Arab Shah Construction Company ( 2019 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                  )
    )
    Arab Shah Construction Company                )      ASBCA No. 61565
    )
    Under Contract No. W912ER-l 7-A-0005          )
    APPEARANCE FOR THE APPELLANT:                        Mr. Mohammad Idrees
    Director
    APPEARANCES FOR THE GOVERNMENT:                      Michael P. Goodman, Esq.
    Engineer Chief Trial Attorney
    Michael E. Taccino, Esq.
    Aimee L. Rider, Esq.
    Engineer Trial Attorneys
    U.S. Army Engineer District, Middle East
    Winchester, VA
    OPINION BY ADMINISTRATIVE JUDGE YOUNGER ON THE
    GOVERNMENT'S MOTION TO DISMISS FOR FAILURE TO STATE A CLAIM
    UPON WHICH RELIEF CAN BE GRANTED
    Appellant Arab Shah Construction Company (appellant) has appealed from the
    Army Corps of Engineers' (Corps') decision to terminate its contract for cause. The
    Corps has moved to dismiss the appeal for failure to state a claim upon which relief
    can be granted, arguing that appellant's complaint did not explicitly dispute the
    termination or make a specific request for relief. We deny the motion.
    STATEMENT OF FACTS FOR PURPOSES OF THE MOTION
    1. By date of December 7, 2016, the Corps awarded Contract No. W912ER-17-A-0005
    (contract) to appellant for diesel generator repair services at power plants located throughout
    Afghanistan (R4, tab 3 at 1, 4} Under the contract, identified as a blanket purchase
    agreement, the Corps would issue orders for appellant to perform the contracted services
    (gov't mot. at 1). The contract referred to those orders as "calls" (R4, tab 3 at 1, tab 4 at 1).
    2. The contract included FAR 52.212-4, CONTRACT TERMS AND CONDITIONS
    COMMERCIAL ITEMS (MAY 2015). Subparagraph (m) of that clause provides the
    government with authority to terminate a contract for cause "in the event of any default
    by the Contractor, or if the Contractor fails to comply with any contract terms and
    conditions, or fails to provide the Government, upon request, with adequate assurances
    of future performance." That subparagraph further provides that "[i]f it is determined
    f
    f
    that the Government improperly terminated this contract for default, such termination
    shall be deemed a termination for convenience." In a separate subparagraph, the
    clause provides that "the Contractor shall be liable for default unless nonperformance
    is caused by an occurrence beyond the reasonable control of the Contractor and
    without its fault or negligence." FAR 52.212-4(f). (R4, tab 3 at 49)
    3. By date of December 15, 2017, the Corps issued a cure notice advising
    appellant that its performance under Call 0003 (Call 3) was deficient and "endangering
    performance under the subject contract" (R4, tab 48 at 1). The cure notice included a
    detailed timeline describing the problems encountered with appellant's performance
    on three generators located at two different power plants (id. at 2-5). The cure notice
    further directed appellant to respond in writing to the contracting officer within
    10 days with a schedule of actions it would take to remedy its deficient performance,
    and to provide a list consisting of manufacturer verification of part and/or serial
    numbers for the replaced parts (id. at 5).
    4. By email dated December 20, 2017, appellant submitted a 48-page response to
    the cure notice that consisted primarily of photographs of various items appearing to be
    parts that were to be installed during contract performance (gov't mot. at 2; R4, tab 49).
    The response briefly described certain actions appellant had either already taken or
    intended to take, and asserted that with respect to one of the generators, the contractor
    responsible for maintenance was not changing the generator's oil in a timely fashion or
    using good quality oil, which impacted its performance (R4, tab 49 at 8-10). Appellant's
    response also included a chart that listed parts and part numbers (id. at 47-48).
    5. In a memorandum for record dated December 29, 2017, the contracting
    officer documented her decision to terminate the contract for cause under
    FAR 52.212-4 for failure to adequately respond to the cure notice (R4, tab 127 at 1-3).
    By letter of the same date, the contracting officer issued the termination notice, finding
    appellant in default "for failure to include a feasible recovery schedule of actions
    [appellant] will take to remedy its deficient performance" with respect to two of the
    three generators identified in the cure notice, and for failure to provide the parts list
    verifying part and/or serial numbers for parts replaced in the generators (R4, tab 2 at 1).
    6. The termination notice described the problems with the two generators
    in substantial detail. With respect to the first generator, the notice described a
    turbocharger "glowing red hot" and continuing to overheat even after appellant
    replaced three fuel injectors. The notice also stated that the Corps had photographic
    evidence showing that replacement parts installed on that generator were not
    "authentic OEM" (original equipment manufacturer), and that appellant was using
    parts with no identifiable serial or part numbers. With respect to the second generator,
    the notice indicated that appellant failed to present a realistic timeline to turn the
    generator over to the end user and failed to identify and validate the replacement parts.
    2
    The notice further stated that photographic evidence indicated that appellant was
    re-using parts instead of replacing them with new parts, which could impact the
    generator's ability to provide sustained use, and that there "is no evidence this
    generator was turned on or could take any sort of load." (Id at 1-2)
    7. By email dated March 24, 2018, appellant filed its notice of appeal with the
    Board, and attached a copy of the termination notice. The notice of appeal described
    in detail certain problems appellant encountered with performance, and quoted and
    specifically responded to the performance deficiencies identified in the termination
    notice. The notice of appeal also repeated appellant's contention that the maintenance
    contractor's failure to properly maintain one of the generators was responsible for the
    performance deficiencies, and included a copy of the parts list provided in its response
    to the cure notice.
    8. By email dated April 18, 2018, appellant filed its complaint with the Board.
    The complaint included some unrelated discussion of Calls 1 and 2; with respect to
    Call 3, it stated that another contractor "was creating problems" for appellant by not
    allowing it to start work. The complaint further stated that this other contractor
    claimed that one of the generators was covered by its contract with the Corps, not
    appellant's, and that the other contractor had stolen some of that generator's parts.
    (Compl. at 1-2)
    9. The complaint also referenced a number of attachments consisting of emails
    and email chains between appellant and various Corps representatives, in which it
    raised concerns with respect to the other contractor (whom appellant identified as the
    maintenance contractor). In a February 20, 2017 email, appellant informed the Corps
    that the maintenance contractor would "not [allow] us to start the work they claimed
    they will fix it and it's on their contract." The February 20, 2017 email also noted that
    when appellant raised this issue with Corps representatives its complaints were
    ignored. Appellant repeated its contention regarding the maintenance contractor
    "creating these problems" in an email dated March 9, 2017. In two additional emails,
    dated October 7 and October 11, 2017, appellant informed the Corps that the
    maintenance contractor was not properly changing the oil and filter on one of the
    generators.
    DECISION
    The Corps has moved to dismiss this appeal for failure to state a claim upon
    which relief can be granted, arguing that appellant has "neither set forth a recognizable
    claim nor claimed entitlement to any relief' (gov't mot. at 3). Appellant opposes the
    motion, repeating its contention that the maintenance contractor denied it access to the
    site and failed to properly perform its maintenance obligations (app. opp'n at 1-3).
    3
    l
    ·.I
    }
    I
    I
    The standards for deciding a motion to dismiss for failure to state a claim upon
    which relief can be granted are well established. A motion to dismiss for failure to
    state a claim can be granted where the facts asserted in the complaint do not entitle
    the claimant to a legal remedy. See Lindsay v. United States, 
    295 F.3d 1252
    , 1257
    (Fed. Cir. 2002). The complaint must allege facts "'plausibly suggesting (not merely
    consistent with)' a showing of entitlement to relief." Cary v. United States, 
    552 F.3d 1373
    , 1376 (Fed. Cir. 2009) (quoting Bell Atlantic Corp. v. Twombly, 
    550 U.S. 544
    ,
    557 (2007)); American General Trading & Contracting, WLL, ASBCA No. 56758,
    12-1 BCA ,r 34,905 at 171,640. In ruling on such a motion, we "must accept
    well-pleaded factual allegations as true and must draw all reasonable inferences in
    favor of the claimant," Kellogg Brown & Root Sen1ices, Inc. v. United States, 
    728 F.3d 1348
    , 1365 (Fed. Cir. 2013), and decide "only whether the claimant is entitled to offer
    evidence in support of its claims, not whether the claimant will ultimately prevail."
    Matcon Diamond, Inc., ASBCA No. 59637, 15-1 BCA ,r 36,144 at 176,407. The
    scope of our review is limited to considering the sufficiency of the allegations set forth
    in the complaint, "matters incorporated by reference or integral to the claim, items
    subject to judicial notice, [and] matters of public record." A&D Auto Sales, Inc. v.
    United States, 
    748 F.3d 1142
    , 1147 (Fed. Cir. 2014) (alteration in original) (internal
    quotation marks and citation omitted); see Zak v. Chelsea Therapeutics Int 'l, Ltd,
    780 F.3d 597,606 (4th Cir. 2015) (On a motion to dismiss for failure to state a claim,
    courts may consider documents attached or incorporated into the complaint.).
    Although the Corps describes appellant's complaint as failing to explain its
    allegations or request any actual relief (gov't mot. at 2), "the primary document setting
    forth the claim is not the complaint, per se, but is either the contractor's claim or the
    government's claim, the latter asserted in a contracting officer's final decision as
    required by the Contract Disputes Act." Lockheed Martin Integrated Systems, Inc.,
    ASBCA Nos. 59508, 59509, 17-1 BCA ,r 36,597 at 178,281. Thus, in addition to
    appellant's complaint, we look to the Corps' December 29, 2017 termination notice.
    See Jurass Company, ASBCA No. 51527, 06-1 BCA ,r 33,186 at 164,503 (termination
    for cause is a government claim).
    Read in conjunction with the termination notice, appellant's complaint alleges
    sufficient facts '"plausibly suggesting (not merely consistent with)' a showing of
    entitlement to relief." See 
    Cary, 552 F.3d at 1376
    ; American General Trading &
    Contracting, 12-1 BCA ,r 34,905 at 171,640. The Corps' termination notice describes
    I
    in detail the problems encountered with the generators covered by Call 3 (statement 6).
    Appellant's complaint incorporated the emails submitted as attachments, in which it
    specifically communicated to the Corps that the maintenance contractor was
    interfering with its access to the site and was not properly changing the generator's oil
    and filter (statements 8-9). A contractor's default may be excused "if it is caused by
    Il
    ..
    ,,
    an occurrence that is beyond its reasonable control and without its fault or
    4                                                I:
    i
    negligence." Earthstar Constn1ction and Logistics Company, ASBCA No. 58086,
    13 BCA 135,461 at 173,901; see statement 2. Appellant's allegations regarding the
    problems it encountered with the maintenance contractor, and the impact of those
    problems on its performance, go to the question of whether its alleged performance
    deficiencies can be excused.
    With respect to the Corps' claim that appellant's complaint failed to request any
    form of relief, the Corps has not cited, and we are unaware of, any precedent requiring
    an appellant's complaint to recite a specific request for relief. The Board's rules, like
    the Federal Rules of Civil Procedure, only require notice pleading. UniTech Services
    Group, Inc., ASBCA No. 56482, 10-1 BCA 134,362 at 169,695. By virtue of
    filing its notice of appeal, it is clear that appellant did not agree with, and was
    challenging, the Corps' decision to terminate its contract for cause. Under the
    contract's terms, "[i]f it is determined that the Government improperly terminated this
    contract for default, such termination shall be deemed a termination for convenience."
    FAR 52.212-4(£); see statement 2. Although appellant did not explicitly request the
    termination for cause be converted to a one for convenience, that form of relief is a
    logical inference from appellant's decision to file this appeal.
    CONCLUSION
    The government's motion is denied.
    Dated: February 12, 2019
    Administrative Judg ___
    Armed Services Board
    of Contract Appeals
    I concur
    RICHARD SHACKLEFORD                               OWENC~SON
    Administrative Judge                              Administrative Judge
    Acting Chairman                                   Vice Chairman
    Armed Services Board                              Armed Services Board
    of Contract Appeals                               of Contract Appeals
    5                                                f
    I
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA No. 61565, Appeal of Arab
    Shah Construction Company, rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    6
    l
    

Document Info

Docket Number: ASBCA No. 61565

Judges: Younger

Filed Date: 2/12/2019

Precedential Status: Precedential

Modified Date: 2/25/2019