2006 CO Bartholomew responded to SBN's LaSharr
    regarding corridor ceiling heights:
    I would like to reiterate what has been passed on in other
    e-mails and telecons. Nothing in the meeting minutes
    authorized any reduction in ceiling heights. Mr. Dyer's
    comments were just that as a result of the meeting on what
    was said. There has been no authorization to lower ceiling
    heights and there would not be a relief from the contract
    requirements without consideration. We have had many
    instances of design variances which is [SBN]'s (the
    design-builder) responsibility.
    188
    We have lost almost a year directly related to the
    recalcitrance of your mechanical subcontractor to provide
    what was required by the contract.
    This project is perilously close to a situation that neither
    side will be pleased with.
    (R4, tab 169 at 4333, tab 617; tr. 3/189-90) He also renewed a previous request to the
    Chairman and CEO of SBN, Gordon Marks, to schedule a meeting about the project
    (R4, tabs 117-18, 617). On 19 January 2006 the following summary was provided to
    Mr. Marks by SBN's Morris in anticipation of a meeting with CO Bartholomew:
    Fort Lewis/ 185 Lodging Units, 4 stories:
    Original Completion Date: 12/24/05
    Current Estimated Completion Date: 9/07/06
    At this time we have (3) significant issues that are being
    discussed.
    1. RFI Approval: They will not review or approve
    RFI's, however, they will not accept the 100%
    documents unless the RFI' s are included in the
    documents.
    2. Corridor Ceiling Heights: The RFP calls for
    8'-4" ceilings in the corridors and during the
    design development it was discussed that with
    the concrete structure and the overall building
    height limitations, this requirement could not be
    achieved. We relied on the Army's agreement
    (via e-mail at the 35% design comments) on the
    8' ceiling heights during the design and the issue
    has re-appeared. They expect a credit, or
    consideration; we have informed Bart that there
    was no cost savings to us to pass along.
    3. Unit Square Footage: over 100 units do not
    meet the RFP minimum requirements. The
    dimension busts are taken off the CAD
    drawings. We will be developing our letter to the
    189
    Owner. Bart is not completely knowledgeable of
    the magnitude of the issue at this time.
    The impacts to the square footage were a result
    of drawing completion and shear walls that were
    added within the building space that affect the
    net rentable area, design deficiencies with the
    architect. There is some confusion as to how the
    square footage was originally calculated; we are
    in the process of figuring this out.
    Units Summary Breakdown
    Less          16 to 21 SF       4 Units
    Less          10 to 12 SF       4 Units
    Less          6 to 9 SF         56 Units
    Less          I to 5 SF         56 Units
    Gain          I to 5 SF         24 Units
    Gain          6 to 9 SF         7 Units
    Gain          12to14SF          3 Units
    Gain          15 to20 SF        5 Units
    Total Square Units Impacted              159 Units
    Total Square Feet Lost                   345 Square Feet
    (R4, tab 621) SBN's Montoya testified that the reduction in room square footage
    occurred when SBN was required to "fur-out" walls to eliminate comer column offsets
    in the rooms (tr. 3/186-88; see also finding 191).
    201. On or about 23 January 2006 CFSC provided comments on Botting's
    DDC Controls submittal which included Johnson Controls products:
    I. GENERAL
    •   REVIEW COMMENTS: "The Controller
    Products submitted for section 15910-2.1 "DDC
    System" not applicable to this paragraph as the
    submitted controllers do not constitute a "DDC
    SYSTEM" under this contract.
    •   Furthermore, the products description and listed
    specification section compliance reference do not
    match in described details for that section,
    paragraph and sub-paragraph. The listed controllers
    190
    are inappropriate for the intended use on this project
    and are conceptually inconsistent with the Fort
    Lewis Design Standards Topology and System
    Architecture which uses a standard PC Workstation
    and Tridium Niagara R2 suite of software to
    integrate field device controls to the enterprise level
    platform Supervisory controllers within a
    distributed control network.
    •   It is evident by the conflict in literature and the
    products listed in the submittal register that ... the
    intended architecture is to provide a system that
    does not provide a Web enabled Supervisory
    Software Application on a Workstation PC Platform
    as specified. The submitted Niagara AX software
    model is not the same version or generation of
    software solutions as the existing original Tridium
    Niagara R2 framework provided by Vykon and can
    [not46] provide the same functionality that is
    bundled with Supervisor AX applications served to
    a browser from an embedded JACE platform.
    (R4, tab 618)
    4. 100% Design
    202. In a letter to CO Bartholomew dated 24 January 2006 on the subject of
    "Ceiling Height/100% Documents," SBN's LaSharr stated:
    As [SBN] is eager to move the project forward, we will be
    offering a reasonable credit associated with revision of the
    ceiling heights. Please note that we make this offer even
    though we still believe that this issue has already been
    resolved through the design submittal process. In advance
    of this offer, we are enclosing 100% documents inclusive
    of all previous design review comments for your approval.
    It is critical that the Army accepts and reviews these
    documents immediately to mitigate the ongoing delays
    caused by the previous refusals to accept these documents.
    46
    It is obvious to us from the context of the surrounding language that the author was
    communicating a lack of functionality as it applied to the proposed DDC design.
    191
    Furthermore, the project cannot continue absent the release
    of the limited notice to proceed for the HVAC with the
    design as submitted in the 95% documents along with the
    subsequent clarifications. We have currently reduced our
    forces and suspended work on all areas that are being
    affected by the failure to provide additional LNTP and
    failure to address RFI' s that are delaying the sequence of
    work (specifically 164, 168, 171, 172, 173, 174, 175, and
    177). Once we have received the additional [LNTP] and
    response to the critical RFI' s we will continue with that
    portion of Work and will advise of the impacts and costs
    associated thereto independent of the REA addressed
    above.
    We hereby request that you forward the appropriate
    [LNTP] for the HVAC scope of work and request an
    expedient review of the 100% documents such that a final
    notice to proceed can be issued in order to mitigate further
    impacts to all parties. This letter also serves as formal
    notification that the Army's failure to accept the 100%
    Documents for review and its failure to issue a [LNTP]
    with the HVAC scope of work has caused, and continues
    to cause, significant impacts to the Project Schedule and,
    potentially, the Project Cost. Consequently, [SBN] will
    continue to perform its contractual obligations pursuant to
    a full reservation of rights.
    (R4, tab 1155)
    203. In emails dated 30 January 2006 SBN requested information from
    CO Bartholomew regarding non-payment of its invoices, citing payment clauses in the
    contract that provided for withholding only 10% retainage (finding 24).
    CO Bartholomew responded that those clauses only apply when the work is
    satisfactory (R4, tab 1157; see also finding 21 (clause H-21-4.1 provides that entire
    payments can be withheld when there is unsatisfactory progress)).
    204. By letter dated 31 January 2006 SBN offered a $10,953 credit as
    consideration for changing certain ceiling heights from 8'-4" to 8'-0" and an $8,492
    credit as consideration for a net reduction of 198 square feet in the room areas in the
    192
    entire project. 47 SBN also enclosed 100% design documents and requested an LNTP
    for the HVAC work as well as the final NTP upon an "expedient review" of the 100%
    design. (R4, tabs 118, 169 at 4018-31; tr. 3/191-93, 5176; see also R4, tab.169 at
    3124) By letter dated 2 February 2006 SBN increased its offered consideration to a
    total of$100,000 (R4, tabs 119, 642, 644; tr. 31194-96). CO Bartholomew responded
    on 3 February 2006 that Army Lodging:
    Authorized [the CO] to accept the two variances for
    corridor ceiling heights, and room sizes only ... for no less
    than $200,000 .... Please be advised the number I was
    provided by lodging was a lot higher than $200,000, but I
    told them that termination and delay costs for
    reprocurement had to be factored into the equation.
    (R4, tab 121at2852, tab 670; tr. 31197-98, 219; see also R4, tab 1158; tr. 3/190) SBN
    accepted the Fund's counteroffer of$200,000 on 6 February 2006 to resolve the
    corridor ceiling height and an unspecified number of guest room square footage
    variances, as well as associated variances (i.e., light switch locations, ceiling fans, etc.)
    (R4, tab 121 at 2851-52, tab 169 at 4339, tabs 645-650, 1159; tr. 3/198-02, 7/279).
    CO Bartholomew later rejected the $200,000 amount (finding 206; tr. 3/202-204). The
    parties continued to negotiate and reached a final settlement of the issues associated
    with ceiling heights and room sizes in the amount of $500,000, reserving only the
    issue of delay (finding 212). SBN's Montoya testified that it was CO Bartholomew's
    near constant threat of termination for default that prompted SBN to agree to a credit
    of $500,000 (tr. 3/204-20).
    205. On 10 February 2006 CO Bartholomew tasked ORB's Monson with
    reviewing SBN's 100% drawings submitted on 31January2006 with respect to the
    room square footage and ceiling height variances (finding 204):
    If the design is at fault, we can call Jensen Fey errors and
    omissions insurance. If constructability is different from
    the design we could terminate or reprocure some or all of
    the construction work deviations under the bonds and then
    also go after the E&O insurance under the A/E of Record's
    CQC responsibilities.
    Something will happen very soon as the contract ends
    21 February and will not be extended without imposing
    47
    (See finding 209 (SBN and Jensen/Fey acknowledged that, of the 185 rooms in the
    project, 127 "vary from the RFP requirement. Of these 127 units, 60 are
    associated with square footage less then [sic] that required by the RFP. "))
    193
    liquidated damages and a high 6 or 7 figure consideration
    offering if it were to be considered.
    (R4, tab 1160)
    206. Also on 10 February 2006, CO Bartholomew provided the following
    information to SBN representatives and copied to CFSC, ORB and Army personnel in
    two emails:
    The situation at Ft. Lewis is approaching a meltdown. In
    addition to at least 34 serious non-conforming rooms, low
    ceilings, and the latest list of other room problems, the
    following is now noted:
    We will not accept a $200,000 credit for all the room and
    ceiling deficiencies noted and had not previously
    considered the issues herein until reporting had verified
    actual conditions. You are strongly urged to review these
    matters as we are.
    (R4, tab 1161)
    207. On 15 February 2006 SBN provided Botting and Jensen/Fey with its comments
    regarding "noncompliance issues associated with the RFP" in Botting's mechanical
    submittal (R4, tab 654). Also on 15 February 2006 there was an "Onity Meeting" attended
    by SBN, SME, Botting and Fort Lewis Lodging personnel (R4, tab 655).
    208. On 16 February 2006 SBN acknowledged receipt of a 23 December 2005
    email from CO Bartholomew granting a unilateral 60-day extension of the contract
    performance period48 however, SBN objected to the 60 days as inadequate and
    expressed its belief that any extension should also be compensable (R4, tab 125 at
    2869). CO Bartholomew responded the same day:
    The 60 day noncompensable extension was granted since
    the Army Lodging Fund may be responsible for up to 60
    days due to some unforeseen site issues we encountered in
    the late fall of 2004. If it is determined that time is
    compensable, or any other additional time, it will be
    48
    We do not find a copy of the 23 December 2005 email in the record, nor is there an
    explanation for why it took SBN nearly two months to acknowledge its receipt.
    194
    granted when we discuss your Request for Equitable
    adjustment and all of the delays and costs the Fund has
    experienced for deficient design and nonconforming
    construction.
    (R4, tab 125 at 2867) Also on 16 '.February 2006, CO Bartholomew emailed SBN's
    Sundgren:
    Ft. Lewis has had some serious delays, deviations and
    variances. As the contracting officer on that one, I am not
    sure of at this writing what we are going to do. That
    contract had a 60 day noncompensible extension until next
    Tuesday - after which liquidated damages are assessible if
    we go forward. We have been blindsided here oflate with
    all kinds of problems that should have been raised a year
    ago. We also, sadly, put up with 18 months of non-
    compliance on the mechanical design - and that is my fault
    because we relied on the trust [SBN] earned on [another]
    project. ...
    (R4, tab 122 at 2855)
    209. On 17 February 2006 SBN and Jensen/Fey acknowledged that, of the 185
    rooms in the project, 127 '"vary from the RFP requirement. Of these 127 units, 60 are
    associated with square footage less then [sic] that required by the RFP" (R4, tabs 120,
    123, at 2858-59, tab 124 at 2865-66, tab 126 at 2871, tab 127 at 2874, tabs 657-59,
    1158). CO Bartholomew responded:
    Gentlemen: We cannot digest all of the impacts and
    information at this time. It appears that if we go forward,
    there will be a need for considerable consideration,
    possibly/probably on the order of$750,000 to $1 million,
    considering all issues, costs and delays.
    In the interim, I will authorize a 10 day non-compensible
    [sic] extension of the contract completion date, from
    21 February 2006 to 3 March 2006. We reserve all rights
    including the right to issue a Show Cause why we should
    continue and not Terminate for Default. I am copying both
    our Deputy General Counsel, and the Senior Contracts
    Attorney on this project.
    (R4, tab 126 at 2870)
    195
    210. On 2 March 2006 SBN recorded the following in a handwritten document
    identified as "Minutes of Mtg":
    SUMMARY
    -    AN AGREEMENT WAS REACHED AFTER SEVERAL
    ROUNDS OF NEGOTIATION IN WHICH [SBN] AGREED
    TO A $500,000 DEDUCTIVE CHANGE ORDER
    -     INCONSIDERATION THEREOF THE ARMY CFSC
    ASSURES THAT
    © NO LIQUIDATED DAMAGES WILL BE ASSESSED
    THRO THE END OF [SBN]'S NEXT SCHEDULE UPDATE
    WHICH WILL INCLUDE THE REVISED MOCK-UP
    PROCESS AGREED UPON IN THIS MEETING
    ~ THE MINOR DEVIATIONS WILL BE FLUSHED OUT
    DURING THE REVISED MOCK-UP PROCESS AGREED
    UPON IN THIS MEETING. A RESOLUTION WILL BE
    AGREED UPON FOR EACH. ARMY LODGING WILL BE
    INFORMED, PRIOR TO PUNCH LIST PROCEEDINGS,
    THAT THE MINOR DEVIATIONS HA VE BEEN AGREED
    UPON AND CONSIDERATION PROVIDED.
    THE REVISED MOCK-UP PROCESS AGREED UPON IN THE
    MEETING INCLUDES THE FOLLOWING STEPS:
    3/7/06     [SBN] WILL PROVIDE RESPONSES TO THE CFSC
    MOCK-UP COMMENTS INCLUDING PROPOSED
    SOLUTIONS
    3/14/06 CFSC WILL RESPOND TO THE ABOVE COMMENTS
    AND PROPOSED SOLUTIONS.
    3/17 /06 [SBN] WILL ISSUE A REVISED PROJECT SCHEDULE
    TO INCLUDE THE REVISED MOCK-UP PROCESS AND
    THE IMPLEMENTATION OF THE SOLUTIONS TO THE
    MINOR DEVIATIONS.
    3/21106 AN ON-SITE JOB WALK WILL BE HELD WITHIN
    THRU    THREE WEEKS OF 3/2 l/06 AT WHICH ALL ISSUES
    196
    4111106 WILL BE REVIEWED AND FINALLY RESOLVED.
    3131106 100% DRAWINGS WILL BE SUBMITTED
    INTEGRATING THE RESOLUTIONS TO THE MINOR
    DEVIATIONS.
    (R4, tab 1168)
    211. CFSC conducted a second Mockup Rooms Inspection on 9 March 2006
    (R4, tab 1169).
    212. On 30 March 2006 CO Bartholomew and SBN's regional director
    Sundgren executed contract Modification No. P00003 which incorporated by reference
    the parties' 23 March 2006 settlement agreement:
    a. Subject Contract is hereby modified to reduce the sum
    of the contract by $500,000.00 in accordance with the
    attached Settlement and Release Agreement, dated
    24 March 2006.£491A new completion date will be agreed
    to by the parties and codified in an appropriate
    modification to follow.
    b. Previous Contract Price               $17,397,806.26
    Modification P0003                       (500,000.00)
    New Contract Price Not to Exceed      $16,897 ,806.26
    c. All other terms and conditions of the aforementioned
    contract remain unchanged and in full force and effect.
    (R4, tabs 68, 371) The attached Settlement and Release Agreement provided:
    C.      [SBN] and CFSC desire to fully compromise and
    settle all current disputes between them regarding certain
    Project design nonconformance issues relating to the
    Project, as more fully described below, without the
    admission of liability on the part of either [SBN] or CFSC.
    49
    The actual date on the settlement agreement is 23 March 2006 (R4, tab 371; see also
    finding 210).
    197
    1.      Settlement Amount. The Parties agree to a
    settlement amount of... $500,000 .. .in full and complete
    satisfaction of all known claims and disputes between
    [SBN] and CFSC which are in any way related to the
    Project which either Party may have as of the date of this
    Settlement Agreement except as expressly reserved herein.
    The Parties agree that the Contract price shall be reduced
    in the amount of $500,000 upon execution of this
    Settlement Agreement by both parties and issuance of an
    appropriate modification to the Contract by the authorized
    CFSC Contracting Officer.
    2.      Release. Upon execution of an appropriate
    modification to the Contract, the Parties, on behalf of
    themselves and all of their respective predecessors,
    successors, affiliates, administrators and assigns, hereby
    release and forever discharge the other and each of their
    respective officers, directors, employees, predecessors,
    successors, affiliates, and assigns, of and from any and all
    claims, liabilities and causes of action relating to those
    issues identified in paragraph 3 of this Settlement
    Agreement and subject to the reservation of rights in
    paragraph 4. The claims released hereby are hereafter
    referred to as the "Released Claims," and the Parties giving
    a release hereunder are hereafter referred to as the
    "Releasing Party(ies)." In addition to the foregoing, CFSC
    expressly waives any right it has or may have to assess or
    seek liquidated, direct or consequential damages related to
    any actual or alleged deficiency under the Contract related
    to the Released Claims.
    3.     Released Claims. The following are the Released
    Claims and are related to variations in the Contract's
    requirements.
    A.     Ceiling Heights. CFSC accepts [SBN]'s
    proposed ceiling heights as shown on the construction
    documents (including construction drawings), including,
    but not limited to, those ceiling heights within the corridors
    of the Project which are reduced to eight feet (8'-0") and
    the ceiling heights in G-28, G-39 and G-51 units which are
    reduced from an eight feet, four inches (8'-4 ") requirement
    to eight feet (8'-0").
    198
    B.      Square Footage. CFSC accepts [SBN]'s
    revisions to all floor plan square footage and configuration
    requirements for individual rooms in the Project whether
    the proposed square footage and configuration is either
    more than or less than the requirements of the Contract,
    including necessary adjustments to individual room
    components.
    C.      Impacts Resulting From Ceiling Height or
    Square Footage. The Parties acknowledge that there are
    and may be direct or indirect impacts to the design of the
    Project resulting from the changes to Ceiling Heights
    and/or Square Footage as described herein. The Parties
    agree that reasonable changes in the configuration,
    variation and location of, by way of example, light
    switches, furniture, PTAC units, doorway entry widths,
    door swing direction, bedroom door configuration in
    family suites, closet widths, window blinds and draperies
    which are either directly or reasonably related to the
    changes to Ceiling Heights and/or Square Footage will be
    accepted if such changes meet all performance
    requirements of a facility of the type and size contemplated
    in the Contract, including, but not limited to those related
    to the Americans with Disabilit[ies] Act, safety and
    functionality. [5o1
    D.     Memorialization of Changes. The Parties
    acknowledge that at the time of final acceptance of the
    Project there will be changes in the final product as a result
    of this Settlement Agreement. Accordingly, the changes to
    which the Parties agree shall be incorporated into the
    Construction Documents (100% Design Submissions) and
    will be accepted by the Army as a baseline for final
    acceptance of the facilities.
    4.     Reservation of Rights.
    Except as expressly provided for in this Settlement
    Agreement, [SBN] and CFSC reserve all of their rights
    50
    Ms. Moinette agreed that the reduction in the room sizes from the sizes required by
    the RFP presented no functional or visual impacts to lodging guests (tr. 12/44).
    199
    under the Contract. Notwithstanding any provision of this
    Settlement Agreement, [SBN] expressly reserves its rights
    to assert a request for equitable adjustment and/or a claim
    for time and associated cost impacts which result from or
    are in any way related to the Contract. CFSC agrees,
    pursuant to the Contract, to review and consider any
    request for equitable adjustment and/or claims submitted
    by [SBN].
    6.      Covenant Not to Sue. The Releasing Parties agree
    that they will not institute, cause to be instituted or
    participate or cooperate in the institution of any claim,
    action or litigation against any Released Party in which
    liability is sought in any way to be predicated upon any of
    the Released Claims.
    7.      No Admission of Liability. [SBN] and CFSC have
    entered into this Settlement Agreement solely for the
    purposes of avoiding the expense and inconvenience of
    contesting the claims, with potential subsequent litigation.
    By entering into this Settlement Agreement, neither [SBN]
    nor CFSC admits liability or wrongdoing of any kind, and
    in fact each continues to deny that it has engaged in any
    wrongful conduct or is in any way liable to the other
    concerning the Released Claims.
    (R4, tabs 68, 371; see also finding 259) Reading the express terms of Modification
    No. P00003 as a whole, and harmonizing its terms as much as possible51 , we find that
    SBN agreed in Modification No. P00003 not to submit claims for anything other than
    time and associated cost impacts where the subject of the claim was either a dispute in
    existence prior to 23 March 2006 or was associated with the "Released Claims" of
    ceiling heights, square footage and/or impacts resulting from them.
    213. On 4 April 2006 SME reported to SBN that SBN' s superintendent,
    Bowman, "called the military police onto the site yesterday, directing them to speak
    with our superintendent ... Padgett" when he refused to leave SBN's trailer until he got
    an answer to his question (R4, tabs 703-04). The personality conflict between SBN's
    Bowman and SME's Padgett continued through June 2006, when Mr. Padgett was
    51
    LAI Services, Inc. v. Gates, 
    573 F.3d 1306
    , 1314 (Fed. Cir. 2009).
    200
    asked to leave the 20 June 2006 subcontractor meeting (R4, tab 773), and July 2006
    (R4, tabs 772, 778).
    214. On 5 April 2006 the CO asked when SBN would submit updated 100%
    design documents that included the issues of door swings and light switches in 17
    extended-stay rooms which he identified as "a Contracting Officer directive" (R4,
    tabs 130, 707). SBN considered "these changes [to] fall within our recent settlement
    agreement, Modification #3, paragraph C" and stated its intention to "submit an
    appropriate change request" and to submit updated 100% design documents on
    10 April 2006 (R4, tabs 130, 707). SBN confirmed that it had hired a third-party
    inspector to review Botting's mechanical work and COR Dyer stated that he intended
    to have ORB/BCE also provide "an extra measure of oversight" (R4, tab 707).       ·
    215. In a handwritten document dated 20 April 2006, signed by both
    CO Bartholomew and SBN's LaSharr, it was agreed that:
    The NAFI hereby authorizes a mechanical Notice to
    Proceed for all mechanical/RVAC/Plumbing, subject to an
    RFI verification/acceptance of the RBI Boiler and
    restamped drawings, effective this date.
    (R4, tab 1171; tr. 5/77-78)
    216. On 4 May 2006 SBN provided to its architect and subcontractors the
    following schedule for "completion of 100% submittal documents (both drawings and
    specifications":
    May 4 I May 8 Jensen Fey to forward updated
    backgrounds to all designers.
    May 4 I May 8 Designers to incorporate as-built
    conditions and RFI' s into documents (only RFI' s with
    Army CFSC Response)
    May 8 I May 12 Designers incorporate updated
    backgrounds and make adjustments to coordinate the
    documents. Drawings must be stamped by licensed
    engineer. Drawings must have updated title block with
    correct date of May 15, 2006, lOOo/o Submittal.
    May 15 All Designers to have updated, coordinated plans
    and specifications in our office for [SBN] review, printing,
    and distribution to the Army.
    201
    These dates cannot slip, as submittal of these
    coordinated documents is critical to the forward
    progression of this project.
    (R4, tab 733; tr. 9/182-85)
    217. On 4 May 2006 SME identified numerous errors and conflicts in SBN' s
    most recent project schedule:
    After reviewing the schedule from SBN[] it appears that
    who ever [sic] put this schedule together has not followed
    the agreements that have been previously made by Rick
    LaSharr and our team. The start and finish dates for each
    area according to the new schedule has overlapping
    occurances [sic] for every area. Also they are showing
    SME to go into the rooms 4 different times. Wall rough-in,
    ceiling rough-in, finish trims, and Dwyer install will need
    electrical connections made up. If we were to follow their
    current schedule we would need to double even our most
    recent manpower calculations. The schedule also has many
    occurances [sic] with trades stacked into rooms to do trim
    outs with very minimal days to do the work. The schedule
    also has areas of work that are already shown completed
    that we have not been able to work in i[.]e. the Lobby
    Area. The schedule does not show anytime allowed for
    walkway lighting or canopy lighting. This schedule does
    not match the 4-week look ahead schedule issued to the
    Subs. Bottom line is that this schedule has many conflicts
    and needs to be fixed.
    The substantial completions have moved ahead about 3
    months.
    (R4, tab 732)
    218. As of the 18 May 2006 progress meeting COR Dyer reported:
    1. The 100% design will be finalized and distributed
    middle of next week (May 24 )....
    2. The next CFSC site visit is intended to "kill 2 birds with 1
    stone". Review/inspect the mockup rooms and conduct a
    100% design review meeting. IF [SBN] does provide the
    202
    design as stated by the above date, and IF [SBN] does
    complete the work for the 2 mockup rooms, the earliest that
    CFSC will make the site visit is the week of June 12 ....
    3. You said that I cancelled the May 29 on site review by
    CFSC. May 29 is a federal holiday, Memorial Day. The
    cancellation of the site visit discussed during our April
    visit is being done because the mockup rooms are not
    "guaranteed" to be finished by the scheduled date.
    Rick LaSharr told me/us in April that the mockup rooms
    would be completed by middle of next week. During
    yesterday's discussion, you admitted this was not possible.
    Therefore, the decision to cancel the site visit to review the
    mockup rooms had to be made.
    (R4, tab 132)
    219. On 23 May 2006 COR Dyer advised that SBN had delayed the
    submission of its 100% design documents further:
    Rick LaSharr, [SBN] Project Manager, informed me today
    that the 100% design is "potentially" not going to be
    shipped out this Friday, May 26. If so, this will not allow
    us 2 full weeks of review time prior to the week of
    June 12, which was supposed to be the week after the
    mockup rooms will be finished. As you know, we have
    cancelled next week's journey to Lewis because of carpet
    delivery issues, etc. [see e.g., R4, tabs 750, 755]. Unless
    everyone wants to go to Lewis in back-to-back weeks, I
    don't think it's wise to separate both functions.
    (R4, tab 749) Also on 23 May 2006, SBN advised CO Bartholomew that the mockup
    rooms would be complete by 12 June 2006 (R4, tab 751). CFSC experienced a "'travel
    lockdown" that precluded travel by CO Bartholomew and COR Dyer from Virginia to
    Fort Lewis for the scheduled walk-through of the mock-up rooms and the 100% design
    review meeting during the week of 12 June 2006. COR Dyer notified SBN of the
    lockdown and advised that the events scheduled for the week of 12 June 2006 would
    be rescheduled as soon as the lockdown was lifted. (R4, tab 169 at 4046) The events
    were rescheduled to take place on 11-12 July 2006 (id. at 4055).
    220. By letter dated 30 May 2006 SBN notified SME "that the current schedule
    is being driven by SME and is affecting the completion date of the project" (R4,
    tab 757). On 31 May 2006 SBN forwarded CO Bartholomew's direction to install
    203
    outlets beneath the PTCA units to SME. SME responded that "[r]edoing the 2
    mockups is 1 thing, but we have already roughed-in 22 additional units and counting."
    (R4, tab 759) SME estimated that the roughed-in outlets at 40 PTAC units would
    require relocation (R4, tab 762).
    221. On 26 June 2006 SME notified SBN that SME could not complete its
    scheduled rough-in work at nine (9) listed locations due primarily to incomplete work
    by the framing subcontractor who assured SME "he would do what he could but at
    some locations he was waiting for HVAC to be completed before he could continue
    (R4, tab 769). On 2 August 2006 SME notified SBN that, per SBN's Schedule S46V,
    its work was being delayed 16 days by lack of framing and "HVAC shaft duct work
    not done" (R4, tab 782).
    222. On 11August2006 SBN provided to the CO SBN's responses to the
    100% design review comments (R4, tab 133).
    223. On 9 October 2006 COR Dyer emailed the following to CO Bartholomew,
    ORB/BCE representatives and Stedman regarding the importance of the mock-up rooms
    and SBN' s quality control procedures:
    [Bob Monson,] I also want to speak to you about the
    schedule to have both mock-up rooms completely finished
    and truly becoming the standard for workmanship and
    quality. After the mess I saw, we must emphasize to [SBN]
    the importance of these two rooms, and how they indeed
    establish the level of quality and workmanship throughout
    the entire facility .... It may be beneficial to get the team
    assembled once more to have one final look at both rooms
    and stress to SBN[] how we plan on conducting our
    pre-final (shortly after Thanksgiving?) ....
    PS-Modification P00004 established a contract completion
    date of February 12, 2007. Just 4 months away? Bart, I
    asked Rick [LaSharr] to take one more "hard" look at his
    schedule and to once and for all determine his date. I have
    a sneaky suspicion that he'll be coming back to us asking
    for March 1 or March 15. Either date is fine with me. I just
    wanted [SBN] to understand that the QC pre-final
    inspection and correction of the Architect's/Engineer's of
    Record list(s) must be done within the contract time.
    Before [SBN] declares that they are ready for the
    204
    Government's pre-final, we' 11 have a signoff by the
    Architect and Engineer's [sic] that their punch lists have
    been satisfactorily completed in accordance with the
    Quality Control plan and workmanship and quality
    established in the Mock-up rooms.
    (R4, tab 816)
    224. On 12 October 2006, several years into the contract, Jensen/Fey asked SBN
    what Jensen/Fey's responsibility was as CCQC as it related to coordination with the
    various subcontractors and inspection of their designs and installations (R4, tabs 819-20).
    225. By agreement dated 20 November 2006, and executed on 21 November
    2006, SBN agreed to pay Botting against its claim as follows:
    c. Any payment to [Botting] required above under
    Paragraph 2(b) is expressly conditioned and contingent
    upon the outcome of the litigation between [SBN] and
    Owner and [SBN] 's actual collection of sums from Owner
    for [Botting]'s Pass-Through Claim.
    h. . .. [I]t is specifically agreed that [SBN] shall be
    liable to [Botting] only to the extent that the Owner is
    liable to [SBN] for such sums ....
    (R4, tabs 842, 1180; tr. 4/64-66) Similar agreements were made with Paras (concrete
    subcontractor) on 27-30 November 2006 (R4, tab 1181), Jensen/Fey on 1 December
    2006 (R4, tab 1182), and SME on 1November2007 (R4, tab 1200).
    226. On 22 December 2006 CO Whitley issued a Letter of Concern to SBN
    stating that SBN's 6 December 2006 project schedule showed a loss of production on
    the critical path of 30 calendar days and requesting a ''viable Recovery Plan" within 5
    days. SBN replied that it would respond after the holidays. (R4, tab 135)
    227. Modification No. P00005, dated 4 January 2007, provided notification
    that, effective immediately, CO Whitley replaced CO Bartholomew as the assigned
    contracting officer; the modification also formally accepted SBN' s 100% design and
    issued a full NTP for construction of the project. There was no change to the project
    completion date of 12 February 2007. (R4, tabs 136, 860; tr. 5/91, 95-100,
    12/164-165; finding 223)
    205
    5. Project Completion
    228. As of 8 January 2007 Jensen/Fey had not provided updated Daily Reports to
    ORB's Monson as requested; Monson advised that SBN's December 2006 pay request
    for $870,000 would not be processed until the Daily Reports were received (R4,
    tab 1183; tr. 9/118-20). Again on 18 January 2007, Monson reported that SBN had not
    provided Daily Reports "since around the last part of October [2006]" (R4, tab 1185).
    229. The 17 January 2007 Progress Meeting #52 minutes contained the
    following items pertinent to the service gate and intercom:
    Hydr[au]lic Gate
    1216106 Rick provided new proposed design to Drew
    [Dyer]. Drew was satisfied with the proposal, but
    requested a formal submittal. SBN[] will provide submittal
    information with pricing. SBN[] will provide cost/credit
    info associated with gate to CFSC by 12/13.
    12/14/06 SBN[] forwarded pricing info to CFSC.
    12120106 Sheryl requested a method for lodging personnel
    to open the gate w/o interaction with the front desk. This is
    not called for in the RFP. SBN[] will provide intercom
    submittal. Rick will provide associated pricing with
    intercom. The Delta Scientific gate and associated labor
    was deducted and the new gate and labor was added. The
    new gate will require additional electrical lines to power
    the second boom.
    12/27/06 CFSC to approve hydraulic gate.
    1/3/07 CFSC to approve hydraulic gate.
    1/17/07 Direction to proceed provided by [CO]
    Reginald [Whitley], but no modification bas been
    issued.
    Intercom/Extention of Phone System
    1216106 Drew requests copy of intercom submittal. There
    is a meeting at 9:00am on 12/7 with SME, Onity, Jensen
    Fey, and SBN[] to coordinate the operation of intercom,
    front doors, and hydraulic gates. SBN[] will forward
    intercom submittal to CFSC after 12/7 meeting.
    12/14/06 Rick to forward submittal.
    12120106 Intercom is not required to be separate from
    phone system per RFP. Duane consulted the DOIM
    206
    Communications officer and determined that the
    government does not prohibit the simultaneous use of their
    lines, but stipulates that the government will not be liable
    for any problems on lines connected to other systems.
    Intercom will be installed separate from government lines
    and Rick has forwarded associated costs to CFSC. Drew
    will recommend to [CO] Reginald [Whitley] that CFSC
    disapprove increase[ d] costs associated with separate
    intercom lines. Rick requests CFSC issue direction
    quickly.
    12/27/06 [CO] Reginald [Whitley] to provide direction.
    1/3/07 [CO] Reginald [Whitley] to provide direction.
    1117/07 Intercom will not be tied to phone system.
    Direction to proceed provided by [CO] Reginald
    [Whitley], but no modification has been issued.
    (R4, tab 169 at 4101, 4109-10)
    230. As of 18 January 2007 Botting's DDC specification submittal still did not
    meet all the RFP requirements as it was deficient in 29 specification sections (R4,
    tabs 1186, 1187). The list of deficiencies was provided to SBN on 17 April 2007 (R4,
    tab 1184 at 3125).
    231. On 25 January 2007 CO Whitley requested from ORB a copy in
    electronic form of all documentation associated with this project in order to respond to
    a FOIA request (R4, tab 1189; tr. 101109-12).
    232. In an Information Paper dated 2 February 2007, CO Bartholomew52
    reported the following information to Army Lodging's Ms. Moinette:
    SUBJECT: Status ofNonappropriated Fund (NAF)
    Contract for New 185-Room Army Lodge at Ft. Lewis,
    WA
    1. Purpose: Advise CG ofNAF construction contract for
    the new Army Lodge at Ft. Lewis, WA
    2. Project Overview: A design-build contract was
    awarded in May 2004 to [SBN], Bellevue, WA, for
    52   CO Bartholomew was no longer the assigned CO for the project as of 4 January
    2007 (finding 227), but was reassigned again effective 1 February 2007
    (finding 234).
    207
    $17,359,397. Contractor design delays and subsequent
    project delay resulted in a negotiated contract reduction
    of $500,000 in March 2006. The project completion date
    was extended to February 2007. Construction work is
    good to very good.
    3. Background.
    a. Project Scope. This Army Lodge project
    includes the construction of a new 185-room Army
    Lodge to be integrated into a three-building "campus".
    The Contractor is responsible for both the design and
    construction of the new building. Renovation of the
    second existing building in this complex is under design
    review and project development for award to another
    contractor.
    b. Recent Changes. Two months of additional
    delays have resulted in a further delay of the project
    completion date from February 2007 to mid-April 2007. It
    will take an additional 4 to 6 weeks to correct minor
    deficiencies and load the furniture into the building.
    Soldiers can begin to occupy the building in late May
    2007. Routine change orders in progress will not further
    delay the project.
    c. Pending Development Plans. The NAF
    Contracting, Construction and Army Lodging staffs are
    conducting weekly progress review meetings and
    teleconferences to ensure all aspects of the project come
    together for May 2007 occupancy.
    4. Related Issues:
    a. Two of [SBN]'s subcontractors are seeking
    additional money from the contractor. They have
    submitted Freedom of Information (FOIA) requests to
    FMWRC. Other issues in dispute with the Contractor are
    currently under Contracting Officer review. These issues
    will not delay project completion.
    b. The storage and staging for the furniture, fixtures
    and equipment (FFE) for the new facility is being closely
    208
    worked by the project team to ensure smooth transition and
    storage cost control.
    (R4, tab 1191)
    233. On 13 February 2007 SME provided to SBN a list of its work items that
    were unable to be completed by "the date of the owner punch (3/13/07)" due to work
    still remaining to be done by other trades (R4, tab 873).
    234. Modification No. P00006, dated 16 February 2007, formally assigned
    CO Bartholomew again to the Fort Lewis project, effective 1February2007 (R4,
    tabs 137, 870; tr. 5195, 12/164-65). On 16 February 2007 he directed SBN to proceed
    with "a complete Duress Alarm System" and providing a bead of clear caulk at
    specified locations (R4, tabs 876-77).
    235. On 20 February 2007 CO Bartholomew signed Modification No. P00004
    in the amount of $252, 154.20 as compensation for 13 items of previously directed
    changed work; the modification also revised the contract completion date to
    12 February 2007 (R4, tab 134). We have found no explanation in the record for why
    the modification shows an effective date of 6 October 2006.
    236. Modification No. P00007, dated 23 February 2007, established final
    pricing for the 13 items of work listed in Modification No. P00004 by decreasing the
    contract price by $14,273.00 and extending the contract performance period 60 days
    from 12 February 2007 to 13 April 2007 without additional compensation. The cover
    page of the Modification included:
    The NAFI reserves the rights to determine if liquidated
    damages are assessible [sic] and the Contractor reserves
    their right to seek authorized or comepensible [sic] time.
    (R4, tabs 138, 883) However, the detailed list included in the Modifications stated:
    14) Add 60 days to the contract completion date without
    assessment of liquidated damages or additional
    compensation. Both the NAFI and Contractor reserve
    their rights to revisit this extension. The new contract
    completion date is 13 April 2007.
    (Id.)
    237. By letter dated 28 March 2007 the Architect of Record expressed its
    determination that the project was substantially complete and requested a pre-final
    209
    inspection be scheduled two weeks later (R4, tab 139; tr. 5/101-05, 7/279-82). The
    next day SBN sent a letter to CO Bartholomew formally requesting a pre-final
    inspection. CO Bartholomew scheduled the pre-final inspection to begin on or about
    16 April 2007. (R4, tab 140; tr. 5/105-07)
    238. On 2 April 2007 SBN's LaSharr requested information from Botting
    regarding the installed DDC controls which did not permit workstation access to the
    building control system and "the LON cards that continue to be an issue" (R4, tab 1192).
    239. On 30 April 2007 it was discovered that SBN had not provided the DDC
    software required by its own DDC specification dated 28 November 2005.
    CO Bartholomew requested that SBN do so before requesting a final inspection. (R4,
    tabs 141, 892) SBN responded that it had already requested that Botting do so (id.).
    CO Bartholomew advised that a final inspection would not be scheduled until the
    software was installed and tested. In addition:
    We also will need resolution of the punchlist for the
    interiors and any technical comments from our consultants
    revised. It is our intent to transmit our formal list within
    the next week.
    (Id.)
    240. Modification No. P00008, dated 3 May 2007, increased the contract price
    by $313,854 for 20 listed items of previously directed and changed work. The
    Modification specifically reserved the Fund's right to consider assessment of
    liquidated damages and reserved SBN' s right to seek an extension of the performance
    period for any associated delays to the critical path. (R4, tabs 143, 895)
    241. On 8 May 2007 CFSC provided to SBN the Pre-Final Inspection punchlist
    which was "only for the areas that could be inspected and did not include an exterior
    inspection of the building" (R4, tab 144).
    242. A "DDC Conference Call" was held on 15 May 2007 which resulted in
    the following:
    1. [SBN] will issue direction today to [Botting] to
    provide/install Workplace Pro and Lonmaker software[.]
    Automated Controls will install software [see also, R4,
    tab 205]. Lead time is short.
    2. The Notebook computer referenced in Spec 15910
    Section 2.1.5 .1 is not required.
    210
    3. [Botting] will provide to [SBN] by Friday a copy of all
    commissioning documentation, the T &B report, and a
    response to the Owner's DDC RFI.
    4. Automated Controls will provide by next Tuesday,
    5/22/07, all control parameters specified in Spec 15910
    Section 2.1.3.2 or a response clarifying why a specific
    parameter listed can not be provided.
    5. Following #4 (above), Randy Hieburg [sic] (BCE) will
    meet onsite with Automated Controls, [Botting], [SBN]
    and DPW. Automated will then demonstrate compliance
    with Spec 15910, including each available setpoint, etc.
    Randy Hieburg [sic] will then clarify, if necessary, what
    additional points are required to conform to Spec 15910.
    (R4, tabs 145, 897, 1199) BCE's Heiberg testified that:
    [T]he system wasn't usable, there were some concerns that
    were raised by [DPW] ... and what we found was that the
    JACE, the system was extremely slow, there were points
    that hadn't been commissioned, so things weren't working,
    things weren't controlling. There were graphics that would
    cue up as you looked at a piece of equipment, but
    extremely slow, and there were operational issues with
    ventilation equipment, serving the ventilation air to all the
    rooms. They were cycling, burners were coming on and
    going full fire and then shutting off, and full fire and
    shutting off.
    So temperature swings all over the place, and once
    we got into it in a few more details, we discovered that a
    single JACE panel had been installed, and all of the
    graphics-I mean a global controller has certain memory
    capabilities, it's not a big PC, and they had graphics
    resident on this while all of the controls for the building
    were being-so basically the architecture needed some
    tweaking in their design of their system. The graphics
    should have been, and were later moved to another
    controller so they weren't inhibited by serving up the
    graphics that the controller, the main controller, the main
    JACE was being used to control all the hard points and
    hardware, the control functionality of all of the equipment
    connected to it.
    211
    There was another, I believe at some point, another
    controls contractor that came in and took care of some of
    those issues.
    [A] global controller is the next step up in an
    architecture from a unitary controller. A heat pump serving
    this room would be a unitary controller. It would talk to the
    next level up, which would be a global controller .... Then
    that global controller would talk to 31 other global
    controllers if this was a huge complex .... And then you
    could go up to the next level to a piece of equipment. Well,
    they basically tried to put way too much equipment and
    graphics serving requirements on one global controller
    serving the whole building. So the design was somewhat
    flawed inasmuch as they taxed-I mean, it would
    eventually serve it up, but it made the system so slow that
    it wasn't usable ....
    So while the machine is serving up graphics, it's
    trying to make computations to decide what to do with the
    heat pump that it's controlling also, ... , or some other
    piece of equipment. So it had to time share, it just simply
    had too many tasks to do.
    [The issue was resolved when] [t]hey put in a
    server, a graphics server, site based to take care of all the
    graphics.
    (Tr. 111144-46) Mr. Kommers, SBN's expert witness, testified that the slowness of
    the system was because CFSC had required more than the RFP did in the way of
    graphics and interface (tr. 13/78-79).
    243. The final 100% design drawings and specifications are dated 15 May
    2007 (R4, tabs 1175-76).
    244. On 24 May 2007 SBN advised Botting that there were still errors in the
    DDC computer system being able to communicate with the units. SBN also stated that
    it had not received "the commissioning check list or response to the RFI as requested
    numerous times." (R4, tab 900)
    245. On 24 May 2007 COR Dyer recommended to CO Bartholomew that the
    project be "conditionally" accepted on 25 May 2007:
    212
    We provided [SBN] with copies of the final remaining
    items yesterday and today. [SBN] did an outstanding job of
    reducing the interior punch list from almost 4,000 to
    approx. 120 as the team ended day one of the final
    inspection. The leftover items were being corrected today
    and will continue tomorrow. There are a few items on
    order (mirrors, refrigerator doors, etc). I may be able to
    check off several more items before the day ends
    tomorrow.
    The quality and level of work is outstanding. The spirit of
    cooperation and upbeat attitude of everyone on the job was
    very refreshing considering recent projects.
    (R4, tab 146) That same day, CO Bartholomew formally notified SBN's Montoya by
    letter that:
    The Army Lodging Final Inspection Team has been
    on-site this week evaluating the work [SBN] has done on
    the Pre-Final Punch List items, previously provided to
    [SBN], and other work not previously reviewed or
    inspected at the new Lodge. I am pleased to report the
    Team has been impressed with the work done to correct
    items on the Pre-Final Punch List. There has also been
    significant work done on the outside of the building. I also
    received other positive comments regarding [SBN' s]
    cooperation, positive attitude, and efforts to complete this
    project.
    In view of the foregoing, the Fund will
    Conditionally Accept the new Ft. Lewis Lodge tomorrow,
    May 25, 2007. The one-year Warranty of Construction will
    then begin for all accepted work. The items reported to me
    that condition the building acceptance are:
    1.     Mechanical equipment, to include DDC's and
    Specification 15910. This includes receipt of all
    appropriate software licenses.
    Tomorrow will also be established as the
    Conditional Beneficial Occupancy Date/Substantial
    213
    Completion Date (with conditions). Ft. Lewis Army
    Lodging will also take control of the building tomorrow.
    All card keys, and keys to locks accessing the building, are
    to be turned over to Ms. Cindy Moinette, Lodging
    Manager, or staff she specifically designates to receive
    them. Beginning tomorrow, all access to the building, by
    [SBN] and their subcontractors, to complete the work
    above and other punch list items, will be requested
    through, and controlled by, Ms. Moinette or her designated
    staff. Please ensure the Fund Project Manager, Mr. Drew
    Dyer, is copied on all written and e-mail communications.
    A Final Inspection Punch List will be provided as
    soon as it is available. A stairwell and exterior punch list
    (essentially a Pre-Final Punch List for those areas), as
    received, will be provided to you today by e-mail. Please
    inform the Fund's Project Manager, and the undersigned,
    when all remaining items of work have been completed.
    We appreciate your efforts to complete the
    remaining work, while we perform other work in the
    building, and trust it will be done as quickly as possible so
    that we may begin closing out the contract. We look
    forward to opening the new 185-room Army Lodge for
    Soldiers' use.
    (R4, tab 147; tr. 5/107; see also R4, tabs 1193, 1207 at SUPP-118)
    246. Ms. Moinette testified that, as originally awarded, the project was
    supposed to be complete within 18 months but that, as a result of the delayed
    completion, Army Lodging suffered actual damages:
    [I]t was a big impact as far as sending bed nights off post,
    because we were so busy. Therefore, not only did we lose
    the income, also the travel account and expenses increased,
    because they had to pay downtown rates rather than our
    rates, which are normally 50 percent of per diem.
    When I did a scale to see approximately how much
    actually [sic] revenue was lost, it was about 2.5 million
    dollars because of the late opening of the lodge. I mean,
    that's two summers that were critical.
    214
    [T]hen you run into that they have to have transportation.
    And having soldiers off post is very difficult if they are not
    entitled to have a rental car.
    Some of them do not get authorized rental cars. So,
    therefore, it was an issue if your family is coming from
    Europe, they don't have transportation. So, that becomes a
    bigger issue that they have to take their family downtown
    without vehicles.
    I sent way over 120 some thousand bed nights off post in
    one year.
    (Tr. 12/27-29) We find no evidence that liquidated damages were assessed against SBN.
    247. Almost three months after CFSC took beneficial occupancy of the Lodge
    (finding 245), 13-15 August 2007 was set as the date for the demonstration and
    acceptance of the DDC along with the provision of:
    [T]he final testing and balance report(s), commissioning
    and start-up reports, O&M manuals, record drawings, and
    all other appropriate documentation.
    (R4, tab 905 at 12834) On 31 July 2007 CO Bartholomew expressed frustration to
    SBN that "Botting is jerking you, and us, around and it needs to stop (R4, tab 905 at
    12835). By return email dated 2 August 2007 SBN responded that:
    We have reviewed the submittal that we received from WA
    Botting and find same not to be complete. We met with
    them today, and they are going to review the issues with
    the controls contractor. We can send you what we have,
    and advise what is missing, but I know the preference is to
    get all the information.
    I am very aware that this is not what you wanted to hear.
    (Id. at 12833) CO Bartholomew replied:
    Your assessment is correct! [COR Dyer] has set aside the
    13th and 15th of August for us to wrap this up. WE NEED
    TO DO IT THEN!
    215
    I will also be available during that time. It is imperative we
    get the documents and schedule the demonstrations those
    days. The hotel is opening and the installation has raised
    this and other issues.
    We have privity of contract with you. Please do what you
    need to do to make this work so we can energize our
    consultant(s) [ORB/BCE] to assist. I do not want this to get
    ugly after the building has turned out so well in almost all
    other respects.
    (Id.)
    248. By 15 August 2007 the DDC software installation, testing and
    documentation had still not been provided and SBN was concerned:
    [CO Bartholomew] called and he is threatening to call the
    bond on the Fort Lewis project today ifhe does not receive
    the software and response for the DDC. Problem is that the
    systems cannot be balanced and filters are clogged. Work
    is required. If they do not receive the software and a
    response to the warranty or problematic work today they
    will procure all necessary materials and services to
    complete the work and charge against our bond.
    (R4, tabs 907, 1195)
    249. On 17 August 2007 SBN issued a "Notice to Cure Subcontractor Default"
    to Botting:
    This letter serves as formal notification that W .A. Botting
    is in default of its contractual obligations with [SBN] on
    the above-referenced project. ... W.A. Botting is directed to
    immediately comply with all project requirements. As
    described in previous correspondence, W.A. Botting has
    materially breached the contract ....
    Per the Subcontract Terms and Conditions, W.A. Botting is
    liable for all costs, direct and indirect, related to the delays
    and disruptions caused by W.A. Botting's failure to
    216
    perform its contractual obligations. Such damages will
    include damages to the Owner, [SBN], as well as damages
    incurred by other subcontractors.
    (R4, tab 908) The copies of the letter in the record show that it was sent to Botting by
    certified mail and that the letter was stamped as received by Botting on 21 August
    2007 (R4, tabs 908-09). However, Botting obviously received the letter before that
    date because, on 20 August 2007, it made reference to the letter in its own "Notice to
    Cure Subcontract Default" to Automated Controls (R4, tab 910).
    250. As of 28 August 2007 Botting had still not completed the DDC software
    installation, testing and documentation required by Specification 15910 (R4, tabs 148-53,
    903). COR Dyer expressed to SBN that, ifhe had known that this issue would still be
    open, he would not have recommended that the Fund take possession of the building in
    May (R4, tab 153; see finding 245). On 4 September 2007 CO Bartholomew issued a
    "Requirement to Cure DDC Software Issues":
    Unfortunately things are not all in order and there are
    problems with the software system and its functionality as
    currently set up.
    [COR Dyer] has been communicating with our technical
    folks and John Timmers. I had a brieftelecom with the
    both of them this afternoon.
    According to John Timmers, the DPW authority at Ft.
    Lewis, changes made to the controls set points can be
    made on the Supervisor but nothing happens at the VAV.
    Additionally, there are problems with the AAON units
    function and variance of discharge from 85 degrees down
    to 55 degrees. There are issues with the sequence of
    operations and the modulating unit capability is apparently
    not working.
    This is an electronic notice to Cure this condition. It may
    be followed with a formal demand on the Performance
    Bond issuer that the DDC controls for the facility, accepted
    conditionally in May 2007, are not properly working.
    We have invested almost two years of time and untold
    hours and meetings dealing with these issues. Our meeting
    on 15 August 2007 led decision-makers on our side to
    217
    grant an extension to 24 August. Efforts were made by the
    [SBN] Team to get us the needed software licenses and
    O&M manuals that were way overdue. However, the DDC
    controls issue seems to be a continuing problems [sic] with
    the functionality and operation (or lack thereof) of the
    system.
    Please respond with the remediation plan to correct these
    issues by 1700PDT tomorrow, 5 Sep 17 or we will take
    any and all actions necessary to get this work corrected and
    charge back against any remaining monies yet to be paid or
    a demand on the bond issuer who has been copied.
    (R4, tabs 154, 911) As of the next day, 5 September 2007, SBN stated that it
    considered the DDC issue corrected and closed (R4, tab 157).
    251. The Grand Opening of the Rainier Inn took place on 13 September 2007
    (R4, tabs 1197-98; tr. 5/108, 9/253-54, 12/31). In addition to the Rainier Inn
    (designated as Building 2107), the Fort Lewis lodging complex included two
    pre-existing lodging facilities of 80 rooms each (Buildings 2110 and 2111 ), as well as
    a maintenance building (Building 2108) (tr. 12/53-54).
    252. Again, on 14 September 2007, CO Bartholomew advised SBN of"many
    disturbing reports ... that the [DDC] situation is not fixed." After Botting advised on
    18 September 2007 that it was taking control of the situation, CO Bartholomew replied
    to SBN:
    I am at a total loss as to what the [Botting] e-mail below
    means. WA Botting has been responsible for the controls
    all along. For two years they have failed to hire a proven
    firm capable of installing and making the Tridium and
    related softwares [sic] HVAC interfaces/points work
    properly. The building was accepted conditionally in May
    and here we are the end of September. We met on site with
    two of the Bottings, TRSC531 and Automated Controls
    representatives and I gave your team a couple weeks to
    resolve. It has cost us thousands of extra dollars to have
    our consultants go in and look at what is going on I only to
    be told it is still not correct.
    53
    TRS replaced Automated Controls and sometime between 8/15/07 and 9/26/07; the
    replacement contractor was an approved DDC contractor for Fort Lewis (R4,
    tabs 149, 160 at 3063, 3067).
    218
    If you do not choose to get new blood into this project
    immediately (by COB today), we will take all necessary
    actions to get the system fixed and charge back/call
    bonds/etc. I again reiterate that we have provided you the
    names of the three Tridium licensed firms that Ft. Lewis
    DPW has used successfully and you may obtain that
    information again from Mr. John Timmers.
    (R4, tabs 158, 914; see also R4, tab 913)
    253. On 24 September 2007, when the DDC controls work in accordance with
    Specification 15910 had still not been completed, CO Bartholomew directed that
    software programming could continue but further directed that all "mechanically
    oriented work" was not authorized until an appropriate "ACTION/REMEDIATION
    PLAN" had been submitted by SBN and authorized by CFSC (R4, tab 160).
    254. As of 2 October 2007 SBN acknowledged that the DDC work by TRS
    was not complete (R4, tab 160 at 3060). SBN advised COR Dyer that "a complete
    functional test of the system" was scheduled for 15-16 October 2007 when COR Dyer
    was at the project site (R4, tab 161at3078). The DDC installation and testing was
    considered complete after the Thanksgiving holiday, however, as of 31 December
    2007, the contract-required documentation was not complete. Nevertheless,
    COR Dyer recommended to CO Bartholomew that the DDC system be accepted as of
    1 December 2007. (R4, tab 162)
    255. On 25 February 2008 CO Bartholomew advised SBN that the DDC
    documentation was considered complete and confirmed 1December2007 as the start
    of the one year warranty for the DDC controls (R4, tab 163). CFSC acknowledged
    receipt of mechanical system as-builts, including DDC, on 20 May 2008 (R4, tabs 166,
    169 at 3129).
    256. SBN submitted an REA to CFSC on 2 April 2008 (R4, tab 1207 at
    SUPP-121). We have not found a copy of this REA in the massive record before us,
    presumably because it was subsumed in SBN's 2010 certified claim (finding 267). On
    8 April 2008 CO Bartholomew acknowledged receipt of a four-volume REA from
    SBN in the amount of$7,561,051.89:
    The claim is apparently based on "unnecessary delays to
    [SBN's] design and construction of the Project" and there
    are reservations for interest, attorneys [sic] fees and other
    unforseen [sic] costs. Please recall that we negotiated a
    $500,000 contract reduction, in lieu of termination for
    219
    default, in March 2006. We also did not accept the DDC
    system (digital mechanical system controls) until last
    month, retroactive to December 1, 2007. The controls were
    not completed correctly when we took the building in May
    2007 and had been both a design and construction
    discrepancy for several years.
    I will review the documentation in the next 24 hours and
    keep you informed.
    (R4, tab 164) Later the same day, CO Bartholomew provided further input to SBN
    regarding the REA:
    We have received [SBN's] [REA] and have it under
    review. I have copied our contract attorney, project
    manager, and Army Lodging program manager.
    Our review of your request will be detailed. Unfortunately,
    I am unaware of any [SBN] management still present in
    your office that was involved in 2003/2004 during the
    solicitation and award process. Those records/history
    shortly after award resulted in much of the [SBN]
    difficulties in the start of this project and the delays which
    ensued I including the failure by [SBN] to investigate the
    site properly until after the 35% design submission. This
    was further exacerbated by [SBN] assignment of the first
    project manager, new to [SBN] and with no design-build
    construction experience/capability, or understanding of the
    contract and process, and [SBN's] clear intent not to
    follow the contractual requirements for the Contractor
    Quality Control Management System that was to be
    headed by the Architect of Record. The Architect of
    Record repeatedly told us that they had not been hired to
    be responsible for the overall design management, which
    was confirmed by the former [SBN] executive who signed
    the contract (subsequently "released" by [SBN]).
    We acknowledge there are unpaid contract funds
    (retainage). We[] have repeatedly requested an invoice for
    $125,000 to release that portion of the retainage following
    final acceptance, retroactively, for the DDC
    220
    controls/system over 6 months after the conditional
    acceptance of the building, and after more than two years
    of back and forth on what was required by the Ft Lewis
    Installation Design Guide (and the Ft Lewis Department of
    Public Works). This lost two years is a critical path. We
    advised the remaining retainage would be released with
    receipt of as-builts and a close out invoice with a Release
    of Claims. The $125,000 will still be released with an
    invoice request in that amount.
    (R4, tabs 165, 920)
    257. By email dated 23 June 2008, CO Bartholomew provided to SBN an
    informal summary of his review of the "major issues" contained in SBN's April 2008
    REA, specifically stating that it was not a contracting officer's final decision:
    I will call you Wednesday at a time you are available, to
    discuss how we can separate out these issues, plan to
    conduct telecom and/or face-to-face meetings, involve
    consultants as needed, and go over the documentation and
    process necessary prior to issuing a final decision. I expect
    that we will conduct a number of meetings and information
    exchanges before getting to a final decision on those items
    where there is not agreement. Once a final decision is
    issued by the contracting officer, it may be appealed to the
    [ASBCA].
    Again, I am open for additional discussions, clarifications
    and exchanges of information on what you have submitted.
    I do not believe we have acted unreasonably or required
    anything that unjustly enriched us at the expense of [SBN]
    or any of their subcontractors.
    (R4, tabs 167, 922, 1201) CO Bartholomew later stated that his 23 June 2008 response
    to SBN's REA was a "complete denial" but included the possibility of further
    negotiation (finding 259).
    258. By email dated 10 July 2008, SBN's Montoya responded:
    I have reviewed your email and while this issue is
    significant, and the sums involved are as well, I am
    221
    suggesting the following steps be taken in order to resolve
    this between us.
    1.     We need to determine whether there are major
    disagreements on the relevant facts denoted in our REA.
    From the general nature of the response provided I am
    unsure. The response provided does not include any
    analysis for our review. Once each component in our REA
    is addressed we can move to the next step.
    2.     Once step 1 is completed we can identify the facts
    we agree/disagree on. For those items we agree on we can
    resolve the associated dollar amounts at this time.
    3.      For those items we disagree on we can review the
    facts together to better understand each other[']s position.
    If necessary we can each provide additional information to
    support our respective positions.
    4.    We negotiate a settlement based on the information
    reviewed in step 3.
    The process identified above may take 2 or 3 meetings at
    the most. I recommend we meet the week of28 July to
    accomplish Step 1 and Step 2. We can then meet the week
    of 18 August to address step 3 and 4. Let me know what
    date and location for each week works for you.
    (R4, tab 168 at 3115-16, tab 923; tr. 3/221-25) CO Bartholomew responded that he was
    out of the office on business through the first week in September, but he suggested a few
    dates in August that could work for an initial meeting (R4, tab 168 at 3115, tab 923).
    259. In a "Pre-negotiation Meetings Plan" dated 1August2008, CO Bartholomew
    stated the following:
    Background: The Ft Lewis Lodge (185 rooms) was
    competitively awarded under a design-build RFP to [SBN],
    Bellevue, WA for $17.36 Million in May 2004. [SBN]
    attempted to change the mechanical system design
    requirements from the outset and they were not accepted.
    [SBN] also completed the initial designs/3 5%/later designs
    without performing required site investigation/geotechnical
    exploration until later in the design process. This led to
    222
    required design changes in the foundation system and site
    elevations, among others, in December 2004, due to fiber
    optic lines running immediately under the proposed
    building layout along grid line 13. Subsequently, the entire
    [SBN] management and project teams were
    changed/replaced from late 2004 through 2005. This
    included multiple project managers, quality control chiefs,
    superintendents and upper management at the Bellevue,
    WA regional office. Mechanical and design issues resulted
    in protracted back-and-forth and extensive project delays.
    In early 2006 it was proposed by the Construction
    Directorate to terminate the contract for default. In
    February 2006, the Contracting Officer alternatively
    proposed seeking a bilateral contract reduction, in six
    figures, in consideration of not terminating for default. In
    March 2006, a $500,000 contract reduction was negotiated
    in lieu of contract default. Counsel for both parties sought
    to include reservations of all rights and they were
    incorporated in the bilateral agreement. Part of the
    agreement included accepting some non-standard rooms
    and shortened ceilings.
    The project was conditionally accepted in late May 2007.
    The DDC controls system for the HVAC was not complete
    and not accepted by the Contracting Officer. Many
    changes were necessary and the system was not accepted
    until early 2008, retroactive to December 1, 2007.
    In April 2008, [SBN] submitted a large four (4) volume
    REA totaling $7 .6 Million. On 23 June 2008, the
    Contracting Officer issued a denial of the entire _REA.
    However, the response did acknowledge the holding of
    retainage and a previous decision of the Contracting
    Officer to release $125,000 of the $251,000 retainage upon
    receipt of an invoice for same. An invoice was received on
    July 2008 and the $125,000 retainage was released via
    wire transfer within a few days.
    Other Comments: Manufacturing problems have been
    encountered with the McQuay packaged terminal air
    conditioning (PTAC) units provided by the contractor
    (actually under a subcontract with W.A. Botting, the
    mechanical subcontractor, who has a claim for seven
    223
    figures as part of the overall REA request). Approximately
    half of the PTAC units require replacement and work is
    underway under the Warranty of Construction contract
    clause.
    Contracting Officer Summary of Actions Taken:
    Following a lengthy review of the REA documentation
    [SBN] provided in four large volumes, a complete denial
    was made 23 June 2008, but it did include the possibility
    of additional consideration with a bifurcation of some
    issues and additional documentation. The initial finding by
    the Contracting Officer was not a final decision, and [h]as
    not been reviewed by a staff attorney. In the denial, the
    Contracting Officer anticipated a number of meetings and
    information exchanges before getting to a final decision on
    those items where there is not agreement.
    [SBN] Request: Following the Contracting Officer's initial
    denial of the REA, a dialogue was opened with the [SBN]
    Vice President/Division Manager, Mr. Ron A. Montoya,
    who oversaw the end of the project. He requested
    face-to-face dialogue meetings that were agreed to by the
    Contracting Officer. [SBN] requested the first of the
    meetings to be held 19/20 August in Arvada, CO so that their
    outside counsel, who participated in the bilateral agreement
    in 2006, could participate and understand the process. The
    first meeting will be to: 1) go over the original submission in
    detail; 2) identify areas where additional consideration is
    possible; 3) identify areas where a formal denial will
    occur/where there is no agreement; 4) discuss the intent of
    reservations taken with the agreement in march 2006; and 5)
    discuss the bifurcation of certain issues that might result in
    additional consideration (issues that [SBN] considers
    continued after the March 2006 agreement).
    Negotiation Plan: The plan would be to conduct two
    face-to-face meetings followed by additional submissions,
    if appropriate, by [SBN] and their subcontractors. The
    initial meetings on 19/20 August 2008 are pre-decisional.
    A second meeting will likely be scheduled in Seattle, late
    September/October 2008, to take advantage of any
    224
    required technical input/participation by: the Architect of
    Record, Jensen Fey Architects; W.A. Botting, mechanical
    systems subcontractor; SME Electric, electrical
    subcontractor; other subcontractors as appropriate; ORB
    Architects, NAFI consultant; BCE Engineers,
    subconsultant to ORB Architects; and Ft Lewis, WA DPW
    representatives who were involved in establishing the
    Installation Design Guide requirements for HVAC systems
    and the DDC tridium controls. A Final Decision of the
    Contracting Officer is not expected until at least November
    2008.
    (R4, tab 1202)
    260. CO Bartholomew and SBN representatives participated in a "lengthy
    conference call" on 19 August 2008 (R4, tab 170 at 1-3; tr. 3/221-25). The record contains
    no evidence of any later discussions between CO Bartholomew and SBN representatives.
    261. CO Bartholomew retired at the end of December 2008 and, thereafter, did
    not participate in any further discussion or resolution of SBN's 2008 REA (R4,
    tabs 170, 1203, 1207 at SUPP-121; tr. 12/163, 190-93). SBN's Montoya left SBN's
    employment on 1 January 2009 (tr. 3/220).
    262. In February 2009 CO John Wallace was assigned as the successor
    contracting officer responsible for the contract matters now at issue (tr. 12/129-30).
    He has been a senior contracting officer in the Major Projects Division for NAF
    contracts since 1992. CO Bartholomew had been his supervisor from 2004-2007 but
    they had no conversations about the specifics of the Fort Lewis lodging project before
    or after CO Bartholomew's retirement. (Tr. 12/129, 140, 147-48, 156, 163, 169-74)
    CO Wallace had previously been contracting officer, with COR Dyer as project
    manager, on two Navy lodging projects and one Army lodging project (tr. 12/140-41,
    213). At the time CO Wallace became involved with the project now at issue:
    Our office [CFSC] was in the middle of the BRAC
    relocation and the Army Lodging Organization was in the
    last phases of its relocation to San Antonio.
    Their area on the fourth floor of our building, which
    we were part of, had been vacated. All their books and
    boxes and everything were packed up for shipment and
    were on their way to San Antonio.
    When I was assigned as the contracting officer on
    the Fort Lewis Lodge, I was looking for contract
    225
    documents, I was looking for emails, I was looking for any
    documents I could get my hands on.
    I was informed that some boxes had been I may
    have been shipped to San Antonio. I was informed that
    there may have been boxes that were shipped to self-
    storage. And I was informed that a lot of boxes had been
    shipped to archives and they couldn't tell me whether or
    not any of them were referencing this particular project.
    Q:    At the time you came on the project in 2009,
    were there any contractual actions outstanding on the Fort
    Lewis Lodge contract?
    A:      I wasn't sure, because I could not gather all
    the documents that I was looking for. I had read the [2008
    REA]. I had reviewed the documents that I had available to
    ·me. And at that point I said, well, there's something here,
    but I can't verify without documentation, and there were
    portions that we were looking for.
    I had tasked our Information Management Office to
    provide me with all the emails that were in the archives or
    records from Mr. Bartholomew, from Mr. Dyer and from
    Army Lodging personnel that were involved in the project.
    That took about four months to get collected.
    (Tr. 12/141-43; see also tr. 12/162-63) Among the documents that CO Wallace could
    not find was the official contract file:
    I could not find all of the file. And that's what I was
    referring to as constantly looking for documents. The files
    were scattered all over the place.
    [W]hen I was given the project, I was told there are
    three boxes in that file cabinet over there where all of [CO
    Bartholomew]' s files are.
    I went there, went into [his] old office, laid them out
    on the table and looked at it and said, there's nothing here.
    I have to go back and start looking for all the missing
    packages.
    There were sections of the RFP file that had been
    tom out, and I don't know why and I don't know how, of
    226
    the folder and kept together in a clip binder. There were
    other parts that were loose.
    I have a feeling based on what I was looking at, at
    the time, is people started rummaging through the files as
    they were packing their files to go to San Antonio and
    there was a big mess in there.
    And I spent I and I think I believe I spoke with you
    [referring to SBN' s counsel] on several occasions where I
    kept telling you I'm still looking for documents.
    (Tr. 12/159-60, 162-64; tr. 12/167) Although CO Wallace had no first-hand
    involvement in drafting the specific RFP for the Fort Lewis project, he had developed
    and was the original author of certain "boilerplate requirements and language that was
    incorporated into" Sections C, Hand L of that RFP (tr. 12/131, 170).
    263. Botting filed bankruptcy on 19 May 2009:
    Company incurred large losses and subsequent claims on
    several projects while managed without Peter Botting in
    period 2003-2006; resulted in "liquidity crisis"
    (R4, tab 926 at 13238; tr. 4/74-75, 79-88 (Chapter 11 in 2009, later converted to
    Chapter 7))
    264. On 26 July 2009, CO John Wallace informed SBN's counsel of his
    intention to hire a schedule consultant to analyze SBN's delay claims. CO Wallace
    expressed appreciation for SBN's patience:
    Based on the above, I do not anticipate completing my
    review and issuance of my decision until after the end of
    the fiscal year (09/30/09) .... How long thereafter will not
    be known until I get the analysis and report from the
    scheduling consultant. I regret any inconvenience this
    causes, but I will not issue a decision without knowing all
    the facts surrounding allegations from both sides ....
    (R4, tab 1203) SBN's counsel sought a further status report from CO Wallace by
    email on 23 September 2009 (R4, tab 1203).
    265. By email dated 6 January 2010 CO Wallace responded to a request for
    update from SBN' s counsel, stating that he had been hospitalized and out of the office
    for two weeks. CO Wallace also informed SBN' s counsel that the schedule consultant
    had questions, the answers to which needed to be provided by SBN.
    227
    Upon receipt of [SBN] 's responses to these questions, I
    will forward to our consultant and schedule a meeting with
    them to discuss their overall assessment and report on the
    REA delay allegations. After that meeting, I anticipate
    being able to provide you and [SBN] a date certain of my
    decision on the REA.
    (R4, tab 1204)
    266. On 17 February 2010, again in response to a request for update from
    SBN' s counsel, CO Wallace informed counsel that:
    I was working with the schedule consultants and they were
    developing their questions and comments based on the
    [SBN] documents and available information. Some of the
    questions they asked were answerable based on information
    in my possession. I was attempting to provide the consultants
    with some key relevant documents (including emails) when
    my computer crashed on January 20th.
    Our IM folks were having a difficult time retrieving the
    e-files, documents and emails out of the old hard drive.
    After the recent historic snow storms in the DC area
    (Federal Govt closed for almost a week), I didn't get most
    of these items back on my new computer until February
    12th (some files appear[] to have been lost and hard copies
    are being tracked).
    I regret the delay ... it was unfortunate and untimely. As
    soon as I can assemble the rest of the hard documents, I
    will forward these documents to the consultant in order for
    them to refine their questions and re-submit them to me for
    forwarding to you and [SBN]. I will notify you when I plan
    to forward the consultant's questions related to [SBN]'s
    REA (Delay Allegations) as soon as possible.
    (R4, tab 1205)
    D. Certified Claim and Appeal
    267. On 7 June 2010, SBN formally withdrew its 2 April 2008 REA
    (finding 256) and submitted to CFSC a disk containing its nearly 6,800-page certified
    claim in the amount of$6,768,830.26:
    228
    It has now been 26 months since [SBN] submitted
    its REA. There has been no substantive response from the
    Army, no attempt to discuss the specifics of the REA and
    no decision. As [SBN] has not received a final decision nor
    has the Army acted within a reasonable time, [SBN]
    believes the Army's lack of action implies a rejection of
    the REA. Accordingly, [SBN] considers the REA to be in
    dispute, and, as required by the Disputes clause, [SBN]
    hereby submits its certified claim ....
    As stated in the Claim narrative, [SBN] demands a
    modification to the Contract in an amount of
    $6,765,830.26. The Claim, which is included in the
    enclosed CD, includes a narrative, schedule analysis and
    supporting documents. The Claim is substantially the same
    as the April 2, 2008, REA although the schedule analysis
    has been updated to include description of a number of
    delays and disruptions not included in the original REA.
    Since your earlier emails indicated that you and your
    scheduling consultants had reviewed the REA and should
    be familiar with it, we request a Contracting Officer's
    decision on the Claim within the required sixty (60) days.
    We direct your attention to the circumstances
    surrounding the Army's removal of [SBN's] Project
    Manager early in the project. The Army's action adversely
    impacted [SBN's] ability to complete the project in a
    timely manner. We believe the documentation, including
    email, which is contemporaneous with the removal of our
    Project Manager demonstrates less than good faith on the
    part of certain Army personnel.
    (R4, tab 170 at 9911-14, tabs 1206-07; tr. 5/203-04)
    268. The disk containing SBN's voluminous claim was delivered to CFSC
    while CO Wallace was on extended official travel:
    At the time the claim came in, I was actually on
    travel traveling through Korea, Alaska, Hawaii. And got
    back to my office and I got in about two and a half weeks
    after they told me the FedEx package was on my desk.
    229
    I found the FedEx package, opened it up and read
    that it was a certified claim. And I started thumbing
    through the disk to see what the claim was all about.
    It was an expansion of the initial REA, but I had to
    get hard copies made of it. And at that point, I notified
    Army Lodging that I needed to get printing of this
    document, because it was about 6,800 pages of documents.
    Well, we were in the process of getting the
    documents printed and reviewed. And in the meantime, I
    was still traveling. I had 25 projects that I was working on
    at the time and still traveling around the country.
    When I got back, the printed boxes were on my
    desk I or the printed copies were stacked on my desk and I
    began to go through them.£541
    And at that point around early August I got a
    letter ... that there was an appeal before the Armed Services
    Board of Contract Appeals.
    And I continued my review, but I was working on I
    towards a response, but was not ready to issue a final
    decision at that point.
    (Tr. 12/143-45, 178-204) CO Wallace admitted he never formally acknowledged to
    SBN receipt of the claim, stating "[i]t slipped through the cracks" (tr. 12/208-12).
    269. The claimed amount was broken down as follows:
    Contract balance                                    $110,650.00
    General Conditions                                $1,571,629.95
    Labor and Material Escalation                       $225,668.67
    Disputed Change Orders                           $348,836.07[551
    Subcontractor Claims                              $4,665,045 .57
    Liquidated Damages                                $(153,000.00)
    *Requested Contract Modification                  $6, 768,830.26
    Unabsorbed Home Office Overhead                     $328,020.44
    54 The printed hard copy of SBN's certified claim in the record consists of 15 (fifteen)
    3-inch binders of paper and contains a half-page table of contents for sections
    of the claim (some containing thousands of pages) with no tabs to assist in
    finding documentation referenced in the narrative.
    55 (See app. br. at 293; R4, tab 169 at 5182)
    230
    *The Unabsorbed Home Office Overhead costs are additive to
    the Requested Contract Modification requiring an adjustment
    upon offer of settlement in order to avoid duplication of
    requested overhead in line items above.
    (R4, tab 169 at 3126) The claim summarizes the delays asserted by SBN as follows:
    •   Actual Delay I 518 Calendar Days [12/23/05-5/25/07]
    •   Compensable Delay I 393 Calendar Days
    •   Excusable Delay I 23 Calendar Days
    •   Non-excusable Delay I 102 Calendar Days [SBN responsible]
    •   Delay Mitigation I 37 Calendar Days
    (R4, tab 169 at 3125)
    270. The Subcontractor Claims submitted to SBN and included within its own
    claim were broken down as follows:
    Jensen Fey Architecture & Planning                    $477,918.00
    KHS&S                                                 $443,539.00
    Olympic Construction Sitework Contracting              $80,917.00
    Paras Concrete Contractors                             $57,383.00
    SME Electrical                                      $2,059,820.00
    W.A. Botting                                        $1,596,122.00
    Non-Compensable Delay Deductions                     -$482,343.63
    Change Order Request Deductions                      -$269,665.00
    Dama2es Disputed Chan2es                            $3,963,690.37
    Overhead/Fee Insurance                                $701,355.20
    Total Subs Claims                                   $4,665,045.57
    (R4, tab 1207 at SUPP-160)
    271. CO Wallace failed to respond to SBN's Claim within sixty (60) days of
    receipt (see finding 25, § (f)) and, to date, no contracting officer's final decision
    (COFD) has been issued by CFSC. When asked at the hearing why no COFD was
    prepared, CO Wallace testified:
    Once ... the lawyers got involved, I was not prepared to
    issue it, because there was still a lot of documentation that
    I did not have.
    (Tr. 12/144-46)
    231
    272. SBN appealed to the Board from a deemed denial on 18 August 2010 (R4,
    tab 1207 at SUPP-121; tr. 121145).
    DECISION
    The subject of this appeal is the design and construction by SBN of the Rainier
    Lodge, a 185-room, four-story lodging facility at Fort Lewis, Washington. As the
    voluminous record demonstrates, this was a project with all the attendant challenges
    inherent in such a complex undertaking. SBN seeks compensation from the Fund in
    the amount of $6,768,830.26. We address the disputed matters before us, as much as
    possible, in the chronological order in which they occurred during contract
    performance and in which they were presented in SBN's 3 June 2010 certified claim.
    Preliminary Matters
    A. Conduct of CO and COR
    Before addressing the rest of SBN' s positions and arguments in this appeal, we
    will address its allegation that the Fund administered this contract with an intention to
    harm SBN (see, e.g., app. hr. at 306-07, 376; app. reply at 4-5). The Fund argues that.
    CO Bartholomew and COR Dyer were not motivated by animosity or ill will, but were
    merely resolute in fulfilling their obligations on behalf of the Fund to ensure that the
    contract requirements were met (gov't hr. at 226-28). The extensive record in this
    appeal is replete with expressions of frustration, pique, and even anger by
    representatives of both parties to the contract, as well as their agents and
    subcontractors. In any project the parties work in their respective best interests to
    accomplish the common goal of a well-executed project. However, especially in a
    project of the size and complexity of this one, the parties' interests can often appear to
    be at odds. Finding common ground is essential but it often takes considerable
    patience, professionalism and give-and-take. It is obvious that there are specific
    instances in this record where the actions of one party/individual or another were ill-
    advised or out of proportion to the triggering event(s). But in our analysis, we are
    required to look at the totality of the circumstances and to consider specific alleged
    examples in context and not in isolation.
    Both parties to a contract are subject to the implied duty of good faith and fair
    dealing. Centex Corp. v. United States, 
    395 F.3d 1283
    , 1304 (Fed. Cir. 2005). The
    duty is breached by the Fund only upon proof by clear and convincing evidence of a
    specific intent to injure SBN' s ability to obtain the benefit of the express terms of the
    contract or by actions intended to delay or hamper SBN' s performance. Metcalf
    Construction Co. v. United States, 
    742 F.3d 984
    , 990 (Fed. Cir. 2014); Puget Sound
    Environmental Corp., 
    ASBCA No. 58828
    , 16-1BCA~36,435. After careful
    232
    consideration of the voluminous record in this appeal, there is no evidence that the
    Fund intended to injure SBN or to delay or hamper its contract performance. Quite the
    opposite, it is clear to us that CFSC's actions on behalf of the Fund were intended to
    resolve delays and move the contract forward. When we consider the totality of the
    actions and inactions of both parties and all the various actors, we do not find the
    overall conduct of any of the parties over the course of the project to rise to the level of
    clear and convincing evidence of bad faith or to provide a separate basis for
    compensation. As was the case in The Clark Construction Group, Inc., JCL BCA
    No. 2003-1, 05-1BCA,32,843 at 162,500-01 (citation omitted):
    [T]he record contains numerous examples of a lack of
    communication and cooperation between the parties, who
    often took extreme or untenable positions ... , which
    enhanced an adversarial and distrustful atmosphere ....
    While we are not prepared to conclude that either party
    acted in bad faith, the lack of mutual confidence and
    respect caused and exacerbated many of the disputes raised
    in this appeal.
    We have considered SBN' s arguments alleging that the overall conduct of
    CO Bartholomew and COR Dyer over the course of the entire contract performance
    period constituted a breach of the implied duty of good faith and fair dealing and find
    them unpersuasive. We have separately addressed below several specific instances of
    the CO's and COR's conduct alleged by SBN to entitle it to damages.
    B. Delay Damages
    SBN has asserted claims for alleged excusable or compensable delays
    associated with a number of the substantive claims addressed in the following sections
    of this decision. A compensable delay is one for which both a time extension and
    monetary relief are due and an excusable delay is one for which only a time extension
    is due. ME.S., Inc., 
    ASBCA No. 56149
     et al., 12-1 BCA, 34,958 at 171,857 n.3. In
    order to prove that it is entitled to delay damages in the form of time and/or money,
    SBN must prove that the government was responsible for specific delays, overall
    project completion was delayed as a result and the government-caused delays were not
    concurrent with delays within SBN's control. Versar, Inc., 
    ASBCA No. 56857
     et al.,
    12-1BCA,35,025 at 172,128. Normally only delays to work shown to be on the
    critical path at the time of the alleged delay will cause a delay in overall project
    completion. States Roofing Corp., 
    ASBCA No. 54860
     et al., 10-1BCAif34,356 at
    169,661. Damage is also an element of entitlement and, while mathematical certainty
    233
    is not required56 , some proof of damage is required. BAE Systems San Francisco Ship
    Repair, ASBCA Nos. 58810, 59642, 16-1BCA~36,404 at 177,503; Lear Siegler
    Services, Inc., 
    ASBCA No. 57264
    , 12-2 BCA ~ 35,112 at 172,425. For each of SBN's
    claims for delays we will apply these elements to the relevant facts.
    I. HVAC/Mechanical Design
    The single largest and most pervasive dispute between the parties was also the
    first to present itself. As SBN stated in its brief: "The mechanical design was an
    important element of the overall Lodge design because it affected costs and impacted
    many other disciplines including the architectural and electrical designs" (app. br. at
    390). We first summarize the facts pertinent to the matter of SBN's
    HVAC/mechanical design for the common areas which comprised 10-12% of the total
    Lodge space designed to receive conditioned air (findings 69, 74, 76, 100).
    The original RFP was based on a 10% concept design and specifically
    encouraged "innovative, creative, or cost-saving proposals that meet or exceed the
    RFP-specified requirements" (findings 2, 7). Amendment No. P00005 reiterated that
    encouragement when it stated that "[a]lternative systems may be submitted by
    Offerors for consideration" (finding 36). However, Offerors were not given carte
    blanche by either the original RFP or Amendment No. P00005:
    The requirements in the RFP are minimum standards and
    may be exceeded by the Offerors. Deviations from these
    technical or functional requirements shall be clearly
    identified for Government review and may be approved if
    considered by the Government to be in its best interest.
    (Finding 7) (Emphasis added) In other words, any proposed deviations from RFP
    requirements were required to be specifically called to the attention of the government
    and identified as deviations that the government may, or may not, approve and
    formally incorporate into any resulting contract (findings 32, 49).
    The RFP required that the HVAC designed for the Lodge was to use PTAC
    units in the guestrooms and DOIM room and that the rest of the building (often
    referred to by the parties as "common areas") with conditioned air (estimated to be
    approximately 10-12% of the total conditioned space):
    [S]hall be part of a VA V system utilizing constant volume
    fan powered terminal boxes, air cooled chiller and hot
    56
    Specific proof of the amount of monetary damages is a quantum issue which is not
    before us.
    234
    water boiler for primary air handler and re-heat at the
    terminal unit [see finding 17]. Code-required outside air
    ventilation and make up air shall be provided the primary
    air handling unit using chilled water cooling and hot water
    heating to precondition all outside air before delivery
    through ductwork to each space.
    (Finding 14) RFP Section L-20-1 was explicit in its requirement that:
    Requirements, codes, standards and any other information
    contained or specified in SECTION C and elsewhere in
    this RFP will be assumed to be included and to be a part of
    the Offeror[']s proposal. It need not be repeated therein.
    All alternates shall be specifically addressed and expanded
    upon in the proposal. The criteria specified in this RFP are
    binding contract criteria and in cases of any conflict,
    subsequent to award, between RFP criteria and
    Contractors['] submittals, the RFP criteria shall govern
    unless there is a written agreement between the
    Contracting Officer and the Contractor waiving the
    specific requirement or accepting a specific condition
    pertaining to the offer.
    Proposals will be evaluated for conformance to the
    minimum criteria in the RFP and for quality scoring.
    (Finding 32) In addition, in order to be considered technically responsive, the
    proposal was required to include: (1) a narrative describing any alternative HVAC
    system proposed; (2) why that particular system was selected for proposal; and, (3)
    catalog cuts of the particular equipment proposed (finding 32).
    SBN's proposal included an alternative HVAC system instead of the
    boiler/chiller system required by the RFP "because we couldn't meet the price with the
    boiler and chillers. And it didn't fit [our] design." (Findings 35, 64, 74) However,
    SBN's HVAC/mechanical proposal narrative, prepared by Botting, did not expressly
    state that it included any alternatives or deviations from the RFP requirement for a
    boiler/chiller system in the common areas, nor did it offer any narrative at all as to
    why an alternate system was selected and there were no catalog cuts of the proposed
    alternative equipment (findings 42, 76). As quoted just above, the RFP put SBN on
    notice that, in the absence of a specifically identified alternative/deviation, the
    proposal would be presumed to meet RFP minimum requirements (finding 32). SBN
    235
    and Botting now admit that the proposed HVAC/mechanical system for the common
    areas did not meet the RFP requirements (findings 64, 66, 76). However, SBN takes
    the position in its claim that the use of the term "packaged" as descriptive of the
    proposed system, together with the absence of the words "boiler" or "chiller," in the
    proposal's brief narrative as it relates to the common areas, equipment list and
    drawings was enough to put the government on notice that the proposal included a
    deviation from the RFP (finding 64; app. br. at 391-92; app. reply at 26-29). We
    disagree; the mere use or non-use of the words "packaged," "boiler," or "chiller" in the
    HVAC/mechanical system narrative without an affirmative, clearly identified
    statement that an alternative/deviation was proposed instead of the RFP-required
    boiler/chiller system and why it was proposed, did not meet the RFP requirements for
    the proposal of a deviation/alternative.
    SBN's proposal was one of nine submitted to the CFSC for review.
    Approximately two hours were spent on the review of each entire proposal. SBN' s
    proposal was so lacking in information regarding the HVAC/mechanical system
    design that it was rated ninth out of the nine proposals and fifth out of nine overall
    (finding 45). SBN argues that CFSC was negligent because the members of the
    proposal review team did not include anyone who was experienced in the
    HVAC/mechanical field and that, had the team included such a person, the team would
    have been able to interpret SBN/Botting's design as an alternative/deviation from what
    the RFP required (app. br. at 11-24; app. reply at 26-29). However, the RFP's
    guidance to prospective contractors provided that "professional evaluation" would first
    be part of the review process at the time of the 35% design review and made no such
    statement about the makeup of the proposal review team (finding 20). We understand
    the RFP requirement that alternatives/deviations were to be clearly identified and
    explained in the narrative to provide a mechanism by which the proposal review team
    would be alerted that something other than the RFP requirements were included and
    that additional attention and/or expertise might be needed to review a proposed
    alternative/deviation. In the absence of the RFP-required clear identification of an
    alternative/deviation in SBN's HVAC/mechanical proposal, including the required
    specific narrative, an explanation of why the alternative/deviation was proposed and
    catalog cuts for proposed equipment, there was nothing to alert the proposal review
    team that anything other than the RFP minimum requirements were proposed.
    We find that the government proposal review team followed the RFP guidance
    (finding 32) and that, given the limited amount of time for review of each proposal and
    in the absence of an express statement by SBN calling the government's attention to a
    proposed deviation from, or alternative to, the RFP requirements, the proposal review
    team was justified in assuming that SBN's mechanical/HVAC proposal met the RFP
    requirements for a boiler/chiller system (see finding 32). SBN's failure to specifically
    advise the government that its HVAC/mechanical proposal included a deviation from the
    RFP requirements was repeated when, in response to questions from CO Bartholomew
    236
    seeking clarification of its proposal, SBN again failed to identify the alternative design
    and why it was proposed and merely stated that its proposal was "fully compliant with
    the technical requirements of the RFP" (finding 46).
    Notes from a telephone conference on 5 March 2004 stated that CO Bartholomew
    was still seeking clarification of the HVAC/mechanical portion of SBN' s proposal.
    SBN' s Henrickson testified that he did not recall having a discussion about the
    HVAC/mechanical proposal, rather, "[t]hey just wanted us to clarify. We had already
    stated that was a package, but they wanted more clarification." (Finding 48)
    Nevertheless, SBN now argues that during this telephone conversation, CO Bartholomew
    acknowledged and approved SBN's alternate HVAC/mechanical design (app. br. at
    393-94; app. reply at 53-54). We find absolutely no contemporaneous documentary
    evidence in the extensive record before us of such a detailed discussion or agreement (see
    finding 49) and note that in the entirety of the voluminous record before us there is
    nothing to document that SBN ever even made an allegation of the existence of such an
    agreement until it submitted its 2010 claim, six years after the alleged agreement and
    several years after contract completion. SBN urges us to assume that such an agreement
    was memorialized in CO Bartholomew's Determination and Finding for Award, a
    document which is not in the record because the official contract file was never found
    (app. reply at 53-54; see also findings 262, 266, 271). However, in the absence of the
    document, it would be inappropriate to find that such an important agreement was, or was
    not, in the document without further contemporaneous corroborating evidence. Rather,
    given the importance of the HVAC/mechanical design and associated design and
    performance issues and delays documented throughout the record, we find it hard to
    believe that if, as SBN now claims, CO Bartholomew had approved of the alternate plan
    prior to contract award, SBN would not have made its own detailed record of the alleged
    agreement and raised it loudly and often with CFSC from 2004-2010. There is no
    evidence that SBN did so. We, therefore, conclude that the hearing testimony, many
    years after the fact, alleging the existence of such an agreement to be uncorroborated by
    any detailed contemporaneous evidence and to have little credibility.
    In its 23 March 2004 BAFO, SBN's mechanical/RVAC proposal stated that:
    •   The lobby and administrative areas are served from
    a packaged variable volume unit located on grade as
    indicated on the mechanical concept drawings. Air
    is distributed to fan powered terminal units with
    electric heat to provide energy efficient comfort
    zomng.
    (Finding 50) Again, there is nothing in this description specifically calling to the
    Fund's attention that what is proposed is a deviation from, or alternative to, the
    RFP-specified boiler/chiller system nor does the narrative state why an alternative is
    237
    being proposed. Once again, SBN argues that the mere use of the term "packaged"
    was sufficient to put the government on notice that the proposal included something
    other than the RFP-specified boiler/chiller system and, once again, we disagree.
    SBN' s own expert witness, Mr. Kommers, testified that there are such things as
    packaged boiler and chiller systems and we have found that heat generation boilers are
    commonly powered by gas or electric (finding 50). Once again, the mere presence or
    absence of the words "packaged," "boiler," or "chiller" in SBN's BAFO was
    insufficient to specifically identify and call attention to SBN' s inclusion of an
    alternative HVAC/mechanical design and not the RFP-required boiler/chiller design.
    On 26 March 2004 SBN again assured CO Bartholomew that:
    Our proposal complies with the RFP and if awarded a
    contract we ensure material compliance with the RFP
    requirements. We have reviewed and verified our pricing
    and it is acceptable for the basis of a firm fixed price
    contract if awarded this project.
    (Finding 51) Again SBN made no mention of its known proposed deviation from, or
    alternative to, the RFP-required boiler/chiller system. The RFP specifically obligated
    SBN to expressly identify any alternative/deviation (finding 32), and we cannot agree
    with SBN that, upon its failure to make such a specific identification, the CFSC
    proposal review team was required to hunt through SBN' s proposal to see if it could
    unearth clues to such an alternative. The CFSC BAFO proposal review team again, in
    compliance with the terms of the RFP and in the absence of a specific statement by
    SBN that it was proposing an alternative/deviation, had no reason to believe SBN's
    proposal included anything other than the RFP-specified boiler/chiller system
    (findings 32, 52).
    The contract was awarded to SBN on 11 May 2004 and both the RFP and
    SBN' s BAFO proposal were incorporated by reference. By its express terms, in the
    case of a conflict between the contract and SB N's proposal, the contract "shall prevail"
    unless there is a written agreement waiving the specific RFP requirement or accepting
    a specific deviation from the RFP (finding 32). SBN argues that the mere act of
    incorporation of SBN' s entire BAFO proposal into the contract was sufficient to meet
    the contract requirement for a specific waiver by CO Bartholomew of the
    RFP-required HVAC design for the common areas. (App. reply at 26-27) In order to
    show waiver, SBN must show that CO Bartholomew expressly and knowingly
    rescinded the Fund's contract right to require the specific RFP-required HVAC system
    for the common areas. General Dynamics C4 Systems, Inc., 
    ASBCA No. 54988
    , 09-2
    BCA ,-r 34,150 at 168,818. In addition, the express terms of the contract require that
    such a waiver be in writing (finding 53). We have found no evidence, nor has SBN
    directed us to any, of such a written agreement at the time of contract award regarding
    238
    a specific waiver of the RFP-required HVAC/mechanical system for the common
    areas, nor have we found any evidence of the existence of a specific acceptance of
    SBN's proposed alternate HVAC system for the common areas at the time of contract
    award. (Finding 53) We, therefore, hold that SBN's alternative HVAC/mechanical
    system design for the common areas was in conflict with the RFP-required
    boiler/chiller design and that the conflict must be resolved in favor of the
    RFP-required boiler/chiller design. CFSC was, therefore, justified in demanding that
    SBN provide the boiler/chiller HVAC/mechanical system that was specified in the
    RFP and resulting contract.
    SBN submitted the 35% ASBCA No. 58755
    ,       15-1BCA~35,939     at 175,653-54.
    A Type I differing site condition claim is dependent
    on what is "indicated" in the contract. Foster Constr. CA.
    and Williams Bros. Co. v. United States, 
    435 F.2d 873
    , 881
    (Ct. Cl. 1970) ("On the one hand, a contract silent on
    subsurface conditions cannot support a changed conditions
    claim .... On the other hand, nothing beyond contract
    indications need be proven."). A contractor cannot be
    eligible for an equitable adjustment for Type I changed
    conditions unless the contract indicated what those
    246
    conditions would supposedly be. P.J. Maffei Bldg.
    Wrecking Corp. v. United States, 
    732 F.2d 913
    , 916 (Fed.
    Cir. 1984); S.T.G. Construction Co. v. United States, 
    157 Ct. Cl. 409
    , 414 (1962).
    NDG Constructors, 
    ASBCA No. 57328
    , 12-2 BCA ~ 35,138 at 172.503; see also C.R.
    Pittman Construction Co., 
    ASBCA No. 57387
     et al., 15-1BCA~35,881at175,427.
    The first element of SBN' s burden of proof is met by the record evidence that
    the RFP provided express "indications" of existing utilities in a topographic drawing
    of the jobsite showing the locations of various existing underground utilities at the
    time the RFP was issued (findings 8-9, 40-41). The second element requires that SBN
    show that, based upon the information reasonably available to it at the time of its
    proposal, the actual conditions it encountered were unforeseeable. Prospective
    contractors were cautioned to perform their own reasonable site investigations
    (findings 8, 28, 40). The parties disagree as to what constituted "reasonable site
    investigation." The Fund argues that SBN was unreasonable to rely on the RFP's
    representations as to the location and characteristics of existing utilities and that SBN
    should have performed its own pre-proposal subsurface investigations (gov't hr. at
    269-275). SBN and its subcontractors maintain that a requirement for pre-proposal
    subsurface investigation is unreasonable, given that they were not permitted to do any
    digging until after issuance of an LNTP and a digging permit was granted by DPW
    (see finding 17; app. hr. at 353-59). We agree with SBN. The record shows that SBN
    and several of its subcontractors attended a pre-proposal site visit and compared what
    they observed at the site with the representations of the utilities in the RFP
    (findings 19, 34). Further subsurface investigation, such as would have revealed any
    of the alleged differing site conditions before us, was not mentioned nor required by
    the RFP and we find the Fund's argument in this regard unreasonable. We therefore
    find that SBN has met its burden of proof with respect to the second element. On the
    basis of the record before us, as well as our holdings with respect to elements one and
    two, we also find that SBN has met its burden of proof as to the third element that it
    reasonably relied upon its interpretation of the RFP and contract documents with
    respect to existing utilities. The fourth element requires that SBN prove that it was
    damaged as a result of the material variation between expected _and encountered
    conditions. We will address below SBN' s claimed damages associated with each of
    the individual differing site conditions claimed.
    SBN further argues that the Fund breached the doctrine of superior knowledge
    because the Fund was allegedly in possession of more current utility drawings than
    were provided to SBN (app. br. at 362-63). SBN did not assert a claim for superior
    knowledge in its certified claim and it is, therefore, not properly before us.
    247
    On 25 October 2004 SBN was issued an LNTP for foundations, underground
    utilities and the building structure (finding 92). SBN requested a digging permit on
    29 October 2004 and the permit was issued on 1 November 2004 (finding 95). SBN
    could not proceed to work on the jobsite until after issuance of the LNTP. SBN claims
    that it was delayed from proceeding with work on the project starting 1 November
    2004 (findings 117, 119). As of Progress Meeting #3, held on 5 January 2005, SBN
    reported that it was waiting for direction from CFSC regarding alleged differing site
    conditions identified in RFis 15-19 (finding 113; see also findings 104, 106). Each of
    the alleged differing site conditions for which SBN now seeks compensation will be
    addressed in detail separately below.
    On 26 January 2005 and 8 February 2005 SBN submitted REAs 031and035
    seeking a total of$514,315.00 and a 127-day extension to the contract performance
    period due to alleged differing site conditions and associated delays (findings 119,
    124). On 23 December 2005 CO Bartholomew unilaterally granted a noncompensable
    extension to the contract performance period for 60 days associated with "unforeseen
    site issues we encountered in the fall of 2004''. (finding 208).
    A. DOIM Communication Duct Bank
    On an unidentified date prior to 19 November 2004, SBN's excavation
    subcontractor encountered existing underground communication (DOIM) ductwork
    that had less than the contract-specified 3-foot amount of cover (see finding 47).
    There is evidence that SBN notified CFSC of the issue on or about 12 November 2004.
    On 19 November 2004 SBN met on-site with representatives from Fort Lewis DOIM
    and ORB. The DOIM representative "approved" SBN's proposed method to lower the
    ducts "so they would be well below [SBN's] designed finish grades." SBN then
    sought a change order from CO Bartholomew to accomplish the work, pointing out
    that the DOIM communication duct issue needed to be resolved concurrent with
    resolution of primary electrical ductwork issues discussed in more detail below.
    (Finding 97)
    Another meeting was held on 30 November 2004 attended by a variety of
    Fort Lewis DPW personnel and COR Dyer regarding "Utility Issues." It was
    determined that lowering the DOIM ductwork was not compatible with the building
    and site design and that the DOIM ducts, cables and manhole would have to be
    relocated. (Finding 103) There is evidence that this information was conveyed to
    SBN on 1December2004 (finding 109).
    On 20 December 2004 SBN submitted RFI # 19 to "confirm[] delay" associated
    with the DOIM communication ductwork (finding 109). On 10 January 2005
    CO Bartholomew attended a meeting at the jobsite. SBN's minutes of the meeting
    reported that CO Bartholomew acknowledged that relocating the DOIM ductwork
    248
    would "probably delay the project at least 60 days and will have considerable cost
    impacts." CO Bartholomew then requested that SBN prepare a civil redesign of the
    site that accommodated the existing DOIM ductwork and he acknowledged that this
    was compensable extra-contractual work. It was his intention to then present the civil
    redesign to DPW for consideration. It was agreed that SBN and its subcontractor
    would provide the requested redesign. (Finding 114) As of 21 January 2005,
    CO Bartholomew acknowledged responsibility for the DOIM ductwork redesign and
    sought funds from DPW (finding 116). The civil redesign was dated 19 January 2005
    and SBN' s 8 February 2005 REA 031 sought a total of $154,803 .49 for the redesign
    and changed work as well as an extension to the contract performance period for
    associated delays (finding 124 ).
    SBN now seeks a total amount of$106,369.94 for the direct costs and
    associated critical path delays from 2 November 2004 through 29 March 2005 59
    resulting from the DOIM ductwork differing site condition (ex. A-7; R4, tab 169 at
    4994, 5182; app. br. at 291, 293-94, 296, 298, 359, 383, 384).
    As of the 13 April 2005 Progress Meeting #7, CFSC had still not issued a
    change order for the DOIM ductwork and the meeting minutes stated that "The CFSC
    position of this request is that [it] is non-compensable" (finding 149). The item still
    remained open for resolution as of the 22 June 2005 Progress Meeting #12
    (finding 166). Even though CO Bartholomew acknowledged responsibility in January
    2005 (finding 116), the Fund takes the position in this appeal that SBN is not entitled
    to compensation (gov't br. at 267-79). We agree in part.
    Under the terms of Modification No. P00003, SBN agreed that all disputes
    existing prior to 23 March 2006, except those for time and associated costs, were
    released (finding 212). The DOIM differing site condition existed prior to 23 March
    2006 and SBN' s claim for the costs of performing the associated work were not reserved
    in Modification No. P00003. The only claim reserved was for associated delays.
    With respect to delay damages, SBN claims that it is entitled to be compensated
    for critical path delays associated with the DOIM ductwork from 2 November 2004
    through 29 March 2005. The period of delay from 2 November 2004 through 8 March
    2005 is concurrent with the SBN/Botting-caused HVAC/mechanical design delay on
    the critical path (see Section I above). CO Bartholomew granted a non-compensable
    60-day extension of the contract performance period due to SBN' s encountering a
    59
    SBN states in its brief that the CFSC delay in providing direction regarding the
    DOIM ductbank ended on 8 March 2005 (app. br. at 384) and that the extra
    work was completed on 30 March 2005 (id. at 383). Its 2010 claim (R4,
    tab 169 at 4994) and Exhibit A-7, however, assert that all delay associated with
    the DOIM ductbank ended on 29 March 2005.
    249
    variety of differing site conditions (finding 208). We find that SBN is entitled to be
    compensated for the critical path delay period from 9-29 March 2005 (15 calendar
    days) which was solely caused by the Fund. The amount of compensation for the
    delay is a quantum issue which is not before us.
    B. Telephone Cable
    The RFP provided, with respect to telephone cables, that:
    E. Telephone: Telephone wiring will be run into and
    through a Communications Manhole adjacent to the
    site. An existing ductbank travels west from this
    manhole to Bldg 2003, DOIM main switch building.
    Coordinate installation of new twisted pair bundle in
    this ductbank back to 2003. The Contractor will make
    cross-connections at 2003 under DOIM
    supervision/direction. Coordinate all requirements with
    Post DOIM during design and construction.
    (Finding 9)
    Sometime after 1November2004 (findings 116, 119), SBN encountered
    underground telephone cables that "pass[ed] through the building pad in three locations"
    and, as of 29 November 2004, had been advised that DPW would remove th.em
    (finding 99). On 1 December 2004 SBN was informed that the underground telephone
    line discovered at the east end of the project could not be abandoned and removed as
    previously stated by DPW because that telephone line was active and provided phone
    service to the existing hotel to the east of the jobsite. That line passed through the
    loading dock area of the new Lodge design which had footings deeper than the
    telephone cables' existing location. Both CO Bartholomew and COR Dyer were on-site
    that day to observe the situation. The next day SBN provided formal written notice of a
    differing site condition. (Finding 102) On 16 December 2004 SBN submitted RFI #18
    seeking direction with regard to the active telephone cable (finding 109).
    As of21January2005, internal CFSC communications admitted liability for
    the telephone cable issue; the only question seemed to be which government
    organization's funds should be used for the payment (finding 116). On 11 February
    2005 SBN thanked CO Bartholomew for his direction on that date for SBN to perform
    the work of rerouting the active telephone cable for a price not to exceed $12,694.26
    (findings 124, 126, 133). Contract Modification No. P00002, with an effective date of
    14 February 2005, memorialized the parties' agreement (finding 129).
    250
    On 10 March 2005 SBN advised CFSC that the telephone cable reroute work would
    require additional time and cost because it was discovered that it was not direct-buried but
    encased in steel pipe (finding 138). As of the 13 April 2005 Progress Meeting, SBN
    reported that the work was completed (finding 149). As of 22 June 2005 SBN reported that
    CFSC had issued a change order for the work associated with rerouting the telephone cable
    and that SBN was awaiting payment for the costs of the work (finding 166). In the absence
    of evidence to the contrary, we find that SBN has been compensated for the cost of
    performing the changed work associated with rerouting the telephone cable.
    SBN also seeks critical path delay damages for the period from 1 December 2004
    when the live telephone cable was discovered through 29 March 2005 when the telephone
    cable reroute was completed (app. hr. at 65, 359, 383-84). The period of delay from
    1December2004 through 8 March 2005 is concurrent with the SBN/Botting-caused
    HVAC/mechanical design delay on the critical path (see Section I above). The remaining
    claimed period of delay is the same as the delay period sought by SBN for the DOIM
    ductwork and for which we have found SBN to be entitled above. We therefore find that
    SBN is not entitled to any further compensation for delay associated with the telephone
    cable reroute.
    C. Primary Electrical Interconnect Cable
    The RFP provided the following regarding a primary underground electrical
    distribution line:
    D. Electricity: There is an existing 13.8KV, 3-phase
    primary electrical distribution line on the perimeter of
    this site. Coordinate the services drop location with
    DPW during design and construction. An existing
    underground feeder line and pad-mount transformer
    exists on the site and may have to be rerouted/relocated
    depending on the final site plan arrangement.
    (Finding 9) RFP Amendment No. 00005 included the following additional information:
    7       NOTE: There is a pad-mount transformer on the site
    which will be removed by DPW with demolition of the two
    wood buildings on site. Removal of existing wood poles, OH
    electrical lines, and the transformer pad will be accomplished
    by the Contractor. There is also an underground secondary
    electrical feeder ... running through the site which will have
    to be rerouted around the building footprint as required.
    (Finding 36)
    251
    SBN' s electrical subcontractor, SME, testified that it conducted a pre-award site
    walk during which it observed nothing materially different from what was represented
    in the RFP. However, SME contends that, after contract award while meeting with
    DPW for the purpose of establishing temporary power at the jobsite, certain DPW
    personnel provided site-specific information that differed from what was included in
    the RFP (finding 91). The record indicates that on 22 October 2004 SBN/SME
    provided notice that they believed they had encountered a differing site condition with
    respect to the underground primary electrical interconnect (finding 109). On
    28 October 2004 ORB advised CO Bartholomew that DPW would not permit the
    primary power interconnect to remain under the building and that SBN was required to
    relocate it from under the building footprint (finding 94). On 29 November 2004 SBN
    notified COR Dyer of SBN's plan for rerouting the primary electrical interconnect
    (finding 99; see also finding 103). It was DPW's position that the work of relocating
    the primary electric interconnect was required by the contract (finding 103). SBN also
    notified CFSC that resolution of the DOIM ductwork is~me (see Section IIA above)
    would need to be performed concurrent with the primary electrical interconnect work
    (finding 97). SBN's RFI #15 requesting direction as to the primary electrical
    interconnect was submitted on 16 December 2004 (finding 109).
    As of 10 January 2005, it was agreed between CFSC and SBN/SME that
    responsibility for the work required to be performed with respect to the primary
    electrical interconnect was "split" between them:
    1-03. Electrical Duct Rerouting: 117/05 I
    [CO Bartholomew] confirmed that the existing
    electrical primary power duct bank will be rerouted,
    as necessary, to allow for the construction of the
    new building. It was confirmed by CFSC, [SBN]
    and SME[], that there is a split responsibility for
    this rerouting. The Contractor is responsible for the
    portion of the rerouting that is included in the
    SME[] design drawings and CFSC is responsible for
    the additional rerouting to make the interconnection
    from Pendleton A venue to Utah Street. The
    additional rerouting includes the portion of the duct
    bank from SME' s transformer vault around to the
    Utah Avenue side of the site. SME will provide a
    drawing showing the new interconnect arrangement.
    CFSC has a Contractor to do the work. The
    additional scope for [SBN] will be included in a
    Change Directive from CF[SC]. Pat Ellwood of
    SME[] suggested that relocating the existing
    252
    cross-connect vault would save some money.
    Action: CFSC/SME
    (Finding 114) On 8 February 2005 SBN provided details regarding the work
    associated with the primary electrical interconnect and how responsibility for it was
    split (finding 124). On 11February2005 CO Bartholomew directed that:
    1. Effective ... (14 February 2005), [SBN] is authorized to
    begin all electrical site reroute work and will coordinate
    other electrical work by the garrison DPW as appropriate.
    Any legitimate additional change costs for this piece of
    work shall be negotiated but the work is directed.
    (Finding 126) On that same date SBN thanked CO Bartholomew for the direction and
    advised that "DPW has already started the interconnect work" (id.). The parties'
    agreement regarding the work was memorialized in Contract Modification No. P00002
    (finding 129).
    On 24 February 2005 SBN reported that DPW had done all of the primary
    electrical interconnect work but SBN still requested that CFSC issue a change order to
    SBN on account of that work (finding 133).
    The record shows that the electrical reroute work was performed by DPW and
    not SBN or SME. SBN now seeks compensation for alleged critical path delays
    caused by the discovery of the primary electrical interconnect and the performance of
    the associated rerouting work from 28 October 2004 through 24 February 2005 (app.
    br. at 78, 359). Elsewhere in its brief SBN claims it experienced critical path delay
    from 22 October 2004 through 11February2005 (id. at 384). We find that the
    discovery of the primary electrical interconnect and the completion of the associated
    work delayed the critical path from 22 October 2004 to 24 February 2005. The period
    of delay from 2 November 2004 through 24 February 2005 is concurrent with the
    SBN/Botting-caused HVAC/mechanical design delay on the critical path (see Section I
    above). We therefore find that SBN is entitled to be compensated for the critical path
    delay period from 22 October 2004 through 1November2004 (7 calendar days) which
    was solely caused by the Fund. The amount of compensation due for the delay is a
    quantum issue which is not before us.
    D. Natural Gas Line
    The RFP provided that:
    F.     Natural Gas: Natural Gas is available at the site.
    Puget Sound Energy (PSE) owns the lines.
    253
    Coordinate connection points and construction
    requirements with DPW and PSE during design and
    construction.
    (Finding 9) On 15 November 2004 it was reported that a gas line that had not been
    marked by DPW was ruptured while a tree was being removed; the gas company
    repaired the ruptured line (finding 96).
    As of 29 November 2004 SBN had identified that the existing underground gas
    lines would have to be relocated because they were in the area where the storm sewer
    system was to be installed (finding 99). Internal DPW communication on 7 December
    2004 concerned the issue of who would pay for relocating the natural gas line that had
    not been identified in the digging permit (finding 103).
    SBN's RFI #17, dated 16 December 2004, sought direction from the
    government with regard to the natural gas line (finding 109). In the minutes of a
    10 January 2005 "Site Issues" meeting, SBN noted that:
    1.) [CO Bartholomew] indicated that the gas line
    would probably be lowered. Direction may be given
    to [SBN] to proceed with this work as an added
    scope to the contract. [SBN] awaits a Change
    Directive from CF[SC] on this issue.
    (Finding 114) As of21January2005, CO Bartholomew described the situation and
    sought funds from DPW:
    The gas [line is] directly impeding our contractor's ability
    to proceed with excavation work I estimated cost to
    relocate comm[unication] and gas lines is $25K. Current
    cost of the delay associated with the inability of our
    contractor to proceed is $1 OOK I some portion of this is
    associated with the time to identify the redesign solution to
    the DOIM telecommunications trunks ....
    We have no choice but to absorb the redesign/site
    work (associated w/DOIM trunks) increase of $40K as a
    project cost. Similarly we are stuck with funding the delay
    costs of$100K (associated with work stoppage due to all
    the unidentified/misrepresented utilities). However, as we
    discussed it seems unreasonable for the project to bear the
    254
    total $I I 5K cost associated with the previously
    unidentified/misrepresented communication and gas lines
    as well as to fund any requirement for back-up power tie in
    to another building when such was not represented in the
    plans the installation provided as a departure point for our
    contractor's design effort.
    (Finding 116) By email dated 11February2005 CO Bartholomew authorized SBN to
    perform the work associated with the natural gas line:
    4. The contractor is authorized and directed to perform the
    gas line reroute for a Not To Exceed cost of$23,793.00.
    Contractor is asked to coordinate this reroute to the extent
    necessary to avoid impacted site features and the new
    building. Request that unnecessarily longer reroutes by the
    gas utility subcontractor be strongly discouraged
    and coordinated with our on-site representative
    Mr. Bob Monson and/or John Patterson.
    (Finding 126; see also finding 124) This exact language was included in Contract
    Modification No. P00002 (finding 129). As of24 February 2005 SBN reported that it
    had contacted a subcontractor to perform the work (finding 133). SBN's gas line
    subcontractor reported that, as of 22 March 2005, it was still waiting for a digging
    permit from Fort Lewis (finding 143). SBN reported that the work was complete in
    the minutes of the 13 April 2005 Progress Meeting but that SBN was still waiting for a
    change order from CFSC (finding 149). In the minutes of the 22 June 2005 Progress
    Meeting SBN reported that CFSC had issued a contract modification and SBN had
    submitted an invoice to be paid for the work associated with the rerouting of the gas
    line (finding 166). In the absence of evidence to the contrary, we find that SBN has
    been compensated for the cost of performing the changed work associated with the
    natural gas line.
    SBN now seeks compensation for critical path delays to excavation work from
    15 November 2004 through 7 April 2005 caused by encountering a natural gas line not
    marked by the gas company (app. br. at 71, 359, 384). We find that the discovery of
    the unmarked natural gas line and the completion of the associated work delayed the
    critical path from 15 November 2004 through 7 April 2005. The period of delay from
    15 November 2004 through 8 March 2005 is concurrent with the SBN/Botting-caused
    HVAC/mechanical design delay on the critical path (see Section I above). The period
    of delay from 9-29 March 2005 is concurrent with the delay already granted for the
    DOIM ductwork (see Section I above). We therefore find that SBN is entitled to be
    compensated for the critical path delay period from 30 March 2005 through 7 April
    255
    2005 (7 calendar days) which was solely caused by parties outside SBN's control. The
    amount of compensation due for the delay is a quantum issue which is not before us.
    E. Over-Excavation
    On 22 April 2005 SBN's Project Manager Roberts reported internally that its
    on-site subcontractors were encountering "a significant amount of overexcavation for
    our footings" (i.e., more than six feet deep) and requested that CFSC be given notice
    of a differing site condition:
    Fortunately, for both [SBN] and the Owner, depending on
    who pays for it, the geotechnical engineer has determined
    that the existing unsuitable material that has to be
    overexcavated, is only unsuitable because it is loose, so
    that same material can be placed back in the overexcavated
    footings and compacted to 95% density. This reduces the
    need for imported structural fill.
    (Finding 151) As of2 May 2005 Project Manager Roberts reported that the areas
    involved were "not significant" and the whole issue from beginning to end
    encompassed "a few days" (finding 155). Despite the contemporaneous report of its
    own Project Manager, SBN now argues that it suffered a critical path delay to the
    foundation construction from 25 April 2005 through 9 June 2005 as a result of various
    differing site conditions (app. hr. at 102-03, 360). We have addressed SBN's
    allegations of critical path delays for all alleged differing site conditions other than
    overexcavation above. We find no support for SBN's allegation of critical path delay
    due to overexcavation and deny entitlement.
    III. Removal of SBN's Project Manager
    It is undisputed that SBN's Project Manager Roberts was barred from the
    jobsite by CFSC and Army Lodging. SBN argues that there was no contractual
    provision that permitted the government to do so and that this impermissible action
    had a detrimental effect on SBN's ability to perform under the contract (app. br. at
    84-101, 309, 341; app. reply at 29-32; finding 139).
    The contract provided that:
    The Contractor agrees to utilize only experienced,
    responsive and capable people in the performance of the
    work. The Contracting Officer may require that the
    Contractor remove employees who endanger persons or
    property, or whose continued employment under this
    256
    contract is inconsistent with the interest of military
    security.
    (Finding 26) In addition, the contract required SBN to have on the jobsite at all times
    during contract performance:
    [A] competent superintendent who is satisfactory to the
    Contracting Officer and has authority to act for the
    Contractor.
    (Finding 31) The contract is silent as to a remedy available to CFSC in the case of a
    failure by SBN to comply with the requirement.
    In June 2004, the month after contract award, SBN hired Mr. Roberts and
    assigned him as its Senior Project Manager, responsible for SBN's on-site
    performance of the project now at issue (finding 55). The first mention we find in the
    record of government dissatisfaction with Project Manager Roberts is in an email
    dated 22 December 2004 in which COR Dyer referred to Roberts as "inept" and stated
    that .he thought Roberts should be removed from his position (finding 110; see also
    findings 141, 156). Five days later on 27 December 2004, CO Bartholomew advised
    SBN's Henrickson that:
    Our relationship is in serious jeopardy. We will in no way
    accept Mr. Roberts' statements ... about RFI's and may ask
    you to have him removed from the project. He has been an
    impediment at most turns and will not pick up the phone
    and call instead of this childish behavior. Swinerton
    Corporate should be advised that our holdings of your
    stock is [sic] dropping like a rock into an abyss. I may have
    to make a formal notification that I do not want to make.
    (Finding 111)
    On 25 February 2005 CO Bartholomew and SBN's Montoya discussed during a
    telephone call what the CO characterized as "Bill Roberts ... continues to be the
    communication problem." After the call, Montoya sent the following email to the CO
    and copied COR Dyer, SBN's Henrickson and ORB's Monson:
    I appreciate the insight you have given me on the project.
    As we discussed, we believe it would be in our best
    interest if I became your main point of contact. As I said
    earlier, I might not have an immediate answer for you but I
    257
    will gather the information and provide same as best and as
    timely as I can.
    We agree that we need to resolve these items once and for
    all so we can move forward with construction and not
    continue to "carry this baggage" any longer. The process
    you described with regards to the handling of these items
    also seems reasonable.
    (Finding 134) We understand Mr. Montoya's 25 February 2005 communication to
    express SBN's agreement with the CO that it was in neither party's best interest for
    Project Manager Roberts to remain SBN' s primary contact with respect to the project.
    As of 2 March 2005 Project Manager Roberts' base pass was rescinded by
    Army Lodging's Moinette, who was the official sponsor of all the passes associated
    with the project. Project Manager Roberts testified that he did not tum over his pass
    on 1March2005 when Ms. Moinette first requested it, but did so the following day.
    Ms. Moinette and SBN' s Montoya and Roberts all testified that they were never given
    a reason by CO Bartholomew or COR Dyer for why Project Manager Roberts' pass
    was directed to be rescinded. Both SBN' s Montoya and COR Dyer testified that it
    boiled down to a personality conflict between Project Manager Roberts and
    COR Dyer. Thereafter, Project Manager Roberts conducted project business and met
    with SBN and subcontractor personnel off-site. (Finding 136) CFSC, however,
    declined to acknowledge Mr. Roberts as SBN's Project Manager as of9-10 March
    2005 (finding 139).
    Project Manager Roberts testified that he got a day pass to get on base several
    times and was reported to be on thejobsite on 21March2005 (finding 141).
    CO Bartholomew's response was:
    I will send an e-mail to appropriate authorities that
    identifies Mr. Roberts as an objectionable employee and
    possible security threat to Ft. Lewis and seek to have him
    denied access. He can appeal and I will be happy to
    respond to the Garrison and/or Corps Commander. They
    will have to take responsibility for him ifhe is
    subsequently allowed access to the installation.
    (Id.) We find no evidence in the record to support a characterization of Project Manager
    Roberts as a security threat (findings 141-42). On 22 March 2005 Mr. Coulson, Chief of
    Army Lodging Operations, stated that "[t]he Project Manager personnel issue was
    resolved in Jan 05" (finding 142). We find no other mention of a "Project Manager
    personnel issue" in the record before us so we are unable to determine whether facts
    258
    surrounding it were, or could have been, the basis for the rescission of Project Manager
    Roberts' base pass. According to Mr. Freeman, the Head of Physical Security Fort Lewis,
    on or about 25 March 2005:
    An individual having access to Fort Lewis can only be
    barred entry due to the committment [sic] of a crime or
    other violation .... [T]he original sponsor ... can remove or
    take possession of an individual's ID pass card and vehicle
    sticker so he cannot obtain entry. If he gets another pass
    through other temporary means then the original sponsor
    can have the MP's come and take his ID and vehicle passes
    again and escort him off the base .... [T]he "list of
    undesirables" at the main gate guard house is for those
    individuals that have committed a crime or "other
    violation".
    (Finding 144)
    As of2 May 2005 Project Manager Roberts reported that the project was not
    behind schedule (finding 155). Project Manager Roberts resigned on or about 20 May
    2005 and Senior Superintendent Zeman resigned effective 27 May 2005. SBN's
    Montoya hired new Project Manager LaSharr, who started in June 2005 and remained
    on the project through its completion, as well as new Superintendent Bowman who
    started work on the project in August 2005. Project Manager LaSharr testified that,
    when he came on as SBN's new Project Manager, SBN's ability to "move forward
    with the project" was not impacted by the absence of Roberts and Zeman.
    (Finding 162) We find Mr. LaSharr's testimony to be credible as he was SBN's
    on-site project manager responsible for the project's progress.
    While Project Manager Roberts complained to SBN's upper management about
    the rescission of his base pass (findings 151, 155), we find absolutely nothing in the
    record to show that SBN' s management registered any contemporaneous disagreement
    or displeasure with CFSC about the matter (finding 139) until the submission of its
    REA in 2008 and its certified claim in 2010 (finding 267), both of which were
    submitted years after contract completion and Mr. Roberts' resignation. We note that,
    in addition to an absence of any record of contemporaneous complaint or objection to
    Mr. Roberts' removal, in June 2005 SBN also made a number of its own upper
    management and project management changes that, according to CO Bartholomew,
    resulted in a dearth of design-build experience on the project (findings 162, 165).
    SBN argues that it is entitled to compensation on the basis of several theories of
    recovery related to the Fund's actions or inactions with respect to the rescission of
    Project Manager Roberts' base pass.
    259
    A. Breach of the Implied Duty of Good Faith and Fair Dealing
    SBN argues that the Fund breached its implied duty of good faith and fair
    dealing by rescinding the base pass of SBN's on-site Project Manager Roberts (app.
    br. at 309-16). It is well established that the implied duty of good faith and fair
    dealing applies to the government as it does to every other party to a contract and:
    [R]equires a party to refrain from interfering with the other
    party's performance and from acting to destroy the
    reasonable expectations of the other party regarding the
    fruits of the contract.
    SupplyCore, Inc., 
    ASBCA No. 58676
    ,      16-1BCA~36,262       at 176,907.
    The only contract provision for the removal of contractor personnel from the
    jobsite was on the basis that they were a danger to persons or property or they were a
    security risk/threat (finding 26). We find no credible evidence that Mr. Roberts was a
    danger to persons or property, nor that he was a security risk or threat. CFSC has
    never provided a reason to SBN, nor even internally within the government, for
    Mr. Roberts' removal. The Fund argues that Mr. Roberts was objectionable because
    he did not meet the contract requirements of "experienced, responsive and capable"
    (gov't br. at 208-31; findings 26, 141) It is a matter of record that Project Manager
    Roberts was inconsistent in holding Botting responsible to provide the contractually-
    required HVAC/mechanical design and in holding Jensen/Fey responsible for its
    contractual design and quality control obligations as Architect of Record, both of
    which resulted in design and contract performance delays and inefficiencies for other
    subcontractors (findings 18, 73, 77, 89, 101, 111, 105, 106, 111, 115, 119, 133, 140,
    152, 155, 217, 221). SBN also created its own causes of delay and inefficiency on the
    part of its subcontractors by changing the building design from a steel structure to a
    post tension concrete structure (finding 76) and by directing that its framing
    subcontractor install studs 24" on center instead of the designed 16" on center
    (finding 191). However, the contract does not provide to the government a unilateral
    remedy in the form of removal of an individual from the project for such management
    shortcomings. The record contains evidence of a personality conflict between
    Mr. Roberts and COR Dyer (and perhaps CO Bartholomew), but we find that is also
    not enough to justify his removal in the absence of a contract provision that authorizes
    such a removal.
    We have held that the government does not have the right to remove
    subcontractor personnel without obligating the government to compensate the prime
    contractor for additional costs incurred to perform the contract work as a result of the
    260
    removal. Advanced Engineering & Planning Corp., ASBCA Nos. 53366, 54044, 05-1
    BCA ~ 32,806 at 162,320.
    There is no greater interference with the manner and
    method of performance, short of termination of the work
    itself, than the ordered replacement of the craftsmen
    originally chosen to do the work.
    Liles Constr. Co. v. United States, 
    455 F.2d 527
    , 531-33 (Ct. Cl. 1972). The Court in
    Liles further held that such a change in the method or manner of performance was a
    compensable change entitling the contractor to recover excess costs proven to have
    resulted from the government's direction of removal. We find CFSC's removal of
    Mr. Roberts by rescinding his base pass and refusing to acknowledge him as the prime
    contractor's Project Manager to be improper in the absence of an express right to such
    a removal under the contract.
    SBN now claims that Mr. Roberts' removal resulted in damages in the form of
    "immediate and long-term impacts" in an unspecified amount of time or money (app.
    br. at 309, 314-16). The record before us is devoid of even a single contemporaneous
    letter, email or telephone call from SBN management or corporate offices expressing
    concern about, or even requesting an explanation of, CFSC's removal of Mr. Roberts
    from the jobsite. In fact, there is evidence that SBN's corporate management agreed
    that the removal of Mr. Roberts was "reasonable" and that Mr. Montoya, not
    Mr. Roberts, was the more appropriate person to be CFSC's primary SBN contact
    (finding 134). There is also no contemporaneous communication from SBN, other
    than the writings of the aggrieved Mr. Roberts, that SBN experienced any financial or
    other impact at the time. In fact, Mr. Roberts' replacement, Project Manager LaSharr,
    testified that he did not believe the project experienced any impact as a result of
    Mr. Roberts' removal from the project (finding 162).
    Nevertheless, SBN now seeks damages in the form of "interest, attorney's fees
    and costs" in an unspecified amount as a result of the alleged breach (app. br. at 341).
    On a purely hypothetical basis, one can conclude
    that surely there must have been some impact on
    appellant's operations .... But, we do not operate on the
    basis of pure theory. We are more pragmatic than that.
    We want some proof of an effect and proof as to any extra
    costs which may have been incurred.
    Space Age Engineering, Inc., 
    ASBCA No. 25761
     et al., 86-1 BCA ~ 18,611 at 93,472.
    Proof of the element of damages, while not necessary to a mathematical certainty, is
    necessary to a finding of entitlement on the basis of the alleged breach of the implied
    261
    duty. BAE Systems San Francisco Ship Repair, 16-1 BCA ~ 36,404 at 177,503; Military
    Aircraft Parts, 
    ASBCA No. 60009
    , 16-1BCA~36,388 at 177,410. Where, as here, no
    amount of damages has even been alleged to have resulted from Mr. Roberts' removal,
    much less proven, SBN has failed to establish a necessary element of its alleged breach
    and, on that basis, we deny entitlement on the basis of the rescission of Project Manager
    Roberts' base pass.
    B. Breach of Contract
    SBN also seeks unspecified damages allegedly incurred as a result of the
    rescinding of Mr. Roberts' base pass under the theory of breach of contract (app. br. at
    341). We deny entitlement for the same reasons stated above.
    IV. Trickle Vents and 95% Review Process
    The RFP required the following for outside air ventilation to guestrooms:
    Code-required outside air ventilation and make up air shall
    be provided the primary air handling unit using chilled
    water cooling and hot water heating to precondition all
    outside air before delivery through ductwork to each space.
    The outside air handling unit shall have the outside air
    intake at least I 0 feet above grade. The central AHU shall
    be provided with minimum 30% efficiency prefilters
    followed by 65% efficiency filters.
    (Finding 14) RFP Amendment No. 00005, dated 22 December 2003, reiterated the
    encouragement contained in the original RFP (finding 7) for the submission of alternative
    systems for consideration (finding 36). RFP Amendment No. 00006 provided that:
    1.   Outside air shall be supplied to the guest suites by a
    separate HVAC system. Outside air intakes shall not
    be provided at individual PTAC units (See Section
    C-5 Page 32).
    (Finding 37) RFP Amendment No. 00007 further clarified the requirement for outside
    air ventilation to the guestrooms:
    1. There have been a number of requests for
    clarification of air intake and centralized air distribution
    system requirements since the question and answer
    (Q/A #61) in Amendment #005, and the clarification in
    262
    Amendment #0006. The new lodge requires a central air
    distribution system, to distribute fresh air to the rooms.
    Individual PTAC units in the rooms are not to be used for
    make up or outside air intake, as stated in Section
    C-5.15.4d.
    (Finding 38) This verbatim language was reiterated in RFP Amendment No. 00009,
    dated 9 March 2004 (id.).
    Over one year later, on 30 March 2005, SBN/Botting proposed for the first
    time, in its 95% design submission, the use of passive trickle vents instead of the
    contract-required tempered forced air ventilation. There is testimony that the trickle
    vents were proposed in an effort to "simplify the system" and to save money.
    (Finding 145) The trickle vent proposal was rejected by CFSC on 7 April 2005 as not
    in compliance with the contract requirements for tempered forced air ventilation
    (findings 147, 149). On 13 April 2005 Botting replied that, despite CFSC's rejection
    of its proposed alternative, it was going forward with the trickle vents because without
    them, it opined, its HVAC system did not meet the required DoD Antiterrorism
    standards (findings 148: 150, 155). We note that, ifBotting's stated position was true,
    then the HVAC system it had proposed at the 35% and 65% design phases was also
    not in compliance with contract requirements and, if it was as important a
    consideration as SBN/Botting now claims, the fact that neither Botting nor SBN nor
    Jensen/Fey recognized the deficiency in their HVAC design for over a year is
    inexcusable.
    By 27 April 2005, less than 30 days after SBN's trickle vent proposal, CFSC
    had rejected the trickle vent proposal in writing three times while holding out the
    possibility of approving the proposal if a credit acceptable to CFSC was offered.
    Nevertheless, Botting was still pressing for approval of the trickle vents without
    offering any credit, obviously not wanting to share the alleged cost savings of the
    trickle vents with the Fund (findings 154-55). SBN recognized that the trickle vent
    issue was delaying its ability to complete its 95% design submission:
    I'm not sure that Botting understands that until it is
    determined which way we are going, i.e., trickle vent, or
    ducted make up air, we cannot complete our 95% design
    submittal. This is the only item that we need resolutiol'_l on
    to release everyone on the design, and we cannot release
    them without this decision. The trickle vent decision
    affects the building footprint at all four floors and the roof.
    It affects the electrical design, and the fire sprinkler piping.
    It affects partition types and chase locations on all four
    floors. No one can make the changes to the drawings that
    263
    are necessary to accomodate [sic] the trickel [sic] vent,
    until we know which system we are using. It is the single
    largest issue on the project, and has been for a month now.
    [Botting's] Burrus will not return my calls or my emails.
    We have written direction from the Owenr [sic] to provide
    the gas pack system we originally proposed, with ducted
    make up air to the guest rooms. If you can't get Burrus to
    respond with a credit so we can get approval from Drew
    for the trickle vent, then we are going to have to tell all the
    designers to proceed to 95% with the original system. The
    issuance of the 95% submittal is critical to getting this job
    bought out, and to preventing it from stopping because we
    don't have the subs and materials to continue the work
    beyond the structural phase.
    (Finding 154) On 29 April 2005, Botting again expressed its intention to include the
    trickle vent design in the 95% design submission despite CFSC's express disapproval
    (id.). As of 2 May 2005, even though it agreed that the trickle vent system did not
    meet contract requirements (finding 147), SBN also expressed its intention to include
    the unapproved trickle vents in its 95% design submission and its intention to force the
    government to accept the proposal:
    Due to the fact that the building construction is
    progressing, if the Owner rejects the 95% submittal
    because of the trickle vent system, it will be too late to
    revert to the original ducted system without suffering
    severe cost and schedule problems.
    We are gambling on the force protection issue, combined
    with the credit that the subcontractor is offering for the
    trickle vent to be sufficient for the Owner to ultimately
    accept the trickle vent. To date, the credit offer has not
    been sufficient for the Army to approve the trickle vent,
    and the Army has stated that ifthe 95% design is submitted
    with the trickle vent included, the entire submittal will be
    rejected. If that happens, the notice to proceed beyond the
    structural shell will not be issued, and the job will
    ultimately stop dead, waiting for a design resubmittal with
    different mechanical system, or some other approach, such
    as arbitration, to produce a solution that will cause the
    Army to issue the full NTP. The decision to switch to the
    264
    trickle vent system as a design basis for the project, rather
    than propose it as a V.E. issue, has now delayed the 95%
    design submittal by two months, so it is imperative that the
    Army accept the trickle vent design.
    (Finding 155) By letter dated 27 May 2005 SBN proposed including PTAC air dampers
    instead of trickle vents in its HVAC/mechanical system design (finding 159-60). On
    3 June 2005 CO Bartholomew responded that, unless SBN/Botting provided a significant
    6-7 figure credit, they were directed to incorporate into the 95% design submittal the
    3 February 2005 amended HVAC/mechanical design that included the contract-required
    outside air system for the guestrooms (finding 161). As of 11June2005 there was still
    no agreement with respect to the guestroom outside air system, causing the overall design
    to be in limbo and subcontractors to be concerned about moving forward without an
    approved design (finding 163). On 15 June 2005 Botting acknowledged its receipt of
    SBN' s directive to proceed with its 3 February 2005 design that included a "fully ducted
    system for each floor" and did not include trickle vents (finding 165).
    SBN admits that:
    The CO had a right to refuse this value engineering
    proposal or to impose conditions such as a reasonable
    credit. The CO was not required to accept the trickle vent
    proposal.
    (App. br. at 404) What SBN complains of is what it characterizes as the CO
    encouraging SBN/Botting to continue to pursue the trickle vents rather than
    disapproving it outright when it was proposed (id. at 404). The record, however,
    shows us that the trickle vent proposal was disapproved in writing three times within
    less than 30 days of its submission (findings 147, 149) and that it was SBN/Botting
    who nevertheless persisted in pursuing the use of the trickle vents despite the express
    written disapprovals (findings 148, 150, 154-55). It was only after SBN/Botting
    prolonged the discussion over trickle vents for nearly two months, from their initial
    disapproval on 8 April 2005 to 3 June 2005, that CO Bartholomew suggested a 6-7
    figure credit (finding 161). Nevertheless, Botting persisted in its pursuit of the use of
    the trickle vents until, on 15 June 2005, it was directed by SBN to proceed with its
    approved 3 February 2005 amended design that included a "fully ducted system for
    each floor" (finding 165). As a result of Botting's persistence in pursuing its trickle
    vent and PTAC damper proposals long after they were rejected by CFSC, SBN's 95%
    design submission was delayed until 14 July 2005 (findings 165, 167; app. br. at 405).
    Even then, SBN's Montoya admitted that the 95% submission on 14 July 2005 was
    incomplete (findings 167). In fact, SBN's 95% design submission was not complete
    for many months (see Section V below).
    265
    SBN further states that it is not seeking compensation for alleged delays
    associated with SBN/Botting's trickle vent proposal:
    Although [SBN] is not claiming time or money for
    delays related to the trickle vent option, the back-and-forth,
    which lasted about two months, is relevant to evaluating
    delays to the 95% design submittal, which was ready on
    June 3, 2005. Absent the Fund's encouragement of [SBN]
    and WAB to continue pursuit of the trickle vent option, the
    95% design submission and review could have occurred
    earlier. Had the Fund said initially that a seven figure
    credit would be required for the trickle vent option, or
    unequivocally denied the proposal, the time involved in the
    back-and-forth would have been saved. Furthermore,
    absent the earlier [alleged] design changes related to the
    HVAC system, the outside air proposals never would have
    occurred or certainly would have occurred at a much
    earlier date.
    The Fund's handling of the trickle vent proposal
    was a violation of its duty to cooperate and the Fund is
    responsible for associated damages. Those damages are
    difficult to measure, but are part of the overall cumulative
    impact experienced by [SBN].
    (App. br. at 405; see also app. br. at 109) We disagree. As summarized above, the
    record demonstrates that SBN/Botting caused the delay associated with the 11th hour
    trickle vent proposal and that SBN was fully aware that the trickle vent delay was
    delaying the 95% design submission. The record also shows that, even after the trickle
    vent delay was resolved, the 95% design submission was not complete.
    On the basis of the foregoing, we deny SBN' s claim that the Fund is
    responsible for any delays or impacts associated with the trickle vent proposal and the
    delayed submission of the 95% design.
    V. Framing LNTP and Direct Digital Controls (DDC) Design
    Prior to construction of the new Lodge (Building 2107) which is the subject of
    this appeal, the existing Fort Lewis Lodge (Building 2111) had a check-in desk and
    ONITY equipment (thermostats, key control and safes). Once the new Lodge was
    constructed, the RFP required relocation of the check-in desk and associated
    equipment to the new Lodge, but the relocated equipment in the new Lodge was still
    required to control the thermostats in Building 2111, the existing Lodge. The ONITY
    266
    equipment relocated to the new Lodge was required to communicate with the
    base-wide Tridium-based DDC system that controlled HVAC systems base-wide60 at
    Fort Lewis from a series of PCs or laptops located in DPW. There were two
    independent ONITY control systems at Fort Lewis. DPW was responsible for ongoing
    maintenance of the common areas and central mechanical systems at Fort Lewis and
    managed one ONITY system. The second ONITY system that controlled guestroom
    PTAC units was managed by MWR. Tridium R2 was the legacy version of the open
    protocol network for BACnet or Lonworks based controllers used by Fort Lewis and
    JACE was a graphics program "that brought this information in to PCs and allowed
    them to customize access into each building with floor plans and graphics." Tridium
    AX was a newer, different protocol that did not interface with the existing Tridium R2
    protocol used by Fort Lewis. (Findings 14-17)
    RFP Section C-1 required that SBN/Botting's proposed HVAC system be
    controlled by the specified DDC system:
    D. Controls: The HVAC system shall be controlled
    by a DDC system that complies with the Fort
    Lewis Design Standard DDC Design Guide
    Specification (See Section J). Each AHU and
    terminal unit shall have a Lon WORKS or
    BACnet DDC controller connected to a Tridium
    JACE controller. The JACE controller shall be
    connected to the building LAN (Ethernet Cat 5)
    and routed to a desk-top computer, with Tridium
    Niagra Web Supervisor and Workplace Pro,
    installed in the mechanical room. The
    maintenance staff shall have access to the
    system through any computer connected to the
    Network via use of a web browser that is
    password protected.
    E. . .. An existing ONITY "Senercomm" lnnPulse
    On-line system will be relocated from the
    Check-in point in existing Building 2111 to the
    new facility. Senercomm "SensorstatDDC"
    programmable digital thermostats or equal will
    be provided in new guest rooms. Connect all
    60   Over the course of 10-15 years, Fort Lewis had been including DDC systems with new
    HVAC systems when installed so they would communicate with the base-wide
    DDC system; older HVAC systems did not communicate with the base-wide DDC
    system (finding 14).
    267
    new room thermostats and Bldg 2111 thermostat
    system to the relocated lnnPulse Server, update
    software/system as required .... Coordinate with
    comm./data requirements and electrical
    capacities.
    (Finding 14) This section of the RFP also required that, if SBN/Botting's proposal did
    not include identified substitutions, they were required to "provide the products listed
    in the RFP" (finding 10).
    RFP Section C-5 required, with respect to DDC:
    15.    MECHANICAL
    15.1   General:
    G. The contractor shall have the responsibility to coordinate
    Mechanical equipment as it interfaces internally with
    DDC controls and externally with Division 16.
    15.6   Automatic Temperature Controls: Controls shall be
    stand-alone DDC and compatible with the Fort Lewis EMS
    "Tridium" system. The system will be connected to the
    Post-wide EMS system at a later date. The DDC system shall
    monitor HVAC equipment as defined in the paragraph herein.
    See Design Requirements in Section C3 & C4 for additional
    information regarding the control system. The DDC control
    system shall monitor, report and/or alarm the following
    HVAC functions and any other points required to control,
    operate and maintain the critical areas of the facility.
    F. Direct Digital Control (DDC) Points List: The following
    is a list of the minimum required DDC points:
    1. Air Handling Units (AHU)
    268
    4. PTAC Heat Pump Units
    5. Fans (other than AHU system fans)
    6. Terminal Units
    7. Boiler System
    8. Chiller System
    G. The DDC system shall provide automatic control of the
    common area HVAC system. This includes the AHU' s
    their zone terminal units and associated exhaust fans and
    heating/cooling equipment.
    1. In addition, provide for DDC control of individual
    PTAC heat pump units. This shall be a sub-DDC
    system designed specifically for the hospitality
    industry (ONITY "SenerComm" SensorstatDDC or
    equal), yet compatible with Tridium EMS for future
    connection to the Post system. Contractor shall be
    required to provide information about the DDC system
    submitted including: history, capabilities,
    compatibilities, useful life, maintenance costs,
    experience and reliability for use in this PTAC I heat
    pump application. The intent is to control/adjust each
    guest PTAC from a central control point using the
    ONITY "InnPulse" on-line monitoring/reporting
    system at the front desk, in addition to providing
    occupied/unoccupied sensing and setbacks and
    allowing the individual guest to control/adjust at the
    guest room.
    (Finding 17)
    269
    RFP Section L required that SBN's proposal include:
    (t)   HVAC System:
    (vi) DDC Controls: Provide narrative
    description of intended EMS Control
    system and catalog cuts of equipment to be
    provided.
    (Finding 32) Contrary to the RFP requirements, neither SBN's original proposal nor its
    BAFO included any DDC information (finding 82). SBN did confirm to CO Bartholomew,
    however, that it intended to be fully compliant with the RFP's requirements (finding 9).
    Likewise, none of SBN's 35% or multiple 65% design submittals included any information
    at all, compliant or not compliant, about what it specifically intended to provide to meet the
    RFP's DDC requirements (findings 86-87). SBN's 95% design submittal was the first one
    to include any DDC information (findings 88, 128) and SBN admitted that the submitted
    information was incomplete (finding 167).
    Botting's DDC subcontractor, Automated Controls, was a dealer for Johnson
    Controls equipment and a system integrator that took:
    [C]hillers, boilers, air handlers, cooling towers, ... all these
    different systems, some with different protocols and we
    marry them all into one system .... [W]e kind of define it as
    the brain of a building and we make them all work, talk to
    each other.
    (Finding 71) Automated Controls admitted that, in the pre-award proposal phase, it
    was not provided a design specification by Botting61 but it nevertheless provided
    Botting with an amount of$10-20,000.00 to include in Botting's HVAC proposal to
    SBN for the entire DDC system (finding 130). Later, after being provided the RFP
    design requirements, Automated Controls admitted to Botting that it had made
    incorrect assumptions:
    Project History:
    •    We quoted our standard DDC system .. .including
    [thermo ]stats for the rooms but not a hotel system as
    61
    We understand this to mean that Botting did not provide a copy of the RFP as it
    related to the DDC.
    270
    called out in the design build spec. We were not
    given the design spec .... [their budget up front to
    Botting before Botting provided the design spec did
    not include a hotel system that now they see is what
    is required (tr. 71180-181, 197-201)]
    •   [Botting's] Dave [Fillo] and I met to figure out how
    to cover the cost of the flat spec' ed Onity Hotel
    System (terms in spec also list "or equal" but after
    meeting with the Lodge personnel and review the
    existing facility they will be going with Onity).
    •   Dave and I submitted on the JCI Hotel System
    (equal) with the intent it would be rejected and then
    we would request a scope change to cover the cost
    of the Onity Hotel System.
    This is a government specification and a tough one
    to work around
    (Finding 130) Automated Controls estimated that providing the contract-specified
    DDC system would cost $50,000.00 more than the amount it had provided to Botting
    for inclusion in the proposal (finding 71).
    The president of Automated Controls testified that the RFP "called out Onity or
    equal as the base system ... [i]t'sjust all one system" (finding 71). However, our review of
    the RFP reveals that it actually only provided for the possibility of an "or equal" as it
    pertained to the thermostats. The RFP was otherwise very clear that the Fort Lewis system
    was ONITY and that the other components of the system were required to interface with
    the existing Fort Lewis ONITY system. (Findings 14, 17, 131)
    Regardless of the RFP requirement for interface ofDDC components with the
    existing Fort Lewis ONITY system, Automated Controls intended to:
    [B]ring [a Johnson Controls system] and do a comparison
    of [the Fort Lewis system]. Once we walked around the
    [existing lodging] facility, they showed us into the rooms.
    They showed us their thermostats. They went and showed
    us the front end of their system and they said it's Onity.
    And then we all sat down to review okay, how are we
    going to look at this project as a design-build. We quickly
    knew that the or equal side of that was not an option.
    They wanted Onity. They made it really clear to us they
    271
    wanted Onity. I don't even know ifl got my product
    submittal out of my bag to even show them at that point in
    time.
    (Finding 71) (Emphasis added) Even though Automated Controls admits it knew that
    Fort Lewis wanted an ONITY system, it still proposed a Johnson Controls system at a price
    that it knew was approximately $50,000 less than the ONITY system would cost (id.).
    Q:     Why did you do that?
    A:     We wanted it to be documented that they
    weren't accepting the or equal from the project, so there
    would be a justification for the costs associated with going
    to the Onity.
    (Findings 71) As we held above, the RFP permitted submission of an ''or equal"
    product for the thermostats only, not the entire DDC system. And Botting did not do
    an independent review of Automated Controls DDC submission before including it in
    their proposal to SBN (finding 131 ).
    In early February 2005, CFSC, DPW and Army Lodging agreed to accept
    SBN/Botting's 3 February 2005 amended alternative HVAC/mechanical system
    design (see Section I above) so long as two conditions were met, one of which was
    that the DDC system provided by SBN/Botting/Automated Controls met the
    RFP/contract specifications (findings 132, 135, 164). As of the end of February 2005,
    DPW had made clear that it would not accept a DDC system that was not compliant
    with the RFP/contract (finding 132) and SBN was reporting that "Botting understands
    what the RFP is calling for, and they will provide it, if they have to" (findings 133,
    135) (emphasis added).
    On 14 July 2005 SBN submitted an admittedly incomplete 95% design to CFSC
    (finding 167; see also Section IV above). Despite SBN's promise that the DDC system
    provided would meet the RFP/contract requirements, Botting's DDC design
    incorporated into SBN's 95% design submission was not in compliance "in any way
    shape or form!" and did not contain any of the required drawings or diagrams
    (findings 168-69, 171-72). SBN promised to resubmit the "mechanical items that are
    missing/need revised" on 12 August 2005 (finding 173). As of 15 August 2005 SBN
    agreed to the rejection of the resubmittal, which it had not reviewed before submitting,
    because it still had no DDC drawings and the DDC specification was "very sketchy and
    incomplete overall." Botting acknowledged that SBN had made clear that the DDC
    submittal was "critical" to the issuance of the next LNTP. (Finding 174) As of
    29 August 2005, SBN/Botting's re-submittal was still not complete (findings 175-78).
    272
    By letter dated 6 September 2005, SBN directed Botting to immediately complete the
    mechanical design documents for re-submittal no later than 9 September 2005 and that:
    Be advised that WA Botting's inability to obtain approval
    is currently imp~cting our schedule and has exposed [SBN]
    and others to potential non-recoverable costs. These
    impacts will be substantial if WA Botting does not obtain
    100% design approval, thus allowing [SBN] to receive a
    full notice to proceed with the Work. Please be aware that
    [SBN] will seek full recovery from WA Botting for all
    associated delays and impacts.
    Furthermore, be advised that the Owner has notified us that
    they will be withholding all payments due [SBN] and
    associated Subcontractors until this submission is
    approved.
    Please produce your re-submittal no later than
    September 9, 2005. A failure to complete all
    documentation as noted above may require that [SBN]
    direct all subcontractors to proceed with the work in
    advance of full approval from the Army to avoid further
    delays to the schedule. If this were to occur, [SBN] will
    seek full recovery from WA Botting for changes that may
    be necessary as a result of the final approval documents.
    (Finding 178; see also finding 179) As of 26 October 2005, almost two months later,
    SBN agreed that its 95% submission was still not complete (findings 180-82). On
    26 October 2005 CO Bartholomew authorized an additional LNTP, "subject to no
    HVAC authorization" (findings 183-85). In an internal Botting email, dated
    13 November 2005, the DDC design was apparently still not finalized:
    In an attempt to save the $85k we are spending on Onity
    controls, it was my intention to use the flawed controls
    specification to try and get out of buying the ONITY
    Controls and put them on the owner. After spending the
    afternoon going through all the correspondence from last
    year on this issue, it would be foolish for me to go down
    this path now. If we attempted to take this position at the
    start of the project, we might have had a slim chance.
    However, the project record clearly indicates that we were
    planning on providing an alternate system from day one
    and we had several opportunities in the past to put this on
    273
    the owner. We don't need to lose anymore [sic] credibility
    on this project.
    (Finding 187) On 28 November 2005 SBN/Botting submitted a revised DDC
    specification (finding 188; see also finding 192). No later than 15 December 2005,
    SBN was authorized to proceed with 100% design (finding 190). In the 23 January
    2006 comments to the 100% design submittal, the reviewers stated that the proposed
    DDC design still did not comply with the RFP:
    •   Furthermore, the products description and listed
    specification section compliance reference do not
    match in described details for that section,
    paragraph and sub-paragraph. The listed controllers
    are inappropriate for the intended use on this project
    and are conceptually inconsistent with the Fort
    Lewis Design Standards Topology and System
    Architecture which uses a standard PC Workstation
    and Tridium Niagara R2 suite of software to
    integrate field device controls to the enterprise level
    platform Supervisory controllers within a
    distributed control network.
    •   It is evident by the conflict in literature and the
    products listed in the submittal register that ... the
    intended architecture is to provide a system that
    does not provide a Web enabled Supervisory
    Software Application on a Workstation PC Platform
    as specified. The submitted Niagara AX software
    model is not the same version or generation of
    software solutions as the existing original Tridium
    Niagara R2 framework provided by Vykon and can
    [not] provide the same functionality that is bundled
    with Supervisor AX applications served to a
    browser from an embedded JACE platform.
    (Finding 201) On 15 February 2006 SBN provided Botting with its own comments
    regarding RFP noncompliance issues in Botting's mechanical design. On that same
    date there was an "Onity meeting" attended by SBN/Botting and Fort Lewis personnel.
    (Finding 207) SBN expressed its intention to submit the 100% design on 10 April
    2006 (finding 214). On 20 April 2006 CO Bartholomew authorized an HVAC LNTP
    (finding 215). Thereafter, SBN extended the 100% design submission date almost
    another month to 15 May 2006 (finding 216). SBN did not submit the 100% design
    until sometime between 26 May 2006 and 11August2006 (findings 216, 218-19,
    274
    222). On 4 January 2007, CFSC accepted the 100% design and issued a full NTP for
    construction of the project (finding 227).
    As it turned out, the existing ONITY equipment could not be relocated to the
    new Lodge because the distance between the existing and new Lodge buildings made
    interconnectivity difficult and because the new ONITY equipment installed in the new
    Lodge (thermostats, key control and safes) could not communicate with the existing
    ONITY system (finding 16). The cost of providing a new ONITY InnPulse Server
    (app. hr. at 127), as well as equipment SBN claims it was required to provide that was
    not specified in the contract (id. at 133-37) is included in SBN's claim.
    Throughout April and May 2007 there were multiple issues with the DDC
    system installed not being in compliance with SBN/Botting's own design and
    specifications to the point that it was "unusable" (findings 238-39, 242, 244). CFSC
    conditionally accepted the new Lodge effective 25 May 2007, subject to, among other
    listed items, the completion of the DDC system, including all required software
    licenses (finding 245). The DDC system was set for completion, demonstration and
    acceptance on 13-15 August 2007 (finding 247). However, by 15 August 2007, the
    DDC software installation, testing and documentation had still not been provided by
    Botting/Automated Controls (finding 248). On 17 August 2007 SBN issued a cure
    notice to Botting on the basis of the stated default of not meeting its contractual
    obligations and Botting had, in tum, issued a cure notice to Automated Controls
    several days later (finding 249). When the DDC open issues had still not been
    resolved by 28 August 2007, CO Bartholomew issued a cure notice to SBN requiring
    the matter to be resolved by 5 September 2007 (finding 250). The ceremony opening
    the new Lodge took place on 13 September 2007 (finding 251). However, as of
    14 September 2007, it was determined that the DDC issues still had not been
    corrected; SBN, even after Botting had replaced Automated Controls with TRS,
    acknowledged that, as of2 October 2007, the DDC work was not complete. In fact,
    the work was not considered complete and accepted by CO Bartholomew until
    1 December 2007 and the final documentation was not provided and considered
    complete until 25 February 2008 (findings 252-55). On 20 May 2008, the Fund
    acknowledged receipt of as-builts (finding 255).
    SBN argues that it is entitled to compensation on the basis of several theories of
    recovery related to the Fund's actions or inactions with respect to the DDC design.
    A. Breach of the Implied Duty of Good Faith and Fair Dealing
    It is SBN's position that the Fund breached the implied duty of good faith and fair
    dealing when it refused to issue the LNTP for framing based on then-existing issues
    involving the DDC portion of the HVAC/mechanical design (app. hr. at 335-37). SBN
    275
    argues that the DDC issues were unrelated to the framing LNTP and that the delay in
    issuing the LNTP pushed the framing work into the rainy winter months (id. at 336-37).
    SBN has not asserted a claim for any amount of damages as a result of the
    alleged breach. Proof of the element of damages, while not necessary to a
    mathematical certainty, is necessary to a finding of entitlement on the basis of the
    alleged breach of the implied duty. BAE Systems San Francisco Ship Repair, 16-1
    BCA ~ 36,404 at 177,503; Military Aircraft Parts, 16-1 BCA ~ 36,388 at 177,410.
    Where, as here, damages have not even been alleged, much less proven, SBN has
    failed to establish a necessary element of its alleged breach and, on that basis, we deny
    entitlement.
    B. Delay
    SBN argues that CFSC's failure to issue a timely LNTP for framing on the
    basis of the non-compliant DDC design delayed work on the critical path from
    17 August 2005 through 30 October 2005 (app. hr. at 119, 385-86; ex. A-7). SBN
    further argues that DDC design issues, for which it alleges SBN and CFSC share
    responsibility, delayed work on the critical path from 2 August 2005 through
    6 December 2005 (app. hr. at 119, 385; ex. A-7). On the basis of the foregoing, we
    find that SBN was solely responsible for critical path delay caused by the failure of the
    DDC design to comply with the contract requirements from 2 August 2005 through
    6 December 2005 and CFSC was solely responsible for critical path delay from
    17 August 2005 through 30 October 2005 due to its failure to issue a framing LNTP.
    As SBN's caused delay is fully concurrent with CFSC's caused delay, we find that
    SBN is not entitled to delay damages.
    VI. Ceiling Heights, Room Sizes and Mechanical LNTP
    As we held above, the parties agreed in Modification No. P00003 that no claim
    based upon ceiling heights, square footage or associated impacts could be brought
    after 23 March 2006 except as reserved in paragraph 4 of the modification. The only
    claims reserved were those for ''time and associated cost impacts" (finding 212). We
    therefore reject SBN's claim for damages due to a breach of the implied duty of good
    faith and fair dealing on the basis of the ceiling height and square footage issues. We
    will limit our discussion here to SBN' s claim for delay damages which was reserved in
    Modification No. P00003.
    The RFP required that "Offerors who choose to submit alternate building or site
    configurations must meet all requirements in the RFP" (finding 7) which included:
    Guest Room floor plan, layout and sizes shall be in
    accordance with the concept guest room drawings provided
    276
    in the RFP. Mechanical chases, plumbing chases, etc. are
    to be integrated without reducing net areas shown or
    specified.
    (Id.; see also finding 13) RFP Amendment No. 00005, Question and Answer 34,
    reiterated the RFP's requirement that corridor ceilings were to be a minimum of 8'4"
    (finding 36). On 29 January 2004 SBN assured CO Bartholomew that SBN's proposal
    was compliant with the square foot requirements of the RFP (finding 46).
    As of the 8 July 2004 35% design review meeting, it was noted by COR Dyer that:
    24.    Corridor ceiling heights are shown 8'-4". There may
    be cases where corridor ceiling heights are adjusted
    downward to account for piping and ductwork. In
    thos.e cases, CFSC will be advised beforehand.
    Swinerton will not design or construct any corridor
    ceiling heights less than 8'-0".
    (Finding 62) (Emphasis added) SBN's 65% mechanical design, as a result of
    including the RFP-required boiler/chiller and its associated piping, also included:
    The piping was accommodated by making all corridor
    ceilings no higher than 8'-0"and by raising the second floor
    by four inches, and taking two inches off of the distance
    between the third and fourth floors.
    (Finding 84) In the 22 September 2004 65% Design Review Comments, COR Dyer
    made a reference to an understanding that ceilings would be no lower than 8'-0" but
    there is no indication that the referenced understanding extended beyond the single
    item to which he made the comment (finding 81). By the time SBN and its
    subcontractors met on 27 October 2004 to discuss the 95% design, SBN acknowledged
    that all the guest room dimensions were too small and that the ceiling heights in all the
    public corridors were at a maximum height of 8'-0" (finding 93).
    If, as argued by SBN/Botting, it changed its designed ceiling heights to 8'0" to
    accommodate the piping necessary for the boiler/chiller system, it follows that
    SBN/Botting's original design that included a not-yet-approved alternative design
    included the required 8'4" ceiling heights. In early February 2005 CO Bartholomew
    approved Botting's 3 February 2005 amended alternative design which no longer
    needed the space for the piping associated with the boiler/chiller (see Section I above).
    SBN, however, made the unilateral decision not to change the building design back to
    the 8'4" corridor ceilings because the designs of SBN and its subcontractors had
    already been changed to accommodate the 8'0" ceiling heights and SBN sought to
    277
    mitigate the impact of the HVAC design delays on the designs of SBN and its other
    subcontractors (findings 129, 197).
    On 14 December 2005 SBN contacted CO Bartholomew about the LNTP for
    HVAC rough-in being held up due to corridor ceiling heights less than 8'4":
    Previously, it was my understanding that the issue was
    within the rooms and as you know we have
    acknowledged and revised those ceiling heights at the
    entries. We are currently reviewing the issue at the
    corridors and the correspondence that has resulted in the
    ceiling heights being at 8'-0" upon determination of same
    we will advise. It should be noted that we are being
    impacted by being unable to proceed with the HVAC
    work at this time.
    (Finding 189) As of 15 December 2005 COR Dyer stated that SBN's 100% design
    documents were to show "all RFP ceiling heights being attained" (finding 190). The
    19 December 2005 mock-up room inspection comments noted that:
    SBNW admitted [the extended stay (ES)] room was
    approx. 293 SF, below the 300 SF standard. The reason is
    apparently due to the shear wall adjacent to the adjoining
    ES room. SBN[] was requested to issue RFI informing
    Lodging how many rooms in the entire building fall
    below the standard. VERY IMPORTANT!
    (Finding 191)
    By letter dated 22 December 2005, SBN advised CO Bartholomew that the lack
    of a LNTP for HVAC rough-in was "adversely affecting the project" and that:
    [I]t was clear that all parties understood and agreed that
    the 8'-4" ceiling heights within the corridors were
    unachievable with the [boiler/chiller] design
    requirements and this was accepted at the early stages
    of the project which is evident by the documents
    provided by the Army. As noted in same I it is true that
    this item has not been changed via the change process,
    but it is clear that all parties were amiable to the
    revision. It is our belief that this revision at the 35%
    documents and 65% document review provide
    agreement with the revised ceiling elevations and
    278
    allowed for the reduction in the ceiling height to 8'-0".
    As such, we request the release of the [LNTP] with the
    HVAC based on the prior agreement of the 8'-0"
    ceilings being acceptable.
    (Finding 193) CO Bartholomew responded the next day:
    I would have an incredibly hard time believing anyone on
    our end would permit a lowering of ceiling heights without
    a serious discussion and a significant credit. This issue has
    come up on a number of other projects in the past and is a
    Lodging ''Hot Button". While the reduction of 4" may not
    have been picked up in our reviews, there has been no
    contractual action taken to lessen the contract requirement
    for ceiling heights in this building. I refer back to a letter
    that is part of the contract signed by an ind[iv]idual who
    signed the bid that [SBN] would be materially compliant
    with the RFP.
    (Finding 195) A week later, CO Bartholomew again stated that there had been no
    contractual action to reduce the required ceiling heights from 8'4" to 8'0" and that the
    RFP-required ceiling heights must be included in the 100% design submission "even if it
    delays [the submission]" (finding 195). This direction was reiterated by CO Bartholomew
    and COR Dyer on 5 January 2006 (finding 196). By letter dated 10 January 2006, The
    Architect of Record, Jensen/Fey, weighed in on the subject of ceiling heights:
    We acknowledge receipt of your e-mail regarding the
    requirement for 8'-4"ceiling heights. It should be
    specifically noted that the 8'-0" ceiling heights were
    included in the 35% submittal documents and are very
    clearly shown in the 65% and 95% documents and were
    subsequently discussed during the review conferences with
    the Army Team at each phase. The agreement on this issue
    was relied upon to develop the progress drawings and
    therefore shown on the drawings and constructed in the
    field.
    In an effort to accommodate your latest request to revert
    back to the 8'-4" ceiling height, a design meeting was held
    at the site on January 5, 2006 to review options available.
    After numerous discussions and strategies we were unable
    to come up with any solutions to revert to the 8'-4" ceiling
    279
    height (short of tearing the building down and starting
    over).
    Therefore, we believe that the 8'-0" ceiling heights
    aesthetically have no significant impact on the quality or
    performance of the facility and shall remain as previously
    noted.
    (Finding 197) COR Dyer denied the allegation that the 8'0" ceilings had been
    discussed and resolved during the 35%, 65% and 95% design review meetings,
    however:
    My only suggestion at this point [is] to seek a form of
    compensation for the error and omission. I know this is a
    copout, but what other option do we have except to tear
    down the building and start again? What is really
    disturbing is that Lodging is being asked to accept
    something different than was specifically stated in their
    requirements (again). Why do we always have to bend
    over, especially when it's a clearly written requirement in
    the proposal that we send to hand selected design-builders?
    (Finding 198) CO Bartholomew agreed that there had been no contractual action to
    change the contract requirement for ceiling heights at a minimum of 8'4" and that he
    would not approve any deviation without consideration in the form of a credit from
    SBN (finding 200).
    As of 19 January 2006 SBN admitted that 159 of the 185 guestrooms did not
    meet the contractual square footage requirements:
    3. Unit Square Footage: over 100 units do not
    meet the RFP minimum requirements. The
    dimension busts are taken off the CAD
    drawings. We will be developing our letter to the
    Owner. Bart is not completely knowledgeable of
    the magnitude of the issue at this time.
    The impacts to the square footage were a result
    of drawing completion and shear walls that were
    added within the building space that affect the
    net rentable area, design deficiencies with the
    architect. There is some confusion as to how the
    280
    square footage was originally calculated; we are
    in the process of figuring this out.
    ums
    "t summary B re akd own
    Less           16 to 21 SF        4 Units
    Less           10 to 12 SF        4 Units
    Less           6 to 9 SF          56 Units
    Less           1to5 SF            56 Units
    Gain           1 to 5 SF          24 Units
    Gain           6 to 9 SF          7 Units
    Gain           12 to 14 SF        3 Units
    Gain           15 to 20 SF        5 Units
    Total Square Units Impacted              159 Units
    Total Square Feet Lost                   345 Square Feet
    (Finding 200)
    By letter dated 31 January 2006 SBN offered a $10,953 credit as consideration
    for changing certain ceiling heights from 8'-4" to 8'-0" and an $8,492 credit as
    consideration for a net reduction of 198 square feet in the room areas in the entire
    project. They also enclosed 100% design documents and requested an LNTP for the
    HVAC work as well as the final NTP upon an "expedient review" of the 100% design.
    (Findings 202, 204) Several days later SBN increased the offered credit to $100,000
    for both the ceiling height and room square footage issues (finding 204).
    CO Bartholomew responded that he and Army Lodging would accept no less than a
    $200,000 credit. SBN agreed to the amount of $200,000 but stated that it would be a
    credit to cover the ceiling heights, room square footages, as well as associated
    variances such as light switch locations, ceiling fan locations, etc. A contract
    modification was never issued memorializing the credit of $200,000 and its basis. The
    parties continued to negotiate and CO Bartholomew:
    Authorize[ d] a 10 day non-compensible [sic] extension of
    the contract completion date, from 21February2006 to
    3 March 2006. We reserve all rights including the right to
    issue a Show Cause why we should continue and not
    Terminate for Default.
    (Finding 209)
    On 2 March 2006 SBN recorded the following in a handwritten document
    identified as "Minutes of Mtg":
    281
    SUMMARY
    -     AN AGREEMENT WAS REACHED AFTER SEVERAL
    ROUNDS OF NEGOTIATION IN WHICH (SBN] AGREED
    TO A $500,000 DEDUCTIVE CHANGE ORDER
    -     INCONSIDERATION THEREOF THE ARMY CFSC
    ASSURES THAT
    CD No LIQUIDATED DAMAGES WILL BE ASSESSED
    THRU THE END OF [SBN]'S NEXT SCHEDULE UPDATE
    WHICH WILL INCLUDE THE REVISED MOCK-UP
    PROCESS AGREED UPON IN THIS MEETING
    Cl) THE MINOR DEVIATIONS WILL BE FLUSHED OUT
    DURING THE REVISED MOCK-UP PROCESS AGREED
    UPON IN THIS MEETING. A RESOLUTION WILL BE
    AGREED UPON FOR EACH. ARMY LODGING WILL BE
    INFORMED, PRIOR TO PUNCH LIST PROCEEDINGS,
    THAT THE MINOR DEVIATIONS HA VE BEEN AGREED
    UPON AND CONSIDERATION PROVIDED.
    THE REVISED MOCK-UP PROCESS AGREED UPON IN THE
    MEETING INCLUDES THE FOLLOWING STEPS:
    3/7106     [SBN] WILL PROVIDE RESPONSES TO THE CFSC
    MOCK-UP COMMENTS INCLUDING PROPOSED
    SOLUTIONS
    3/14/06 CFSC WILL RESPOND TO THE ABOVE COMMENTS
    AND PROPOSED SOLUTIONS.
    3/17/06 (SBN] WILL ISSUE A REVISED PROJECT SCHEDULE
    TO INCLUDE THE REVISED MOCK-UP PROCESS AND
    THE IMPLEMENTATION OF THE SOLUTIONS TO THE
    MINOR DEVIATIONS.
    3/21/06 AN ON-SITE JOB WALK WILL BE HELD WITHIN
    THRU    THREE WEEKS OF 3/21/06 AT WHICH ALL ISSUES
    4/11/06 WILL BE REVIEWED AND FINALLY RESOLVED.
    282
    3/31/06 100% ORA WINGS WILL BE SUBMITTED
    INTEGRATING THE RESOLUTIONS TO THE MINOR
    DEVIATIONS.
    (Finding 210) In these contemporaneous notes of the agreement memorialized in
    Modification No. P00003, SBN makes no mention or other indication that it
    considered the negotiated amount to be what it now claims was "excessive" and
    "extortionate" (app. hr. at 316; app. reply at 22; gov't br. at 181-82). Nor do we find
    any other contemporaneous support for this allegation. Bilateral Contract
    Modification No. P00003, in the amount of a $500,000 credit, was executed on
    30 March 2006 (findings 204, 210, 212).
    SBN argues that it is entitled to compensation for delays to the critical path
    from 14 December 2005 to the 20 April 2006 issuance of the mechanical LNTP
    (finding 215; app. br. at 175). The alleged period of delay occurred during Period 4 in
    which trade rough-in was on the critical path (finding 98; app. br. at 281; ex. A-7). 62
    We find no evidence that the contract requirements for ceiling height and room square
    footage were ever formally modified. The parties disagree as to whether there was an
    informal agreement to accept corridor ceiling heights at 8'-0", however, we have
    found no evidence of any agreement by CFSC to accept room square footage changes
    prior to the agreement memorialized in Modification No. P00003. SBN admits that, as
    of 14 December 2005, it was aware ofCFSC's concerns about nonconforming room
    sizes (app. hr. at 175). We find that the changes in the room square footages as
    constructed occurred because of the design confusion resulting from the
    HVAC/mechanical design issues early in the contract (see Section I above) and the
    out-of-sequence work and re-work required of SBN and the other subcontractors
    (findings 63, 66, 67, 69, 74, 76, 79, 84, 129, 140, 161, 178, 182, 217, 221). As of
    19 January 2006 SBN acknowledged that 159 of the 185 guestrooms "do not meet the
    RFP minimum requirements," with some rooms being larger and some smaller and
    that CO Bartholomew "is not completely knowledgeable of the magnitude of the issue
    at this time" (finding 200). About a week later, SBN offered a credit as consideration
    for CFSC's acceptance of the non-conforming room sizes. The parties reached
    agreement on the amount of the consideration on 2 March 2006, which was then
    memorialized in Modification No. P00003 dated 30 March 2006. (Finding 212)
    We find that SBN was solely responsible for the critical path delay due to
    nonconforming room sizes from 14 December 2005 to the 2 March 2006 agreement on
    consideration. We find that SBN is entitled to be compensated for the critical path
    62
    Curiously, SBN does not show this alleged delay to the critical path on Exhibit A-7,
    nor does it discuss this alleged delay in its critical path delay narrative. This
    omission, however, does not negate SBN's arguments regarding the delay
    elsewhere in its brief.
    283
    delay period from 3 March 2006 through the 26 April 2006 issuance of the mechanical
    LNTP (39 calendar days) which was solely caused by CFSC and the claim for which
    was expressly reserved in Modification No. P00003. The amount of compensation due
    for the delay is a quantum issue which is not before us.
    VII. Mock-up Rooms and 100% Design
    The contract required the construction of external (outside the building)
    stand-alone mock-up concept rooms for each of the two guestroom types on the
    project site. The mock-up rooms were to be subject to a "walkthrough of rough
    construction" by CFSC at the time of the 35% Design Review Meeting. The final
    walkthrough of the completed mock-up rooms was to take place "at an appropriate
    time to allow for design corrections and adjustments prior to submission of the final
    design." The contract also required the completion of two Final Concept Rooms
    inside the building. (Finding 7) Throughout the record both parties refer to both the
    external mock-up rooms and the internal Final Concept Rooms as the mock-up rooms.
    In CFSC's detailed 35% review comments, it was stated that it was CFSC's
    intention to accept completed mock-up rooms on or about 21 September 2004 after the
    65% design review meeting (finding 60). On or about 22 September 2004, in the
    context of 65% design review comments, it was noted that the external mock-up rooms
    were no longer to be constructed; however, there is no record of a contract
    modification to delete this work or to give the Fund a credit for the deleted work. The
    first CFSC inspection of the two internal Final Concept Rooms (referred to by the
    parties as mock-up rooms) took place on 13 December 2005 (finding 189). The
    19 December 2005 inspection comments (finding 191) raised the issue of room sizes
    and several other issues addressed in Section VI above. SBN's 100% design was
    submitted on 31January2006 (finding 204). A second CFSC inspection of the Final
    Concept Rooms (mock-up rooms) was conducted on 9 March 2006 (finding 211).
    As of 30 March 2006 the parties had resolved their differences over ceiling
    heights and room square footage and the express terms of Modification No. P00003
    specified that the results of their agreement were to be incorporated into a 100%
    design resubmission (findings 205, 212, 214). As of23 May 2006 SBN had still not
    submitted its 100% design to CFSC and was not sure it would meet its promised
    submission date of26 May 2006 (findings 216, 218-19). The 100% design was
    submitted sometime between 26 May 2006 and the week of 12 June 2006, the week
    scheduled for the 100% design review and a walk-through of the internal mock-up
    rooms (findings 218, 219). Sometime around 7 June 2006 CFSC experienced a travel
    lockdown and was unable to travel from Virginia to Fort Lewis during the week of
    12 June 2006. When the travel lockdown was lifted, the 100% design review and the
    walk-through of the mock-up rooms was rescheduled for 11-12 July 2006.
    (Finding 219) As of 9 October 2006, the quality of the Final Concept Rooms
    284
    (mock-up rooms) was still an issue and a post-Thanksgiving inspection was suggested
    (finding 223).
    SBN argues that it is entitled to compensation on the basis of several theories of
    recovery related to the Fund's actions or inactions with respect to the mock-up rooms.
    A. Breach of the Implied Duty of Good Faith and Fair Dealing
    SBN argues that CFSC breached the implied duty of good faith and fair dealing
    by intentionally failing to respond to numerous RFis associated with the mock-up
    rooms (app. br. at 337-40). However, SBN has not asserted a claim for any amount of
    damages in the form of either time or money as a result of the alleged breach. Proof of
    the element of damages, while not necessary to a mathematical certainty, is necessary
    to a finding of entitlement on the basis of the alleged breach of the implied duty. BAE
    Systems San Francisco Ship Repair, 16-1 BCA ~ 36,404 at 177,503; Military Aircraft
    Parts, 16-1BCA~36,388 at 177,410. Where, as here, damages have not even been
    alleged, much less proven, SBN has failed to establish a necessary element of its
    alleged breach and, on that basis, we deny entitlement.
    B. Constructive Changes
    There is no dispute that the mock-up room process was changed when the
    requirement for the exterior mock-up rooms was deleted. Even though work was
    deleted without deleting a commensurate amount of money from the contract amount .
    as a credit to the Fund, SBN alleges that it and its subcontractors performed extra work
    and incurred additional costs during the claimed period from 6 January 2006 through
    9 May 2006 due to the Fund's deletion of the external mock-up rooms over a year
    earlier in September 2004 (app. br. at 148-49, 154, 374-76; app. reply at 49). It is
    clear to us from our examination of the extensive record in this appeal that SBN and its
    subcontractors did indeed perform additional and out-of-sequence work because of the
    extensive delays and design confusion associated with the nonconforming HVAC
    design and later DDC design (see Sections I , IV and V above). SBN has failed to
    show that it incurred specific costs and/or experienced specific delays directly as a
    result of the deletion of the external mock-up rooms. We, therefore, deny entitlement.
    285
    C. Delay
    SBN argues that it experienced a constructive suspension of work on the critical
    path from 7 June 2006 through 12 July 2006, the time between CFSC's notification to
    SBN of a travel lockdown that precluded its ability to travel to Fort Lewis during the
    week of 12 June 2006 and the rescheduled dates of 11-12 July 2006 for the 100%
    Design Review Meeting and the walk-through of the mock up rooms (app. br. at 178,
    386-88). SBN further claims:
    The delay to the Mock-Up and 100% design review
    impacted the Project critical path. Absent prior delay and
    disruption to the design and Mock-Up process (see
    sections on The 95% Design Review Process, Direct
    Digital Controls and Initial Mock-Up Room Process) these
    activities would not have been on the critical path at this
    time. Because of those prior delays, however, the 100%
    design review and Mock-Up completion were critical and
    the Fund is responsible for the delay ....
    (App. br. at 178)
    We found above in Section IV that SBN was responsible for the critical path
    delay to the 95% design review process. We found in Section V that, while the Fund
    was responsible for critical path delay from 17 August 2005 through 30 October 2005
    due to its failure to issue a framing LNTP, that delay was concurrent with the critical
    path delay caused by the failure of the DDC design to comply with the contract
    requirements from 2 August 2005 through 6 December 2005 for which SBN was
    solely responsible and, as a result, we found that SBN is not entitled to delay damages.
    If we were to follow SBN' s reasoning in its brief, those delays, for which we have
    found SBN responsible, were what caused the mock-up room walk-through and 100%
    design review to be on the critical path and that would also be SBN' s responsibility.
    In addition, the delay period claimed by SBN is the period between the
    originally-scheduled events to take place during the week of 12 June 2006 and when
    they actually took place on 11-12 July 2006 due to the CFSC travel lockdown. There
    is no evidence of when the lockdown actually ended, nor have we found any evidence
    of discussions between the parties about whether the rescheduled dates were a function
    of the availability of SBN participants, CFSC participants or a combination of both.
    As a result, we have no basis upon which to find that the period of time upon which
    SBN bases its claim was unreasonable under the circumstances. We, therefore, deny
    SBN's claim for delay damages associated with the reschedule of the mock-up room
    walk-through and the 100% design review.
    286
    VIII. Final and Other Direct Changes
    SBN argues that it is entitled to compensation under the contract's Changes
    clause for the following directed changes to its work. SBN argues in the alternative
    that, should we not find the following to have been direct changes, they were
    constructive changes. SBN also seeks delay damages associated with the alleged
    changed work as specified below. (App. br. at 364-74, 376-78; app. reply at 47-48)
    A. Changed Work
    1. Final Changes
    a. Front Desk Modifications-Casework
    b. Front Desk Modifications-Camera monitoring
    c. Front Desk Modifications-Alarm system
    d. Irrigation System
    e. Building Corbels
    f. Service Gate and Intercom
    Five of the six (6) claimed Final Changes were included in unilateral
    Modification No. P00008 (finding 240), however, SBN argues that Modification
    No. P00008 did not compensate it at all for the costs associated with the service gate
    and intercom. With respect to the other five (5) claimed components of Final
    Changes, SBN claims that the work was directed by CO Bartholomew and agrees that
    Modification No. P00008 partially compensated it, however, the compensation was for
    less than the amount of the increased costs it incurred in performing the work. SBN
    now seeks $4,697 .00 for the service gate and intercom63 plus an additional amount for
    the other five listed Final Changes which it characterizes as "disputed mark-up only"
    (app. br. at 178-86, 291, 293, 364-66; R4, tab 169 at 5182).
    With respect to the first five claimed Final Changes (all but the service gate and
    intercom), the Fund agrees that they were changed work and SBN is entitled to
    compensation for that work. The Fund, however, argues that SBN was fully
    compensated in Modification No. P00008 for its increased costs (gov't br. at 280; app.
    br. at 365-66). The additional amounts now sought by SBN for disputed mark-up are
    questions of quantum and the proof thereof which is not now before us.
    The Fund argues that it denied change order requests for work associated with the
    service gate and intercom (gov't br. at 280, 285), however, the Progress Meeting
    minutes of 17 January 2007 show that CO Whitley authorized both changes during the
    63
    SBN seeks the difference in the cost of the revised service gate and intercom that
    was installed ($17,226.00) and the originally designed service gate
    ($12,529.00) (app. br. at 186, 291, 293).
    287
    meeting (finding 229). From 4-31 January 2007 CO Whitley was the person with
    authority to bind the Fund (findings 227, 234). On this basis, we find SBN entitled to be
    compensated for the service gate and intercom work authorized by CO Whitley. The
    amount of the compensation is a question of quantum and quantum is not before us.
    2. Furring Out Walls
    SBN argues that the Fund directed that one wall in Rooms 215, 315, 216, 316,
    256, 236 and 336 was to be furred out between columns (app. hr. at 291, 366, 376-77).
    SBN claims the work was completed and now seeks compensation for the work in the
    amount of $3,414.00 (app. br. at 291, 293; R4, tab 169 at 5182, 05234-36). The Fund
    responds that this work was associated with the square footage issues which were
    specifically released by SBN in Modification No. P00003 (gov't hr. at 283-85; see
    also Section VII above). We agree and deny entitlement.
    3. Revisions to Administration Rooms
    SBN claims that the Fund directed certain design revisions to the administration
    rooms in the new Lodge and that the work was completed on 14 September 2006.
    SBN now seeks compensation for the work in the amount of$6,539.50. (App. br. at
    291, 293, 366-67, 377; R4, tab 169 at 5182) The Fund's briefs do not dispute this
    portion of SBN' s claim. We therefore find SBN entitled to be compensated for the
    claimed work. The amount of the compensation is a quantum matter which is not now
    before us.
    4. Revise Rubber Stair Treads and Risers
    SBN claims that the Fund directed it to install rubber stair treads and risers
    instead of the contract-required VCT resilient flooring and that the work was
    completed 10-13 March 2007. SBN now seeks compensation for the work in the
    amount of $9,838.30. (App. hr. at 292-93, 367, 377; R4, tab 169 at 5182). The Fund's
    briefs do not dispute this portion of SBN' s claim. We therefore find SBN entitled to
    be compensated for the claimed work. The amount of the compensation is a quantum
    matter which is not now before us.
    5. Relocation of Electrical Boxes
    SBN claims that the Fund's direction to install outlets directly below the PTAC
    units (finding 220) was a change to the contract requirements and that the work was
    completed. SBN now seeks compensation for the work in the amount of$17,823.00.
    (App. br. at 292-93, 367, 377-378; R4, tab 169 at 5182) The Fund's briefs do not
    dispute this portion of SBN' s claim. We therefore find SBN entitled to be paid for the
    288
    claimed work. The amount of the payment is a quantum matter which is not now
    before us.
    6. Installing Laundry Floor Drain
    SBN claims that the Fund's direction to add a floor drain in the main laundry
    room (Room G-40) was a change to contract requirements. SBN seeks compensation
    for the work in the amount of $3,861. 00. (App. br. at 292-93, 367, 377; R4, tab 169 at
    5182). The Fund's briefs do not dispute this portion of SBN's claim. We therefore
    find SBN entitled to be paid for the claimed work. The amount of the payment is a
    quantum matter which is not now before us.
    7. Installing Change and Soap Vending Machines
    SBN claims that the Fund changed the contract requirement for the change and
    soap vending machines from government-furnished/government-installed equipment
    to government-furnished/contractor installed equipment. SBN now seeks
    compensation in the amount of $1, 191.00 for its installation of the equipment. (App.
    br. at 293, 367-68, 378; R4, tab 169 at 5182). The Fund's briefs do not dispute this
    portion of SBN's claim. We therefore find SBN entitled to be paid for the claimed
    work. The amount of the payment is a quantum matter which is not now before us.
    8. Other Direct Changes
    a.   COR 26: Furnish freezer & refrigerator
    b.   COR 27: Add vanity base cabinets
    c.   COR 31: Revise break room configuration
    d.   COR 32: Remediate P-lam at mock-ups
    e.   COR 35: Extension at refrigerators
    f.   COR 42: Supply & install mangler
    g.   COR 46: Washer & Dryer pricing
    h.   COR 52: Revise carpet layout
    With respect to the eight (8) claimed components of Other Direct Changes,
    SBN seeks the total amount of $4,766.77 for which it was not compensated in
    Modification No. P00008 and which it characterizes as "disputed mark-up only" (app.
    br. at 290, 293, 368, 378; R4, tab 169 at 5182). There are no claims for delay damages
    associated with the Other Direct Changes. The Fund's briefs do not dispute this
    portion of SBN' s claim. We therefore find SBN entitled to be paid for the claimed
    work. The amount of the payment is a quantum matter which is not now before us.
    289
    B. Delay
    SBN seeks critical path delay damages from 17 January 2007 through 26 March
    2007 due to front desk changed work (app. hr. at 179-81). The front desk work was on
    the critical path until the end of Period 6 which was 6 February 2007 (finding 98). As
    we discussed above, the Fund has agreed that it directed the front desk changed work
    and that it is responsible for the costs associated with performance of the work. With
    respect to the claimed delay damages associated with the front desk changed work, the
    Fund's position is that SBN has already been compensated for the delay in the
    modification issued for the changed work (ex. G-5 at 8). It is well established that a
    contractor is presumed, in the absence of a specific reservation in the modification, to
    have included in its cost proposal for extra work an amount to compensate it for the
    time required to complete the changed work. R. W Contracting, Inc., 
    ASBCA No. 24627
    , 84-2 BCA ~ 17,302; CBC Enterprises, Inc. v. United States, 
    24 Cl. Ct. 187
    (1991). However, in Modification No. P00008 the parties specifically reserved SBN's
    right to seek additional time. This is consistent with CFSC's position throughout the
    record that discussions of time and delays would be addressed at the end of the project
    in discussion of SBN's REA/claim, which, as we address in Section XI below, never
    happened. We therefore find SBN entitled to compensation for critical path delay
    from 17 January 2007 through 6 February 2007 (15 calendar days) associated with the
    front desk changed work.
    SBN further claims that it experienced additional delays due to other changed
    work that it admits were not on the critical path (app. hr. at 183-84, 186). As these
    delays were not on the critical path, they are not compensable.
    IX. Pre-final Inspection
    The contract required that SBN' s design team, led by its Architect of Record,
    Jensen/Fey (finding 19), was to inspect the entire project and determine when it was
    ready for a pre-final inspection. Once SBN received the determination from
    Jensen/Fey, it was to notify the CO in writing that it was ready for a pre-final
    inspection. (R4, tab 1 at 97) SBN argues that the parties had agreed to conduct a
    pre-final inspection during the week of 12 March 2007 (app. hr. at 187-88). However,
    as of 13 February 2007, SME reported to SBN that it would be unable to be ready for a
    pre-final inspection by mid-March 2007 due to work still remaining to be done by
    other trades (finding 233).
    The first notification by Jensen/Fey of a determination that the project was
    ready for a pre-final inspection was by letter dated 28 March 2007 sent to COR Dyer,
    and followed up the following day by a letter from SBN to CO Bartholomew formally
    requesting a pre-final inspection. CO Bartholomew scheduled the pre-final inspection
    290
    to begin on or about 16 April 2007. (Finding 237) The pre-final inspection took place
    17-19 April 2007 (app. br. at 188).
    SBN claims that the cancellation of an alleged 12 March 2007 pre-fmal inspection
    for the convenience of CO Bartholomew constituted a constructive suspension of work
    on the critical path from 9 March 2007 through 17 April 2007 (app. br. at 186-89,
    388-89). The record, however, demonstrates: (1) that SME, SBN's electrical
    subcontractor, advised SBN that it did not believe it could be ready for a mid-March 2007
    pre-final inspection and (2) we find no evidence that Jensen/Fey, as head of the design
    team, had provided the required formal notification that it had inspected the entire project
    and determined it to be ready for a pre-final inspection, a contractually-required
    prerequisite to SBN's formally requesting a pre-final inspection. On the basis of the
    foregoing, we find SBN solely responsible for the claimed delay and deny entitlement to
    delay damages claimed with respect to the pre-final inspection.
    X. Failure to Process Pay Applications and Unpaid Contract Balance
    SBN argues that CFSC's failure to timely process its December 2005 pay
    application (findings 199, 203) was a breach of contract entitling it to damages
    incurred as a result of the nonpayment (app. br. at 341-43; app. reply at 41-42). SBN
    alleges that the failure of CFSC to timely process its December 2005 payment
    application "caused cash flow problems for [SBN] and its subcontractors (app. br. at
    343). However, we have found no evidence in the record of when the December 2005
    pay application was actually paid. SBN's arguments on this subject do not mention
    when actual payment occurred and we find no contemporaneous documentation to
    indicate that payment of the December 2005 pay application was made more than a
    reasonable period of time after its submission. Contrary to SBN' s arguments
    regarding alleged impacts of untimely payment of the December 2005 pay application,
    SBN's LaSharr, its Project Manager from June 2005 through project completion,
    testified that he was not aware of any delays to project performance as a result of
    delays in the processing of SBN's pay applications (finding 199). The Fund argues
    that payment of SBN's December 2005 pay application was merely delayed and that a
    delay in payment does not constitute a breach of contract (gov't br. at 263-264). See
    Highland Al Hujaz Co., 
    ASBCA No. 58243
    , 16-1BCA~36,336. Given the absence
    of evidence of when actual payment occurred, we have no basis upon which to
    determine that any delay in payment was unreasonable. We therefore deny SBN' s
    claim for breach damages on the basis of a delay in payment of its December 2005 pay
    application for lack of proof.
    SBN further claims that CFSC breached the contract by not paying SBN the
    unpaid contract balance of $110,650.00 comprised of unpaid portions of Pay
    Applications 19, 26, 27 and 29 (findings 259, 269; app. br. at 286-87, 411). SBN further
    argues that there should be no right of setoff for "any potential liquidated damages to
    291
    which the Fund may assert entitlement" because there has been no SBN breach (app. br.
    at 287, 411). We find no evidence in the record that the Fund has assessed any liquidated
    damages. The Fund argues that this was not part of SBN' s claim submitted to the CO
    and is therefore not properly before the Board (gov't br. at 264). The Fund is incorrect,
    as this was very clearly set out in SBN's 2010 claim (finding 269). In the alternative, the
    Fund argues that the amount claimed was properly withheld from payments as retainage
    (finding 24) and that the Fund attempted to resolve the matter with SBN in August 2008,
    without success (gov't br. at 264). We find no basis for the Fund's nonpayment of
    retainage as promised by CO Bartholomew:
    We advised the remaining retainage would be released
    with receipt of as-builts and a close out invoice with a
    Release of Claims.
    (Findings 256) We therefore find that SBN is entitled to be paid the amount of the
    contract balance which was withheld as retainage. The amount to be paid is a matter
    of quantum which is not presently before us.
    XI. Failure to Issue a Contracting Officer's Final Decision
    On 26 January 2005 SBN's Roberts submitted three REAs to CFSC
    (findings 119, 124 ). From time to time thereafter the parties referred to the REAs but
    both parties apparently deemed it more important to first address jobsite issues current
    at the time (see, e.g., findings 135, 180-81, 199).
    On 2 April 2008, approximately six months after the Lodge was opened for use
    (finding 251), SBN submitted an REA that included and updated all issues for which
    SBN sought equitable adjustment (finding 256; app. br. at 329). CO Bartholomew
    responded to the REA on 23 June 2008, specifically declining to issue a COFD, and
    inviting further negotiation if it was desired by SBN (finding 257). SBN accepted the
    invitation to continue negotiations (findings 258). Thereafter, the parties engaged in
    continued discussions until CO Bartholomew retired at the end of December 2008
    (findings 259-61; app. br. at 329). 64
    In February 2009 CO Wallace was assigned as the contracting officer responsible
    for matters relating to the contract now at issue. At the time of his assignment, CFSC
    was in the middle of a BRAC relocation and Army Lodging was completing its relocation
    64
    SBN argues that the failure of the Fund to call CO Bartholomew as a witness at the
    hearing put SBN at a disadvantage (app. reply at 4), however, SBN knew
    CO Bartholomew was not on the Fund's witness list and yet SBN failed to
    request a subpoena to compel his testimony when it requested subpoenas for
    four other Fund witnesses.
    292
    to San Antonio, Texas. As a result of these relocations, CO Wallace had difficulty
    locating documents, including the official contract file, related to the Lodge project.
    CO Wallace advised SBN and its counsel of the difficulties in locating documents, as
    well as his intention to procure expert assistance in analysis of SBN' s claimed delays.
    SBN's counsel sought updates from CO Wallace throughout 2009 and into 2010.
    (Findings 262, 264-66)
    On 7 June 2010 SBN formally withdrew its 2 April 2008 REA and submitted to
    CFSC a disk containing a nearly 6,800-page certified claim which is the subject of the
    appeal now before us. SBN described its certified claim as including a narrative,
    schedule analysis and supporting documents and "is substantially the same as the
    April 2, 2008, REA although the schedule analysis has been updated to include
    description of a number of delays and disruptions not included in the original REA."
    (Findings 267, 269, 270) Before CO Wallace could review SBN's claim, it had to be
    converted from the submitted disk to a hard copy consisting of fifteen (15) 3-inch
    binders. A hard copy is in the record; the table of contents does not include page
    numbers and the various sections of the voluminous claim are not divided by tabs or
    otherwise identified within the voluminous document. CO Wallace never formally
    acknowledged receipt of SBN's claim. (Finding 268) CO Wallace failed to respond
    to SBN' s claim within 60 days of receipt, never provided SBN with a date by which a
    COFD would be issued and neither CO Wallace nor any other contracting officer for
    CFSC has ever issued a COFD (finding 271). SBN appealed from a "deemed denial"
    on 18 August 2010 (finding 272).
    A. Breach of the Implied Duty of Good Faith and Fair Dealing
    A CFSC CO has a duty to make a reasonable attempt to negotiate disputes that
    arise between a contractor and the Fund. In the absence of a successful settlement, the CO
    is then required to issue a COFD. AR 215-4, § 6-11. (Finding 25) There is no dispute
    that, after CO Bartholomew's retirement at the end of December 2008, no CFSC CO
    continued negotiations with SBN on the subject of its 2 April 2008 REA, no CFSC CO
    attempted any negotiations with SBN on the subject of its 7 June 2010 certified claim, and
    no CFSC CO has ever issued a COFD on the subject of the 2010 claim.
    SBN argues that CFSC's failure to negotiate and failure to issue a COFD are a
    breach of the Fund's implied duty of good faith and fair dealing (app. hr. at 329-35;
    app. reply at 35-37). We would agree that SBN has shown that the Fund had a duty to
    issue a COFD and that it failed to perform that duty. However, SBN has not asserted a
    claim for any identified amount of damages resulting from the failure to issue a
    COFD. Proof of the element of damages, while not necessary to a mathematical
    certainty, is necessary to a finding of entitlement on the basis of the alleged breach of
    the implied duty. BAE Systems San Francisco Ship Repair, 16-1 BCA ~ 36,404 at
    177,503; Military Aircraft Parts, 16-1BCA~36,388 at 177,410. Where, as here,
    293
    damages have not even been alleged, much less proven, SBN has failed to establish a
    necessary element of its alleged breach and, on that basis, we deny entitlement.
    B. Breach of Contract
    On the basis of the same facts underlying its assertion of breach of the implied
    duty of good faith and fair dealing, SBN argues that the Fund has also materially
    breached the contract by failing to negotiate its various REAs and certified claim and
    also failing to issue a COFD (app. br. at 344-347; app. reply at 42). SBN further
    argues that:
    As to the element of damages, the Fund's complete
    inaction on [SBN]'s 2005 REAs, 2008 REA, and Certified
    Claim damaged [SBN] due to the lack of payment for ( 1)
    unpaid contract balance ... , (2) change orders ... , (3)
    additional costs associated with general conditions,
    unabsorbed home office overhead, and labor and material
    escalation ... , and (4) amounts payable to subcontractors.
    (App. br. at 34 7)
    The four alleged damage components listed by SBN are addressed elsewhere in
    this decision as follows: (1) is addressed in Section X; (2) is addressed in Section VIII;
    (3) is understood to be a quantum issue associated with various delays claimed by SBN
    and addressed throughout this decision; and (4) is addressed in Section XII. SBN also
    seeks interest, attorney's fees, and costs in unspecified amounts that it argues are to be
    resolved during the quantum phase of this appeal (app. br. at 347-49). We have found
    SBN entitled to compensation for certain changed work, delays and unpaid contract
    balance in other sections of this decision. SBN is not entitled to compensation for those
    items again here. To the extent SBN claims additional compensation on the basis of the
    failure of CFSC to issue a COFD, it has failed to allege additional amounts of damage
    specifically caused by the absence of a COFD. As we held above, proof of damages is a
    necessary element of breach of contract and where such damages have not been alleged,
    much less proven, SBN has failed to establish a necessary element of its alleged breach.
    On that basis, we deny entitlement.
    XII. Subcontractor Claims to SBN
    SBN's claimed amount of $6,768,830.26 includes $3,963,690.37 for claims
    against SBN by its subcontractors, plus $701,355.20 added by SBN for "Overhead/Fee
    Insurance" for a total claimed by SBN for subcontractor claims against it of
    $4,665,045.57 (findings 269-70). Throughout its briefs SBN refers to the
    subcontractor claims submitted to it as "pass through claims" (see, e.g., finding 225).
    294
    We are not bound by SBN' s choice of words. The only party with privity of contract
    with the Fund is SBN and SBN has confirmed that it is the only party before us in this
    appeal (tr. 1/5-6, 7, 3/5; Bd. corr. 6 September 2012). The subcontractor claims
    against SBN were not sponsored nor prosecuted before us as separate claims, but were
    included by SBN within its own claim, with SBN's mark-ups added, as evidence of
    damages allegedly suffered by SBN (app. br. at 286, 294-305; see also findings 225,
    270). We have addressed SBN's claimed theories of recovery between it and the
    Fund. In accordance with SBN's agreements with its subcontractors (see finding 225),
    to the extent that we have found SBN entitled to compensation for any portion of its
    claim against the Fund, it is up to SBN to resolve any associated claims between itself
    and its subcontractors.
    CONCLUSION
    All arguments made by the parties which are not specifically addressed in this
    decision have been carefully considered and found not to be persuasive. The
    following is a summary of claim items for which we have found SBN to be entitled to
    compensation:
    Service Gate and Intercom
    Revisions to administration rooms
    rubber stair treads and risers
    RP.1   '.~tP       electrical boxes
    laundry floor drain
    change and soap vending machines
    direct changes
    Unpaid contract balance
    Delay damages as follows:
    DOIM ductwork                             15 calendar days
    Primary electrical interconnect            7 calendar days
    Natural gas line                           7 calendar days
    Mechanical LNTP                           39 calendar days
    Front desk changed work                   15 calendar days
    TOTAL DELAY            83 calendar days
    295
    We sustain SBN' s appeal to the extent of the above listed claim items. SBN' s appeal
    in all other respects is denied. We remand the appeal to the parties for negotiation of
    quantum in accordance with the above.
    Dated: 24 April 2017
    ~x~
    DIANA S.DICKINSON
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                         I concur
    ~#--
    Administrative Judge
    RICHARD SHACKLEFORD
    Administrative Judge
    Acting Chairman                                  Vice Chairman
    Armed Services Board                             Armed Services Board
    of Contract Appeals                              of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 57329
    , Appeal of
    Swinerton Builders Northwest, rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    296
    

Document Info

Docket Number: ASBCA No. 57329

Judges: Dickinson

Filed Date: 4/24/2017

Precedential Status: Precedential

Modified Date: 5/8/2017