Laguna Construction Company, Inc. ( 2014 )


Menu:
  •                 ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                 )
    )
    Laguna Construction Company, Inc.            )          
    ASBCA No. 58569
    )
    Under Contract No. FA8903-04-D-8690          )
    APPEARANCE FOR THE APPELLANT:                           Carolyn Callaway, Esq.
    Carolyn Callaway, P.C.
    Albuquerque, NM
    APPEARANCES FOR THE GOVERNMENT:                         E. Michael Chiaparas, Esq.
    DCMA Chief Trial Attorney
    Gregory T. Allen, Esq.
    Trial Attorney
    Defense Contract Management Agency
    Manassas, VA
    OPINION BY ADMINISTRATIVE JUDGE DELMAN ON
    APPELLANT'S MOTION TO DISMISS FOR LACK OF JURISDICTION
    Laguna Construction Company, Inc. (Laguna, appellant, LCC), moves to dismiss
    this appeal for lack of jurisdiction, contending that the government's monetary claim was
    filed more than six years from the date the claim accrued, and therefore is barred under
    the Contract Disputes Act (CDA), 
    41 U.S.C. § 7103
    (a)(4)(A). 1
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
    1. On 21November2003, the Air Force Center for Environmental Excellence
    (government) awarded to appellant Contract No. FA8903-04-D-8690 for Worldwide
    Environmental Remediation and Construction (WERC) (R4, tab 1)2 • Laguna received 16
    task orders (TOs) under this contract to perform various items of construction work in Iraq.
    1
    In response to appellant's motion to dismiss, the government conceded: "The
    Government Acknowledges Its Cost Reasonableness Claim ... on TO [Task Order]
    0002 was Untimely" (gov't opp'n at 9). Accordingly, we address herein the
    balance of the government's claim, under TOs 0006 and 0015.
    2
    We cite to the Rule 4 file submitted under 
    ASBCA No. 57977
    , as supplemented
    thereafter, which appeal was later consolidated with ASBCA Nos. 58324 and
    58569 (SOF ~ 13).
    2. Under TO 0006, awarded to appellant on 25 June 2004, appellant was to
    renovate facilities at the An Numaniyah Training Base (R4, tab 4). Under this TO
    appellant awarded a subcontract to "Yacoub & Ramzi Snobar Company" (Snobar) for
    11 Kv Distribution Loop and Transformers (app. reply, attach. 4 at 3). It also awarded a
    subcontract to "Al Huda Company" (AHC) to perform work on a range complex
    (id., attach. 5 at 5). According to the government's claim, the Snobar and AHC
    subcontracts were not awarded based upon adequate competition, and appellant failed to
    document that these award prices were reasonable (see SOF ~ 12).
    3. During contract performance in 2005 appellant submitted vouchers for progress
    payments to the government on behalf of these subcontractors, which vouchers identified
    the progress payment requested and the awarded subcontract price (app. reply, attach. 4 at
    6, attach. 5 at 6).
    4. Under TO 0015, awarded to Laguna on 12 July 2005 (gov't opp'n, appx. 1),
    appellant was to construct inter alia, barracks and classroom buildings for the Baghdad
    Police College. "Sigma International Construction, LLC" (Sigma) was awarded a
    subcontract to construct the barracks (app. reply, attach. 1 at 7). 'The New Millennium"
    (TNM) was awarded a subcontract to construct the classroom buildings (id., at 10).
    According to the government's claim, the awarded subcontract prices - which significantly
    increased from those initially proposed by the subcontractors - were not based upon
    adequate competition. As for TNM, it received award for the classroom buildings but was
    not the lowest bidder for this work. According to the government's claim, appellant failed
    to justify award to TNM as other than the lowest bidder, and failed to document that the
    Sigma and TNM subcontract award prices were reasonable. (SOF iI 12)
    5. The government was aware of Sigma's and TNM's original subcontract price
    proposals through appellant's original cost proposal (2nd supp. R4, tabs 45, 46), and was
    also aware of the proposed increases to these prices prior to their award (mot., attach. 2).
    The government was also aware of the subcontract prices ultimately awarded. As was
    the case with TO 0006, during performance in 2005, LCC requested progress payments
    from the government on behalf of the TO 0015 subcontractors for work performed, which
    included the amount of the progress payment requested and the subcontract price
    (app. reply, attach. 1 at 7, 10).
    6. On 6 December 2005, the Defense Contract Audit Agency (DCAA) Iraq
    Branch Office issued Audit Report No. 213 l-2006Tl 7900001 to the DCAA Salt Lake
    Valley Branch Office, entitled "Audit Report on Laguna Construction Company's
    Subcontract Management System" under this contract. Insofar as pertinent, the report
    stated as follows:
    2
    [W]e reviewed Laguna Construction Company (LCC)
    subcontract management system and examined a sample of
    32 LCC subcontracts totaling $147,701,411 under Prime
    Contract No. FA8903-04-D-8690 on Oct. 22, 2005. The
    purpose of the examination was to review the subcontract
    management system to verify policies and procedures are in
    place to assure compliance with FAR 52.216-7, Allowable
    Cost and Payment. We also reviewed LCC 's procurement
    files to determine whether LCC complied with FAR 15 .4, to
    justify sole source procurements, performance of an adequate
    cost or price analysis of the subcontractors to ensure
    negotiation of a fair and reasonable price, or award
    subcontracts competitively.
    (R4, tab 8 at G-91) DCAA's report concluded, inter alia, as follows:
    In our opinion the [Laguna] subcontract management
    system and related internal control policies and procedures
    are inadequate and cannot be relied upon to ensure
    subcontracts are awarded in accordance with FAR 15 .4,
    Contract Pricing, or subcontract payments by LCC are in
    accordance with FAR 52.216.7, Allowable Cost and Payment.
    (R4, tab 8 at G-93) Among the objectionable conditions found by DCAA under the
    contract were "Condition 1: No Price Analysis Determining Subcontract Costs were
    'Fair and Reasonable,'" and "Condition 2: No Justification Provided for
    Subcontractor Not the Lowest Bidder" (id. at G-95-97).
    7. By Audit Report No. 3231-2006117900001, dated 9 February 2006, the DCAA
    Salt Lake Valley Branch Office forwarded the DCAA findings to the administrative
    contracting officer (ACO) in an audit report entitled: "Flash Report on Subcontractor
    Management System Deficiencies." DCAA found the following with respect to this contract:
    •   On subcontracts awarded without adequate price
    competition, LCC did not perform a price analysis to
    determine whether the costs are fair and reasonable.
    •   LCC did not document justification for awarding
    subcontracts to other than the lowest bidder in
    accordance with FAR 15.408.
    (R4, tab 15 at G-145) The audit report also concluded as follows:
    3
    Subcontract costs comprise a significant portion of
    costs on Contract No. FA8903-04-D-8690 .... Due to the
    deficiencies in the internal controls related to LCC's
    subcontract management system we believe a significant risk
    is present relative to allocability, allowability and
    reasonableness of subcontract costs billed to the U.S.
    Government. We believe this deficiency is serious enough to
    render the subcontract management system inadequate.
    Accordingly, we recommend the contracting officer require
    LCC to submit requests for Consent to Subcontracts in
    accordance with FAR Part 44.2.
    (Id. at G-146) The DCAA report did not specifically cite to the subcontracts in issue here.
    8. Approximately three years later, on 12 March 2009, the ACO sent a copy of the
    9 February 2006 DCAA audit report to Laguna (R4, tab 22).
    9. By letter to Laguna dated 1 May 2009, the ACO identified "on-going and
    significant LCC subcontract management system deficiencies. These deficiencies were
    first detailed in DCAA Audit Report [No.] 3231-2006JJ7900001 dated February 9, 2006
    (Encl) which at the time reviewed subcontract awards under FA8903-04-D-8690
    (WERC)." The ACO determined that it was appropriate to suspend or withhold
    30% from LCC's interim billings under this contract, which represented the cost risk to
    the government for the deficiencies reported. (R4, tab 24) (Emphasis added)
    10. DCAA submitted an audit report to the ACO by date of 27 October 2009,
    entitled "Report on Audit of Subcontract Award Control Activities within Purchasing
    System." Insofar as pertinent, DCAA found the following conditions:
    •       inadequate policies, procedures, and practices
    covering subcontract cost or price analysis,
    •       inadequate documentation in subcontract procurement
    files,
    It should be noted the contractor has already been
    cited for these same deficiencies in Audit Report No.
    3231-2006JJ7900001, dated February 6 [sic], 2006.
    (R4, tab 25 at G-214) (Emphasis added)
    4
    11. On 17 March 2011, more than five years after the 200 5-2006 audit reports,
    DCAA issued to Laguna a "NOTICE OF CONTRACT COSTS SUSPENDED AND/OR
    DISAPPROVED," Notice No. 2011-003, which disapproved $2,089,799 under this
    contract, including amounts under the AHC and Snobar subcontracts under TO 0006, and
    amounts under the Sigma and TNM subcontracts under TO 0015. According to this
    DCAA Notice, these subcontract awards "had no evidence of competition and all failed
    to meet the test of fair and reasonable pricing" based upon a lack of support "in [LCC's]
    procurement files sufficient to demonstrate the Government paid a fair and reasonable
    price for the services subcontracted." (R4, tab 27 at G-233-34) The disapproved amount
    was increased to $2,383,370 by DCAA Notice No. 201 l-003a, dated 4 August 2011
    (R4, tab 33).
    12. By letter to Laguna dated 17 December 2012, the ACO issued a final decision
    providing disposition of the costs disapproved by the DCAA under Form 1 Notice
    2011-003a. Insofar as pertinent, the ACO determined inter alia, that with respect to the
    AHC and Snobar subcontracts under TO 0006, LCC's procurement files were insufficient
    to determine the reasonableness of the subcontract prices. With respect to TO 0015, the
    ACO determined inter alia, that appellant's procurement files failed to document the
    reasonableness of Sigma's and TNM's subcontract prices and also failed to document
    appellant's decision to award the construction of the classrooms to TNM, who was not
    the lowest bidder. The total government claim, including associated G&A, was
    $3,815,232.68. (2nd supp. R4, tab 49 at G-421-23)
    13. Appellant appealed this decision on 22 February 2013, and the Board
    docketed the appeal as 
    ASBCA No. 58569
    . The appeal was later consolidated with
    ASBCA Nos. 57977 and 58324. These latter appeals are not subject to this motion.
    DECISION
    Under the CDA, 
    41 U.S.C. § 7103
    (a)(4)(A), a contract claim, whether that of the
    contractor or the government, must be "submitted within 6 years after the accrual of the
    claim." We do not have jurisdiction over a claim that fails to meet this requirement. The
    government, as proponent of our jurisdiction here, bears the burden of proving the facts
    sufficient to support our jurisdiction. Raytheon Missile Systems, 
    ASBCA No. 58011
    ,
    13 BCA ~ 35,241.
    The CDA does not define claim accrual, but the FAR does so. Effective
    21 November, 2003, the date of the contract award, FAR 33.201 provided the following
    definition:
    5
    "Accrual of a claim" means the date when all events,
    that fix the alleged liability of either the Government or the
    contractor and permit assertion of the claim, were known or
    should have been known. For liability to be fixed, some
    injury must have occurred. However, monetary damages
    need not have been incurred. [Emphasis added]
    In order to determine when the alleged liability was fixed for purposes of claim
    accrual, it is necessary to examine the legal basis of the claim. Gray Personnel, Inc.,
    
    ASBCA No. 54652
    , 06-2 BCA ii 33,378 at 165,475. The legal predicate of the
    government's claim here is appellant's failure to document the reasonableness of
    subcontract awards under this contract that were not based upon competition. The
    DCAA was fully aware of appellant's failure to document the reasonableness of
    subcontract awards under this contract that were not based upon competition by late
    2005, and it documented its findings by audit reports dated 6 December 2005 and
    9 February 2006, which latter report was issued to the ACO. That the DCAA did not
    single out these subcontracts by name in the audit reports is irrelevant. DCAA reviewed
    32 subcontracts under the contract totaling $147,701,411 which presumably was a
    significantly large sample upon which to support its findings.
    The government was also aware of its "injury" here, i.e., the subcontract prices
    awarded by appellant and paid by the government, as early as 2005. The ACO did not
    file this claim until 17 December 2012.
    For purposes of claim accrual, we have stated that the "events fixing liability
    should have been known when they occurred unless they can be reasonably found to have
    been either concealed or 'inherently unknowable' at that time." Raytheon, 13 BCA
    ii 35,241at173,016. There is nothing of record suggesting that the Sigma, TNM, Snobar
    and AHC subcontract files under TOs 0006 and 0015 were concealed or inherently
    unknowable during DCAA's 2005 audit review of appellant's subcontracting practices
    under this contract. The "should have been known" test of claim accrual has a
    reasonableness component- it turns, objectively, upon what facts were reasonably
    knowable to the claimant. Raytheon, 13 BCA ii 35,241at173,016. Given the nature of
    the government's claim here, i.e., the inadequacy of appellant's subcontract files to
    support the reasonableness of these subcontract prices, we believe that all events fixing
    the alleged liability of the claim were reasonably knowable and should have been known
    by the government no later than 9 February 2006, when the DCAA report was submitted
    totheACO.
    Accordingly, we conclude the government's claim accrued no later than
    9 February 2006. The final decision asserting a government claim was dated
    6
    17 December 2012. We conclude the government's claim was untimely and is barred
    under the CDA. 3
    CONCLUSION
    The government has conceded that its monetary claim under TO 0002 was barred
    under the CDA as untimely (see note 1). For reasons stated herein, we conclude that the
    government's monetary claim under TO 0006 and under TO 0015 are also barred under
    the CDA as untimely. Accordingly, the CO's decision dated 17 December 2012 is
    hereby deemed null and void.
    The appeal is dismissed for lack of jurisdiction.
    Dated: 29 May 2014
    (\~---,
    ~
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                            I concur
    RICHARD SHACKLEFORD
    Administrative Judge                                Administrative Judge
    Acting Chairman                                     Vice Chairman
    Armed Services Board                                Armed Services Board
    of Contract Appeals                                 of Contract Appeals
    3
    Given that the government's claim of 17 December 2012 is barred based upon the date
    of claim accrual of 9 February 2006, we need not address whether the claim
    accrued even earlier, i.e., from 6 December 2005, the date of the first DCAA audit
    report.
    7
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 58569
    , Appeal of Laguna
    Construction Company, Inc., rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    8
    

Document Info

Docket Number: ASBCA No. 58569

Judges: Delman

Filed Date: 5/29/2014

Precedential Status: Precedential

Modified Date: 10/30/2014