Vigor Works, LLC ( 2023 )


Menu:
  •                   ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of -                                )
    )
    Vigor Works, LLC                           )    
    ASBCA No. 62607
    )
    Under Contract No. H92222-11-D-0080        )
    APPEARANCES FOR THE APPELLANT:                  Mark G. Jackson, Esq.
    Stowell B. Holcomb, Esq.
    Jackson Holcomb LLP
    Seattle, WA
    APPEARANCES FOR THE GOVERNMENT:                 Caryl A. Potter, III, Esq.
    Deputy Chief Trial Attorney
    Maj Danelle McGinnis, USAF
    Trial Attorney
    OPINION BY ADMINISTRATIVE JUDGE THRASHER
    Vigor Works, LLC (Vigor or appellant) appealed under the Contract Disputes
    Act (CDA), 
    41 U.S.C. §§ 7101-7109
    , from a contracting officer’s final decision
    (COFD) denying appellant’s certified claim in the amount of $5,213,618. Vigor seeks
    excess costs incurred from what it describes as the government constructively changing
    the contract by accelerating the production pace and sequence through the issuance of
    delivery orders. The parties have elected a written disposition under Board Rule 11.
    We deny the appeal.
    FINDINGS OF FACT
    1. On September 28, 2011, the United States Special Operations Command
    (SOCOM or government) awarded Contract No. H92222-11-D-0080 (the contract) to
    Vigor Works, LLC 1 (R4, tab 9). The contract was for the design, development, and
    fabrication of Combatant Craft, Medium Mark 1 (CCM Mk 1) systems (compl. ¶ 7;
    R4, tab 9a at 4).
    2. The contract was an indefinite-delivery, indefinite-quantity (IDIQ) contract
    with firm-fixed-price and cost reimbursable contract line items (CLINs) for a total
    period of performance of ten years, including option periods (R4, tab 9 at 3). Part I of
    the contract contained “THE SCHEDULE” (R4, tab 9 at 2).
    1
    SOCOM awarded the contract to Oregon Iron Works, Inc. (OIW), but OIW later
    became Vigor Works, LLC (R4, tab 36 at 3; app. supp. R4, tab 25 at 3).
    3. The Schedule, Section B, Supplies or Services and Prices, divided the
    CLINs into four successive periods:
    • Base Period (CLINs 0001-0008)
    • If applicable, Test Article Refurbishment (CLINs 0009-0018)
    • If applicable, Low Rate Initial Production (CLINs 0019-0044)
    • If applicable, seven Production/Sustainment Ordering Periods (CLINs 1001-
    7027)
    (R4, tab 9 at 3) Each CLIN was to be “set forth under individual delivery order” and
    performed “in accordance with Sections C 2 and J” of the contract (see R4, tab 9 at 4-
    126).
    4. The Schedule, Section F, Deliveries or Performance, established delivery
    information for each CLIN, including delivery dates for CLINs 0001 to 7027 (R4,
    tab 9 at 1, 133-46).
    5. Part III of the contract contained “LIST OF DOCUMENTS, EXHIBITS
    AND OTHER ATTACHMENTS” (R4, tab 9 at 1). Section J listed the documents,
    exhibits, and other attachments. The first item listed is Exhibit A, Contract Data
    Requirements Listings A, E, L, dated August 11, 2011. (R4, tab 9 at 182; see also R4,
    tab 9k) The contract required the contractor to provide several Contract Data
    Requirement Lists (CDRLs), including A006 Integrated Program Master Schedule
    (IPMS) (R4, tab 9 at 6).
    6. The Data Description for A006 IPMS provides:
    1) The Contractor shall prepare, maintain, and update a
    CCM Mk 1 Integrated Program Master Schedule
    (IPMS) that reflects the Contractor’s program and
    schedule planning. The Contractor shall ensure the
    IPMS reflects the baseline schedule and all changes
    thereto and maintain the IPMS throughout the life of
    the contract.
    2
    There is no “X” under Part I, Section C, Description/Specs/Work Statement. The
    contract included the Statement of Work as Attachment 01 under Section J (see
    R4, tab 9 at 1, 182).
    2
    2) The IPMS shall contain the networked, detailed tasks
    necessary to ensure successful program execution. The
    IPMS is vertically traceable to the Contract Work
    Breakdown Structure (CWBS), and the Statement of
    Work (SOW). The IPMS shall be used to verify
    attainability of contract objectives, to evaluate progress
    toward meeting program objectives, and to integrate the
    program schedule activities with all related
    components.
    3) The IPMS shall also include the accomplishments and
    criteria necessary for the delivery of the CCM Mk 1 TA
    in the first period; deliveries of the LRIP CCM Mk 1
    Systems and FRP CCM Mk 1 Systems in the second
    period; and implementation and execution of the
    performance based logistics process in the second
    period.
    (R4, tab 9k at 9)
    7. Section J included the Statement of Work (SOW) as Attachment 01 (R4,
    tab 9 at 182; see also R4, tab 9a). Section 3.2, Program Schedule, of the SOW stated
    “[Vigor] 3 shall depict and track the CCM Mk1 program schedule in an up-to-date
    Integrated Program Master Schedule (IPMS). [Vigor] shall maintain the IPMS for the
    duration of the contract.” (R4, tab 9a at 5) Additionally, Section 7.3.2 of the SOW
    provided:
    [Vigor] shall prepare, maintain, and update a CCM Mk 1
    IPMS that reflects [Vigor’s] program and schedule
    planning. [Vigor] shall ensure the IPMS reflects the
    baseline schedule and all changes thereto and maintain the
    IPMS throughout the life of the contract. The IPMS shall
    also include the accomplishments and criteria necessary for
    the delivery of the CCM Mk 1 TA in Period One;
    deliveries of the LRIP CCM Mk 1 Systems and FRP CCM
    Mk 1 Systems in Period Two; and implementation and
    execution of the performance based logistics process in
    Period Two. [Vigor] shall ensure the IPMS is up to date
    and available at all Government meetings. [Vigor] shall
    3
    The SOW refers to OIW, which we previously noted later became Vigor (see n.1).
    3
    submit the CCM Mk 1 IPMS as well as all updates for the
    life of the contract in accordance with CDRL A00[6]. 4
    (R4, tab 9a at 32)
    8. Section J also included a version of Vigor’s IPMS as Attachment 06 (R4,
    tab 9 at 182; see also R4, tab 9f).
    9. Notably, the Solicitation provided that those offerors in the competitive
    range would each be awarded a contract for construction and delivery of a CCM Mk1
    Test Article (TA); support for government testing of the TA; and submission of
    revised proposals, if requested by the government (R4, tab 1 at 183). After delivery of
    the TA and completion of the government’s testing and assessment, the government
    would downselect to one contractor (R4, tab 1 at 142). After completing its TA
    evaluation, the government requested a Best and Final Offer (BAFO) from each
    offeror (app. br. at 6; gov’t br. at 24). Vigor submitted its BAFO in late 2013 (compl.
    ¶ 59; R4, tab 179). Vigor’s BAFO included an updated version of the IPMS (BAFO
    IPMS) 5 (R4, tab 179 at 132-34). Vigor’s BAFO stated,
    [Vigor’s] CCM Mk1 proposed IPMS reflects our program
    and schedule planning and the baseline schedule and all
    changes. [Vigor] will maintain the IPMS throughout the
    life of the contract. . . . [Vigor] will ensure the IPMS is up
    to date and available at all meetings. [Vigor] will update
    the IPMS throughout the life of the contract and submit it
    per CDRL A00[6].
    (R4, tab 179 at 30)
    10. In February 2014, the government awarded Vigor the final down select for
    the production contract for CCM Mk1 craft and refurbishment of the TA (R4, tab 21
    at 533). Effective February 20, 2014, the parties bilaterally executed Modification No.
    P00010 (R4, tab 21). Modification No. P00010 exercised the options for Test Article
    Refurbishment (TAR), Low Rate Initial Production (LRIP), and the first Full Rate
    4
    Section 7.3.2 inadvertently refers to CDRL A007. The government later
    administratively changed this reference from CDRL A007 to CDRL A006 (see
    R4, tab 14 at 83).
    5
    Vigor’s Rule 11 brief places significant emphasis on the version of the IPMS that
    was included with its BAFO. Therefore, for clarity, we refer to this version as
    the “BAFO IPMS.”
    4
    Production (FRP) ordering period. It also included updated versions of various
    attachments in Section J to include Vigor’s BAFO IPMS. 6 (R4, tab 21 at 1, 24)
    11. Vigor subsequently provided several updated versions of the IPMS (see
    generally R4, tabs 121-26, 128-35, 137, 139-57, 159-67, 218-30). 7
    12. On March 19, 2014, the parties executed bilateral Modification No.
    P00011, which updated the dates associated with each potential ordering period under
    Section B (R4, tab 23 at 6).
    13. The government issued individual delivery orders consistent with the
    ordering periods in the contract. The government issued seven delivery orders
    purchasing CCM Mk 1 systems, each of which established delivery dates:
    • Delivery Order 0001: Ordered one TA system and set the period of
    performance as September 27, 2011 to September 26, 2012 (R4, tab 37 at 2,
    6). Modification No. 08 added TAR, to be delivered August 20, 2014 (R4,
    tab 37i at 7, 9).
    • Bilateral Delivery Order 0002: Ordered two LRIP systems, to be delivered
    March 27, 2015 and June 12, 2015 (R4, tab 38 at 4, 8).
    • Delivery Order 0003: Ordered 2 LRIP systems, to be delivered August 18,
    2015 (R4, tab 39 at 2, 5).
    • Delivery Order 0004: Ordered 1 LRIP system, to be delivered
    November 16, 2015 (R4, tab 40 at 3, 6).
    • Bilateral Delivery Order 0005: Ordered 8 FRP systems, to be delivered
    February 18, 2016, March 31, 2016, May 12, 2016, June 23, 2016, August
    4, 2016, September 15, 2016, October 27, 2016, and December 8, 2016 (R4,
    tab 41 at 3, 6). Modification No. 01 added a ninth FRP system, to be
    delivered March 17, 2017 (R4, tab 41c at 1, 3).
    6
    The government notes “there is no indication that the parties ever attached this BAFO
    IPMS version to Contract Modification No. P00010. Instead, as evidenced by the
    Government’s official file copy of that Modification, it appears that a completely
    different schedule from [Vigor’s] BAFO was inadvertently attached as Attachment
    06 to IDIQ Contract Modification No. P00010.” (Gov’t br. at 88)
    7
    The record also includes quite a few versions of the IPMS that predate Modification
    No. P00010 (see R4, tabs 204-17).
    5
    • Bilateral Delivery Order 0018: Ordered 3 FRP systems, to be delivered
    May 17, 2017, June 21, 2017, and July 26, 2017 (R4, tab 181 at 3, 5).
    • Bilateral Delivery Order 0019: Ordered 1 FRP system, to be delivered
    August 30, 2017 (R4, tab 182 at 3, 5).
    14. The parties subsequently executed several bilateral modifications extending
    the delivery dates on these delivery orders:
    • Delivery Order 0001: Modification No. 12 (R4, tab 180).
    • Delivery Order 0002: Modification Nos. 05, 07, and 08 (R4, tabs 38e, 38g,
    38i).
    • Delivery Order 0003: Modification Nos. 01 and 02 (R4, tabs 39b, 39d).
    • Delivery Order 0004: Modification No. 02 (R4, tab 40f).
    • Delivery Order 0005: Modification Nos. 02, 03, 04, and 05 (R4, tabs 41e,
    41l, 41n, 41t).
    • Delivery Order 0018: Modification Nos. 01, 02, and 03 (R4, tabs 183, 185,
    188).
    • Delivery Order 0019: Modification Nos. 01 and 02 (R4, tabs 184, 186).
    15. On September 1, 2017, Vigor submitted a request for equitable adjustment
    (REA) seeking $4,148,629 for excess costs incurred and a reasonable profit on such
    costs. The REA alleged that the government made numerous changes in the
    production sequence and pace specified in the contract resulting in Vigor’s excess
    costs. (R4, tab 168 at 1, 22-23) Vigor alleges five changes to the contract’s
    production pace and three changes to the contract’s production sequence:
    • Production Pace
    1. The BAFO IPMS anticipated that TAR would commence in
    January 2014, but the government did not initiate TAR until February
    2014, without adjusting for the 42-day delay.
    2. The BAFO IPMS called for just two LRIP systems, but the government
    ordered two additional LRIP systems.
    6
    3. The BAFO IPMS provided for delivery of a fifth system in September
    2016, but the government ordered the fifth system to be delivered by
    November 2015.
    4. The government ordered the sixth through fourteenth systems to be
    delivered four to nine months earlier than shown in the BAFO IPMS.
    5. The government ordered the fifteenth through eighteenth systems to be
    delivered two to three months earlier than shown in the BAFO IPMS.
    • Production Sequence
    1. The BAFO IPMS provided that LRIP would not begin until TAR was
    finished, but TAR and LRIP were required to run concurrently.
    2. The BAFO IPMS had a three-month break between the end of LRIP and
    the start of FRP, but the government placed so many orders that
    appellant was forced to ramp up production and lost this anticipated
    break.
    3. The contract required a baseline configuration be finalized by the end of
    TAR, but the government ordered multiple configuration changes after
    TAR.
    (Compl. ¶¶ 167-68; see also app. br. at 8-24)
    16. The contracting officer (CO) responded to the REA on April 18, 2018. The
    CO acknowledged that the contract varied from the original Request for Proposal
    Statement of Work and the ordering periods stated in the contract Schedule, Section B.
    However, the REA response maintained that the changes were implemented via
    formal, bilateral agreements with appellant’s consent. (R4, tab 169 at 1)
    17. Appellant requested reconsideration of the REA on August 15, 2018 (R4,
    tab 170). On September 14, 2018, the CO responded to the request for
    reconsideration. The CO admitted no liability for the allegations made by appellant
    but stated that the CO was willing to settle the REA in a manner equitable to both
    parties. (R4, tab 171)
    18. The parties continued to exchange correspondence, including an April 24,
    2019, revision to the REA in the amount of $5,903,143. The CO requested that the
    Defense Contract Audit Agency (DCAA) perform an independent review of the
    amounts proposed by appellant in its revised REA. (R4, tab 175 at 3) The DCAA
    audit report, dated January 10, 2020, concluded that appellant’s “proposed amounts do
    7
    not comply with FAR 52.243-1, Changes-Fixed Price and contract terms” (R4,
    tab 175 at 7). Based on the results of the DCAA audit report, the CO denied the REA
    in full on January 27, 2020. The CO stated that there was “no financial basis to award
    Vigor any additional consideration beyond numerous, no cost production delivery
    order extensions already granted.” (R4, tab 173)
    19. On February 10, 2020, appellant resubmitted its REA as a certified claim.
    The claim stated that it was comprised of its REA, request for reconsideration of the
    REA, and a repricing adjustment prepared in response to the DCAA audit report. (R4,
    tab 176a) The totaled claimed amount was $5,213,618 (R4, tab 176).
    20. On April 23, 2020, the CO issued a final decision denying appellant’s
    claim (R4, tab 177). Vigor timely appealed the decision to the Board on July 15, 2020.
    DECISION
    The Parties’ Contentions
    Appellant argues that the government constructively changed the contract by
    accelerating the production pace and sequence through the issuance of delivery orders.
    Appellant maintains that the BAFO IPMS represented the baseline schedule for
    production and that the government’s delivery orders required Vigor “to fabricate
    more systems much earlier than specified in the IPMS, necessitating that Vigor
    perform significant extra work in order to meet the accelerated production schedule.”
    (App. br. at 29-31).
    The government maintains that it did not constructively change the contract.
    Rather, the government argues that the contract schedule, as bilaterally modified by
    the parties, represented the parties’ agreement on delivery dates. (Gov’t br. at 76)
    Discussion
    For appellant to demonstrate a constructive change, the burden of proof is on
    appellant to show: (1) that it performed work beyond the contract requirements, and
    (2) that the additional work was ordered, expressly or impliedly, by the government.
    Envtl. Chem. Corp., ASBCA Nos., 59280, 60760, 
    22-1 BCA ¶ 38,166
     at 185,361
    (citing Bell/Heery v. United States, 
    739 F.3d 1324
    , 1335 (Fed. Cir. 2014)). In this
    case, appellant argues that the government altered the contract’s requirements through
    the issuance of delivery orders. Appellant states that these orders: (1) required it to
    complete TAR and LRIP concurrently rather than consecutively; (2) increased the
    number of systems it was required to produce during LRIP and eliminated the three-
    month break that was supposed to follow LRIP; and (3) accelerated the delivery dates
    of the systems relative to the schedule. (App. br. at 29-30)
    8
    Appellant maintains that the parties incorporated into the contract the BAFO
    IPMS, which represented the baseline schedule for production. Appellant notes that
    the SOW refers to the IPMS as the baseline schedule and that each CLIN was to be
    performed in accordance with Sections C and J of the contract. (App. br. at 31-32)
    Section J of the contract, as modified by Modification No. P00010, included the
    BAFO IPMS (finding 10). Appellant states, “[w]hile the Contract may have entitled
    the Government to purchase the specified quantities of systems within the enumerated
    ordering periods, the plain language of the Contract also required that all such systems
    were to be produced in accordance with the SOW and IPMS” (app. br. at 32).
    Conversely, the government maintains that the IPMS deliverable represented
    appellant’s proposed plan to meet its contractual, agreed-to delivery dates. The
    government argues that the “CDRL A006 IPMS deliverable was . . . part of a broader
    Government effort to monitor project status and ‘evaluate progress towards meeting
    program objectives’, including the contractor’s ability to satisfy its contractual
    delivery date obligations and ‘ensure successful program execution’” (gov’t br. at 84;
    see also finding 6). The government argues that appellant understood the IPMS’s role
    by acknowledging the requirement to update it throughout the life of the contract
    (gov’t br. at 82; see also finding 9). The government notes that appellant in fact
    provided regular updates to the IPMS (gov’t br. at 82; see also finding 11). The
    government states that “[o]nly when later seeking additional compensation from the
    Government . . . did [appellant] suddenly proclaim that one particular version of its
    IPMS (the “2013 IPMS” from is BAFO) somehow overrode not only all other IPMS
    versions, but even the Contract’s established delivery schedule . . .” (gov’t br. at 86).
    This is then a question of contract interpretation, which is a matter of law for
    this Board to decide. D&J Machinery, Inc., 
    ASBCA No. 62019
    , 
    22-1 BCA ¶ 38,118
    at 185,165 (citing Blake Constr. Co. v. United States, 
    987 F.2d 743
    , 746 (Fed. Cir.
    1993)). “In matters of contract interpretation, the preferred approach is to read the
    entire contract as a whole, and to give the language of the contract its plain meaning.
    In doing so, different parts of the contract are to be read in harmony, if possible, and
    preference is given to an interpretation that gives effect to all the terms of the contract
    and does not render one or more of them meaningless.” ECC Int’l, LLC, 
    ASBCA No. 58993
     et al., 
    22-1 BCA ¶ 38,073
     at 184,887 (citing Jowett, Inc. v. United States, 
    234 F.3d 1365
    , 1368 (Fed. Cir. 2000); Christos v. United States, 
    300 F.3d 1381
    , 1384 (Fed.
    Cir. 2002); Air-Sea Forwarders, Inc. v. United States, 
    166 F.3d 1170
    , 1172 (Fed. Cir.
    1999); United Pac. Ins. Co. v. United States, 
    204 Ct. Cl. 686
    , 693-94 (1974)).
    “Further, a contract will be found to be ambiguous if it is susceptible to more than one
    reasonable interpretation, each of which is consistent with the contract language and
    the other provisions of the contract.” ECI Constr., Inc., 
    ASBCA No. 54344
    , 
    05-1 BCA ¶ 32,857
     at 162,807 (citing Lockheed Martin IR Imaging Systems, Inc. v. West,
    
    108 F.3d 319
    , 322 (Fed. Cir. 1997)). Each interpretation must fall within a “zone of
    reasonableness.” ECI Constr., 
    05-1 BCA ¶ 32,857
     at 162,807 (citing Metric
    9
    Constructors, Inc. v. NASA, 
    169 F.3d 747
    , 751 (Fed. Cir. 1999); Community Heating
    & Plumbing Co. v. Kelso, 
    987 F.2d 1575
    , 1578 (Fed. Cir. 1993); WPC Enters., Inc. v.
    United States, 
    323 F.2d 874
    , 876 (Ct. Cl. 1963)).
    Here, appellant’s interpretation of the contract, specifically the contractual
    significance of the BAFO IPMS, does not fall within the zone of reasonableness. The
    Data Description for A006 IPMS plainly explains the purpose of the IPMS. It is a tool
    used to “reflect[] the [c]ontractor’s program and schedule planning.” It is “used to
    verify attainability of contract objectives, and to integrate the program schedule
    activities with all related components.” The contractor must “ensure the IPMS reflects
    the baseline schedule and all changes thereto and maintain the IPMS throughout the life
    of the contract.” (Finding 6) Section 7.3.2 of the SOW further provides that the
    contractor “shall ensure the IPMS is up to date and available at all Government
    meetings” (finding 7). Appellant understood its responsibility to update the IPMS.
    Appellant’s BAFO acknowledged that it would “maintain the IPMS throughout the life
    of the contract” and “ensure the IPMS is up to date and available at all meetings”
    (finding 9). Indeed, appellant updated the IPMS several times. The record includes
    multiple versions of the IPMS that appellant submitted both before and after the BAFO
    IPMS. (Finding 11) We do not believe it is reasonable to maintain that one specific
    version of the IPMS, namely the BAFO IPMS, was intended to be the schedule when
    the contract clearly contemplated that appellant would submit multiple versions of the
    IPMS over time.
    The contract included the schedule in Part I (finding 2). Part I of the contract
    included Sections B and F (findings 2, 4). Section B established the potential ordering
    periods for each exercised CLIN. The parties subsequently bilaterally updated the
    dates for the ordering periods. (Findings 3, 12) The CLINs were to be “set forth
    under individual delivery order” (finding 3). Section F established delivery
    information for each CLIN, including delivery dates (finding 4). Appellant places
    significant emphasis on the fact that Section B incorporates the BAFO IPMS because
    Section B states that each CLIN was to be performed “in accordance with Sections C
    and J of the contract” and Section J contained appellant’s BAFO IPMS as incorporated
    by Modification No. P00010 (findings 3, 10). Notably, the contract did not contain a
    Section C. Rather, the contract included the SOW (which would have been Section
    C), as Attachment 01 under Section J (see n. 2). Reading the contract as a whole in
    harmony with its different parts, it is clear that the CLINs were to be performed in
    accordance with Section J (i.e., the SOW). The only reasonable interpretation for the
    inclusion of the BAFO IPMS in Section J was that it represented appellant’s “program
    and schedule planning” at that time. Furthermore, the parties understood that the
    IPMS would change over time.
    As noted above, each CLIN was to be “set forth under individual delivery
    order” (finding 3). After the parties bilaterally exercised the options for TAR, LRIP,
    10
    and the first FRP ordering period, the government issued delivery orders for CCM Mk
    1 systems (findings 10, 13). Notably, most of the delivery orders were also signed by
    appellant. The government issued seven delivery orders, which established delivery
    dates for each CCM Mk 1 system. (Finding 13) Appellant acknowledged in its brief
    that the CO “had contractual authority to issue each of the delivery orders” and that the
    contract “entitled the Government to purchase the specified quantities of systems
    within the enumerated ordering periods” (app. br. at 30, 32). Appellant’s contention is
    that the delivery orders differed from what was in the BAFO IPMS. But, again,
    appellant’s interpretation regarding the contractual significance of the BAFO IPMS
    does not fall within the zone of reasonableness. Therefore, appellant has failed to meet
    its burden in demonstrating a constructive change to the contract.
    Appellant also argues that “[e]ven if the delivery orders were bilateral, they did
    not cover Vigor’s increased costs and would not eliminate Vigor’s right to recover an
    equitable adjustment” (app. br. at 35). In support, appellant cites Chantilly Constr.
    Corp., 
    ASBCA No. 24138
    , 
    81-1 BCA ¶ 14,863
    . In Chantilly Constr. Corp., the Board
    allowed the contractor to seek increased costs where “[t]he formal modifications
    which incorporated the site changes compensated appellant solely for the direct costs
    of performing the changed work itself and did not cover appellant's increased costs . . .
    attributable to the delays in the overall project.” 
    Id.
     We do not believe Chantilly
    Constr. Corp. is relevant to our analysis here. While Chantilly Constr. Corp. involved
    a demonstrated change to the work itself, Vigor has failed to demonstrate that there
    was a constructive change to the contract in this appeal. Rather, in accordance with
    the contract, the government issued delivery orders for CCM Mk 1 systems and when
    appellant was unable to meet the delivery dates, the parties bilaterally modified the
    delivery orders to extend the delivery dates (findings 13-14).
    Finally, appellant argues that any bilateral modifications are invalid for lack of
    consideration because “Vigor received no compensation for accepting an accelerated
    schedule by modification” (app. br. at 37). But, again, appellant has failed to meet its
    burden in demonstrating that there was an accelerated schedule constituting to a
    constructive change to the contract. The government did issue delivery orders for
    CCM Mk 1 systems, and the parties did bilaterally modify those delivery orders to
    extend the delivery dates (findings 13-14). This does not equate to a constructive
    11
    change to the contract. Moreover, appellant received consideration for these bilateral
    modifications to the delivery orders in the form of extended delivery dates.
    CONCLUSION
    The appeal is denied.
    Dated: February 22, 2023
    JOHN J. THRASHER
    Administrative Judge
    Chairman
    Armed Services Board
    of Contract Appeals
    I concur                                         I concur
    RICHARD SHACKLEFORD                              J. REID PROUTY
    Administrative Judge                             Administrative Judge
    Vice Chairman                                    Vice Chairman
    Armed Services Board                             Armed Services Board
    of Contract Appeals                              of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 62607
    , Appeal of Vigor
    Works, LLC, rendered in conformance with the Board’s Charter.
    Dated: February 22, 2023
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    12