Lulus Ostrich Ranch ( 2019 )


Menu:
  •                 ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeals of --                          )
    )
    Lulus Ostrich Ranch                    )                ASBCA Nos. 59252, 59450, 59598
    )                           59814,59815
    )
    Under Contract Nos. 48695391, 48695490 )
    48695290,48695390)
    APPEARANCE FOR THE APPELLANT:                           Mr. William R. Hayward
    Owner
    APPEARANCES FOR THE GOVERNMENT:                         Daniel K. Poling, Esq.
    DLA Chief Trial Attorney
    Robin Walters, Esq.
    Michael P. Thiefels, Esq.
    Trial Attorneys
    DLA Disposition Services
    Battle Creek, MI
    OPINION BY ADMINISTRATIVE WDGE MCILMAIL
    FINDINGS OF FACT
    In January 2014, appellant, after submitting a sealed bid in response to an
    Invitation For Bid (IFB), contracted to buy and remove four different types of metallic
    and non-metallic scrap from government locations in Afghanistan (R4, tabs 1-2, 8).
    The government awarded the contract only after appellant protested the government's
    earlier, initial decision not to award a contract to appellant out of concern that appellant
    could not perform at its bid prices (R4, tabs 5, 7). The contract states "Refer to IFB for
    complete item description" (R4, tab 8 at block 10), and for each type of scrap, the IFB
    includes a "SALES CONTRACT/BIDDING" provision that states:
    This contract is a sales contract. The bidder will be
    purchasing scrap property from the United States
    Government. At no time will there be. a payment by the
    USG to the bidder for services within this contract. The
    property removed by the bidder will be scrap property and
    in poor condition. The bidder will be required to remove
    all property in this item description regardless of condition.
    There will be absolutely no changes, modifications,
    adjustments, or negotiations concerning bid price after
    mvard
    (R4, tab 1 at 6-9 (emphasis added))
    After the award of the contract appellant told the government that it had made a
    bid mistake, then went ahead and removed scrap, despite the contracting officer warning
    that "[t]he bid price will not be adjusted in any way to reflect other bidders [sic] prices'';
    appellant hasn't paid the government anything for any of that scrap (see R4, tabs 10-12;
    tr. 1/219, 2/139-42; app. br. at 15). In August 2014, the contracting officer terminated
    the contract for default, for non-payment (according to the government) of $1,303,218
    (R4, tab 21 ).
    DECISION
    ASBCA No. 59252: Price Reformation
    Appellant requests reformation of its contract prices, saying that after it was awarded
    the contract it discovered that it had made an arithmetical mistake in its bid that made the
    prices it offered to pay for the government's scrap too high (see app. br. at 10). The
    government opposes, relying upon the IFB provisions that state there will be "absolutely no
    changes, modification, adjustments, or negotiations concerning bid price after award" (gov't
    br. at 2,113, 16) (emphasis added). Appellant counters (app. reply br. at 1) with Federal
    Acquisition Regulation (FAR) 14.407-4, "Mistakes after award," which, under certain
    circumstances, authorizes the government to rescind or reform a contract if "a contractor's
    discovery and request for correction of a mistake in bid is not made until after the award."
    Appellant points to no authority in which FAR 14.407-4 trumped an "absolutely no
    changes" provision in an IFB and required reformation of a contract price. Based upon the
    "absolutely no changes" provisions, appellant's post-award request for reformation of its
    contract prices is rejected. The appeal is denied.
    ASBCA No. 59./.50: Request to Stay Payments
    Appellant requests that it be allowed not to have to pay the government for the
    scrap it removed until after ASBCA No. 59252 is adjudicated (July 25, 2014, letter).
    With the denial of ASBCA No. 59252, that request is moot, and the appeal is denied.
    ASBCA No. 59598: Contract Termination
    Appellant challenges the termination of its contract for default (app. br. at 13).
    The government says the termination is justified because appellant never paid anything
    for the scrap it removed from government locations (gov't br. at 21 ). Appellant is
    2
    silent on whether its non-payment is a default (see app. br. at 13). In not paying for
    scrap it removed, appellant defaulted, justifying the termination.
    Now it's up to appellant to demonstrate that the default is excused. See Joseph
    Sottolano, ASBCA Nos. 59081, 60043, 16-1BCAi136,315 at 177,065-67. Appellant
    provides no good reason for failing to pay anything for the scrap it removed. Even
    given the parties' dispute over .price, that dispute did not prevent appellant from paying
    at least the amount it believed it owed under what it believes the contract prices should
    be. The appeal is denied.
    ASBCA Nos. 59814 & 59815: Bad Faith Contract Administration
    Appellant seeks $1,252,543 for allegedly fraudulent contract administration; in
    other words, bad faith (app. br. at 10-12; Feb. 23, 2015 compls.; app. reply br. at 8-9).
    See Dan's Janitorial Service, Inc., ASBCA No. 27837, 85-1 BCA i-117,924 at 89,749.
    However, appellant points to no clear and convincing evidence that the government
    administered the contract with the specific intent to injure appellant. See Puget Sound
    Environmental Corp., ASBCA No. 58828, 16-1 BCA i136,435 at 177,597 (citing Road
    and Highway Builders, LLC v. United States, 
    702 F.3d 1365
    , 1368 (Fed. Cir. 2012);
    referencing Am-Pro Protective Agency v. United States, 
    281 F.3d 1234
    , 1240 (Fed. Cir.
    2002); and reciting test for proving bad faith). The appeals are denied.
    CONCLUSION
    The appeals are denied. Accordingly, appellant's recent request that its
    "debt...be moved back to DFAS - Defense Finance and Accounting until [the Board]
    has made a decision" is denied as moot.
    Dated: February 6, 2019
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    (Signatures continued)
    3
    I concur in result (see separate opinion)       I concur in result (see separate opinion)
    J. REID PROUTY                                  RICHARD SHACKLEFORD
    Administrative Judge                            Administrative Judge
    Vice Chairman                                   Acting Chairman
    Armed Services Board                            Armed Services Board
    of Contract Appeals                             of Contract Appeals
    4
    OPINION BY ruDGE PROUTY AND ruDGE SHACKLEFORD
    CONCURRING IN RESULT
    We concur in the result in these appeals, because we agree with the ultimate
    outcome but not in the brief analysis which leads to that outcome with respect to the
    issues of contract reformation and bad faith contract administration. Thus, the legal
    analysis that follows constitutes the precedential decision of the Board on those subjects.
    With respect to Judge Mcllmail' s denial of appellant's request for contract
    reformation, his opinion provides that appellant is not entitled to reformation because:
    Appellant points to no authority in which the FAR 14.407-4
    trumped an "absolutely no changes" provision in an IFB
    and required reformation of a contract price. Based upon
    the "absolutely no changes" provisions, appellant's
    post-award request for reformation of its contract prices is
    rejected.
    Yet, he does precisely what he accuses appellant of doing - he points to no
    authority in which an "absolutely no changes" provision trumps FAR 14.407. In our
    view, it does not and cannot.
    The sale of federal personal property is governed by Part 102-38 of the Federal
    Management Regulation (FMR). FMR § 102-38.260 instructs that the administrative
    procedures for handling mistakes in bids are contained in FAR 14.407. That section of
    the FAR sets forth the procedures for processing mistakes in bids both discovered
    before and after award, and since Lulus alleges it discovered a mistake after award
    FAR 14.407-4 applies. That section of the FAR states in part:
    If a contractor's discovery and request for
    correction of a mistake in bid is not made until after the
    award, it shall be processed under the procedures of
    Subpart 33.2 [Disputes and Appeals] and the following:
    (a) When a mistake in a contractor's bid is not
    discovered until after award, the mistake may be corrected
    by contract modification if correcting the mistake would be
    favorable to the Government without changing the
    essential requirements of the specifications.
    (b) In addition to ... paragraph (a) above ... agencies
    are authorized to make a determination --
    5
    ( 1) To rescind a contract;
    (2) To reform a contract (i) to delete the items
    involved in the mistake; or (ii) to increase the price if the
    contract price, as corrected, does not exceed that of the
    next lowest acceptable bid under the original invitation for
    bids; or
    (3) That no change shall be made in the contract as
    awarded, if the evidence does not warrant a determination
    under subparagraphs ( 1) or (2) above.
    In addition to the regulatory requirement, the right to assert a mistake in bid is
    based upon pure contract law. In Wender Presses, Inc. v. United States, 
    343 F.2d 961
    (Ct. Cl. 1965), a mistake in bid after award case involving the sale of surplus government
    property, the plaintiff sought rescission of the portion of the contract upon which a
    mistake in bid was alleged and recovery of its bid deposit. There the Court stated:
    It is plain that plaintiff may recover only if
    defendant's responsible officials knew or should have
    known of the mistake at the time the bid was accepted.
    Since plaintiff did not directly apprise defendant of
    the mistake prior to the acceptance of plaintiffs bid ... so that
    there is no showing of any actual knowledge, the only
    question is whether defendant's officials should have
    known of the mistake. Included in this problem is the
    question of whether, even though they could not have
    known with certainty from the bid data that a mistake had
    been made, there nevertheless was enough to have
    reasonably cast upon defendant's officials the duty to make
    inquiry, which inquiry would have led to the requisite
    knowledge. For although an award normally results in a
    binding contract fixing the parties' rights and obligations so
    that "Ordinarily no relief will be granted to a party to an
    executory contract in the case of a unilateral mistake,"
    Saligman v. United States, 
    56 F. Supp. 505
    , 507 (E.D. Pa.,
    1944 ), nevertheless an acceptance of a bid containing a
    palpable, inadvertent, error cannot result in an enforceable
    contract. An "offeree will not be permitted to snap up an
    offer that is too good to be true; no agreement based on such
    6
    an offer can then be enforced by the acceptor." 1 Williston,
    Contracts (3d ed. 1957) § 94. [Citations 
    omitted] 343 F.2d at 962-63
    .
    Perforce, a so-called "absolutely no changes" provision in a contract cannot
    permit a contracting officer to accept a bid, knowing it was in error, since in that
    circumstance no enforceable contract could come into existence and such an agreement
    would be unenforceable. Thus, the proper way to initially analyze this case is to
    determine if the contracting officer knew or should have known a mistake was made at
    the time of the award. As the Wender Court pointed out, the test as to whether the
    contracting officer knew or should have known of the mistake is one of reasonableness,
    "i.e., whether under the facts and circumstances of 'the particular case there were any
    factors which reasonably should have raised the presumption of error in the mind of the
    contracting officer."' Wender, 343 F .2d at 963.
    We have reviewed the parties' briefing on this issue, including facts and analyses
    and find that based upon this record, appellant has not demonstrated that the contracting
    officer either knew or should have known that a mistake was made in its bid. More
    particularly, we are persuaded by the arguments made by the government in its brief
    (gov't br. 6-7) as follows:
    The [CO] did not know the Appellant had made a
    mistake in its bid price, nor did he have reason to know.
    The bid sheet submitted by the Appellant contained no
    obvious errors, no errant marks, no improper payment or
    weight classification. Instead it demonstrated four line
    item prices clearly marked in pounds with the prices
    expressed in dollars as required by the IFB. There was no
    evidence on the face of the bid that suggested a clerical or
    mathematical error. In determining whether the
    contracting officer should have known of the mistake, a
    "reasonable person standard is used." The Kato Corp.,
    ASBCA No. 47601, 1997 ASBCA LEXIS 127, 97-2, BCA
    ,r 29,130 at 144,932.
    In this case [Lulu's] price was not so far off from
    other bidders as to suggest anything other than different
    judgments about the cost of doing business in Afghanistan
    or the revenues to be derived from scrap sales in
    Afghanistan, especially since the Appellant's plan
    appeared to rely on exports. Appellant's bid was lower
    than those of several other bidders. [Lulu's] bid was only
    7
    slightly higher than the next highest bidder and there was a
    group of 3 bidders with prices within 20% of the
    Appellant's.
    For these reasons, we conclude that under the particular circumstances of this
    case, there were no factors which reasonably should have raised the presumption of
    error in the mind of the contracting officer. Thus we concur in the result reached by
    Judge Mcllmail regarding Lulu's contract reformation claim, though not his analysis.
    We similarly diverge from Judge Mclmail's analysis regarding the set of issues
    that he characterizes as "Bad Faith Contract Administration" or ·'fraudulent contract
    administration," though we come to the same ultimate conclusion. These issues
    include allegations in Lulu's brief of "alleged contract interference, improper billing,
    improper contract termination, issuing more contracts than there was available scrap
    metal, and awarding contracts with the intention of 'giv[ing] only minimum amount of
    scrap material' [and allegations that] the government lied to appellant's subcontractor
    and [that on occasion, the government] delivered only dirt.'' Although we agree with
    Judge Mcllmail's general determination that these bases for Lulus' appeal should be
    denied, we also believe that, for the most part, he applied the incorrect standard to
    obtain this result.
    In large part, these allegations fit within the category of breaches of the duty of
    good faith and fair dealing. This doctrine is based upon the notion that every contract
    "imposes upon each party a duty of good faith and fair dealing in its performance and
    enforcement." Metcalf Constr. Co. v. United States, 
    742 F.3d 984
    , 990 (Fed. Cir. 2014)
    (quoting RESTATEMENT (SECOND) OF CONTRACTS§ 205 (1981)); see also Kelly-Ryan,
    Inc., ASBCA No. 57168, 18-1 BCA ~ 36,944 at 180,030; Relyant, LLC, ASBCA
    No. 59809, 18-1 BCA ~ 37,085 at 180,539. Pursuant to this implicit duty, each party's
    obligations "include the duty not to interfere with the other party's performance and not
    to act so as to destroy the reasonable expectations of the other party regarding the fruits
    of the contract." 
    Metcalf, 742 F.3d at 991
    (quoting Centex Corp. v. United States, 
    395 F.3d 1283
    , 1304 (Fed. Cir. 2005)). The government need not, however, act in bad faith
    or with intent to injure the contractor to be found liable for a breach of the duty. To be
    sure, the Federal Circuit's opinion in Precision Pine & Timber, Inc. v. United States,
    
    596 F.3d 817
    , 831 (Fed. Cir. 2010), seemed to imply such a requirement, but the
    Federal Circuit's subsequent opinion in Metcalf made clear that there was no such
    intent to injure necessary. 
    See 742 F.3d at 992-93
    (rejecting requirement to
    "specifically target" contractor).
    Thus, we part ways with Judge Mcllmail's opinion on the law applied to this issue.
    Judge Mcllmail' s opinion requires that Lulus' point to "clear and convincing evidence
    that the government administered the contract with the specific intent to injure appellant,"
    and cites the appeal of Puget Sound Environmental Corp., ASBCA No. 58828, 16-1 BCA
    8
    ~ 36,435 at 177,597. This would be inconsistent with the binding law of Metcalf and is
    not supported by our ruling in the cited case of Puget Sound. The issue before us in the
    cited portion of Puget Sound was a challenge to the government's failure to exercise
    options, which is generally not reviewable unless the government acts in bad faith. Puget
    Sound, 16-1 BCA ~ 36,435 at 177,596. Similar requirements are applied in challenges to
    the government's decision to terminate contracts for convenience. 
    Id. If there
    were an
    allegation here that the government wrong fully terminated Lulus' contracts for
    convenience, the Puget Sound formulation might be proper, but the terminations here
    were for default, and the portion of Judge Mcllmail's opinion that we join already
    dispatches this argument. Thus, the remaining issues before us here are of contract
    administration and are not subject to Puget Sound's "specific intent to injure" standard,
    but are instead governed by Metcalf.
    Applying the proper standard, we still reach the same result, primarily for lack
    of record evidence supporting Lulus' allegations. Judge Mcllmail directed the parties
    to reference all factual support for their arguments in their briefs (see tr. 2/168-69);
    Lulus did not do so. Nevertheless, we performed a review of the Rule 4 documents
    and the transcript of the hearing, and, on these subject areas, the only evidence
    presented was about delays or problems in allowing Lulus' subcontractor onto the
    military bases in Afghanistan (e.g., tr. 1/65-66, 211-12), and that the government
    allegedly provided "dirt" as opposed to scrap metal, as expected (tr. 1/215, 229). This
    evidence was all based on hearsay, and allegations of the government's bad motives
    were admittedly speculation (tr. 2/39).
    The government, by contrast, presented evidence that access to bases in
    Afghanistan was properly limited for security reasons (tr. 2/88-90). The government
    also presented evidence that the scrap provided to all contractors, in accordance with
    the contract, was not limited to metal, but also included many other things like canvas,
    glass, wood, PVC pipe, and shredded electronic scrap (tr. 2/78-79). We read this as
    consistent with the "dirt" of which Lulus complained. The contracting officer also
    explained that there were multiple scrap metal contract awards made because
    oftentimes, during the course of contract performance, contractors drop out and there
    is a need to "surge" for the work (tr. 2/83).
    Thus, Lulus presented weak to nonexistent evidence to support its allegations of
    a violation of the duty of good faith and fair dealing. The government presented
    evidence that its actions were reasonable undertakings in the war zone in which the
    contract was performed and where Lulus knew it would be operating. Lulus has not
    met its burden of proof that government action "interfere[d] with [its] performance" or
    acted "so as to destroy [Lulus'] reasonable expectations ... regarding thefmits of the
    9
    contract." 
    Metcalf, 742 F.3d at 991
    . Accordingly, we agree with Judge Mcllmail's
    decision to deny this portion of the appeals.
    Dated: February 6, 2019
    RICHARD SHACKLEFORD
    Administrative Judge                             Administrative Judge
    Acting Chairman                                  Vice Chairman
    Armed Services Board                             Armed Services Board
    of Contract Appeals                              of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the Armed
    Services Board of Contract Appeals in ASBCA Nos. 59252, 59450, 59598, 59814, 59815,
    Appeals ofLulus Ostrich Ranch, rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    10
    

Document Info

Docket Number: ASBCA No. 59252, 59450, 59598, 59814, 59815

Judges: McIlmail

Filed Date: 2/6/2019

Precedential Status: Precedential

Modified Date: 2/25/2019