StructSure Projects, Inc. ( 2021 )


Menu:
  •                   ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of -                                )
    )
    StructSure Projects, Inc.                  )    
    ASBCA No. 62927
    )
    Under Contract No. W9127S-17-D-6004        )
    APPEARANCE FOR THE APPELLANT:                   Michael S. Alfred, Esq.
    Hallett & Perrin, P.C.
    Dallas, TX
    APPEARANCES FOR THE GOVERNMENT:                 Michael P. Goodman, Esq.
    Engineer Chief Trial Attorney
    Michael T. Geiselhart, Esq.
    Liz K. Harris, Esq.
    Engineer Trial Attorneys
    U.S. Army Engineer District, Little Rock
    OPINION BY ADMINISTRATIVE JUDGE EYESTER
    ON THE GOVERNMENT’S MOTION TO DISMISS
    StructSure Projects, Inc. (appellant or StructSure) filed an appeal alleging it is
    owed money for the government’s use of certain temporary phasing facilities and other
    services. The U.S. Army Corps of Engineers (government or USACE) has moved to
    dismiss the appeal, arguing that: (1) the notice of appeal was filed by StructSure’s
    project manager, who did not have the requisite authority to file such an appeal; and
    (2) StructSure lacks proper representation because it is represented by its subcontractor’s
    counsel who, for several reasons, has a conflict of interest. Because we find that the
    notice of appeal was filed properly and StructSure is represented by an individual who
    meets the requirements of Board Rule 15, we deny the government’s motion.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
    1. On July 14, 2017, USACE awarded multiple award task order contract
    (MATOC) No. W9127S-17-D-6004 to StructSure for design-build construction services
    (R4, tab 1 at 2-3). 1 Subsequently, on September 27, 2018, USACE issued task order
    No. W9127S-18-F-0112 to StructSure for various services, including design and
    alteration services for and temporary phasing facilities at the David Grant Medical
    1
    The MATOC was actually awarded to United Excel Corporation (R4, tab 1 at 3).
    However, on July 1, 2019, the government issued a modification changing the
    Center, Travis Air Force Base (R4, tab 2 at 46, 48-52). StructSure’s subcontractor for the
    temporary phasing facilities was Sustainable Modular Management (Sustainable
    Modular) (see R4, tab 13 at 158).
    2. In March and April of 2020, the government issued several notices to
    StructSure stating that the task order award was designated non-mission essential and
    StructSure and its subcontractors could not continue on-site construction activity until
    later notified (R4, tabs 4, 7-9). On April 29, 2020, the government informed StructSure
    that it could recommence immediately on-site construction activities (R4, tab 10 at 134).
    3. StructSure submitted a request for equitable adjustment (REA) stating that the
    temporary phasing facilities and associated rental furniture and equipment were in use by
    the government during the time the project was classified as non-mission essential and as
    such, StructSure incurred extended rental costs (R4, tab 13 at 155). The agency denied
    the REA, and StructSure next submitted a claim seeking reimbursement for the same
    costs (R4, tabs 14-18). The claim was signed by Mark Benne, a program manager for
    StructSure (R4, tab 15 at 170). The claim was later certified by C. Kevin Rogers, chief
    executive officer of StructSure (R4, tab 18 at 190). On March 30, 2021, USACE issued a
    contracting officer’s final decision (COFD) denying the claim (R4, tab 19 at 191-92).
    4. On May 14, 2021, StructSure filed a notice of appeal of the COFD with the
    Board, which was signed by StructSure’s project manager, Matt Callaway, and submitted
    on StructSure letterhead. Copies of the notice of appeal were also sent to several
    individuals, including: StructSure’s chief executive officer, president, and vice president;
    Michael S. Alfred, Esq., of Hallett and Perrin; the chief executive officer for Sustainable
    Modular; and the contracting officer. (Notice of Appeal at 1) The notice also included
    several attachments, including the COFD (id. at 4-5). Another attachment was a letter to
    Matt Callaway from Michael S. Alfred, Esq., stating that Mr. Alfred’s firm represents
    Sustainable Modular who “expresses its intent for [StructSure] to facilitate the appeal of
    the [COFD]” (id. at 2).
    5. The Board issued an Order on May 20, 2021, stating that the record did not
    identify Mr. Callaway as a corporate officer or attorney and therefore, StructSure was
    directed to show it was represented by a person meeting the requirements of Board
    Rule 15(a), or to designate a proper person as its representative. On May 26, 2021,
    Michael S. Alfred, Esq., entered a notice of appearance “as counsel for Sustainable
    Modular Management, Inc., which is prosecuting the above-referenced appeal in the
    name of Appellant, StructSure Projects, Inc.” (notice of appearance at 1). It is not
    disputed that Mr. Alfred is a duly licensed attorney in Texas.
    contractor’s name to StructSure Projects, Inc. on the MATOC and all task order
    awards (R4, tab 3 at 116).
    2
    6. On June 21, 2021, “Appellant, Sustainable Modular Management, Inc. [],
    which is prosecuting this appeal on behalf of StructSure Projects, Inc.” filed a complaint
    (compl. at 1). A footnote in the complaint stated the following: “By prosecuting this
    appeal, [Sustainable Modular] is not waiving any of its rights, claims, positions or
    remedies against [StructSure] and/or its surety, Arch Insurance Company, all of which
    are expressly reserved” (compl. at 2 n.2). The complaint’s caption stated it was the
    appeal of StructSure (compl. at 1). The complaint was signed by Michael S. Alfred of
    Hallett & Perrin, PC, as attorney for Sustainable Modular (compl. at 2).
    7. On June 23, 2021, the government filed its motion to dismiss (gov’t mot. at 1).
    8. On June 29, 2021, StructSure’s chief executive officer, Kevin Rogers, filed a
    letter with the Board stating that “Matt Callaway, Project Manager, is an authorized
    representative for StructSure Projects [and StructSure] has named Matt Callaway as an
    authorized agent for the purposes of filing claims or taking appeals on behalf of
    [StructSure]” (app. corr. ltr. dtd. June 29, 2021).
    9. In addition, in its response to the government’s motion, Michael S. Alfred, Esq.,
    clarified that Sustainable Modular “is pursuing this appeal in the name of [StructSure]” as
    permitted by the subcontract between the two companies. Mr. Alfred also stated that as
    “the undersigned counsel [he] is representing [StructSure] for purposes of this appeal
    based on the waiver of a conflict of interest set forth” in the subcontract. As such,
    Mr. Alfred states that because he represents StructSure in “this narrow and limited
    situation,” Sustainable Modular has not waived any of its rights against StructSure or the
    surety for monies that may be owed under the subcontract. (App. resp. at 1)
    10. The Board finds that Matt Callaway was authorized to file the notice of appeal
    on behalf of StructSure and that Mr. Alfred, a licensed attorney, represents StructSure in
    this matter.
    DECISION
    Authority to File Appeal
    The government contends that Mr. Callaway, as the project manager for
    StructSure, did not have authority to file an appeal on behalf of the company at the time
    the appeal was filed and therefore, the Board lacks jurisdiction over the appeal (gov’t
    reply at 3-4). As support, the government argues that since Mr. Callaway did not submit
    the claim to the agency, and was not authorized as an agent of StructSure until after the
    3
    appeal was filed, he did not have authority to pursue the timely filed appeal at the Board
    (gov’t reply at 4).
    The Contract Disputes Act states that a contractor--a party to a Federal
    government contract--may appeal a COFD to the Board. 
    41 U.S.C. §§ 7101
    (7), 7104(a).
    To take an appeal, an appellant (contractor) must file a notice of appeal with the Board
    within 90 days from the date of receipt of the COFD. Board Rule 1(a). We have
    previously held that an authorized representative or agent may file a notice of appeal on
    behalf of a contractor. See, e.g., Left Hand Design Corp., 
    ASBCA No. 62458
    , 
    21-1 BCA ¶ 37,916
     at 184,142-43 (holding that an administrative assistant was acting as an
    authorized agent on behalf of the contractor when she filed the appeal); Garrison
    Engineers Constr., Inc., NW Mech., Inc., ASBCA Nos. 29015, 29536, 
    85-1 BCA ¶ 17,731
     at 88,514.
    Matt Callaway was authorized to file the notice of appeal on behalf of StructSure
    (SOF ¶ 10). In this case, it is irrelevant that StructSure’s chief executive officer notified
    the Board that Mr. Callaway was an authorized representative after the notice was filed
    because the notification serves as a clear indication that Mr. Callaway was acting on
    appellant’s behalf at the time the appeal was filed. In other words, and to state the
    obvious, if the chief executive officer of StructSure did not believe Mr. Callaway should
    have filed the notice of appeal, he would have said so in the correspondence with the
    Board rather than specifically name Mr. Callaway as an authorized agent to take appeals
    on behalf of the company.
    Representation of Appellant
    The government also contends that, to the extent Mr. Alfred has clarified he
    represents StructSure in this matter, Mr. Alfred is not a “proper” representative due to
    conflicts of interest (gov’t reply at 1-3). 2 According to the government, Mr. Alfred also
    represents Sustainable Modular, who has sued StructSure’s surety in the Eastern District
    Court of California on these exact claims. The government argues that the surety would
    only be liable if StructSure has wrongfully failed to pay. (Id. at 2) Further, according to
    the government, since Sustainable Modular states it is not waiving any rights against
    StructSure or its surety, it is not proper for Mr. Alfred to represent both the subcontractor
    and prime contractor here (gov’t reply at 2; gov’t mot. at 5).
    Board Rule 15(a) states that a corporation may be represented by one of its
    officers or a licensed attorney. There is no dispute that Mr. Alfred, a licensed attorney,
    2
    The government initially argued that StructSure was not represented by a corporate
    officer or licensed attorney as required by Board Rule 15(a) (gov’t mot. at 1).
    Mr. Alfred, a licensed attorney, clarified that he represents StructSure (SOF ¶ 9),
    and the government subsequently amended its argument.
    4
    represents StructSure in this matter (SOF ¶ 10). Although the government argues the
    appeal should be dismissed for lack of proper representation due to a conflict of interest,
    we interpret the government’s contention as an attempt to have Mr. Alfred disqualified as
    appellant’s attorney, thereby creating a Board Rule 15(a) compliance conundrum. 3
    The Board has entertained motions to disqualify counsel before as the discretion to
    regulate attorney conduct is inherent in our judicial capacity. Asahi Gen. Trading &
    Cont. Co. W.L.L., 
    ASBCA No. 62445
    , 
    21-1 BCA ¶ 37,767
     at 183,323. For example, “[i]f
    a conflict of interest resulting in demonstrable bias is shown to exist, it may have an
    effect on the proceeding.” AEC Corp., 
    ASBCA No. 42920
    , 
    95-2 BCA ¶ 27,750
    at 138,354. The moving party bears the burden of proving that we should disqualify
    counsel and the issue is resolved based upon the established record and parties’
    submissions. Asahi General Trading & Cont. Co. W.L.L., 
    21-1 BCA ¶ 37,767
    at 183,323.
    As the government has acknowledged, sponsorship by a prime contractor of a
    subcontractor’s claim has long been allowed by the Board, approved by the Federal
    Circuit, and is expressly permitted by regulation. TPS, Inc., 
    ASBCA No. 52421
    , 
    01-1 BCA ¶ 31,375
     at 154,917; Federal Acquisition Regulation 44.203(c). However, the
    government believes that this appeal is somehow different in that if the appeal fails, the
    prime contractor may ultimately owe the subcontractor, and there has been no express
    waiver of the conflict (gov’t reply at 3). The government has not shown how any of this
    will prejudice the government in defending its case or affect the current proceeding, nor
    has it specifically identified any statute, regulation, case law, or code of professional
    responsibility to support its position.
    At this time, both StructSure and Sustainable Modular maintain the same position-
    -that the government owes StructSure the rental costs associated with the use of
    temporary phasing facilities, rental furniture and equipment during the time the project
    was classified as non-mission essential. Therefore, on this record, we are unable to
    conclude that any of the alleged adverse interests would create a conflict of interest in
    counsel representing both companies as to essentially require disqualification of
    StructSure’s counsel. See AEC Corp., 
    95-2 BCA ¶ 27,750
     at 138,354. Further, as
    Mr. Alfred, an attorney at law, has confirmed to the Board that he represents StructSure
    for purposes of this appeal, and StructSure itself has not alleged there is any conflict of
    interest, we will not require StructSure to expressly waive any perceived conflict.
    3
    In this regard, it is not clear why, even if there were an issue with representation, the
    Board would not first provide an opportunity for StructSure to obtain a new
    representative and file a new notice of appearance.
    5
    CONCLUSION
    For the foregoing reasons, the government’s motion is denied.
    Dated: December 2, 2021
    LAURA EYESTER
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                         I concur
    RICHARD SHACKLEFORD                              OWEN C. WILSON
    Administrative Judge                             Administrative Judge
    Acting Chairman                                  Vice Chairman
    Armed Services Board                             Armed Services Board
    of Contract Appeals                              of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 62927
    , Appeal of StructSure
    Projects, Inc., rendered in conformance with the Board’s Charter.
    Dated: December 2, 2021
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    6
    

Document Info

Docket Number: ASBCA No. 62927

Judges: Eyester

Filed Date: 12/2/2021

Precedential Status: Precedential

Modified Date: 12/21/2021