Assist Consultants Inc. ( 2021 )


Menu:
  •                 ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeals of -                                   )
    )
    Assist Consultants Inc.                        ) ASBCA Nos. 61525, 62090
    )
    Under Contract No. W912ER-18-C-0009            )
    APPEARANCES FOR THE APPELLANT:                    Lee-Ann C. Brown, Esq.
    Douglas L. Patin, Esq.
    Sabah K. Petrov, Esq.
    Bradley Arant Boult Cummings LLP
    Washington, DC
    APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.
    Engineer Chief Trial Attorney
    Rebecca L. Bockmann, Esq.
    Matthew Tilghman, Esq.
    Engineer Trial Attorneys
    U.S. Army Engineer District, Middle East
    Winchester, VA
    OPINION ON THE GOVERNMENT’S MOTION FOR RECONSIDERATION BY
    ADMINISTRATIVE JUDGE D’ALESSANDRIS
    In an opinion dated April 29, 2021, the Board denied cross-motions for summary
    judgement filed by appellant Assist Consultants, Inc. (ACI) and respondent, the United
    States Army Corps of Engineers (USACE or government). Assist Consultants, Inc.,
    ASBCA Nos. 61525, 62090, 
    21-1 BCA ¶ 37,850
    . The government timely filed a motion
    for reconsideration, alleging error in our decision “insofar as it concludes that, as a matter
    of law, a request for termination for convenience sufficiently replaces the requirement
    that a contractor who has continued performance after discovering a breach must reserve
    its rights to avoid a finding waiving its right to claim breach later” (gov’t mot. at 1). For
    the reasons stated below, the government’s motion for reconsideration is denied.
    DECISION
    A motion for reconsideration is not the place to present arguments previously
    made and rejected. “[W]here litigants have once battled for the court’s decision, they
    should neither be required, nor without good reason permitted, to battle for it again.”
    Dixon v. Shinseki, 
    741 F.3d 1367
    , 1378 (Fed. Cir. 2014) (quoting Official Comm. of the
    Unsecured Creditors of Color Tile, Inc. v. Coopers & Lybrand, LLP, 
    322 F.3d 147
    ,
    167 (2d Cir. 2003)). Moreover, “[m]otions for reconsideration do not afford litigants the
    opportunity to take a ‘second bite at the apple’ or to advance arguments that properly
    should have been presented in an earlier proceeding.” Dixon, 741 F.3d at 1378; see also
    Avant Assessment, LLC, 
    ASBCA No. 58867
    , 
    15-1 BCA ¶ 36,137
     at 176,384. On the
    other hand, if we have made mistakes in the findings of fact or conclusions of law, or by
    failing to consider an appropriate matter, reconsideration may be appropriate. See
    Robinson Quality Constructors, 
    ASBCA No. 55784
    , 
    09-2 BCA ¶ 34,171
     at 168,911;
    L&C Europa Contracting Co., 
    ASBCA No. 52617
    , 
    04-2 BCA ¶ 32,708
    . The Board
    recently summarized the standard for reconsideration stating “[i]n short, if we have
    made a genuine oversight that affects the outcome of the appeal, we will remedy it.”
    Relyant, LLC, 
    ASBCA No. 59809
    , 
    18-1 BCA ¶ 37,146
     at 180,841. Here, as in Relyant,
    no such mistakes have been identified.
    In our decision, we held that the government had satisfied its initial burden of
    demonstrating that its termination for default was justified, but denied the government’s
    motion for summary judgment, because there were material issues of fact regarding
    ACI’s affirmative defense alleging a prior material breach by the government. Assist
    Consultants, 
    21-1 BCA ¶ 37,850
     at 183,799. Under the summary judgment standard of
    review, we also denied the government’s argument that, even if its failure to disclose the
    base access restrictions to bidders could constitute a material breach, that ACI had
    waived the breach by preforming and not reserving its rights. 
    Id. at 183,810
    . We
    rejected the argument, noting that “the government’s argument completely ignores the
    fact that ACI requested a no-cost termination for convenience immediately after the
    preconstruction conference where the government announced that Afghan workers
    would not be permitted on the base.” 
    Id.
     The Board did not hold, as a matter of law,
    that a request for a termination for convenience was legally sufficient to reserve ACI’s
    right, but rather, cited the termination for convenience request as an example of a factual
    issue preventing the entry of summary judgment.
    To the extent the government argues in its motion for reconsideration that it is
    entitled to entry of judgment as a matter of law, because ACI did not identify a specific
    reservation of rights, we disagree and hold that there are material factual issues in dispute.
    The government cites selectively from 13 Williston on Contracts § 39:35 (4th ed.) for the
    proposition that ACI’s failure to expressly reserve its rights entitles the government to
    judgment as a matter of law (gov’t reply at 2). However, read in full, Williston provides:
    Mere silence, acquiescence, or inactivity is insufficient to
    show a waiver of contract rights where there is no duty to
    speak or act. But silence or inaction, coupled with
    knowledge by the party charged with a waiver that the
    contract’s terms have not been strictly met, and detrimental
    reliance by the other, for such a length of time as to
    manifest an intention to relinquish the known right may
    result in a waiver of rights under the contract.
    2
    13 RICHARD A. LORD, WILLISTON ON CONTRACTS § 39:35 (4th ed. 2013) (footnotes
    omitted).
    ACI asserts, in opposition to the government’s motion for reconsideration, that it
    did not have complete knowledge of the government’s breach until after the termination
    and subsequent discovery (app. resp. at 4-10). ACI alleges that the government misled
    ACI by stating that the USACE had received “no UAE confirmation” that there was a
    policy denying access to Afghan passport holders (id. at 8; R4, tab 13), and that the
    government’s statement was misleading because the government knew that it would not
    get confirmation from the UAE authorities and that the USACE never tried to get
    confirmation after the pre-construction meeting (app. resp. at 8). ACI’s allegations are
    supported by Mr. Amiri’s declaration and an e-mail, produced in discovery, demonstrating
    that the government was aware of a potential base access problem in June 2017, months
    before the December 2017 award at issue here (app. mtn. sum. J. ex. 2). ACI further
    points to its response to the show cause letter where ACI reported that it was “taking all
    steps to submit the required documentation to the UAE and obtain a written position from
    UAE authorities as to whether or not we will be allowed access” as proof that it did not
    yet possess full knowledge regarding the ability of its Afghan workers to access the base
    (app. resp. at 8 (quoting R4, tab 15)). The courts have held that waiver does not apply
    during a limited course of action while a party seeks more information. See, e.g., O.K.
    Sand and Gravel, Inc. v. Martin Marietta Corp., 
    819 F. Supp. 771
    , 783 (S.D. Ind. 1992)
    aff’d 
    36 F.3d 565
     (7th Cir. 1994) (single renewal of agreement after knowledge of breach
    while producer demanded more information was not ongoing acquiescence required to
    establish waiver).
    The government cites to e-mails between ACI and its legal consultant to argue
    that ACI knew on January 21, 2018, that it had a potential legal argument that the
    government had materially breached the contract (gov’t reply at 5-7). However, the
    government did not cite these documents in its summary judgment briefing, or even in
    its opening brief in this motion for reconsideration. We do not consider new arguments
    raised in a motion for reconsideration where the evidence was available to the moving
    party at the time it filed its brief. Dixon, 741 F.3d at 1378; Avant Assessment, LLC,
    
    15-1 BCA ¶ 36,137
     at 176,384. Accordingly, we continue to find that there is a
    material factual dispute regarding ACI’s knowledge. See Northern Helex Co. v. United
    States, 
    455 F.2d 546
    , 551 (Ct. Cl. 1972).
    ACI additionally notes that it never received a notice to proceed under the
    contract, and thus, alleges that contract performance had not begun such as to trigger
    the election doctrine (app. resp. at 8-9). The government disputes ACI’s interpretation,
    again citing to documents in that record that it failed to cite in its dispositive motion
    (gov’t reply at 21-24). The fact that ACI did contractual work without having received
    a notice to proceed is relevant to the waiver argument in that the reasoning behind the
    waiver provision is so that “one side cannot continue after a material breach by the
    3
    other (such as failure to pay), act as if the contract remains fully in force (although
    stopping performance would be fair and convenient), run up damages, and then go
    suddenly to court.” Northern Helex Co. v. United States, 455 F.2d at 551. Here, ACI
    could not run up damages because it was performing the work at its own risk. The
    government also fails to note how it relied to its detriment on ACI’s continued
    performance, absent a notice to proceed.
    Finally, the government’s motion seeks to treat the election requirement as
    applying the moment the contractor first becomes aware of possible breach. The
    government points to the fact that ACI performed for 23 days as evidence of a
    knowing waiver (gov’t reply at 5-13). However, as noted in the government’s reply
    brief, what is required is “reasonable promptness” (gov’t reply at 8 (quoting Supreme
    Foodservice GMBH, 
    ASBCA No. 57884
     et al., 
    16-1 BCA ¶ 36,387
     at 177,395)).
    Whether 23 days is a reasonable time is an issue requiring further factual development.
    See, e.g., TECOM, Inc., IBCA No. 2970-a-1, 
    95-2 BCA ¶ 27,607
     at 137,597 (finding
    no waiver after 4½ months of performance).
    CONCLUSION
    For the reasons stated above, the government’s motion for reconsideration is
    denied.
    Dated: October 18, 2021
    DAVID D’ALESSANDRIS
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                          I concur
    RICHARD SHACKLEFORD                               OWEN C. WILSON
    Administrative Judge                              Administrative Judge
    Acting Chairman                                   Vice Chairman
    Armed Services Board                              Armed Services Board
    of Contract Appeals                               of Contract Appeals
    4
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA Nos. 61525, 62090, Appeals of
    Assist Consultants Inc., rendered in conformance with the Board’s Charter.
    Dated: October 19, 2021
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    5
    

Document Info

Docket Number: ASBCA No. 61525, 62090

Judges: D'Alessandris

Filed Date: 10/18/2021

Precedential Status: Precedential

Modified Date: 11/3/2021