ACC Construction Co., Inc. ( 2021 )


Menu:
  •                 ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeals of --                                 )
    )
    ACC Construction Co., Inc.                    )      ASBCA Nos. 62265, 62937
    )
    Under Contract No. W912QR-17-C-0021           )
    APPEARANCES FOR THE APPELLANT:                           Lochlin B. Samples, Esq.
    Jacob W. Scott, Esq.
    Mackenzie P. Bell, Esq.
    Smith, Currie & Hancock LLP
    Atlanta, GA
    APPEARANCES FOR THE GOVERNMENT:                          Michael P. Goodman, Esq.
    Engineer Chief Trial Attorney
    R. Lauren Horner, Esq.
    Brett R. Howard, Esq.
    Engineer Trial Attorneys
    U.S. Army Engineer District, Louisville
    OPINION BY ADMINISTRATIVE JUDGE MELNICK ON THE GOVERNMENT’S
    MOTION TO STRIKE THE FIRST AMENDED COMPLAINT
    The government seeks to strike ACC Construction Co., Inc.’s (ACC) July 12,
    2021, first amended complaint. The government contends that the amended complaint
    alters allegations made in the original complaint without leave to amend and raises a
    new issue not advanced in either of the claims submitted to the contracting officer.
    The motion is partially granted and partially denied.
    ACC’s original claim, dated May 14, 2019, stems from a contract to design and
    construct various facilities for the United States Army Reserve in Virginia. It sought
    the costs (along with extra time) associated with unexpected storm water drainage
    requirements imposed by Virginia, basing the government’s liability upon theories of
    defective specifications and constructive change. (R4, tab 3) Upon denial of that
    claim, ACC appealed here and that proceeding became ASBCA No. 62265. ACC’s
    original complaint added differing site conditions and breach of the implied duty of
    good faith and fair dealing to its list of legal theories.
    On February 12, 2021, after conducting discovery, ACC submitted another
    claim to the contracting officer. The new claim alleged that the government did not
    disclose its prior knowledge that the construction project had been classified as an
    industrial site. It also alleged that the government failed to disclose it had earlier
    dealings with the relevant Virginia agency and “experienced, issues, delays, and
    problems.” (R4, tab 42 at 2977, 2986, 2991-93) Accordingly, ACC sought recovery
    under the theory of superior knowledge. That matter was also appealed to the Board
    upon denial of the claim and assigned ASBCA No. 62937. The appeals were
    consolidated and ACC filed an amended complaint on July 12, 2021.
    The government maintains that the new complaint alters certain prior allegations
    without seeking leave from the Board to do so. It also argues that a newly raised issue
    has never been presented to the contracting officer, and is therefore not within the
    Board’s jurisdiction to consider. Finally, the government generally complains that,
    rather than add its new allegations to the end of the original complaint, ACC revised,
    re-phrased, and edited the original in a manner that will unfairly require the government
    to draft an entirely new answer.
    We turn first to the altered language. The government accurately observes that
    the amended answer goes beyond simply adding superior knowledge allegations.
    Instead, it rewrites some of the allegations of the original complaint. These
    modifications strike us as a refinement by ACC of its case after performing discovery
    and further considering the evidence. The government does not argue that any of these
    changes unfairly prejudice it by, for instance, retracting key prior admissions that the
    government had been led to believe it could rely upon. Though ACC should have
    sought leave ahead of time to amend its prior allegations, the absence of demonstrated
    prejudice to the government compels the conclusion that such a request would have
    been granted. Nor are we persuaded by the government’s suggestion that it is unfair to
    expect it to perform the work of drafting an answer to the amended complaint. We are
    confident the government is up to the challenge. Accordingly, we will not strike the
    complaint because of the changes to the allegations in the first complaint.
    Turning to the government’s jurisdictional challenge, the original claim and
    complaint contained a category seeking costs arising from Virginia’s delay reviewing
    the project, the need for ACC to redesign and resubmit plans to satisfy Virginia, and
    time lost because of the postponement of project work into the cold season (R4, tab 3
    at 19-20, 25-32; compl. at 2). ACC’s second claim, premised upon a superior
    knowledge theory, adds that the government withheld vital information about the site’s
    industrial classification, as well as the difficulty of dealing with Virginia, also causing
    the review, redesign, and weather related delays (R4, tab 42 at 2986-94). However,
    ACC’s amended complaint injects still another factual basis for recovering under its
    superior knowledge theory. In addition to its allegations about the industrial site and
    difficulties with Virginia, the new complaint also alleges that the government failed to
    disclose that it had not followed standard operating procedures requiring coordination
    and design development (am. compl. at 3, ¶¶ 26, 50, 78, 127, 179). This is a new,
    separate operative factual allegation that has never been presented to the contracting
    2
    officer. ∗ When an amended complaint relies upon different operative facts than what
    was previously submitted to the contracting officer, the Board lacks jurisdiction to
    decide the un-submitted matter. See Gold Tree Techs., Inc., ASBCA Nos. 54158,
    54159, 
    05-1 BCA ¶ 32,856
     at 162,803; see also Lee’s Ford Dock, Inc., ASBCA
    No. 59041, 
    14-1 BCA ¶ 35,679
     at 174,638-41 (explaining that whether a superior
    knowledge claim is a new claim depends upon whether the operative facts described in
    the claim communicated the particular disparity of knowledge between the contractor
    and the government before award), aff’d in part and dismissed in part, 
    865 F.3d 1361
    (Fed. Cir. 2017). Because the claim related to the government’s failure to follow
    standard operating procedures is beyond the Board’s jurisdiction, it must be stricken
    from the amended complaint. See Alfajer, Ltd., ASBCA No. 62125, 
    20-1 BCA ¶ 37,660
     at 182,859 (striking allegations over which the Board does not possess
    jurisdiction). Accordingly, we grant the government’s motion to the extent that we
    strike clause (3) in the first paragraph of page 3 of the amended complaint, as well as
    paragraphs 26, 50, 78, 127, and 179.
    Dated: September 22, 2021
    MARK A. MELNICK
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    (Signatures continued)
    ∗
    If ACC had included the allegation that the government had not followed its usual
    procedures as part of its explanation of the events leading to the government’s
    failure to disclose its superior knowledge about site classification and problems
    with Virginia, we would likely have found the allegations permissible and the
    sort of information routinely uncovered during discovery that a party could be
    forgiven for not including in its claim. Here, though, ACC is alleging that the
    failure to disclose that the government did not follow its procedures is, itself, an
    instance of superior knowledge. The new allegations, supporting an entirely
    different piece of information allegedly withheld from ACC cannot be seen as a
    mere refinement of the evidence.
    3
    I concur                                         I concur
    RICHARD SHACKLEFORD                              J. REID PROUTY
    Administrative Judge                             Administrative Judge
    Acting Chairman                                  Vice Chairman
    Armed Services Board                             Armed Services Board
    of Contract Appeals                              of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA Nos. 62265, 62937, Appeals of
    ACC Construction Co., Inc., rendered in conformance with the Board’s Charter.
    Dated: September 23, 2021
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    4
    

Document Info

Docket Number: ASBCA No. 62265, 62937

Judges: Melnick

Filed Date: 9/22/2021

Precedential Status: Precedential

Modified Date: 10/6/2021