Classic Site Solutions, Inc. ( 2014 )


Menu:
  •                 ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeals of --                                 )
    )
    Classic Site Solutions, Inc.                  )      ASBCA Nos. 58376, 58573
    )
    Under Contract No. W912DR-l l-C-0022          )
    APPEARANCES FOR THE APPELLANT:                       Mark S. Dachille, Esq.
    Nicole L. Campbell, Esq.
    Huddles Jones Sorteberg & Dachille, P.C.
    Columbia, MD
    Drew W. Colby, Esq.
    Partridge Snow & Hahn, LLP
    Westborough, MA
    APPEARANCES FOR THE GOVERNMENT:                      Thomas H. Gourlay, Jr., Esq.
    Engineer Chief Trial Attorney
    William J. Selinsky, Esq.
    Scott C. Seufert, Esq.
    Richard P. White, Esq.
    Assistant District Counsel
    U.S. Army Engineer District, Baltimore
    OPINION BY ADMINISTRATIVE JUDGE CLARKE
    ON THE PARTIES' CROSS-MOTIONS FOR SUMMARY JUDGMENT
    The parties each move for summary judgment in what is referred to as the "Tank
    Mix" claim, ASBCA Nos. 58376, 58573. The contract involved construction of a test
    track for military vehicles, including tanks, at Aberdeen Proving Ground, Maryland.
    These particular motions involve questions of contract interpretation relating to the type
    of pavement required by the contract. We have jurisdiction pursuant to the Contract
    Disputes Act of 1978 (CDA), 
    41 U.S.C. §§ 7101-7109
    . We grant partial summary
    judgment in favor of the government and deny appellant's motion.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTIONS
    1. Contract No. W912DR-l 1-C-0022 (0022) was awarded to CSSI on 31May2011
    (R4, tab 4 at 2, tab 11). The contract required CSSI to construct an automotive vehicle test
    and evaluation facility (ATEF) at Aberdeen Proving Ground, Maryland (APG), that
    included a 4.5 mile paved test track (R4, tab 4 at 5). The contract included three contract
    line item numbers (CLINs): CLIN 0001 Construction of ATEF Phase II; CLIN 0002
    Bituminous Cone. Wearing Course; and CLIN 0003 Bituminous Cone. Binder Course (id. at
    3, 4).
    2. The project construction specifications included section 32 12 16, Hot-Mix
    Asphalt (HMA) for Roads (R4, tab 7), that reads in pertinent part:
    2.3 MIX DESIGN
    a. HMA classified as Tank Mix shall be used for all
    bituminous concrete pavements. Tank Mix is used
    exclusively at Aberdeen Proving Ground for heavy-duty
    pavements, and has been locally available for several years.
    The nominal maximum aggregate size (NMAS) shall be
    19.0 mm for the binder course and 12.5 mm for the
    wearing course. The Tank Mix producer shall have at least
    5 years of experience in producing the submitted Tank
    Mix, and a record of successful production and use of such
    product on the APG Garrison. If Tank Mix is no longer
    locally available, then the Contractor shall develop the mix
    design as specified in Part b. or c., below.
    (R4, tab 7 at 13) Subparagraph b. provides that the contractor shall develop a mix design
    in accordance with the guidance therein. Subparagraph c. allows the use of "MdDOT
    Superpave hot mix" in accordance with the guidance therein. (Id.)
    3. The contract incorporated the FAR 52.236-5, MATERIAL AND WORKMANSHIP
    (APR 1984) clause (R4, tab 4 at 7), which provides in pertinent part:
    References in the specifications to equipment, material,
    articles, or patented processes by trade name, make, or
    catalog number, shall be regarded as establishing a standard
    of quality and shall not be construed as limiting competition.
    The Contractor may, at its option, use any equipment,
    material, article, or process that, in the judgment of the
    Contracting Officer, is equal to that named in the
    specifications, unless otherwise specifically provided in this
    contract.
    4. On 16 January 2012, CSSI submitted its mix design for approval (supp. R4, tab
    33 at 2). The submittal included two letters from Maryland Paving, Inc., indicating that it
    would supply mix design "option 'C"' as approved by the Maryland State Highway
    Administration (id. at 6). The submittal was disapproved:
    2
    The mix design does not satisfy Part 2.3 "A" of the project
    specifications. The specifications require that "Tank Mix"
    hot mix asphalt be used by the contractor on this project,
    provided it is still locally available. To-date, this mix design
    is locally available from Independence Materials, of
    Aberdeen, Md. Therefore, the contractor cannot exercise
    options "B" or "C" for this project. However, this submission
    by the Contractor is an effort to exercise option "C"; altering
    a MdDOT Superpave mix design to meet the project
    specifications.
    Please contact a local supplier and submit a "Tank Mix"
    design that has been successfully used for at least 5 years on
    the APG Garrison.
    (Supp. R4, tab 33 at 3)
    5. On 20 February 2012, CSSI objected to the government's disapproval of the
    mix design submittal stating among other things that the government was improperly
    requiring a brand name product (R4, tab 19).
    6. On 4 April 2012, CSSI submitted two separate requests for mix design
    approval (supp. R4, tabs 34, 35). The first submission was the same mix design that was
    submitted on 16 January 2012 that had been disapproved. This mix design was again
    disapproved with the same rationale. (Supp. R4, tab 34 at 2) The second submission that
    offered the "Tank Mix" formula from Independence Construction Materials (ICM), of
    Aberdeen MD, was approved by the government (supp. R4, tab 35 at 3). CSSI
    subsequently supplemented its approved submission to respond to the comments (supp.
    R4, tabs 36, 37). The ICM tank mix design was approved (supp. R4, tab 37 at 1).
    7. On 10 May 2012, CSSI's counsel submitted to the government a "Written
    Notice of Change" for "upwards of $500,000" resulting from the government's order that
    CSSI use ICM's "Brand name" tank mix in lieu of the less expensive alternative mix
    design initially submitted by CSSI for approval (R4, tab 21 ).
    8. CSSI provided ICM's local tank mix and on 8 June 2012, CSSI submitted a
    certified claim for $846,236.60 as a result of the government's direction that CSSI use
    ICM's tank mix design (R4, tab 22).
    9. CSSI submitted an appeal based on a deemed denial on 5 November 2012.
    The Board docketed the appeal as 
    ASBCA No. 58376
     on 6 November 2012. The claim
    was formally denied by contracting officer's final decision dated 5 December 2012 (R4,
    tab 1). CSSI filed a notice of appeal from that final decision on 26 February 2013 and it
    3
    was docketed as 
    ASBCA No. 58573
     and consolidated with 
    ASBCA No. 58376
     and other
    CSSI appeals under the contract.
    DECISION
    Contract Interpretation/Extrinsic Evidence
    We recognize that the parties submitted much more detailed factual analyses than
    reflected in our SOFs above. The parties refer to numerous documents and
    affidavits/declarations from witnesses. Our SOFs reflect the minimum facts necessary for
    the Board to evaluate the parties' contentions; we do not rely on the extrinsic evidence
    submitted by the parties. 1 This is because a motion for summary judgment based on an
    issue of contract interpretation may only be granted if there is no ambiguity requiring
    reliance on extrinsic evidence. Dixie Construction Co., 
    ASBCA No. 56880
    , 10-1 BCA
    ~ 34,422 at 169,918 ("Legal questions of contract interpretation are amenable to summary
    resolution, unless there is an ambiguity that requires the weighing of extrinsic evidence"
    and "extrinsic evidence will not be received unless there is such an ambiguity."). An
    ambiguity exists when there are two reasonable interpretations of the language under
    consideration. Teg-Paradigm Environmental, Inc. v. United States, 
    465 F.3d 1329
    , 1338
    (Fed. Cir. 2006) (When a provision in a contract is susceptible to more than one reasonable
    interpretation, it is ambiguous, and we may then resort to extrinsic evidence to resolve the
    ambiguity.). Additionally, summary judgment is appropriate only where there is no genuine
    issue of material fact and the moving party is entitled to judgment as a matter of law. Any
    significant doubt over factual issues, and all reasonable inferences, must be resolved in
    favor of the party opposing summary judgment. Mingus Constructors, Inc. v. United States,
    
    812 F.2d 1387
    , 1390 (Fed. Cir. 1987); Dixie, 10-1BCA~34,422 at 169,918.
    Thus the Board must attempt to interpret paragraph 2.3a. of specification section
    32 12 16, quoted in SOF ~ 2 above, based on the language alone. Ifwe conclude there is
    more than one reasonable interpretation, the language is ambiguous and summary
    judgment must be denied. Dixie, 10-1 BCA ~ 34,422 at 169,919.
    Contentions of the Parties
    Appellant contends that the government's demand that CSSI provide local tank
    mix was a compensable change for three alternative reasons: (1) Specification 32 12 16,
    Hot-Mix Asphalt (HMA) for Roads, allowed CSSI to provide one of three options: either
    local "Tank Mix" (subparagraph a.), or develop its own mix design (subparagraph b.), or
    provide MdDOT approved Superpave Mix (subparagraph c.) (app. mot. at 21-32); (2) A
    "local tank mix" was not available (app. mot. at 42); or (3) Pursuant to the Material and
    1
    CSSI moved to strike paragraphs in Mr. Babcock's declaration. Since we do not rely
    on his declaration or any other affidavits/declarations, CSSI's motion is moot.
    4
    Workmanship clause, provide a mix design that was "equal" to local tank mix (app. mot.
    at 44-57). CSSI also argues that the government's specification requiring a proprietary
    mix design is too restrictive and the government failed to comply with regulations to
    obtain approval of the use of a proprietary mix design (app. mot. at 32-37).
    The government contends that Section 32 12 16 cannot be interpreted to allow
    submission in accordance with subparagraphs b and c if the tank mix in subparagraph a is
    available. Since a local tank mix design from a producer that successfully produced and
    used the product for at least five years was available, CSSI was obligated to use that
    product (gov't mot. at 10-13).
    Discussion
    Restrictive Solicitation and Regulatory Violations
    CSSI complains that the specifications were too restrictive and the government
    violated procurement regulations (app. mot. at 32-36). CSSl's remedy for overly
    restrictive specifications was to file a protest which it failed to do. C&D Construction,
    Inc., ASBCA Nos. 48590, 49033, 97-2 BCA ii 29,283 at 145,697 ("C&D's remedy was
    to file a bid protest on the basis that the solicitation unduly restricted competition. We do
    not have jurisdiction to make such a determination."). (Citations omitted)
    Interpretation of 2. 3 MIX DESIGN, subparagraph a.
    Paragraph 2.3 MIX DESIGN consists of five sentences; we discuss the three
    relevant sentences. The first sentence of paragraph 2.3a. reads: "HMA classified as
    Tank Mix shall be used for all bituminous concrete pavements" (SOF ii 2). This
    language is clear and unambiguous and susceptible to only one reasonable inte~retation.
    Subject to the rest of subparagraph a., hot-mix asphalt classified as "Tank Mix" must be
    used. We reject CSSl's argument that the words "classified as" somehow detract from
    the clear mandatory meaning of the first sentence as unreasonable (app. mot. at 23-29).
    The second sentence is a statement on historical usage of tank mix at APG and is relevant
    only in that it indicates tank mix "has been locally available for several years." The third
    sentence identifies "nominal maximum aggregate size" for the binder and wearing
    courses of tank mix and is not relevant to our interpretation. The fourth sentence reads,
    "[t]he Tank Mix producer shall have at least 5 years of experience in producing the
    submitted Tank Mix, and a record of successful production and use of such product on
    the APG Garrison." This sentence is clear and unambiguous and susceptible to only one
    reasonable interpretation. It requires that the tank mix producer have 5 years of
    successful "production" of tank mix and successful "use" of tank mix on APG. The fifth
    2
    For our purposes, we need not delve into what 'Tank Mix" is because it would require
    consideration of extrinsic evidence.
    5
    sentence reads, "[i]f Tank Mix is no longer locally available, then the Contractor shall
    develop the mix design as specified in Part b. or c., below." This sentence is clear and
    unambiguous and susceptible to only one reasonable interpretation. It creates a condition
    precedent to the use of subparagraph b. or c. Therefore, we reject CSSI's argument that
    the absence of the words "only" or "only if' creates an ambiguity (app. mot. at 29-32).
    We disagree with CSSI's interpretation of the language of paragraph 2.3 MIX DESIGN
    that it had the right to choose any one of the three options in paragraphs 2.3a., b. and c.
    regardless of the availability of local tank mix. Accordingly we grant summary judgment
    in favor of the government on this point. Appellant was not entitled under the terms of
    the specification to use options b. or c.
    Availability of Local Tank Mix
    CSSI argues that tank mix was not locally available because it "does not meet the
    ATEF II Recipe" (app. mot. at 41-42). We consider "availability" to be a disputed
    question of fact and not susceptible for decision on summary judgment.
    The Material and Workmanship Clause
    The contract includes FAR 52.236-5, MATERIAL AND WORKMANSHIP (APR 1984)
    (SOF ii 3). The clause specifically states that identification by brand name shall not limit
    competition. We have held that the purpose of the clause is to promote competition.
    Southern Playground, Inc., ASBCA Nos. 43797, 43798, 02-1 BCA ii 31,853; CPF
    Underground Utilities, Inc., 
    ASBCA No. 33436
    , 87-1BCAii19,596 at 99,123 (The
    purpose of the clause is "to discourage the potentially monopolistic practice of
    demanding the use of brand-name or designated articles in government contract work.").
    CSSI claims that the government's insistence on ICM's tank mix cost an additional
    $846,236.60 (SOF ii 8) and that the government should bear that cost because CSSI
    offered a less expensive, functionally equivalent design mix.
    Inclusion of the Material and Workmanship clause qualifies the general rule that,
    after award, the government is entitled to strict compliance with every technical
    requirement of the contract's specifications. The clause provides a contractor the right to
    submit a substitute product for a proprietary item called for in the contract's specification
    absent a warning that only the proprietary item will be accepted. North American
    Construction Corp., 
    ASBCA No. 47941
    , 96-2 BCA ii 28,496 at 142,298. Use of the
    word "shall" is not a sufficient warning. Minority Enterprises, Inc., 
    ASBCA No. 45549
     et al., 95-1BCAii27,461at136,827. Language such as,
    "NOTWITHSTANDING any other provision of the contract, no other product will be
    acceptable" is sufficient warning to preclude substitution. Maron Construction Co.,
    
    ASBCA No. 53933
    , 05-1BCAii32,904 at 163,026. The government did not include
    such a warning in paragraph 2.3 MIX DESIGN (SOF ii 2).
    6
    The contractor bears the burden of proof that it is entitled to submit a substitute
    item. The contractor must prove:
    (1) the specifications are proprietary, (2) appellant submitted
    a substitute product along with sufficient information for the
    contracting officer to make an evaluation of the substitute,
    and (3) the proposed substitute meets the standard of quality
    represented by the specifications.
    North American, 96-2 BCA ii 28,496 at 142,299; Blount Brothers Corp., 
    ASBCA No. 31202
    , 88-3 BCA ii 20,878 at 105,575. The record as it presently exists does not
    allow the Board to conclude that CSSI has satisfied this burden of proof and therefore
    whether it is entitled to an equitable adjustment for the contracting officer's refusal to
    allow CSSI to substitute for the "Tank Mix" alleged to be proprietary.
    CONCLUSION
    For the reasons stated above, we grant partial summary judgment in favor of the
    government as to the interpretation of the Mix Design clause as set forth herein. We
    deny the remainder of the government's motion. We deny CSSI's motion.
    Dated: 26 June 2014
    Administra ve Judge
    Armed Services Board
    of Contract Appeals
    I concur                                           I concur
    ``~ RIC~CKLEFORD
    Administrative Judge                              Administrative Judge
    Acting Chairman                                   Vice Chairman
    Armed Services Board                              Armed Services Board
    of Contract Appeals                               of Contract Appeals
    7
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA Nos. 58376, 58573, Appeals of
    Classic Site Solutions, Inc., rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    8
    

Document Info

Docket Number: ASBCA No. 58376, 58573

Judges: Clarke

Filed Date: 6/26/2014

Precedential Status: Precedential

Modified Date: 10/30/2014