Expresser Transport Corporation ( 2018 )


Menu:
  •                   ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                  )
    )
    Expresser Transport Corporation               )      
    ASBCA No. 61464
    )
    Under Contract No. N00033-82-C-1013           )
    APPEARANCE FOR THE APPELLANT:                        Patrick H. Mccaffery, Esq.
    General Counsel
    APPEARANCES FOR THE GOVERNMENT:                      Craig D. Jensen, Esq.
    Navy Chief Trial Attorney
    Robert R. Kiepura, Esq.
    Senior Trial Attorney
    OPINION BY ADMINISTRATIVE JUDGE MELNICK
    GRANTING SUMMARY JUDGMENT FOR THE GOVERNMENT
    This is an appeal from the government's denial of an indemnification claim.
    Because the claim was waived by the contract's express terms, summary judgment is
    granted to the government and the appeal is denied. The following facts are undisputed.
    In 1983, the contractor, Expresser Transport Corporation, and the United States
    entered into the time charter contract identified above (which was then amended and
    restated in 1985) for the Military Sealift Command (MSC) to hire MV 1s1 Lt Alex
    Bonnyman to support the prepositioning of military equipment and supplies (compl.
    111-2; R4, tab 1 at 1-6, 55). 1 The 145-page agreement (not counting annexes)
    contained extremely detailed language governing the parties' relations, obligations,
    and responsibilities (R4, tab 1). Consistent with the nature of a time charter, Expresser
    remained responsible for operating the ship, which it contractually accomplished
    through its parent company, Maersk Line, Limited (compl. 1 1; R4, tab 1 at 6).
    However, the government could place civilian contractors aboard for communications
    and cargo maintenance (compl. 13; R4, tab 1 at 77). The government agreed to
    "indemnify [Expresser] for liabilities resulting from the carriage of such personnel"
    (compl. 1 4; R4, tab 1 at 78).
    1
    While discussing the vessel bearing his name, it is worth noting that Lt Bonnyman
    was a United States Marine posthumously awarded the Congressional Medal of
    Honor for heroic actions in 1943 during the battle of Betio Island, Tarawa. See
    http://www.marinemedals.com/bonnymanalexander.htm.
    Article 38 of the charter was entitled "WAIVER OF CLAIMS." It stated:
    All claims whatsoever for moneys due the
    Contractor under this Charter must be submitted in
    accordance with the applicable Military Sealift Command
    billing instruct~ons within two years of the date of
    redelivery of the Vessel, except as otherwise provided in
    Article 44(a). Except as so provided, all claims not
    submitted within the two-year limit shall be deemed to
    have been waived by the Contractor.
    (R4, tab 1 at 120)2 The charter also incorporated Defense Acquisition Regulation
    (DAR) 7-103.12, DISPUTES (JUN 1980) (R4, tab 1 at 149). This clause stated the
    charter was "subject to the Contract Disputes Act of 1978 (P.L. 95-563)" (CDA), and
    in relevant part described the procedures for pursuing a claim. See Santa Fe Eng 'rs,
    Inc., 
    ASBCA No. 36292
    , 92-2 BCA ,r 24,795 at 123,677. 3
    On May 11, 2007, a government contract employee stationed aboard Bonnyman
    suffered an injury leaving him a paraplegic. In June of 2008, the employee filed suit in
    the United States District Court for the Southern District of Ohio against, among
    others, the government and Maersk. (Compl. ,r,r 5-6) The complaint sought damages
    for maintenance, cure, wages, attorney fees, and punitive damages (R4, tab 2).
    Expresser was added as a defendant by an amended complaint (R4, tab 5.18).
    The charter was terminated by the government for its convenience on July 15,
    2009 (compl. ,r 2). Neither party disputes that Bonnyman was redelivered on that date
    (gov't mot. at 4; app. opp'n at 4).
    In May of 2010, the district court dismissed the government from the employee's
    suit (compl. ,r 7). On March 21, 2011, the employee settled with Expresser and Maersk,
    releasing them from liability in exchange for $2,500,000 (compl. ,r 9; gov't mot. ,r 7).
    Slightly less than six years later, on March 15, 2017, Mr. Steven E. Hadder, President of
    Expresser and Vice President of Maersk, submitted a certified claim to the contracting
    officer seeking $2,782,088.62 in reimbursement for the settlement and for legal fees
    (compl. ,r 10; R4, tabs 3-4). Mr. Hadder contended that Expresser and Maersk were
    entitled to recover based upon the government's indemnification of Expresser for liabilities
    2
    Article 44(a) contained exceptions neither party contends are relevant here (R4,
    tab 1 at 139).
    3
    The Board requested the government to provide a copy of the actual clause as it
    existed in 1980, but it was unable to do so. Santa Fe Engineers recites its
    relevant portions.
    2
    resulting from the carriage of private civilian contractors aboard Bonnyman. The
    contracting officer denied the claim on October 3, 2017 (R4, tab 3). This appeal followed.
    DECISION
    I.       The Merits
    The government moves to dismiss the appeal for failure to state a claim upon
    which relief may be granted. 4 Because the parties rely upon statements and materials
    outside the pleadings, the motion is treated as one for summary judgment. 5 See FED.
    R. CIV. P. 12(d). Summary judgment should be granted if there are no genuine issues
    of material fact and the moving party is entitled to judgment as a matter of law.
    Celotex Corp. v. Catrett, 
    477 U.S. 317
    ,322 (1986).
    The government's argument is fairly simple. Article 38 of the charter stated
    that "[a]ll claims ... for moneys due ... under [the] Charter must be submitted in
    accordance with the applicable Military Sealift Command billing instructions within
    4
    The claim letter opens by referring to Maersk as MLL. Later it states that
    "Expresser and MLL are hereinafter referred to collectively as 'MLL. "'
    Mr. Hadder's certification, located at the end of the letter, included the
    statement "that the amount requested accurately reflects the contract adjustment
    for which MLL believes the Government is liable; and that I am duly authorized
    to certify the claim on behalf of MLL." By order issued September 18, 2018,
    the Board inquired of the parties whether this language complied with the
    reference to "contractor" contained in 
    41 U.S.C. § 7103
    (b)(l)(C).
    In response, the government advances a request to dismiss the appeal for
    lack of jurisdiction, observing that Maersk is not the contractor and suggesting that
    "[t ]he fact that the letter indicates that the claim was being certified by 'MLL,'
    meaning Maersk, means that the claim contains no certification at all" (gov't resp.
    to Bd. inquiry 41 U.S.C. § 7103
    (b)(l)(C). (R4, tabs 3-4)
    5
    Prior to this decision the Board notified the parties that it was considering treating
    the motion as one for summary judgment because the parties relied on materials
    outside the pleadings. The Board invited them to present any pertinent
    additional material. Expresser's supplemental submission is discussed below in
    the section on discovery.
    3
    two years of the date of redelivety of the Vessel." Additionally, "[e]xcept as so
    provided, all claims not submitted within the two-year limit shall be deemed to have
    been waived by the Contractor." Bonnyman was redelivered on July 15, 2009, and
    therefore any money claim was waived unless submitted by July 15, 2011.
    Expresser's March 15, 2017 claim for indemnification was therefore waived.
    Expresser responds that the government's reliance upon Article 38 presents an
    "unacceptable result." Because it is conceivable that a claim against it might not have
    been resolved until more than two years after Bonnyman was redelivered, a claim by
    Expresser for indemnification might not have accrued within Article 38 's allowed time
    period. It notes that a claim cognizable under the CDA cannot '"accrue' until the
    amount of the claim, 'a sum certain,' .. .is 'known or should have been known."'
    Kellogg Brown & Root Servs., Inc. v. Murphy, 
    823 F.3d 622
    , 627 (Fed. Cir. 2016)
    (quoting FAR 2.101). Expresser argues it cannot be the case that it agreed to waive
    potential claims that might not have accrued before Article 38's deadline. Such a
    result would deny it recourse under the CDA, which it says conflicts with the Board's
    decision in Ikhana, LLC, 
    ASBCA No. 60462
     et al., 17-1 BCA ,r 36,871. Citing
    Rejlectone v. Dalton, 
    60 F.3d 1572
    , 1577 (Fed. Cir. 1995) (en bane), Expresser alleges
    that it functioned under the "assumption" that Article 38 only restricted the time within
    which "routine" requests for payment could be submitted. It implies that its
    indemnification claim is not routine and therefore not restricted by Article 38.
    According to Expresser, all that limits the submission of its indemnification claim is
    the doctrine of laches. 6
    · "A contract must...be construed as a whole and 'in a manner that gives meaning
    to all of its provisions and makes sense.'" Bel/Heery v. United States, 
    739 F.3d 1324
    ,
    1331 (Fed. Cir. 2014) (quoting McAbee Constr., Inc. v. United States, 
    97 F.3d 1431
    ,
    1435 (Fed. Cir. 1996)). The relevant portions of the charter are its provision
    permitting government contract personnel to serve aboard Bonnyman, the
    government's promise to indemnify Expresser for liabilities resulting from the carriage
    of such personnel, and Article 38, stating that "[a]ll claims ... for moneys due"
    Expresser under the charter "must be submitted ... within two years of the date of
    redelivety" of Bonnyman. All "claims not submitted within the two-year limit shall be
    deemed to have been waived by" Expresser. Expresser suggests DAR 7-103.12(b) is
    also relevant.
    6
    The parties agree that the CDA's own six-year limit upon the submission of claims,
    provided now at 
    41 U.S.C. § 7103
    (a)(4), does not apply. That statutoty
    provision had not been enacted in 1985 at the time the restated charter was
    executed, and is not retroactive. See Motorola, Inc. v. West, 
    125 F.3d 1470
    (Fed. Cir. 1997).
    4
    The sensible meaning of all the charter's relevant provisions is that the government
    indemnified Expresser for liabilities resulting from the carriage of government contract
    personnel. However, the government's exposure to such claims was not open ended.
    Claims not submitted by Expresser within two years of Bonnyman's redelivery were
    waived. That Expresser may now find Article 38 "unacceptable," because it waived
    claims that might not have accrued before the deadline, does not change what it agreed to.
    It is far from surprising that the charter's comprehensive treatment of the parties' rights
    established a firm date beyond which any claims for money due would not be viable. As
    Expresser observed, claims made against it could take an indeterminate amount of time to
    resolve, potentially delaying the accrual of its own claims upon the government for
    indemnification for an unknown period. By limiting that exposure, Article 38 is
    comparable to a statute of repose, which "cuts off a cause of action at a certain time
    irrespective of the time of accrual." Weddel v. Secy ofHealth and Human Servs.,
    
    100 F.3d 929
    , 931 (Fed. Cir. 1996). Contrary to Expresser's suggestion, nothing in
    DAR 7-103.12(b) conflicts with this conclusion. That provision merely stated that "all
    disputes arising under or relating to [the charter] shall be resolved in accordance with this
    clause." It did not forbid the contractual expiration of Expresser's right to seek payments
    under the charter.
    Notably, the scenario Expresser suggests is objectionable about Article 38, that
    its indemnification claim could have been waived before it accrued, did not happen.
    The parties disagree over when Expresser's indemnification claim accrued, with the
    government contending it occurred on the date the employee was injured in May of
    2007, and Expresser maintaining that the sum certain it seeks could not be known until
    it settled with the employee on March 21, 2011. There are other possible dates in
    between that could apply. However, even if Expresser's March 21 date is correct, it
    had from then until July 15 to submit a claim to the contracting officer before it was
    waived. Expresser does not suggest it could not do so.
    Expresser represents that it assumed Article 38 only applied to "routine"
    requests for payment, implying its indemnification claim is not routine. However, it
    presents no tangible evidence that it interpreted the charter that way. Mere argument
    by its attorney is not evidence. Gemtron Corp. v. Saint-Gobain Corp., 
    572 F.3d 1371
    ,
    1380 (Fed. Cir. 2009). Moreover, even if Expresser had submitted otherwise
    competent extrinsic evidence of the charter's meaning, it would be irrelevant given that
    Article 38 is unambiguous. See Auto. Mgmt. Servs. FZE, 
    ASBCA No. 58352
    , 15-1
    BCA ,r 36,119 at 176,329 (holding the Board does not consider extrinsic evidence to
    interpret an unambiguous contract). Nothing in it or any other part of the charter
    limited the waiver provision merely to "routine" requests for payment.
    Also, Expresser's reliance upon Rejlectone to establish the distinction it
    proposes is misplaced. Rejlectone holds that a written demand seeking the payment of
    money as of right need not already be in dispute when submitted to the contracting
    5
    officer to constitute a CDA claim, except if it is a voucher, invoice or other routine
    request for payment. Reflectone, 
    60 F.3d at 1577
    . If Expresser is correct that its claim
    is non-routine (and the government does not contest that assertion) than that simply
    means it was ripe for submittal to the contracting officer regardless of whether it was
    previously in dispute. Rejlectone does not govern the merits of a claim or restrict the
    parties from agreeing to the conditions of its waiver.
    Jkhana does not favor Expresser either. There, a contractor purported to assign to
    its surety its "contract rights," after which the surety attempted to dismiss the
    contractor's appeal to this Board and release the government from all claims. The Board
    rejected the idea that such an assignment could preclude the contractor from exercising
    its statutory right of appeal to this Board. Noting the CDA is intended to equalize the
    parties' bargaining power by guaranteeing at least one impartial review of contracting
    officer decisions, the Board observed that "[p]ermitting parties to contract away Board
    review entirely would subvert this purpose." 17-1 BCA ,r 36,871 at 179,731 (quoting
    Burnside-Ott Aviation Training Ctr. v. Dalton, 
    107 F.3d 854
    , 859 (Fed. Cir. 1997)). The
    statutory right to appeal from contracting officer final decisions is unwaivable. 
    Id.
    Article 38 does not waive any of Expresser's statutory rights, much less its right
    to appeal to this Board. Thus, this appeal is here. Article 38 places substantive
    limitations upon Expresser's contract rights by waiving claims not submitted within two
    years of vessel redelivery. Nothing in lkhana, or any other authority cited by Expresser,
    forbids the parties from arranging their contractual relationship in this manner.
    II.    Discovery
    In its supplemental submission, Expresser argues that "several genuine issues of
    material fact exist which Expresser should be permitted to examine in the course of
    discovery" (app. supp. br. at 4). In particular, it seeks discovery into whether the MSC
    billing instructions with which claims had to be in accord under Article 38 support its
    position that an indemnification claim is not within the scope of Article 38. It suggests
    the meaning of the article is a genuine issue of material fact. Expresser also implies it
    needs discovery into other issues, including whether its claim accrued when the
    contractor employee was injured, whether there is a factual basis "for the Government's
    defense of laches" (id. at 7), and whether its CDA certification is defective.
    "In deciding motions for summary judgment, the Board looks to Rule 56 of the
    Federal Rules of Civil Procedure for guidance." Board Rule 7(c)(2). Federal Rule of
    Civil Procedure 56(d) provides that a court may allow time for discovery if the
    nonmoving party shows by affidavit or declaration that "for specified reasons, it
    cannot present facts essential to justify its opposition" to the motion. Expresser has
    not met the threshold requirement for an affidavit or declaration making the showing
    required by Rule 56(d). See Brubaker Amusement Co. v. United States, 
    304 F.3d
                                       6
    ( among other reasons, rejecting appeal from denial of discovety before summaiy
    judgment given that there was no affidavit). 7
    Furthermore, summaiy judgment need not be deferred or denied to permit
    discoveiy based upon a mere speculative hope that a claimant might find evidence to
    support its case. Brubaker Amusement, 304 F.3d at 1361. Though it does not have to
    be clairvoyant, Expresser must "state with some precision the materials [it] hope[s] to
    obtain with further discoveiy, and exactly how [it] expect[s] those materials would
    help [it] in opposing summaiy judgment." Simmons Oil Corp. v. Tesoro Petroleum
    Corp., 
    86 F.3d 1138
    , 1144 (Fed. Cir. 1996) (quoting Krim v. BancTexas Grp., Inc.,
    
    989 F.2d 1435
    , 1443 (5 1h Cir. 1993)). Expresser is not "allowed to conduct discovety
    that has no chance of leading to the denial of summaiy judgment for" the government.
    Jiang/in Zhou v. United States, 
    727 F. App'x 651
    , 654 (Fed. Cir. 2018) (quoting RQ
    Squared, LLC v. United States, 
    119 Fed. Cl. 751
    , 758 (2015)). Nor is it enough to
    imply that "something will tum up." Simmons Oil, 
    86 F.3d at 1144
    .
    Expresser is clear enough that it seeks to take discovety about the MSC billing
    instructions applicable to Article 38 claims, but it is far less apparent what they might
    reveal to help its case. It speculates they might "support Expresser's contention that
    the 2-year limitation in Article 38 ... does not bar the submission of a claim for
    indemnification." It suggests they might say that an indemnification claim need not be
    submitted under them. Expresser provides no explanation as to why it expects they
    might say that. Indeed, Article 38's scope was unlimited. It applied to "[a]ll claims
    whatsoever for moneys due the Contractor under this Charter" and it required them to
    be "submitted in accordance with applicable ... billing instructions within two years of
    the date of redeliveiy" (R4, tab 1 at 120). Though the billing instructions might dictate
    the procedures for submitting claims, Article 3 8 did not provide any basis for them to
    carve out a class of claims for moneys due that could be excluded from its time limits.
    Thus, even if the Board were to look past Expresser's failure to present an affidavit or
    7
    Brubaker Amusement addressed Rule 56(g) of the Rules of the United States Court
    of Federal Claims as they existed at that time. That rule was substantively
    similar to the current version of Federal Rule of Civil Procedure 56( d), stating:
    Should it appear from the affidavits of a party opposing the
    motion that such party cannot for reasons stated present by
    affidavit facts essential to justify such party's opposition,
    the court may refuse the application for judgment or may
    order a continuance to permit affidavits to be obtained or
    deposition to be taken or discoveiy to be had or may make
    such other order as is just.
    Bntbaker Amusement, 304 F.3d at 1361 n.4.
    7
    declaration, Expresser's reasons for seeking the billing instructions rely upon flawed
    logic, do not rise above the level of a speculative hope, and amount to little more than
    the suggestion that something might turn up.
    The remaining three reasons Expresser gives for seeking discovery are even less
    compelling. First, there is no need for discovery into whether Expresser's claim
    accrued when the contractor employee was injured, as the government contends. As
    explained above, assuming Expresser's claim accrued as late as March 21, 2011, as it
    suggests, the claim was still waived by the time Expresser submitted it in 201 7.
    Second, contrary to Expresser's suggestion, the government has not premised its motion
    upon the defense of laches. Third, the government's motion to dismiss based upon the
    absence of a certification has been denied. Accordingly, discovery for the purposes of
    these last three reasons has no chance of leading to the denial of summary judgment for
    the government. Expresser's request to take discovery is therefore denied.
    CONCLUSION
    Summary judgment is granted in favor of the government. The appeal is denied.
    Dated: December 7, 2018
    .;]£(~
    MARK A. MELNICK
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                          I concur
    +=P     C>-
    R1C1{] SHACKLEFORD                                J. REID PROUTY
    Administrative Judge                              Administrative Judge
    Acting Chairman                                   Vice Chairman
    Armed Services Board                              Armed Services Board
    of Contract Appeals                               of Contract Appeals
    8
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 61464
    , Appeal of
    Expresser Transport Corporation, rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    9