PHA-JMR JV ( 2014 )


Menu:
  •                  ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                             )
    )
    PHA-JMR JV                               )        
    ASBCA No. 59032
    )
    Under Contract No. FA4686- l O-C-0018 )
    APPEARANCES FOR THE APPELLANT:                   Martin R. Salzman, Esq.
    Kevin S. Dale, Esq.
    David M. Gersh, Esq.
    Hendrick Phillips Salzman & Flatt, P.C.
    Atlanta, GA
    APPEARANCES FOR THE GOVERNMENT: Col Robert J. Preston II, USAF
    Acting Air Force Chief Trial Attorney
    Christopher M. McNulty, Esq.
    Capt Eric J. Singley, USAF
    Trial Attorneys
    OPINION BY ADMINISTRATIVE JUDGE JAMES
    ON JURISDICTION
    On 25 February 2014, the Board, sua sponte, asked the parties to briefthe
    question whether the 30 April 2013 Contract Disputes Act (CDA) certification signed by
    Scott Manning, treasurer of subcontractor Progressive Roofing as "Attorney-in-fact for
    JMR," one of the PHA-JMRjoint venturers, by a limited power of attorney that expired
    on 31 January 2013, was a valid CDA certification. Both parties submitted briefs. At the
    parties' request, the Board also heard oral argument. Upon review of the parties' briefs,
    attached exhibits and the transcript of the oral argument, we refocus the question as
    follows: whether either appellant's 25 January 2013 claim or 30 April 2013 claim is
    within the CDA jurisdiction of this Board.
    STATEMENT OF FACTS (SOF)
    I. On 11 August 2010, the U.S. Air Force 9th Contracting Squadron entered into
    Contract No. FA4686-10-C-0018 (the contract) with PHA-JMR JV to construct roof
    sections A and B for Building No. 1086 at Beale Air Force Base, California (R4, tab 1
    at 1-3).
    2. For PHA-JMR JV, "PHILIP L. HA WK.INS, MANAGING PARTNER"
    signed the contract and its bilateral Modification Nos. P00002, P00003 and P00004
    (R4, tabs 1, 3-5).
    3. "JMR" subcontracted with Progressive Services, Inc. (Progressive) for a
    portion of the contract roofing work, including demolition (Salzman aff., ex. 1 at 1). As
    our following Statement of Facts demonstrate, there are many confusing aspects of this
    appeal. We place "JMR" in quotes for the following reasons, and note that neither the
    Progressive subcontract nor the Joint Venture agreement is in evidence. The "JMR"
    citation is to appellant's undated initial "claim" letter (see SOF if 8). The "claim" is on
    the subcontractor's letterhead and is signed by the subcontractor's treasurer. While it is
    denominated as PHA-JMR JV's claim, the body of the letter stated: "Please accept the
    letter as PHA-JMR's (' JMR') certified claim submission and request for a final
    Contracting Officer's decision on behalf of its subcontractor, Progressive Services, Inc.
    d/b/a Progressive Roofing." It is unclear in the record what appellant intended by its
    parenthetical ("JMR") in this sentence. In various documents sometimes PHA-JMR JV
    is used to refer to the contractor and appellant in this appeal, and sometimes JMR is
    used. Of course, JMR is only one of the JV partners and not the contractor itself.
    4. On 1 November 2010, during the initial roof demolition, Progressive's "Roof
    Warrior" cutting device struck several metal plates atop the concrete deck underlying the
    existing roofing. Progressive notified the government of this discovery on the next day.
    (Salzman aff., ex. 1 at 2, exs. IA, lB)
    5. PHA-JMR JV's Request for Information 003 (RFI #3) dated 10 November
    2010 was authored by John Morrill of JMR, who provided further information to the
    government regarding the alleged differing site condition (Salzman aff., ex. lE).
    6. On 3 June 2011 Progressive sent JMR a $57,210.00 change request consisting
    of$51,080 for labor and $6,130 for "Overhead & Profit@ 12%" relating to the metal
    plates (supp. R4, tab 10 at 4of9).
    7. The 16 June 2011 letter of JMR's John Morrill to contracting officer
    (CO) Pank, on PHA-JMR JV letterhead, forwarded Progressive's 3 June $57,210.00
    request, to which was added "MIU $8,582.00" ("Profit overhead=@ 15%") and "Bond
    $1,144.00" for a total of$66,936.00 (supp. R4, tab 10 at 2-3 of9).
    8. The undated letter to CO Pank on the letterhead of Progressive Roofing, signed
    by Scott Manning, submitted a $240,767 equitable adjustment for "Unforeseen Site
    Conditions," for the metal plates, and requested a CO's final decision. The $240,767
    adjustment included the $66,936 requested by Progressive and JMR on 16 June 2011 and
    added "extended overhead in the sum of at least $173,831.00 for which }MR/Progressive
    is entitled to be reimbursed" (emphasis added). (Salzman aff., ex. 1 at 1-2) We find that
    PHA-JMR JV or JMR added "$8,582.00" (for profit and overhead at 15%), "Bond
    $1,144.00" and "$173,831.00" in extended overhead costs, to Progressive's $57,210
    claim that included $6, 13 0 for "Overhead & Profit @ 12 %. "
    2
    9. Accompanying Progressive's letter were two documents each entitled
    "CONTRACTOR'S CERTIFICATION." The first was on plain bond, whose text
    complied with FAR 33.207(c) and was signed by "Scott Manning, Attorney-in-fact for
    JMR." The second was on Progressive letterhead, signed by "Scott Manning, Treasurer,"
    its text was the same as the other certification. (Salzman aff., ex. 1 at 1, 5-7)
    Mr. Salzman mailed the foregoing "written certified claim ... to the [CO] on behalf of
    Appellant on or about January 25, 2013" (Salzman aff. at 1).
    10. On 13 March 2013 CO Sandra Siiberg rejected the claim because it did not
    appear to originate from the prime contractor, PHA-JMR JV, but was presented on a
    subcontractor's letterhead, and the claim certifier "is variously represented as either the
    apparent claim author ... designated attorney for a partial component (JMR) of the prime
    contractor PHA-JMR JV (with no firm letterhead representation), or, a principal
    (treasurer) of the ... subcontractor" (Salzman aff., ex. 2).
    11. The 30 April 2013 letter of "PHA-JMR JV ('JMR')" to CO Siiberg repeated
    the statements and included the "CONTRACTOR'S CERTIFICATION" signed by
    "Scott Manning, Attorney-in-fact for JMR" in its January 2013 claim letter, and
    appended the following:
    LIMITED POWER OF ATTORNEY
    KNOW ALL MEN BY THESE PRESENTS:
    JMR Construction Corp .... pursuant to a separate Joint
    Prosecution agreement, JMR is. pursuing the claims of
    Progressive Services, Inc .... ("Progressive") against the
    Project Owner pertaining to a differing site condition alleged
    by Progressive pertaining to roofing removal and replacement
    in connection with ... the Air Force Contract for Repair Roof,
    Flightline Support, B 1086 at Beale AFB, California.... In
    connection with the pursuit of the said claims, the Contract
    Disputes Act requires a Contractor Certification that the
    claims are made in good faith, that the supporting data is
    accurate and complete to the best of the contractor's
    knowledge and belief, and that the amount requested
    accurately reflects the contract adjustment for which the
    contractor believes the Government is liable. JMR does not
    have sufficient or personal knowledge, particularly as to
    Progressive' s supporting data, to execute such a certification.
    3
    Scott Manning, Treasurer for Progressive, does possess such
    knowledge.
    Accordingly, the undersigned hereby names,
    nominates and appoints Scott Manning .. .in JMR's name,
    place and stead, to sign its name and execute on its behalf the
    Contractor's Certification. The undersigned does hereby
    consent to, ratify and confirm everything which the said
    attorney-in-fact, pursuant to the powers herein contained,
    shall legally do by virtue of these presents.
    This Limited Power of Attorney shall not be affected
    by any disability and shall expire January 31, 2013.
    IN WITNESS WHEREOF, the undersigned have
    hereunto executed this document on this 21st day of
    December, 2012.
    JMR Construction Corp.
    JoAnne [illegible]      By:      Ron [illegible]
    Witness                    Its: Vice President
    (Gov't resp., attach. 1 at 8 of 8)
    12. CO Siiberg denied PHA-JMR's 30 April 2013 claim on 26 August 2013.
    PHA-JMR timely appealed from that decision on 22 November 2013.
    Contentions of the Parties
    Appellant argues that once the appeal record added the Limited Power of
    Attorney appointing Scott Manning as attorney-in-fact on behalf of JMR to certify
    PHA-JMR N's claim, PHA-JMR N's January 2013 "written certified claim" met all
    the statutory requirements. The 31 January 2013 expiration of such power of attorney
    did not impair the validity of its January 2013 certification. If appellant's January 2013
    certification was defective, it is correctible pursuant to the amended CDA. (App.
    br. at 1-3, 5-7; tr. 6-10) Respondent argues that appellant ignores a fatal defect in its
    January 2013 certification: court and board decisions precluding delegation to a
    subcontractor of the prime contractor's authority to execute the prime contractor's CDA
    certification. An updated limited power of attorney for Mr. Manning to correct a defect
    is futile, because his power of attorney is invalid. (Gov't resp. at 1-6, attach. 3 at 6;
    tr. 25, 27-29)
    4
    DECISION
    We first identify the pertinent statutory, regulatory and decisional requirements and
    rules for submitting a CDA claim.
    For a contractor claim the CDA requires that: (1) the
    contractor must submit the demand in writing to the CO, (2)
    the contractor must submit the demand as a matter of right,
    and (3) the demand must contain a sum certain. HL. Smith,
    Inc. v. Dalton, 49 F .3d 1563, 1565 (Fed. Cir. 1995). The
    claim must request, expressly or implicitly, a final decision of
    the CO, who must issue a decision thereon, or fail to decide
    the claim within the prescribed time. See James M Ellett
    Construction Co. v. United States, 
    93 F.3d 1537
    , 1542-43 n.4
    (Fed. Cir. 1996). If the contractor's claim exceeds $100,000,
    it must be certified. See 
    41 U.S.C. § 7103
    (b)(l).
    ERKA Construction Co., 
    ASBCA No. 57618
    , 12-2 BCA ii 35,129 at 172,473-74.
    The requirement for a "sum certain" is not in the CDA but is in the FAR § 2.101
    definition of a "claim" as "a written demand or written assertion by one of the contracting
    parties seeking, as a matter of right, the payment of money in a sum certain." See
    Rejlectone, Inc. v. Dalton, 
    60 F.3d 1572
    , 1575 (Fed. Cir. 1995) (applying the FAR
    definition of "claim"); see also Precision Standard, Inc., 
    ASBCA No. 55865
    , 11-1 BCA
    ii 34,669 at 170,788-89 ("at least $151,749.06" is not a sum certain because "the
    contractor's use of qualifying language leaves the door open for the request of more
    money on the same basis," so appeal dismissed for lack of CDAjurisdiction).
    On 11August2011, when the contract was awarded to PHA-JMR JV, the CDA
    provided in 
    41 U.S.C. § 7103
    (b):
    (b) Certification of claims.-
    ( l) Requirements generally.-For claims of more than
    $100,000 made by a contractor, the contractor shall certify
    that-
    (A) the claim is made in good faith;
    (B) the supporting data are accurate and complete to the
    best of the contractor's knowledge and belief;
    (C) the amount requested ac.curately reflects the contract
    adjustment for which the contractor believes the Federal
    Government is liable; and
    (D) the certifier is authorized to certify the claim on
    behalf of the contractor.
    5
    (2) Who may execute certification.-The certification
    required by paragraph ( 1) may be executed by an individual
    authorized to bind the contractor with respect to the claim.
    (3) Failure to certify or defective certification .... A defect
    in the certification of a claim does not deprive a court or an
    agency board of jurisdiction over the claim. Prior to the entry
    of a final judgment by a court or a decision by an agency
    board, the court or agency board shall require a defective
    certification to be corrected.
    We conclude that appellant's January and April 2013 claims are not proper CDA
    claims for three reasons.
    First, appellant's claims demanded "at least $173,831.00" for extended overhead
    costs added to Progressive's $57,210 subcontractor claim (SOF ii 8). See Precision
    Standard, 11-1 BCA ii 34,669 at 170,788-89 (amount qualified by "at least" is not a sum
    certain); JP. Donovan Construction, Inc., 
    ASBCA No. 55335
    , 10-2 BCA ii 34,509 at
    170,171, ajf'd, JP. Donovan Construction, Inc. v. Mabus, 
    469 F. App'x 903
     (Fed. Cir.
    2012) ($559,764 subcontractor claim was a sum certain, however, appeal was dismissed
    for lack of jurisdiction due to the qualification "approximately $65,000" of prime's added
    claim costs).
    Second, signing the PHA-JMR JV claims, as distinguished from signing the
    claim certification, was not within Mr. Manning's limited power of attorney (SOF ii 11 ).
    Mr. Manning's limited power of attorney was issued by JMR, not by PHA-JMR JV.
    The third reason requires a brief summary of the pertinent rules regarding joint
    venture claims, which are stated in WorleyPdrsons International, Inc., 
    ASBCA No. 57930
    , 14-1 BCA ii 35,482 at 173,959-60 (government claim against one JV "partner"
    dismissed for lack of jurisdiction):
    A joint venture is an association of partners established
    by contract to carry out a single business activity for joint
    profit. It is essentially a partnership created for a limited
    purpose. Sade/mi Joint Venture v. Dalton, 
    5 F.3d 510
    , 513
    (Fed. Cir. 1993). Typically, ajoint venture has an
    independent existence from its partners. See Pine Prods.
    Corp. v. United States, 
    945 F.2d 1555
    , 1560 (Fed. Cir. 1991).
    Thus, when the government contracts with a joint venture, the
    joint venture is the entity with whom the government is in
    privity of contract, not its partners. Brother's Cleaning Serv.,
    Inc. v. United States, 
    38 Fed. Cl. 106
    , 108 (1997); see also
    Pine Prods. 945 F .2d at 1561. Contrary to its contention here,
    6
    the government has historically opposed efforts by joint
    venture partners to claim independent privity on their joint
    ventures' government contracts, and attempts by partners to
    assert claims in their own names upon such contracts have
    been dismissed.
    See Wackenhut International, Inc. v. Department of State, CBCA No. 1235, 09-2 BCA
    -,r 34,255 at 169,260 (appeal dismissed when one venturer sought to pursue a claim in its
    own right, rather than by the JV); Bellinco, Inc. and A-1 Construction Co., Inc. d/b/al A-1
    Bellinco, Inc. v. Babbitt, 
    1996 U.S. App. LEXIS 31362
     (Fed. Cir. 1996) (JV agreement
    provided for a two member committee, Bell and Roberts, but was silent as to whether one
    member alone could bind or act for the JV; court affirmed Board's dismissal of appeal by
    Bell alone for lack of jurisdiction); Kiewit/Tulsa-Houston v. United States, 981 F .2d 531,
    534-45 (Fed. Cir. 1992) (without an express delegation by both venturers, the managing
    party's general manager lacked authority to bind the JV and so his claim certification was
    inadequate).
    An exception to the foregoing rule arises when a joint venture agreement expressly
    authorizes one venturer or partner to assert a claim against the government and to execute
    a CDA certification on behalf of the JV. E.g., Newberg-Brinderson, 
    ASBCA No. 44845
    ,
    94-3 BCA -,r 27,095 at 135,009 (Dale Gold, vice-president of Newberg, the "Managing
    Venturer," and authorized by both venturers to execute "all other documents ... necessary
    ... to perform and complete construction contracts" had authority to sign the claim
    certification); Stradedile/Aegis Joint Venture, 
    ASBCA No. 39818
    , 95-1BCA-,r27,397 at
    136,587-88 (the presidents of both co-venturers signed the CDA certification of the JV's
    claim, though not expressly so authorized by the JV agreement; government's motion to
    dismiss for lack of jurisdiction denied). This exception is not applicable here.
    Applying the foregoing JV rules to this dispute, JMR's vice president executed
    Mr. Manning's limited power of attorney on behalf of JMR (SOF -,r 11 ). There is no
    evidence, such as the PHA-JMR JV joint venture agreement, that JMR was authorized to
    execute a power of attorney on behalf of the PHA-JMR JV or for Mr. Manning to sign
    PHA-JMR JV's claim (SOF -,r-,r 3, 11 ). And in fact the limited power of attorney does not
    mention the joint venture or the joint venture's claim that is in addition to Progressive's
    claimed amount. For the foregoing reasons, we hold that appellant has not submitted a
    valid CDA claim. Therefore, we need not decide whether a subcontractor's treasurer can
    be authorized to execute a CDA certification pursuant to a limited power of attorney
    signed by one of the two venturers of PHA-JMR JV.
    7
    CONCLUSION
    We dismiss the appeal for lack of jurisdiction, without prejudice to appellant's right
    to submit a compliant CDA claim to the CO. We encourage PHA-JMR JV (the contractor)
    to pay particular attention to who is signing claims and certifications, and in what capacity
    they are signing.
    Dated: 1August2014
    Armed Services
    of Contract Appeals
    I concur                                          I concur
    ``
    MARK N. STEMPLER
    Administrative Judge                              Ad ' mistrative Judge
    Acting Chairman                                   Acting Vice Chairman
    Armed Services Board                              Armed Services Board
    of Contract Appeals                               of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the Armed
    Services Board of Contract Appeals in 
    ASBCA No. 59032
    , Appeal of PHA-JMR JV,
    rendered in conformance with the Board's Charter.
    Dated:
    JEFFREYD. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    8,