Lee's Ford Dock, Inc. ( 2014 )


Menu:
  •                 ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                        )
    )
    Lee's Ford Dock, Inc.                               )      
    ASBCA No. 59041
    )
    Under Contract No. DACW62-1-00-0105                 )
    APPEARANCES FOR THE APPELLANT:                             Alan I. Saltman, Esq.
    Evangelin L. Nichols, Esq.
    Smith, Currie & Hancock LLP
    Washington, DC
    Karl F. Dix, Jr., Esq.
    Smith, Currie & Hancock LLP
    Atlanta, GA
    APPEARANCES FOR THE GOVERNMENT:                            Thomas H. Gourlay, Jr., Esq.
    Engineer Chief Trial Attorney
    Thomas M. Browder III, Esq.
    Engineer Trial Attorney
    U.S. Army Engineer District,
    Nashville
    OPINION BY ADMINISTRATIVE JUDGE CLARKE ON THE
    GOVERNMENT'S MOTION TO DISMISS
    The United States Army Corps of Engineers (COE) moves to dismiss this appeal ,
    alleging that Lee's Ford Dock, Inc. (Lee's Ford) raised a new claim for the first time on
    appeal, failed to certify the new claim, and filed the claim more than six years after
    accrual. We have jurisdiction pursuant to the Disputes clause of the lease at issue and the
    Contract Disputes Act of 1978 (CDA), 
    41 U.S.C. §§ 7101-7109
    . We grant the motion on
    the first basis.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION 1
    1. The COE and Lee's Ford entered into Lease No. DACW62-1-00-0105 on
    29 August 2000 for a commercial concession (marina) at Wolf Creek Dam-Lake
    Cumberland project, Kentucky, commencing on 1 September 2000 and lasting
    1
    The COE's motion includes numerous other facts relating to bankruptcy and other
    matters that are not relevant to the central issue in the motion for the Board to
    decide.
    25 years (R4, tab 3 at 1, 17). Paragraph 32 of the lease, the Disputes clause, stated
    that, except as provided in the CDA, all disputes arising under or related to the lease
    were to be resolved under this clause and the provisions of the CDA. The Disputes
    clause provided that claims were to be submitted to the district engineer. The district
    engineer's decision was to be final unless the lessee appealed as provided in the CDA.
    See 
    41 U.S.C. § 7104
    . Claims over $100,000 required certification. (Id. at 14-15)
    2. The lease provided that the United States had the right "to manipulate the
    level of the lake or pool in any manner whatsoever ... and the lessee shall have no claim
    for damages on account thereof against the United States" (R4, tab 3 at 6). On
    19 January 2007 the COE decided that the dam was at high risk of failure and
    emergency measures were necessary "to reduce imminent risk of human life, health,
    property, and severe economic loss" (R4, tab 15 at 1). The COE concluded that it
    would incrementally lower the "pool" to elevation 680 to achieve maximum risk
    reduction while continuing hydropower and water supply operations (id.).
    3. On 12 July 2007, as a result of lowering the water level in the "pool," the
    COE reduced rent payments to one dollar for the period 1 July 2007 through 30 June
    2008 (R4, tab 7). Regular rents were reinstated on 1 July 2008 (gov't mot. at 4, ~ 15).
    4. On 18 January 2013, Lee's Ford's attorney emailed a claim to the COE's
    district engineer and on 19 January 2013 a copy of the claim was placed in the
    U.S. mail (gov't mot. at 4, ~ 18; app. opp'n at 2, ~ 18). The claim includes the
    following:
    As discussed below, Lee's Ford asserts that the very
    purpose of the Lease contract has been frustrated by the
    now six-year drawdown of Lake Cumberland caused by
    the Corps' decision to lower the Lake on January 19, 2007.
    As a result, Lee's Ford demands that the Lease contract be
    reformed in one or more of the following ways to
    compensate Lee's Ford for the damages it has incurred due
    to the drawdown: (a) rent owed by Lee's Ford to the
    Corps under the Lease should be fully abated until such
    time as the abated rent equals at least $4,000,000.00, which
    is the amount of Lee's Ford's disaster loan debt to the
    U.S. Small Business Administration ("SBA"); (b) the
    Corps will pay the SBA the sum of $4,000,000.00, plus all
    accrued interest and loan fees, in satisfaction of Lee's
    Ford's disaster loan debt to neutralize the detrimental
    effect that the frustrated contract continues to have on
    Lee's Ford; and/or (c) the Corps will commit to working
    with the SBA to develop a federal government policy that
    2
    would allow the SBA to hold the disaster loan debt fully
    satisfied by offsetting Lee's Ford's damages arising out of
    its frustrated Lease against its disaster loan debt under the
    unitary creditor doctrine.
    B. THE LOWERING OF LAKE CUMBERLAND
    As you are aware, Lake Cumberland is dammed by Wolf
    Creek Dam. On January 19, 2007, LTC Steven J. Roemhildt
    and Brigadier General Bruce A. Berwick signed the
    Memorandum for Record on the subject of "Wolf Creek Dam
    Interim Risk Reduction Measures" (the "January 19th Memo"),
    which discussed concerns with the possible failure of
    Wolf Creek Dam and the need to repair it. The January 19th
    Memo concluded that the Lake must be substantially lowered
    in order to accomplish the necessary repairs. Recognizing the
    impacts of the lowering on the Lake region, the Memo
    provided that "[p]lans are being developed to mitigate to the
    maximum extent possible those impacts." Memo, p. 14. The
    Memo also included a commitment that the "Nashville District
    [of the Corps] will work with Lake Cumberland stakeholders to
    minimize to the extent practicable the impact to recreation,"
    which was said to include the "relocation of marinas" and the
    "relaxation of user fees." 
    Id. at 15
    . On January 22, 2007, the
    Corps began to lower the Lake water levels by a total of
    43 feet.
    As the District Engineer for the Nashville District of the
    Corps, Lee's Ford is submitting this letter to you to
    formally assert its "claim" against the Corps and to
    demand reformation of the frustrated Lease contract in
    such a manner as to compensate Lee's Ford for the
    damages it has incurred as a result of the drawdown
    through payment, the adjustment of Lease terms, and/or
    similar relief relating to the Lease ....
    As the lessee under the Lease, Lee's Ford expected to
    have a certain water level at its dock and the business
    3
    traffic that has historically followed that water level.
    While the Lease does contemplate that the Corps has the
    right "to manipulate the level of the lake or pool," the
    parties could not have envisioned at the time that they
    entered into the Lease that the Lake would be drawn down
    to such an extreme degree for such a long period of time,
    as the Lake has only been lowered to 680' once in its more
    than fifty year history. Instead, all that the parties could
    have anticipated was perhaps a short-term drawn [sic]
    down for repairs to the Dam - not a seven-year term of
    drastically lowered levels that required Lee's Ford to
    relocate its entire dock system within the leased area.
    [Footnotes omitted]
    (R4, tab 8 at 1, 2, 5) The claim included other facts relating to SBA involvement
    (id. at 2) and COE actions following the lowering of the lake (id. at 3).
    5. By a 26 August 2013 final decision, signed by both the district engineer and
    the contracting officer (CO), sent by certified mail, the COE denied the claim (R4, tab
    2). Lee's Ford received the final decision on 29 August 2013 (Bd. corr. file). On
    27 November 2013, Lee's Ford timely appealed the final decision to the Board
    (R4, tab 1 at 1). Lee's Ford's complaint, filed with its appeal, included one count,
    Breach of Contract-Nondisclosure of Superior Knowledge, and itemized alleged
    breach damages of $5,755,212.
    6. On 2 December 2013, the Board docketed the appeal as 
    ASBCA No. 59041
    .
    7. On 5 February 2014, the COE filed its motion to "dismiss appellant's
    complaint," which it referred to in the body of the motion as one to dismiss the appeal.
    We treat the motion as one to strike the complaint. The COE contends that the claim
    for "nondisclosure of superior knowledge was raised for the first time on appeal" and
    was "never presented to the [CO] for decision as required by the CDA." (Gov't mot.
    at 7, `` 34, 35)
    8. On 21March2014, Lee's Ford filed its opposition to the COE's motion. On
    29 April 2014, the COE notified the Board that it had decided not to file a reply to the
    opposition.
    4
    DECISION
    Initial Jurisdictional Considerations
    The leases's Disputes clause invokes the CDA. Parties cannot, by contractual
    agreement, confer CDA jurisdiction upon the Board if CDA jurisdiction does not
    otherwise exist. See Florida Power & Light Co. v. United States, 
    307 F.3d 1364
    , 1371
    (Fed. Cir. 2002); Patriot Pride Jewelry, LLC, 
    ASBCA No. 58953
    , 2014 ASBCA Lexis
    at *15 (9 June 2014). However, the Board has jurisdiction to entertain this appeal
    under the Disputes clause alone, which incorporates procedures for appeal to the
    Board. See, e.g., Donald M Lake, dlbla Shady Cove Resort & Marina, 
    ASBCA No. 54422
    , 05-1BCA~32,920. We also have jurisdiction under the CDA because a
    lease involves the disposal of personal property within the CDA's coverage.
    
    41 U.S.C. § 7102
    (a)(4); Arnold V. Hedberg, ASBCA Nos. 31747, 31748, 90-1 BCA
    ~ 22,577; accord New London Development Corp., 
    ASBCA No. 54535
    , 05-2 BCA
    ~ 33,018; see also Forman v. United States, 
    767 F.2d 875
     (Fed. Cir. 1985).
    Jurisdictional Dispute at Issue
    Both parties correctly recognize that whether the complaint asserts a new claim
    or not depends, in part, on if it relies on the same "operative facts" cited in the claim.
    The alleged new claim in this case is failure to disclose superior knowledge.
    The elements of proof of superior knowledge are:
    ( 1) a contractor undertakes to perform without vital
    knowledge of a fact that affects performance costs or
    duration, (2) the government was aware the contractor had
    no knowledge of and had no reason to obtain such
    information, (3) any contract specification supplied misled
    the contractor or did not put it on notice to inquire, and (4)
    the government failed to provide the relevant information.
    Scott Timber Co. v. United States, 
    692 F.3d 1365
    , 1373 (Fed. Cir. 2012). As reflected
    in these elements of proof, the "operative facts'' alleged in the claim must somehow
    communicate to the CO a disparity in knowledge between the parties at contract award
    of which the government was aware. The theory of superior knowledge is unique in
    that it normally relies on "operative facts" in existence before award. Grumman
    Aerospace Corp. v. Wynne, 
    497 F.3d 1350
    , 1357 (Fed. Cir. 2007) (addressing Board's
    determinations about the contractor's knowledge during "pre-award period" and "vital
    knowledge or the opportunity to obtain that knowledge before contract entry"
    (emphasis added); Bannum, Inc. v. United States, 
    80 Fed. Cl. 239
    , 247 (2008) (A
    superior knowledge claim ordinarily relates to knowledge regarding contractual
    5
    specifications that the government failed to impart to a contractor prior to the
    contractor's agreement to undertake performance of a contract); Renda Marine, Inc.
    v. United States, 
    66 Fed. Cl. 639
    , 721 (2005) ('"When analyzing a claim that the
    government breached its duty to disclose superior knowledge, "(t]he court ... must focus
    its inquiry on the government's knowledge at the time of contracting and its
    relationship to the contractor's lack of knowledge)"' (citations omitted). It is the
    pre-award disparity in knowledge that distinguishes the operative facts pertinent to
    superior knowledge allegations from those of other cases of action.
    In Todd Pacific Shipyards Corp., 
    ASBCA No. 55126
    , 06-2 BCA ii 33,421, cited
    by appellant, the contract involved work related to maintenance of U.S. Navy vessels.
    In order to perform the contract Todd had to maintain a large dry dock. After award
    the Navy transferred several of the vessels and decommissioned another resulting in
    less work for Todd. Todd's 18 June 2004 certified claim referred to its 5 March 2004
    "Drydock No. 3 Settlement Proposal" that alleged the following operative facts:
    Todd stated that, upon concluding contract negotiations in
    June, 2001, it had undertaken a five-year repair and
    maintenance project to ensure that dry dock No. 3 would
    remain certified and ready to support all scheduled and
    potential ASBCA No. 55805
    , 08-2 BCA ~ 33,950 (ATTL), which involved a 21September2002
    COE delivery order contract with a small business for sampling and testing dredged
    material. After award A TTL submitted its "initial demonstration of capability data" and
    "standard operating procedures" on 21 February 2003, 5 September 2003, 30 December
    2003, and 18 June 2004 to the Environmental Protection Agency (EPA) for approval. On
    12 August 2004 the EPA found the last submission deficient, as it had all of the previous
    submissions. As a result, the COE decided not to order more than the contract's
    minimum quantity of $5,000 worth of work. ATTL submitted a claim alleging
    constructive change based on a 29 October 2002 letter and the EPA's "improper"
    rejection of its submissions. During discovery ATTL obtained a memorandum written by
    Ms. Beth Nash on 4 December 2001, before contract award, which stated the contract
    should not be a Small Business set-aside, because the contract required a high degree of
    precision and would be difficult for a small business to perform. A TTL also obtained a
    December 2001 memorandum written by Mr. John Hartmann agreeing with Ms. Nash.
    A TTL moved to amend its complaint to allege a superior knowledge cause of action. The
    Board held, "[a]ppellant's original claim alleged operative facts limited to two theories of
    recovery - the government changed the contract and the EPA review of appellant's
    submittals was faulty." Advanced Technologies, 08-2 BCA ~ 33,950 at 167,975. The
    Board held, "[w ]e do not have jurisdiction to the extent that the underlying bases for the
    superior knowledge and commercial impracticability theories are the information in the
    Discovery Documents (i.e., a small business would find it difficult to complete the
    contract)". 
    Id.
     The operative facts in the claim related to a 29 October 2002 letter and
    EPA rejections of ATTL's submissions on 21February2003, 5 September 2003,
    30 December 2003, and 18 June 2004. It is significant that all of the operative facts
    alleged in the claim were well after the 21 September 2002 award of the contract. Again,
    the theory of superior knowledge requires an allegation of operative facts occurring in the
    pre-award period.
    7
    Shams Engineering & Contracting Co. and Ramli Co., ASBCA Nos. 50618,
    50619, 98-2 BCA ii 30,019, involved a United States Agency for International
    Development (USAID) contract to construct residential buildings in Gaza. Shams
    submitted claims alleging "unfair settlement of claims submitted to USAID," "extra
    difficulties which cost us more than ABB SUSA on purchasing materials from Israel
    because of the [border] closure" and "delay of paying the amount of Claims on time
    'interest' as per FAR (Clause 52.233-1)." Shams, 98-2 BCA ii 30,019 at 148,523.
    Appellant appealed the final decision denying the claims and then moved to amend its
    complaint to add six counts. Count 2 was breach of the duty to disclose superior
    knowledge. The Board held:
    In Count 2, appellants contend that USAID
    breached its duty to disclose information vital for
    appellants' performance under the contracts, and that it
    knew or should have known that appellants did not possess
    the information. That information allegedly included
    (a) the volatile political and economic conditions in the
    region, which USAID should have anticipated, (b) the
    terms of the contract written in a language understandable
    to appellants and the physical inclusion of FAR provisions
    rather than their incorporation by reference into the
    contract, and (c) the business and accounting standards to
    which USAID would hold appellants. Those contentions
    are essentially different than those presented to the
    contracting officer in appellants' claims seeking equitable
    adjustments. With respect to Count 2, appellants' motion
    to amend is denied.
    Shams, 98-2 BCA ii 30,019 at 148,526. As before, it is significant that none of the
    operative facts cited in the claim involved facts reflecting a disparity of knowledge
    between the government and the contractors before award.
    Court of Federal Claims cases in this area are also instructive. For example, in
    Laidlaw Environmental Services (GS), Inc. v. United States, 
    43 Fed. Cl. 44
     (1999), which
    involved a waste disposal (magnesium batteries) contract, the parties filed cross-motions for
    summary judgment and the government filed a motion to dismiss for lack of jurisdiction.
    The motion to dismiss alleged that Laidlaw raised three theories of entitlement in its
    complaint that were not presented in its claim to the CO, including superior knowledge:
    As noted supra, the complaint in this court asserts three
    basic theories of liability, i.e., i) breach of contract, ii)
    constructive change, and iii) failure to disclose superior
    8
    knowledge. In contrast, the claim previously filed before
    the contracting officer asserted, in essence, that-i) CLIN
    0502 cannot be used on the contract because it is for state
    regulated batteries only; ii) the tests indicating the toxicity
    of magnesium batteries are disputable; iii) magnesium
    batteries are not regulated in North Carolina; iv) the use of
    CLIN 0502 in the contract was erroneous; and v) such use
    constituted a change in the contract.
    Laidlaw, 43 Fed. Cl. at 50. The operative facts supporting the claim were:
    i) The state of North Carolina does not regulate
    magnesium batteries so that the use of CLIN 0502 was
    erroneous;
    ii) The basis of the tests finding the magnesium batteries to
    be hazardous is disputable;
    iii) The government changed the terms of the contract
    when it informed Laidlaw it would use CLIN 0500 or
    CLIN 0502 in delivery orders because magnesium
    batteries exhibited '"toxicity characteristics for
    chromium" making them a RCRA regulated waste;
    iv) CLIN 0502 cannot be used on the contract because it is for
    state regulated batteries only and magnesium batteries are
    not regulated in North Carolina; and
    v) A new "'RCRA" CLIN with a unit price based on
    supportable data must be added to the contract.
    Laidlaw, 43 Fed. Cl. at 48. Focusing on the superior knowledge theory, the court held:
    The nature of this last claim is an assertion regarding what
    the government and Laidlaw knew in regard to the toxicity
    of magnesium batteries, and when they knew it. While
    such a claim before the contracting officer need not be
    legally precise, if the general nature of this claim had been
    presented to the contracting officer, we would expect a
    statement in Laidlaw's claim to the effect that Laidlaw was
    unaware of the government studies finding that
    magnesium batteries were hazardous under the RCRA; that
    the government did not inform Laidlaw of the results of
    such studies; and that Laidlaw was damaged by this lack
    of, or withheld, knowledge. This claim is thus a new claim,
    and a variance, based on "operative facts'' beyond those
    9
    presented for the contracting officer's final decision and
    must, therefore, be dismissed.
    Laidlaw, 43 Fed. Cl. at 50. Significantly, it was the lack of operative facts reflecting
    that Laidlaw was "unaware" of information the government was aware of that caused
    the court to dismiss. The court commented, "[ n]o reasonable person could have
    inferred, from reading Laidlaw's claim before the contracting officer, that Laidlaw was
    alleging that the government had superior information that Laidlaw did not possess,
    which it had a duty to disclose." Id. at 51.
    The common thread in these and other superior knowledge cases is their
    analysis of whether the operative facts in a claim to the CO communicated the
    disparity of knowledge between the contractor and the government before contract
    award. If they did, there is jurisdiction to consider the claim, if not, there is no
    jurisdiction. That is the standard we apply to Lee's Ford. The legal theories asserted
    in the claim are "frustration of purpose" and "reformation" (SOF ii 4). The claim cites
    the following material operative facts 2 :
    •   On 19 January 2007 a decision was made to lower
    the water level in the lake.
    •   Lee's Ford expected to have "a certain water level
    at its dock and the business traffic that has
    historically followed that water level."
    •   The parties could not have envisioned at the time
    they entered into the Lease that the Lake would be
    drawn down to such an extreme degree for such a
    long period of time, as the Lake has only been
    lowered to 680' once in its more than fifty year
    history.
    (SOF ii 4) The last two bullets relate to pre-award knowledge.
    The parties entered into the lease on 29 August 2000 (SOF ii 1). The decision to
    lower the water level was made over six years after the lease was executed3 (SOF ii 2).
    While two of the operative facts in the claim deal with the parties' knowledge at award
    of the lease, they do not reflect the disparity of knowledge between the parties required
    to support a superior knowledge theory. Indeed, Lee's Ford's assertion that the parties
    could not have envisioned at the time they entered into the Lease that the lake would be
    2
    The facts presented in the claim relating to the SBA and the Corps' mitigation
    efforts are not material to superior knowledge.
    3
    We do not consider the fact that ownership of Lee's Ford changed in 2003 to be
    significant (R4, tab 4).
    10
    drawn down to such an extreme degree for such a long period of time communicates a
    common understanding that is inconsistent with the disparity of knowledge required for
    superior knowledge. We disagree with the implication in appellant's brief that it alleged
    facts supporting superior knowledge, "[f]irst, the claim letter certainly indicates that,
    prior to lease execution, the Corps did not provide Lee's Ford with any information
    about defects with the Wolf Creek Dam that were likely to result in major
    reconstruction." (App. br. at 15) Of critical importance is the complete absence of any
    assertion that the COE had information that appellant did not.
    There is nothing in Lee's Ford's operative facts alleged in the claim that arguably
    supports the theory of superior knowledge. As in Laidlaw, no reasonable person could
    have inferred, from reading Lee's Ford's claim, that it was alleging the government had
    pre-award superior information that Lee's Ford did not possess. Accordingly, the
    complaint incorporated into the appeal constitutes a new claim that has not been
    presented to a CO for decision as required by the CDA, 
    41 U.S.C. § 7103
    (a)(l), we do
    not have jurisdiction to consider it, and we strike it.
    Since we do not have jurisdiction over the superior knowledge count, we do not
    address the government's other two issues, failure to certify and timeliness.
    CONCLUSION
    For the reasons stated above, we strike the complaint as it relates to the theory
    of superior knowledge without prejudice to the filing of a proper claim with the CO. 4
    The appeal, however, remains within the jurisdiction of the Board and Lee's Ford may
    amend its complaint to assert theories supported by the operative facts stated in the
    claim.
    Dated: 23 July 2014
    Administr, tive Judge
    Armed Services Board
    of Contract Appeals
    4
    Since this claim is not before us we express no opinion on any possible untimeliness
    of the filing of the claim, should such occur.
    11
    (Signatures continued)
    I concur                                          I concur
    c
    Administrative Judge                               aministrative Judge
    Acting Chairman                                   Acting Vice Chairman
    Armed Services Board                              Armed Services Board
    of Contract Appeals                               of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 59041
    , Appeal of
    Lee's Ford Dock, Inc., rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    12