Sang Kash Company ( 2019 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                 )
    )
    Sang Kash Company                            )      ASBCA No. 60532
    )
    Under Contract No. W9 l B4N-l 5-D-8013       )
    APPEARANCE FOR THE APPELLANT:                       Mr. Abdul Bari
    President
    APPEARANCES FOR THE GOVERNMENT:                     Raymond M. Saunders, Esq.
    Army Chief Trial Attorney
    MAJ Ronald M. Herrmann, JA
    Trial Attorney
    OPINION BY ADMINISTRATIVE JUDGE WOODROW
    ON THE PARTIES' MOTIONS FOR SUMMARY JUDGMENT
    This is an appeal from the Joint Theater Support Contracting Command's
    (JTSCC or Army) termination for default against Sang Kash Company (Sang Kash or
    appellant). The Army terminated its contract for the supply of bulk concrete with Sang
    Kash after Sang Kash lost its base access privileges to Bagram Airfield, Afghanistan.
    Pending before the Board is the Army's motion for summary judgment and appellant's
    cross-motion. Clause 5152.225-5916 was incorporated into the contract by bilateral .
    modification, which required appellant to maintain access to the installation in order to
    perform work under awarded task orders (R4, tab 14). After the Senior Commander of
    Bagram Airfield Afghanistan revoked appellant's base access, the contracting officer
    terminated the contract for default. Appellant appealed the termination for default
    arguing that: (i) its base access privileges were revoked as a means for the government to
    nullify its contract rights; and (ii) appellant was deprived due process rights.
    We grantthe government's motion for summary judgment and deny the appeal.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
    1. Contract No. W91B4N-l5-D-80l3 (the contract) was a requirements contract
    awarded to Sang Kash on July 8, 2015, by CENTCOM (US Central Command)-Joint
    Theater Support Contracting Command (JTSCC) to obtain bulk concrete for Bagram
    Airfield, Parwan Province, Afghanistan (R4, tab 1 at 50). The contract incorporated by
    reference FAR 52.233-1, DISPUTES (MAY 2014) and FAR 52.249-10, DEFAULT (FIXED-
    PRICE CONSTRUCTION) (APRIL 1984) (R4, tab 1 at 32-33).
    2. The contract required Sang Kash to supply and deliver quantities of bulk
    concrete as requested by JTSCC. The contract did not include a guaranteed minimum
    quantity and explicitly stated that the quantities set forth in the schedule were estimates.
    The following clauses were incorporated into the text of the contract: 52.216-19, ORDER
    LIMITATIONS (OCT 1995) and 52.216-21, REQUIREMENTS (OCT 1995) (R4, tab 1
    at 33-35). Clause 52.216-19 states, in relevant part: "(a) Minimum order. When the
    Government requires supplies or services covered by this contract in an amount of less
    than O cm ( quantity), the Government is not obligated to purchase, nor is the Contractor
    obligated to furnish, those supplies or services under the contract" (R4, tab 1 at 34)
    (emphasis in original). Clause 52.216-21 states, in relevant part:
    (a) This is a requirements contract for the supplies or services
    specified.... The quantities of supplies or services specified in
    the Schedule are estimates only and are not purchased by this
    contract. Except as this contract may otherwise provide, if
    the Government's requirements do not result in orders in the
    quantities described as "estimated" or "maximum" in the
    Schedule, that fact shall not constitute the basis for an
    equitable price adjustment.
    
    Id. The statement
    of work (SOW), written into the contract, states in Section 1.1.1 that
    the purpose of the contract is: "to obtain bulk concrete for Bagram Airfield. All
    other requirements listed in the Statement of Work (SOW) are secondary and not
    guaranteed." (R4, tab 1 at 50) (emphasis in original) SOW Sections 2.23-2.34 address
    access to military installations and bases in Afghanistan (R4, tab 1 at 56-57). SOW
    Section 2.28 states that "Contracting officers may terminate contractors when contractors
    lose the ability to access the work site" (R4, tab 1 at 57).
    3. Bilateral Modification No. P00002, dated November 10, 2015, added Central
    Command (CENTCOM) clause 5152.225-5916 MANDATORY ELIGIBILITY FOR
    INSTALLATION ACCESS (OCT 2015) in full text, to the contract (R4, tab 14). The clause
    required the prime contractor and all subcontractors to be initially eligible for installation
    access to a U.S. and/or coalition installation, and to remain eligible during the entire
    period of contract performance. The clause stated, in relevant part:
    5152.225-5916
    MANDATORY ELIGIBILITY FOR INSTALLATION
    ACCESS
    (OCT 2015)
    (a) U.S. and Coalition Commanders possess inherent
    authority to maintain law and order, provide security, and
    impose discipline necessary to protect the inhabitants of U.S.
    2
    and/or Coalition installations, U.S. and Coalition personnel
    operating outside of installations, and U.S. or Coalition-
    funded developmental projects in Afghanistan. This authority
    allows commanders to administratively and physically control
    access to installations and/or project sites, and to bar
    contractors - including prime contractors, subcontractors at
    any tier, and any employees, from an installation or site. A
    commander's inherent force protection (FP) authority is
    independent of an agency's contracting authority, and it may
    not be superseded by any contractual term or provision.
    (b) The prime Contractor/Vendor acknowledges that:
    submission of a bid, offer, or a proposal; acceptance of
    contract award of any type; or continuing effort under any
    contract that includes this clause; requires that the prime
    Contractor/Vendor, and all subcontractors under any affected
    contracts be initially eligible -- and remain eligible during the
    entire period of contract performance to include any warranty
    period -- for installation access to a U.S. and/or Coalition
    installation, regardless of whether the performance will take
    place on or off a U.S. or Coalition installation.
    (2) Failure to be approved in JCCS -- and thereby be eligible
    for installation access at the prime and subcontractor levels --
    or failure to inform the contracting officer of the names of all
    prospective subcontractors (or provide a negative reply), may
    render the offeror/contractor ineligible for award or continued
    performance. Additionally, any firm that is declared
    ineligible for installation access will be deemed non-
    responsible until such time as that firm is again deemed
    eligible by the appropriate access approval authority.
    ( d) Installation access determinations arise from the
    Combatant Commander's inherent authority and are separate
    and distinct from any law, regulation, or policy regarding
    suspension and debarment authority. Contractor queries or
    requests for reconsideration related to U.S. or Coalition
    installation base access eligibility must be directed to the
    authority responsible for base access decisions.
    (R4, tab 14 at 2)
    3
    4. By letter dated March 25, 2016, the Bagram Support Group (BSG) Commander
    of Bagram Airfield revoked Sang Kash' s access to Bagram Airfield, stating, in relevant
    part:
    Base Access Denial from Bagram Airfield, Afghanistan ...
    2. Pursuant to the above references and my authority
    delegated to me by the Senior Commander ofBagram
    Airfield, you are hereby base access denied from Bagram
    Airfield, Afghanistan effective immediately. You are granted
    provisional access in order to remove personnel and
    equipment from the base for a time period not to exceed ten
    (10) days from the date of this memorandum.
    3. Violation of this order may result in criminal prosecution
    for trespassing under reference a. You may request, within
    (60) days of receipt of this notice, that this order be
    reconsidered by writing me through the United States Forces-
    Afghanistan (USFOR-A) Force Protection Cell.
    5. Pursuant to USFOR-A/RS policy, your base access denial
    from this installation will apply to all USFOR-NRS
    installations in the Combined Joint Operations Area-
    Afghanistan. (CJOA-A), [sic] and will be uniformly enforced
    by each installation.
    (R4, tab 19) (emphasis in original)
    5. Pursuant to contract Modification No. P00003, dated March 29, 2016, the
    contracting officer (CO) terminated the contract for default for"[ v]iolation of Contract
    Clause 5152.225-5916 Mandatory Eligibility for Base Access" and cited to FAR clause
    52.249-10 (Default) (R4, tab 21 at 2). The final decision included the standard appeal
    rights set forth at FAR 33.21 l(a)(4)(v), CONTRACTING OFFICERS DECISION (R4, tab 21
    at 2-3). The modification is countersigned as being received by Sang Kash's
    representative (R4, tab 21 at 1, 3).
    6. By letter dated March 30, 2016, the CO explained Modification No. P00003 to
    appellant, stating that Sang Kash' s status in the Joint Contracting and Contingency
    4
    System (JCCS) had not been approved and its "Vendor Vetting Status" was an
    "Unacceptable Risk" (R4, tab 20).
    7. By email to the contracting officer dated April 10, 2016, Sang Kash's
    representative requested that the BSG Commander of Bagram Airfield reconsider its base
    access denial. Attached to its email were supporting documents. (R4, tab 25) There is
    no evidence in the record that Sang Kash asserted that it was an approved contractor in
    JCCS.
    8. On April 13, 2016, Sang Kash appealed the termination to the Board. The
    Board docketed Sang Kash's appeal as ASBCA No. 60532.
    9. By letter dated May 10, 2016, the BSG Commander of Bagram Airfield denied
    Sang Kash' s request for base access reconsideration, stating, in relevant part:
    After reviewing your request and the underlying basis for
    denial, I have determined that the original denial was based
    on substantiated information. Additionally, I have not been
    provided any supplementary information which would alter
    my original decision. As the BSG Commander, I have the
    inherent authority to protect my forces and you have been
    assessed as a risk to the welfare of the installation's
    personnel. Your request for reconsideration is denied and your
    base access denial status is affirmed.
    (R4, tab 27)
    DECISION
    I.      Standard Of Review For Motion For Summary Judgment
    We will grant summary judgment only if there is no genuine issue as to any
    material fact, and the moving party is entitled to judgment as a matter of law. Celotex
    Corp. v. Catrett, 477 U.S. 317,322 (1986); Colonna 's Shipyard, Inc., ASBCA
    No. 59987 et al., 16-1BCA136,518 at 177,902. A material fact is one that may affect
    the outcome of the decision. Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    ,
    248-49 (1986); Colonna's Shipyard, Inc., 16-1BCA136,518 at 177,902. The moving
    party bears the burden of establishing the absence of any genuine issue of material fact,
    and all significant doubt over factual issues must be resolved in favor of the party
    opposing summary judgment. Mingus Constructors, Inc. v. United States,
    
    812 F.2d 1387
    , 1390-91 (Fed. Cir. 1987); Colonna 's Shipyard, Inc., 16-1BCA136,518
    at 177,902. Once the moving party has met its burden of establishing the absence of
    disputed material facts, then the non-moving party must set forth specific facts, not
    5
    conclusory statements or bare assertions, to defeat the motion. Pure Gold, Inc. v. Syntex
    (US.A.), Inc., 
    739 F.2d 624
    , 626-27 (Fed. Cir. 1984); Colonna 's Shipyard, Inc., 16-1
    BCA ,i 36,518 at 177,902.
    II.    The Parties' Contentions
    The government moves for summary judgment arguing "there is no dispute that
    the appellant failed to maintain access to the base where it was obligated to perform"
    (gov't mot. at 1). The government contends that the contract was bilaterally amended to
    include CENTCOM clause 5152.225-5916 (Mandatory Eligibility for Installation
    Access) requiring "that Sang Kash must maintain access to the installation in order to
    perform work under awarded task orders" (gov't mot. at 7). "The Government
    terminated Sang Kash because the base commander took independent action for a valid,
    sovereign reason to ensure force protection .... [and] the contracting officer properly
    terminated Sang Kash for defaulf' (gov't mot. at 7-8).
    Although not clearly articulated by appellant, the Board interprets its reply to the
    government's motion and understands its argument to be that the BSG Commander, who
    revoked appellant's base access, was not separate from the contracting officer and the
    contract was terminated to get around the guaranteed concrete orders "for convenience"
    of the government (app. resp. at 1-5, 10). Appellant states that the awarded contract was
    a "[g]uaranty for bulk concrete" estimated to be 15,000 cubic yards while JTSCC had
    purchased only 128 cubic meters through the base year (app. resp. at 1). In addition, the
    Board further interprets appellant's argument to include a due process concern.
    Appellant argues that "we have the right to know why our installation access was
    denied,'' as the BSG Commander's base access denial did not articulate specific facts in
    his revocation and he summarily determined that appellant was a security "risk"
    (app. resp. at 9). Appellant argues that although its base access was revoked, "most of
    our on[-]site key personnel are hired immediately by another company inside Bagram Air
    base." Appellant listed the names and badge numbers of six employees who were
    allegedly hired by another company and gained access to Bagram Air Base (app. resp.
    at 10). Appellant requests that "the Board should enter judgment in favor of ... [it] given
    that there is no reason that Sang Kash Company posses[s a] risk to [the] welfare of
    installation personnel but a falsified information, misuse of authority, and favoritism lead
    to termination of [the] contract" which we interpret as a cross-motion for summary
    judgment (app. resp. at 10).
    III.   There Are No Material Facts In Dispute
    Appellant alleges that the BSG Commander revoked its base access as a method to
    terminate the contract for default, because JTSCC was failing to order the requisite
    guaranteed amount of concrete. It is undisputed that the contract is a requirements
    contract and did not include a minimum quantity. Nowhere in the contract does it state a
    6
    minimum amount of concrete will be delivered and installed during the base year. The
    contract expressly states that the bulk concrete contract line item numbers are estimates
    and are not guaranteed. (SOF ,i 2) The record does not support appellant's versions of
    the facts sufficient to show material facts are in dispute, nor does the record support
    appellant's allegations of alternative reasons for the contract termination. Appellant has
    not provided any evidence that JTSCC intended to nullify its contract rights or that the
    termination provided JTSCC an economic advantage. The government has met its
    burden of establishing the absence of disputed material facts. New Era Contract Sales,
    Inc., ASBCA No. 56204, 09-2 BCA ,i 34,147 at 168,795; Emerald Town Group Logistic
    Services, ASBCA Nos. 60300. 60302, 17-1 BCA i! 36,709 at 178,753-55.
    IV     Discussion
    It is undisputed that the parties bilaterally agreed to incorporate CENTCOM
    clause 5152 .225-5916, which required the contractor to maintain its base access
    eligibility during the entire period of contract performance, into the contract (SOF ,i 3).
    CENTCOM clause 5152.225-5916 provides that contractors who were found ineligible
    for base access "may render the []contractor ineligible for. .. continued performance ... "
    (id.). It is undisputed that the contract required appellant to maintain access to the site or
    the contract could be terminated for default (SOF ,i,i 2, 3). Acting upon the commander's
    authority, appellant's base access privileges were revoked (SOF ,i 4). Appellant does not
    dispute that its base access was revoked and that it failed to maintain access to Bagram
    Airfield. per the contract.
    Appellant's allegations that JTSCC terminated the contract as a means to get
    around the ·'guaranteed" or minimum requirements of bulk concrete orders (app. resp.
    at 1, 9) are not supported by the contract or the record (SOF ,i,i 3, 4). Clause 52.216-19
    stated that JTSCC is not obligated to order supplies/services if it has no need (SOF ,i 2).
    In support of its opposition, appellant offered exhibits that do not add anything to the
    discussion nor do they show any facts that may be in dispute regarding the termination
    (app. resp. at 3-8).
    Appellant has raised a due process concern, arguing ··we have the right to know
    why our installation access was denied" (app. resp. at 9). Due process normally requires
    that a contractor receive notice of the charges impugning its integrity and an opportunity
    to be heard. Old Dominion Dairy Products, Inc. v. Secretary of Defense, 
    631 F.2d 953
    ,
    968 (D.C. Cir. 1980); Leslie & Elliott Company, Inc. v. Garrett, 
    732 F. Supp. 191
    ,
    198 (D.D.C. 1990). However, the requirements of due process vary given the
    circumstances. Morrissey v. Brewer, 408 U.S. 471,481 (1972) ("[D]ue process is
    flexible and calls for such procedural protections as the particular situation demands.").
    Installation access decisions are military command decisions. It is well
    established that the commanding officer of a military base has wide discretion as to
    7
    whom he or she can exclude from the base. Cafeteria & Restaurant Workers Union,
    Local 473, AFL-CIO v. McElroy, 
    367 U.S. 886
    , 893-94 (1961) (recognizing power of
    post commander recognized when revocation of employee's security access to
    installation upon the security officer's determination that she failed to meet the security
    requirements of the activity; "It is well settled that a Post Commander can, under the
    authority conferred on him by statutes and regulations, in his discretion, exclude private
    persons and property therefrom, or admit them under such restrictions as he may
    prescribe in the interest of good order and military discipline."); Garco Construction Inc.,
    ASBCA No. 57796, 14-1 BCA ii 35,512 at 174,073 (several contractor's personnel
    installation access were revoked after implementing a policy to deny base access to
    individuals ;'having outstanding wants or warrants, sex offenders, violent offenders, those
    who are on probation, and those who are in a pre-release program'' where ;'the purpose of
    [the] policy was to ensure the safety of personnel on the installation and preserve the
    good order and discipline on the installation."); Conner Brothers Construction Company,
    Inc., ASBCA No. 54109, 07-2 BCA ii 33,703 at 166,876; 166,878 (affirmed by Conner
    Brothers Construction Company, Inc. v. Geren, 
    550 F.3d 1368
    (Fed. Cir. 2008) (allowing
    base commander to deny access to construction company to installation site for 41 days
    following the terrorist attacks of September 11, 2001, which "the purpose of the order
    was to serve national policy objectives, not to relieve the Corps of its contractual
    obligations."); Emerald Town Group Logistic Services, 17-1 BCA ii 36,709 at 178, 753-54
    (termination after contractor's base access was revoked after a determination that "its
    operations have been determined to be a force protection threat to US and Coalition
    Forces at Kandahar Airfield."); Gargoyles, Inc., ASBCA No. 57515, 13 BCA ii 35,330 at
    173,415-16 (Contract was properly terminated when the contractor was unable to obtain
    access to U.S. military installation in Iraq to deliver 56 light armored vehicles).
    A determination of installation access is a matter of inherent command authority
    and is not at the discretion of the contracting officer or this Board. The Board will not
    question a military commander's revocation of base access unless appellant can provide
    substantiated facts to support the contract was terminated to nullify contract rights or to
    provide the government with economic gain. Conner Brothers Construction 
    Company, 550 F.3d at 1374-75
    . In this appeal, because there was no required minimum quantity the
    BSG Commander's decision to revoke appellant's base access would not have nullified
    appellant's contract rights or provided JTSCC an economic advantage. The fact that the
    actions of the government entity that controlled base access were beyond appellant's
    control is not a valid excuse for non-performance. Emerald Town Group Logistic
    Services, 17-1 BCA ii 36,709 at 178,753-54.
    8
    CONCLUSION
    The government's motion for summary judgment is granted. The appeal is denied.
    Dated: June 1 L 2019
    1/"'· :Z) .1-- ·---
    Kt{WNi?rti f1.~ow
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur
    ~---·······--
    OWEN C. WILSON
    Administrative Judge                          Administrative Judge
    Chairman                                      Vice Chairman
    Armed Services Board                          Armed Services Board
    of Contract Appeals                           of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA No. 60532, Appeal of Sang Kash
    Company. rendered in conformance with the Board's Charter.
    Dated:
    ----------                ----------·--
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    9