DLT Solutions, LLC ( 2022 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of -                                   )
    )
    DLT Solutions, LLC                            )   
    ASBCA No. 63069
    )
    Under Contract No. W52P1J-18-A-0001           )
    Order No. M67854-19-F-4035              )
    APPEARANCES FOR THE APPELLANT:                    Thomas O. Mason, Esq.
    Joseph R. Berger, Esq.
    Mona Adabi, Esq.
    Brian Lamb, Esq.
    Thompson Hine LLP
    Washington, DC
    APPEARANCES FOR THE GOVERNMENT:                   Craig D. Jensen, Esq.
    Navy Chief Trial Attorney
    Antonio Robinson, Esq.
    Trial Attorney
    OPINION BY ADMINISTRATIVE JUDGE SWEET ON THE GOVERNMENT’S
    MOTIONS TO DISMISS
    This appeal involves an order by the United States Marine Corps (Ordering
    Activity) under a blanket purchase agreement awarded from a General Services
    Administration (GSA) Federal Supply Schedule contract for a software license and
    associated maintenance and support. The order was for a base year and four option years.
    It also contained provisions that required the Ordering Activity to exercise the options so
    long as there was a bona fide need for the software, and certify that the Ordering Activity
    deleted the software once the order expired. However, the Ordering Activity declined to
    exercise the options, and did not certify that it deleted the software. Appellant DLT
    Solutions, LLC (DLT) raises breach of contract, breach of the covenant of good faith and
    fair dealing, superior knowledge, fraudulent inducement, and estoppel claims.
    The Ordering Activity has moved to dismiss all of the claims for lack of
    jurisdiction, arguing that there was not an adequate claim because DLT should have
    presented its claim to a GSA contracting officer (CO), and not to an Ordering Activity
    CO (Ordering CO). In the alternative, the Ordering Activity moves to dismiss the
    superior knowledge, fraudulent inducement, and the estoppel claims for lack of
    jurisdiction because they are a new claim, allege fraud, and seek promissory estoppel
    respectively. Finally, the Ordering Activity moves to dismiss all of the claims for failure
    to state a claim.
    For the reasons discussed below, we deny the motion to dismiss all of the claims
    because DLT properly presented its claim to the Ordering CO. However, we grant the
    motion to dismiss the superior knowledge claim and the fraudulent inducement claim for
    lack of jurisdiction because they are new claims that DLT did not present to the Ordering
    CO. 1 We also strike the estoppel claim because a portion of that claim seeks specific
    performance or injunctive relief, and the remainder of the claim does not assert an
    independent basis for entitlement to relief. Finally, we deny the motion to dismiss for
    failure to state a claim.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTIONS
    I. The Contracts
    1. From April 11, 2016 through April 10, 2021, DLT entered into Federal Supply
    Schedule Contract GS-35F-267DA (Schedule Contract) with the GSA for various
    computer software services, including services related to Quest software (gov’t br. ex. 1
    at 1-2). 2 The Schedule Contract contained several provisions that the Ordering Activity
    argues are relevant. First, the Schedule Contract contained an Annual Funding Provision,
    which stated that:
    When annually appropriated funds are cited on a maintenance
    order, the period of maintenance shall automatically expire on
    September 30th of the contract period, or at the end of the
    contract period, whichever occurs first. Renewal of a
    maintenance order citing the new appropriation shall be
    required, if maintenance is to continue during any remainder
    of the contract period.
    (Id. at 19) Second, the Schedule Contract contained a Payments Provision, which stated
    that:
    For firm-fixed price orders the ordering activity shall pay the
    Contractor, upon submission of proper invoices or vouchers,
    1
    While the Ordering Activity only moved to dismiss the superior knowledge claim on the
    grounds that it was a new claim (mot. at 14-18), we also dismiss the fraudulent
    inducement claim pursuant to our authority to address jurisdictional issues sua
    sponte, Sharp Elec. Corp. v. McHugh, 
    707 F.3d 1367
    , 1370 (Fed. Cir. 2013),
    because it also is a new claim for the reasons discussed above.
    2
    All citations to exhibit 1 to the Ordering Activity’s brief are to the PDF page number.
    2
    the prices stipulated in this contract for service rendered and
    accepted. Progress payments shall be made only when
    authorized by the order. For time-and-materials orders, the
    Payments under Time-and-Materials and Labor-Hour
    Contracts at FAR 52.212-4 (MAR 2009) (ALTERNATE I –
    OCT 2008) (DEVIATION I – FEB 2007) applies to time-and-
    materials orders placed under this contract. For labor-hour
    orders, the Payment under Time-and-Materials and Labor-
    Hour Contracts at FAR 52.212-4 (MAR 2009)
    (ALTERNATE I – OCT 2008) (DEVIATION I – FEB 2007)
    applies to labor-hour orders placed under this contract.
    (Id. at 60) Finally, the Schedule Contract contained an Order of Precedence Provision,
    which stated that the Schedule Contract will take precedence over any order in the event
    of a conflict (id. at 43, 52, 58, 62).
    2. On November 20, 2017, the United States Army Contracting Command
    awarded Blanket Purchase Agreement No. W52P1J-18-A-0001 (BPA) to DLT from the
    Schedule Contract to reduce the administrative cost of acquiring commercial software
    and services, including services related to Quest software (R4, tab 1 at 1-3). The BPA
    included the Transaction Software Agreement with Quest, which stated that
    “[c]ancellation of Maintenance Services for perpetual Licenses for On-Premise Software
    will not terminate Customer’s rights to continue to use the On-Premise Software” (R4,
    tab 1.1 at 19). The BPA also included a Department of Defense (DOD) Electronically
    Stored Information Supplement to the GSA Exclusive Use License Agreement (EULA),
    which contained a Re-Use Provision stating that “[n]othing in this License Grant or
    elsewhere in this EULA or in other documents concerning this license or the software
    licensed herein shall preclude Licensee from licensing other identical, similar or
    competitive software from other Publishers or Resellers at any time and for any reason
    whatsoever” (R4, tab 1.2 at 24, 28).
    3. On January 29, 2019, the Ordering Activity published Solicitation
    No. M67854-19-Q-4035 (Solicitation) for Quest perpetual licenses and associated
    maintenance and support (app. supp. R4, tab 1-2 at 28-35).
    4. On March 12, 2019, DLT submitted its quote (Quote) to the government. It
    was the only potential contractor to do so. (R4, tab 2 at 69) The Quote required that the
    Order contain a Bona Fide Needs Provision, stating that “[i]t is the intent of the
    Government by placing this Order to exercise each renewal option so long as the bona
    fide needs of the Government for the products or functionally similar products continues
    3
    to exist and the requirements of FAR 17.207 are satisfied” (id. at 74). The Quote also
    contained a Certification Provision, which stated that:
    Within (30) days after the date of expiration or termination of
    any Order in which the Government has not exercised a
    purchase option to acquire the software license, the
    Government shall, at its own risk and expense, have the
    software removed. In connection with such removal of
    software, the Government shall certify in writing to the
    Contractor that the Government has (a) deleted or disabled all
    files and copies of the software from the equipment on which
    it was installed; [and] (b) has no ability to use the returned
    software.
    (id.).
    5. Based upon the solicitation and the Quote, the Ordering Activity awarded
    Order No. M67854-19-F-4035 (Order) on the BPA to DLT for Quest perpetual licenses
    and associated maintenance and support (R4, tab 2 at 31-39). The Order was for one base
    year and four option years (id. at 33-59). The Order also incorporated the Quote (id.
    at 66). The Order was a firm fixed price (FFP) contract, and not a time-and-material or
    labor-hour order (id. at 33-39). Moreover, the Ordering Activity has not established that
    the Order cited annual appropriated funds or that it acquired the software subject to an
    agreement requiring it to indemnify others (id. at 31-77).
    II. Performance
    6. After DLT performed the base year, the Ordering Activity did not exercise the
    first option (compl. ¶¶ 58-60).
    7. DLT alleges that the Ordering Activity has not certified that it deleted or
    disabled all files and copies of the software from the equipment on which it was installed,
    or that it has no ability to use the returned software (Certification) (compl. ¶ 50).
    III. Procedural History
    8. On March 22, 2021, DLT presented a claim to the Ordering CO (R4, tab 4
    at 80). The claim asserted that the Ordering Activity breached the Order by failing to
    exercise the options when there was a bona fide need for the Quest software or a
    functionally similar product, and failing to provide a Certification (id. at 81-83). The
    Claim did not allege that the Ordering Activity knew pre-award that it intended to not
    exercise the options, or that the Ordering Activity failed to disclose, or misrepresented,
    any such knowledge (id. at 80-89).
    4
    9. The Ordering CO issued a CO final decision (COFD) on July 23, 2021 (R4,
    tab 6 at 145).
    10. DLT then filed this appeal. The complaint alleges five counts. First, the
    complaint alleges that the Ordering Activity breached the Bona Fide Needs Provision and
    the covenant of good faith and fair dealing by failing to exercise the options when there
    was a bona fide need for the Quest software or a functionally similar product (compl. ¶¶
    133-36). Second, the complaint alleges that the Ordering Activity breached the
    Certification Provision and the covenant of good faith and fair dealing by failing to
    provide a Certification (id. at ¶¶ 137-41). Third, the complaint alleges that the Ordering
    Activity fraudulently induced DLT to enter into the Order by misrepresentation pre-
    award that it intended to exercise the options if there was a bona fide need, knowing that
    it intended not to exercise the options (id. at ¶¶ 146-47). Fourth, the complaint alleges
    that the Ordering Activity should be estopped from arguing that the Bona Fide Needs
    Provision or the Certification Provision was a nullity, from arguing that either provision
    was superseded by other contractual language, and from using functionally similar
    products when a bona fide need continues to exist (id. at ¶ 154). Fifth, the complaint
    alleges that the Ordering Activity acted with superior knowledge when it failed to
    disclose pre-award its knowledge that it intended not to exercise the options (id. at ¶ 161-
    62). There is no allegation that there was an implied-in-fact contract, apart from the
    implied covenant of good faith and fair dealing. (Id. at ¶¶ 1-163)
    DECISION
    As discussed in greater detail below, we deny the Ordering Activity’s motion to
    dismiss all counts for failure to present a claim to the GSA CO because this dispute does
    not require interpretation of the Schedule Contract, so DLT properly presented its claim
    to the Ordering CO. However, we grant the motion to dismiss the superior knowledge
    and fraudulent inducement claims because those are new claims that DLT failed to
    present to the Ordering CO. We also strike the estoppel claim because a portion of that
    claim seeks specific performance or injunctive relief, and the remainder of the claim does
    not assert an independent basis for entitlement to relief. Finally, we deny the motion to
    dismiss for failure to state a claim because DLT plausibly alleges a claim.
    I. The Failure of DLT to Present a Claim to the GSA CO does not Deprive the Board of
    Jurisdiction
    The failure of DLT to present a claim to the GSA CO does not deprive the Board
    of jurisdiction over this appeal. Under the Contract Disputes Act (CDA), 
    41 U.S.C. §§ 7101-09
    , we only possess jurisdiction over a claim if a contractor presented that claim to
    an authorized CO, and the CO issued a final decision on that claim. 
    41 U.S.C. § 7103
    (a)(1)-(3); Reflectone, Inc. v. Dalton, 
    60 F.3d 1572
    , 1575 (Fed. Cir. 1995) (en banc).
    As a result, when an appeal involves an order from a schedule contract, we do not possess
    5
    jurisdiction when a contractor presents a claim to the wrong CO. Sharp Elec. Corp. v.
    McHugh, 
    707 F.3d 1367
    , 1372-74 (Fed. Cir. 2013); see also 
    48 C.F.R. § 8.406-6
    . In
    determining who is the wrong CO:
    FAR 8.406-6 does not authorize an ordering CO to decide a
    dispute requiring interpretation of schedule contract
    provisions, in whole or in part, regardless of whether the
    parties frame the dispute as pertaining to performance.
    However, the ordering CO is certainly authorized to construe
    the language of the order (or its modifications). . . . We also
    see no reason why an ordering CO resolving a dispute cannot
    apply the relevant provisions of the schedule contract, as long
    as their meaning is undisputed. . . . The dispute only need go
    to the GSA CO if it requires interpretation of the schedule
    contract’s terms and provisions.
    Sharp Elec., 707 F.3d at 1374. The “application of this rule is not necessarily determined
    by how the parties frame the issues and does not prevent the [ordering] CO from
    construing the language of the order or to apply relevant provisions of the schedule
    contract as long as there is no dispute in their meaning.” Hewlett-Packard Co., 
    ASBCA No. 57941
    , 
    13 BCA ¶ 35,366
     at 173,550.
    Here, DLT properly presented its claim to the Ordering CO because the dispute
    does not require interpretation of the Schedule Contract. According to the complaint, this
    dispute is about whether the Ordering Activity breached the Order’s Bona Fide Needs
    Provision and Certification Provision by failing to exercise the options when there was a
    bona fide need, and failing to provide Certifications (SOF ¶ 10). Those issues pertain to
    the performance or the construction of the Order, and do not require any interpretation of
    the Schedule Contract.
    In response, the Ordering Activity raises several meritless arguments about why—
    looking beyond how DLT frames the issue—this dispute may require interpretation of the
    Schedule Contract. First, the Ordering Activity speculates that this dispute may require
    interpretation of the Schedule Contract because its Annual Funding Provision may
    conflict with the Bona Fide Needs Provision by prohibiting renewal of an order (mot.
    at 10-11). However, the Ordering Activity has not raised a genuine dispute suggesting
    that the Annual Funding Provision even applies here because that provision only applies
    “[w]hen annual appropriated funds are cited on a maintenance order,” (SOF ¶ 1), and the
    Ordering Activity has failed to even assert—let alone establish—that the Order cited
    annual appropriated funds (mot. at 10-11; SOF ¶ 5). In any event, instead of prohibiting
    renewal, the Annual Funding Provision mandated renewal of an order at the end of the
    fiscal year—if the maintenance was to continue (SOF ¶ 1). The Annual Funding
    Provision did require that a renewal cite the new appropriation (Id.). While not clearly
    6
    spelled out, it appears that the Ordering Activity may be inferring from that requirement
    that the Annual Funding Provision prohibited renewal when the agency used annually
    appropriated funds and there was no new appropriation (mot. at 10-11). However, that
    prohibition would not be in dispute because the Anti-Deficiency Act, 
    31 U.S.C. § 1341
    (ADA) prohibits such renewals. MACH I AREP Carlyle Center, LLC, 
    ASBCA No. 59821
    , 
    16-1 BCA ¶ 36,389
     at 177,418 (quoting Letter v. United States, 
    271 U.S. 204
    , 207 (1926)). Thus, while the Ordering Activity may frame the issue as whether the
    Bona Fide Needs Provision conflicts with the Annual Funding Provision, the Ordering
    Activity’s true dispute is whether the Bona Fide Needs Provision conflicts with the
    ADA—which is an issue of statutory interpretation that does not require interpretation of
    the Schedule Contract.
    Second, the Ordering Activity speculates that this dispute may require
    interpretation of the Schedule Contract because its Payment Provision may conflict with
    the Bona Fide Needs Provision by requiring the application of Federal Acquisition
    Regulation (FAR) 52.212-4, which in turn requires the application of the ADA (mot. at
    12). However, the Ordering Activity has not raised a genuine dispute suggesting that the
    Payment Provision required the application of FAR 52.212-4 here because the Payment
    Provision only required the application of FAR 52.212-4 to time-and-material and labor-
    hour orders—and not to FFP orders—and the Order was an FFP order (SOF ¶¶ 1, 5).
    Moreover, the Ordering Activity has not raised a genuine dispute suggesting that the
    version of FAR 52.212-4 cited by the Payment Provision required the application of the
    ADA. On the contrary, while the current version of FAR 52.212-4 requires the
    application of the ADA, 
    48 C.F.R. § 52.212-4
    (u)(1) (NOV 2021), the version of FAR
    52.212-4 cited by the Payment Provision—namely the March 2009 version (SOF ¶ 1)—
    did not require the application of the ADA. 
    48 C.F.R. § 52.212-4
     (MAR 2009). 3 In any
    event, while the Ordering Activity may frame the issue as whether the Bona Fide Needs
    Clause conflicts with the Payment Clause, the Ordering Activity’s true dispute once again
    is whether the Bona Fide Needs Provision conflicts with the ADA.
    Third, the Ordering Activity argues that the BPA Transaction Software Agreement
    and the BPA Re-Use Provision may conflict with the Bona Fide Needs Provision and the
    Certification Provision (mot. at 12, 14). 4 Even assuming without deciding that the
    3
    Further, the current version of FAR 52.212-4 merely addresses when the government
    acquires a supply or service subject to an agreement requiring the government to
    indemnify others in violation of the ADA. 
    48 C.F.R. § 52.212-4
     (u)(1). The
    Ordering Activity has not raised a genuine dispute suggesting that that provision
    would apply here because it fails to even assert—let alone establish—that it
    acquired the software subject to an agreement requiring it to indemnify others
    (mot. at 12; SOF ¶ 5).
    4
    Citing R4, tab 1 at 4-5, the Ordering Activity also claims that the BPA incorporates
    FAR 52.217-9 (Option to Extend the Term of Contract) (MAR 2000) (mot. at 13).
    7
    Ordering Activity is correct that the Order conflicted with the BPA, that would not
    support the conclusion that DLT should have presented its claim to the GSA CO because
    it merely would establish that this dispute requires interpretation of the BPA, and not the
    Schedule Contract. If—as is the case here—a claim raises a dispute requiring an
    interpretation of a BPA issued by a different DOD service than the ordering activity, 5
    then the contractor should present that claim to the ordering activity. Hewlett-Packard,
    
    13 BCA ¶ 35,366
     at 173,551-52. That is because “for purposes of CDA jurisdiction, any
    interpretation required of the BPA terms must be viewed as an interpretation of [the
    orders] since those orders were the vehicles that formed the contracts.” 
    Id. at 173,552
    .
    Thus, DLT properly presented any disputes regarding BPA interpretation to the Ordering
    CO.
    Fourth, the Ordering Activity speculates that this dispute may require
    interpretation of the Schedule Contract because its Order of Precedence Provision is
    essential to this dispute (mot. at 10). However, “we only resort to an order of precedence
    provision when there is an actual conflict or inconsistency between different contract
    provisions.” Gen. Dynamics-Nat’l Steel and Shipbuilding Co., 
    ASBCA No. 61524
    , 
    22-1 BCA ¶ 38,067
     at 184,826. As discussed above, the Ordering Activity has failed to raise a
    genuine dispute suggesting an actual conflict or inconsistency between any Schedule
    Contract provision and the Order. Therefore, the Ordering Activity has failed to raise a
    genuine dispute suggesting that the Order of Precedence Provision applies or is essential
    to this dispute.
    Fifth, the Ordering Activity speculates that the Bona Fide Needs Provision
    requires interpretation of the Schedule Contract’s product terms by calling into question
    whether the Ordering Activity used functionally similar products (mot. at 13). However,
    the Ordering Activity does not even cite any particular Schedule Contract provisions—let
    alone show that those provisions require interpretation (id.); Sharp Elec., 707 F.3d
    at 1374. Because this dispute does not require interpretation of the Schedule Contract,
    DLT did not need to present its claim to the GSA CO in order to establish our
    jurisdiction.
    However, the cited pages do not incorporate FAR 52.217-9 (R4, tab 1 at 4-5). In
    any event, any claim that any BPA FAR 52.217-9 conflicts with the Bona Fide
    Needs Provision would not be a basis for requiring DLT to present a claim to the
    GSA CO for the reasons discussed above.
    5
    Recall that the BPA here was issued by the Army.
    8
    II. We do not Possess Jurisdiction Over the Superior Knowledge Claim and the
    Fraudulent Inducement Claim Because Those are new Claims That DLT did not
    Present to the CO
    We do not possess jurisdiction over the superior knowledge claim and the
    fraudulent inducement claim because those are new claims that DLT did not present to
    the CO. We do not possess jurisdiction to entertain a claim if it is a new claim that the
    appellant did not present to the CO. Nassar Grp. Int’l, 
    ASBCA No. 58451
     et al., 19-
    
    1 BCA ¶ 37,405
     at 181,831. While an appellant may introduce on appeal additional
    facts that do not alter the nature of the original claim, its appeal must be based upon a
    common or related set of operative facts to those presented to the CO. 
    Id.
     A claim is
    new when it “presents a materially different factual or legal theory” of relief. 
    Id.
     (quoting
    Lee’s Ford Dock, Inc. v. Sec’y of the Army, 
    865 F.3d 1361
    , 1369 (Fed. Cir. 2017).
    Materially different claims will necessitate a focus on a different or unrelated set of
    operative facts. 
    Id.
    Here, DLT’s superior knowledge claim and fraudulent inducement claim
    necessitate a focus on the Ordering Activity’s pre-award failure to disclose, or
    misrepresentation of, its knowledge that it did not intend to exercise the options because
    those are essential elements of superior knowledge claims and fraudulent inducement
    claims. CAE USA, Inc., 
    ASBCA No. 58006
    , 
    13 BCA ¶ 35,323
     at 173,390; Supreme
    Foodservice GmbH, 
    ASBCA No. 57884
     et al., 
    16-1 BCA ¶ 36,387
     at 177,398. As a
    result, the complaint alleges in support of the superior knowledge claim and the
    fraudulent inducement claim that the Ordering Activity failed to disclose, or
    misrepresented, its knowledge that it intended to not exercise the options (SOF ¶ 10).
    However, that set of operative facts is different and unrelated to the set of operative facts
    presented to the CO because DLT’s claim to the CO did not mention the Ordering
    Activity’s pre-award failure to disclose, or misrepresentation of, its knowledge that it did
    not intend to exercise the options (SOF ¶ 8). Therefore, consideration of the Ordering
    Activity’s pre-award representations of its knowledge of its intent regarding the options
    would alter the nature of the original claim, and the superior knowledge claim and the
    fraudulent inducement claim are materially different claims than the claims presented to
    the CO. Nassar Grp., 
    19-1 BCA ¶ 37,405
     at 181,831. Because they are new claims, we
    do not possess jurisdiction over the superior knowledge claim and the fraudulent
    inducement claim. 
    Id.
    III. DLT’s Estoppel Claim Must be Struck
    We do not possess jurisdiction over DLT’s “estoppel” claim to the extent that it
    seeks to estop the Ordering Activity from using functionally similar products when a
    bona fide need continues to exist because that seeks specific performance or injunctive
    relief, and the remainder of the claim does not belong in the complaint because it does
    not assert an independent basis for entitlement to relief. DLT’s estoppel claim asserts
    9
    that the Ordering Activity should be estopped: (1) from arguing that the Bona Fide Needs
    Provision or the Certification Provision was a nullity; (2) from arguing that either was
    superseded by other contractual language; and (3) from using functionally similar
    products when a bona fide need continues to exist (SOF ¶ 10). The argument that the
    Ordering Activity should be estopped from using functionally similar products when a
    bona fide need continues to exist seeks specific performance or injunctive relief, so we do
    not possess jurisdiction over that portion of the claim. Rig Masters, Inc., 
    ASBCA No. 52891
    , 
    01-2 BCA ¶ 31,468
     at 155,379. The remainder of the claim does not assert
    an independent basis for entitlement to relief, but is an argument about what the
    government should be allowed to argue. As such, it does not belong in the complaint as
    an independent count, though DLT is free to advance that argument at the proper time.
    Therefore, we strike DLT’s estoppel claim.
    IV. DLT Plausibly Alleges Breach of Contract Claims
    DLT plausibly alleges breach of contract claims. “To survive a motion to dismiss,
    a complaint must contain sufficient factual matters, accepted as true, to state a claim to
    relief that is plausible on its face.” K2 Sols., Inc., 
    ASBCA No. 60907
    , 
    17-1 BCA ¶ 36,801
     at 179,376 (quoting Ashcroft v. Iqbal, 
    556 U.S. 662
    , 678 (2009)). While we do
    not accept legal conclusions as true, we must accept all factual pleadings as true. 
    Id.
    Moreover, we draw all reasonable inferences in favor of the appellant. 
    Id.
     The ultimate
    inquiry is whether the complaint alleges sufficient facts to nudge a claim across the line
    from conceivable to plausible. 
    Id.
    Here, the Ordering Activity first argues that DLT fails to plausibly allege a breach
    of contract claim because DLT failed to perform during either option year (mot. at 19).
    However, a party’s nonperformance is excused by the other party’s prior material breach.
    Kellogg Brown & Root Servs., Inc., 
    ASBCA No. 56358
     et al., 
    17-1 BCA ¶ 36,779
    at 179,249. Thus, “[f]aced with two parties to a contract, each of whom claims breach by
    the other, courts will often impose liability on the party that committed the first material
    breach.” 
    Id.
     Here, the complaint plausibly alleges that the Ordering Activity materially
    breached the Bona Fide Needs Provision by failing to exercise the options before any
    failure by DLT to perform during the option years (SOF ¶ 10). Therefore, the complaint
    plausibly alleges that DLT’s nonperformance during the option years was excused and
    we should impose liability on the Ordering Activity as the party committing the first
    material breach.
    The Ordering Activity also argues that DLT fails to plausibly allege a breach of
    contract claim because damages for the second option year are too speculative (mot.
    at 19). That is an issue of damages that requires further factual development, and thus is
    not an appropriate basis for dismissing for failure to state a claim.
    10
    Finally, the Ordering Activity argues that DLT fails to state a breach of contract
    claim because an implied-in-fact contract cannot exist when it covers the same
    obligations as an express contract, and DLT’s express contract expired (mot. at 20). As
    an initial matter, the complaint does not allege that there was an implied-in-fact contract
    (SOF ¶ 10). Instead, DLT asserts that the breach of the Bona Fide Needs Provision and
    the Certification Provision continued during the two option years, or the damages from
    the breaches of those provisions continued to accrue during the two option years (resp.
    at 31). That is a plausible claim. See Force 3 LLC v. Dep’t of Health and Human Servs.,
    CBCA 6621, 
    2021 WL 1691457
     (April 14, 2021). In any event, even if we were to
    liberally construe the complaint as alleging a breach of an implied-in-fact contract, an
    implied-in-fact contract may exist when an express contract expired under certain
    circumstances. Lee v. United States, 
    895 F.3d 1363
    , 1373 (Fed. Cir. 2018). Therefore,
    DLT has plausibly alleged a claim, and the motion to dismiss is denied.
    CONCLUSION
    For the foregoing reasons, the motion to dismiss for lack of jurisdiction is granted
    in part, and denied in part. We strike the superior knowledge claim, the fraudulent
    inducement claim, and the estoppel claim. The motion to dismiss for failure to state a
    claim is denied.
    Dated: May 26, 2022
    JAMES R. SWEET
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                            I concur
    RICHARD SHACKLEFORD                                 J. REID PROUTY
    Administrative Judge                                Administrative Judge
    Acting Chairman                                     Vice Chairman
    Armed Services Board                                Armed Services Board
    of Contract Appeals                                 of Contract Appeals
    11
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 63069
    , Appeal of DLT
    Solutions, LLC, rendered in conformance with the Board’s Charter.
    Dated: May 31, 2022
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    12
    