Name Redacted ( 2017 )


Menu:
  • ARMED SERVlCES BOARD OF CONTRAC'I`` APPEALS
    Appeals of --
    )
    )
    _ ) ASBCA Nos.é<)zoo,eosoz
    )
    )
    )
    Under Contract Nos. WSJ9JE-15-P-0017
    W5]9JE-15-P-0016
    APPEARANCE FOR THE APPELLANT:
    CEO & President
    APPEARANCES FOR THE GOVERNl\/[ENT: Thomas H. Gourlay, Jr., Esq.
    Engineer Chief Trial Attomey
    Matthew S. Tilghman, Esq.
    Michael E. Taccino, Esq.
    Engineer Trial Attomeys
    U.S. Army Engineer District, Middle East
    Winchester, VA
    OPINION BY ADMINISTRA'I``IVE JUDGE WILSON
    ON THE GOVERNMENT’S MOTION FOR SUlvfMARY JUDGMENT
    These appeals involve the default termination of two contracts to perform
    custodial, maintenance, and ground services on several military bases in Afghanistan.
    The terminations were based on the inability of appellant to gain access to the respective
    bases to perform the contracts due to a determination by the government that appellant
    was a force protection threat to the United States and Coalition Forces. The government
    moves for summary judgment contending that the loss of facility access and subsequent
    inability to provide the required services entitled it to terminate the contract for default.
    Appellant counters that the revocation of its access to the installations was not its fault
    and the government wrongfully terminated its contracts. For the reasons stated below,
    we grant the govemment’s motion.
    STATEMENT OF FACTS §SOF) FOR PURPOSES OF THE MOTlON
    
    ASBCA No. 603
     00 - T he Bagram Contract
    1. On 8 July 2015, the Corps awarded Contract No. W5J9JE-15-P-0017 (Bagram
    contract) to appellant to provide custodial and grounds maintenance services at several
    bases and facilities in Afghanistan (Bagram Airfield, Camp Gamberi, Camp Marmal, the
    Kabul Area Offlce and Qargha). The performance period was from l August 2015
    through 31 December 2017. (R4‘, tabs 6, 7 at 5)
    2. The contract contained the following provisions and F ederal Acquisition
    Regulation (FAR) clause:
    1.7.1. Hours of Operation. The Contractor is responsible for
    conducting business and may be required to work a maximum
    of 48 hours per Week, which Will be eight (8) hours per day,
    six (6) days per Week. All personnel will be scheduled
    through shifts...from 8:00 AM through 4:30 PM....
    1.9.1. Base Security Requirements. The Base security
    maintains the ultimate authority for establishing, monitoring,
    and enforcing security requirements for the work site.... The
    Contractor shall be responsible for compliance With all base
    security requirements The Government reserves the right to
    deny access or to require the Contractor to remove any
    personnel or equipment deemed to be a threat to the security
    of facilities or facility personnel. The Contractor shall work
    through the [contracting officer] to assure that all Security
    Regulations are followed.
    1.9.2. Security and Facility Access. The Contractor will be
    responsible for obtaining all permits, licenses, rights of entry,
    and approvals from all local Govemorate and National
    authorities as necessary for the performance of these services.
    Rights of entry include the ability to obtain the proper
    documentation to ensure that personnel can enter facilities
    controlled by Coalition Forces, the U.S. State Department,
    and the [Govemment of Afghanistan]. Contractor Workforce
    must comply With all personal identity verification
    requirements as directed by DOD, HQDA and/or local policy.
    In addition to the changes otherwise authorized by the
    changes clause of this contract, should the Force Protection
    Condition (FPCON) at any individual facility or installation
    change, the Government may require changes in contractor
    security matters or processes.
    l Each of the Rule 4 references specifically relate to the un-consolidated appeal file
    volume of that particular appeal. For ease of reference, we will discuss each
    appeal separately, but the relevant contract language for both appeals is identical.
    2 .
    52.212-4 CONTRACT TERMS AND CONDITIONS -
    COMMERCIAL ITEMS (DEC 2014)
    (m) Termination for cause. The Govemment may terminate
    this contract, or any part hereof, for cause in the event of any
    default by the Contractor, or if the Contractor fails to comply
    with any contract terms and conditions, or fails to provide the
    Govemment, upon request, with adequate assurances of
    future performance.... If it is determined that the Govemment
    improperly terminated this contract for default, such
    termination shall be deemed a termination for convenience.
    (R4, tab 6 at 10-12, 38, 41) We find that appellant had the responsibility to maintain
    access to the facilities. We further find that the contract required continuous services.
    3. By letter dated 30 July 2015, appellant was given the Notice to Proceed (R4, tab 15).
    4. On 19 September 2015, the Deputy Commander, RS Train, Advise, Assist
    Command-South (TAAC-S), Headquarters, Combined Joint Task Force-7, Kandahar
    Airfield, Afghanistan, issued a “Notice to Vacate Kandahar Airfield.” The letter read as
    follows:
    l. Your business and its operations have been determined to
    be a force protection threat to US and Coalition Forces at
    Kandahar Airfield. Therefore, your access to Kandahar
    Airfield is hereby revoked. Effective immediately your
    business, its operations, and employees will no longer be
    permitted on KAF and will be denied base access in the
    future....
    2. You may submit a request for reconsideration to the
    TAAC-S Force Protection Cell, if you believe this
    determination is based on erroneous information or if the
    circumstances have significantly changed. The request must
    be in writing. Your request for reconsideration will be
    forwarded to the Resolute Support and United States _
    Forces-Afghanistan Force Protection Cells. Any requests for
    reconsideration must be received within five days from
    receipt of this notice.
    (R4, tab 16) As a result of this determination, appellant was unable to access any of the
    U.S. and Coalition force bases in Afghanistan (R4, tab 19; gov’t mot., ex. l).
    5. On 24 September 2015, the contracting officer terminated the contract for
    cause pursuant to the contract clause FAR 52.212-4(m) due to lack of base access (R4,
    tab 4).
    6. By letter dated 5 October 2015, the Corps requested that appellant submit a
    final invoice for work performed during the 1-24 September 2015 contract period (R4,
    tab 22). In response, appellant submitted an invoice that was approved and paid in full by
    the Corps (R4, tabs 20, 21).
    7. On 27 October 2015, appellant filed a timely notice of appeal with the Board
    from the termination for cause of the Bagram Contract, which was docketed as 
    ASBCA No. 60300
    .
    
    ASBCA No. 603
     02 - T he Kandahar Contract
    8. On 6 July 2015, the Corps awarded Contract No. W5]9JE-15-P-0016
    (Kandahar Contract) to appellant for janitorial services, maintenance and repair Services
    (including parts and supplies), and generator preventative maintenance services at
    Kandahar Airfield in Afghanistan (R4, tab 5).
    9. The contract specified that the work was to be done on a daily basis (6 days a
    week for custodial services) while other work was to be accomplished on a monthly basis
    or emergency repairs; and general facilities support, which had to be accomplished within
    24-48 hours of a request (R4, tab 5 at 13, 36).
    ' 10. The contract contained the identical access provisions and clause as the
    Bagram Contract (see SOF 11 2).
    ll. As a result of the same letter from TAAC-S (SOF 11 4) appellant’s access to
    Kandahar Airfield was revoked. Subsequently, on 24 September 2015, the contracting
    officer terminated the contract for cause pursuant to the contract clause FAR 52.212-4(m)
    (R4, tabs 3,’ 19).
    12. The Corps requested invoices for work completed up to the date of termination
    (R4, tab 22). Appellant submitted an invoice (R4, tab 20), which was paid (R4, tab 21).
    13. On 27 October 2015, appellant filed a timely notice of appeal from the
    termination for cause of the Kandahar Contract, which was docketed as 
    ASBCA No. 60302
    .
    14. In support of its motion, the government offered a declaration from
    Ms. Cherita Williams, the contracting officer (CO) who terminated the contracts at issue.
    CO Williams states:
    3. On 19 September 2015, the Deputy Commander of the ,
    U.S. Military organization responsible for security on
    Kandahar Airfield issued a memorandum that begins as
    follows: “Your business and its operations have been
    determined to be a force protection threat to US and Coalition
    Forces at Kandahar Airfield. Therefore, your access to
    Kandahar Airfield is hereby revoked.”
    4. At the time when [the Corps] terminated the Contracts, a
    system of vendor vetting was in place for U.S. Govemment
    contractors in Afghanistan. The system is intended to prevent
    the U.S. Govemment from contracting with entities that
    support insurgent groups in Afghanistan. The U.S.
    Government personnel who are responsible for vendor vetting
    make determinations that have dispositive effect on vendors’
    access to U.S. Military installations based on classified
    intelligence information.
    5. At the time when I terminated the Contracts, I had
    personal knowledge that the revocation of [appellant’s] access
    to Kandahar Airfield was the direct result of a vendor vetting
    determination of the kind described in paragraph 4.
    6'. Further, at the time when I terminated the Contracts, based
    on my understanding of the vendor vetting process, I knew
    that the revocation of [appellant’s] installation access applied
    to all U.S. Military installations
    7. After the issuance of the memorandum to [appellant],
    informing it of the revocation of its base access on
    19 September 2015 and before I terminated the Contracts for
    cause, [appellant] ceased performing the services required by
    the Contracts because its personnel did not have access to the
    installations where the services under the Contracts were
    required to be performed.
    (Gov’t mot., ex. 1)
    DECISION
    Summary judgment is appropriate when there is no genuine issue of material fact
    and the movant is entitled to judgment as a matter of law. Proverz``s Scz'entijic Corp. v.
    Innovasystems, Inc., 
    739 F.3d 1367
    , 1371 (Fed. Cir. 2014); Mz``ngus Constructors, Inc. v.
    United States, 
    812 F.2d 1387
    , 1390-91 (Fed. Cir. 1987). A material fact is one that may
    affect the outcome of the decision. Anderson v. Lz'berly Lobby, Inc., 
    477 U.S. 242
    ,
    248-49 (1986). The moving party bears the burden of establishing the absence of any
    genuine issue of material fact, and all significant doubt over factual issues must be
    resolved in favor of the party opposing summary judgment However, more than mere
    assertions are necessary to counter a motion for summary judgment The government
    bears the burden of proof on the issue of correctness of its actions in terminating a
    contractor for cause, See Lz``sbon Contractors, Inc. v. United States, 
    828 F.2d 759
    , 764
    (Fed. Cir. 1987).
    The government contends that it is entitled to summary judgment because the
    terminations for cause were justified as appellant failed to maintain facility access and to
    provide continuous services and did not offer valid excuses for its breaches of contract
    (gov’t mot. at 7).
    Appellant counters, inter alia, that it had no control over vendor vetting and the
    removal of base access was not its fault (app. reply at 1). In support of its opposition,
    appellant offered exhibits that do not add anything to the discussion nor do they show any
    facts that may be in dispute regarding the termination.
    Here, the undisputed record shows that appellant lost its access to the bases that it was
    contractually obligated to maintain (SOF 1[1[ 2, 4, 11). The fact that the government entity that
    controlled base access was beyond appellant’s control is not a valid excuse for non-performance.
    As such, appellant breached the contracts and the government has met its burden of proof that it
    properly terminated the contracts for cause, Therefore, finding that there are no disputed
    material facts and that the government is entitled to judgment as a matter of law, the motion for
    summary judgment is granted.
    CONCLUSION
    The appeals are denied.
    Dated: 29 March 2017
    I concur
    /’ / W "
    ’ MARK N. sTEMPLER /
    Administrative Judge
    Acting Chairman
    Armed Services Board
    of Contract Appeals
    OWEN C. WILSON
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    l concur
    RICHARD SHACKLEFORD
    Administrative Judge
    Vice Chairman
    Armed Services Board
    of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the Armed
    Services Board of Contract Appeals in ASBCA Nos. 60300, 60302, Appeals of -
    _, rendered in conformance with the Board’s Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    

Document Info

Docket Number: ASBCA No. 60300, 60302

Judges: Wilson

Filed Date: 3/29/2017

Precedential Status: Precedential

Modified Date: 4/10/2017