Environmental Safety Consultants, Inc. ( 2014 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                  )
    )
    Environmental Safety Consultants, Inc.        )      
    ASBCA No. 58343
    )
    Under Contract No. N62470-95-B-2399           )
    APPEARANCE FOR THE APPELLANT:                        Mr. Peter C. Nwogu
    President
    APPEARANCES FOR THE GOVERNMENT:                      Ronald J. Borro, Esq.
    Navy Chief Trial Attorney
    Ellen M. Evans, Esq.
    Senior Trial Attorney
    OPINION BY ADMINISTRATIVE JUDGE FREEMAN ON APPELLANT'S
    MOTION FOR PARTIAL SUMMARY JUDGMENT
    Environmental Safety Consultants, Inc. (ESCI) moves for partial summary
    judgment on its appeal of the contracting officer's deemed denial of its termination for
    convenience settlement claim under the captioned contract. ESCI contends that there
    is no genuine issue of material fact that it is entitled to immediate payment of
    (i) $68,230.50 for "work that was completed and accepted at contract price," and
    (ii) $199,950.00 for "settled constructive changes, extensive delays and overheads"
    (mot. at 1-2). The government opposes on the grounds that there is no legal authority
    under the termination for convenience clause for recovery of "selected prices in the
    last invoice and the last modification issued before the termination" (opp'n at 1). We
    agree with the government and deny the motion.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
    1. This appeal arises out of our decision converting the government's
    termination of the captioned contract (hereinafter "Contract 2399") for default to a
    termination for the government's convenience. Environmental Safety Consultants,
    Inc., 
    ASBCA No. 51722
    , 11-2 BCA i! 34,848. 1 We have also addressed, more
    recently, a jurisdictional issue with respect to the total amount ofESCI's termination
    settlement claim. Environmental Safety Consultants, Inc., 
    ASBCA No. 58343
    , slip op.
    (25 July 2014). Familiarity with these decisions is assumed.
    1
    All Rule 4 citations refer to the Rule 4 filed in 
    ASBCA No. 51722
    .
    2. Pursuant to paragraph (c) of the FAR 52.249-10, DEFAULT (FIXED-PRICE
    CONSTRUCTION) (APR 1984) clause of the contract, and as a result of our decision
    sustaining the appeal from the default termination, "the rights and obligations of the
    parties will be the same as ifthe termination had been issued for the convenience of
    the Government" (R4, tab 1 at 69).
    3. The FAR 52.249-2, TERMINATION FOR CONVENIENCE OF THE GOVERNMENT
    (FIXED-PRICE) (APR 1984)-ALTERNATE I clause in Contract 2399 states in pertinent
    part:
    (d) After termination, the Contractor shall submit a
    final termination settlement proposal to the Contracting
    Officer in the form and with the certification prescribed by
    the Contracting Officer ....
    (e) Subject to paragraph (d) above, the Contractor
    and the Contracting Officer may agree upon the whole or
    any part of the amount to be paid because of the
    termination .... However, the agreed amount, whether
    under this paragraph (e) or paragraph (t) below, exclusive
    of costs shown in subparagraph (t)(3) below, may not
    exceed the total contract price as reduced by ( 1) the
    amount of payments previously made and (2) the contract
    price of work not terminated ....
    (t) If the Contractor and Contracting Officer fail to
    agree on the amount to be paid the Contractor because of
    the termination of work, the Contracting Officer shall pay
    the Contractor the amounts determined as follows, but
    without duplication of any amounts agreed upon under
    paragraph (e) above:
    ( 1) For work performed before the effective date of
    termination, the total (without duplication of any items) of-
    (i) The cost of this work;
    (ii) The cost of settling and paying termination
    settlement proposals under terminated subcontracts that are
    properly chargeable to the terminated portion of the
    contract, if not included in subdivision ( i) above; and
    2
    (iii) A sum, as profit on (i) above, determined by
    the Contracting Officer under 49.202 of the Federal
    Acquisition Regulation, in effect on the date of this
    contract, to be fair and reasonable; however, if it appears
    that the Contractor would have sustained a loss on the
    entire contract had it been completed, the Contracting
    Officer shall allow no profit under this subdivision (iii) and
    shall reduce the settlement to reflect the indicated rate of
    loss.
    4. On 5 July 2012, ESCI submitted its termination settlement proposal to the
    contracting officer for a "net proposed settlement" of$1,183,366.59. On
    14 September 2012, it submitted that proposal to the contracting officer as a certified
    claim under the Contract Disputes Act of 1978 (CDA), 
    41 U.S.C. §§ 7101-7109
     (app.
    supp. R4, vol. I, tab 3 at 1-4, tab 5 at 1-2). The contracting officer refused to either
    negotiate a settlement or issue a final decision on the termination settlement claim
    (answer ii 8). On 29 September 2012, ESCI appealed the deemed denial of the claim.
    The appeal was docketed as 
    ASBCA No. 58343
    .
    5. ESCI's motion for partial summary judgment on its termination settlement
    claim has two parts. First, it claims that:
    [T]here are no genuine issues of material fact as to whether
    appellant is entitled to payment of the amount of $68,230.50.
    This amount represents the compensation for completed,
    verified and accepted work at contract price before
    government's termination on June 12, 1998. This amount
    for payment is presented in Table 1.0 - Compensation for
    completed, verified and accepted by the Government on
    June 24, 1997 ....
    (Mot. at 1)
    6. Table 1 is a listing of the progress payment estimates in Invoice No. 7 for
    some, but not all, of the items of work, required to perform Bid Item OOOlA (mot. at
    20-23; R4, tab 14 at 3-16). 2 Bid Item OOOlA was a $358,754 lump sum fixed-price
    2
    Invoice No. 7 for a total progress payment of $138,506.50 was returned to ESCI
    unpaid by the contracting officer in June 1997 on the ground that it contained
    an "invalid" certification. ESCI did not thereafter submit a timely CDA claim
    for payment of the invoice. See Environmental Safety Consultants, Inc.,
    
    ASBCA No. 58847
    , 14-1BCAii35,510, and 
    ASBCA No. 54615
    , 07-1 BCA
    ii 33,483 at 165,984.
    3
    item for ''the entire work, complete in accordance with the drawings and
    specifications, but excluding work described in Bid Items OOOlB, OOOlC, OOOlD,
    OOOlE and OOOlF." As of the date the contract was terminated (12 June 1998), Bid
    Item OOOlA had not been completed. The work items in Table 1 ofESCI's motion
    were part of the Bid Item OOOlA work, but none of those items were separately priced
    in the contract Schedule. (R4, tab 1 at 16, 29-30)
    7. The progress payment estimates for the work items in Invoice No. 7 and in
    Table 1 ofESCI's motion are not based on the actual incurred costs of performing the
    work item. They are based on portions of the Bid Item price assigned to the work item
    by the contractor after award of the contract pursuant to paragraph (b) of the
    FAR 52.232-5, PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS
    (APR 1989) clause of the contract. (R4, tab 1 at 68, 70) Paragraph (b) states in
    pertinent part:
    The Government shall make progress payments monthly as
    the work proceeds, or at more frequent intervals as
    determined by the Contracting Officer, on estimates of
    work accomplished .... The Contractor shall furnish a
    breakdown of the total contract price showing the amount
    included therein for each principal category of the work,
    which shall substantiate the payment amount requested in
    order to provide a basis for determining progress
    payments.
    (R4, tab 1 at 70)
    8. Progress payments under paragraph (b) are not final payments accepting the
    work for which they are paid. The FAR 52.232-27, PROMPT PAYMENT FOR
    CONSTRUCTION CONTRACTS (MAR 1994) clause of Contract 2399 makes a clear
    distinction in this regard between progress payments and final payments as follows:
    Notwithstanding any other payment terms in this
    contract, the Government will make invoice payments and
    contract financing payments under the terms and
    conditions specified in this clause ....
    (a) Invoice Payments. (1) For purposes of this
    clause, there are several types of invoice payments which
    may occur under this contract, as follows:
    (i) Progress payments, if provided for elsewhere in
    this contract, based on Contracting Officer approval of the
    4
    I
    estimated amount and value of work or services performed,
    including payments for reaching milestones in any project:
    (ii) Final payments based on completion and
    acceptance of all work and presentation of release of all
    claims against the Government arising by virtue of the
    contract, and payments for partial deliveries that have been
    accepted by the Government (e.g., each separate building,
    public work, or other division of the contract for which the
    price is stated separately in the contract) ....
    (R4, tab 1 at 79)
    9. The second part of ESCI' s motion for partial summary judgment is a claim
    that: "Appellant is entitled to payment of $199,301, arising from the settlement
    agreement of equitable adjustment through contract modification of June 23/24, 1997
    presented in Table 2" (mot. at 2). The contract modification to which ESCI refers is
    bilateral Modification No. P00006, signed by Peter Nwogu on 23 June 1997 for ESCI
    and by the contracting officer on 24 June 1997 for the government. Modification
    No. P00006 provided for various additions and deletions to the specified work. The
    additional work items included among others:
    j. Subcontract all remaining work, including supervision,
    quality control, and punchlist items.
    k. Provide additional overhead costs incurred due to
    subcontracting.
    n. Provide extended overhead for the Government delays
    under this contract.
    (R4, tab 2 at 11-12)
    10. Modification No. P00006 concluded with a summary of the agreed price
    adjustment and contract completion date for the additions and deletions of work and a
    general release as follows:
    2. TOTAL AMOUNT OF ADDITIONAL WORK                      $199,301.00
    TOTAL AMOUNT OF CREDITS                              $199, 192.00
    5
    The total contract price is increased by $109 .00 from
    $561,764.25 to $561,873.25.
    The contract completion date is extended by 308 calendar
    days from August 26, 1996, to June 30, 1997.
    The foregoing is agreed to as constituting full and
    equitable adjustment and compensation (both time and
    money) attributable to the facts of [sic] circumstances
    giving rise to the change directed hereby, including, but
    not limited to, any changes, differing site conditions,
    suspensions, delays, rescheduling, accelerations, impact, or
    other causes as may be associated therewith.
    (R4, tab 2 at 12)
    DECISION
    ESCI' s termination settlement claim, including the two items in its motion for
    partial summary judgment, is based on its prices for the terminated work and not its
    incurred cost. As such, it is a claim for breach of contract damages (a disappointed
    expectancy in not receiving the full contract price). But there has been no breach. The
    parties agreed in Contract 2399 that if the contract was terminated for default and if     f
    the contractor was subsequently determined not to have been in default, "the rights and
    obligations of the parties will be the same as ifthe termination had been issued for the
    convenience of the Government" (see SOF ~ 2).
    It is not disputed that Bid Item OOOlA was not completed when the contract was
    terminated and accordingly the lump sum fixed-price for that item was not due (see
    SOF ~ 6). It is not disputed that the individual work items in Bid Item OOOlA, agreed
    to by the parties for purposes of progress payments, were not separately priced items
    in the contract Schedule, and were accordingly part of the terminated work (id.). In
    these circumstances, and since the parties did not conclude a termination settlement
    amount agreement (see SOF ~ 4), paragraph (t)(l) of the Termination for Convenience
    clause of the contract provided for the contracting officer to determine the settlement
    amount on the basis of the cost of the terminated work up to the time it was terminated
    and a reasonable profit on that cost. The clause did not provide for determination of a
    settlement amount on the basis of a portion of the contract price of the terminated
    work derived from the progress payment estimates (see SOF ~ 3). Accordingly, we
    find no basis for including ESCI's claim for $68,230.50 of progress payment estimates
    in Table 1 as actual incurred costs in the termination settlement determination.
    6
    We also find no basis in the Termination for Convenience clause for including
    the agreed increased price of $199,301 in Modification No. P00006 for changes and
    delays in the work, as an incurred cost of the terminated work. The agreed price in
    bilateral Modification No. P00006 of $199,301 for government-responsible changes
    and delays in the work was offset in the same modification by an agreed amount of
    $199, 192 for price credits due the government for deleted items of work. The net
    increase in price agreed by the parties in Modification No. P00006 was $109 (see SOF
    ir 10). However, the increased price of $109 is no proof by itself of the amount of any
    cost incurred by ESCI.
    The motion for partial summary judgment is denied.
    Dated: 13 August 2014
    MONROE E. FREEMAN, JR.
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                         I concur
    ~#
    Administrative Judge                            Administrative Judge
    Acting Chairman                                 Vice Chairman
    Armed Services Board                            Armed Services Board
    of Contract Appeals                             of Contract Appeals
    7
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 58343
    , Appeal of
    Environmental Safety Consultants, Inc., rendered in conformance with the Board's
    Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    8
    1
    l
    

Document Info

Docket Number: ASBCA No. 58343

Judges: Freeman

Filed Date: 8/13/2014

Precedential Status: Precedential

Modified Date: 10/30/2014