Alderman Building Co., Inc. ( 2022 )


Menu:
  •                  ARMED SERVICES BOARD OF CONTRACT APPEALS
    Application Under the Equal Access         )
    to Justice Act of --                      )
    )
    Alderman Building Co., Inc.                )   
    ASBCA No. 58082
    -EAJA
    )
    Under Contract No. N40085-09-D-5321        )
    APPEARANCE FOR THE APPLICANT:                  Marilyn H. David, Esq.
    D’Iberville, MS
    APPEARANCES FOR THE GOVERNMENT:                Craig D. Jensen, Esq.
    Navy Chief Trial Attorney
    Russell Shultis, Esq.
    Genifer M. Tarkowski, Esq.
    Trial Attorneys
    OPINION BY ADMINISTRATIVE JUDGE SHACKLEFORD
    ON APPLICANT’S EQUAL ACCESS TO JUSTICE ACT APPLICATION 1
    Applicant, Alderman Building Co., Inc. (Alderman), submitted an Application for
    Award of Attorneys’ Fees and Other Fees & Expenses under the Equal Access to Justice
    Act (EAJA), 
    5 U.S.C. § 504
    , as amended. The underlying appeal arose from a sponsored
    subcontractor claim seeking unabsorbed home office overhead during government-caused
    delays. See Alderman Bldg. Co., 
    ASBCA No. 58082
    , 
    20-1 BCA ¶ 37,613
    . We assume
    familiarity with that decision. We find that Alderman is an eligible, prevailing party, and
    that the government’s position was not substantially justified. Accordingly, we grant
    Alderman’s application, but reduce the requested recovery amount.
    BACKGROUND
    The underlying appeal involved a March 27, 2009, task order for supplies or
    services under Contract No. N40085-09-D-5321 awarded to Alderman for renovations of
    the interior, repairs to building systems, and incidental work, on building M403 at Marine
    Corps Base Camp Lejeune, North Carolina. 
    Id. at 182,566
    . Alderman entered into a
    subcontract with Big John’s Electric Co. Inc. (Big John’s), for labor, equipment,
    materials, and supplies for specified portions of the interior repairs to the building. 
    Id.
    While the solicitation provided that the contract start date would be 10 days after
    award, we found that contract performance was characterized by repeated
    1
    Judge Alexander Younger, who authored the underlying decision on entitlement and
    quantum, has retired.
    government-caused delays that aggregated to 263 days and pushed the start work date
    into February 2010. 
    Id.
    By letter dated August 18, 2011, Alderman submitted a pass-through claim for
    $20,518, on behalf of Big John’s, for Eichleay damages. 
    Id. at 182,568
    . While the
    appeal was pending, Alderman’s proffered expert calculated that the correct amount of
    the claim should be $56,548. 
    Id.
     The contracting officer (CO) denied the claim in its
    entirety. 
    Id.
    Our May 21, 2020, decision on the merits, found that Alderman was entitled to
    Eichleay damages. 
    Id. at 182,574-76
    . While we found that the Navy did not explicitly
    require Alderman or Big John’s to place their workforces on standby, Alderman
    demonstrated by indirect evidence that it had to place its forces on standby. 
    Id. at 182,574-75
    . We also found that while Big John’s made efforts to obtain replacement
    work, it was unable to obtain sufficient replacement work to compensate for the
    disruptive effect of the multiple delays. 
    Id. 182,575-76
    . Accordingly, we found that
    Alderman was entitled to recover $34,795 for Eichleay damages. 
    Id. at 182,576
    .
    As a separate category of relief, we denied Alderman’s contention, independent of
    the Eichleay formula, that it was entitled to $21,753 in direct costs of standby. 
    Id.
    DISCUSSION
    To recover under the EAJA, an applicant must timely file its application, establish
    it is an eligible party as defined by the EAJA, and prove that it was a prevailing party in
    the underlying action. Asia Commerce Network, 
    ASBCA No. 58623
    , 
    19-1 BCA ¶ 37,352
    at 181,621 (citing Rex Sys., Inc., 
    ASBCA No. 52247
    , 
    02-1 BCA ¶ 31,760
     at 156,854). An
    application may be denied if the government’s position was substantially justified or when
    special circumstances make an award unjust. Asia Commerce Network, 
    19-1 BCA ¶ 37,352
     at 181,621; see also 
    5 U.S.C. § 504
    (a)(1). As a partial waiver of sovereign
    immunity, the EAJA is to be strictly construed in favor of the United States. Ardestani v.
    I.N.S., 
    502 U.S. 129
    ,137 (1991).
    I. Timely Application
    An application under the EAJA must be filed within 30 days after the Board’s
    disposition of the appeal has become final. 
    5 U.S.C. § 504
    (a)(2). The Board issued its
    decision on May 21, 2020. Read receipt email messages confirm that both Alderman and
    the Navy received the Board’s decision on May 21, 2020. The Board received Alderman’s
    EAJA application on June 22, 2020. Because this was within the 120 days permitted for an
    appeal of the decision plus the 30 days permitted for filing under the EAJA, we consider
    the application timely. Benjamin S. Notkin & Assocs., 
    ASBCA No. 29336
    , 
    87-1 BCA ¶ 19,483
     at 98,455.
    2
    II. Prevailing Party
    The EAJA application must show that the applicant was the prevailing party.
    
    5 U.S.C. § 504
    (a)(2). Alderman was the prevailing party in the underlying appeal. The
    Board sustained the appeal and determined that Alderman was entitled to recover
    $34,795. Alderman, 
    20-1 BCA ¶ 37,613
     at 182,576. The government’s response to the
    EAJA application also concedes that Alderman was the prevailing party (gov’t resp. at 2).
    III. Eligibility
    The EAJA application must also show that the applicant is eligible to receive an
    award. 
    5 U.S.C. § 504
    (a)(2). “A party is generally eligible for consideration of an award
    of costs under the EAJA if it is an entity having a net worth of no more than $7,000,000
    and no more than 500 employees at the time the adversary adjudication was initiated.”
    K&K Indus., Inc., 
    ASBCA No. 61189
    , 
    19-1 BCA ¶ 37,353
     at 181,627; see also 
    5 U.S.C. § 504
    (b)(1)(B)(ii). “Net worth is determined by subtracting an applicant’s total liabilities
    from its total assets.” Kostmayer Constr., LLC, 
    ASBCA No. 55053
    , 
    09-2 BCA ¶ 34,302
    at 169,440 (citing Broaddus v. United States Army Corps of Engineers, 
    380 F.3d 162
    ,
    167 (4th Cir. 2004)).
    Alderman initiated the underlying appeal in April 2012. In order to demonstrate
    its net worth at that time, Alderman submitted copies of its Form 1120-S, U.S. Income
    Tax Return for an S Corporation, from 2011 and 2012 with its EAJA application (app.
    br., exs. 4-5). The Schedule L, Balance Sheets, on these returns show Alderman’s net
    worth is below the statutory threshold on each return (id. at 44, 48). Alderman also
    submitted an affidavit from its President in 2012 attesting that its maximum number of
    employees never exceeded 50 employees (app. br., ex. 3). 2 There is no apparent
    objection from the government regarding Alderman’s exhibits. After review of the
    documents, we are satisfied that Alderman is an eligible party.
    IV. Substantial Justification
    An application may be denied if the government’s position was substantially
    justified or when special circumstances make an award unjust. Asia Commerce Network,
    
    19-1 BCA ¶ 37,352
     at 181,621; 
    5 U.S.C. § 504
    (a)(1). “The government bears the burden
    to show that its position was substantially justified.” K&K Indus., Inc., 
    19-1 BCA ¶ 37,353
    at 181,628 (citing Amaratek, ASBCA Nos. 59149, 59395, 
    15-1 BCA ¶ 35,866
     at 175,348).
    In order to prevail, the government must “demonstrate that ‘a reasonable person could
    think [the government’s position is] correct, that is [that] it has a reasonable basis in law
    and fact.’” Pro-Built Constr. Firm, 
    ASBCA No. 59278
    , 
    18-1 BCA ¶ 36,975
     at 180,116
    2
    Alderman also submitted an affidavit, tax returns, and payroll history summary
    pertaining to its subcontractor demonstrating that Big John’s also qualifies as an
    eligible party (app. br., exs. 6-9).
    3
    (quoting Pierce v. Underwood, 
    487 U.S. 552
    , 566 n.2 (1988)). “Substantial justification
    applies to the entirety of the litigation position and not just the posture on individual
    issues.” K&K Indus., 
    19-1 BCA ¶ 37,353
     at 181,628. “[T]he government position is more
    likely to be substantially justified when greater ‘legal uncertainty’ is presented.” SST
    (Supply & Serv. Team) GmbH, ASBCA No 59630, 
    18-1 BCA ¶ 36,932
     at 179,932 (citing
    Rex Sys., Inc., 
    ASBCA No. 52247
    , 
    02-1 BCA ¶ 31,760
     at 156,855).
    The Navy maintains it was substantially justified in litigating the claim for
    Eichleay damages. It raises three bases for why it was substantially justified. First, the
    Navy argues that it reasonably believed Alderman and Big John’s could not prove their
    workforces were on standby (gov’t resp. at 3-4). Second, the Navy argues that it had no
    other choice than to litigate the claim because Alderman and Big John’s failed to provide
    adequate documentation supporting the alleged costs (gov’t resp. at 4-5). Lastly, the
    Navy notes that Alderman rejected a reasonable settlement offer (gov’t resp. at 5-6).
    1. Standby
    The Navy notes that it “never explicitly directed Alderman or Big John’s to be on
    standby, prior to contract performance” (gov’t resp. at 3), which we agreed with in our
    2020 decision. Alderman, 
    20-1 BCA ¶ 37,613
     at 182,568 (“[T]he Navy did not explicitly
    require Alderman or Big John’s to place their workforces on standby.”). “In order to
    recover unabsorbed overhead costs using the Eichleay formula, Eichleay Corp., 
    ASBCA No. 5183
    , 
    60-2 BCA ¶ 2688
    , aff’d on reconsid., 
    61-1 BCA ¶ 15,117
    , [Alderman] had to
    show that it was required unreasonably to stand-by during the period of the delay without
    staff reduction and that it was impractical to take on additional jobs during this period.”
    Alvarez & Assocs. Constr. Co., 
    ASBCA No. 50185
    , 
    97-2 BCA ¶ 29,320
     at 145,789
    (citing Daly Constr. Inc. v. Garrett, 
    5 F.3d 520
     at 522 (Fed. Cir. 1993)).
    We previously addressed the question of standby in our December 9, 2014
    decision on the parties’ cross-motions for summary judgment. See Alderman Bldg. Co.,
    
    ASBCA No. 58082
    , 
    15-1 BCA ¶ 35,841
     at 175,273-74. In that decision we found that
    the evidence “show[ed] that [Alderman] had employees on standby during the delay
    period, but [left] open the question of whether they were ‘required to be ready to resume
    work’ by the Navy.” 
    Id. at 175
    ,274 (citing P.J. Dick Inc. v. Principi, 
    324 F.3d 1364
    ,
    1371 (Fed. Cir. 2003). Thus, we found that there was a triable issue regarding standby.
    Alderman, 
    15-1 BCA ¶ 35,841
     at 175,274.
    While we agreed with the Navy that it did not explicitly order Alderman or Big John’s
    to place their workforces on standby (Alderman, 
    20-1 BCA ¶ 37,613
     at 182,568), Alderman
    asserted it was entitled to Eichleay damages based on indirect evidence of standby (app.
    reply br. at 5-6). In cases where the CO does not issue an explicit order to be on standby, the
    contractor must prove standby by indirect evidence. P.J. Dick, 
    324 F.3d at 1371
    .
    4
    On the question of indirect evidence, we found “that contract performance was
    characterized by repeated government-caused delays that aggregated to 263 days . . . .”
    Alderman, 
    20-1 BCA ¶ 37,613
     at 182,566. We found it was “the Navy’s practice to
    afford Alderman and Big John’s little advanced notification of the delays in the project’s
    start dates.” 
    Id. at 182,568
    . Ultimately, we concluded it was necessary and reasonable
    for Alderman to keep its workforce on standby due to the “dwindling period of
    performance with no time extension” coupled with the threat of liquidated damages. 
    Id. at 182,575
    .
    The Navy’s response to the EAJA application did not discuss the indirect evidence
    of standby. The fact that the Board agreed with the Navy on the question of whether
    there was an explicit order to be on standby, does not equate to the Navy’s overall
    litigation position being substantially justified. “Substantial justification applies to the
    entirety of the litigation position and not just the posture on individual issues.” K&K
    Indus., 
    19-1 BCA ¶ 37,353
     at 181,628. This is particularly applicable here, where the
    established law allowed the contractor to prove standby without an explicit order;
    specifically, by indirect evidence.
    2. Documentation Supporting the Alleged Costs
    The Navy argues that it was substantially justified because Alderman and Big John’s
    failed to provide adequate documentation supporting the alleged costs incurred (gov’t resp.
    at 4-5). The Navy maintains that this is demonstrated by the multiple supplements that
    Alderman’s proffered expert made to his report (id. at 4). We are not persuaded by the
    Navy’s argument. “The government bears the burden to show that its position was
    substantially justified.” K&K Indus., Inc., 
    19-1 BCA ¶ 37,353
     at 181,628. The fact that
    Alderman’s expert provided multiple supplements to his report does not in itself
    demonstrate that Alderman failed to provide documentation supporting the alleged costs.
    The Navy has failed to meet its burden in demonstrating how the documentation was
    insufficient.
    3. Navy’s Settlement Offer
    Finally, the Navy maintains that Alderman’s alleged rejection of a reasonable
    settlement offer in November 2015 left the Navy with no other choice than to continue
    litigating the appeal (gov’t resp. at 5-6). The Navy notes that its settlement offer was
    close to Alderman’s ultimate recovery amount (id. at 5). The rejection of a settlement
    offer may be “relevant to the reasonableness of the EAJA fees and costs that are to be
    awarded.” C.H. Hyperbarics, Inc., on behalf of William J. Miller, Jr., Trustee, 
    ASBCA No. 49375
     et al., 
    05-2 BCA ¶ 32,989
     at 163,494. We address the relevance of the
    settlement negotiations in greater detail below in the quantum section of this decision.
    The Navy, however, has raised this issue as a factor in its substantial justification
    argument, which we do not find relevant here.
    5
    4. Substantial Justification Conclusion
    Based upon our review of the record, the Navy has not persuaded us that its
    position was substantially justified.
    V. Special Circumstances
    The government has not contended that there are any special circumstances that
    would make an award of fees and costs unjust. 
    5 U.S.C. § 504
    (a)(1). We conclude that
    no special circumstances exist to preclude an EAJA award.
    VI. Quantum
    Alderman initially sought an enhanced attorneys’ fees rate of $200 per hour (app.
    br. at 7). In response, the Navy properly noted that the Board has long held that it does
    not have discretion to award attorneys’ fees in excess of the EAJA prescribed rate of
    $125 per hour (gov’t resp. at 7-8). See also Optimum Servs., Inc., ASBCA Nos. 58755,
    59952, 
    17-1 BCA ¶ 36,816
     at 179,431-32. Alderman’s reply brief revised its requested
    EAJA award amount downward to account for the $125 per hour rate (app. reply br. at 28).
    To the extent that this is still an open issue, we find that Alderman’s attorneys’ fees rate is
    limited to $125 per hour.
    The parties also agree that an EAJA award should not include any amounts for
    time spent on the denied direct costs of standby claim (app. br. at 6; gov’t resp. at 10;
    app. reply br. at 28). See also C.H. Hyperbarics, 
    05-2 BCA ¶ 32,989
     at 163,491 (“Where
    separate claims are involved they should be treated as separate lawsuits, and no fee
    should be awarded for services on unsuccessful claims.”). In the underlying appeal, we
    denied the direct costs of standby claim and deducted the claimed amount from the
    overall recoverable amount. Alderman, 
    20-1 BCA ¶ 37,613
     at 182,576. Accordingly,
    Alderman’s EAJA award will not include any amounts for time spent on the denied direct
    costs of standby claim.
    We now turn to the remaining areas of disagreement between the parties. The
    Navy’s primary argument is that the Board should limit Alderman’s EAJA award amount to
    its attorneys’ fees and costs from the issuance of the contracting officer’s final decision
    (COFD) on January 19, 2012, 3 to the rejection of the Navy’s $34,000 settlement offer in
    November 2015 (gov’t resp. at 5-7). The Navy also notes that the parties’ decision not to
    3
    We agree with the Navy that the date of the COFD is the beginning of the “adversary
    adjudication” for purposes of the EAJA (gov’t resp. at 9). See also Levernier
    Const., Inv. v. United States, 
    947 F.2d 497
    , 500 (Fed. Cir. 1991). Alderman’s
    requested attorneys’ fees and costs include amounts prior to January 19, 2012,
    but these amounts are relatively minor in comparison to its overall EAJA award
    request.
    6
    move forward with a planned alternative dispute resolution (ADR) session in February 2016
    was another lost opportunity to resolve the appeal and should be considered in determining
    a reasonable EAJA award (gov’t resp. at 8-9).
    Conversely, Alderman’s primary argument is that the EAJA award amount should
    not be curtailed by the settlement negotiations or decision to call off the ADR session
    (app. reply br. at 12-27). Alderman asserts that while the Board awarded it $34,795 for
    its Eichleay damages claim, this amounts to roughly $43,597.65 when interest is included
    (id. at 13). Next, Alderman argues that the Navy’s $34,000 settlement offer “was not
    significant, because the $34,000 lump sum had to be apportioned among extended
    overhead, direct costs, interest, fees, and costs” (id. at 14). Alderman contends that:
    [T]he Navy’s offer amounted to at most about $17,000 for
    extended overhead and direct costs. Assuming, arguendo,
    that the $34,000.00 lump sum was to be divided equally
    between the extended overhead and direct costs claims on the
    one hand and interest, fees, and costs on the other, it would
    mean that 50% of the lump-sum, or $17,000.00, was the part
    of the lump sum offered for the extended overhead and direct
    costs claims.
    (id. at 15). Further, Alderman asserts that it never rejected the Navy’s $34,000 settlement
    offer. Rather, Alderman maintains the offer remained on the table as the parties began to
    consider ADR. (Id. at 16) Leading up to the ADR session, Alderman argues that the
    Navy engaged in bad faith negotiation tactics by “re-litigating” issues and lowering its
    offer in the Navy’s mediation statement (id. at 17-18). Alderman notes that the parties
    mutually agreed to call off the ADR session (id. at 19). Finally, Alderman asserts that its
    fees were reasonable and proportional to the amount recovered (id. at 19-27).
    The parties both cite States Roofing Corp., 
    ASBCA No. 55505
    , 
    11-1 BCA ¶ 34,668
    as instructive in determining the reasonableness of an EAJA award amount (gov’t resp.
    at 9; app. reply br. at 12-13). In States Roofing, the contractor “incurred $211,191 in fees
    and costs to obtain $352,976 (largely exclusive of CDA interest) just $2,976 more than the
    $350,000 settlement offered by the [government].” 
    11-1 BCA ¶ 34,668
     at 170,781. The
    Board found this amount to be “grossly disproportionate” and adopted a reasonableness
    approach to determine the final EAJA award amount. 
    Id.
     We believe a similar approach
    is appropriate here.
    The parties agree that on November 4, 2015, the Navy made a $34,000 lump sum
    settlement offer (gov’t resp. at 5; app. reply br. at 16, ex. 17). The Navy maintains that
    Alderman rejected the settlement offer (gov’t resp. at 5), while Alderman asserts that it
    never rejected the offer (app. reply br. at 16). However, it is clear that on November 9,
    2015, the parties notified that Board that they agreed to pursue ADR. The Board scheduled
    the ADR for February 17-18, 2016. It is also clear that in anticipation of the ADR, on
    7
    February 3, 2016, the Navy submitted its mediation statement, which included a lump sum
    settlement offer of $20,421.60 (gov’t resp. at 8-9; app. reply br. at 17-18). Thereafter, on
    February 9, 2016, the Board held a conference call during which the parties requested to
    cancel the ADR session.
    Similar to States Roofing, under the circumstances, we find it useful to look at
    Alderman’s attorneys’ fees and costs incurred before and after cancellation of the ADR
    session. Alderman provided a breakdown of these costs in its rebuttal:
    Before Cancellation of the ADR Session
    Marilyn H. David, attorney’s fees                          $37,968.75
    Russell S. Gill, attorney’s fees                         + $3,125.00
    Legal expenses and costs                                 + $11,282.47
    Deducting fees and costs for Direct Costs Claim          –   $889.50
    Total: = $51,486.72
    (App. reply br. at 26)
    After Cancellation of the ADR Session
    Marilyn H. David, attorney’s fees                          $25,843.75
    Legal expenses and costs                                 + $25,318.09
    Deducting fees and costs for Direct Costs Claim          – $2,135.50
    Total: = $49,026.34
    (Id. at 27)
    Alderman’s revised requested EAJA award combines its attorneys’ fees and costs
    before and after the cancelled ADR session, totaling $100,513.06 ($51,486.72 +
    $49,026.34 = $100,513.06). Alderman requests an additional $9,741.93 for preparation
    of its EAJA application and rebuttal. Alderman’s revised total is $110,254.99 (id. at 34).
    Conversely, the Navy proposes that a reasonable EAJA award would be $42,233.78 4
    (gov’t resp. at 13).
    After cancellation of the ADR session, Alderman incurred an additional
    $49,026.34 in attorneys’ fees and costs to obtain $34,795 (excluding interest) for its
    Eichleay damages claim. This was just $795 more than the government’s $34,000
    settlement offer. It was also only $14,373.40 more than the government’s proposed lump
    sum payment in its mediation statement. Compared with either the Navy’s settlement
    4
    As discussed above, the Navy’s proposed EAJA award limits recovery “from the
    issuance of the COFD on 19 January 2012 to the rejection of the Navy’s
    reasonable settlement offer in November 2015” (gov’t resp. at 13).
    8
    offer or the amount proposed in the mediation statement, we find Alderman’s attorneys’
    fees and costs to be disproportionate to its ultimate recovery amount. Accordingly, we
    find it reasonable to disregard those attorneys’ fee and costs incurred after cancellation of
    the ADR session.
    We have also considered the nature and relative complexity of the Eichleay
    damages claim, the relationship between it and the denied direct costs of standby claim,
    and degree of success Alderman obtained (app. reply br. at 12-13). See also States
    Roofing, 
    11-1 BCA ¶ 34,668
     at 178,781.
    Consistent with the aforementioned discussion, we believe a reasonable EAJA
    award includes only those attorneys’ fees and costs incurred before the cancelled ADR
    session and those associated with preparing the EAJA application. We disregard those
    attorneys’ fees and costs incurred prior to issuance of the COFD and those relating to the
    denied direct costs of standby claim. Alderman listed its attorneys’ fees and costs before
    cancellation of the ADR session as $51,486.72. Alderman already deducted its fees and
    costs related to the denied direct costs of standby claim. (App. reply br. at 26). However,
    this amount does include some attorneys’ fees and costs incurred prior to issuance of the
    COFD. We disregard the 25 hours ($3,125) attributed to Russell S. Gill, PLLC from
    April 27, 2011 to July 14, 2011 (see app. br., ex. 11 at 63-65). We also deduct one hour
    ($125) billed by attorney Marilyn H. David on January 8, 2012 (see app. br., ex. 12
    at 70). Finally, we deduct $302.59 for legal expenses and costs incurred on July 20, 2011
    (see app. br., ex. 11 at 63). After adding in the $9,741.93 for preparation of the EAJA
    application (see app. reply br. at 30-31), we conclude that an award of $57,676.06 is
    reasonable as summarized in the table below:
    EAJA AWARD
    Add Attorneys’ fees and costs before cancellation of ADR                          $51,486.72
    Deduct 25 hours attributed to Russell Gill from April 27 to July 14, 2011     –    $3,125.00
    Deduct one hour billed by Marilyn David on January 8, 2012                    –     $125.00
    Deduct legal expenses and costs incurred on July 20, 2011                     –     $302.59
    Add costs for preparation of the EAJA application                             +    $9,741.93
    Total:    =   $57,676.06
    9
    CONCLUSION
    Alderman is awarded $57,676.06 in recoverable EAJA fees and costs.
    Dated: April 28, 2022
    RICHARD SHACKLEFORD
    Administrative Judge
    Vice Chairman
    Armed Services Board
    of Contract Appeals
    I concur                                         I concur
    J. REID PROUTY                                   JAMES SWEET
    Administrative Judge                             Administrative Judge
    Acting Chairman                                  Armed Services Board
    Armed Services Board                             of Contract Appeals
    of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals on an application for fees and other expenses
    incurred in connection with 
    ASBCA No. 58082
    -EAJA, Appeal of Alderman Building
    Co., Inc., rendered in conformance with 
    5 U.S.C. § 504
    .
    Dated: April 28, 2022
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    10